-
Assignment Record Form
Student Name : K. Sivabala Naidu
IC / Passport Number : 861101-56-5057
Nationality : Malaysian
IPE Index Number : MYS-0100588
Teamie Index Number : [email protected]
Learning Centre : KL
Course : MBA
Term : 1
Module Title : Project Management
Centre Facilitator Name : Dr. Dasaratha Rao
Assignment Submission Due Date : 1st June 2014
Status : Active
I declare that this is an original piece of work undertaken by
me.
I confirm that I have read and understood the IPE regulations
with regard to referencing and
plagiarism.
YES NO
Note: Please read the Instruction to Upload the Assignment on
TeamieLearning Portal before uploading your assignment.
-
IPE MBA Project Management Assignment Page 2 of 17
Executive summary
The purpose of this report was to undertake a thorough
investigation about as to the various
causative factors which may have contributed to the failure of
KLIA 2 by Malaysia Airports
Holdings Berhad (MAHB) wherein the cost overrun was from RM 1.9
Billion to RM 4.0 Billion
and with more than 2 years of delay in its completion.
One of the major factors which may have contributed to the cost
overrun and delayed completion
is the inability to manage change. As we know, managing the
changes in a project is a part of
project management life cycle. Based on the report, given by CEO
& Managing Director of
Malaysia Airports Holdings Berhad (MAHB) Tan Sri Bashir Ahmad,
the new terminal was
delayed three times from its original completion date of
September 2011, is because of the new
requirements. If only the additional or new requirements was
managed with a scope which is a
major factor in having a balanced project management these cost
overrun and delay would not
had occurred.
After taking all the project success and failure factors into
consideration, I would like to
recommend to the Chairperson of the MAHB Board of Directors to
use Statement of Work
(SOW). Plan the purpose of the project by taking into
consideration, the risk management and
scope in this case is to finish the KLIA 2 as per the initial
project planning without running away
from the schedule and cost and to clearly outline the possible
risks, and management of the risk
so that when a change or new requirements arises we could manage
it without interrupting the
iron triangle, where the main components are quality, scope,
cost and schedule. Which is the key
being the co-ordination between all the sectors working in
building KLIA 2.
-
IPE MBA Project Management Assignment Page 3 of 17
Table of contents
Introduction
1.1 Purpose 4
1.2 Overview. 4
Main Body
2.1 The cost overrun & delays.......... 6
2.2 The lack of change management team in Project KLIA 2 ....
8
2.3 The purpose of project management life cycle in a project
11
2.4 Statement of Work (SOW). 13
2.5 The common pitfalls in a project.... 15
Conclusion & Recommendations. 16
References. 17
Word count: 4.013
-
IPE MBA Project Management Assignment Page 4 of 17
Introduction
1.1) Purpose
The purpose of this report was to undertake a thorough
investigation about as to the various
causative factors which may have contributed to the failure of
KLIA 2, by Malaysia Airports
Holdings Berhad (MAHB) wherein the cost overrun was from RM1.9
Billion to RM 4.0 Billion
and with more than 2 years of delay in its completion. Based on
the report provided by Tan Sri
Bashir Ahmad, CEO & Managing Director of Malaysia Airports
Holdings Berhad (MAHB), the
cost of KLIA 2 has been doubled due to revision to increase 71%
of its original capacity. The
revised plan is based from Air Asias growth projection, this is
simply because Air Asia being
the main stake holder in KLIA 2. In 2013, Air Asia has flown
more than 21.85 million
passengers in LCCT. With 3% growth annually, the initially
planned KLIA 2 will be crowded in
10 years time. To build such airport at that time will cost us
double or triple. Therefore the
revision took place to avoid building another airport in the
next 10 15 years time.
1.2) Overview
The KLIA 2 is built to be Malaysia's Next Generation Hub the
airport hub that will allow
seamless connectivity between low-cost and full service
carriers. The new KLIA 2 terminal is
measured to be at least 257,000 m2, with 60 gates, 8 remote
stands, 80 aerobridges, plus a retail
space of 32,000 m2 to accommodate 225 retail outlets. It is
designed to cater 30 million
passengers a year with the provision to expand to 45 million.
Built at a cost around 4.0 billion
ringgit which was noticeably a cost overrun, the KLIA 2 was
scheduled to open on April 2013
but delayed. Below is a table comparing the cost and other
criteria of KLIA, LCCT and KLIA 2.
Adding to that, KLIA 2 was built to replace the current LCCT.
Firstly, Air Asia the fastest
growing and largest low cost airline in Asia needs a bigger home
to accommodate a larger
number of passengers. Secondly, is to accommodate KLIAs growth
and vision. How does
KLIA2 fit into KLIAs vision? The terminal has an integrated
international concourse that will
enable seamless transfer to domestic flights and vice versa. In
other words, it will provide more
traffic to KLIA. Not only that, due to limited runway capacity
faced by Changi Airport,
Soekarno Jakarta Airport and Bangkok Suvarnabhurmi Airport, ours
KLIA is set to be a regional
-
IPE MBA Project Management Assignment Page 5 of 17
hub in Southeast Asia. The completion of KLIA2 will bring the
airports total capacity to 85
million. But more importantly, the additional runway from KLIA2
will reduce congestion. In
addition, KLIA 2 is also designed to be a retail airport. The
large terminal is due to the large
space for retail. Airport operator now comprehend that more
revenue must come from this
source. The reason is many middle income people from Southeast
Asia choose to fly with Low
Cost Carrier and they expect much more amenities once they land.
When you consider there are
550 million people in ASEAN and only around 4% are currently
flying, you can see the potential
in retail.
The major key player being; Developer Malaysia Airports Holdings
Berhad (MAHB),
Contractor UEM Construction Bina Puri JV, Design Architect LKMD
Architecture Sdn.
Bhd., Architects - A.Hanapiah Architect and Arkitek ICB Sdn.
Bhd. As in any branch or division
of a business unit one needs to have a clear notion on the
accountability and responsibility within
the project management domain too. The project managers must be
well aware of their
responsibilities and the accountability towards the project
whether it is a success or a failure. The
airport operator, which took over as project manager from KLIA
consult in November 2011, has
been blamed for the delay and higher cost of completing KLIA 2,
a terminal dedicated to low
-
IPE MBA Project Management Assignment Page 6 of 17
cost carriers. Project manager should be coordinating all the
sectors and failure in
communication which will result in failure of delivering the
project as per cost and schedule.
Main Body
2.1) The cost overrun and delays
The delay and cost overrun has been mainly due to changes of the
design of the airport
and its size it was initially meant to handle a passenger volume
of 30 million but this was scaled
up to 45 million passengers per year based on the recent Air
Asias growth projection. Thus,
there were a 71% of its original capacity been changed. What
started as a 150,000 m2 terminal
with 50 semi contact gates and 2.5km runway, to a 257,000 m2
terminal with 68 gates fully
aerobridges and 3.9km runway. Rather than anticipating and
managing the changes, the parties
involved in KLIA 2 began to point finger at each other. There is
clearly a shortage of
coordination between the major key players. For example, MAHB
which has come under fire
from all sides for the delay in the completion of KLIA 2 is
pointing finger at Air Asia Berhad,
government agencies and the main contractor. The baggage
handling system was relocated on
the advice of the Department of Civil Aviation. This clearly
shows that there were no prior
discussion with related agencies and department before the
project execution period. There was
no prior anticipation. There was an increase in the scope of
work. Below I have attached a table
of the specifications of the upgrades. Changes, upgrades and new
addition are not a stranger in
the event of a project management, thus the problem or the
reason for the project failure in terms
of cost overrun and inability to deliver on time is due to poor
management skill. Thus, the parties
involved should be able to see clearly that the problem was not
the change; it was the inability to
adapt and deliver to the change. The final design is supposed to
be frozen says the main
contractor The Star online June 28. This statement itself shows
the lack of anticipation. The
planning part is one of the key in project management life
cycle. Under the planning vice comes
risk plan and acceptance plan which will be elaborated in the
later part.
-
IPE MBA Project Management Assignment Page 7 of 17
Major upgrades in specifications
-
IPE MBA Project Management Assignment Page 8 of 17
2.2) The Lack of Change Management Team in Project KLIA 2
Project management is an approach to managing work within the
constraints of time, cost
and business objectives. Whether you are using Six Sigma, DMAIC
or Lean, there are
techniques and tools project teams can apply to plan, control
and monitor results. Change
management can and should follow a similar structured process.
Prosci, whose change
management methodology is one of the most widely used and
recognized approaches for
managing the people side of change, includes a set of
assessments to help you identify risk and
address assumptions you may have made in planning for the
project. At each gate or phase of
your project, Prosci defines specific plans to help execute and
manage the change to ensure you
not only meet your business objectives, but new processes are
adopted and sustained. While
project management handles the technical side of the project,
change management facilitates the
acceptance of the initiative taking place. Project management
life cycle focuses on the technical
aspect of moving from current state to future state while change
management focuses on people
aspect. Change management and project management are
complementary disciplines with a
common objective. When applied using proven steps and tools, you
greatly increase your
probability of success. How dependent are your project outcomes
on people changing the way
they do their work? No matter how well we follow the project
plan, if people do not change the
way they do their job, we will not achieve the desired business
results.
The failure of KLIA 2 is due to the absence in change
management. The number one rule
in change management is preparing for the change and preparing
change management team. We
can clearly see that in KLIA 2 they were not at all open to the
idea of a future change thus the
change has been viewed as a glitch in the project. And when
there is a change in the project, the
people need to cope with the change. Here the partys involved in
KLIA 2 does not manage to
change their mindset and work phase accordingly. If there is an
increase in job scope thus there
is a need to increase the velocity of the work of the people and
maybe a need to increase the
number of workforce. They should have anticipated such changes
in the beginning of the project
itself and have an allocation of cost if such changes would have
occurred. In KLIA 2 they did
blame the cost overrun due to the increase of number of workers
needed. This shows that such
changes were not anticipated by the team. Projects are naturally
subjected to change and it is up
to the project management team to deal with it. If only there
was a change management team in
-
IPE MBA Project Management Assignment Page 9 of 17
Project KLIA 2, the changes or any upgrades nor additional ideas
would have been managed
with structure and delays or cost overrun could been monitored
and controlled. People have a
natural tendency to resist change. No matter how flawlessly
executed, the project will not meet
its objectives if no one follows the new process, uses the new
technology or changes the way
they work. The more effective your change management plan, the
more likely your project is to
finish on or under budget. Effective change management ensures
faster speed of adoption,
increased proficiency and higher utilization.
-
IPE MBA Project Management Assignment Page 10 of 17
-
IPE MBA Project Management Assignment Page 11 of 17
2.3) The Purpose of Project Management Life Cycle in a
Project
Despite the fact that no two projects are exactly alike, but all
projects must go through
these four phases of project management life cycle. Initiation
involves starting up the project by
documenting a business case, conducting a feasibility study,
coming up with the terms of
reference, appointing the team and setting up a project office.
Planning involves setting out the
roadmap for the project by creating the following plans: project
plan, resource plan, financial
plan, quality plan, acceptance plan and communications plan.
Execution involves building the
deliverables and controlling the project delivery, scope, costs,
quality, risks and issues. Closure
involves winding down the project by releasing staff, handing
over deliverables to the
customer and completing a post implementation review.
In the initiation part of the project, these are the steps to be
done; develop a business case,
undertake a feasibility study, establish the project charter,
appoint the project team, set up the
project office and perform phase review. In the planning phase
we need to create a project plan,
resource plan, financial plan, quality plan, risk plan, an
acceptance plan, communications plan,
procurement plan, contract the suppliers, define the tender
process, issue a statement of work,
request for information, request for proposal, and create a
supplier contract and perform another
phase review. In the project execution phase, we build
deliverables and perform monitor and
control, perform time, cost, quality, risk and issue management
and perform procurement
management acceptance and communications management. In the
closure phase, we perform
project closure and review project completion.
At the beginning of project initiation, a project manager is
assigned. The project manager
works with the project sponsor to identify the necessary
resources and team members needed to
further develop the key project parameters Cost, Scope,
Schedule, and Quality (CSSQ). The
project team documents its charge in the form of a project
charter, which is based on the project
proposal, which includes the initial business case. Approval of
the Project Charter by the Project
Sponsor authorizes the designated team to begin the initial
planning effort. The initial Project
Plan resulting from Project Initiation differs in the level of
detail and the validity of its estimates
from Project Origination, and must be at a level sufficient to
acquire any additional resources
needed to progress to the next phase. The Project Plan also
includes plans for involving and
-
IPE MBA Project Management Assignment Page 12 of 17
communicating with all the parties that are affected by the
project, as well as identification of an
initial set of foreseeable risks that can threaten the project.
At the conclusion of Project Initiation,
based on the initial planning documents, the Business Case is
revised and re-evaluated and a
decision is made to halt or proceed with the project.
Project Planning builds on the work done in Project Initiation,
refining and augmenting
CSSQ and Project Plan deliverables. Usually, additional members
join the Project Team, and
they assist the Project Manager in further elaborating the
details of the Cost, Scope, Schedule
and Quality. A number of key elements are added to the Project
Plan, including project-specific
items such as change control, acceptance management and issue
management, as well as
externally-focused items such as organizational change
management and project transition. The
initial list of project risks is augmented, and detailed
mitigation plans are developed. At the
conclusion of Project Planning, the Business Case is revised and
re-evaluated based on the
completed planning documents and a decision is again made to
either halt the project, or to
commit the resources necessary for Project Execution and
Control.
Project Execution and Control is where most of the resources are
applied / expended on
the project. A significant number of team members will join the
project at the beginning of this
phase. The primary task of the Project Manager during Project
Execution and Control is to
enable the Project Team to execute the tasks on the defined
Project Schedule and develop the
product or service the project is expected to deliver. The
Project Manager uses the processes and
plans prepared during Project Initiation and Project Planning to
manage the project, while
preparing the organization for the implementation of the product
/ service and for transitioning
the product / service responsibility from the Project Team to
the Performing Organization.
In Project Closeout, the Project Team assesses the outcome of
the project, as well as the
performance of the Project Team and the Performing Organization.
This is accomplished
primarily through soliciting and evaluating feedback from
Customers, Project Team members,
Consumers and other stakeholders. The primary purpose of this
assessment is to document best
practices and lessons learned for use on future projects.
-
IPE MBA Project Management Assignment Page 13 of 17
2.4) Statement of Work (SOW)
It is important to create a statement of work (SOW) for the case
study where we identify
the purpose, scope, project deliverables, goals and objectives
and cost and schedule estimates. In
risk management we need to identify, analyze and have a risk
plan. In risk management we need
to identify the sources of risk, determine the available
funding, time constraint, staffing,
customer relations, project size and / or complexity, overall
structure and organizational
resistance. Risk analysis is broadly defined to include risk
assessment, risk characterization, risk
communication, risk management, and policy relating to risk.
Risk analysis is a technique used
to identify and assess factors that may jeopardize the success
of a project or achieving a goal.
This technique also helps to define preventive measures to
reduce the probability of these factors
from occurring and identify counter measures to successfully
deal with these constraints when
they develop to avert possible negative effects on the
competitiveness of the company. One of
the more popular methods to perform a risk analysis in the
computer field is called facilitated
risk analysis process (FRAP). FRAP analyzes one system,
application or segment of business
processes at time. FRAP assumes that additional efforts to
develop precisely quantified risks are
not cost effective because; such estimates are time consuming,
risk documentation becomes too
voluminous for practical use, specific loss estimates are
generally not needed to determine if
controls are needed and without assumptions there is little risk
analysis. After identifying and
categorizing risks, a team identifies the controls that could
mitigate the risk. The decision for
what controls are needed lies with the business manager. The
team's conclusion as to what risks
exists and what controls needed are documented along with a
related action plan for control
implementation.
The Risk Impact / Probability Chart are based on the principle
that a risk has two primary
dimensions; Probability A risk is an event that "may" occur. The
probability of it occurring can
range anywhere from just above 0% to just below 100%. *Note: It
can't be exactly 100%,
because at that juncture it would be a certainty, not a risk.
And it can't be exactly 0%, or it would
not be a risk. Impact A risk, by its very nature, always has a
negative impact. However, the size
of the impact varies in terms of cost and impact on health,
human life, or some other critical
factor. The chart allows you to rate potential risks on these
two dimensions. The probability that
a risk will occur is represented on one axis of the chart and
the impact of the risk, if it occurs,
-
IPE MBA Project Management Assignment Page 14 of 17
on the other. It is advisable to use these two measures to plot
the risk on the chart. This gives a
very quick and a clearer view of the priority that needed to be
given to each. You can then decide
what resources needed to be allocated to managing that
particular risk.
I believe there is a drooping in the risk management of the KLIA
2 project. Based on the
report by The Edge, the Senior General Manager of Malaysia
Airports Holdings Berhad
(MAHB) Datuk Azmi Murad stated that the reason for the delay is
the contractor could not
deliver maybe due to under estimation of the difficulties. MAHB
has issued 212 non -
compliances report progressively to UEM Bina Puri JV since it
started construction in the main
building. UEM Bina Puri JV, the main contractor of KLIA 2, is
appealing against the
liquidated and ascertained damages (LAD) fine slapped on it by
Malaysia Airports Holdings
Berhad (MAHB). Bina Puri Construction Sdn. Bhd. Director Henry
Tee Hock Hin said the joint
venture (JV) would appeal based on the terms and conditions of
the contract that stated that the
contractor could appeal for an extension of time (EOT) to finish
up the work, as there had been
many last minute requests and additional changes made by
stakeholders. These were the
extensions of time (EOT) granted by Malaysia Airports Holdings
Berhad (MAHB) to the
contractor as reported by The Edge April 2012 ; Contractor was
given EOT by MAHB,
October / November 2012 ; Contractors commit to opening of the
airport on May 2013, January
2013 ; Contractor asks for 6 more weeks and commits to airport
opening on June 28, May 7 ;
MAHB makes announcement to Bursa Malaysia that the contractor
may have difficulty in
meeting the project deadline, May 16 : The contractor as for an
EOT until Jan 2014 without any
justification, May 29 : Malaysia Airports Holdings Berhad makes
an announcement to the Bursa
-
IPE MBA Project Management Assignment Page 15 of 17
that the contractor has notified that it cannot meet its
contractual obligation to deliver KLIA 2 by
June 28 and on June 18 contractor confirms April 30th
2014 as the new completion date. As per
seen in this case there was a lot of risks in this project.
Malaysia Airports Holdings Berhad and
UEM Bina Puri JV had recently been embroiled in a spat blaming
each other for the works that
could not be completed in time for the opening of KLIA 2. When
all the major stakeholders and
key players start blaming each other it brings upon the risk of
project delivery failure. This is
where the project manager should have used his skills of project
management and risk
management.
2.5) The Common Pitfalls in a Project
There are several pitfalls in a project contributing to its
failure such as unclear objectives,
lack of senior management support and lack of effective project
integration, inadequate funding,
change in business priorities, original assumptions being
invalid, an ineffective team, and lack of
effective communication processes. In order to ensure a project
success there are a few factors to
be kept in mind and put to work such as coordination and
relations, adequacy of structure and
control, the project uniqueness, importance, and public
exposure, success criteria salience and
consensus, a competitive and budgetary pressure, initial over -
optimism, conceptual difficulty
and internal capabilities build up. In KLIA 2 there were a few
changes made after the retail
optimization plan (ROP). Optimization means finding an
alternative with the most cost effective
or highest achievable performance under the given constraints,
by maximizing desired factors
and minimizing undesired ones. But its uncertain the ROP was
coordinated with all the
participating parties, for example the contractor was not
briefed prior hand about the possibilities
of changes in the final design. These have been one the major
factor for the downfall of this
KLIA 2 project. There was absence in effective communication and
privation in co-ordination
and relations.
-
IPE MBA Project Management Assignment Page 16 of 17
Conclusion & Recommendations
We have discussed the various relevant factors which may have
contributed to the failure
of KLIA 2 by Malaysia Airports Holdings Berhad (MAHB). The key
factors being lack of
anticipation to the project plan changes and a poor risk
management.
Thus, I would recommend to the chairperson of MAHB in the future
projects have a
change management team where they help execute and manage change
to ensure, you not only
meet your business objectives but new processes are adopted and
sustained.
Other than that its crucial to follow the four phases of project
management life cycle and
not skipping any of these phases will ensure the success of the
project. It is also important to
create statement of work (SOW) for the business case to identify
the purpose, scope, project
deliverables, goals and objectives and cost and schedule
estimates. These ensure we do not run
out of the planning we initially made thus preventing mishaps
such as cost overrun or delays.
Adding to that the risk management team should calculate the
possible risks with the help
of risk impact / probability chart. This gives a quick and clear
view of the priority we need to
give each, and help us to decide what resource to allocate in
managing the particular risk.
Therefore as conclusion project management skills should be
incorporated with the
theories and models I have presented in my study above should be
followed to attain project
success, as these are the models proven by researches and
trials. I hope these recommendations
will help to elevate the project success in future business
cases.
-
IPE MBA Project Management Assignment Page 17 of 17
References
1. Company's Background. 2013, KLIA 2, viewed 16 May 2014
2. KLIA 2 Proposal. 2013, Proposal, viewed 16 May 2014
3. Info KLIA 2. 2014, Comparison between klia2,klia and lcct,
viewed 18 May 2014
4. Project Management. 2012, Accountability in Project
Management, viewed 20 May 2014
5. The Edge Malaysia. 2014, highlight: klia2 delay, MAHB reveals
all, viewed 19 May
2014
6. Project Management. 2012, project management life cycle,
viewed 2 May 2014
7. Russell D. Archibald,Project Life Cycle Model .2013, The
Six-Phase Comprehensive
Project Life Cycle Model Including the Project
Incubation/Feasibility Phase and the
PostProject Evaluation Phase, viewed 18 May 2014
8. Change Management. 2014, the change management process ,
viewed 19 May 2014
9. PMMP. 2011, The project management life cycle, viewed 19 May
2014
10. PM HUT. 2012, an introduction to project management life
cycle, viewed 20 May 2014
11. SRA. 2014, risk analysis, viewed 21 May 2014
12. Project Smarts. 2013, risk analysis matrix, viewed 21 May
2014