PROJECT DELIVERY SYSTEMS
21

PROJECT DELIVERY SYSTEMS. INTRODUCTION OWNER-PROVIDED DELIVERY TRADITIONAL DESIGN BID-BUILD CONSTRUCTION MANAGEMENT DESIGN-BUILD DESIGN-BUILD VARIATIONS.

Dec 21, 2015

Download

Documents

Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: PROJECT DELIVERY SYSTEMS. INTRODUCTION OWNER-PROVIDED DELIVERY TRADITIONAL DESIGN BID-BUILD CONSTRUCTION MANAGEMENT DESIGN-BUILD DESIGN-BUILD VARIATIONS.

PROJECT DELIVERY SYSTEMS

Page 2: PROJECT DELIVERY SYSTEMS. INTRODUCTION OWNER-PROVIDED DELIVERY TRADITIONAL DESIGN BID-BUILD CONSTRUCTION MANAGEMENT DESIGN-BUILD DESIGN-BUILD VARIATIONS.

PROJECT DELIVERY SYSTEMS

• INTRODUCTION

• OWNER-PROVIDED DELIVERY

• TRADITIONAL DESIGN BID-BUILD

• CONSTRUCTION MANAGEMENT

• DESIGN-BUILD

• DESIGN-BUILD VARIATIONS

• FAST TRACKING

Page 3: PROJECT DELIVERY SYSTEMS. INTRODUCTION OWNER-PROVIDED DELIVERY TRADITIONAL DESIGN BID-BUILD CONSTRUCTION MANAGEMENT DESIGN-BUILD DESIGN-BUILD VARIATIONS.

INTRODUCTION

• Owners, designers, and contractors make the decisions, provide the services, and perform the work to deliver constructed projects. These activities are known collectively as project delivery.

• The generic term “project delivery system” describes how the participants are organized to interact, transforming the owner’s project goals and objectives into a finished facility.

Page 4: PROJECT DELIVERY SYSTEMS. INTRODUCTION OWNER-PROVIDED DELIVERY TRADITIONAL DESIGN BID-BUILD CONSTRUCTION MANAGEMENT DESIGN-BUILD DESIGN-BUILD VARIATIONS.

INTRODUCTION (CONT.)

• The owner usually considers the following factors to decide how project resources are to be organized:– Past practices, traditions, and experience;– The advice of consultants;– Funding sources and constraints;– The effective use of staff and working capital;– The interests of other project stakeholders.

Page 5: PROJECT DELIVERY SYSTEMS. INTRODUCTION OWNER-PROVIDED DELIVERY TRADITIONAL DESIGN BID-BUILD CONSTRUCTION MANAGEMENT DESIGN-BUILD DESIGN-BUILD VARIATIONS.

OWNER-PROVIDED DELIVERY

• Mostly applicable to projects where the scope of the work is within the owner’s range of skills, experience, and resources.

• Owners perform some or all of the design services and construction work themselves.

• E.g. simple modifications to an existing facility, projects with limited cost or complexity, repetitive projects.

Page 6: PROJECT DELIVERY SYSTEMS. INTRODUCTION OWNER-PROVIDED DELIVERY TRADITIONAL DESIGN BID-BUILD CONSTRUCTION MANAGEMENT DESIGN-BUILD DESIGN-BUILD VARIATIONS.

TRADITIONAL DESIGN BID-BUILD (DBB)

• For many years, DBB has been the most common method of project delivery for public projects, and for many private projects as well.

• Design Bid-Build is effective on projects – where the owner needs both professional design

services and construction services

– where the designer does not require detailed knowledge of the means and methods of construction.

Page 7: PROJECT DELIVERY SYSTEMS. INTRODUCTION OWNER-PROVIDED DELIVERY TRADITIONAL DESIGN BID-BUILD CONSTRUCTION MANAGEMENT DESIGN-BUILD DESIGN-BUILD VARIATIONS.

TRADITIONAL DBB (cont.)

• DBB provides the owner with a high degree of control. That’s why it is the preferred project delivery system for owners who:– Wish to closely monitor projects

– Are public owners and must account in detail for expenditures.

– Are obligated by statute to procure professional design services by qualifications-based selection (QBS) regulations and constructors by competitive bidding.

Page 8: PROJECT DELIVERY SYSTEMS. INTRODUCTION OWNER-PROVIDED DELIVERY TRADITIONAL DESIGN BID-BUILD CONSTRUCTION MANAGEMENT DESIGN-BUILD DESIGN-BUILD VARIATIONS.

TRADITIONAL DBB (cont.)

• The owner defines project goals and objectives, secures the financing, and specifies the standards and contract terms.

• The owner may perform planning, conceptual design and full design, or may engage an outside design professional (designer) for some or all of these tasks.

• During this planning and preliminary stage, owner and designer work as a team to obtain required permits and conduct necessary site investigations.

Page 9: PROJECT DELIVERY SYSTEMS. INTRODUCTION OWNER-PROVIDED DELIVERY TRADITIONAL DESIGN BID-BUILD CONSTRUCTION MANAGEMENT DESIGN-BUILD DESIGN-BUILD VARIATIONS.

TRADITIONAL DBB (cont.)• The designer prepares the construction bid documents to

reflect the owner’s project goals and objectives, the project’s site conditions, and sound engineering practices.

• Prospective contractors prepare their bids from these complete and specific bid documents.

• The bidders submit their proposals to the owner (often w/ designer) , who determines the most responsive (typically the lowest) bid meeting project requirements.

• In certain circumstances, owner may be justified in selecting a contractor outright and negotiating contract terms directly.

Page 10: PROJECT DELIVERY SYSTEMS. INTRODUCTION OWNER-PROVIDED DELIVERY TRADITIONAL DESIGN BID-BUILD CONSTRUCTION MANAGEMENT DESIGN-BUILD DESIGN-BUILD VARIATIONS.

CONSTRUCTION MANAGEMENT• Many owners engage construction managers

(CMs) to assist in developing bid documents and overseeing project construction.

• CM:– Is a professional or a firm trained in the management of

construction processes.– Is generally interposed between the owner and some or

all of the other participants.

• There are two general types of CM:– Agency Construction Managers (ACM)– Construction managers-at-risk (CM-at-risk)

Page 11: PROJECT DELIVERY SYSTEMS. INTRODUCTION OWNER-PROVIDED DELIVERY TRADITIONAL DESIGN BID-BUILD CONSTRUCTION MANAGEMENT DESIGN-BUILD DESIGN-BUILD VARIATIONS.

CONSTRUCTION MANAGEMENT (cont.)

• ACM acts as an agent of the owner and extends the owner’s internal capabilities in performing traditional owner responsibilities.

• The level of service by the ACM can range from on-call advice to full project management.

• In some cases, the owner hires the ACM before design begins and ACM may participate in the selection of and contracting with the designer or might even be the designer.

Page 12: PROJECT DELIVERY SYSTEMS. INTRODUCTION OWNER-PROVIDED DELIVERY TRADITIONAL DESIGN BID-BUILD CONSTRUCTION MANAGEMENT DESIGN-BUILD DESIGN-BUILD VARIATIONS.

CONSTRUCTION MANAGEMENT (cont.)

• CM-at-risk arrangement increases significantly owner’s delegation of control and risk.

• CM-at-risk typically contracts with the owner in two stages.

• First, CM-at-risk manages and undertakes services during conceptual & preliminary design phases with the design professional.

• When design is complete, owner and CM-at-risk then agree on a price and schedule for the completion of the construction work.

• CM-at-risk is popular for owners of private projects.

Page 13: PROJECT DELIVERY SYSTEMS. INTRODUCTION OWNER-PROVIDED DELIVERY TRADITIONAL DESIGN BID-BUILD CONSTRUCTION MANAGEMENT DESIGN-BUILD DESIGN-BUILD VARIATIONS.

DESIGN-BUILD

• The owner contracts with a single entity to provide the design and to construct the project according to that design.

• The contract might be negotiated with a single design-builder or result from competitive proposals.

• The selection can be based on low price or on a set of value criteria (experience, staff, bonding capacity, etc.).

Page 14: PROJECT DELIVERY SYSTEMS. INTRODUCTION OWNER-PROVIDED DELIVERY TRADITIONAL DESIGN BID-BUILD CONSTRUCTION MANAGEMENT DESIGN-BUILD DESIGN-BUILD VARIATIONS.

DESIGN-BUILD (cont.)• Design-build provides the owner with a single point

of contact for project responsibilities, eliminating the need to assist in resolving designer-contractor disputes.

• With the contractor playing a major role in design, costs are typically defined and maintained to a greater degree, and the coordination of fast-track management to achieve early completion is greatly simplified.

• The design-builder makes many decisions that owner would make under DBB, due to delegation of greatly increased authority.

Page 15: PROJECT DELIVERY SYSTEMS. INTRODUCTION OWNER-PROVIDED DELIVERY TRADITIONAL DESIGN BID-BUILD CONSTRUCTION MANAGEMENT DESIGN-BUILD DESIGN-BUILD VARIATIONS.

DESIGN-BUILD (cont.)• For many owners, delegation of responsibilities leads

to satisfactory projects. However, if the parties are inexperienced and do not cooperate, the transfer of control and risk can be disappointing.

• The owner may need to restructure his/her internal procedures to accommodate design-build approach.

• Compared to DBB, this involves a significantly different set of requirements and expectations for process, timelines and communications.

• A clear understanding and documentation of design-build processes enhances the quality of design-build projects.

Page 16: PROJECT DELIVERY SYSTEMS. INTRODUCTION OWNER-PROVIDED DELIVERY TRADITIONAL DESIGN BID-BUILD CONSTRUCTION MANAGEMENT DESIGN-BUILD DESIGN-BUILD VARIATIONS.

DESIGN-BUILD VARIATIONS

• Funding Option Variations

• Turnkey

• Developer Financed Projects

• Turnkey Variations

Page 17: PROJECT DELIVERY SYSTEMS. INTRODUCTION OWNER-PROVIDED DELIVERY TRADITIONAL DESIGN BID-BUILD CONSTRUCTION MANAGEMENT DESIGN-BUILD DESIGN-BUILD VARIATIONS.

Funding Option Variations

• Private capital and developer participation offer private owners several variations on design-build.

• Lease-develop-operate arrangement: The owner gives a private operator a long-term lease to use, operate, and expand an existing facility.

• Public-private partnership or wrap around: Ownership of or fiduciary responsibility for a project is assigned to a private party. That party designs, builds, and may even own, operate and maintain the new facility.

Page 18: PROJECT DELIVERY SYSTEMS. INTRODUCTION OWNER-PROVIDED DELIVERY TRADITIONAL DESIGN BID-BUILD CONSTRUCTION MANAGEMENT DESIGN-BUILD DESIGN-BUILD VARIATIONS.

Turnkey

• Turnkey adds to the design-builder’s responsibilities the operation and/or maintenance of the completed project.

• Turnkey delivery has the potential for bringing a new project on line more quickly.

• Three forms of turnkey project delivery:– Design-build-operate-transfer– Design-build-operate-maintain– Design-build-own-operate-transfer

Page 19: PROJECT DELIVERY SYSTEMS. INTRODUCTION OWNER-PROVIDED DELIVERY TRADITIONAL DESIGN BID-BUILD CONSTRUCTION MANAGEMENT DESIGN-BUILD DESIGN-BUILD VARIATIONS.

Developer-Financed Projects

• For highly specialized projects and circumstances, financing from a private or public developer or other third parties can offer additional variations on design-build and turnkey project delivery, each with new roles for owners, designers, and contractors.

Page 20: PROJECT DELIVERY SYSTEMS. INTRODUCTION OWNER-PROVIDED DELIVERY TRADITIONAL DESIGN BID-BUILD CONSTRUCTION MANAGEMENT DESIGN-BUILD DESIGN-BUILD VARIATIONS.

Turnkey Variations• Variations on turnkey add financing as a key

component. While financing arrangements are unique for each project, developer financed projects generally resemble one of the turnkey delivery methods:– FDBT (Finance, design, build, transfer)– FDBOT (Finance, design, build, operate, transfer)– FDBOOT (Finance, design, build ,own, operate,

transfer)

• In each case, the transfer of the project occurs only after the developer’s interests and financial obligations have been satisfied.

Page 21: PROJECT DELIVERY SYSTEMS. INTRODUCTION OWNER-PROVIDED DELIVERY TRADITIONAL DESIGN BID-BUILD CONSTRUCTION MANAGEMENT DESIGN-BUILD DESIGN-BUILD VARIATIONS.

FAST-TRACKING• Fast-track approach compresses the schedule by

sequencing the start of construction on underlying project elements (e.g. foundation, basic supporting structures) before final design is complete for interior or adjacent elements.

• Fast-tracking is not a method of delivery, rather, it’s a management strategy within delivery methods.

• While often successful in achieving schedule reductions, problems on fast-track contracts can create a domino effect on follow-on contracts for the project.

• Fast-track is more successful on projects that are straightforward and have a high level of predictability.