Top Banner
1 Project Management Session Five Organizational Structures Project Management Session Five Organizational Structures Kerzner: Chapter 3 Burke: Chapter 20 PMBOK: Chapter 2
42

Project Management Session Fivegsme.sharif.edu/~projectmanagement/PMSession5.pdf4 Project Management Traditional Weaknesses Management is satisfied with its technical skills, but projects

Jun 22, 2020

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Project Management Session Fivegsme.sharif.edu/~projectmanagement/PMSession5.pdf4 Project Management Traditional Weaknesses Management is satisfied with its technical skills, but projects

1

Project ManagementSession FiveOrganizational Structures

Project ManagementSession FiveOrganizational Structures

Kerzner: Chapter 3Burke: Chapter 20PMBOK: Chapter 2

Page 2: Project Management Session Fivegsme.sharif.edu/~projectmanagement/PMSession5.pdf4 Project Management Traditional Weaknesses Management is satisfied with its technical skills, but projects

2

Hidden Revolution:New Organization StructuresHidden Revolution:New Organization Structures

Organizations need to be dynamic in naturerapid restructuring to environmental conditions.Management usually look externally for solutionsHuman resources more important than non-human Need to balance socio and technical requirementsFactors: Control, Integration, External Relations

AuthorityResponsibilityAccountability

Organizations need to be dynamic in naturerapid restructuring to environmental conditions.Management usually look externally for solutionsHuman resources more important than non-human Need to balance socio and technical requirementsFactors: Control, Integration, External Relations

AuthorityResponsibilityAccountability

Page 3: Project Management Session Fivegsme.sharif.edu/~projectmanagement/PMSession5.pdf4 Project Management Traditional Weaknesses Management is satisfied with its technical skills, but projects

3

Restructuring NecessityRestructuring NecessityThe technology revolution (complexity and variety of products, new materials and processes, and the effects of massive research)Competition and the profit squeeze (saturated markets, inflation of wage and material costs, and production efficiency)The high cost of marketingThe unpredictability of consumer demands (due to high income, wide range of choices available, and shifting tastes)

The technology revolution (complexity and variety of products, new materials and processes, and the effects of massive research)Competition and the profit squeeze (saturated markets, inflation of wage and material costs, and production efficiency)The high cost of marketingThe unpredictability of consumer demands (due to high income, wide range of choices available, and shifting tastes)

Page 4: Project Management Session Fivegsme.sharif.edu/~projectmanagement/PMSession5.pdf4 Project Management Traditional Weaknesses Management is satisfied with its technical skills, but projects

4

Project ManagementTraditional WeaknessesProject ManagementTraditional Weaknesses

Management is satisfied with its technical skills, but projects are not meeting time, cost, and other project requirements.There is a high commitment to getting project work done, but great fluctuations in how well performance specifications are met.Highly talented specialists involved in the project feel exploited and misused. Particular technical groups or individuals constantly blame each other for failure to meet specifications or delivery dates.Projects are on time and to specifications, but groups and individuals aren’t satisfied with the achievement.

Management is satisfied with its technical skills, but projects are not meeting time, cost, and other project requirements.There is a high commitment to getting project work done, but great fluctuations in how well performance specifications are met.Highly talented specialists involved in the project feel exploited and misused. Particular technical groups or individuals constantly blame each other for failure to meet specifications or delivery dates.Projects are on time and to specifications, but groups and individuals aren’t satisfied with the achievement.

Page 5: Project Management Session Fivegsme.sharif.edu/~projectmanagement/PMSession5.pdf4 Project Management Traditional Weaknesses Management is satisfied with its technical skills, but projects

5

Which Structure Is Best For Project Management?

Page 6: Project Management Session Fivegsme.sharif.edu/~projectmanagement/PMSession5.pdf4 Project Management Traditional Weaknesses Management is satisfied with its technical skills, but projects

6

QuestionsQuestionsTo what extent does the task of organization call for close control if it is to be performed efficiently?What are the needs and attitudes of the people performing the tasks? What are the likely effects of control mechanisms on their motivation and performance?What are the natural social groupings with which people identify themselves? To what extent are satisfying social relationships important in relation to motivation and performance?

To what extent does the task of organization call for close control if it is to be performed efficiently?What are the needs and attitudes of the people performing the tasks? What are the likely effects of control mechanisms on their motivation and performance?What are the natural social groupings with which people identify themselves? To what extent are satisfying social relationships important in relation to motivation and performance?

Page 7: Project Management Session Fivegsme.sharif.edu/~projectmanagement/PMSession5.pdf4 Project Management Traditional Weaknesses Management is satisfied with its technical skills, but projects

7

Questions (continued)Questions (continued)

What aspect of the organization’s activities needs to be closely integrated if the overall task is to be achieved?What organizational measures can be developed that will provide an appropriate measure of control and integration of work activities, while at the same time meeting the needs of people and providing adequate motivation?What environmental changes are likely to affect the future trend of company operations? What organizational measures can be taken to insure that the enterprise responds to these effectively?

What aspect of the organization’s activities needs to be closely integrated if the overall task is to be achieved?What organizational measures can be developed that will provide an appropriate measure of control and integration of work activities, while at the same time meeting the needs of people and providing adequate motivation?What environmental changes are likely to affect the future trend of company operations? What organizational measures can be taken to insure that the enterprise responds to these effectively?

Page 8: Project Management Session Fivegsme.sharif.edu/~projectmanagement/PMSession5.pdf4 Project Management Traditional Weaknesses Management is satisfied with its technical skills, but projects

8

The Classical Management Structure

GeneralManager

Engineering Production Sales MarketingAdminis-trationDirector Level

Division Level

Department Level

Section Level Functional Responsibility

Admin.

Page 9: Project Management Session Fivegsme.sharif.edu/~projectmanagement/PMSession5.pdf4 Project Management Traditional Weaknesses Management is satisfied with its technical skills, but projects

9

Classical Structure AdvantagesClassical Structure Advantages

Easier budgeting and cost control are possible.Better technical control is possible.– Specialists can be grouped to share

knowledge and responsibility.– Personnel can be used on many different

projects.– All projects will benefit from the most

advanced technology (better utilization of scarce personnel).

It provides flexibility in the use of manpower.

Easier budgeting and cost control are possible.Better technical control is possible.– Specialists can be grouped to share

knowledge and responsibility.– Personnel can be used on many different

projects.– All projects will benefit from the most

advanced technology (better utilization of scarce personnel).

It provides flexibility in the use of manpower.

Page 10: Project Management Session Fivegsme.sharif.edu/~projectmanagement/PMSession5.pdf4 Project Management Traditional Weaknesses Management is satisfied with its technical skills, but projects

10

Advantages (Continued)Advantages (Continued)

It provides a broad manpower base to work with.It provides continuity in the functional disciplines; policies, procedures, and lines of responsibility are easily defined and understandable.It readily admits mass production activities within established specifications.It provides good control over personnel, since each employee has one and only one person to report to.Communication channels are vertical and well established.Quick reaction capability exists, but may be dependent upon the priorities of the functional managers.

It provides a broad manpower base to work with.It provides continuity in the functional disciplines; policies, procedures, and lines of responsibility are easily defined and understandable.It readily admits mass production activities within established specifications.It provides good control over personnel, since each employee has one and only one person to report to.Communication channels are vertical and well established.Quick reaction capability exists, but may be dependent upon the priorities of the functional managers.

Page 11: Project Management Session Fivegsme.sharif.edu/~projectmanagement/PMSession5.pdf4 Project Management Traditional Weaknesses Management is satisfied with its technical skills, but projects

11

Classical Structure DisadvantagesClassical Structure Disadvantages

No one individual is directly responsible for the total project (i.e., no formal authority; committee solutions).It does not provide the project-oriented emphasis necessary to accomplish the project tasks.Coordination becomes complex, and additional lead time is required for approval of decisions.

No one individual is directly responsible for the total project (i.e., no formal authority; committee solutions).It does not provide the project-oriented emphasis necessary to accomplish the project tasks.Coordination becomes complex, and additional lead time is required for approval of decisions.

Page 12: Project Management Session Fivegsme.sharif.edu/~projectmanagement/PMSession5.pdf4 Project Management Traditional Weaknesses Management is satisfied with its technical skills, but projects

12

Disadvantages (Continued)Disadvantages (Continued)

Decisions normally favor the strongest functional groups.There is no customer focal point.Response to customer needs is slow.There is difficulty in pinpointing responsibility; this is the result of little or no direct project reporting, very little project-oriented planning, and no project authority.Motivation and innovation are decreased.Ideas tend to be functionally oriented with little regard for ongoing projects.

Decisions normally favor the strongest functional groups.There is no customer focal point.Response to customer needs is slow.There is difficulty in pinpointing responsibility; this is the result of little or no direct project reporting, very little project-oriented planning, and no project authority.Motivation and innovation are decreased.Ideas tend to be functionally oriented with little regard for ongoing projects.

Page 13: Project Management Session Fivegsme.sharif.edu/~projectmanagement/PMSession5.pdf4 Project Management Traditional Weaknesses Management is satisfied with its technical skills, but projects

13

Functional/Traditional Organization Structure

GeneralManager

Engineering Production Sales MarketingAdminis-trationDirector Level

Division Level

Department Level

Section Level Functional Responsibility

Admin.

Page 14: Project Management Session Fivegsme.sharif.edu/~projectmanagement/PMSession5.pdf4 Project Management Traditional Weaknesses Management is satisfied with its technical skills, but projects

14

Functional WeaknessesFunctional Weaknesses

Functional organizations tend to emphasize the separate functional elements at the expense of the whole organization.Under functional departmentation there is no group that effectively integrates the various functions of an organization and monitors them from the “big picture standpoint.”Functional organizations do not tend to develop “general managers.”Functional organizations emphasize functional relationships based on the vertical organizational hierarchy.

Functional organizations tend to emphasize the separate functional elements at the expense of the whole organization.Under functional departmentation there is no group that effectively integrates the various functions of an organization and monitors them from the “big picture standpoint.”Functional organizations do not tend to develop “general managers.”Functional organizations emphasize functional relationships based on the vertical organizational hierarchy.

Page 15: Project Management Session Fivegsme.sharif.edu/~projectmanagement/PMSession5.pdf4 Project Management Traditional Weaknesses Management is satisfied with its technical skills, but projects

15

Functional Weaknesses(Continued)Functional Weaknesses(Continued)

Functional organizations tend to fragment other management processes.Functional organizations develop a strong resistance to change.Functional segregation through the formal organization process encourages conflict among the various functions.The emphasis on the various operation functions focuses attention on the internal aspects and relations of the company to the detriment of its external relations.Functional organizations tend to be closed systems.

Functional organizations tend to fragment other management processes.Functional organizations develop a strong resistance to change.Functional segregation through the formal organization process encourages conflict among the various functions.The emphasis on the various operation functions focuses attention on the internal aspects and relations of the company to the detriment of its external relations.Functional organizations tend to be closed systems.

Page 16: Project Management Session Fivegsme.sharif.edu/~projectmanagement/PMSession5.pdf4 Project Management Traditional Weaknesses Management is satisfied with its technical skills, but projects

16

Departmental Project Management

Division Manager

Department ZDepartment X Department Y

Project Leaders Project Leaders Project Leaders

Section Level Section Level Section Level

Page 17: Project Management Session Fivegsme.sharif.edu/~projectmanagement/PMSession5.pdf4 Project Management Traditional Weaknesses Management is satisfied with its technical skills, but projects

17

Project ExpeditorProject Expeditor

PIPING HVAC CHEMICAL DRAFTING

ENGINEERING DIVISION

LIAISON

DEPT.

Formal authority / reporting flow

Informal authority / reporting flow

legend

Page 18: Project Management Session Fivegsme.sharif.edu/~projectmanagement/PMSession5.pdf4 Project Management Traditional Weaknesses Management is satisfied with its technical skills, but projects

18

Project CoordinatorProject Coordinator

PROJECT MGR.

DIVISION MGR.LEGEND

FORMAL FLOW

INFORMAL FLOW

DEPT. MANAGER DEPT. MANAGER

Page 19: Project Management Session Fivegsme.sharif.edu/~projectmanagement/PMSession5.pdf4 Project Management Traditional Weaknesses Management is satisfied with its technical skills, but projects

19

Project Coordinator WeaknessesProject Coordinator Weaknesses

Upper-level management was not ready to cope with the problems arising from shared authority.Upper-level management was reluctant to relinquish any of its power and authority to project managers.Line-staff project managers who reported to a division head did not have any authority or control over those portions of a project in other divisions; that is, the project manager in the engineering division could not direct activities in the manufacturing division.

Upper-level management was not ready to cope with the problems arising from shared authority.Upper-level management was reluctant to relinquish any of its power and authority to project managers.Line-staff project managers who reported to a division head did not have any authority or control over those portions of a project in other divisions; that is, the project manager in the engineering division could not direct activities in the manufacturing division.

Page 20: Project Management Session Fivegsme.sharif.edu/~projectmanagement/PMSession5.pdf4 Project Management Traditional Weaknesses Management is satisfied with its technical skills, but projects

20

Pure Project Structure

General Manager

Project AManager

Project BManager

Project CManager

ENG. MFG.ENG. MFG. ENG. MFG.

Page 21: Project Management Session Fivegsme.sharif.edu/~projectmanagement/PMSession5.pdf4 Project Management Traditional Weaknesses Management is satisfied with its technical skills, but projects

21

Projectized Structure AdvantagesProjectized Structure Advantages

It provides complete line authority over the project (i.e., strong control through a single project authority).The project participants work directly for the project manager. Unprofitable product lines are easily identified and can be eliminated.There are strong communications channels.Staffs can maintain expertise on a given project without sharing key personnel.Very rapid reaction time is provided.

It provides complete line authority over the project (i.e., strong control through a single project authority).The project participants work directly for the project manager. Unprofitable product lines are easily identified and can be eliminated.There are strong communications channels.Staffs can maintain expertise on a given project without sharing key personnel.Very rapid reaction time is provided.

Page 22: Project Management Session Fivegsme.sharif.edu/~projectmanagement/PMSession5.pdf4 Project Management Traditional Weaknesses Management is satisfied with its technical skills, but projects

22

Advantages (Continued)Advantages (Continued)

Personnel demonstrate loyalty to the project; better morale with product identification.A focal point develops for out-of-company customer relations.There is flexibility in determining time (schedule), cost, and performance trade-offs.Interface management becomes easier as unit size is decreased.Upper-level management maintains more free time for executive decision making.

Personnel demonstrate loyalty to the project; better morale with product identification.A focal point develops for out-of-company customer relations.There is flexibility in determining time (schedule), cost, and performance trade-offs.Interface management becomes easier as unit size is decreased.Upper-level management maintains more free time for executive decision making.

Page 23: Project Management Session Fivegsme.sharif.edu/~projectmanagement/PMSession5.pdf4 Project Management Traditional Weaknesses Management is satisfied with its technical skills, but projects

23

Projectized Structure DisadvantagesProjectized Structure Disadvantages

Cost of maintaining this form in a multi-product company would be prohibitive due to duplication of effort, facilities, and personnel; inefficient usage.There exists a tendency to retain personnel on a project long after they are needed. Upper-level management must balance workloads as projects start up and are phased out.

Cost of maintaining this form in a multi-product company would be prohibitive due to duplication of effort, facilities, and personnel; inefficient usage.There exists a tendency to retain personnel on a project long after they are needed. Upper-level management must balance workloads as projects start up and are phased out.

Page 24: Project Management Session Fivegsme.sharif.edu/~projectmanagement/PMSession5.pdf4 Project Management Traditional Weaknesses Management is satisfied with its technical skills, but projects

24

Disadvantages (Continued)Disadvantages (Continued)

Technology suffers because, without strong functional groups, outlook of the future to improve company’s capabilities for new programs would be hampered (i.e., no perpetuation of technology).Control of functional (i.e., organizational) specialists requires top-level coordination.There is a lack of opportunities for technical interchange between projects.There is a lack of career continuity and opportunities for project personnel.

Technology suffers because, without strong functional groups, outlook of the future to improve company’s capabilities for new programs would be hampered (i.e., no perpetuation of technology).Control of functional (i.e., organizational) specialists requires top-level coordination.There is a lack of opportunities for technical interchange between projects.There is a lack of career continuity and opportunities for project personnel.

Page 25: Project Management Session Fivegsme.sharif.edu/~projectmanagement/PMSession5.pdf4 Project Management Traditional Weaknesses Management is satisfied with its technical skills, but projects

25

The Matrix Management Structure

Engineering Operations Finance Others

Project Mgr.X

Project Mgr.Y

Project Mgr.Z

GeneralManager

Project Responsibility

Func

tiona

l Res

pons

ibili

ty

Page 26: Project Management Session Fivegsme.sharif.edu/~projectmanagement/PMSession5.pdf4 Project Management Traditional Weaknesses Management is satisfied with its technical skills, but projects

26

Matrix DevelopmentMatrix Development

Participants must spend full time on the project; this ensures a degree of loyalty.Horizontal as well as vertical channels must exist for making commitments.There must be quick and effective methods for conflict resolution.There must be good communication channels and free access between managers.

Participants must spend full time on the project; this ensures a degree of loyalty.Horizontal as well as vertical channels must exist for making commitments.There must be quick and effective methods for conflict resolution.There must be good communication channels and free access between managers.

All managers must have input into the planning process.Both horizontally and vertically oriented managers must be willing to negotiate for resources.The horizontal line must be permitted to operate as a separate entity except for administrative purposes.

All managers must have input into the planning process.Both horizontally and vertically oriented managers must be willing to negotiate for resources.The horizontal line must be permitted to operate as a separate entity except for administrative purposes.

Page 27: Project Management Session Fivegsme.sharif.edu/~projectmanagement/PMSession5.pdf4 Project Management Traditional Weaknesses Management is satisfied with its technical skills, but projects

27

Matrix Structure AdvantagesMatrix Structure Advantages

The project manager maintains maximum project control (through the line managers) over all resources, including cost and personnel.Policies and procedures can be set up independently for each project, provided that they do not contradict company policies and procedures.

The project manager maintains maximum project control (through the line managers) over all resources, including cost and personnel.Policies and procedures can be set up independently for each project, provided that they do not contradict company policies and procedures.

The project manager has the authority to commit company resources, provided that scheduling does not cause conflicts with other projects.Rapid responses are possible to change, conflict resolution, and project needs.The functional organization exists primarily as support for the project.

The project manager has the authority to commit company resources, provided that scheduling does not cause conflicts with other projects.Rapid responses are possible to change, conflict resolution, and project needs.The functional organization exists primarily as support for the project.

Page 28: Project Management Session Fivegsme.sharif.edu/~projectmanagement/PMSession5.pdf4 Project Management Traditional Weaknesses Management is satisfied with its technical skills, but projects

28

Matrix Structure Advantages (Continued)

Matrix Structure Advantages (Continued)

Each person has a “home” after project completion. People are susceptible to motivation and end-item identification. Each person can be shown a career path.Because key people can be shared, the program cost is minimized. People can work on a variety of problems: that is, better people control is possible.A strong technical base can be developed, and much more time can be devoted to complex problem-solving. Knowledge is available for all projects on an equal basis.

Each person has a “home” after project completion. People are susceptible to motivation and end-item identification. Each person can be shown a career path.Because key people can be shared, the program cost is minimized. People can work on a variety of problems: that is, better people control is possible.A strong technical base can be developed, and much more time can be devoted to complex problem-solving. Knowledge is available for all projects on an equal basis.Conflicts are minimal, hierarchical referral are easily resolved. There is a better balance between time, cost and performance.Rapid development of specialists and generalists occurs.Authority and responsibility are shared.Stress is distributed among the team (& functional managers).

Conflicts are minimal, hierarchical referral are easily resolved. There is a better balance between time, cost and performance.Rapid development of specialists and generalists occurs.Authority and responsibility are shared.Stress is distributed among the team (& functional managers).

Page 29: Project Management Session Fivegsme.sharif.edu/~projectmanagement/PMSession5.pdf4 Project Management Traditional Weaknesses Management is satisfied with its technical skills, but projects

29

Matrix Structure DisadvantagesMatrix Structure Disadvantages

Multidimensional information flow.Multidimensional work flow.Dual reporting.Continuously changing priorities.Management goals different from project goals.Potential for continuous conflict and conflict resolution.Difficulty in monitoring and control.

Multidimensional information flow.Multidimensional work flow.Dual reporting.Continuously changing priorities.Management goals different from project goals.Potential for continuous conflict and conflict resolution.Difficulty in monitoring and control.

Company-wide, the organizational structure is not cost-effective because more people than necessary are required, especially administrative.Each project organization operates independently. Care must be taken that duplication of efforts does not occur.More effort and time are needed initially to define policies & procedures, compared to traditional organizational form.

Company-wide, the organizational structure is not cost-effective because more people than necessary are required, especially administrative.Each project organization operates independently. Care must be taken that duplication of efforts does not occur.More effort and time are needed initially to define policies & procedures, compared to traditional organizational form.

Page 30: Project Management Session Fivegsme.sharif.edu/~projectmanagement/PMSession5.pdf4 Project Management Traditional Weaknesses Management is satisfied with its technical skills, but projects

30

Matrix Structure Disadvantages (Continued)

Matrix Structure Disadvantages (Continued)

Functional managers may be biased with own priorities.The balance of power between the project and functional organizations must be watched.The balance of time, cost & performance must be monitored.Although rapid response time is possible for individual problem resolution, the reaction time can become quite slow.

Functional managers may be biased with own priorities.The balance of power between the project and functional organizations must be watched.The balance of time, cost & performance must be monitored.Although rapid response time is possible for individual problem resolution, the reaction time can become quite slow.

Employees and managers are more susceptible to role ambiguity than in the traditional organizational form.Conflicts and their resolution may be a continuous process (possibly requiring support of an organizational specialist).People do not feel they have any control over their own destiny when continuously reporting to multiple managers.

Employees and managers are more susceptible to role ambiguity than in the traditional organizational form.Conflicts and their resolution may be a continuous process (possibly requiring support of an organizational specialist).People do not feel they have any control over their own destiny when continuously reporting to multiple managers.

Page 31: Project Management Session Fivegsme.sharif.edu/~projectmanagement/PMSession5.pdf4 Project Management Traditional Weaknesses Management is satisfied with its technical skills, but projects

31

Matrix Structure Disadvantages (Continued)

Matrix Structure Disadvantages (Continued)

Employees and managers are more susceptible to role ambiguity than in the traditional organizational form.Conflicts and their resolution may be a continuous process (possibly requiring support of an organizational specialist).People don’t feel they control their own destiny when continuously reporting to multiple managers.

Employees and managers are more susceptible to role ambiguity than in the traditional organizational form.Conflicts and their resolution may be a continuous process (possibly requiring support of an organizational specialist).People don’t feel they control their own destiny when continuously reporting to multiple managers.

Page 32: Project Management Session Fivegsme.sharif.edu/~projectmanagement/PMSession5.pdf4 Project Management Traditional Weaknesses Management is satisfied with its technical skills, but projects

32

Matrix Management Structure (With a Director of Project Management)

Director:Project Mgmt.

Director:Engineering

Director:Manufacturing

Director:Finance/Admin.

Project Mgr. X

Project Mgr. Y

Project Mgr. Z

General Manager

Page 33: Project Management Session Fivegsme.sharif.edu/~projectmanagement/PMSession5.pdf4 Project Management Traditional Weaknesses Management is satisfied with its technical skills, but projects

33

Weak Matrix OrganizationWeak Matrix Organization

ChiefExecutive

FunctionalManager

FunctionalManager

FunctionalManager

Staff

Staff

Staff

Staff

Staff

Staff

Staff

Staff

Staff

ProjectCoordination

Page 34: Project Management Session Fivegsme.sharif.edu/~projectmanagement/PMSession5.pdf4 Project Management Traditional Weaknesses Management is satisfied with its technical skills, but projects

34

Balanced Matrix OrganizationBalanced Matrix Organization

ChiefExecutive

FunctionalManager

FunctionalManager

FunctionalManager

ProjectManager

Staff

Staff

Staff

Staff

Staff

Staff

Staff

Staff

ProjectCoordination

Page 35: Project Management Session Fivegsme.sharif.edu/~projectmanagement/PMSession5.pdf4 Project Management Traditional Weaknesses Management is satisfied with its technical skills, but projects

35

Strong Matrix OrganizationStrong Matrix Organization

ChiefExecutive

FunctionalManager

FunctionalManager

FunctionalManager

Staff

Staff

Staff

Staff

Staff

Staff

Staff

Staff

Staff

ProjectCoordination

Manager ofProj Mgrs

ProjectManager

ProjectManager

ProjectManager

Page 36: Project Management Session Fivegsme.sharif.edu/~projectmanagement/PMSession5.pdf4 Project Management Traditional Weaknesses Management is satisfied with its technical skills, but projects

36

Composite Matrix OrganizationComposite Matrix Organization

ChiefExecutive

FunctionalManager

FunctionalManager

FunctionalManager

Staff

Staff

Staff

Staff

Staff

Staff

Staff

Staff

Staff

ProjectCoordination

Manager ofProj Mgrs

ProjectManager

ProjectManager

ProjectManager

Proj

ect

Coo

rdin

atio

n

Page 37: Project Management Session Fivegsme.sharif.edu/~projectmanagement/PMSession5.pdf4 Project Management Traditional Weaknesses Management is satisfied with its technical skills, but projects

37

Organization StructureInfluence on ProjectsOrganization StructureInfluence on Projects

Functional WeakMatrix

BalancedMatrix

StrongMatrix

Project-ized

Project M.Authority

Little Limited Low to Moderate

ModerateTo High

High toTotal

ResourceAvailability

Little Limited Low to Moderate

ModerateTo High

High toTotal

Control ofBudget

FunctionalManager

FunctionalManager

Mixed ProjectManager

ProjectManager

Project M.Role

Part-time Part-time Full-time Full-time Full-time

Project M.Adm Staff

Part-time Part-time Part-time Full-time Full-time

Page 38: Project Management Session Fivegsme.sharif.edu/~projectmanagement/PMSession5.pdf4 Project Management Traditional Weaknesses Management is satisfied with its technical skills, but projects

38

The Out-of-control Matrix

Reduced authority for the project manager.

All project decision-making performed at executive levels.

Increase in executive meddling in projects.

Creation of endless job description manuals.

When a matrix appears to be out of control executives tend to revert back to classical management. This results in:

This can often be prevented by asking for authority / responsibility clarification and using a responsibility assignment matrix (RAM).

Page 39: Project Management Session Fivegsme.sharif.edu/~projectmanagement/PMSession5.pdf4 Project Management Traditional Weaknesses Management is satisfied with its technical skills, but projects

39

Factors for Selecting an Organizational FormFactors for Selecting an Organizational FormProject sizeProject lengthProject management experiencePhilosophy and visibility of executivesProject locationAvailable resourcesUnique aspects of the project

Project sizeProject lengthProject management experiencePhilosophy and visibility of executivesProject locationAvailable resourcesUnique aspects of the project

Page 40: Project Management Session Fivegsme.sharif.edu/~projectmanagement/PMSession5.pdf4 Project Management Traditional Weaknesses Management is satisfied with its technical skills, but projects

40

Balancing Technical and Human Skills

Technical Skills High

LowHuman Skills

Junior Senior Supervisor Middle Senior PresidentTeam Member Team Member Manager Officer

Page 41: Project Management Session Fivegsme.sharif.edu/~projectmanagement/PMSession5.pdf4 Project Management Traditional Weaknesses Management is satisfied with its technical skills, but projects

41

Multidimensional MatrixMultidimensional Matrix

Time, Dimension or Space

Note: Each slice could be a different country.

Page 42: Project Management Session Fivegsme.sharif.edu/~projectmanagement/PMSession5.pdf4 Project Management Traditional Weaknesses Management is satisfied with its technical skills, but projects

42

Project vs. Functional Influences

Project Influence in Decision-Making

Dual Influence

FunctionalOrganization

Matrix ProjectOrganization

Rel

ativ

e In

fluen

ce

Functional InfluenceIn Decision-Making

Organization