Top Banner
PROJECT FINANCE
27

PROJECT FINANCE

Feb 16, 2016

Download

Documents

bobby

PROJECT FINANCE. Presented by…. It’s All About Risk!. The key to project financing is the reallocation of any risk away from the lenders to the project. WHAT IS PROJECT FINANCE ?. - PowerPoint PPT Presentation
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: PROJECT FINANCE

PROJECT FINANCE

Page 2: PROJECT FINANCE

M-4105APEKSH

A

M-4131JUHI

M-4123SONALI

M-4135PALVI

Presented by…

Page 3: PROJECT FINANCE

THE KEY TO PROJECT FINANCING IS THE REALLOCATION OF ANY RISK AWAY FROM THE LENDERS TO THE PROJECT.

It’s All About Risk!

Page 4: PROJECT FINANCE

WHAT IS PROJECT FINANCE ?

Page 5: PROJECT FINANCE

Project Finance involves a corporate sponsor investing in and owning a single purpose, industrial asset through a legally independent entity financed with non-recourse debt.

Page 6: PROJECT FINANCE

The financing of long-term infrastructure, industrial projects and public services.

project financing is a loan structure.

attractive to the private sector.

Page 7: PROJECT FINANCE

WHY PROJECT FINANCE?

Page 8: PROJECT FINANCE

Size and cost of projects

Risk minimization

May be only way that enough funds can be raised

Page 9: PROJECT FINANCE

FEATURE

Page 10: PROJECT FINANCE

It is provided for a “ring-fenced” projectThere is a high ratio of debt to equityThere are no guaranteesLenders rely on the future cash flow The main security for lenders

Page 11: PROJECT FINANCE

ADVANTAGES

Page 12: PROJECT FINANCE

Project financing is usually chosen by project developers in order to inter alia: Eliminate or reduce the lender’s recourse to the sponsorsPermit an off-balance sheet treatment of the debt financingMaximize the leverage of a projectReduce political risks affecting a project

Page 13: PROJECT FINANCE

Circumvent any restrictions or covenants binding the sponsors under their respective financial obligationsAvoid any negative impact of a project on the credit standing of the sponsorsObtain better financial conditions when the credit risk of the project is better than the credit standing of the sponsors

Page 14: PROJECT FINANCE

DISADVANTAGES

Page 15: PROJECT FINANCE

Often takes longer to structure than equivalent size corporate finance.Higher transaction costs due to creation of an independent entity can be up to 60bpProject debt is substantially more expensive (50-400 basis points) due to its non-recourse nature.Extensive contracting restricts managerial decision making.Project finance requires greater disclosure of proprietary information and strategic deals.

Page 16: PROJECT FINANCE

TYPES

Page 17: PROJECT FINANCE

PUBLIC FINANCE

CORPORATE FINANCE

LIMITED-RESOURCES

Page 18: PROJECT FINANCE

PARTICIPANTS

Page 19: PROJECT FINANCE

Government Equity FundersNonrecourse Debt FundersOperatorConstruction/Engineering ConsultantsAffected Communities

Page 20: PROJECT FINANCE

Developmental projects

Page 21: PROJECT FINANCE

1)ROAD: L&T Transportation

Infrastructure Limited(L&T-TIL) construction of a 28km bypass roadBypass commenced in Dec.1998 and Jan.2000 respectively

Page 22: PROJECT FINANCE

2)AIRPORT: Bangalore International Airport

Limited (BIAL)project covers construction of a 4000m runwayexpected traffic demand of 4.1 million passengers per yearinvestment will be US$240 million (Rs.1240 crores).

Page 23: PROJECT FINANCE

3)BRIDGE : Narmada Infrastructure

Construction Enterprise Limited (NICE)The construction of a 1.4km-long bridge adjacent to the first bridge & 4.6km of approach roadsService began in nov. 2000

Page 24: PROJECT FINANCE

4) TRADE & EXHIBITION CENTRE: Hyderabad International Trade

Expositions Limited (HITEX)developed on a 100-acre ploteight air cooled halls of 3500 Sqm each of indooran open exhibition space (32,825 Sqm) conference rooms of a total area of 4553 Sqm

Page 25: PROJECT FINANCE

5) WATER SUPPLY PROJECTS Vizag Industrial Water Supply

Company Limited (VIWSCO)Pipeline works from Rajahmundry to YLBC 56 kmConcession period for the project is 32 years

Page 26: PROJECT FINANCE
Page 27: PROJECT FINANCE