Top Banner

of 14

Project Management - Money

Jun 04, 2018

Download

Documents

Kymie Perez
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
  • 8/13/2019 Project Management - Money

    1/14

  • 8/13/2019 Project Management - Money

    2/14

    MONEY

    Often a Project Manager is evaluated on his or her ability to complete a project within budg

    effectively managed the project resources and project schedule, this should not be a probl

    however, a task that requires the project manager's careful attention. You can only manage

    limited number of cost items, so focus on the critical ones

    COSTS

    CONTINGENCIES

    PROFIT

  • 8/13/2019 Project Management - Money

    3/14

    COSTS

    COSTS

    ESTIMATE

    ACTUAL

    VARIABILITY

  • 8/13/2019 Project Management - Money

    4/14

    CONTINGENCIES

    CONTINGENCIES

    WEATHER

    SUPPLIERS

    DESIGN ALLOWANCE

  • 8/13/2019 Project Management - Money

    5/14

    PROFIT

    PROFIT

    COST

    CONTINGENCIES

    REMAINDER

  • 8/13/2019 Project Management - Money

    6/14

    CAPITAL COST

    The capital cost for a construction project includes the expenses related to the inital establishm

    Land acquisition, including assembly, holding and improvement

    Planning and feasibility studies

    Architectural and engineering design

    Construction, including materials, equipment and labor

    Field supervision of construction

    Construction financing

    Insurance and taxes during construction

    Owner's general office overhead

    Equipment and furnishings not included in construction

    Inspection and testing

  • 8/13/2019 Project Management - Money

    7/14

    OPERATION AND MAINTENANCE COST

    The operation and maintenance cost in subsequent years over the project life cycle includ

    expenses:

    Land rent, if applicable

    Operating staff

    Labor and material for maintenance and repairs

    Periodic renovations

    Insurance and taxes

    Financing costs

    Utilities

    Owner's other expenses

  • 8/13/2019 Project Management - Money

    8/14

    CONTINGENCIES / UNEXPECTED COSTS

    In most construction budgets, there is an allowance for contingencies or unexpected costs occuconstruction. This contingency amount may be included within each cost item or be included in of construction contingency. The amount of contingency is based on historical experience and tdifficulty of a particular construction project.

    EXAMPLE

    Construction firm estimates of the expected cost in five different areas in construction

    Design development changes,

    Schedule adjustments,

    General administration changes (such as wage rates),

    Differing site conditions for those expected, and

    Third party requirements imposed during construction, such as new permits.

  • 8/13/2019 Project Management - Money

    9/14

  • 8/13/2019 Project Management - Money

    10/14

    TYPES OF CONSTRUCTION COST ESTIMATES

    Construction cost estimates may be viewed from different perspectives because of differen

    requirements. In spite of the many types of cost estimates used at different stages of a pro

    estimates can best be classified into three major categories according to their functions.

    Design Estimates

    Bid Estimates

    Control Estimates

  • 8/13/2019 Project Management - Money

    11/14

    DESIGN ESTIMATES

    For the owner or its designated design professionals, the types of cost estimates encounte

    with the planning and design as follows:Screening estimates (or order of magnitude estim

    Preliminary estimates (or conceptual estimates)

    Detailed estimates (or definitive estimates)

    Engineer's estimates based on plans and specifications

  • 8/13/2019 Project Management - Money

    12/14

    BID ESTIMATES

    For the contractor, a bid estimate submitted to the owner either for competitive bidding or n

    consists of direct construction cost including field supervision, plus a markup to cover gene

    and profits. The direct cost of construction for bid estimates is usually derived from a comb

    following approaches.

    Subcontractor quotations

    Quantity takeoffs

    Construction procedures.

  • 8/13/2019 Project Management - Money

    13/14

  • 8/13/2019 Project Management - Money

    14/14

    REFERENCES

    http://management.about.com/cs/projectmanagement/a/PM101d.htm

    http://pmbook.ce.cmu.edu/05_Cost_Estimation.html#5.9 Applications of Cost Indices to

    http://management.about.com/cs/projectmanagement/a/PM101d.htmhttp://management.about.com/cs/projectmanagement/a/PM101d.htmhttp://management.about.com/cs/projectmanagement/a/PM101d.htm