Page 1: Project engineer test   level 3

HERVE BARON

© 2015 – Hervé Baron

Welcome to this assessment

It will test you general knowledge as a Project Engineer.

Enjoy!

Comments are most welcome ([email protected]), which I will incorporate for the benefit of all.

Hervé

Project Engineer knowledge test

Page 2: Project engineer test   level 3

HERVE BARON

© 2015 – Hervé Baron

What is the cost of the Spare Parts for 2 years operation for the following commodity:

0% of PO Price

10% of PO Price

20% of PO price?

Pressure Vessels

Pumps

Control, ON/OFF valves, PSVs

Unit Control Panel

Project Engineer knowledge test

Page 3: Project engineer test   level 3

HERVE BARON

© 2015 – Hervé Baron

What is the cost of the Spare Parts for 2 years operation for the following commodity:

0% of PO Price

10% of PO Price

20% of PO price?

Pressure Vessels – 0%

Pumps – 10%

Control, ON/OFF valves, PSVs – 20%

Unit Control Panel – 10%

Project Engineer knowledge test

Page 4: Project engineer test   level 3

HERVE BARON

© 2015 – Hervé Baron

What is missing from the table of contents of the Engineering Design Data shown below?

Project Engineer knowledge test

Page 5: Project engineer test   level 3

HERVE BARON

© 2015 – Hervé Baron

What is missing from the table of contents of the Engineering Design Data shown below?

Project Engineer knowledge test

Source: ”The Oil & Gas Engineering Guide”, Hervé Baron, Editions Technip, page 12

Page 6: Project engineer test   level 3

HERVE BARON

© 2015 – Hervé Baron

Which system is used to calculate the engineering progress by document weight and progress steps (revision status)

1) the Project scheduling software, such as Primavera,

2) the document control system and master document register

3) another system

Project Engineer knowledge test

Page 7: Project engineer test   level 3

HERVE BARON

© 2015 – Hervé Baron

Which system is used to calculate the engineering progress by document weight and progress steps (revision status)

1) the Project scheduling software, such as Primavera,

2) the document control system and master document register

3) another system, as the progress measurement is done by group of documents, e.g., Unit 12 P&IDs, not by individual document which is the level system 2 goes to. The grouping is finer than that of the scheduling software.

Project Engineer knowledge test

Page 8: Project engineer test   level 3

HERVE BARON

© 2015 – Hervé Baron

Project Engineer knowledge test

What is the graphic scale of the Civil Works Installation (also called Civil Area) drawings?

1) 1:50

2) 1:200

3) 1:500

Page 9: Project engineer test   level 3

HERVE BARON

© 2015 – Hervé Baron

What is the graphic scale of the Civil Works Installation (also called Civil Area) drawings?

1) 1:50

2) 1:200

3) 1:500

Project Engineer knowledge test

Page 10: Project engineer test   level 3

HERVE BARON

© 2015 – Hervé Baron

Project Engineer knowledge test

When does Engineering progress picks-up to reach cruising speed on an EPC?

1) after all disciplines have been mobilized

2) after the P&IDs have been finalized

3) after the Plot Plan has been finalized

4) after the purchase orders for equipment have been placed

5) after the completion of the 3D model

Page 11: Project engineer test   level 3

HERVE BARON

© 2015 – Hervé Baron

Project Engineer knowledge test

When does Engineering progress picks-up to reach cruising speed on an EPC?

1) after all disciplines have been mobilized

2) after the P&IDs have been finalized

3) after the Plot Plan has been finalized

4) after the purchase orders for equipment have been placed. Cruise speed is reached 2 months after 50% of equipment purchase orders have ben placed.

5) after the completion of the 3D model

Page 12: Project engineer test   level 3

HERVE BARON

© 2015 – Hervé Baron

Project Engineer knowledge test

What type of specification is issued (by Equipment/Mechanical discipline) for air-coolers?

1) a particular specification

2) a general specification

Page 13: Project engineer test   level 3

HERVE BARON

© 2015 – Hervé Baron

Project Engineer knowledge test

What type of specification is issued (by Equipment/Mechanical discipline) for air-coolers?

1) a particular specification

2) a general specification

Page 14: Project engineer test   level 3

HERVE BARON

© 2015 – Hervé Baron

Project Engineer knowledge test

The lengths of pipes used for the first purchase order of piping materials are obtained from?

1) The Piping General Arrangement drawings,

2) The Plot plan,

3) Piping layout drawings,

4) The 3D model,

5) The isometric drawings,

Page 15: Project engineer test   level 3

HERVE BARON

© 2015 – Hervé Baron

Project Engineer knowledge test

The lengths of pipes used for the first purchase order of piping materials are obtained from?

1) The Piping General Arrangement drawings,

2) The Plot plan,

3) Piping layout drawings,

4) The 3D model,

5) The isometric drawings,

Page 16: Project engineer test   level 3

HERVE BARON

© 2015 – Hervé Baron

Project Engineer knowledge test

Which of the following documents are produced at BASIC engineering stage (prior to FEED stage)

1) Equipment Process data sheets

2) Equipment Mechanical data sheets

3) Material Take-Off's

4) Piping routing drawings

Page 17: Project engineer test   level 3

HERVE BARON

© 2015 – Hervé Baron

Project Engineer knowledge test

Which of the following documents are produced at BASIC engineering stage (prior to FEED stage)

1) Equipment Process data sheets

2) Equipment Mechanical data sheets

3) Material Take-Off's

4) Piping routing drawings

Page 18: Project engineer test   level 3

HERVE BARON

© 2015 – Hervé Baron

Project Engineer knowledge test

What is a Material Take-Off?

1) an estimate of quantities to be supplied/erected,

2) the cumulated quantities of what is shown on a set of drawings

Page 19: Project engineer test   level 3

HERVE BARON

© 2015 – Hervé Baron

Project Engineer knowledge test

What is a Material Take-Off?

1) an estimate of quantities to be supplied/erected,

2) the cumulated quantities of what is shown on a set of drawings

Page 20: Project engineer test   level 3

HERVE BARON

© 2015 – Hervé Baron

Project Engineer knowledge test

What does IP level of electrical and instrumentation equipment mean and stand for?

Level of mechanical protection

Level of explosion protection

IP means: ………….

Page 21: Project engineer test   level 3

HERVE BARON

© 2015 – Hervé Baron

Project Engineer knowledge test

What does IP level of electrical and instrumentation equipment mean and stand for?

Level of mechanical protection

Level of explosion protection

IP means: Ingress Protection. It means mechanical protection and protection again ingress of water, dust etc. Reference code is IEC 60529 "Degree of Protection provided by enclosures". Typically a certain IP level is specified for outdoor equipment and another one for indoor equipment.

Page 22: Project engineer test   level 3

HERVE BARON

© 2015 – Hervé Baron

Project Engineer knowledge test

What do you call the Instrument & Control drawing showing all details of wiring, with termination and inter-connections from primary element to final, including tags of

• Primary element, • Individual cables, • Junction boxes, • Multipair cables, • Cable cores • Terminals, • I/O cards, • Panels, • Locations (field, technical rooms)

Page 23: Project engineer test   level 3

HERVE BARON

© 2015 – Hervé Baron

Project Engineer knowledge test

Source: ”The Oil & Gas Engineering Guide”, Hervé Baron, Editions Technip, page 173

Page 24: Project engineer test   level 3

HERVE BARON

© 2015 – Hervé Baron

Project Engineer knowledge test

Which of the following Equipment Vendor documents are critical for Engineering progress?

1) Cross section drawings and bills of materials

2) List of inputs/outputs to DCS

3) Foundation layout and loading plan

4) Filled-in data sheet

5) Operating Manual

6) General arrangement drawing

7) Strength calculation note

8) Utility consumption list

9) Performance curve

Page 25: Project engineer test   level 3

HERVE BARON

© 2015 – Hervé Baron

Project Engineer knowledge test

Which of the following Equipment Vendor documents are critical for Engineering progress?

1) Cross section drawings and bills of materials

2) List of inputs/outputs to DCS

3) Foundation layout and loading plan

4) Filled-in data sheet

5) Operating Manual

6) General arrangement drawing

7) Strength calculation note

8) Utility consumption list

9) Performance curve

Page 26: Project engineer test   level 3

HERVE BARON

© 2015 – Hervé Baron

Project Engineer knowledge test

Which sentences are correct:

1) The Piping General Arrangement Drawing contains all the information required to produce the piping isometric drawing,

2) The piping isometric drawing indicates the piping material class. The exact material designation is found in the piping material class specification.

3) The piping isometric drawing is used for piping pre-fabrciation,

4) The Piping General Arrangement drawing is used for piping erection,

5)The 3D model is often used nowdays in lieu of the Piping General Arrangement,

Page 27: Project engineer test   level 3

HERVE BARON

© 2015 – Hervé Baron

Project Engineer knowledge test

Which sentences are correct:

1) The Piping General Arrangement Drawing contains all the information required to produce the piping isometric drawing,

2) The piping isometric drawing indicates the piping material class. The exact material designation is found in the piping material class specification.

3) The piping isometric drawing is used for piping pre-fabrciation,

4) The Piping General Arrangement drawing is used for piping erection,

5)The 3D model is often used nowdays in lieu of the Piping General Arrangement,

Page 28: Project engineer test   level 3

HERVE BARON

© 2015 – Hervé Baron

Project Engineer knowledge test

The Process Data Sheet of a heat exchanger indicates which of the following information?

1) the duty

2) the heat exchange area

3) the fouling factor

4) the type of each exchanger (U-tube etc.)

5) the allowable pressure drop

6) dimensions

7) overdesign

Page 29: Project engineer test   level 3

HERVE BARON

© 2015 – Hervé Baron

Project Engineer knowledge test

The Process Data Sheet of a heat exchanger indicates which of the following information?

1) the duty

2) the heat exchange area

3) the fouling factor

4) the type of each exchanger (U-tube etc.)

5) the allowable pressure drop

6) dimensions

7) overdesgin

Page 30: Project engineer test   level 3

HERVE BARON

© 2015 – Hervé Baron

Project Engineer knowledge test

Which codes gives the corrosion rate (in mm/year) for the usual corrosion phenomena found in Oil & Gas facilities?

1) ASME VIII

2) NACE MR103

3) API RP 581

4) none of the above

Page 31: Project engineer test   level 3

HERVE BARON

© 2015 – Hervé Baron

Project Engineer knowledge test

Which codes gives the corrosion rate (in mm/year) for the usual corrosion phenomena found in Oil & Gas facilities?

1) ASME VIII

2) NACE MR103

3) API RP 581

4) none of the above

Page 32: Project engineer test   level 3

HERVE BARON

© 2015 – Hervé Baron

Project Engineer knowledge test

FEED studies primarily focus on

1) Plant Layout

2) Piping routing

3) Process design

Page 33: Project engineer test   level 3

HERVE BARON

© 2015 – Hervé Baron

Project Engineer knowledge test

FEED studies primarily focus on

1) Plant Layout

2) Piping routing

3) Process design

Page 34: Project engineer test   level 3

HERVE BARON

© 2015 – Hervé Baron

Project Engineer knowledge test

"free draining" and "no pocket" indication on P&IDs mean the same thing. Right or Wrong?

Page 35: Project engineer test   level 3

HERVE BARON

© 2015 – Hervé Baron

Project Engineer knowledge test

"free draining" and "no pocket" indication on P&IDs mean the same thing. Right or Wrong?

Page 36: Project engineer test   level 3

HERVE BARON

© 2015 – Hervé Baron

Project Engineer knowledge test

Which drawing corresponds to the following definition: "initial graphic piping plan. It is not a finished document, nor is it a deliverable to a Client. It shows all equipment in a given area to scale and includes major process and utility piping systems, significant valving and instruments. It indicates the exact equipment locations and elevations, nozzles, platform and ladder requirements and any pipe support that affects the design of equipment or structure other disciplines".

1) the Piping and Instrumentation Diagram

2) the Unit Plot Plan

3) the line diagram

4) the Piping layout drawing

5) the Piping General Arrangement drawing

Page 37: Project engineer test   level 3

HERVE BARON

© 2015 – Hervé Baron

Project Engineer knowledge test

Which drawing corresponds to the following definition: "initial graphic piping plan. It is not a finished document, nor is it a deliverable to a Client. It shows all equipment in a given area to scale and includes major process and utility piping systems, significant valving and instruments. It indicates the exact equipment locations and elevations, nozzles, platform and ladder requirements and any pipe support that affects the design of equipment or structure other disciplines".

1) the Piping and Instrumentation Diagram

2) the Unit Plot Plan

3) the line diagram

4) the Piping layout drawing

5) the Piping General Arrangement drawing

Page 38: Project engineer test   level 3

HERVE BARON

© 2015 – Hervé Baron

Project Engineer knowledge test

Which pumps are inter-changeable, i.e., have standard dimensions

1) the ones designed to API code

2) the ones designed to ANSI code

Page 39: Project engineer test   level 3

HERVE BARON

© 2015 – Hervé Baron

Project Engineer knowledge test

Which pumps are inter-changeable, i.e., have standard dimensions

1) the ones designed to API code

2) the ones designed to ANSI code

Page 40: Project engineer test   level 3

HERVE BARON

© 2015 – Hervé Baron

Project Engineer knowledge test

The process engineer enters the heat exchange area and transfer coefficient in the process simulator as input data. Right or Wrong?

Page 41: Project engineer test   level 3

HERVE BARON

© 2015 – Hervé Baron

Project Engineer knowledge test

The process engineer enters the heat exchange area and transfer coefficient in the process simulator as input data. Right or Wrong. The Process engineer enters the outlet temperature only.

Page 42: Project engineer test   level 3

HERVE BARON

© 2015 – Hervé Baron

Project Engineer knowledge test

That’s all for now folks, but I won’t be long with new tests…

Page 43: Project engineer test   level 3

HERVE BARON

© 2015 – Hervé Baron

The Oil & Gas Engineering Guide - 2nd edition

A unique synthesis for the busy Project professional 270 pages 300 illustrations

Interested and wanting to know more on Engineering?

Page 44: Project engineer test   level 3

HERVE BARON

© 2015 – Hervé Baron

The Oil & Gas Engineering Guide - 2nd edition

Table of Contents

Page 45: Project engineer test   level 3

HERVE BARON

© 2015 – Hervé Baron

The Oil & Gas Engineering Guide - 2nd edition

Discipline presentation: activities and deliverables

Table of Contents

The overall process

Methods & tools

Page 46: Project engineer test   level 3

HERVE BARON

© 2015 – Hervé Baron

The Oil & Gas Engineering Guide - 2nd edition

Table of Contents

Discipline presentation: activities and deliverables

Page 47: Project engineer test   level 3

HERVE BARON

© 2015 – Hervé Baron

The work of each Engineering

discipline is described

Page 48: Project engineer test   level 3

HERVE BARON

© 2015 – Hervé Baron

Design activities are explained, e.g., Plant

Equipment layout

Page 49: Project engineer test   level 3

HERVE BARON

© 2015 – Hervé Baron

Complex activities, such as

QRA, are explained through a practical example.

Page 50: Project engineer test   level 3

HERVE BARON

© 2015 – Hervé Baron

How are materials of

construction selected ?

Page 51: Project engineer test   level 3

HERVE BARON

© 2015 – Hervé Baron

How and when are Piping

Materials ordered?

Page 52: Project engineer test   level 3

HERVE BARON

© 2015 – Hervé Baron

A sample of all common Engineering documents is

included

Page 53: Project engineer test   level 3

HERVE BARON

© 2015 – Hervé Baron

A sample of all common Engineering documents is

included

Use this to specify what you

want to your Engineering supplier !

Page 54: Project engineer test   level 3

HERVE BARON

© 2015 – Hervé Baron

Verify the contents of

engineering documents with check lists.

Page 55: Project engineer test   level 3

HERVE BARON

© 2015 – Hervé Baron

Difference between

Engineering and Shop drawings

Page 56: Project engineer test   level 3

HERVE BARON

© 2015 – Hervé Baron

Understand the main

technical aspects, e.g., DCS vs ESD

Page 57: Project engineer test   level 3

HERVE BARON

© 2015 – Hervé Baron

The common 2 types of

package control

Page 58: Project engineer test   level 3

HERVE BARON

© 2015 – Hervé Baron

The different Plant drainage

systems

Page 59: Project engineer test   level 3

HERVE BARON

© 2015 – Hervé Baron

The dynamic forces to

which an Off-Shore Plant is subject

Page 60: Project engineer test   level 3

HERVE BARON

© 2015 – Hervé Baron

The Oil & Gas Engineering Guide - 2nd edition

Table of Contents

The overall process

Page 61: Project engineer test   level 3

HERVE BARON

© 2015 – Hervé Baron

Use this as standard, question deviations.

Page 62: Project engineer test   level 3

HERVE BARON

© 2015 – Hervé Baron

Understand the new 3D-model centered engineering process

Page 63: Project engineer test   level 3

HERVE BARON

© 2015 – Hervé Baron

Know the interfaces

between disciplines... and with Vendors

Page 64: Project engineer test   level 3

HERVE BARON

© 2015 – Hervé Baron

Understand what drives

the Project schedule

Page 65: Project engineer test   level 3

HERVE BARON

© 2015 – Hervé Baron

The Oil & Gas Engineering Guide - 2nd edition

Table of Contents

Methods & tools

Page 66: Project engineer test   level 3

HERVE BARON

© 2015 – Hervé Baron

Use these methods as

standard, question deviations.

Page 67: Project engineer test   level 3

HERVE BARON

© 2015 – Hervé Baron

Implement powerful

procedures

Page 68: Project engineer test   level 3

HERVE BARON

© 2015 – Hervé Baron

Request meaningful progress

reports

Page 69: Project engineer test   level 3

HERVE BARON

© 2015 – Hervé Baron

Implement effective Project

Control

Page 70: Project engineer test   level 3

HERVE BARON

© 2015 – Hervé Baron

The Oil & Gas Engineering Guide - 2nd edition

This book is destined to both:

Oil & Gas companies Project execution personnel

Oil & Gas contractors Project execution personnel

Date of publication: March, 2015.

Page 71: Project engineer test   level 3

HERVE BARON

© 2015 – Hervé Baron

The Oil & Gas Engineering Guide 2nd edition

If your are on the Client side, i.e., contracting Engineering services, this book will help you to:

Specify to an Engineering supplier what you want: what deliverables and with what contents,

Set a standard in Engineering execution that you and your supplier can adhere to: design stages/gates, methods to be used, etc.

Specify the progress report you want, with the meaningful indicators,

Ask the right questions to assess the true progress,

Page 72: Project engineer test   level 3

HERVE BARON

© 2015 – Hervé Baron

The Oil & Gas Engineering Guide 2nd edition

If your are on the Contractor side, i.e., performing Engineering activities, this book will help you to:

Understand the work of each discipline and the overall picture,

Challenge what one discipline tells you,

Understand the critical areas,

Put in place the right methods to be successful,

Page 73: Project engineer test   level 3

HERVE BARON

© 2015 – Hervé Baron

The Oil & Gas Engineering Guide 2nd edition

Order direct from the publisher:

http://www.editionstechnip.com/en/catalogue-detail/1111/oil-gas-engineering-guide-the.html