    2006 Management Meeting

    PROJECT MANAGEMENT IN GLOBAL & OFFSHORE R&D ENVIRONMENT:ISSUES AND EVOLUTION OF PROCESS

    Narendra Pratap [email protected]

  • 8/8/2019 Project Management in Global Offshore Rd Environment

    2/18

    About The Topic

    Offshoring of product design, development, engineering and research

    is fairly new global phenomenon. Workflow at R&D center entailscomplexities in terms of varying size of work packets, work content,clarity level, type of work, control level etc.This is an effort to provide a practitioner's perspective about evolutionof project management system & process at an offshore R&D andengineering center

    StructurePhenomenon of offshoring

    Categorization of workflow

    Project performance of offshore center

    Project Management Practices at the offshore R&D center

    Planning, Time, Communication, Cost, Quality, HR, Portfolio

    System requirement, PMO and Future predictions

  • 8/8/2019 Project Management in Global Offshore Rd Environment

    3/18

    Product of Flat World

    Driven by organizational growthoriented forcesMarket expansion

    Selling

    Product customization & modificationfor local needsManufacturing localization for costcuttingLocal engineering supportEngineering support to other businessunits engineering teams

    Success of engineering & design teams

    Created confidence about skills

    External Drivers like corecompetency, cost competitionIT outsourcingBP outsourcing

    KP outsourcingEngineering Services

    OutsourcingOffshoring

    Success & cost saving by IT, BPO & KPO C

    reated environment

    Phenomenon of globalization of Business is taken as Flattening of World

    Two forces, one from inside organization and another from external environmentshaped offshoring of design, engineering and R&D

    Currently 500 offshore Engineering and R&D centers working in India

    No. growing @ 23% CAGR*

  • 8/8/2019 Project Management in Global Offshore Rd Environment

    4/18

  • 8/8/2019 Project Management in Global Offshore Rd Environment

    5/18

    Workflow Projectizing it

  • 8/8/2019 Project Management in Global Offshore Rd Environment

    6/18

    Issue of Performance Parameters

    Traditional benchmarks for project performance parameterTime and schedule efficiency

    Cost and financial efficiencyResource utilization efficiency

    Deliverables quality as per predefined known acceptability parameters

    Performance benchmark for Innovation centers sponsorBusiness value of output

    Cost saving by offshoring

    New initiativesIntellectual property creation

    Best utilization of all type of resources proper administration

    Corporate measures the project output of their offshore center, differently from the

    existing project performance parameters

  • 8/8/2019 Project Management in Global Offshore Rd Environment

    7/18

    TRIZ Framework for Project Categorization

    TRIZ provides tools and methods for use in problem formulation,system analysis, failure analysis, and patterns of system evolution(both 'as-is' and 'could be').

  • 8/8/2019 Project Management in Global Offshore Rd Environment

    8/18

    Project Mgmt. Practices Project Planning

    General Issues

    Away from market,customer &manufacturing

    Multiple locations /multiple systems

    Scoping

    OwnershipEnd to end project foroffshore center

    Specs. by sponsor,detailing and execution atoffshore

    Work details fromsponsor, to do task atoffshore

    Interventions

    Resolution

    Process for project initiation andauthorization

    One innovation, product developmentprocess

    Collaborative planning

    ScopingMajor role for sponsor

    Offshore center should try to fill open spacein scope, proactively

    Clear-cut work breakdown

    Clarity on ownership of WBSTime line, milestones & deliverablesdefinition mutually agreed

    Approval on all aspects

  • 8/8/2019 Project Management in Global Offshore Rd Environment

    9/18

    Project Mgmt. Practices Time Mgmt.

    Vis--vis onsite,

    offshore workingadds extra hours

    Requirementunderstanding

    Communication

    Data managementReviews,approvals andreports

    At least twolayers of project

    managementTime efficiencybecomes veryimportant

    Resolution

    Invest time in requirement understanding

    Setting expectation

    Fully aligned team for each location/program

    Integrated project plan for both offshore andsponsor

    Time and task tracking system

    Fill gap projects and competency building foreffective resource utilization

    Under a project

    Develop schedule for WBS

    Extra care for the scheduling of shared domainexperts

    Resource leveling as per project priority

  • 8/8/2019 Project Management in Global Offshore Rd Environment

    10/18

    Project Mgmt. Practices Communication Mgmt.

    Considered important for

    project successChallenge in offshoreenvironment

    Cultural aspects

    Distance and sense of itPeople handlingcommunication hard coredomain expert

    Communicated things get

    lost in the haze of time

    Provide required infrastructure

    Mail/tele/video con, recording,session sharing tools

    Policy matter on communicationCalendar for real-timecommunication

    On-site visits at regular intervals

    Communication RecordImportant with PDLC

    Unified system for communication

    archiving

  • 8/8/2019 Project Management in Global Offshore Rd Environment

    11/18

    Project Mgmt. Practices Cost Mgmt.

    Cost headsCost of humanresources hrs.

    All project expenses

    Common expenses

    Capital expenditure

    Common

    Facilities (e.g. RP

    Machines)

    Time management systemAverage cost of hours from cost of human resource

    Project management system based expense

    trackerInputs from financial operation

    Well defined financial process and tracker

    Organizational policy for common expense loading

    Depreciation loading for common capex. directly relatedto hours of project e.g.= (hrs. on project x/ total

    hrs)*(total depreciation)Tracker for the usage of special facilities

    Load the cost to projects

    Cost saving first reason of offshoring

    Cost of project directly loaded to the cost of product, research program, new initiative

  • 8/8/2019 Project Management in Global Offshore Rd Environment

    12/18

    Project Mgmt. Practices HR Mgmt.

    Organizational Structure

    More than just a matrix structureProgram (Vertical), Domain (Horizontal), COEs(Bubble)

    Support departments (Finance, HR, Operation) Coordination

    Performance Management

    Input from project portfolio systemAppraise from all elements of org. structure

    Training need

    RecruitmentFor thinking ability, application mind and then forknowledge

    McGregors Y peopleFailure handling / high self esteem people

    RetentionStrategic aspect can make or break the result

    Maslows hierarchy

    Inside a project

    Assigning resourceas per WBS

    Project leader

    Project specificteam structure

    Domain specificleader

    Proper resourceleveling

  • 8/8/2019 Project Management in Global Offshore Rd Environment

    13/18

    Project Mgmt. Practices Quality Mgmt.

    Quality measurementfor varying type ofoutputs

    Objectively measurable

    Quality of unseen,

    unknownQuality of research

    Quality as a feature

    Subjective quality statement about qualityof product would work as a guidelinesomething like Quality Mission Statement

    Review deliverables at every stage gatejointly by sponsor, domain experts and teammembers

    Review comments & feedback from sponsoras first priority input

    Quality process for measurable

    Usage of suitable processes for subjectivevariables at appropriate stage

    FMEA, Six Sigma, DFA, DFMQuality in-built with work

  • 8/8/2019 Project Management in Global Offshore Rd Environment

    14/18

    Project Portfolio Management

    Central system, a repository of all projects

    Immediate indicator about risk, deadlines, completionsReport to corporate about performanceProject based performance indicators

    Business value creationDirect and Indirect contribution

    Contribution in top-line, bottom-line and business sustenanceAll project expenses and costsProgram performanceTeams, individualsCompetency development

  • 8/8/2019 Project Management in Global Offshore Rd Environment

    15/18

  • 8/8/2019 Project Management in Global Offshore Rd Environment

    16/18

    PMO

    Process owner and manager

    Process standardization / templates /best practices

    Support, guidance & training provider

    Owner of project management system

    Strong IT support team for project management system

    Time management, engagement level assuranceRequirement more prominent as the size of is now feltprominently

    Integrate the job for portfolio management

    Practical exposer of product development / innovationprocess first priority, knowledge of PM methodology second