PROJECT MANUAL
PROPOSED SIX STOREY BUILDING WITH BASEMENT TABLE OF CONTENTS
Table of contents.doc 10/27/11 Page - - 1 -
PROJECT MANUAL
TABLE OF CONTENTS
DivisionSectionHeadingPage NumberDIVISION 00BIDDING AND CONTRACT
REQUIREMENTS00020Invitation to Bid..00020-1 to 200025Affidavit of
Site Inspection00025-100100Instruction to Bidders00100-1 to
600300Bidders Proposal Form00300-1 to 300430Sub-contractor
Listing..00430-1 00450Bid Bond Form..00450-100500Construction
Contract..00500-1 to 700700General Conditions..0700-1 to 43
DIVISION 01GENERAL REQUIREMENTS01000Explanation to
Specifications.01000-1 to 201010Summary of Work01010-1 to
301020Summary of Materials and Finishes.01020-1 to 3001100Items for
Submission by the Contractor.01100-1 to 401200Shop Drawings.01200-1
to 301300Field Engineering.01300-101400Construction.01400-1 to
401500Materials and Equipment01500-1 to 501750Warranties and
Bonds.01750-1 to 2
DIVISION 02SITEWORK02050Demolition.02050-1 to 202100Site
Preparation02100-1 to 202160Excavation Support System02160-1 to
202200Earthwork..02200-1 to 902280Termite and Bukbok
Proofing.02280-1 to 402400Site Drainage.02400-102500Roads and
Parking02500-1 to 302520Concrete Curbs, Gutter and Paved
Walks02520-1 to 7
DIVISION 02CONCRETE 03100Concrete Formwork..03100-1 to
303200Concrete Reinforcement..03200-1 to 303300Cash in Place
Concrete03300-1 to 6
DIVISION 04MASONRY04100Mortar04100-1 to 204200Unit
Masonry04200-1 to 2
DIVISION 05METALS05100Structural Metal Framing...05100-1 to
505200Miscellaneous Metals 05200-1 to 2
DIVISION 06WOOD AND PLASTICS06100Rough Carpentry.06100-1 to
206200 Finish Carpentry..06200-1 to 2
DIVISION 07THERMAL AND MOISTURE 07100Waterproofing..07100-1 to
207400Preformed Roofing..07200-1 to 207900Joint Sealants..07300-1
to 2
DIVISON 08DOORS AND WINDOWS08100Metal Doors and Windows.08100-1
to 808200Wood Doors..08200-1 08520Aluminum Jalousie Windows.08520-1
to 208700Hardware..08700-1 to 208800Glazing..08800-1 to 2
DIVISION 09FINISHES
09200Plaster09200-1 09300Tile..09300-1 to 209510Suspended
Ceiling Systems..09510-1 to 409900Painting..09900-1 to 5
DIVISION 10SPECIAL TIES10400Identifying Devices10400-1
10800Toilet Accessories.10800-1
DIVISION 14CONVEYING SYSTEMS14310Elevators.14310-1 to 2
DIVISION 15MECHANICAL15100Air-conditioning and Ventilating
System15100-1 to 515300Standpipe and Sprinkler Systems..15300-1 to
815400Basic Plumbing Materials and Methods.15400-1 to 13
DIVISION 16 ELECTRICAL16050General Requirements16050-1 to
916100Basic Electrical Materials and Methods...16100-1 to
216420Electrical Distribution System16420-1 to 216700Fire Alarm and
Emergency Management System.16700-1 to 416800Pathways for
Communications Systems.16800-1 to 516850Structured Cabling..16850-1
to 1216870Video Surveillance16870-1 to 23
END OF TABLE OF CONTENTS
DIVISION 00PROCUREMENT AND CONTRACTING REQUIREMENTS
SECTION 00020INVITATION TO BID
PROJECT : PROPOSED SIX STOREY BUILDING WITH BASEMENTLOCATION :
85 OSMENA BLVD., CEBU CITY
TO : ________________________________ DATE: ________ You are
invited to participate in bidding for the above project:
The details of the bid are as follows:
1.0 QUALIFIED BIDDERS
Those invited to bid.
2.00 SECUREMENT OF CONTRACT DOCUMENTS
For invited bidders, complete Bid Documents, may be secured
from:NATZ ARCHITECTURE SERVICES85 Osmena Blvd., Cebu CityMobile:
0921- 3600-023 Tel.No.: 253-1901 (Loc. 409)
3.00 PRE-BID DOCUMENTS
For further clarifications and instructions regarding the
project, a Pre-bid Conference among the bidders, Owner and
Architect shall be held at:
Place:
Date:Time:
Attendance at the Pre-bid conference is compulsory for the
bidders or their authorized representatives.
4.00 SUBMITTAL AND PUBLIC OPENING OF BIDS Sealed proposals for
the above project shall be received by the Owner or his
representatives at:
Place:
Date:Time:
The Bids shall then be publicly opened and read.
5.00 RIGHT TO REJECT BIDS
The owner and the Architect reserve the right to reject any or
all Proposals, waive any defects or informality therein, or to
accept such bid which may be considered most advantageous.
6.00 OFFICIAL NOTIFICATION OF ARCHITECT
Invited Bidder must notify in writing or telegram the Architect
of their intent to participate or not in the bidding. The
notification should reach the Architects office not later than
three (3) days after receipt of invitation.
Received by: _____________________________________
Date: _____________________________________
Note:Please sign in and return two (2) copies of this invitation
to the office of the Architect.
END OF SECTION 00020
SECTION 00025AFFIDAVIT OF SITE INSPECTION
This is to certify that the following person/s:
representing our
company:_____________________________________________________________________________
Name of Bidder
has/have visited the site for the project: PROPOSED SIX STOREY
BUILDING WITH BASEMENT located at
________________________________________________ on the following
date/s:
__________________________________________________________________________________________________________________________________________________________
for the purpose of investigating the nature of the site and
acquainting ourselves with the circumstances found therein
affecting the proposed works and our own responsibilities over the
circumstances found therein of making a bid entering into a
construction agreement with _______________________.
BIDDERS AUTHORIZED SIGNATORY:
__________________________________________________________
Name__________________________________________________________
Signature
ATTESTED BY:
Owners representative
Date
END OF SECTION 00025
SECTION 00100INSTRUCTIONS TO BIDDERS
PROJECT : PROPOSED SIX STOREY BUILDING WITH BASEMENTLOCATION :
85 OSMENA BLVD., CEBU CITY
TO : ______________________________ DATE: _________________
1.0 SCOPE OF THE CONTRACT
The Contractor shall be fully responsible for all labor,
materials, equipment and services necessary for the complete
project construction, ready for use, as shown on the drawings
and/or described in the Specifications. These shall include final
connections of all utilities to existing mains. The Owner, however,
reserves the right to assign other Contracts in connection with
this work.
2.0 SECURING AND COMPLIANCE WITH BIDDING DOCUMENTS
Drawings, Specifications, and other supporting Bid Documents may
be obtained at the time and place indicated in the invitation to
bid (Section 00020) or as informed by the office of Architect
Nathaniel J. Hernando. Bidders shall comply with all conditions
stipulated in these bidding documents.
3.0 REQUIREMENTS BEFORE SUBMITTING PROPOSALS
The site and all structures located thereon shall be thoroughly
examined in relation to all conditions which directly affect the
Contract work. The proposal sum shall reflect all such affecting
conditions.
4.0 INTERPRETATION OF DRAWINGS AND DOCUMENTS
Bidders are advised to carefully scrutinize the Bidding and
Contract Requirements (Division 00), and particularly the Summary
of Materials and Finishes (Section 01020). If any Bidder, in
preparing his bid, has doubt as to the true meaning and intent of
any part of the Bid Documents or find errors, discrepancies,
conflicts, or omissions in them, he shall at once request
interpretation or correction from the Architect.
Request of such clarification must be in the office of the
Architect at least seven (7) days before the bid opening date. If
the matter in question is deemed to have possible effects on the
bid amount, the architect shall then promptly issue his/her
response on the matter in the form of a Bid Bulletin. Verbal
instruction will have no validity regardless of source.
Bidders shall be notified by telephone or telegram of the
issuance of all Bid Bulletins, to be secured from the office of the
Architect. For bidders who are distantly based, or who may be
difficult to contact, it is advised that they communicate with the
Architect prior to Bid Opening to inquire if ay Bid Bulletins have
been issued to the Contractors.
5.0 PREPARING AND SUBMITTING BID PROPOSALS
The following shall be followed to the letter, otherwise,
proposals may be declared unacceptable.
A. Bid/Tender (Section 00300) shall be submitted in triplicate;
one (1) original as attached herewith, plus two (2) photocopies.B.
Contractors Sub-Contractor Listing (Section 00430) including major
suppliers listing shall likewise be submitted in triplicate ; one
(1) original as attached herewith, plus two (2) photocopies.
Bidders are required to the Specifications for guidance.C. The
Bidders legal name and business address shall be stated in full.D.
Erasures, changes or interlineations on the Proposals and Cost
Estimate sheets shall bear the signature or initial of the
Bidder.E. The Bid Price shall include all work contemplated in the
Plans and Specifications (except as specifically excluded therein)
plus additions, deletions or modifications required by any addenda
or Bid Bulletins issued prior to the Bid Opening. Therefore the
amount quoted in the Contractors Proposal will be deemed to have
included all items contained in these documents, and Bidders may
not choose to exclude any item or work called for or mentioned in
the Bid Documents.F. No Verbal telephone or telegraphic proposals,
modifications or cancellations will be considered.G. The Bidder
guarantees his Bid to be good for a period of sixty (60) days after
the Bid Opening.H. Signatures shall be longhand and executed by a
principal duly authorized to enter into contracts.I. Bid envelopes
shall contain nothing but the following:1. Bid/ Tender (Proposal),
in triplicate.2. Sub-Contractor Listing and major suppliers
listing, in triplicate.3. Cost estimate Sheets and Cost Estimate
Guide, in triplicate.4. Cash bond, in managers check, of not less
than five (5%)(5) of the Bid Price.
J. Bid envelopes shall be legal size brown envelopes bearing the
Bidders name, sealed and addressed as follows:
BID FOR
PROJECT : PROPOSED SIX STOREY BUILDING WITH BASEMENTLOCATION :
85 OSMENA BLVD., CEBU CITY
K. It is the Bidders responsibility to see to it that his
proposal is received at the proper time. Any proposal received
after the scheduled Bid Opening time will be returned to the
Bidders unopened. L. All taxes, licenses, fees adand permits
imposed by the local and/or national government shall be included
in the Bid price.M. No claims for extra compensation shall be
entertained by the Owner and the Architect for negligence or
inadvertence on the Contractors part in obtaining all necessary
data and clarifications.N. The Bid amount in the Proposal shall be
quoted in words as well as in figures. In case of discrepancy
between prices quoted in words and those in figures, the words
shall prevail.O. In case of discrepancy between the prices on the
Contractors proposal shall prevail. However, accuracy of cost
estimate will have a great bearing on the evaluation of the
Contractors Proposal.
6.0 BID WITHDRAWALS
Prior to Bid opening, Bidders may withdraw bid by written
request or by reclaiming bid envelopes before the opening of
bids.
7.0 SUB-CONTRACTORS AND SUPPLIERS
The Bidders proposed sub- Contractors and suppliers shall be
subject to the approval of the Owner and the Architect.
8.0 FACTORS AFFECTING AWARD OF CONTRACT
The Bidders proposed sub-contractors and major suppliers
adherence to Specifications, compliance with the Instructions to
Bidders, together with the amount of the Bid, shall be vital
elements considered in the award of the Contract.
9.0 OPENING OF BIDS
See Item 4.00 of the Invitation to Bid. Bidders are encouraged
to come early since late comers will be automatically
disqualified.
10.00 AWARD OR REJECTION OF BIDS
The Owner reserves the right to accept any proposal and to
reject any or all bids and to waive informality or irregularity
therein.
11.00 ACCEPTANCE OF PROPOSAL
The acceptance of proposal shall be a written approval of award
within sixty (60) days after the Opening of Bids. No Bidder shall
consider himself under the Contract until such notice has been
issued and/or the Contract has been signed.
12.00 CHANGE ORDER
All proposed changes in construction shall be made on the
Standard Change Order Form, a sample copy of which is attached
herewith. No changes in the Contract shall be allowed unless
authorized on this form.
13.00 REQUEST FOR PAYMENT
As provided for in the General Conditions (Section 00700) of the
Contract, the Contractors payment request shall be subject to the
review and approval of the Owner and the Architect.
14.00 CASH BOND AND BID BOND
Each proposal shall be accompanied by a Cash Bond in the form of
Managers Check issued by a reputable banking institution , made
payable to _______________________, in the amount of not less than
five percent (5 %) of the Bid Price. Proposal shall become NULL and
VOID if Cash Bond is addressed or dat5eddated incorrectly and if
the amount is less than the required percentage.
The Cash Bond will be returned to unsuccessful Bidders within
three (3) days after the proposals are opened, except those that
the Owner elects to hold until the successful bidder is determined.
The conditionally accepted bidder may replace his Cash Bond with a
bond during the sixty (60) days guarantee period. Bid Bond shall be
equal to the amount of the Cash Bond and issued by a bonding
company approved of the Owner.
15.00 EXECUTION OF PROPOSAL AMDAND DAMAGES FOR FAILURE TO
EXECUTE
The successful Bidder shall, within ten (10) days after the
Owners written approval of award, enter into Contract with the
Owner and shall commence work within ten (10) days after execution
of the Contract. Failure to do so shall constitute a breach of the
agreement and the Bidder/Contractor shall be liable to liquidate
damages. The damages for such breach will include loss from
interference with the Owners Construction Program and other items
whose accurate amount will be difficult or impossible to compute.
The Bid Bond shall be retained by the Owner as liquidated
damages.
In the event that the Bidder, whose Proposal has been accepted,
fails or refuses to execute the Contract as required, the Owner
may, at his option, determine that such Bidder has abandoned the
Contact,Contract, and thereupon, his Proposal and the acceptance
thereof shall become NULL and VOID, ant and the Owner shall be
entitled to liquidate damages, for this purpose, the Bid Bond shall
be forfeited in favor of the Owner.
16.00 CONTRACTS, PAYMENTS AND PERFORMANCE BONDS
The right and obligations provided in the Contract shall become
effective and bonding upon the parties only upon its execution. The
Contract shall be executed in six (6) copies and shall be
accompanied by a Performance Bond and a Payment Bond. Both the form
of the Bond and the company issuing them shall be subject to the
approval of the Owner. Bonds issued by companies not approved by
the Owner will not be accepted. The costs of such Bonds shall be
the obligation of the Contractor.
The performance Bond shall be in sum equal to thirty (30)
percent of the Contract Price, conditioned for the faithful
performance of the Contractor to its tenure and shall be enforced
for a period of extending at least sixty calendar days beyond the
contract period.
The Payment Bond shall be in a sum equal to thirty (30) percent
of the Contract Price, conditioned for the satisfaction of
obligations for the materials and labor employed upon the work.
17.00 ADDITIONAL SECURITY
Should any Surety Bond for the performance of the Contract
become unacceptable to the Owner, the Contractor shall promptly
furnish such additional securities as may be required from time to
protect the interest of the Owner and persons supplying labor
and/or materials in the prosecution of the work contemplated by the
Contract.
18.00 RELEASE OF THE PERFORMANCE AND PAYMENT BONDS
The Contractors Payment Bond shall be released by the Owner upon
submission of a complete release of liens arising out of this
Contract, all receipts, and an affidavit that the release and
receipt include labor and materials.
The Performance Bond shall be released by the Owner within five
(5) days after Acceptance of the work and after the Contractor
shall have furnished the Owner with a Guarantee Bond equal to
twenty percent (20 %) of the contract Price. The Guarantee Bond
shall be for the purpose of guaranteeing the material and
workmanship supplied by the contractor for a period of one (1)
year. The Guarantee Bond shall be issued by a bonding company
approved by the Owner.
(Try to check where would the all risk insurance be
inserted)
END OF SECTION 00100
SECTION 00300BIDDERS PROPOSAL FORM
PROJECT : PROPOSED SIX STOREY BUILDING WITH BASEMENTLOCATION :
85 OSMENA BLVD., CEBU CITY
COMPANY/CONTRACTOR/FIRM:
________________________________________
BUSINESS ADDRESS:
_________________________________________________
GENTLEMEN:
1.0 In accordance with your Invitation to Bid, for the complete
construction of the above project and subject to the Plans,
Specifications and other Contract Documents as prepared by the
office of Architect Nathaniel J. Hernando, which in so far as they
relate to this TENDER, are made part hereof, the undersigned hereby
proposes to furnish all materials, labor, equipment, tools,
transportation, services, licenses, fees, permits, and other items
required to complete the project in the Total Bid Amount (Total
Amount as shown below of
____________________________________________________________________________________________________________________________________(P
__________________________)
Broken down as follows:
Bid ItemAmount
1. GENERAL REQUIREMENTSP
2. SITEWORKP
3. CONCRETE WORKS & REINFORCEMENT P
4. MASONRY WORKS P
5. METALSP
6. WOOD & PLASTICSP
7. THERMAL & MOISTURE PROTECTIONP
8. DOORS & WINDOWSP
9. FINISHES P
10. SPECIALTIESP
11. MECHANICALP
12.ELECTRICALP
Total Bid AmountP
2.0 ( I) have available, and will use the following equipment on
this project at any time they are needed.
_____________________________ ___________________________
________________________
_____________________________ ___________________________
________________________
_____________________________ ___________________________
________________________
3.0 For additional work not included in the Bid, we (I) agree to
furnish all additional labor, materials and services required at
cost, plus a fee of fifteen percent (15%) to cover overhead,
Contractors tax and profit.
4.0 We (I) propose to start work within ten (10) calendar days
from the date we (I) receive your letter of authority to commence
work and will complete the same within a period of
_______________________________________________________________________________(________________________)
days including Sundays and holidays.
5.00 Cost of all export, national and local taxes, licenses and
fees, building, sanitary, electrical, fencing permit, and final
certificates required by the authorities, are included in the above
proposal.
6.00 The undersigned agrees to furnish Performance Bond and a
Payment Bond in accordance with the Instructions to Bidders.
7.00 Invitation to Bid dated
_____________________________________________________________And
Bid Bulletin Nos.
_____________________________________________________________have
been received.
8.00 We (I) have visited the site and are (am) aware and
acquainted with the conditions as they exist and the facilities,
difficulties, and restrictions affecting the performance of the
work and that we (I) have completely examined the Plans and
Specifications of the Owner and the Architect.
9.00 The complete proposal, all items required by Article 5,
Section J of the Instructions to Bidders are attached herewith.
In Testimony hereof, the Bidder has hereunto set his hand this
_______________day of _____________, 20___.
Respectfully submitted:
(If Bidder is an individual or Partnership)Name of Bidder /
Partner :
__________________________________________________Signature of
Bidder / Partner:
__________________________________________________Firm name:
_______________________________________________________________
Address:
___________________________________________________________________PTR
No.: __________________issued at _______________________on
______________Contactors License No. ______________________________
Res. Cert. No. _______________________issued at
____________________________ on ______________________Tax
Identification No.:____________
Names and Addresses of Partners:
Name
Address
Name
Address
(If Bidder is a Corporation)
Name of Authorized Representative:
____________________________________________________Signature of
Authorized Representative:
__________________________________________________Firm Name :
________________________________________________________________________Address
:
________________________________________________________________________
PTR No.: __________________issued at _______________________on
______________Contactors License No. ______________________________
Res. Cert. No. _______________________issued at
____________________________ on ______________________Tax
Identification No.:____________
Names of Officers of the Corporation:
Name
Address
Name
Address
END OF SECTION 00300
SECTION 00430SUB-CONTRACTOR LISTING
PROJECT : PROPOSED SIX STOREY BUILDING WITH BASEMENTLOCATION :
85 OSMENA BLVD., CEBU CITY
CONTRACTOR : __________________________________________ Bid
Opening Date: __________
Division of WorkSub-Contractor ProposedLabor
AmountMaterialsAmountTotalAmount
NOTE: Provide additional Sheet of same format if necessary.
END OF SECTION 00430
SECTION 00450BID BOND FORM
KNOWN ALL MEN BY THESE PRESENTS:
That we
_____________________________________________________________________________
of
_______________________________________________________________________________,
as
principal, and the
_____________________________________________________________________
Corporation / Company, a corporation duly organized and existing
under and by virtue of the laws of the Philippines as Surety, are
held and firmly bound unto the in the sum of
___________________________
(Php __________________________________), for the payment of
which sum to be truly made, we bind
ourselves, jointly and severally, by these presents.
WHEREAS, the above-bound Principal will submit a Bid on
_____________ which, subject to all conditions of Contract,
required of the Bidder a bond for the said Bid.
NOW, THEREFORE, the conditions of this obligation are such that
if the above-bound Principal in case becomes the successful Bidder,
and shall within 10 (Ten) days after receiving written Notice of
Award, enter into a Contract with
______________________________________ or its duly designated
representative(s) for the construction of the PROPOSED SIX STOREY
BUILDING WITH BASEMENT, then this obligation shall be null and
void, otherwise, it shall remain force and effect.
Designed at Cebu City Philippines this _______________ day of
___________, 20___.
_________________________________________________________________Corporation
/ Company
_________________________________________________________________PrincipalBy:_________________________________________________________________Surety
In the Presence of:
_________________________________________
_________________________________________
_________________________________________
_________________________________________
END OF SECTION 00450SECTION 00500CONSTRUCTION CONTRACT
KNOWN ALL MEN BY THESE PRESENTS:
This Agreement made and entered into this ________ day of
_______________, 20___, by and between:
WITNESSETH:
That the parties hereto, for the consideration hereinafter
named, hereby covenant and agree as follows:
ARTICLE I THE CONTRACT DOCUMENTS
That the instruction to Bidders, Contractors Proposal, General
Conditions of the Contract, Technical Specifications, Plans,
Bidders Bond Bulletins and/ or Addenda, as well as Drawings
relating thereto on file in the office of the Architect, form the
Contract and are hereby made hereto and acknowledged to be n
integral part of this Contract Documents are signed by both
parties.
ARTICLE II SCOPE OF WORKS
That the CONTRACTOR, in consideration of the payment to be made
by the OWNER to the CONTRACTOR of the sum of money hereinafter
named, shall construct/ perform and erect.
PROPOSED SIX STOREY BUILDING WITH BASEMENT- 85 OSMENA BLVD.,
CEBU CITY
Upon the site, in the manner and form shown on the Plans thereof
and described in the Technical Specifications prepared by NATZ
ARCHITECTURE SERVICES, hereinafter referred to as the ARCHITECT,
and to satisfaction of the said Architect, Plans and Technical
Specifications, as hereto attached and made a part thereof.
In the said construction, The CONTRACTOR, shall fully and
faithfully perform all labor, furnish all tools, plants, equipment
and all materials; and will do all things necessary for the proper
construction and completion of all work shown and described by the
Contract Documents.
ARTICLE III TIME OF COMPLETION AND SCHEDULE OF CONSTRUCTION
A. The work to be performed by the CONTRACTOR under this
contract shall commence not later than
_________________________________________________ and completion
shall not be later than
_________________________________________________ unless an
extension of time has been authorized and approved by the OWNER and
the ARCHITECT in writing.
B. It is understood that time is an essential feature of this
Contract and that upon failure of the CONTRACTOR to complete the
work stipulated in this Contract within the time provided, the
CONTRACTOR shall pay the Owner the sum of 1/10th of ONE (1) PERCENT
of the Contract Price or PESOS:
____________________________________________________________________________________
________________________________________________________________
(P________________)Philippine Currency, (per diem) for each day of
delay in the completion of the Contract, said payment to be made as
liquefied damages, and not by way of penalty; and the OWNER may
deduct form any sum due or to become due to the CONTRACTOR any
accrued sum from liquidated damages as hereinafter stated, without
need of any court action.
C. A preliminary punch list of any deficiencies shall be
prepared by the Project Supervisor and submitted to the CONTRACTOR
Ten (10) days before the date set for the completion of the work as
stated in Article III A ( taking into consideration any time
extension approved in writing by the OWNER and the ARCHITECT). All
items in the preliminary punch list shall be completed prior to
final walk-through and final punch listing.
D. The Contractors Ten Percent (10%) retention shall be retained
by the OWNER until all items on the final Punch list are
satisfactorily completed. If the CONTRACTOR shall refuse or fail to
complete the final punch list within the time fixed by a written
notice, the OWNER shall then have the right to use the Contractors
ten percent (10%) retention amount to complete the same, and the
balance, if any, shall be returned to the CONTRACTOR.
ARTICLE IV SCOPE OF WORKS
The OWNER, for and in consideration of the fulfillment of this
Contract by the CONTRACTOR, in accordance with the provisions of
the Contract Documents and subject to the additions and deductions
provided therein, shall pay to the CONTRACTOR, to wit:
LUMP SUM: PESOS:
__________________________________________________________________
____________________________________________________________
(P_____________________)Where the quantities originally
contemplated are so changed during the progress of the
construction, that application of agreed current unit prices to the
quantity of the work performed is shown to create a hardship to the
OWNER or the CONTRACTOR, there shall be equitable adjustment of the
Contract to prevent such a hardship.
ARTICLE V PAYMENTS
The OWNER shall make payment on account of this Contract (not
more than once a month ) based on the value of work accomplished
less ten percent (10%) retention (regardless of the percentage of
completion of the contract) and Expanded Withholding Tax (One
Percent of the amount due), for the duration of the Contract.
As required by Philippine law, the Contractors Expanded
Withholding Tax withheld from each payment to the CONTRACTOR shall
be transmitted by the OWNER to the Bureau of Internal Revenue in
favor of the CONTRACTORS Tax Account NO.
____________________________.
No payment shall be made unless Payment requests are on the
prescribed form and bear the approval of the Architect.
The full and final payment, together with the Ten percent (10%)
retention shall be paid to the CONTRACTOR as provided for and upon
compliance of all requisites under Article 22, 11 of the General
Conditions.
ARTICLE VI LABOR AND MATERIALS COST INCREASE
Increase in the cost of labor and/or materials due to government
action or to any other factor shall be for the sole account of, and
charged to the CONTRACTOR.
On the other hand, any decrease in the cost of labor and/or
materials shall not affect the Contract Sum herein.
ARTICLE VII GUARANTEE
Unless otherwise specified under the individual specification
headings, the CONTRACTOR hereby guarantees the work stipulated in
this Contract, and shall make good any defect in materials and
workmanship which makes itself evident within ONE (1) year after
Final Acceptance of the work without prejudice to the provisions of
Article 1723 of the Civil Code. The CONTRACTOR shall leave the work
in perfect order upon completion and present the Final Certificates
to the ARCHIOTECTARCHITECT promptly.
If in the opinion of the OWNER and the ARCHITECT, the CONTRACTOR
has failed to act promptly in rectifying any defect in the work
that appear within the period mentioned above, the OWNER and the
ARCHITECT may, at their own discretion, using the Guarantee Bond
amount for corrections, have the work done by another Contractor at
the expense of the CONTRACTOR or his Bondsmen.
However, nothing in this section shall in any way affect or
relieve the CONTRACTOR of his responsibility to the OWNER.
ARTICLE VII PERFORMANCE, PAYMENT, AND GUARANTEE BONDS
The CONTRACTOR shall, in accordance with section 16 of the
Instruction to Bidders of the Contract Documents for this Project,
furnish a Performance Bond in the form of a Surety Bond issued by
any Insurance Company approved by the OWNER, in the amount of
THIRTY Percent (30%) of the Contract Price or PESOS:
____________________________________________________________________________________
(__________________________) conditioned for the faithful
performance and compliance with all the terms and conditions of
this agreement as well as the Plans, Technical Specifications,
General Conditions and other Contract Documents relating thereto,
including payment of liquidated damages stipulated in paragraph B
of Article III of this Contract. The CONTRACTOR shall also furnish
Payment Bond in the form of a Surety Bond acceptable to the OWNER
in the amount of THIRTY percent (30%) approved of the Contract
price of PESOS:
____________________________________________________________________________________
_________________________________ ( P __________________________
) to guarantee the payment of the wages of the laborers as required
by the Labor Code and its implementing laws and regulations, and
the settlement of all outstanding indebtedness for materials used,
taxes, and all unpaid accounts in connection with this
Contract.
Upon completion and sign-off of the final punch list work, the
CONTRACTOR shall provide the OWNER with the Certificate of Final
Completion issued by the ARCHITECT and shall simultaneously furnish
a Guarantee Bond executed by the OWNERS approved Surety Company, in
the amount of TWENTY percent (20%) or PESOS:
____________________________________________________________________________________
(P_____________________) conditioned upon the faithful
compliance by the CONTRACTOR of the Guarantee stipulated under
Article VII of this agreement.
Upon OWNERS receipt of the Guarantee Bond, the OWNER shall
notify the respective bonding companies of the project completion
and request cancellation of the Performance and Payment Bonds for
this Project.
Should any Surety bonds for the performance of the Contract
become unacceptable become unacceptable to the OWNER, the
CONTRACTOR shall promptly furnish such additional securities as may
be required from time to time to protect the interest of the OWNER
and of persons supplying labor and/or materials in the prosecution
of the work contemplated by the Contract.
ARTICLE IX INSURANCE OF THE WORK
The CONTRACTOR shall have the project insured for the full
insurable value thereof against loss by fire, tornado, earthquake,
tidal wave, typhoons, and like occurrences. (All risk insurance).
The insurance policy shall be issued by an insurance company
approved by the OWNER and shall be on file at the OWNERS office
within TEN (10) days after signing the Contract. The insurance
policy shall be made payable to the OWNER.
ARTICLE X VALIDITY OF THE CONTRACT DOCUMENTS
The validity, interpretation and construction of this Contract,
with the exception of the Plans, Specifications, and General
Conditions, shall be governed by the laws of the Republic of the
Philippines. The decision of the ARCHITECT ofand the OWNER, NATZ
ARCHITECTURE SERVICES, upon all matters affecting the works, and
his interpretation of the Plans and Specifications, shall be
binding upon both parties.
ARTICLE XI ADDITIONAL CONDITIONS
In addition to the foregoing terms and conditions, it is further
agreed that:
A. The OWNER, ARCHITECT, and any persons authorized by them
shall at all reasonable time have access to the building site,
workshops of the CONTRACTOR, or other places where work is being
prepared for the building for the purpose of checking the materials
and equipment used on the project.
B.The CONTRACTOR shall furnish to the ARCHITECT all submittals
for the latters approval. Said submittals, once approved, shall
become the standard selection for building.
C. The CONTRACTOR shall submit to the ARCHITECT three (3) copies
of his proposed Construction Schedule in Network Analysis System
(PERT-CPM) within ten (10) days after signing of the Contract. The
OWNER and the ARCHITECT shall have the right to evaluate the
schedule and make necessary corrections or changes as needed.
D.If at any time, the CONTRACTOR exceeds the percentage weight
of items in his Bid Proposal, the OWNER reserves the right, without
need of court action, to cancel this Contract and complete this
work on a Negotiable Contract basis with a Contractor of his
choice.
E.UAP Documents 301 (General Conditions) is acknowledged to be
part of this Contract. All the Conditions therein, in so far as
they are not in conflict with any provisions mentioned in any of
the foregoing or elsewhere in the Contract Documents as judged by
the ARCHITECT, shall be complied with.
ARTICLE XII FINAL PAYMENT
Following the successful completion and Acceptance of the
Contract Work by the OWNER, a final progress payment statement
covering the balance of the amount due under the Contract shall be
sent to the ARCHITECT for signature who shall in turn forward the
certified final progress payment of the OWNER. The OWNROWNER shall
then verify the statement and make any corrections or adjustments
necessary to reflect liquidated damages or uncompleted work, if
there be any, on the project. Final payment shall then be made by
the OWNER on the above statements or amendments.
ARTICLE XIII CONTRACT COPIES
This contract shall be made and executed in six (6) copies.
IN WITNESS THEREOF the parties to this Contract have on this day
in the first above given, hereunto set
their hands and seals at the bottom of this page and on the left
hand margin of all other pages of this agreement.
OWNER CONTRACTOR
By: ___________________________________By:
________________________________
Signed in the presence of:
_________________________________________________________________________
A C K N O W L E D G M E N T
REPUBLIC OF THE PHILIPPINES)
PROVINCE OF _______________)
CITY OF ____________________ )
Personally appeared before me:
Name:________________________________________________________________
Res. Cert.
No.:________________________________________________________________
Issued on
:________________________________________________________________
And
Name:________________________________________________________________
Res. Cert.
No.:________________________________________________________________
Issued on
:________________________________________________________________
Known to me to be the same persons who executed the foregoing
Construction Contract, consisting of SEVEN (7) pages including this
page, wherein this acknowledgment is written, signed by the parties
and their instrumental witnesses on each and every page thereof and
they acknowledge to me that the same is their free and voluntary
act and deed.
WITNESS MY HAND AND SEAL at ____________________, Philippines,
this _________day of ___________________________, 20___.
END OF SECTION 00500
Countercheck stipulations for Site demolitions and
relocation
SECTION 00700GENERAL CONDITONS
1.0DEFINITIONS
1.0CONTRACT DOCUMENTS
The Contract consists of the following documents, including all
additions, deletions, and modifications, incorporated therein
before the execution of the Contract.A.Agreement Section 00500 in
its final/signed formB.General ConditionsSection 00700 including
all referralsC.Specifications Division 00 to 16 of Project Manual
D.DrawingsIncluding all revisions
1.02OWNER ____________________________, the company ordering the
project execution, including duly appointed successors, or
authorized representatives.
1.03ARCHITECT
Natz Architecture Services, a firm commissioned by the Owner
acting personally or through assistants duly authorized in writing
by the Architect to act on his behalf.
1.04ENGINEER
The person so named in the Contract Documents or his
representative duly authorized in writing to act for an
Engineer.
1.05PROJECT REPRESENTATIVEThe Full-time Construction Inspector
if one should be so hired by the Owner duly authorized in writing
to assist the Architect and Engineer in the supervision of the
work.
1.06CONTRACTOR
The person or firm whose proposal has been accepted and to whom
the Contract was awarded.
1.07SUB-CONTRACTORAnyone having a direct contract with the
contractor who acts for or on behalf of the Contractor in executing
any part of the Contract, not including one who merely furnishes
materials without labor.
1.08SURETY
The person, firm or corporation who provides the guarantee for
the Contractors Bonds.
1.10PROPOSAL BONDThe Cashiers check or Surety Bond accompanying
the Proposal submitted by the Bidder, as a guarantee that the
Bidder will enter into a Contract with the Owner for the
Construction of the work, if the Contract is awarded to him.
1.11PERFORMANCE BOND
The approved form of security furnished by the Contractor and
His Surety as a guarantee of good faith on the part of the
Contractor to execute the work in accordance with the terms of the
Contract.
1.12PAYMENT BOND
The approved form of security furnished by the Contractor and
his Surety as a guarantee of good faith on the part of the
Contractor to pay all obligations arising from the Contract.
1.13GUARANTEE BOND
The approved form of security furnished by the Contractor and
his surety as a guarantee to the quality of the materials and
equipment installed and the workmanship performed by the
Contractor.
1.14AGREEMENT
The contract between the Owner and the Contractor undertaking
the project described in the Contract Documents including all
supplemental agreements thereto and all special provisions
pertaining to the work or materials therefore.
1.15ADVERTISEMENT or INVITATION TO BID
The notice published by the Owner or the invitations issued to
prospective Bidders, giving information as to the nature of the
Proposed Project, conditions for the issuance of contract
documents, date of bidding, and estimated cost or information that
would give the Contractor a general idea of the magnitude and
extent of the project.
1.16BID BULLETIN
The additional information on Contract Documents issued to
bidders before date of bidding.
1.17INTRUCTIONS TO BIDDERS
The list of instructions stipulating the manner on how bids are
to be prepared and conditions for the award of contract.
1.18DRAWINGSThe graphical presentations of the work involved in
the project. They include all supplementary details and shop
drawings.
1.19GENERAL CONDITIONS
The printed documents stipulating the procedural and
administrative aspects of the contract.
1.20SPECIAL PROVISIONS
The instructions which may be issued prior to the bidding to
supplementary and/or modify Drawings, Specifications, and/or
General Conditions of the Contract.
1.21SPECIFICATIONS
The written or printed descriptions of work to be done
describing qualities of materials and mode of construction.
1.22SUPPLEMNENTARYSUPPLEMENTARY SPECIFICATIONS
The additional information which may be issued as an addition or
amendment to the provisions of the Specifications.
1.23SCHEDULE OF MATERIALS AND FINISHESAn outline specification
enumerating the type or trade names of materials to be used.
1.24BREAKDOWN OF WORK AND CORRESPONDING VALUE
A listing of the different parts of the work indicating in each
part the corresponding value in materials and labor, including an
allowance for profit and overhead.
1.25WRITTEN NOTICE
Written Notice means information, advice, or notification
pertinent to the project delivered in person or sent by registered
mail to the individual, form or corporation at the last known
business address of such individual, firm or corporation.
1.26ACT OF GOD or FORCE MAJEURE
Includes an earthquake, flood, typhoon, cyclone and other
cataclysmic phenomena of nature and all misfortune and accidents
which human prudence can not foresee or prevent. Rain, wind, flood
or other natural phenomena or inconsequential degree for the
locality shall not be construed as an Act of God or Force Majeure
and no reparation shall be made to the Contractor for the damages
to work resulting there form.from.
1.27TIME LIMITS
The duration of time allowed by the Contractor for the
completion of the Project in any stipulated portions thereof.
1.28LOCAL LAWS
Pertains to all laws, ordinances and other government
regulations applicable to the project and its undertaking.1.29
WORK
Includes labor or material, or both, as well as equipment,
transportation, or other facilities of the Contractor or
Sub-contractor necessary to commence and complete the construction
called for in the Contract.
1.30FURNISH
The word furnish shall be understood to mean Purchase and/or
fabricate and deliver to the jobsite or other location when so
designated.
1.31INSTALL
The word install shall mean to build in, mount in positions,
connect or apply any object specified ready for the intended
use.
1.32PROVIDE
The words provide shall be understood to mean furnish and
install.
1.33REQUIRED OR NECESSARY
The word require and/or necessary shall mean as required or
necessary for the complete execution of that portion of the
work.
1.34APPROVED, DIRECTED AND ACCEPTABLE
The words approved, directed, and acceptable, or words of like
import shall mean approved, directed by or acceptable to the
Architect unless otherwise stipulated in the Contract.
1.35SINGULAR or PLURAL
In all cases where a device, item or part of equipment is
referred to in the singular number, it is intended that such
reference shall apply to as many devices, items, or parts as are
required to complete the work.
2.0 EXECUTION, CORRELATION AND INTENT OF DOCUMENTS
2.01SIGNATURE ON DOCUMENTS
The Contract Documents shall be signed in quintuplicate by the
Owner and the Contractor duly witnessed.
2.02INTENT OF CONTRACT DOCUMENTS
The Contract Documents are complementary, and what is called for
by any one shall be as binding as if called for by all. The intent
of the Drawings and the Specifications is to prescribe a complete
work that the Contract is to undertake to comply with the Contract.
The intention of the Documents is to include all labor and
materials, equipment and transportation necessary for the proper
execution of the work.2.03CONFORMITY TO CONTRACT DOCUMENTS
All work shall conform to the Contract Documents.
a.If there would be a variance between the Drawings and the
Specifications, the provisions of the Specifications shall control.
In case of conflict between the General Conditions of the Contract
or any modifications thereof and the detailed Specifications
requirements, the detailed Specifications requirements shall
control.
b.Any discrepancies found between the Drawings and
Specifications and the site conditions or any errors or omissions
in the Drawings or Specifications shall be immediately reported to
the Architect or Engineer, who shall promptly correct such
discrepancies, errors, or omissions after his discovery. Any work
involving such discrepancies shall be done at the Contractors
Account.
c.Responsibility for adequacy of the design and for sufficiency
of the Drawings and Specificationsshall be borne by the Owner. The
complete requirements of the work to be performed under the
Contract shall be set forth in the Drawings and Specifications to
be supplied by the Owner through the Architect or Engineer or by
Architect or Engineer as representative of the Owner. Drawings and
Specifications furnished shall be in accordance with the Contract
Documents and shall be the true accurate development thereof.
d.The Architect or Engineer shall furnish from time to time all
additional detail drawings and instructions essential to the proper
execution of the work. The Architect or Engineer shall furnish with
reasonable promptness such additional detail drawings and
instructions. All the additional drawings and instructions shall be
consistent with Contract Documents, true development thereof, and
reasonably inferable there from. All such additional drawings and
instructions are to be considered of equal force as those which
originally accompany the Specifications.
e.The Contractor and the Architect or the Engineer, if either
one so requests, shall jointly prepare a schedule, subject to
change from time to time in accordance with the progress of the
work, fixing dates at which the various detail drawings will be
required and the Architect or Engineer shall furnish them in
accordance with that schedule. Under like conditions, a schedule
shall be prepared, fixing the dates for the submission of shop
drawings, for the beginning of manufacture and installation of
material, and for the completion of the various parts of the
work.
2.04CONTRACT DOCUMENTS AT SITE OF WORK The Contractor shall keep
at the site of the work, in good order, one copy of all Drawings,
Specifications, Breakdown of Work, Schedule of Construction of Work
and including all instructions and graphs to be available to the
Architect and his representative.
2.05OWNERSHIP OF CONTRACT DOCUMENTS
The Drawings, Specifications, and Models, including all
additional instructions and copies thereof, furnished for this work
by the Architect are the property of the Architect. They are not to
be used on any other work, and, with the exception of the signed
contract set, are to be returned to the Architect at the completion
of the work, before the Final Payment to the Contractor is
made.
3.0DRAWINGS AND SPECIFICATIONS
3.01COPIES OF DRAWINGS AND SPECIFICATIONS
The Architect shall furnish the contractor free of change, five
sets of drawings and Specifications necessary for the securance of
building permits as required by the building official.
In addition, 2 sets of drawings labeled For Construction and 1
Set labeled For Modification shall likewise be furnished to the
Contractor. One of the two (2) sets designated For Construction and
the one designated For Modification shall be kept at the site at
all times, preserved and protected from handling, damage and other
hazards which may disfigure the documents. The set designated For
Modification shall generally act as notations sheets for the
immediate recording of any deviation in the plan or detail as they
may necessarily occur in the course of the work. This set shall be
the basis for the As-built plans and shall be returned to the
Architect after the completion d the Work. All other copies of
Drawings and Specifications as required by the Contractor will be
furnished to him by the Architect at cost.
3.02COORDINATION OF DRAWINGS AND SPECIFICATIONS
All drawings are intended to be coordinated with the
Specifications to from a part thereof and also to form a part of
the Contract Documents. Where figures are given, they are to be
followed in preference to measurements by scale. Anything shown on
the Drawings but not mentioned in the Specifications, or
vice-versa, or anything not expressly set forth shall be understood
as though specially shown in both, without any extra charge.
3.03CLARIFICATION OF MEANING OF DRAWING AND SPECIFICATIONS
The Contractor shall carefully examine, compare and verify the
data furnished by the Drawings and Specifications. Any doubt as to
the meaning of the Drawings (including notes thereon) or of the
Specifications, will be explained, and all directions and
explanations necessary and proper to make more definite and certain
any requirements of the Drawings (including notes thereon) or of
the provisions of the Specifications and give them due effect, will
be given by the Architect.
a.Should a conflict occur in or between Drawings and
Specifications, the Contractor shall be deemed to have estimated
the more expensive way of doing work unless he shall ask for and
obtain a decision in writing from the Architect, before submission
of proposals, as to which method or materials will be required. If,
afterward, the less expensive work is done, the Contractor shall
credit the Owner an amount equivalent to the difference between the
more expensive and the less expensive work.b.If, in the Contractors
opinion, any work indicate in the Drawings is specified in such
manner as will make it impossible to produce a first class work, he
shall refer the same to the Architect for interpretation before
proceeding with the work. If the Contractor fails to make such
reference, no excuse will thereafter be entertained for failure to
carry out the most satisfactory manner.
3.04DISCREPANCIES IN DRAWINGS
In case of discrepancy in the figures or drawings, the matter
shall be submitted immediately to the Architect before any
adjustment shall be made by the Contractor save only at the latters
own risk and expense. The decision of the Architect on the
adjustment of discrepancies so as to conform to the real intent of
the Drawings and Specifications shall govern and shall be followed
by the Contractor.
4.0DETAIL DRAWINGS AND INSTRUCTIONS
See Section 01200: Detail and Shop drawings.
5.0SHOP DRAWINGS
See Section 01200: Detail and Shop Drawings.
6.0LAWS, REGULATIONS AND SITE CONDITIONS
6.01LAWS AND REGULATIONS
In general, the Contractor shall comply with all the laws, city
or municipal ordinances, and all Building Codes, rules and
regulations, in so far as they are binding upon or affect the
parties hereto, the work, or those engaged thereon. He shall also,
comply with regulations of firms furnishing utilities such as
water, gas, telephone, and electricity for the project.
If the Contractor performs any work contrary to such laws,
ordinances, rules regulations, and without such notice to the
Architect, he shall bear arising there from.
6.02SITE CONDITIONS
Before the bidding and the awarding of the Contract, the
Contractor is expected to have visited the locality of the work and
made his own estimates of the facilities and difficulties attending
to the execution of the proposed contract, including local
conditions and all other contingencies. Short of sub-surface
exploration, the Contractor shall be responsible for identifying,
verifying and measuring actual site dimensions, contour, natural
grade, areas for demolition and clearing, and all other matters in
so far as they may affect the scope of the work, and to consider
such when he prepares his proposal. No extra compensation and
extension of time will be given due to negligence or inadvertence
of the Contractor.
7.0PERMITS, TAXES AND SURVEYS
7.01PERMITS AND LICENSES
All construction permits and licenses necessary for the
execution of the work or of any temporary work and easements in
relation thereto should be secured, and the corresponding required
fees paid for, by Contractor if specifically stipulated in the
prior instructions of the Owner or the Architect.
The Contractor shall be solely responsible for the actions taken
by him should be the construction is started before acquiring the
necessary permits and licenses.
The Contractor shall also secure the final occupancy permit but
he shall not be responsible for the non-issuance or the delay in
the issuance thereof through no fault of the Contractor.
7.02TAXES
Whenever the law of the place of building requires sales,
consumer, use, or other similar tax related or pertinent only to
the construction of the project, the Contractor shall pay such
tax.
7.03CONSTRUCTION STAKES AND REFERENCE MARK
The Owner shall be responsible for the establishment of lot
lines, boundary lines, easements, and benchmarks by a certified
surveyor. The Owner may relegate this responsibility to the
Contractor provided the Owner pay for the cost of said services.
All other grade, lines, levels, and benchmarks necessary for the
prosecution of the work shall be established and maintained by the
Contractor.
a.The Contractor shall verify all grades, lines, levels and
dimensions as indicated on the Drawings. He shall report any error
or inconsistency to the Architect before commencing work.
b.The Contractor shall provide and maintain well-built batter
boards at all corners. He shall establish benchmarks in not less
than two widely separated places. As work progresses, he shall
establish benchmarks at each floor giving exact levels of various
floors.
c.As work progresses, the Contractor shall lay out exact
location of all partitions as a guide to all trades.
7.04SERVICES OF LICENSED SURVEYOR
See Section 01300: Field Engineering
7.05FINAL CERTIFICATION
Final certification shall be submitted upon completion of work,
or upon completion of any section of work, if required by the
Architect, and before final payment is made. Any exception or
deviations from the Drawings shall be noted on final certificate,
and there shall be included maps, plots, notes, and the like
necessary in the opinion of the Architect to constitute a full and
complete report.
8.0EQUIPMENT AND MATERIALS
8.01GENERAL
All materials and equipment must conform to all laws,
ordinances, regulations and building codes now or hereafter may be
in force and applicable during the period of construction and the
Contractor shall obtain the necessary permits and pay the required
fees therefore to the proper authorities. The Contractor shall bear
all damages by reason of any delay in the work arising from his
failure to comply with the provisions of this clause.
9.0EQUIPMENT
9.01QUALITY OF EQUIPMENT
In order to establish the standards of quality, the Architect
and the Engineer may have, in the detailed specifications, referred
to certain equipment by name and catalog number. This procedure is
not to be construed as eliminating from competition other products
of equal or better quality by other manufacturers with fully
suitable design.a.The Contractor shall furnish the complete list of
proposed substitutions prior to the signing of the contract,
together with such engineering and catalog data as the Architect
and Engineer may require.
b.The Contractor shall abide by the Architects and Engineers
judgments when proposed substitute items of equipment are judged to
be acceptable and shall furnish the specified item of equipment in
such case. All proposals for substitutions shall be furnished in
writing by the General Contractor and not by individual trades or
materials suppliers. The Architects and Engineer will approve or
disapprove proposed substitutions in writing within a reasonable
time. No substitute equipment shall be used unless approved in
writing.
10.0MATERIALS, FIXTURES, APPLIANCES
10.01 MANUFACTURERS AND DEALERS
Names of proposed ,manufacturers, material men, and dealers who
are to furnish materials, fixtures, appliances or other fittings,
if not mentioned in the specifications shall be submitted to the
Architect for approval as early as possible, to afford proper
investigation and checking.
10.02SAMPLES OF MATERIALS
The Contractor shall promptly furnish for approval, samples as
specified or specified or required. Work shall be in accordance
with approved samples.a.Unless otherwise specified, three samples
shall be submitted, and of adequate sizes as to show quality, type,
color, range, finish and texture of the material.
b.Each sample shall be labeled, bearing the material name, date,
project name, and other pertinent data.
c.A letter of transmittal in triplicate, from the Contractor
requesting approval shall accompany all sets of samples.
d.Materials shall not be ordered until approval is received from
the Architect.
10.03TRADE NAME MATERIALS AND SUBSTITUTEa.Whenever items or
class of materials is specified exclusively by trade name, by
manufacturers name or by catalog reference, only such items shall
be used.
b.No substitution shall be made for any material, article or
process required under the contract unless approved in writing by
the Architect.
c.Material and articles installed or used without such approval
shall be at the risk of subsequent rejections.
d.Samples of materials for use in reinforced concrete work such
as steel bars, cement and aggregates and their certificates of
origin are to be approved by the Architect.
10.04TESTING OF MATERIALS
The Contractor shall submit to the Architect as many samples as
may be needed for purpose of testing. Testing of all samples shall
comply with Specifications and government standards shall be
performed by a competent entity or testing laboratory approved by
the Architect. All costs for shipment, delivery, handling and
tagging of samples are to be paid by the Contractor.
10.05QUALITY OF MATERIALS
Unless otherwise specified, all materials shall be new. The
quality shall be of the best grade of their respective kinds for
the purpose. The work shall be performed in the best and most
acceptable manner in strict accordance with the requirements of the
Drawings and Specifications.
The decision of the Architect as to quality and quantity of work
and materials shall be final and precedent to the Contractors right
to receive any payment hereunder.
10.06STORAGE AND STOCKPILING OF MATERIALS
All materials not conforming to the requirements of these
specifications shall be considered as defective. Defective
materials shall be removed from the field of work and from the site
promptly. No defective materials, the defects of which have been
subsequently corrected, shall be used until approval has been
granted. Upon failure of the Contractor to remove the condemned
material form site promptly, the Architect shall have the authority
to cause their removal and replacement and to deduct the costs of
such removal and replacement from any money due to the
Contractor.
a.The apparent silence of the Specifications, Drawings, Special
Provisions and Supplementary Specifications, as to any detailed
description of quality shall be taken to mean that only the best
general practice is to prevail and that only materials and
workmanship of the best quality are to be used.
b.Failure or neglect on the part of the Architect to reject bad
or inferior materials shall not be construed to imply acceptance of
such materials if are discovered at any time prior to final
acceptance of such materials are discovered at any time prior to
final acceptance of the work by the Owner.
10.08MATERIALS REQUIRING LEAD TIME
The Contractor shall take cognizance of the time element of the
Contract. He shall make early arrangements for the purchase and
delivery of all materials that require lead time in order to avoid
delay of the work. No extension of time or substitution of
materials shall be allowed due to negligence or inadvertence of the
Contractor to allow for lead time in the procurement of
materials.
11.0OWNER SUPPLIED MATERIALS
12.0ROYALTIES AND PATENTS
The Contractor shall pay for all royalties and license fees on
all patented materials and processes. He shall defend the Owner
against all suits or claims for infringement of any patent and
trademark rights and shall save the Owner from losses on account
thereof.
13.0MANUFACTURERS DIRECTIONS
All manufactured articles, materials, and equipment shall be
applied, installed, connected, erected, used cleaned, and
conditioned in accordance with the manufacturers printed
directions, unless herein specified to the contrary. Where
reference is made to the manufacturers directions, the Contractor
shall submit a copy of such directions to the Architect.
14.0USE OF PREMISES
The Contractor shall confine his apparatus, storage of
materials, and the operations of his workmen to the limits
indicated by law, ordinances, permits or directions of the
Architect and shall not unreasonably encumber the premises with his
materials.
The Contractor shall not use permanent driveway for the
transportation of construction material nor allow heavy equipment
and trucks to pass over imbedded or underground pipes and
utilities. Curbs and gutters, side permanent pavements and all
permanent structures, shall be protected from damage.
The Contractor shall not load or permit any part of the
structure to be loaded with a weight that will endanger its
safety.
The Contractor shall not allow workmen or any other person not
involved in the construction operations to stay, loiter or sleep on
site.
15.0TEMPORARY STRUCTURES AND FACILITIES
15.01TEMPORARY OFFICES
The Contractor shall at all times provide and maintain adequate
watertight temporary offices with water, light, telephone, and
toilet facilities for the use of the Architect, resident engineers,
inspectors, contractor and sub-contractors. These offices shall be
provide with a wooden floor raised above the ground, windows,
doors, and locks, tables, blackboard, tack board, benches and racks
for drawings. One room of approximately 12m2 shall be provided with
adequate air-conditioning for the Architects use.
15.02TEMPORARY WORKERS HOUSING
The temporary buildings for housing men or other forms of
protection will be permitted only at such places as the Owner or
Architect shall designate, and the sanitary condition of the
premises and the grounds in or about such structures shall at all
times be maintained. Cooking, sleeping or smoking within the
building line shall be strictly prohibited.
15.03TEMPORARY SANITARY FACILITIES
The Contractor shall provide, construct and maintain for the
duration of the Contract, ample sanitary toilets including adequate
water connections for the use of the personnel and laborers. These
facilities shall be provided with adequate devices for privacy and
located at such points on site as to be convenient for use but out
of the way of the work. The use of these sanitary at all times and,
together with its connections, is removed prior to the completion
of the project.
15.04TEMPORARY BARRICADES AND GUARD LIGHTS
The Contractor shall furnish and put up all temporary barricades
and guard lights necessary for the safety and protection of workers
on site. Guard lights at the top of false work towers, barricades,
railings and other such safety devices shall be maintained by the
Contractor throughout the duration of construction.
15.05TEMPORARY WATER, POWER AND TELEPHONE FACILITIES
The Contractor shall make all necessary arrangements with the
local utility companies in order that temporary facilities for
water, power, and telephone are sufficiently provided till the
completion of work. All expenses in connection therewith and all
expenses for consumption be paid by the Contractor.
15.06TEMPORARY SIGNS
No signs or advertisements will be put up on site without the
Architects approval. The Contractor shall erect a billboard giving
names and addresses of the Architect and his Design Engineers, the
Contractors, and the various sub-contractors, the text, design,
size, colors, lettering and location of which shall be approved by
the Architect.
15.07TEMPORARY STAIRS, LADDERS, RAMPS, AND RUNWAYSThe Contractor
shall furnish and maintain equipment such as temporary stairs,
ladders, ramps, scaffolds, runways, derricks, chutes and the like,
as required for the proper execution of the works by all trades.
All such apparatus shall meet the safety standards and all
requirements of the Labor Law and all other Laws applicable
thereto.
15.08TEMPORARY ENCLOSURES
The Contractor shall provide temporary weather tight enclosures
for all exterior openings as soon as walls and roof are built so as
to protect all work from weather.
15.09REMOVAL OF TEMPORARY STRUCTURES
The Contractor shall remove all temporary work from the
premises, and shall clean the premises as a condition for
completing the work before acceptance by the Owner.
16.0PROTECTION OF WORK AND PROPERTY
16.01PROTECTION OF WORK AND OWNERS PROPERTYThe Contractor shall
put up and continuously maintain adequate protection for all his
work from damage and shall protect the Owners property, as well as
all materials furnished and delivered to him by the Owner from
damage or loss. He shall make good any such damage or loss except
such as may be caused by agents or employees of the Owner due or
those that may be considered as Acts of God.
a.The Contractor shall provide competent and reliable watchmen
to guard the site and premises for the duration of the Construction
until turn over. The Contractor shall provide locking devices on
doors and openings as soon as the structure is ready to accept such
devices and shall keep these under his control. In the event that
the Architect deems the security arrangements inadequate or
incompetent, the Contractor shall immediately address such
inadequacy to the Architects satisfaction.
b.Smoking and open fires on site shall be strictly prohibited
except in clearly designated areas, and signs to these effects
shall be posted conspicuously.
c.The Contractor shall provide and maintain barrels of water and
fire buckets on site for fire protection, which shall not be used
for any other purpose.
d.The Contractor shall provide and maintain in good working
condition an adequate number of the extinguishers.
16.01OLD MATERIALS
All old materials of value found by the Contractor on site,
including old salvageable material from the demolition of existing
structures on site shall be carefully stock piled by the
Contractor. The Contractor shall be responsible for these materials
until they shall have been removed from the site by the Owner or
until final acceptance of the Work.
16.02TREES AND OTHER PLANTS
Existing trees, plants, shrubs, etc. which are to remain shall
be boxed and otherwise protected from damage. No trees within the
site or located outside the building lines shall be cut or removed
without specific approval from the Architect.
a.All trees and other plants that need to be transplanted
elsewhere within fifty (50) meters from the building lines shall be
done by the Contractor at his own expense in accordance with
instructions from the Architect.
b.Damage to trees, plants, shrubs, streets, sidewalks, etc.
resulting from construction work shall be made good by the
Contractor at his own expense to the satisfaction of the
Architect.
17.01PROTECTION OF ADJACENT PROPERTY AND EXISTING UTILITIES
17.01ADJACENT PROPERTY
The Contractor shall adequately protect adjacent property as
provided by law and the Contract Documents. The construction
building or work in addition to any neighboring property or
building which may be jeopardized in any manner, shall be
thoroughly and substantially braced against winds, floods,
settling, falling, or like damage and when necessary, covered and
protected from whether at the Contractors expense. The Contractor
shall be liable and shall pay for all such damages caused by his
work and by the acts or neglect of his agents, employees or
workmen.
17.02EXISTING UTILITIES
Existing utilities if manageddamaged in the course of the work
shall be restored by the Contractor at his own expense.
18.01PROTECTION OF LIFE, WORK AND PROPERT DURING
CONSTRUCTION
The Contractor shall employ all means and devices to protect
life and property during construction. For this purpose, he shall
provide his workmen adequate safety equipment and shall institute a
safety program to inform and instruct his workmen regarding
standard safety procedures and practices and the use of safety
equipment.
In an emergency affecting the safety of life or of the work or
of adjoining property, the Contractor, without special instruction
or authorization from the Architect or Owner is hereby permitted to
act at his best discretion, to prevent such loss injury or damage,
and he shall so act without appeal, if so instructed or authorized.
Any compensation claimed by the Contractor on account of emergency
work, shall be determined by agreement or arbitration.
19.0LABOR
19.01CHARACTER OF WORKMEN
The Contractor shall employ only competent and efficient
engineers, superintendents, foremen, mechanics, laborers, or
artisans. Whenever, in the opinion of the Architect or the Owner,
any employee is careless or incompetent, or obstructs the progress
of the work or acts contrary to instructions or conducts himself
improperly, the Contractor shall, upon written request of the
Architect, discharge or otherwise remove him from and not employ
him in the work again.
Should the Contractor fail to remove unsatisfactory workmen or
fail to furnish suitable and sufficient equipment or personnel for
the proper prosecution of the work, the Architect may withhold
payment which are or may become due, or may suspend the work until
such orders are complied with.
19.02SUPERINTENDENCE AND SUPERVISION
The Contractor, if he supervises the work personally, must be a
licensed Engineer or Architect otherwise he must have in his employ
a licensed Engineer or Architect, acceptable to the Architect who
will supervise the work personally and inspect at least once a
week.
The Contractor shall keep in the project site, at all times
during the works progress, a competent Project Engineer or
Superintendent and any necessary assistants, all satisfactory to
the Architect. The Project Engineer or Superintendent shall
represent the Contractor in his absence and all directions given to
him shall be as binding as if given to the Contractor. He shall
have full authority to execute the orders or directions of the
Architect without delay and to prompt supply such materials, tools,
plant, equipment, and labor as may be required.
20.0WORK
20.01METHODS AND APPLIANCES
The Contractor shall use such methods and appliances for the
performance of all the operations connected with the work embedded
under this Contract as will produce satisfactory quality of work
and rate of progress which in the opinion of the Architect, will
ensure the completion of the work within the contract time.
a.If, at any time before commencement or during the progress of
the work such methods or appliances appear to the Architect to be
inefficient or inappropriate for producing the quality of work
required, or insuring the required rate of progress, the Architect
may order the Contractor to increase the rate orof their efficiency
or improvement or character of methods and rate of progress as are
called for in this Contract.
b.The Contractor shall, if required, furnish to the Architect
for approval full information and satisfactory evidence as to name
of the manufacturer or machinery, mechanical or other pertinent
information.
20.0LAYING OUT THE WORK
The Contractor shall lay out the lines and grades of the work as
per conditions set forth under Article 7.03 (Construction Stakes
and Reference Mark) of the General Conditions.
All stakes, bench marks, etc. placed by the Contractor inlaying
out the work, approved by the Architect, shall be carefully guarded
and preserved by the Contractor. In case such stakes or marks are
displaced or rendered useless through the carelessness or neglect
of the Contractor or of his agents, employees, or workmen, they
shall be replaced by the Contractor at his own expense.
20.03INSPECTION OF WORK
The Owner, Architect and their representatives shall at all
times have access to the work whenever it is in preparation or
progress and the Contractor shall provide proper facilities for
such access and for inspection.
a.If the Technical Specifications, the Architects instructions,
laws, ordinances or any public authority require any work to be
specifically tested or approved, the Contractor shall give the
Architect and other parties required to make the inspection, timely
notice of its readiness for inspection, and the date fixed for such
inspection. Inspections by Architect shall be promptly made and
where practicable, at the source of supply. If any work should be
covered up without approval or consent of the Architect, it must,
if required by the Architect, be uncovered for examination at the
Contractors expense.
b.Re-examination of questioned work may be ordered by the
Architect and if so ordered, the work must be uncovered by the
Contractor. If such work be found not in accordance with the
Contract Documents, the Contractor shall pay the cost of removal,
repair and corrective reconstruction.
c.The Contractor shall furnish promptly without additional
charge, all reasonable facilities, labor and materials necessary
for the safe and convenient inspection and tests that may be
required by the inspectors. All inspections and tests shall be
performed in such manner as not to unnecessarily delay the
work.
d.If there are indications that the work done are not in
accordance with Plans and Specifications, the Architect may at any
time before final acceptance of the entire work make an examination
of the work already completed. By removing or tearing out same, the
Contractor shall on request, promptly furnish all necessary
facilities, labor, and materials. If such work is found to be
defective in any material respect due to fault of the Contractor or
his sub-contractors, the Contractor shall defray all the expense of
such examination and of satisfactory reconstruction. If, however,
such work is found to meet the requirements of the Contract, the
actual cost of labor and materials necessarily involved in the
examination and replacement plus 15 percent shall be allowed the
Contractor and he shall, in addition, if completion of the work has
been delayed thereby, be granted a suitable extension of time on
account of the additional work involved.
20.04DEFECTIVE WORK
Defective work may be condemned by the Architect at any time
before the final acceptance o the work, and when such work has been
condemned, it shall be taken out immediately by the Contractor and
rebuilt in accordance with Drawings and Specifications. Failure or
neglect on the part of the Architect or any of his agents to
condemn or reject bad or inferior work, shall not be construed to
imply acceptance of the work of the same if such bad or inferior
work is discovered at any time prior to final acceptance of the
work by the Owner and the release of the Contractor.
20.05WORKS DURING AN EMERGENCY
The Contractor shall perform any work and shall furnish and
install all materials and equipment necessary during an emergency
endangering life or property. In all cases he shall notify the
Architect and the Engineer of the emergency as soon as practicable,
but he shall not wait instructions before proceeding to properly
protect both life and property.
20.06INCREASED OR DECREASED QUANTITIES OF WORK
Adjustments of drawings to suit field conditions which cannot be
foreseen at the time of calling for bids may be necessary during
construction. It is the essence of the contract to recognize such
changes in drawings as constituting a normal and expected margin of
adjustment, and not involving nor permitting change or modification
of Contract prices; provided only, that the resulting overruns or
under runs from the quantities in the proposal do not exceed five
percent. In case of discrepancy, the matter shall be submitted
immediately to the Architect, before any adjustment shall be made
by the Contractor, otherwise it shall be at his own risk and
expense.
20.07CHANGES IN THE WORK
a.CHANGES ORDERED BY OWNER: The Owner or Architect matmay at any
time, without invalidating the Contract and without notice to
sureties, order extra work or make changes by altering, adding to
or deducting from the work, as covered by the Drawings and
Specifications of this Contract and within the general scope
thero0f.therof. Such changes shall be ordered by the Owner or
Architect in writing, and no change or omission from the Drawings
and Specifications shall be considered to have been authorized
without written instructions signed by the Owner.
b.CHANGE OF SUB-SURFACE CIONDITIONS:CONDITIONS: If during the
progress of work, sub-surface conditions at the site are materially
different from those shown on the Drawings or indicated in the
Specifications are discovered or encountered, the attention of the
Architect shall be called immediately to such conditions, before
they are disturbed. The Architect shall thereupon promptly
investigate the conditions, and if he finds that they materially
differ from those shown on the Drawings or indicated in the
Specifications , he shall at once, at the approval of the Owner ,
make such changes in the Drawings and Specifications as he may find
necessary.
c.ADJUSTMENT OF CONTRACT: All such changes shall be executed
under the conditions of the original contract. If such changes
cause an increase or decrease in the amount due under the Contract,
or in the time required for its performance, an equitable
adjustment shall be made and the Contract shall be modified in
writing accordingly. The express consent of the sureties shall be
obtained in writing. In the event that the work involved was
increased by such changes, the Contractor shall furnish
proportionate additional bond.
d.VALUE OF EXTRA WORK: The value of extra work or change shall
be determined in any one or more of the following ways:
1.By estimate and acceptance in a lump sum.2.By unit prices
stipulated in the Contract or subsequently agreed upon, provided
the extra or credit does not exceed 25 % of original Contract of
the particular work involved.3.By actual direct cost plus fifteen
percent (15%) for Contractors profit, overhead and Contractors
tax.
Under case 3, he shall keep and present in such form as the
Architect may direct, a correct account of the cost, together with
vouchers. In any case, the Architect shall certify to the amount,
including the fifteen percent (15%) allowance of overhead and
profit, due the Contractor.
e.PERIOD FOR WHICH CLAIM FOR ADJUSTMENT HAS TO BE ASSERTED: Any
claimed for adjustment involving questions of fact must be asserted
within fifteen days from the date the change is ordered unless the
Architect shall for proper cause extend such time. Except as
otherwise specially provided in this Contract, all disputes
concerning questions of fact arising under this Contract shall be
decided by the Architect or his duly authorized representative.
Noting, however, as provided for in Article 20.07, shall excuse the
Contractor from proceeding with the prosecution of the work so
changed.
f.CHANGES ORDERED BY THE ARCHITECT: In giving instructions the
Architect shall have the authority to make minor changes in the
work, not involving extra cost, and not inconsistent with the
design concept of the building.
g.AWARD OF EXTRA WORK TO OTHER CONTRACTOR: IN case any extra
work shall be required in the proper performance of the work
contemplated under this Contract, it is understood that if the
Contractor and the Owner fail to arrive at any agreement as to any
other person, firm, or corporation than said Contractor.
20.08CLAIMS FOR EXTRA COST
If the Contractor claims that any instructions by Drawings or
otherwise involve extra cost under this Contract, he shall give the
Architect written notice thereof within fifteen days after the
receipt of such instruction and in any event, before proceeding to
execute the work, except in emergency endangering life or property,
and the procedure shall then be as provided for in Article 20.05
(Work During an Emergency) of the General Conditions. No such claim
shall be valid unless so made.
In like manner, if the Contractor incurs a delay in the
mobilization and /or in the progress of his work for reasons
attributable to the Owner, e.g., Owner-supplied materials not
arriving on time, movements or work executed by the Owner which
interfere with the progress of the Contractors work, delayed
decisions and other matters related thereto, he shall give the
Architect written notice thereof within fifteen days after
recognition of such delay and proceed to claim for extra cost that
may arise from such delays. No claim shall be valid unless such
written notice has been executed.
20.09CLEANING UP AT COMPLETION WORK
The Contractor shall at all times, keep the premises free from
accumulation of waste materials or rubbish caused by his employees
or his works. At the completion of the work, he shall remove all
such rubbish from and about the building, and all his tools,
scaffolding and surplus materials, and turn over the work for
occupancy with.
a.All dirt, stains, and the like on all finishing of floors,
walls, and ceiling, decorative work, finishing hardware and
fixtures, removed;
b.All woodwork, finishing hardware and all metal works, cleaned
and polished;
c.All glazing, marble and tile work, washed and polished.
d.All toilet fixtures washed and cleaned.
The Contractor shall also clean the building site and all areas
which the Contractor shall have used in the construction of the
project. At no time shall any rubbish by thrown from windows or
other parts of the building without the use of rubbish chutes.
20.10USE OF COMPLETED PORTIONS OF WORK
The Owner shall have the right to take possession of and use any
completed or partially completed portions of the work,
notwithstanding that the time for completing the entire work or
such portions may not have expired; but such taking possession and
use shall not be deemed an acceptance of any work not completed in
accordance with the Contract Documents. Neither shall it be deemed
a waiver by the Owner of the rights to claim for damages due to
delays in the completion of the work. If such prior use increases
the cost of or delays the completion of uncompleted work or causes
refinishing of completed work, the Contractor shall be entitled to
such extra compensation, or extension of time or both, as agreed
upon prior to the occupancy.
20.11CERTIFICATE OF COMPLETION OF WORK
Upon due notice from the Contractor that he has substantially
completed the work, the Architect shall make an inspection of the
project. If the contract covers the furnishing and/or installation
of equipment, fixtures, and utilities, said equipment, fixtures and
utilities shall be fully tested and test-run in order that the work
can be considered as substantially completed. However, should the
Contractor, through no fault of his, be unable to test-run the
equipment at the time of substantial completion, he shall be given
the necessary time extension for that portion of the work. As soon
as, in the opinion of the Architect, the work shall have been
substantially completed and shall have satisfactorily passed any
final test of materials that may be prescribed in the Contract, the
Architect shall issue a Certificate of Completion for the work.
Even before the completion of the whole work; upon written
application of the Contractor, the Architect may likewise issue
such a Certificate of satisfaction of the Architect sndand occupied
or used by the Owner. In all cases, prior to the issue of the said
Certificate of Completion, the Contractor shall execute a written
undertaking to finish any outstanding work during the Period of
Making Good of Known Defects of Faults are defined in Article 20.12
hereof.
20.12PERIOD OF MAKING GOOD OF KNOWN DEFECTS OF FAULTS
The expression Period of Making Good of Known Defects or Faults
shall mean period of not more than sixty (60) calendar days, unless
otherwise expressly stated in the Contract, calculated from the
date of issue of the Certificate of Completion of the whole or any
apart thereof, in accordance with Article 20.11.
20.13MAKING GOOD OF KNOWN DEFECTS OR FAULTS
The Contractor shall execute at his expense all works necessary
for making good of known defects, imperfections or faults within
the period of sixty (60) days after the issuance of the Certificate
of Completion or within fifteen (15) days after expiration, as a
result of an inspection made by or on behalf of the Architect prior
to its expiration.
If, in the opinion of the Architect, the defect or fault is due
to the Owner or Owners representative in their occupancy of the
structure or parts of it, the value of such work shall be
ascertained and paid for as if it were additional work.
If the Contractor shall fail to do any such work aforesaid, the
Owner shall upon written notice to the Contractor be entitled to
carry out such by his own workmen or by other contractors, and if
such work which the Contract should have carried out is at the
Contractors cost, the Owner shall be entitled to recover from the
Contractor the cost thereof, or may deduct the same from any monies
due or may become due to the Contractor.
20.14SEARCH FOR CAUSES OF DEFECTS OF FAULTS