Top Banner
SARDA ENERGY AND MINERALS LIMITED. PROJECT FEASIBILITY REPORT 350 MW POWER PROJECT PROJECT FEASIBILITY REPORT FOR PROPOSED 350MW (2x150 + 1x50 MW) THERMAL POWER PLANT AT Village : Kolam, Tehsil : Tamnar Distt : Raigarh (C.G.) FOR SARDA ENERGY & MINERALS LIMITED (Formerly known as Raipur Alloys & Steel Limited) Corporate Office PHASE – 1, INDUSTRIAL GROWTH CENTRE, SILTARA, RAIPUR (C.G.) 493 111 Ph: 07721- 403926
60

PROJECT FEASIBILITY REPORT FOR PROPOSED 350MW … energy/New PF... · PROJECT FEASIBILITY REPORT FOR PROPOSED 350MW ... Exit Volume of Flue Gas shall be reduced by about 22127 ...

Mar 08, 2018

Download

Documents

doxuyen
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: PROJECT FEASIBILITY REPORT FOR PROPOSED 350MW … energy/New PF... · PROJECT FEASIBILITY REPORT FOR PROPOSED 350MW ... Exit Volume of Flue Gas shall be reduced by about 22127 ...

SARDA ENERGY AND MINERALS LIMITED. PROJECT FEASIBILITY REPORT

350 MW POWER PROJECT

PROJECT FEASIBILITY REPORT

FOR PROPOSED 350MW

(2x150 + 1x50 MW)

THERMAL POWER PLANT

AT

Village : Kolam,

Tehsil : Tamnar

Distt : Raigarh (C.G.)

FOR

SARDA ENERGY & MINERALS LIMITED

(Formerly known as Raipur Alloys & Steel Limited)

Corporate Office

PHASE – 1, INDUSTRIAL GROWTH CENTRE,

SILTARA, RAIPUR (C.G.) 493 111

Ph: 07721- 403926

Page 2: PROJECT FEASIBILITY REPORT FOR PROPOSED 350MW … energy/New PF... · PROJECT FEASIBILITY REPORT FOR PROPOSED 350MW ... Exit Volume of Flue Gas shall be reduced by about 22127 ...

SARDA ENERGY AND MINERALS LIMITED. PROJECT FEASIBILITY REPORT

350 MW POWER PROJECT

2

TABLE OF CONTENTS

CHAPTER-I 6

Executive Summary 6

1.1 Executive Summary 6

1.2 Project at a Glance 7

CHAPTER-II 10

Introduction of the project / Background information 10

2.1 Company Background 10

2.2 Management 10

2.3 Present Proposal 11

2.4 Cost of Project 12

2.5 Employment Generation (Direct and Indirect) due to Project 15

CHAPTER-III 16

Project Description 16

3.1 Type of project including interlinked and interdependent projects 16

3.2 Location (map showing general location, specific location, and project boundary and project site layout) with coordinates

16

3.3 Details of alternate sites considered and the basis of selecting the proposed site, particularly the environmental considerations gone into should be highlighted

20

3.4 Size or magnitude of operation 22

3.5 Project description with process details (a schematic diagram/flow chart showing the project layout, components of the project etc. should be given)

22

3.6 Raw material required along with estimated quantity, likely source, marketing area of final product/s, Mode of transport of raw material and Finished product.)

36

3.7 Resources optimization/recycling and reuse envisaged in the project, If any, should be briefly outlined.

37

3.8 Availability of water its source, Energy/Power requirement and source should be given

37

3.9 Quantity of wastes to be generated (liquid and solid) and scheme for their Management/disposal

40

3.10 Schematic representations of the feasibility drawing which give information of EIA purpose

43

Page 3: PROJECT FEASIBILITY REPORT FOR PROPOSED 350MW … energy/New PF... · PROJECT FEASIBILITY REPORT FOR PROPOSED 350MW ... Exit Volume of Flue Gas shall be reduced by about 22127 ...

SARDA ENERGY AND MINERALS LIMITED. PROJECT FEASIBILITY REPORT

350 MW POWER PROJECT

3

CHAPTER-IV 44

Site Analysis 44

4.1 Connectivity 44

4.2 Land Form, Land use and Land ownership 44

4.3 Topography (along with map) 44

4.4 Existing land use pattern (agriculture, non-agriculture, forest, water

bodies (agriculture, non-agriculture, forest, water bodies (including area

under CRZ)), shortest distances from the periphery of the project to

periphery of the forests, national park, wild life sanctuary, eco sensitive

areas, water bodies (distance from the HFL of the river), CRZ.

46

4.5 Existing Infrastructure 46

4.6 Soil classification 46

4.7 Climatic data from secondary sources 47

4.8 Social Infrastructure available 48

CHAPTER-V 49

Planning Brief 49

5.1 Planning concept 49

5.2 Population Projection 49

5.3 Land use planning (breakup along with green belt etc.) 49

5.4 Assessment of Infrastructure Demand (physical & social). 50

5.5 Amenities/Facilities 50

Page 4: PROJECT FEASIBILITY REPORT FOR PROPOSED 350MW … energy/New PF... · PROJECT FEASIBILITY REPORT FOR PROPOSED 350MW ... Exit Volume of Flue Gas shall be reduced by about 22127 ...

SARDA ENERGY AND MINERALS LIMITED. PROJECT FEASIBILITY REPORT

350 MW POWER PROJECT

4

CHAPTER-VI 51

Proposed Infrastructure 51

6.1 Industrial Area (Processing Area) 51

6.2 Residential Area (Non Processing Area) 51

6.3 Green Belt 51

6.4 Sewerage system 51

6.5 Industrial Waste Management 52

6.6 Solid Waste Management 52

6.7 Power Requirement & Supply/source 52

CHAPTER-VII 53

Rehabilitation and Resettlement (R & R) Plan 53

CHAPTER-VIII 54

Project Schedule and Cost Estimates 54

8.1 Likely date of start of construction and likely date of completion 54

8.2 Estimated project cost along with analysis in terms of economic viability of the project

58

Page 5: PROJECT FEASIBILITY REPORT FOR PROPOSED 350MW … energy/New PF... · PROJECT FEASIBILITY REPORT FOR PROPOSED 350MW ... Exit Volume of Flue Gas shall be reduced by about 22127 ...

SARDA ENERGY AND MINERALS LIMITED. PROJECT FEASIBILITY REPORT

350 MW POWER PROJECT

5

CHAPTER-IX 59

Analysis of proposal (Final Recommendations) 59

9.1 Financial and social benefits with special emphasis on the benefits to the local people including tribal population, if any, in the area

59

CHAPTER-I

Page 6: PROJECT FEASIBILITY REPORT FOR PROPOSED 350MW … energy/New PF... · PROJECT FEASIBILITY REPORT FOR PROPOSED 350MW ... Exit Volume of Flue Gas shall be reduced by about 22127 ...

SARDA ENERGY AND MINERALS LIMITED. PROJECT FEASIBILITY REPORT

350 MW POWER PROJECT

6

Executive Summary

1.1 Executive Summary

The basis of selection of major equipment including a review of technologies

and their evaluation is indicated in the report. The chapter in the report also

deals with the annual requirement of raw material.

The project report also covers the plant facilities and plant description for the

Power Plant.

The detailed process description of all the system has been covered in the

project report.

The chapter in the project report deals with the facilities provided for the plant

water system and other utilities such as fuel, compressed air, steam etc. The

pollution control measures proposed to be adopted in the Power Plant are also

described in the Chapter.

The chapter of the report also includes the organization and estimated

manpower for the proposed 350 MW Power Plant.

The estimates of capital cost, annual manufacturing expenses and the

financial analysis of the project are presented in the report.

Page 7: PROJECT FEASIBILITY REPORT FOR PROPOSED 350MW … energy/New PF... · PROJECT FEASIBILITY REPORT FOR PROPOSED 350MW ... Exit Volume of Flue Gas shall be reduced by about 22127 ...

SARDA ENERGY AND MINERALS LIMITED. PROJECT FEASIBILITY REPORT

350 MW POWER PROJECT

7

1.2 Comparison of benefits of (2x150 MW) units over (2x135 MW + 1x30 MW)

units.

It is proposed to install (2x150 MW +50 MW) units in place of earlier proposed

(2x135 MW +30MW +50 MW) units.

Reasons for installing the presently proposed (2x150 MW) units instead of

(2x135 MW +30MW) units are:

1. The inefficient, non re-heat type 30 MW unit has very High Turbine Heat Rate, Low Boiler Efficiency and hence Very High Specific Coal Consumption. Hence we have discarded the 30 MW Unit.

2. The proposed 150 MW units have lower Turbine Heat Rate, higher Boiler Efficiency and hence Lower Specific Coal Consumption in comparison to 135 MW units.

Thus the configuration with (2x150 MW +50 MW) units have following

advantages over the configuration with (2x135 MW +30MW +50 MW) units.

� Coal Consumption shall be reduced by about 1.87Lac MT/Year (7.42% ). � Total Ash produced shall be reduced by about 0.70 lac MT/Year (6.30% ).

� Exit Volume of Flue Gas shall be reduced by about 22127 NM3/hr. � Gross Pollution Load (Air) shall be reduced by about 8.76Tonnes/ year.

� Water consumption shall be reduced by about 0.51 MCM/Year (6%).

� Chimney Height for (2x150 MW) units shall be 220 Meters for better dispersion of emission.[ Chimney Height for (2x135 MW +30MW) units was kept at 180 Meters.]

(An approximate comparison of these factors is enclosed in the report).

Page 8: PROJECT FEASIBILITY REPORT FOR PROPOSED 350MW … energy/New PF... · PROJECT FEASIBILITY REPORT FOR PROPOSED 350MW ... Exit Volume of Flue Gas shall be reduced by about 22127 ...

SARDA ENERGY AND MINERALS LIMITED. PROJECT FEASIBILITY REPORT

350 MW POWER PROJECT

COMPARISION OF PROJECT CONFIGURATIONS ( 2X135 MW + 1X30 MW+ 1X50 MW) Vs ( 2X150 MW + 1X50 MW)

DESCRIPTION Original Proposal Present Proposal PLANT CAPACITY 350 MW 350 MW

UNIT CONFIGURATION 1 X 30 MW

1 x 50 MW

2 X 135 MW

2 X 150 MW

1 x 50 MW

TURBINE HEAT RATE Kcal / Kwh 2600 2460 2390 2230 2460 BOILER EFFICIENCY % age 0.82 0.84 0.85 0.86 0.84 PLANT HEAT RATE 3095 2929 2812 2593 2929

Reduction

COAL CONSUMPTION ( 90% PLF) % age

Lac

MT

Specific Coal Consumption Kg/Kwh 0.9905 0.9371 0.8998 0.8298 0.9371 Unit wise Consumption Million MT / Year 0.2343 0.3694 1.92 1.9626 0.3694 TOTAL Million MT / Year 2.52 2.33 7.42% 1.87

Ash Produced

Fly Ash Million MT/ Year 0.90

0.84

6.30%

0.60

Bottom Ash Million MT/ Year 0.22 0.21 0.10

TOTAL Million MT/ Year 1.1 1.05 0.70

Water Consumption

Condenser Cooling Water Make up M3/Hr 130 187 755 820 187 Condenser Cooling Water Make up MCM/Year 1.02 1.47 5.95 6.46 1.47 TOTAL ( MCM / Year) 8.45 7.94

6.06% 0.51 MCM

Note :

1. Average Coal (Middling + Coal ) CV 3125 Kcal/kg

2. Average Ash Content in Coal 45%

Page 9: PROJECT FEASIBILITY REPORT FOR PROPOSED 350MW … energy/New PF... · PROJECT FEASIBILITY REPORT FOR PROPOSED 350MW ... Exit Volume of Flue Gas shall be reduced by about 22127 ...

SARDA ENERGY AND MINERALS LIMITED. PROJECT FEASIBILITY REPORT

350 MW POWER PROJECT

9

3. Fly Ash to Bottom Ash Ratio 80:20

4.Make water requirement considered only for condenser make up , Balance requirement shall remain almost same.

Approximate Comparison of Gross Pollution Load (Air)

300 MW 300 MW

2 x 135

MW

1 x 30

MW

2 x 150

MW Diff.

A B C (A+B)-C

Flue Gas Exit Volume NM3/hr 1684800 209327 1872000 22127

Gross Pollution Load Air Kg/hr 84.24 10.47 93.60 1.11

Tonne/year 667.18 82.89 741.31 8.76

(Emission Level 50 mg/NM3)

Page 10: PROJECT FEASIBILITY REPORT FOR PROPOSED 350MW … energy/New PF... · PROJECT FEASIBILITY REPORT FOR PROPOSED 350MW ... Exit Volume of Flue Gas shall be reduced by about 22127 ...

SARDA ENERGY AND MINERALS LIMITED. PROJECT FEASIBILITY REPORT

350 MW POWER PROJECT

CHAPTER-II

Introduction of the project / Background information

2.1 Identification of Project and Project Proponent

Sarda Energy & Minerals Ltd. (Formerly Chhattisgarh Electricity Company Ltd.),

Incorporated on 23rd January 1998, is a Public Limited Company. Power has been

the prime mover of growth in the Company. The Company had installed 20 MW coal

based thermal power plant, which commenced operations in the year 2001, gradually

the capacity of power plant has been increased to 81.5 MW. The Company also

installed five 9 MVA Submerged Arc Ferro alloys furnaces in phases to use captive

power from power Plant and to have maximum realization for the power generated

presently total capacity of plant is 45 MVA, which makes company the second largest

producer of manganese based Ferro Alloys in the country. The facilities are installed

at Industrial Growth Centre, Siltara, Raipur over an area of about 70 acres.

Chhattisgarh Electricity Company Ltd. has got merged with Raipur Alloys & Steel

Limited as per the orders of Hon’ble High Court of Chhattisgarh, Bilaspur dated 11th

May, 2007 & the name of Raipur Alloys & Steel Limited has also been Changed to

“Sarda Energy & Minerals Limited”(SEML) as per Fresh Certification of Incorporation

dated 2nd August 2007. Liberalization of economy by the Government, throwing open

for manufacturing of Iron and Steel including mining of iron ore, coal and other

related minerals to private entrepreneurs, provided an avenue for further growth in

this segment to SEML. Company is a industrial house to set up a modern integrated

steel plant at Siltara Industrial Estate, Raipur. The steel plant uses non-coking coal

for sponge iron production of 79,200 TPA, further it has expanded to 4,60,000 TPA

sponge iron production. Initially for meeting its requirement for 79,200 TPA sponge

iron, SEML obtained a mining lease for iron ore situated at Dongarbor in the

Rajnandgaon District, to produce 2.0 lakhs TPA. After expansion of sponge iron plant

to meet its requirement of iron ore, the company has increased production capacity

of Dongarbor Iron Ore Mine from 2.0 lakhs TPA to 15.0 lakhs TPA for extraction of

iron ore in the year 2007. Company has been allotted a captive coal block at Karwahi

near Tamnar, District- Raigarh, Chhattisgarh State to produce 1.2 Million TPA coal.

Company is proposed for installation of 1.1 Million TPA Integrated Steel Plant and 60

MW WHRB Power Plant at Siltara Industrial Growth Centre, Mandhar, Raipur.

2.2 Brief Description of nature of Project

Company proposes to install 350 MW power plant with a configuration of 2 x

150 MW + 1 x 50 MW. Coal for the proposed power project will made available

through company's own captive coal mines and middling generated from coal

Washery. The entire coal shall be transported through closed conveyor and

road from Mines / Washery to Plant site which is about 4.5 KM. Necessary

water required for power plant operation shall be taken from nearby Kelo

Page 11: PROJECT FEASIBILITY REPORT FOR PROPOSED 350MW … energy/New PF... · PROJECT FEASIBILITY REPORT FOR PROPOSED 350MW ... Exit Volume of Flue Gas shall be reduced by about 22127 ...

SARDA ENERGY AND MINERALS LIMITED. PROJECT FEASIBILITY REPORT

350 MW POWER PROJECT

11

River. Power Generated shall be evacuated at 400 KV level by installing

dedicated power evacuation lines from plant to Tamnar Sub Station.

2.3 Need for the project and its importance to the country and or region

The Government of India’s 5th National Power Plan has envisaged a total installed

capacity of 2,12,000 MW as per the 16th Electric Power Survey. This capacity is to be

achieved by end of the 11th Plan, March 2012. The Government of India has

projected a GDP growth rate of about 7.4% based on power capacity to be achieved in

the 11th plan. To achieve a target of higher than 10,000 MW per annum, huge

investment in power sector is required and also the manufactures, contractors,

vendors and supporting will need to increase their capacities to meet this target of

power sector.

Presently state generating capacity in thermal and hydro power is about 1800 MW &

143 MW respectively. No. of villages are still to be electrified and presently there is a

power crises in the state which is affecting industrial production. In order to have a

10% GDP in the state the generating capacity of power has to be enhanced

Considerably.

In the 11th plan period in the state of Chhattisgarh the following departments are

planned to be enhanced the power generation.

1. Central sector – 4480 MW

2. State Sector - 3250 MW

3. Private Sector – 2950 MW

MOUs signed by various organizations for 42000 MW.

In order to complete the expansion plans in the area of steel and alloys it is essential

for the company to install captive power plants so that the cost of production shall be

competitive on Global basis.

State grid company desires companies to install their own power plant to meet

requirement and balance power can be for export. Company is presently having

generation capacity of 81.5 MW and they are also exporting upto 10 Mwh..

In view of the above M/s Sarda Energy & Minerals Ltd. (SEML) has decided to setup

a coal & middling based Thermal Power Plant with a total capacity of 350 (2x150 +

1x50) MW in District Raigarh, Chhattisgarh. SEML has retained Anacon Laboratories

Nagpur to undertake on Environmental Impact Assessment study and preparation of

Environment Management Plan for the proposed 350 MW Thermal Power Plant for

Environment Clearance from State Level Environment Impact Assessment Authority.

Page 12: PROJECT FEASIBILITY REPORT FOR PROPOSED 350MW … energy/New PF... · PROJECT FEASIBILITY REPORT FOR PROPOSED 350MW ... Exit Volume of Flue Gas shall be reduced by about 22127 ...

SARDA ENERGY AND MINERALS LIMITED. PROJECT FEASIBILITY REPORT

350 MW POWER PROJECT

12

2.4 Demand -Supply Gap

PRESENT INSTALLED GENERATION CAPACITY

At the end of 1st quarter for the year 2010 the installed generation capacity in the

country are 159398.49 MW. Owing to the rapid industrialization all over the country

and in particular in eastern India which so far was neglected, is witnessing massive

investment both from foreign companies in form of FDI as well as from domestic

players in the field of iron & steel, Aluminium, chemical, mines, infrastructure & etc.

and for all these, power remains the most important driving force, but in the recent

past it has been observed that power generation is not keeping pace with rapid

industrialization, which in turn is increasing demand for power, that too quality

power, because the modern machineries which are being used nowadays are

sensitive & costlier, for smooth & continuous operation, these machineries require

quality power. Keeping these entire things in mind, India must change its present

status from being a power deficit country to a power surplus country to maintain a

steady GDP growth. The state of Chhattisgarh like many other eastern India states is

also witnessing huge investment in Iron & steel and aluminium sectors. As a result

power demand is increasing day by day. Therefore, to meet the huge demand of

power in Chhattisgarh as well as many adjoining states like Orissa, Jharkhand,

Madhya Pradesh, Uttar Pradesh & Maharashtra, the demand for power in these

states has witnessed a huge surge in the last five years due to rapid industrialization.

As the state of Chhattisgarh is strategically centrally located to these adjoining

states, it has got ready market for utilization of power generated in Chhattisgarh in

these areas, where the demand for power is huge. Moreover Chhattisgarh, especially

districts like Korba, Janjgir and Raigarh have got huge reserves of untapped

hydrocarbon fuels i.e coal, being so close to the primary fuel for a thermal power

station, the transportation cost of fuel to the envisaged site shall be minimal, as a

result the cost of power generation shall be drastically reduced.

MINISTRY OF POWER’S BLUEPRINT FOR POWER DEVELOPMENT

The energy shortage in the country during first quarter of 2010 was 8980 million

units amounting to 11.7 per cent shortage and the peak power shortage was 15748

MW translating to 13.3 per cent. The Ministry of Power has developed appropriate

strategies and a blueprint to address the power situation in the country in a time

bound manner. Based on the demand projections made over 100,000 MW of

additional generation capacity needs to be added by the year 2012 to bridge the gap

between demand and supply of power.

Page 13: PROJECT FEASIBILITY REPORT FOR PROPOSED 350MW … energy/New PF... · PROJECT FEASIBILITY REPORT FOR PROPOSED 350MW ... Exit Volume of Flue Gas shall be reduced by about 22127 ...

SARDA ENERGY AND MINERALS LIMITED. PROJECT FEASIBILITY REPORT

350 MW POWER PROJECT

13

POWER SCENARIO IN INDIA

The projected peak power demand and energy requirement during the years 2007-12

as indicated in 17th Electric Power Survey of India is listed in the table below.

Table: - Peak Power Demand and Energy requirement

Year Peak Power Demand in MW Energy requirement in Million

kWHr

2007-08 113059 744515

2008-09 121891 794561

2009-10 131413 848390

2010-11 141678 906316

2011-12 152746 968659

Upto march,2010 the installed generation capacity of the country was 159398.49

MW, peak availability was 102725 MW and the energy generated was 67513 Million

kWHr. The energy shortage in the country during first quarter of march, 2010 was

8980 million units amounting to 11.7 per cent shortage and the peak power shortage

was 15748 MW translating to 13.3 per cent as per CEA website in the chapter “Power

Scenario at a Glance”. To meet the shortfall as well as the future demand, several

new projects are proposed.

Capacity augmentations due to the projects which are under construction or

proposed and expected to be commissioned during XI plan (2007-2012) are in Table

below.

Table: -Projected peak power & energy demand along with the deficit

Details year

2007-08 2008-09 2009-10 2010-11 2011-12

Projects Under Construction

Thermal

(MW)

6620 2485 9106 18755 13791

Hydel (MW) 2423 969 39 1436 3370

Page 14: PROJECT FEASIBILITY REPORT FOR PROPOSED 350MW … energy/New PF... · PROJECT FEASIBILITY REPORT FOR PROPOSED 350MW ... Exit Volume of Flue Gas shall be reduced by about 22127 ...

SARDA ENERGY AND MINERALS LIMITED. PROJECT FEASIBILITY REPORT

350 MW POWER PROJECT

14

Nuclear

(MW)

220 0 440 1220 1500

Total (MW) 9263 3454 9585 21411 18661

Source: CEA website “White Paper on Strategy for 11th Plan”.

AVAILABILITY OF POWER

The power availability of the system is dependent on the following factors:

a) Planned outages due to maintenance, forced outages, etc.

b) Spinning reserve

c) Auxiliary power consumption

d) Stabilization period in case of newly commissioned units

e) Partial non-availability due to poor quality of indigenous coal, non availability of

gas, uncertain irrigation releases resulting in uncertainty of hydro generation at peak

hours, loss of active power due to high reactive demand of units.

Considering the peak power and energy availability from the existing plants, peak

power and energy availability of future plants based on the mix in development of

hydro, thermal and nuclear power plants projections are made for the region. The

projected peak power demand, power requirement, energy availability and energy

requirement along with the deficit or surplus are shown in table below.

Table: - Projected peak power & Energy demand along with the deficit.

S.No. Details Year

2007-08 2008-09 2009-10 2011-12

1 Peak Power

Availability

(MW)

90793 96685 102725 142765

2 Peak Power

Demand (MW)

108866 109809 118472 152746

3 Peak power

Deficit (MW) (+

for surplus, -

for

deficit)

-18073 -13124 -15748 -9981

Page 15: PROJECT FEASIBILITY REPORT FOR PROPOSED 350MW … energy/New PF... · PROJECT FEASIBILITY REPORT FOR PROPOSED 350MW ... Exit Volume of Flue Gas shall be reduced by about 22127 ...

SARDA ENERGY AND MINERALS LIMITED. PROJECT FEASIBILITY REPORT

350 MW POWER PROJECT

15

4 Peak power

deficit (%)

-16.6% -12% -13.3% -6.5%

5 Energy

requirement

(MU)

739345 774324 830300 968659

6 Energy

Availability

(MU)

666007 689021 746493 948836

7 Energy Deficit

(MU)

-73338 -85303 -83807 -19823

8 Energy Deficit

(%)

-9.9 -11 -10.1 -2

From the above table, it is obvious that there is a deficit in the power availability and

energy availability in India. By the year 2012, Government of India has decided to

increase the power generation by 100000 MW. Coal is identified as the main fuel for

thermal power. The plants located in pit heads would have a greater economic and

logistical advantage in terms of cost of energy.

2.5 Employment Generation (Direct and Indirect) due to Project

The major benefit due to the proposed project will be in the sphere of generating

employment for about 700 persons in that area. The proposed project will benefit

local population. The manpower requirements for the operational phase of the Power

Plant will be about 700 people. In addition, there will be an indirect employment for

skilled/ semi skilled people during project life. All attempts will be made to employ

suitable, locally available, skilled personnel from the study area. In case of non-

availability of skilled persons, people will be employed from outside the study area.

Page 16: PROJECT FEASIBILITY REPORT FOR PROPOSED 350MW … energy/New PF... · PROJECT FEASIBILITY REPORT FOR PROPOSED 350MW ... Exit Volume of Flue Gas shall be reduced by about 22127 ...

SARDA ENERGY AND MINERALS LIMITED. PROJECT FEASIBILITY REPORT

350 MW POWER PROJECT

16

CHAPTER-III

Project Description

3.1 Type of project including interlinked and interdependent projects

POWER PLANT

It is proposed to install 350 MW (2x150 + 1x50 MW) a Thermal Power Plant for

generation of electric power, also utilizing the washery middling of our Captive

Mines allotted by the Government.

Electricity Generated shall be used in company's own Steel and Alloys

Manufacturing projects as well as excess Electricity shall be made available to

National and State grid.

3.2 Location (map showing general location, specific location, and project

boundary and project site layout) with coordinates

The site, admeasuring 127.0 ha of land for the proposed power plant has been identified at

village Kolam, District Raigarh, Chhattisgarh, which is located within 22o 10’ N latitude & 83o

25’ 30” E longitude.

Page 17: PROJECT FEASIBILITY REPORT FOR PROPOSED 350MW … energy/New PF... · PROJECT FEASIBILITY REPORT FOR PROPOSED 350MW ... Exit Volume of Flue Gas shall be reduced by about 22127 ...

SARDA ENERGY AND MINERALS LIMITED. PROJECT FEASIBILITY REPORT

17

Fig.- Map Showing General Location

Project Site

Location

Page 18: PROJECT FEASIBILITY REPORT FOR PROPOSED 350MW … energy/New PF... · PROJECT FEASIBILITY REPORT FOR PROPOSED 350MW ... Exit Volume of Flue Gas shall be reduced by about 22127 ...

SARDA ENERGY AND MINERALS LIMITED. PROJECT FEASIBILITY REPORT

18

Fig.-Project Layout Plan

Page 19: PROJECT FEASIBILITY REPORT FOR PROPOSED 350MW … energy/New PF... · PROJECT FEASIBILITY REPORT FOR PROPOSED 350MW ... Exit Volume of Flue Gas shall be reduced by about 22127 ...

SARDA ENERGY AND MINERALS LIMITED. PROJECT FEASIBILITY REPORT

19

Fig. - Coordinate Map

Page 20: PROJECT FEASIBILITY REPORT FOR PROPOSED 350MW … energy/New PF... · PROJECT FEASIBILITY REPORT FOR PROPOSED 350MW ... Exit Volume of Flue Gas shall be reduced by about 22127 ...

SARDA ENERGY AND MINERALS LIMITED. PROJECT FEASIBILITY REPORT

350 MW POWER PROJECT

20

3.3 Details of alternate sites considered and the basis of selecting the proposed

site, particularly the environmental considerations gone

The proposed project site is situated at Village: Kolam, Tehsil : Gharghoda (Now

Tamnar), District : Raigarh, Chhattisgarh State, 4.0 km away from SEML Captive

Karwahi Open Cast Coal Mine near Tamnar, Raigarh. No any alternative site is

considered.

The following are the factors in favor of selection of site at village Kolam,

Raigarh.

_ Proximity and availability of raw material

_ Proximity to the power evacuation at 400 KV

_ Proximity to the source of fuel

_ Availability of adequate water

_ Availability of adequate land for locating the plant with approach roads

_ Suitability of land from topography and geological aspects

_ Proximity of National Highways & Transport of heavy equipments

Page 21: PROJECT FEASIBILITY REPORT FOR PROPOSED 350MW … energy/New PF... · PROJECT FEASIBILITY REPORT FOR PROPOSED 350MW ... Exit Volume of Flue Gas shall be reduced by about 22127 ...

SARDA ENERGY AND MINERALS LIMITED. PROJECT FEASIBILITY REPORT

350 MW POWER PROJECT

21

The environmental consideration of the site is tabulated below:

Sr. No. Particulars Details

1. Latitude 22o 10’ N

2. Longitude 83o 25’ 30” E

3. Altitude 300 m above MSL

4. Toposheet 64 N/8,12

5. Seismicity Area falls under least affected earthquakes zone II as per IS 1893 - 2002

6. Present land use Single Crop Agricultural Land and Revenue Forest Land

7. Climatic condition (Annual Average)

Ambient Air temp 7oC to 48oC Avg. annual rainfall 1400 mm (IMD, Raigarh)

8. Nearest village Kolam(0.8 km, East), Chiramura (1.8 km, North)

9. Nearest towns Ghargoda (8 km, West)

10. Nearest railway station Raigarh Raigarh (35 km)

11. Nearest airport Raipur (250 km)

12. Streams / Rivers Kelo River (SE-8.0 km), Pajhar Nala (W-0.6 km ),Tadipara Nala (NNW-6.0 km),Karanera Nala(SE-8.6 km),Kasaia Nala (WNW-8.7 km),ChuiNala (SSW-8.2 km),Gardhakari Nala (SSW-8.8km),Digi Nala (SSW-4.9 km),Ranai Nala (SW-6.6km) ,Bhendra Nala (SW-7.0 km)

13. Sanctuaries /National Parks/ Biospheres, etc.

Nil

14. Topography Gently undulating and sloping toward west

15. Defense Installations Nil

16. Historical Places Nil

17. Reserve Forest/Protected Forest

Silot RF (NE-3.6 km),Rampur PF (NE-7.5 km),Deodongar RF (NE-9.2 km), Gare PF (ESE-6.7km), Samaruma RF (SW-6.6 km),Amaghat PF(SSW-8.4 km) and Revenue Forest (NW side).

Page 22: PROJECT FEASIBILITY REPORT FOR PROPOSED 350MW … energy/New PF... · PROJECT FEASIBILITY REPORT FOR PROPOSED 350MW ... Exit Volume of Flue Gas shall be reduced by about 22127 ...

SARDA ENERGY AND MINERALS LIMITED. PROJECT FEASIBILITY REPORT

350 MW POWER PROJECT

22

3.4 Size or magnitude of operation

The details of proposed power plant are presented in Table below:

Sr. No. Features

1. Capacity 350 (2 x 150 + 1 x 50) MW

2. Type of Boiler CFBC / AFBC / PC

3. Temperature 545 0C

4. Atmospheric Pollution Control

System

Electrostatic Precipitation

5. Fuel Raw coal and Middling

6. Source Coal: Captive Karwahi Coal Mine.

Middling: Captive Coal Washery.

7. Steam Turbine Generator One / Two Cylinder, Axial Flow

3.5 Project description with process details

Plant Site

A total area of around 313 acres is identified for the installation of 350 MW (2 x150 + 1

x 50 MW) Thermal Power Plant in Village: Kolam ( 4.5 KM. away from our Karwahi

open cast coal mine), Tehsil : Tamnar, Dist. Raigarh, (Chhattisgarh) for proposed

plant.

Statement of Area

The facility and the proposed area of the plant are shown in Table given below:

Statement of Area for Proposed Power Plant

S. No. Facility Actual Required Area

(Acre)

1. Main Plant Area 88

2. Coal Handling Area 15

3. Storage of Other Fuel 18

4. Ash Disposal Area 30

5. Ash Brick Plant 27

Page 23: PROJECT FEASIBILITY REPORT FOR PROPOSED 350MW … energy/New PF... · PROJECT FEASIBILITY REPORT FOR PROPOSED 350MW ... Exit Volume of Flue Gas shall be reduced by about 22127 ...

SARDA ENERGY AND MINERALS LIMITED. PROJECT FEASIBILITY REPORT

350 MW POWER PROJECT

23

6. Administration Block 6

7. Roads 26

8. Green Belt 103

TOTAL 313

MECHANICAL EQUIPEMENTS AND SYSTEMS

STEAM TURBINE FOR 2X150MW

TURBINE ALTERNATOR SET Steam Turbine – 2 x 150 MW

Make From Reputed manufacturers like M/s

BHEL / SEIMENS / SKODA / CHINA Etc.

with the following specifications

Type One / Two Cylinder, Axial Flow.

Steam Pressure 133.00 Kg/cm2

Temperature 537oC

Back Pressure -0.91 Kg/cm2

RPM 3000

Alternator 02 Nos.

Type Hydrogen/Water Cooled/ Air Cooled

Rating 3 Phase, 50 Cycles at 0.8 P.F.

Voltage 14.5 + 0.5 K Volts

Speed 3000 RPM

Capacity 300 MW (2 x 150 MW)

Page 24: PROJECT FEASIBILITY REPORT FOR PROPOSED 350MW … energy/New PF... · PROJECT FEASIBILITY REPORT FOR PROPOSED 350MW ... Exit Volume of Flue Gas shall be reduced by about 22127 ...

SARDA ENERGY AND MINERALS LIMITED. PROJECT FEASIBILITY REPORT

350 MW POWER PROJECT

24

TG Set Auxiliaries

Turbine Auxiliaries Like Condenser, Feed

re-generative system, CEPs, AOP, air

ejectors, Feed Pumps, NGT, Oil purifiers,

Oil Coolers and associated piping and

fittings will be procured from reputed

manufacturers.

STEAM TURBINE FOR 1X50MW

TURBINE ALTERNATOR SET Steam Turbine – 1 x 50 MW

Make From Reputed manufacturers like M/s

BHEL / SEIMENS / SKODA / CHINA Etc.

with the following specifications

Type Single Cylinder, Axial Flow.

Steam Pressure 89 Kg/cm2

Temperature 535oC

Back Pressure - 0.90 Kg/cm2

RPM 3000

Alternator 01 Nos.

Type Air Cooled / Water Cooled

Rating 3 Phase, 50 Cycles at 0.8 P.F

Voltage 13.5 + 0.5 KV

Speed 3000 RPM

Capacity 50 MW

Page 25: PROJECT FEASIBILITY REPORT FOR PROPOSED 350MW … energy/New PF... · PROJECT FEASIBILITY REPORT FOR PROPOSED 350MW ... Exit Volume of Flue Gas shall be reduced by about 22127 ...

SARDA ENERGY AND MINERALS LIMITED. PROJECT FEASIBILITY REPORT

350 MW POWER PROJECT

25

TG Set Auxiliaries

Turbine Auxiliaries Like Condenser, Feed

re-generative system , CEPs, AOP, air

ejectors, Feed Pumps, NGT, Oil purifiers,

Oil Coolers and associated piping and

fittings will be procured from reputed

manufacturers.

STEAM GENERATOR FOR 2X150MW

BOILER AFBC/CFBC/PF Boiler

Make Reputed make like CVL/BHEL/Thermax

/China etc.

Capacity (Max) 520 TPH x 2 Nos

Working Pressure (S/H Outlet) 138 Kg/cm2

Temperature 540oC

Type Water Tube, Coal Fired Boiler

Auxiliary associated with Boiler Feed ID Fans, FD Fans, PA Fans, Electrical

Feed Pumps, Air/Flue Gas ducting, Ash

Hoppers, Dense Phase Ash Handling

System & associated piping & ducting.

Page 26: PROJECT FEASIBILITY REPORT FOR PROPOSED 350MW … energy/New PF... · PROJECT FEASIBILITY REPORT FOR PROPOSED 350MW ... Exit Volume of Flue Gas shall be reduced by about 22127 ...

SARDA ENERGY AND MINERALS LIMITED. PROJECT FEASIBILITY REPORT

350 MW POWER PROJECT

26

STEAM GENERATOR FOR 1X50MW

BOILER AFBC/CFBC / PF Boiler

Make Reputed make like CVL /

Thermax / China etc.

Capacity (Max) 110 TPH x 2 Nos.

Working Pressure (S/H Outlet) 92 Kg/cm2

Temperature 530 ± 10oC

Type Water Tube, Coal Fired

Boiler

Auxiliary associated with Boiler Feed ID Fans, FD Fans, PA Fans,

Electrical Feed Pumps,

Air/Flue Gas ducting, Ash

Hoppers, Dense Phase Ash

Handling System &

associated piping & ducting.

The other utilities of plant consist of Coal Handling System, Auxiliary Cooling water

for SG and TG , DM water plant, softener plant, ash-handling system etc. Each boiler

will be connected with an ESP of 99.5% efficiency. The de-dusting system will be

installed at various junction points to control the emission.

Page 27: PROJECT FEASIBILITY REPORT FOR PROPOSED 350MW … energy/New PF... · PROJECT FEASIBILITY REPORT FOR PROPOSED 350MW ... Exit Volume of Flue Gas shall be reduced by about 22127 ...

SARDA ENERGY AND MINERALS LIMITED. PROJECT FEASIBILITY REPORT

350 MW POWER PROJECT

27

ELECTRO STATIC PRECIPITOR

Make Any reputed make like ACC/Thermax /

Ricco etc.

Specification

Gas Temperature (Optg/max.) 140 Deg. C

Gas Pressure (-) 250 ( mm WG) max.

Moisture content 10 % to 12 %

ESP Inlet Dust conc. 60 gm/NM3

ESP Outlet Dust emission < 50 Mg/NM3

Page 28: PROJECT FEASIBILITY REPORT FOR PROPOSED 350MW … energy/New PF... · PROJECT FEASIBILITY REPORT FOR PROPOSED 350MW ... Exit Volume of Flue Gas shall be reduced by about 22127 ...

SARDA ENERGY AND MINERALS LIMITED. PROJECT FEASIBILITY REPORT

350 MW POWER PROJECT

28

COAL HANDLING SYSTEM

The coal required for Power Plant is of size - 30 mm and whereas the coal received

from the mine ( - 300 mm) & middling received from washery is of size < 10 mm .

Thus the coal received is required to be crushed and screened.

The coal received will be feed into ground hopper. This will be crushed and screened

to - 30 mm size. From the screen it will be fed into traveling tripping trolley installed

on the coal bunkers and the oversize coal will be again fed for re-crushing to crusher.

Traveling Tripper trolley installed above the Coal Bunker will facilitate uniform

distribution of the coal into the bunkers. The Coal handling system consists of the

following major equipments:

a] Ground Hopper

b] Impact Crusher

c] Vibrating Screen

d] Conveyor Belt

e] Traveling Tripper Trolley

f] Stacker and Reclaimer

COAL YARD

The coal required for the thermal power plant will be stored in a open yard. Floor of

the yard will be concrete floor and there will be partition walls for proper stacking of

the coal and it is proposed to construct shed for storing the coal for rainy season

requirement.

Page 29: PROJECT FEASIBILITY REPORT FOR PROPOSED 350MW … energy/New PF... · PROJECT FEASIBILITY REPORT FOR PROPOSED 350MW ... Exit Volume of Flue Gas shall be reduced by about 22127 ...

SARDA ENERGY AND MINERALS LIMITED. PROJECT FEASIBILITY REPORT

350 MW POWER PROJECT

29

ASH HANDLING SYSTEM

For handling of fly ash of the steam generator, dense phase, pneumatic conveying

system is provided. The ash collected in the hoppers located in economizer, air pre-

heated sections of SG and ESP hoppers will be pneumatically conveyed and collected

in a silo from where the ash will be disposed off by road trucks for brick

manufacturing and selling to cement plants.

COMPRESSED AIR SYSTEM

The compressed air is required for operation of control valves pneumatic cylinders,

conveying of Ash through ash handling system.

WORKSHOP

A mechanical workshop will be set to meet maintenance services of the plant. Lathe,

Shaping Machine, Vertical Drill, Bending Machine, Punch Press, Shearing Machine,

Welding Transformer/Rectifier, Power Hack-Saw Machine, Hand Grinders etc. are

planned.

LABORATORY

A fully equipped chemical laboratory for the inspection, analysis and quality control

of incoming raw materials and water will be built.

COOLING WATER SYSTEM

The water is the main raw material for generation of power. The water will be used in

Boiler, Auxiliary cooling water (ACW system) for SG, TG and various parts of

Turbine, Compressor cooling etc. The water is also required for drinking and

sanitation purpose, fire fighting for afforestation etc.

The water from the reservoir will be sent to clarifier. For this purpose a pump house

will be constructed adjacent to clarifier unit.

The water required for the Boiler shall be de-mineralized water. Accordingly DM

Water Plant will be installed.

The temperature of Auxiliary cooling water supply to these equipments should be at

33oC max. During circulation there is a temperature rise of water to the tune of 10oC

due to heat transfer. Thus, to achieve inlet water temperature of 33oC a induced

draft cooling tower will be installed for power plant auxiliary cooling.

Page 30: PROJECT FEASIBILITY REPORT FOR PROPOSED 350MW … energy/New PF... · PROJECT FEASIBILITY REPORT FOR PROPOSED 350MW ... Exit Volume of Flue Gas shall be reduced by about 22127 ...

SARDA ENERGY AND MINERALS LIMITED. PROJECT FEASIBILITY REPORT

350 MW POWER PROJECT

30

To maintain the hardness of circulating water the periodical blow down of water from

induced draft cooling tower is done. This water will be used for fire fighting,

sanitation, afforestation purpose etc.

Water Quality Requirement For Boiler

Specific electrical conductivity at 25oC measured after cation exchanger in the H+ form and after Co2 removal

0.5 Qs /cm (max.)

Total Iron 0.01 ppm (max.)

Total copper 0.01 ppm (max)

Total Silica 0.02 ppm (max)

Oxygen 0.007 ppm (max)

Hydrazine residual 0.01 - 0.02 ppm

pH at 25oC (Copper Alloy Pre-boiler

System)

8.8 - 9.2

pH at 25oC (Copper free Pre-boiler

System)

9.0 - 9.4

Permanganate max. ppm - Nil

Hardness ppm - Nil

Total Co2 ppm - Nil

Oil ppm - Not allowed

Boiler Water Total dissolved solids ppm - Not more than 100

Specific electrical conductivity at 25 Deg

CQs/cm

Not more than 200

Phosphate residual ppm - 15 - 25

pH at 25 Deg. C 9.8 - 10.2

Silica max. ppm - 0.02

Page 31: PROJECT FEASIBILITY REPORT FOR PROPOSED 350MW … energy/New PF... · PROJECT FEASIBILITY REPORT FOR PROPOSED 350MW ... Exit Volume of Flue Gas shall be reduced by about 22127 ...

SARDA ENERGY AND MINERALS LIMITED. PROJECT FEASIBILITY REPORT

350 MW POWER PROJECT

31

ELECTRICAL EQUIPMENTS

The Power from Captive Power Plant will fed to our 400 KV substation. CSEB Supply

will be connected to our sub station for Import / Export / start up power. For

auxiliaries 6.6 KV and 415 Volts will be used for which separate power system will be

designed

EMERGENCY DG SET

An emergency diesel engine generator set of suitable rating will be provided to meet

emergency power to loads such as turbine A.C. lube oil pump, UPS and plant

illumination system during failure of AC power within the Power Plant.

LIGHTING

Lighting load will be supplied through lighting transformer of unity ratio installed at

lighting distribution boards. Lighting transformers will feed lighting distribution

board. Lighting panels/receptacle panels for various areas will cater the actual

lighting and power receptacle requirement of the plant.

Page 32: PROJECT FEASIBILITY REPORT FOR PROPOSED 350MW … energy/New PF... · PROJECT FEASIBILITY REPORT FOR PROPOSED 350MW ... Exit Volume of Flue Gas shall be reduced by about 22127 ...

SARDA ENERGY AND MINERALS LIMITED. PROJECT FEASIBILITY REPORT

350 MW POWER PROJECT

32

PLANT INTER COMMUNICATION SYSTEM

The adequate communication system will be provided in the power plant to facilitate

plant operations by establishing quick communication among the operating

personnel at various location of the plant.

CONTROL AND INSTRUMENTATION

The objective of this section is to outline the design philosophy adopted for control

and instrumentation (C&I) systems for thermal power plant. The total plant operation

will be controlled through DCS. However, in case of failure of the DCS, the total

control can be transferred to manual operation and the total plant can be

operated manually from control room only by using closed loop controllers and

A.O.M. switches. Thus the failure of DCS system will not affect the plant operation.

FIRE PROTECTION SYSTEM

The Fire protection system proposed will provide early detection and suppression of

fires. The entire fire protection system will be designed as per the requirements of the

Tariff Advisory Committee - Fire Protection Manuals to avail maximum possible

rebate in fire insurance premium. The fire protection system will consist of fire

hydrants, sprinkler system for coal yard, fire water pumps and provision of portable

fire extinguishers.

AIR CONDITIONING AND VENTILATION

The common control room for the operation of steam generator and TG will be air-

conditioned.

The ventilation system for turbine building to be provided to evacuate the heat

generated from the operating equipment like turbine, pumps, motors etc. and also to

provide good working condition by providing fresh air with adequate number of air

changes.

Page 33: PROJECT FEASIBILITY REPORT FOR PROPOSED 350MW … energy/New PF... · PROJECT FEASIBILITY REPORT FOR PROPOSED 350MW ... Exit Volume of Flue Gas shall be reduced by about 22127 ...

SARDA ENERGY AND MINERALS LIMITED. PROJECT FEASIBILITY REPORT

350 MW POWER PROJECT

33

Control System

D.C.S. control system along with turbo-visory system shall be adopted for

thermodynamics system of power generation. All equipments will be centrally

controlled and monitored from the control room with choice to run locally, whenever

required.

PROCESS OF POWER GENERATION

Coal Based AFBC/CFBC/ PF Boiler – Capacity 2 X 520 TPH & 2 X 110 TPH

For Thermal Power Plant coal & water are the essential raw material in the process.

Coal & Middling will be transported from mines by road / conveyor. Coal received by

road is unloaded by truck tipper arrangement. The coal is brought to the coal

hoppers by conveyors. The coal from the hoppers is fed by vibro-feeder to a coal

conveyor. The coal from the conveyor is passed through coal crusher where the size

of the coal is reduced to -30 mm size. Subsequently the crushed coal is fed to the

vibratory screen where the size of the coal has been bifurcated in less than 30 mm &

more than 30 mm size. The Coal size having more than 30 mm is brought again to

the crusher the after crushing the size is reduced to less than 30 mm size. The coal

passing through vibrating screen of less than 30 mm size is transported through the

belt conveyor to the coal bunker. Now the coal available in the bunker is ready for

burning in the boiler.

Boiler

Boiler is provided with various auxiliaries such as ID Fan, FD, fan, PA fan, Coal

feeder, ESP, Ash handling system. The boiler is provided with various fittings duly

approved by IBR authorities.

Boiler consist of Steam Drum, water wall tube, PSH, SSH, Eco, Air heater. Initially

the DM water is filled in the boiler up to the center level of the Steam Drum provided

on the top of the boiler, This will ensure filling of DM water of all water side parts

such as economizer, bed coils, all the four walls of the boiler.

Initially ID fan started to maintain the natural draught in the furnace. Subsequently

FD fan will be started. The FD fan draws the air from the atmosphere and delivers to

the air heater and subsequently passes to air box / Burner provided with the boiler.

The PA fan is started to convey coal inside the Boiler after attaining ignition

temperature.

Lighting up of the Boiler is done through LDO , after achieving the temp. more than

600 Deg C of the furnace, the PA fan and Coal feeders/ Mills will be started.

Subsequently the coal of the desired quantity is fed into the boiler. The quantity of

Page 34: PROJECT FEASIBILITY REPORT FOR PROPOSED 350MW … energy/New PF... · PROJECT FEASIBILITY REPORT FOR PROPOSED 350MW ... Exit Volume of Flue Gas shall be reduced by about 22127 ...

SARDA ENERGY AND MINERALS LIMITED. PROJECT FEASIBILITY REPORT

350 MW POWER PROJECT

34

the coal injected into the furnace is slowly increase to achieve the boiler design

parameters.

The heat generated due to burning of the coal will be absorbed in the boiler parts and

the flue gases will be passed through various parts of the boiler so that the final gas

temperature achieve to 140 to 150 Deg C and finally pass through ESP, ID, Chimney

and to the atmosphere. While passing the dust-laden gas in the ESP, all the dust is

removed to the hoppers of the ESP and subsequently pass to the ash storage silo.

Boiler is generating steam of the desired parameters of the turbine and the generated

steam is passed through the turbine.

Turbine

The Steam Turbine is directly coupled with Generator and Exciter. Steam is passed

through turbine and at the last stage it is passed through the condenser where all

the exhaust steam is condensed in to the water by indirect cooling in the condenser.

Now turbine is rotating at the desired speed as it is directly coupled with the

generator and exciter. Generator generates AC current as per the manufacturer ‘s

recommended voltage. Now the power is available at the generator terminals & it can

be fed to substation. In the process Mechanical energy is converted into the electrical

energy.

Water

The water received from the river or any other water source is pumped to DM plant

and clarifier plant. In the DM plant water is purified to suit the Boiler. In Clarifier

plant, the water is purified to the desired extent and this water is used as the make

up to the small Induced draft Cooling Tower.

Page 35: PROJECT FEASIBILITY REPORT FOR PROPOSED 350MW … energy/New PF... · PROJECT FEASIBILITY REPORT FOR PROPOSED 350MW ... Exit Volume of Flue Gas shall be reduced by about 22127 ...

SARDA ENERGY AND MINERALS LIMITED. PROJECT FEASIBILITY REPORT

350 MW POWER PROJECT

35

Process Flow Diagram

The Project layout plan is enclosed in section 3.2 of this report.

Makeup Makeup Makeup Makeup

WaterWaterWaterWater

Coal Handling Coal Handling Coal Handling Coal Handling

PlantPlantPlantPlant

Coal Coal Coal Coal

Cooling Cooling Cooling Cooling

TowerTowerTowerTower

CondenserCondenserCondenserCondenser

Boiler Feed Boiler Feed Boiler Feed Boiler Feed

WaterWaterWaterWater

BoilerBoilerBoilerBoiler

CondensateCondensateCondensateCondensate

SteamSteamSteamSteam

SteamSteamSteamSteam

TurbineTurbineTurbineTurbine

GeneratorGeneratorGeneratorGenerator

TransformerTransformerTransformerTransformer

Cooling Cooling Cooling Cooling

Tower Tower Tower Tower

BlowdownBlowdownBlowdownBlowdown

BoilerBoilerBoilerBoiler

BlowdownBlowdownBlowdownBlowdown

Electrostatic Electrostatic Electrostatic Electrostatic

PrecipitatorsPrecipitatorsPrecipitatorsPrecipitators

BottomBottomBottomBottom

AshAshAshAsh

Fly AshFly AshFly AshFly Ash

Switch YardSwitch YardSwitch YardSwitch Yard

Bottom Ash Bottom Ash Bottom Ash Bottom Ash

StorageStorageStorageStorage

Dry Ash Dry Ash Dry Ash Dry Ash

Storage SilosStorage SilosStorage SilosStorage Silos

ChimneyChimneyChimneyChimney

Stack Stack Stack Stack

EmissioEmissioEmissioEmissio

nnnn

Ash Ash Ash Ash

UtilizationUtilizationUtilizationUtilization

DeaeratorDeaeratorDeaeratorDeaerator

CoolingCoolingCoolingCooling

waterwaterwaterwater

AshAshAshAsh

DykeDykeDykeDyke

To GridTo GridTo GridTo Grid

Page 36: PROJECT FEASIBILITY REPORT FOR PROPOSED 350MW … energy/New PF... · PROJECT FEASIBILITY REPORT FOR PROPOSED 350MW ... Exit Volume of Flue Gas shall be reduced by about 22127 ...

SARDA ENERGY AND MINERALS LIMITED. PROJECT FEASIBILITY REPORT

350 MW POWER PROJECT

36

3.6 Raw material

Raw Material

The main raw material required for generation of power is coal. The company has

been allotted captive coal blocks. The mined ROM coal will be washed for upgrading

the same for utilization in sponge Iron plant. The middling generated from our

proposed coal washery at Bajarmure & Dholnara will be utilized for generation of

power . The company will meet requirement of coal by Captive Karawahi Coal Mine,

Raigarh. All the coal will be transported from Mines/ Washery to plant site by closed

conveyor belts and road. The Power Generated from Power Plant shall be evacuated

through Tamnar Sub Station at 400 KV.

Name of Raw Material Total Quantity Required MTPA

Non Coking Coal 1.996

Middling From Coal Washery 0.334

Total 2.330

Start Up System – LDO / HFO

LDO / HFO fuel oil is required at the time of Boiler start up and stabilization period .

Total quantity estimated on annual basis as 3600 m3/year.

Coal

Coal and Middling consumption of the 350 MW power plants will be about 19.96

Lakhs TPA + 3.34 lakhs TPA when plant would operate at a Plant load factor (PLF) of 90

%.

Page 37: PROJECT FEASIBILITY REPORT FOR PROPOSED 350MW … energy/New PF... · PROJECT FEASIBILITY REPORT FOR PROPOSED 350MW ... Exit Volume of Flue Gas shall be reduced by about 22127 ...

SARDA ENERGY AND MINERALS LIMITED. PROJECT FEASIBILITY REPORT

350 MW POWER PROJECT

37

Expected Range of Coal Quality

S.No. Parameters Coal Middling

1. Sulphur (%) 0.3-0.4 0.3-0.4

2. Moisture (%) 8-12 10-16

3. Ash (%) 40-45 50-55

4. Gross Calorific

Values (GCV)

kCal/kg

3000-3600 1400-2200

5. Grade F G

Transport Facilities

Coal will be transported from the Captive Karwahi Coal Mine and Middling will be

transported from captive coal Washery to project site by Closed Conveyor belt and

Road.

3.7 Resources optimization/recycling and reuse envisaged in the project

Proper Blending of Raw Coal and Middling will be ensured while operation of plant to

have highest boiler efficiency and optimum coal consumption per kWh of energy

generated.

Ash generated from power plant shall be made available to nearby Cement Plants,

making of Eco friendly Bricks, Road building, Back filling of excavated mines in

Environment friendly manner.

Zero discharge of effluent shall be ensured from Power Plant by treating and re

utilizing all the waste water generated during operation.

3.8 Availability of water its source, Energy/Power requirement and its source

The overall water requirements of the plant including the re-circulating systems,

make-up water system, water treatment facilities, etc have been discussed in the

following paragraphs.

Page 38: PROJECT FEASIBILITY REPORT FOR PROPOSED 350MW … energy/New PF... · PROJECT FEASIBILITY REPORT FOR PROPOSED 350MW ... Exit Volume of Flue Gas shall be reduced by about 22127 ...

SARDA ENERGY AND MINERALS LIMITED. PROJECT FEASIBILITY REPORT

350 MW POWER PROJECT

38

Water requirements

Water is required in the plant mainly for the purpose of equipment cooling and make

up in cooling towers. Water is also required for drinking, sanitary and fire fighting

purposes. In order to conserve water and minimize the make-up water requirements,

it is proposed to adopt re-circulating systems for equipment cooling. In re-circulating

system same water re-circulates again and again for after proper treatment/bleed off.

The detail of water requirement is given below in the table:-

Water BalanceWater BalanceWater BalanceWater Balance

Sr.Sr.Sr.Sr.

No.No.No.No.

UUUUnitsnitsnitsnits Water Quantity (Cum/hr)Water Quantity (Cum/hr)Water Quantity (Cum/hr)Water Quantity (Cum/hr)

Water Water Water Water

RequirementRequirementRequirementRequirement

System LossSystem LossSystem LossSystem Loss WastewaterWastewaterWastewaterWastewater

1 Cooling Tower 1007 843 164

2 DM Water

3. For steam generation 4. For Potable

83 81 2

3 Service Water 25 22 3

TotalTotalTotalTotal 1115111511151115 946946946946 169169169169

Withdrawal of river water will be 1175 m3/hr, after considering loss due to

desludging, evaporation etc. (1115+60 = 1175 m3/hr).

Page 39: PROJECT FEASIBILITY REPORT FOR PROPOSED 350MW … energy/New PF... · PROJECT FEASIBILITY REPORT FOR PROPOSED 350MW ... Exit Volume of Flue Gas shall be reduced by about 22127 ...

SARDA ENERGY AND MINERALS LIMITED. PROJECT FEASIBILITY REPORT

350 MW POWER PROJECT

39

Water Balance DiagramWater Balance DiagramWater Balance DiagramWater Balance Diagram

Fig.- Water Balance Diagram

Raw WaterRaw WaterRaw WaterRaw Water

ReservoirReservoirReservoirReservoir

Service WaterService WaterService WaterService Water Filt. & DM PlantFilt. & DM PlantFilt. & DM PlantFilt. & DM Plant Cooling TowerCooling TowerCooling TowerCooling Tower

1007100710071007

164164164164

CT BleedCT BleedCT BleedCT Bleed

Back WashBack WashBack WashBack Wash

Potable Potable Potable Potable

WaterWaterWaterWater

DMDMDMDM

WaterWaterWaterWater

Plant Plant Plant Plant

utilitiesutilitiesutilitiesutilities

WastewaterWastewaterWastewaterWastewater

Total WastewaterTotal WastewaterTotal WastewaterTotal Wastewater

169169169169

ETP

ETPETPETPETP

1175

1115

25 83 1007

2

3 78 3

22

164 2 3

Road & Vehicle Road & Vehicle Road & Vehicle Road & Vehicle

washingwashingwashingwashing VentilationVentilationVentilationVentilation Coal Handling/Dust Coal Handling/Dust Coal Handling/Dust Coal Handling/Dust

SuppurationSuppurationSuppurationSuppuration GreenbeltGreenbeltGreenbeltGreenbelt Ash Handling Ash Handling Ash Handling Ash Handling

PlantPlantPlantPlant

169

6 22 29 83 29

All Values in mAll Values in mAll Values in mAll Values in m3333/hr/hr/hr/hr

60606060

Evaporation loss

843

Page 40: PROJECT FEASIBILITY REPORT FOR PROPOSED 350MW … energy/New PF... · PROJECT FEASIBILITY REPORT FOR PROPOSED 350MW ... Exit Volume of Flue Gas shall be reduced by about 22127 ...

SARDA ENERGY AND MINERALS LIMITED. PROJECT FEASIBILITY REPORT

350 MW POWER PROJECT

40

The water requirement for the power plant will be 81 m3/MW/ Day. The total water

requirement for the proposed power plant will be 1175 m3/ Hour.

Total plant water requirement shall be met from Kelo River. According to Water

Resource department required water is available in the Kelo River. Necessary

permission for withdrawing water has already been obtained from Authorities.

Dedicated water pipe line shall be laid from proposed Anicut to Plant which is about

7.7 KM from plant. A pump house shall be constructed at Anicut for pumping of

water.

Electricity for Pump House operation shall be taken via 33 KV line from nearby

substation.

3.9 Quantity of wastes to be generated (liquid and solid) and scheme for their

Management/disposal

The origin and the likely form of environmental pollution caused by various

operations in the proposed plant are summarized in Table given below.

From the table, it may be observed that dust pollution of ambient air is predominant

for which necessary pollution control measures are necessary.

ORIGIN AND FORM OF POLLUTION

Operational Principal

constituents

Likely form of

environmental pollution

Pollution Control

Measures

Raw materials

handling

Coal Air pollution due to dust,

Non toxic solid wastes

Localized noise pollution

Bag Filters , Water

Sprinkling etc.

Disposal in closed

containers and

other recycling

Industry

Proper Equipment

Selection and

maintaining Noise

norms across

plant boundary

Power Plant Flue gas from

boilers

Stack emissions Electro Static

Precipitators

Page 41: PROJECT FEASIBILITY REPORT FOR PROPOSED 350MW … energy/New PF... · PROJECT FEASIBILITY REPORT FOR PROPOSED 350MW ... Exit Volume of Flue Gas shall be reduced by about 22127 ...

SARDA ENERGY AND MINERALS LIMITED. PROJECT FEASIBILITY REPORT

350 MW POWER PROJECT

41

It is proposed to construct two nos. RCC stacks - One no. 220 meter height twin flue

for 2 x 150 MW Boiler & One no of 110 meters height for 50 MW boiler.

A brief review on pollution sources of respective production departments is discussed

below to identify the sources and the nature of environmental pollution in respect of

air, water, noise etc.

Raw Material Handling

In the raw material handling section the fugitive dust emissions arise from the

stockpiles of coal and other raw material handling units like crushing and screening

unit, material transfer points of conveyor system etc. Noise pollution may occur in

localized areas such as the crushing and screening unit.

Water pollution

In the proposed plant the major water pollution occurs in the wastewater generated from the DM plant and small quantity from cooling tower of the thermal power plant. Total 169 m3/hr waste water will be generated from plant and the same will be treated in Effluent Treatment Plant. The treated effluent will be utilized within the plant premises (Dust Suppuration for Road & Vehicle Washing, Ventilation, Coal Handling/Dust Suppuration, Greenbelt and Ash Handling etc.)

POLLUTION CONTROL MEASURES

The four principal pollutants in the plant are:

(i) Fugitive emissions of dusts in raw materials handling.

(ii) Air pollution due to stack emissions of combustion units

(iii) Waste water discharged from the various production units

(iv) Solid wastes generation. In each plant unit above, adequate

pollution control measures will be provided to meet the prevailing

emissions regulations and the allowable limits of waste water

discharge characteristics.

Page 42: PROJECT FEASIBILITY REPORT FOR PROPOSED 350MW … energy/New PF... · PROJECT FEASIBILITY REPORT FOR PROPOSED 350MW ... Exit Volume of Flue Gas shall be reduced by about 22127 ...

SARDA ENERGY AND MINERALS LIMITED. PROJECT FEASIBILITY REPORT

350 MW POWER PROJECT

42

Some of the major pollution control measures which have been envisaged in

the proposed project are outlined below:

Air Pollution Control

i) Extensive dust extraction systems such as dust cyclones, bag

filters and electrostatic precipitators to arrest the dusts emissions

from the raw materials handling in power plant. The conveyors will

be closed as far as practicable.

ii) Stacks of appropriate heights based on proper dispersion of stack

emissions.

Water Pollution Control

In all other departments the cooling water will be re circulated, and the system

operated as zero discharge. While in the case of indirect cooling circuits,

there is no treatment required, in case of contaminated circuits it will be

necessary to have a treatment facility.

The drain water (storm water drainage) will be generally impounded in the

lower reaches of the plant for use inside the plant. This water will be used

for gardening, sanitary uses, sprinkling in dusty areas, road washing etc.

Noise Pollution Control

Noise pollution control measures will be provided in respective departments by

way of providing silencers, sound-proof cubicles / covers, and proper

selection of less noise prone plant and machineries.

Page 43: PROJECT FEASIBILITY REPORT FOR PROPOSED 350MW … energy/New PF... · PROJECT FEASIBILITY REPORT FOR PROPOSED 350MW ... Exit Volume of Flue Gas shall be reduced by about 22127 ...

SARDA ENERGY AND MINERALS LIMITED. PROJECT FEASIBILITY REPORT

350 MW POWER PROJECT

43

Solid Waste Management

Ash is the main solid waste generated in the coal based thermal power plant.

The quantity of fly ash and bottom ash generated will be (0.84 MTPA) and

(0.21 MTPA) respectively.

Bottom ash will be disposed off by using slurry disposal system. Unutilized fly

ash will also be disposed off in designated ash disposal area. Fly ash will be

utilized in cement manufacturing, bricks plant and filling of mines etc.

Green Belt Department

It is proposed to have extensive green belts all around the plant by planting

suitable species of evergreen trees. Adequate tree plantations will substantially

abate the dust pollution, filter the polluted air, reduce the noise and

ameliorate the plant environment. Where tree plantations may not be feasible,

the unpaved land shall be covered with grass and small height bushes in order

to avoid soil erosion.

Workers Safety Measures

Besides the above, the operating and maintenance personnel will be provided

with all the necessary safety equipment such as hand gloves, gum boots,

aprons, helmets, protective glasses, ear muffs etc.

Workers training will focus on reduction of wastes, utilization of wastes and

generally maintaining a clean and healthy environment.

Pollution Monitoring

Necessary provisions for routine monitoring of stack emissions, ambient air

quality, noise level, water quality as required by the regulations will also be

provided.

3.10 Schematic representations of the feasibility drawing which give

information of EIA purpose

Please Refer Point no : 3.2 for Plant Layout , Point No. 3.5 for Process Flow Chart ,

Point No. 3.8 for Water Balance of the same report mentioned above.

Page 44: PROJECT FEASIBILITY REPORT FOR PROPOSED 350MW … energy/New PF... · PROJECT FEASIBILITY REPORT FOR PROPOSED 350MW ... Exit Volume of Flue Gas shall be reduced by about 22127 ...

SARDA ENERGY AND MINERALS LIMITED. PROJECT FEASIBILITY REPORT

350 MW POWER PROJECT

44

CHAPTER-IV

Site Analysis

4.1Connectivity

The proposed power plant would be located at village: Kolam in Tahsil: Tamnar dist :

Raigarh , Chhattisgarh State. The nearest town from the site is Ghargoda which is

around 8 KM. The nearest railway station is Raigarh on Mumbai – Howrah main line

which is around 35 KM. Nearest air port is at Raipur which is 250 KM from site. The

nearby sea ports are Vizag – 500 KM and Kolkata – 800 KM.

The site is connected to Raigarh – Panjipatra State Highway 76 at Tamnar which is

17 KM from Site

4.2 Land Form, Land use and Land ownership

The project requires about 127 Ha of land. Identified site ( 127 Ha) is mainly

comprising of agriculture land having single crop in a year , non irrigated land ,

revenue forest ( about 14.474 Ha). Land ownership is private mostly from village

Kolam , revenue forest is govt land .

4.3 Topography - with map

The proposed project site is fairly flat with shrubs present at some places.

There will not be much cutting and felling of trees for the proposed project.

The topography of the proposed site is gently undulating and sloping towards west.

Page 45: PROJECT FEASIBILITY REPORT FOR PROPOSED 350MW … energy/New PF... · PROJECT FEASIBILITY REPORT FOR PROPOSED 350MW ... Exit Volume of Flue Gas shall be reduced by about 22127 ...

SARDA ENERGY AND MINERALS LIMITED. PROJECT FEASIBILITY REPORT

45

Fig. - Topographical Map of 10 KM radius from proposed site.

Page 46: PROJECT FEASIBILITY REPORT FOR PROPOSED 350MW … energy/New PF... · PROJECT FEASIBILITY REPORT FOR PROPOSED 350MW ... Exit Volume of Flue Gas shall be reduced by about 22127 ...

SARDA ENERGY AND MINERALS LIMITED. PROJECT FEASIBILITY REPORT

350 MW POWER PROJECT

46

4.4 Existing land use pattern (agriculture, non-agriculture, forest, water bodies (agriculture, non-agriculture, forest, water bodies (including area under CRZ)), shortest distances from the periphery of the project to periphery of the forests, national park, wild life sanctuary, eco sensitive areas, water bodies (distance from the HFL of the river), CRZ.

127.0 ha of single crop agricultural land is under acquisition for the proposed

projects including 14.474 ha of revenue forests land which is about 4.0 KM from

company's captive Coal Mine. The physical changes in respect of topography and

land use, though permanent, shall be compensated by developing green belt and

afforestation activities in and around the project site.

No National Park and Wildlife Sanctuaries in 10 KM radius from the proposed site.

Details of nearby Reserve Forest

1. Silot Reserve Forest - 3.6 KM North East 2. Deodongar Reserve Forest - 9.2 KM North East 3. Samaruma Reserve Forest - 6.6 KM South West 4. Amaghat Protected Forest - 8.4 KM South South West 5. Revenue Forest - Adjacent North West Side

Nearby Eco-sensitive Zones – Nil

Nearby Elephant/Tiger Reserves – Nil

Migratory Routes – No

4.5 Existing Infrastructure

Good infrastructure is available in the vicinity of Plant which makes proposed site

ideal for Power Generation Plant; some of the key features are listed below

1. Availability of Lailunga - Gharghoda Road of 10 meter width along side plant

boundary. Same can be used for transportation of all kind of Power Plant

Equipment , Raw material and Ash transportation.

2. Availability of adequate Water Resources in the radius of 8 KM

3. Power Evacuation through National Grid at Tamnar (15 KM distance from site )

4.6 Soil classification

Page 47: PROJECT FEASIBILITY REPORT FOR PROPOSED 350MW … energy/New PF... · PROJECT FEASIBILITY REPORT FOR PROPOSED 350MW ... Exit Volume of Flue Gas shall be reduced by about 22127 ...

SARDA ENERGY AND MINERALS LIMITED. PROJECT FEASIBILITY REPORT

350 MW POWER PROJECT

47

Plant site is hard sub soil with very good soil bearing capacity. Physical

characteristics of soil are delineated through specific parameters viz. particle size

distribution, bulk density, porosity, water holding capacity and texture.

The bulk density of the soil in the site ranged between 1.31 to 1.49 g/cc which

indicates favorable physical condition for plant growth. The porosity and water

holding capacity of the soils are in the range of 33.65 % to 39.54 % and 34.21 % to

37.64% respectively. The soil in the impact zone has sandy loam structure with

moderate water holding capacity

4.7 Climatic data from secondary sources

Climatical data collected from Secondary source i.e. IMD Raigarh. The details of data

are tabulated below:-

Month

Temperature (oc) Relative Humidity (%) Rain-fall

Min Max Min Max Mean

January 13.3 28.3 40 61 11.2

February 16.0 31.6 30 53 15.7

March 20.4 36.0 23 41 2.4

April 25.1 40.3 20 38 13.8

May 28.0 42.6 21 40 17.5

June 27.1 38.0 50 63 199.0

July 24.7 31.6 76 85 453.8

August 24.7 31.1 78 86 494.5

September 24.5 32.2 73 81 287.2

October 22.0 32.4 59 71 49.1

November 17.1 30.3 47 61 3.7

December 13.2 28.2 44 62 4.1

Page 48: PROJECT FEASIBILITY REPORT FOR PROPOSED 350MW … energy/New PF... · PROJECT FEASIBILITY REPORT FOR PROPOSED 350MW ... Exit Volume of Flue Gas shall be reduced by about 22127 ...

SARDA ENERGY AND MINERALS LIMITED. PROJECT FEASIBILITY REPORT

350 MW POWER PROJECT

48

The maximum wind speed of the area is 60 KM/hr.

4.8 Social Infrastructure available

Kolam is the Nearest village to plant, General social infrastructure like Samudayik

Bhawan , School etc are available in the nearby villages.

Page 49: PROJECT FEASIBILITY REPORT FOR PROPOSED 350MW … energy/New PF... · PROJECT FEASIBILITY REPORT FOR PROPOSED 350MW ... Exit Volume of Flue Gas shall be reduced by about 22127 ...

SARDA ENERGY AND MINERALS LIMITED. PROJECT FEASIBILITY REPORT

350 MW POWER PROJECT

49

CHAPTER-V

Planning Brief

5.1 Planning concept

Type of industry: Power Plant

Transportation Facilities: Lailunga - Gharghoda Road for transportation . Gharghoda

is connected to national Highway.

Town and Country planning/Development authority: Gram Panchayat

5.2 Population Projection

Total Population in 10 KM radius of site is estimated as 76638.

5.3 Land use planning (breakup along with green belt etc.)

The present project requires 126.67 ha of land. The break-up of the land use for

the project is given in Table below. The layout plan of the proposed power plant is

presented in Section 3.2 of this report.

Table-Breakup of Land Use

S. No. Description Area (ha)

1. Main Plant Area 35.61

2. Coal Handling Area 6.07

3. Storage of Other Fuel 7.28

4. Green Belt 41.68

5. Ash Disposal Area 12.14

6. Admin Block 2.43

7. Roads 10.52

8. Ash Brick Plant 10.93

Total 126.67

(Say 127 ha.)=

Page 50: PROJECT FEASIBILITY REPORT FOR PROPOSED 350MW … energy/New PF... · PROJECT FEASIBILITY REPORT FOR PROPOSED 350MW ... Exit Volume of Flue Gas shall be reduced by about 22127 ...

SARDA ENERGY AND MINERALS LIMITED. PROJECT FEASIBILITY REPORT

350 MW POWER PROJECT

50

The main objective of the green belt is to provide a buffer between the sources of

pollution and the surrounding areas. The green belt helps to capture the fugitive

emissions and attenuate the noise apart from improving the aesthetics quality of the

region. A 20 – 25 m wide greenbelt shall be developed along the periphery of the plant

and in all open areas. Avenue plantation shall also be developed as per the standard

norms. Approximately 1500 trees per Ha will be planted in consultation with the local

forest department. .33% area of the total plant area will be developed as Green belt .

5.4 Assessment of Infrastructure Demand (physical & social).

Basic infrastructure demand for nearby area would be first to have internal roads ,

availability clean and pure drinking water , availability of good schools , availability of

Hospitals , community halls , Sulabh Shauchalaya , easy and faster means of

transportation and connectivity to nearby town and city , availability of

uninterrupted electricity etc are the present assessed demands for sustained and

healthy growth of nearby area of site. Most of the infrastructure demand mentioned

above comes automatically when industry of this magnitude comes in such remote

area , systematic efforts shall be made to bring such facility in the surrounding area

for all round physical and social development.

5.5 Amenities / Facilities

For the social development in the affected area the company has plans firm as to

construct community halls, road, drinking water etc. Company shall provide mobile

medical van for the free treatment for nearby villagers. Time to time the company

shall also organize free eye check up, cataract camp, free distribution of spectacles

etc.. The company will initiate and construct primary health center in association

with Heath Department of Chhattisgarh Government.

Page 51: PROJECT FEASIBILITY REPORT FOR PROPOSED 350MW … energy/New PF... · PROJECT FEASIBILITY REPORT FOR PROPOSED 350MW ... Exit Volume of Flue Gas shall be reduced by about 22127 ...

SARDA ENERGY AND MINERALS LIMITED. PROJECT FEASIBILITY REPORT

350 MW POWER PROJECT

51

CHAPTER-VI

Proposed Infrastructure

6.1 Green Belt

The main objective of the green belt is to provide a buffer between the sources of

pollution and the surrounding areas. The green belt helps to capture the fugitive

emissions and attenuate the noise apart from improving the aesthetics quality of the

region. A 20 – 25 m wide greenbelt shall be developed along the periphery of the plant

and in all open areas. Avenue plantation shall also be developed as per the standard

norms. Approximately 1500 trees per Ha will be planted in consultation with the local

Forest Department. 33% area of the total plant area will be developed as Green belt .

6.2 Social Infrastructure

For the social development company will provide the arrangement of community

hall, road, water, electricity etc. in the affected villages. For the economical

development the company will provide the employment as per requirement and

individuals qualification and eligibility. For the educational development the set up of

an English medium school is proposed.

For the social development in the affected area the company is planning to construct

community hall and will provide other facility like road, water, electricity etc.

6.3 Drinking Water Management

The source of water to the plant is Kelo river. The drinking water system will cater to

the drinking and sanitary requirements of plant personnel as well as laboratory and

contingent users. The required water will be withdrawn from the storage reservoir by

two pumps (including one stand-by). The treated water will be chlorinated and stored

in the overhead tank for distribution as drinking water.

6.4 Sewerage system

It is proposed to collect fecal sewerage through sewerage network from the

plant and lead it to the sewage treatment plant. The treatment plant shall

consist of screen grit separator, primary sedimentation tank, activated sludge

plant, secondary clarifier, sludge recirculation pump house etc. The treated

Page 52: PROJECT FEASIBILITY REPORT FOR PROPOSED 350MW … energy/New PF... · PROJECT FEASIBILITY REPORT FOR PROPOSED 350MW ... Exit Volume of Flue Gas shall be reduced by about 22127 ...

SARDA ENERGY AND MINERALS LIMITED. PROJECT FEASIBILITY REPORT

350 MW POWER PROJECT

52

effluent quality shall conform to the Indian Standard for discharge to surface

water.

6.5 Industrial Waste Management

Management procedure and methodology of all kind of wastes from Plant like Ash

& Effluent Water etc is already discussed in details under point no. 3.9 of this

report.

6.6 Solid Waste Management

The main solid waste from the proposed Power Plant will be ash (Fly ash and Bottom

ash). The ash generation of about 3181 TPD(1.05 MTPA). Out of this, the bottom ash

will be about 20% of the total bottom ash generated i.e. 636 TPD (0.21MTPA ) and the

fly ash will be about 2545 TPD (0.84 MTPA ) . It is proposed to utilize 100% of the fly

ash generated. During emergency the ash will be disposed off safely in ash pond area

to avoid environmental hazards. All efforts, however, will be made to utilize fly ash for

various purposes. Unused fly ash will be disposed off in the ash pond. To control

fugitive dust emission from the ash pond area water sprinkling would be done. After

the ash pond is abandoned, its area will be reclaimed through tree plantation.

6.7 Power Requirement & Supply /Source

Power shall be required from CSEB during Construction of Power Plant and initial

start up of Plant. Once Plant is synchronized power will be flowing out from the plant.

Occasionally power will be required from the grid at the time of black of condition.

Total 15000 KVA connected demand is envisaged for plant.

Page 53: PROJECT FEASIBILITY REPORT FOR PROPOSED 350MW … energy/New PF... · PROJECT FEASIBILITY REPORT FOR PROPOSED 350MW ... Exit Volume of Flue Gas shall be reduced by about 22127 ...

SARDA ENERGY AND MINERALS LIMITED. PROJECT FEASIBILITY REPORT

350 MW POWER PROJECT

53

CHAPTER-VII

Rehabilitation and Resettlement (R & R) Plan

The total area identified for the proposed project is 127.0 ha.(313 Acre). There was no

displacement of people. Thus R & R issues are not applicable.

Page 54: PROJECT FEASIBILITY REPORT FOR PROPOSED 350MW … energy/New PF... · PROJECT FEASIBILITY REPORT FOR PROPOSED 350MW ... Exit Volume of Flue Gas shall be reduced by about 22127 ...

SARDA ENERGY AND MINERALS LIMITED. PROJECT FEASIBILITY REPORT

350 MW POWER PROJECT

54

CHAPTER-VIII

Project Schedule and Cost Estimates

8.1 Likely date of start of construction and likely date of completion

Phase I - Year March 2014 (2 x 150 MW) Phase II - Year June 2014 (1x50 MW)

PROJECT IMPLEMENTATION CONCEPT

In order to ensure coordinated implementation within the short construction

period envisaged for the project, it will be necessary to evolve an optimal

compromise between the fully disaggregated mode and the turnkey package

implementation mode. In principle, it will be prudent to tie up the technology

requirements and the key equipment in the production units to reliable and

high quality vendors. In the case of the major production packages, it will be

necessary for the Principal supplier (responsible for the basic engineering,

equipment engineering, technology, critical equipment supply, and

performance guarantees). The local procurement can cover the balance non-

critical equipment, auxiliaries and systems. The major auxiliary packages in

the power system, water system and the yard utilities will be formed into

discrete packages.

The proposed model has been adopted in a number of projects with

considerable success and fast ramp up. The construction schedule for the

project has been drawn up accordingly.

CONSTRUCTION SCHEDULE

Taking into account the estimated volume of work, the need to commission the

plant facilities in the shortest times with a rational planning of the production

facilities, a preliminary construction schedule for the proposed plant will be

prepared.

The commencement, duration and completion of the major construction

activities are given in this schedule. It will be noted that the schedule

envisages commissioning of the first unit of the plant in 27 month from ‘go-

ahead’ and the second unit 30 months.

ADVANCE ACTIONS

The project due to its large investment stands to gain substantially if the actual

construction and implementation period is kept to the minimum. For this purpose it

Page 55: PROJECT FEASIBILITY REPORT FOR PROPOSED 350MW … energy/New PF... · PROJECT FEASIBILITY REPORT FOR PROPOSED 350MW ... Exit Volume of Flue Gas shall be reduced by about 22127 ...

SARDA ENERGY AND MINERALS LIMITED. PROJECT FEASIBILITY REPORT

350 MW POWER PROJECT

55

is necessary that the planning and preparatory work on the project be done in a

thorough manner, which will ensure that the project construction and

implementation once started can proceed uninterrupted and without any delays. The

start date (Zero date) for the construction schedule is reckoned as the completion of

these advance actions.

The advance actions on the project which will provide the appropriate foundation for

cost effective and timely implementation are:

i) Acquisition of land at the selected location

ii) Site survey and preliminary soil investigations

iii) Environmental clearance for implementation of the project

iv)Finalization of the financing arrangements for the project and the creation of a

project organization

v)Finalization of the adequate details of the project to enable site activities to

commence from the date of ‘go-ahead’.

vi) Issue of inquiries for the major packages and finalization of the orders for the

same

vii) Actions for linkages of power, water and other infrastructure.

SITE DEVELOPMENT & CONSTRUCTIONS FACILITIES

Site development activities include contour survey, soil investigation, site

preparation, site drainage, construction water, construction power, construction

storage yards etc. Activities related to site acquisition surveys and soil investigations

will envisage to be accomplished by the time the ‘go-ahead’ for project commences.

Establishment of construction power, water site preparation and other activities will

be completed in three (3) months from ‘go-ahead’.

Special efforts will have to be made during implementation to keep the earthwork and

the site preparation to the minimum both for cost savings as well as reduction in

construction time.

CIVIL & STRUCTURAL WORK

The schedule for carrying out the civil work and structural steel work is based on the

volume of work and interlink between the completions of some of these activities to

enable the subsequent activities to proceed. Structural steelwork covers all the

building structures. In order to meet the overall time-frame envisaged in the

schedule, the completion of civil and structural work in a time-bound manner is a

pre-requisite for the project completion for the schedule.

Page 56: PROJECT FEASIBILITY REPORT FOR PROPOSED 350MW … energy/New PF... · PROJECT FEASIBILITY REPORT FOR PROPOSED 350MW ... Exit Volume of Flue Gas shall be reduced by about 22127 ...

SARDA ENERGY AND MINERALS LIMITED. PROJECT FEASIBILITY REPORT

350 MW POWER PROJECT

56

EQUIPMENT MANUFACTURE & DELIVERY

As indicated earlier, as an advance action, specifications will have to be issued for the

various plant and equipment, on a reputed manufacture / tenders basis and will be

evaluated and orders to be finalized. Major packages will cover material handling

system and Power plant, and these will need to be tendered out. Placement of order

for such packages is envisaged within two (2) months to (4) months from the date of

go ahead for project construction. It is assumed that advance work on the

preparation of specifications, evaluation of tenders and readiness for placement of

orders will be taken. The duration generally accepted internationally for manufacture

and delivery of various equipment have been taken into account while evolving the

implementation schedule.

The delivery schedule of equipment for power, water, utility and other auxiliary

systems has been so framed that they can be commissioned in time to cater to the

respective plant facilities for their commissioning.

Page 57: PROJECT FEASIBILITY REPORT FOR PROPOSED 350MW … energy/New PF... · PROJECT FEASIBILITY REPORT FOR PROPOSED 350MW ... Exit Volume of Flue Gas shall be reduced by about 22127 ...

SARDA ENERGY AND MINERALS LIMITED. PROJECT FEASIBILITY REPORT

350 MW POWER PROJECT

57

EQUIPMENT ERECTION

Erection of equipment will have to commence after availability of fronts on completion

of the civil and structural work as well as delivery of equipment at the plant site. It is

expected that the duration for erection of equipment for plant facilities will vary

between (10) months and (16) months from the date of commencement of equipment

erection.

EXTERNAL FACILITIES

The various off site facilities such as external water supply, external power supply ,

road links etc will be implemented to suit the schedule envisaged. It is expected that

the above facilities will be ready well prior to commencement of trial runs and

commencement of the various plant facilities.

TRIAL RUNS & COMMISSIONING

A period of 2 months has been envisaged for carrying out trial runs.

PROJECT MONITORING

At the project implementation stage, all project activities from design and engineering

to construction, equipment supply, erection, testing and commissioning of the plant

and equipment will be monitored on the basis of a computerized network monitoring

system. Various reports as relevant for different aspects of project monitoring will be

generated through the computerized system.

Action points will be identified agency-wise and actions taken for timely

implementation the milestones to be achieved for meeting this schedule will be

identified and monitored for their achievement. Critical activities of the project as

they arise, will also be identified and monitored and followed up to ensure timely

completion.

Page 58: PROJECT FEASIBILITY REPORT FOR PROPOSED 350MW … energy/New PF... · PROJECT FEASIBILITY REPORT FOR PROPOSED 350MW ... Exit Volume of Flue Gas shall be reduced by about 22127 ...

SARDA ENERGY AND MINERALS LIMITED. PROJECT FEASIBILITY REPORT

350 MW POWER PROJECT

58

8.2 Estimated project cost along with analysis in terms of economic viability of

the project

COST OF PROJECT

The estimated cost of the project is Rs 1400 Crores including pre-operative expenses

and margin money for working capital requirements. The financing and pre-operative

cost has been considered based on the proposed financial package.

Particulars TOTAL in Lacs

Land and Site Development 6000.00

Civil &Building 16250.00

Plant & Machinery 100500.00

Preliminary Expenses 2250.00

Consultants Fees 2250.00

Pre-Operative Expenses 5750.00

Margin Money on Working Capital 3500.00

Contingencies 3500.00

TOTAL 140000.00

The financing and pre-operative cost has been considered based on the proposed

financial package.

MEANS OF FINANCE

The project is proposed to be financed at a debt equity ratio of 2:1. The promoters

contribution will be met out of internal accruals and shortfall, if any, would be met

out of unsecured loans (interest free) brought in by the promoters.

Page 59: PROJECT FEASIBILITY REPORT FOR PROPOSED 350MW … energy/New PF... · PROJECT FEASIBILITY REPORT FOR PROPOSED 350MW ... Exit Volume of Flue Gas shall be reduced by about 22127 ...

SARDA ENERGY AND MINERALS LIMITED. PROJECT FEASIBILITY REPORT

350 MW POWER PROJECT

59

CHAPTER-IX

Analysis of proposal (Final Recommendations)

9.1 Financial and social benefits with special emphasis on the benefits to the

local people including tribal population, if any, in the area

The proposed 350 MW Power plant will result in improvement of infrastructure as

well as upliftment of social structure in the area. The people residing in the nearby

areas will be benefited directly and indirectly. It is anticipated that the proposed

power plant will provide benefits for the locals in two phases i.e. during construction

phase as well as during operational stage of the plant.

• Construction Phase

Employment

The major benefit due to the proposed project will be in the sphere of

generating employment for about 700 persons in that area. The proposed

project will benefit local population.

• Operational Phase

Community Services

SEML will employ local people to the extent possible for avoiding creation of

additional infrastructure. SEML will develop medical facilities for catering to

the needs of the project personnel. These facilities will also be extended to the

local community in due course.

Education

SEML will initiate action for social up liftment in the area like female education,

vocational training. Financial support will also be extended to strength education

infrastructure in the region.

Employment

The manpower requirements for the operational phase of the Power Plant will be

about 700 people. In addition, there will be an indirect employment for skilled/ semi

skilled people during project life. All attempts will be made to employ suitable, locally

available, skilled personnel from the study area. In case of non-availability of skilled

persons, people will be employed from out side the study area.

Page 60: PROJECT FEASIBILITY REPORT FOR PROPOSED 350MW … energy/New PF... · PROJECT FEASIBILITY REPORT FOR PROPOSED 350MW ... Exit Volume of Flue Gas shall be reduced by about 22127 ...

SARDA ENERGY AND MINERALS LIMITED. PROJECT FEASIBILITY REPORT

350 MW POWER PROJECT

60

Transportation

There will also be small increase in the vehicular traffic due to passenger transport.

This increase in traffic will not have any consequence to warrant special mention.

One should expect that the increased passenger load in the sector would prompt the

state government/ private movers to start new and frequent public transport services

to this area, bringing up liftment to the whole locality.

Other Benefits

SEML is equally conscious for the all round socio-economic development and is

committed to raise the quality of life and social well being of communities where it

operates. Its CSR initiatives have been prioritized on local needs, which focus on

Health, Education, Infrastructure Development and Environment Conservation.