8/13/2019 Project Management - Money
1/14
8/13/2019 Project Management - Money
2/14
MONEY
Often a Project Manager is evaluated on his or her ability to complete a project within budg
effectively managed the project resources and project schedule, this should not be a probl
however, a task that requires the project manager's careful attention. You can only manage
limited number of cost items, so focus on the critical ones
COSTS
CONTINGENCIES
PROFIT
8/13/2019 Project Management - Money
3/14
COSTS
COSTS
ESTIMATE
ACTUAL
VARIABILITY
8/13/2019 Project Management - Money
4/14
CONTINGENCIES
CONTINGENCIES
WEATHER
SUPPLIERS
DESIGN ALLOWANCE
8/13/2019 Project Management - Money
5/14
PROFIT
PROFIT
COST
CONTINGENCIES
REMAINDER
8/13/2019 Project Management - Money
6/14
CAPITAL COST
The capital cost for a construction project includes the expenses related to the inital establishm
Land acquisition, including assembly, holding and improvement
Planning and feasibility studies
Architectural and engineering design
Construction, including materials, equipment and labor
Field supervision of construction
Construction financing
Insurance and taxes during construction
Owner's general office overhead
Equipment and furnishings not included in construction
Inspection and testing
8/13/2019 Project Management - Money
7/14
OPERATION AND MAINTENANCE COST
The operation and maintenance cost in subsequent years over the project life cycle includ
expenses:
Land rent, if applicable
Operating staff
Labor and material for maintenance and repairs
Periodic renovations
Insurance and taxes
Financing costs
Utilities
Owner's other expenses
8/13/2019 Project Management - Money
8/14
CONTINGENCIES / UNEXPECTED COSTS
In most construction budgets, there is an allowance for contingencies or unexpected costs occuconstruction. This contingency amount may be included within each cost item or be included in of construction contingency. The amount of contingency is based on historical experience and tdifficulty of a particular construction project.
EXAMPLE
Construction firm estimates of the expected cost in five different areas in construction
Design development changes,
Schedule adjustments,
General administration changes (such as wage rates),
Differing site conditions for those expected, and
Third party requirements imposed during construction, such as new permits.
8/13/2019 Project Management - Money
9/14
8/13/2019 Project Management - Money
10/14
TYPES OF CONSTRUCTION COST ESTIMATES
Construction cost estimates may be viewed from different perspectives because of differen
requirements. In spite of the many types of cost estimates used at different stages of a pro
estimates can best be classified into three major categories according to their functions.
Design Estimates
Bid Estimates
Control Estimates
8/13/2019 Project Management - Money
11/14
DESIGN ESTIMATES
For the owner or its designated design professionals, the types of cost estimates encounte
with the planning and design as follows:Screening estimates (or order of magnitude estim
Preliminary estimates (or conceptual estimates)
Detailed estimates (or definitive estimates)
Engineer's estimates based on plans and specifications
8/13/2019 Project Management - Money
12/14
BID ESTIMATES
For the contractor, a bid estimate submitted to the owner either for competitive bidding or n
consists of direct construction cost including field supervision, plus a markup to cover gene
and profits. The direct cost of construction for bid estimates is usually derived from a comb
following approaches.
Subcontractor quotations
Quantity takeoffs
Construction procedures.
8/13/2019 Project Management - Money
13/14
8/13/2019 Project Management - Money
14/14
REFERENCES
http://management.about.com/cs/projectmanagement/a/PM101d.htm
http://pmbook.ce.cmu.edu/05_Cost_Estimation.html#5.9 Applications of Cost Indices to
http://management.about.com/cs/projectmanagement/a/PM101d.htmhttp://management.about.com/cs/projectmanagement/a/PM101d.htmhttp://management.about.com/cs/projectmanagement/a/PM101d.htm