Top Banner
1 Project Management
45
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Project Management Techniques

1

Project Management

Page 2: Project Management Techniques

2

Project

Management Techniques

Page 3: Project Management Techniques

3

Project Management

Questions:

1. Why do we need to study Project Management?

2. How does a project management technique work?

(to p4)

(to p5)

Page 4: Project Management Techniques

4

Objective

• The main purpose is to govern the operations of a project such that all activities involved are well administrated and that we can also control its completion time

(to p3)

Page 5: Project Management Techniques

5

Project management technique

Steps to solve a project management

problem:

1. to represent a ‘project problem” graphically

2. to determine its completion time

3. to carry out sensitivity analysis, if any

(to p6)

(to p12)

(to p29)

Page 6: Project Management Techniques

6

1. Represent a ‘project problem” graphically

Steps:

1. Gather all information and organize them in a table format that consists of: event, processing time, and precedent constraints as follows:

2. Draw a semantic network to represent them

Special case!

Event Processing Time

Precedent constraints

A

B

C

20

30

10

--

A

B

(to p7)

(to p9)

(to p4)

Page 7: Project Management Techniques

7

Semantic network to represent them

Here, we use three symbols:

node to represent stage

line/branch to represent event

arrow to represent precedentconstraint

Example (to p8)

(to p6)

Page 8: Project Management Techniques

8

Example

1 2 3

Path Event Proc

Time

Pred

Const

1-2

2-3

3-4

A

B

C

20

30

10

--

A

B

A

4

CB

20 30 10

Rule1: All nodes must starts from oneNode and ends with one node

(to p7)

Page 9: Project Management Techniques

9

Special case!

• When two or events taken places in the same time interval

• (known an concurrent events)

• Consider the following example!

• How to draw it?

Event Processing Time

Precedent constraints

A

B

C

3

5

7

--

A

A

(to p10)

Page 10: Project Management Techniques

10

Case 1

1 2 3A B

C

35

7

Wrong! Rule2: no node can havetwo outcomes and end with the same note

Solution (to p11)

Page 11: Project Management Techniques

11

Solutions for Rule 2

Three ways to draw it:

1 2

3

4

5A

B

C

Dummy 1=0

Dummy 2 = 0

1 2

3

4A B

CDummy = 0

1 2

3

4A

B

C

Dummy = 0

Solution 1:

Solution 2:

Solution 3:

What oneis better?

A dummy activity showsa precedence relationshipReflects no processing time

(to p6)

Page 12: Project Management Techniques

12

2. Determine its completion time

Consider the project network as shown in next slide

Question: Is it an easy way to find out the solution?

Answer: YES, it knows as Critical Path Method (CPM)

(to p15)

(to p13)

Page 13: Project Management Techniques

13

The Project Network All Possible Paths for Obtaining a Solution

Figure 8.3Expanded network

for building a house showing

concurrent activities.

Table 8.1Possible Paths to

complete the House-Building

Network

Then the completion time for paths A, B, C and D can be computed as

(to p14)

Page 14: Project Management Techniques

14

The Project Network

Completion time for:

path A: 12 3 4 6 7, 3 + 2 + 0 + 3 + 1 = 9 months (Critical Path)

path B: 1 2 3 4 5 6 7, 3 + 2 + 0 + 1 + 1 + 1 = 8 months

path C: 1 2 4 6 7, 3 + 1 + 3 + 1 = 8 months

path D: 1 2 4 5 6 7, 3 + 1 + 1 + 1 + 1 = 7 months

The critical path is the longest path through the network; the minimum time the network can be completed.

Figure 8.5Alternative paths in the

network

This is theSolution!

(to p12)

Page 15: Project Management Techniques

15

Critical Path Method (CPM)

• General concepts:– For each branch of the project network, we firstly

determine four values of ES, EF, LS and LF– For each branch, we compute their slack time,

• Slack time = (LS-ES) or (LF-EF)

– The critical path is located at branch that has slack time = 0

(Do you know the reason why?)

How it works? (to p16)

Page 16: Project Management Techniques

16

How CPM works?

Steps:1. Prepare the project

network

2. Construct a table as follows:

3. Compute ES and EF

4. Compute LS and LF

5. Compute LS-ES or LF-EF

Branch ES EF LS LF

ESij = max (EFi) EFij = ESi + tij

with EF1=0Critical path when LS-ES=0

(to p4)

(to p17)

(to p26)

(to p22)

Page 17: Project Management Techniques

17

Compute ES and EF

Note: When computing these values, the pattern is like moving zic-zac format by firstly computer ES12 and then adding it to EF12

and move to next branch by copying the max values of the branch 1-2 to say, 2-3

We compute them from top to bottom!Their relationship : Example 1:

(to p18)

(to p22)(to p19)

Page 18: Project Management Techniques

18

The starting point of ES and EF

Consider:

Then

EF1 = 0

ES12 = max (EF1) EF12 = ES12 + t12

= 0 = 0 + t12

1 2t12

(to p17)

Page 19: Project Management Techniques

19

Branches ESij = max(EFi) EFij=ESij+tij

1-2

2-3

2-4

3-4

4-5

4-6

5-6

6-7

ES12= max(EF1)=

ES23=max(EF2)=

ES24=max(EF2)=

ES34=max(EF3)=

ES45=max(EF4)=

ES46=max(EF4)=

ES56=max(EF5)=

ES67=max(EF6)=

EF12=ES12+t12=

EF23=ES23+t23=

EF24=

EF34=

EF45=

EF46=

EF56=

EF67=The overall computation is shown in next slide(to p20)

Page 20: Project Management Techniques

20

Branch ESij = max (EFi ) EFij = ESij + tij 1 -2 2-3

ES12 = max (EF1) = 0 ES23 = max (EF2) = 3

EF12 = ES12 + t12 = 0 + 3 =3 EF23=ES23+t23 = 3 + 2 = 5

2-4 3-4 4 -5

ES24 = max(EF2) = 3 ES34= max (EF3) = 5 ES45= max (ES4) = 5

EF24=ES24+t24 =3 + 1 = 4 EF34=ES34 + t34 = 5 + 0 = 5 EF45 = ES45 + t45 = 5 + 1 = 6

4 -6 5-6 6-7

ES46=max(EF4) = 5 ES56=max(EF5) = 6 ES67=max(EF6) =8

EF46=ES46+t46 =5 + 3 = 8 EF56=ES56 +t56 =6 + 1 = 7 EF67=ES67+t67 = 8+ 1 = 9

- ES is the earliest time an activity can start. ESij = Maximum (EFi)

- EF is the earliest start time plus the activity time. EFij = ESij + tij

(note:you can compute these values and show in the network diagram as well)

Add all t to note 4 and take the longest time

Max (node 3+t34, node2+t24)

max (5+0, 3+1)

=max(5,4)=5

add all ti for note 2

Max(node4+t46,node5+t56

=max(5+3,5+1)=8

Complete solution

(to p4)(to p21)

Page 21: Project Management Techniques

21

The Project Network Activity Scheduling- Earliest Times

- ES is the earliest time an activity can start. ESij = Maximum (EFi)

- EF is the earliest start time plus the activity time. EFij = ESij + tij

Figure 8.6Earliest activity start and finish times

(to p20)

Page 22: Project Management Techniques

22

Compute LS and LF

Note: We compute these values from the bottom to top, with assigning:

LSij = LFi -tij LFij = min LSj

with

the end of LFij = EFij

Example: computing Figure 8.3 (to p23)

Page 23: Project Management Techniques

23

Branches LSij = LFij-tij LFij=min(LSj)1-2

2-3

2-4

3-4

4-5

4-6

5-6

6-7

LS12 = Li12-t12 =LS23 = LF23-t23 =LS24 = LF24-t24 =LS34 = LF34-t34 =

LS45 = LF45-t45 =LS46 = LF46-i46 =LS56 = LF56-t56 =LS67 = LF67-t67 =

LF12=min(LS2)=

LF23=min(LS3)=

LF24=min(LS4)=

LF34=min(LS4)=

LF45=min(LS5)=

LF46=min(LS6)=

LF56=min(LS6)=

LF67=min(LS7)=

The overall computational is shown in next slide(to p24)

Page 24: Project Management Techniques

24

- LS is the latest time an activity can start without delaying critical path time. LSij = LFij - tij

- LF is the latest finish time LFij = Minimum (LSj)

Branches

LSij=LFij-tij

LFij=min LSj

1-2 2-3 2-4

LS12=LF12-t12 = 3-3 =0 LS23=LF23-t23=5-2=3 LS24=LF24-t24=5-1=4

LF12 = Min(LS2) =3 LF23=Min(LS3) = 5 LF24=Min(LS4)=5

3-4 4-5 4-6

LS34=LF34-t34=5-0 = 5 LS45=LF45-t45 = 7-1=6 LS46=LF46-t46=8-3=5

LF34=Min(LS4) = 5 LF45=Min(LS5)=7 LF46=Min(LS6)=8

5-6 6-7

LS56=LF56-t56=8-1=7 LS67=LF67-t67=9-1=8

LF56=Min(LS6)=8 LF67=Min(LS67)=9

Start with the end node first Same as EF67from the previous slide

Again, you can place these values onto the branches

Min(node 6-t46,node5-t45)

=Min(8-3,7-1)

=Min(5,6)=5

Min(node3-t23,node4-t24)

=Min(5-2,5-1)=Min(3,4)=3

Min(node 7-t67)

=Min(9-1)=8

(to p25) (to p22)

Page 25: Project Management Techniques

25

The Project Network Activity Scheduling - Latest Times

- LS is the latest time an activity can start without delaying critical path time. LS ij = LFij - tij

- LF is the latest finish time LFij = Minimum (LSj)

Figure 8.7Latest activity start and finish times

(to p24)

Page 26: Project Management Techniques

26

Compute LS-ES or LF-EF

Two ways you can achieve it:

1. by compiling slack, Sij

2. by showing branches

(to p27)

(to p28)

(to p16)

Page 27: Project Management Techniques

27

The Project Network Calculating Activity Slack Time

- Slack, Sij, computed as follows: Sij = LSij - ESij or Sij = LFij - EFij

Table 8.2 Activity Slack

 

Figure 8.9Activity Slack

*

What does it mean?

(to p26)

Page 28: Project Management Techniques

28

The Project Network Activity Slack

• Slack is the amount of time an activity can be delayed without delaying the project.

• Slack time exists for those activities not on the critical path for which the earliest and latest start times are not equal.

• Shared slack is slack available for a sequence of activities.

Figure 8.8Earliest activity start and finish times

(to p26)

Page 29: Project Management Techniques

29

Sensitivity Analysis

• Today, we only consider one case –

“Probabilistic Activity Times”

• Refer to activity time estimates usually can not be made with certainty

• PERT is known as the solution method(to p30)

Page 30: Project Management Techniques

30

PERT

• In PERT, three different time estimations are applied:

most likely time (m),

the optimistic time (a) , and

the pessimistic time (b).

• How do we make use of these three values? (to p31)

Page 31: Project Management Techniques

31

Probabilistic Activity Times

•We used these values to estimate the mean and variance of a beta distribution:

mean (expected time):

variance:

How to use these values to solve a project network problem?

6

b 4m a t

2

6

a - b

v

(to p32)

Page 32: Project Management Techniques

32

PERT

• We simply apply t values in CPM and determine the values of:

• ES

• EF

• LS

• LF

• S

and branches with slack = 0 still consider as critical paths

• Example. (to p33)

Page 33: Project Management Techniques

33

Procedures for PERT

Step 1: based on the values of a, b and m, determine the t and v values for each path

Step 2: determine the critical path by using t values in the CPM

Step 3: compute its corresponding means and standard deviations according.

Example Result implicationApplications

(to p34)

(to p38)

(to p39)

Page 34: Project Management Techniques

34

PERT Example

• Step 1: computer t and v values

• Step 2: determine the CPM

• Step 3: determine v value

(to p35)

(to p36)

(to p37)

(to p33)

Page 35: Project Management Techniques

35

Step 1: computer t and v values

Figure 8.11Network with mean activity times and variances

Table 8.3Activity Time Estimates for

Figure 8.10

6

b 4m a t 2

6

a - b

v

(to p34)

Page 36: Project Management Techniques

36

Step 2: determine the CPM

Figure 8.12Earliest and latest activity times

Table 8.4Activity Earliest and

Latest Times and Slack

(to p34)

Page 37: Project Management Techniques

37

Step 3: determine v value• The expected project time is the sum of the expected times of the critical path activities.

• The project variance is the sum of the variances of the critical path activities.

• The expected project time is assumed to be normally distributed (based on central limit theorum).

In example, expected project time (tp) and variance (vp) interpreted as the mean () and variance (2) of a normal distribution:

= 25 weeks

2 = 6.9 weeks

Critical Path Activity Variance

1 3 3 5 5 7 7 9

1 1/916/9 4

total 62/9

(to p34)

Page 38: Project Management Techniques

38

Probability Analysis of the Project Network

- Using normal distribution, probabilities are determined by computing number of standard deviations (Z) a value is from the mean.

- Value is used to find corresponding probability in Table A.1, App. A.

Figure 8.13Normal distribution of network duration Critical value

(to p33)

Page 39: Project Management Techniques

39

Consider when

x = 30

x = 22

Tutorial Assignment

(to p40)

(to p41)

(to p42)

Page 40: Project Management Techniques

40

Probability Analysis of the Project NetworkExample 12 = 6.9 = 2.63

Z = (x-)/ = (30 -25)/2.63 = 1.90

-Z value of 1.90 corresponds to probability of .4713 in Appendix A of p715. Probability of completing project in 30 weeks or less : (.5000 + .4713) = .9713,

or 97.13% (Why so high a probability rate?)

Figure 8.14Probability the network will be completed in 30 weeks or less

(to p39)

Page 41: Project Management Techniques

41

Probability Analysis of the Project NetworkExample 2

Z = (22 - 25)/2.63 = -1.14

Z value of 1.14 (ignore negative) corresponds to probability of .3729 in Table A.1, appendix A.

Probability that customer will be retained is .1271 (= 0.5- 0.3729) , or 12.71%

(Again, why so low probability rate?)

Figure 8.15Probability the network will be completed in 22 weeks or less

(to p39)

Page 42: Project Management Techniques

42

Tutorial Assignment

• Try to use QM to solve CPM/PERT problems (see slide 19)

• Exercises (Chapter 8)– Old: 8, 10, 17– New: 4, 6, 11

(to p43)

Page 43: Project Management Techniques

43

Probability Analysis of the Project NetworkCPM/PERT Analysis with QM for Windows

Exhibit 8.1

(to p16)

Page 44: Project Management Techniques

44

The Project Network Activity Slack

• Slack is the amount of time an activity can be delayed without delaying the project.

• Slack time exists for those activities not on the critical path for which the earliest and latest start times are not equal.

• Shared slack is slack available for a sequence of activities.

Figure 8.8Earliest activity start and finish times

Page 45: Project Management Techniques

45

The Project Network Calculating Activity Slack Time

- Slack, Sij, computed as follows: Sij = LSij - ESij or Sij = LFij - EFij

Table 8.2 Activity Slack

 

Figure 8.9Activity Slack

*