Project Cost Project Cost Management Management PMBOK Chapter 7 PMBOK Chapter 7
Nov 08, 2014
Project Cost ManagementProject Cost Management
PMBOK Chapter 7PMBOK Chapter 7
PROCESS GROUPSPROCESS GROUPS
Cost Estimating
Cost Budgeting
Cost Control
I
Planning
E
Controlling
C
Cost EstimatingCost Estimating
Cost estimating and Pricing:Cost estimating and Pricing: Cost estimating: how much will it cost the performing Cost estimating: how much will it cost the performing
organization to provide the product or service organization to provide the product or service involved?involved?
Pricing: how much will the performing organization Pricing: how much will the performing organization charge for the product or service? charge for the product or service? Business decisionBusiness decision..
Estimating should be done by the person doing Estimating should be done by the person doing the work.the work.
Cost EstimatingCost Estimating
Based on the WBS to increase the accuracy.Based on the WBS to increase the accuracy. Project managers should analyze the needs of Project managers should analyze the needs of
the project, to compare and reconcile any the project, to compare and reconcile any differences with cost requirements from differences with cost requirements from management.management.
1. WBS2. Resource
requirements3. Resource rates.4. Act. duration est.5. Historical info.6. Chart of accounts7. Risks
1. Analogous est.2. Parametric
modeling3. Bottom-up est.
1. Cost estimates2. Cost
management plan
Inputs Tools Outputs
Cost EstimatingCost Estimating Cost estimates for all resources that will be Cost estimates for all resources that will be
charged to the project.charged to the project. Generally expressed in units of currency to facilitate Generally expressed in units of currency to facilitate
comparisons both within and across projects.comparisons both within and across projects. Generally includes appropriate risk response planning.Generally includes appropriate risk response planning.
Supporting detail must include:Supporting detail must include: Reference to WBS.Reference to WBS. How it was developed?How it was developed? Assumptions made.Assumptions made. Range of possible results.Range of possible results.
Cost management plan how cost variances will Cost management plan how cost variances will be managed.be managed.
Cost BudgetingCost Budgeting
Allocate the overall cost estimates to individual Allocate the overall cost estimates to individual activities or work packages to establish a cost activities or work packages to establish a cost baseline for measuring project performance.baseline for measuring project performance.
1. Cost estimates2. WBS3. Project schedule4. Cost
management plan
1. Cost budgeting tools and techniques
1. Cost baseline
Inputs Tools Outputs
Cost BudgetingCost Budgeting
The cost baseline will be used to measure and The cost baseline will be used to measure and monitor cost performance of the project.monitor cost performance of the project.
Expected Cash Flow
Cost Baseline
Cumulative Values
Time
Estimates vs. AccuracyEstimates vs. Accuracy
Most difficult to estimate as very Most difficult to estimate as very little project info is availablelittle project info is available
EstimateEstimate AccuracyAccuracy
Order of Order of Magnitude Magnitude (Early)(Early)
-25%-25%
+75%+75%
Budget Budget EstimateEstimate
-10%-10%
+25+25
Definitive Definitive EstimateEstimate
-5%-5%
10%10%
Used to finalize the Request for Used to finalize the Request for Authorization (RFA), and establish Authorization (RFA), and establish commitmentcommitment
Development stage estimate. Development stage estimate. Needed to predict revised project Needed to predict revised project completion datecompletion date
Tools for Estimating (and Tools for Estimating (and Budgeting)Budgeting)
Top Down Top Down EstimatingEstimating
Accuracy depends on experienceAccuracy depends on experienceFast, but estimates are roughFast, but estimates are rough
Bottom Up Bottom Up EstimatingEstimating
Slow, but reliableSlow, but reliableHigh cost (time) / WBS neededHigh cost (time) / WBS neededBuy-in from the teamBuy-in from the team
Parametric Parametric ModelingModeling
Mathematical models to predict costsMathematical models to predict costsTwo types: REGRESSION ANALYSIS, Two types: REGRESSION ANALYSIS,
and LEARNING CURVEand LEARNING CURVE
Delphi Delphi Method Method (analogous)(analogous)
Expert judgmentExpert judgmentTasks need not to be identifiedTasks need not to be identifiedConsiderable experience neededConsiderable experience needed
Cost ControlCost Control
Monitor Cost PerformanceMonitor Cost Performance Detect and understand variances from Detect and understand variances from
plan plan Ensure all changes are recorded and Ensure all changes are recorded and
agreed uponagreed upon Prevent bogus changes from being Prevent bogus changes from being
included in cost baselineincluded in cost baseline Inform stakeholders of authorized changesInform stakeholders of authorized changes Bring costs within acceptable limitsBring costs within acceptable limits
Cost Control Cost Control
Understand what is driving variances, good and Understand what is driving variances, good and bad, and decide what action to take.bad, and decide what action to take.
1. Cost Baseline2. Performance
Reports3. Change Requests4. Cost
Management Plan
1. Cost Change Control System
2. Performance Measurement
3. Earned Value Management
4. Additional Planning
5. Computerized Tools
1. Revised Cost Estimates
2. Budget Updates3. Corrective Action4. Estimate at
Completion5. Project Closeout6. Lessons learned
Inputs Tools Outputs
Cost ControlCost Control
Work completion methods:Work completion methods:• 0/100 0/100 Conservative approach. No work, no Conservative approach. No work, no
money.money.• 20/80 20/80 20% at start of the project, the rest when 20% at start of the project, the rest when
it is completed.it is completed.• 50/50 50/50 Liberal approach. Liberal approach.
Cost Control: Earned Value Cost Control: Earned Value ManagementManagement
Earned Value:
Integrates cost, time and scope. Used to forecast future performance and project completion dates
Key concepts:Key concepts:EV = Earned Value (BCWP)EV = Earned Value (BCWP)
Estimated value of the work actually accomplishedEstimated value of the work actually accomplished
PV = Planned Value (BCWS)PV = Planned Value (BCWS)Estimated value of the work planned to be doneEstimated value of the work planned to be done
AC = Actual Cost (ACWP)AC = Actual Cost (ACWP)Actual cost incurred for the work accomplishedActual cost incurred for the work accomplished
Earned Value ManagementEarned Value Management
BAC = Budget At Completion BAC = Budget At Completion Estimated total cost of the project when doneEstimated total cost of the project when done
EAC = Estimate At Completion EAC = Estimate At Completion Forecast of most likely total project cost based on Forecast of most likely total project cost based on
projectproject performance and risk quantificationperformance and risk quantification
CPI = Cost Performance Index CPI = Cost Performance Index Ratio of budgeted costs to actual costRatio of budgeted costs to actual cost
SPI = Scheduled Performance Index SPI = Scheduled Performance Index Estimated total cost of the project when doneEstimated total cost of the project when done
Earned Value Management Earned Value Management Key Formulas:Key Formulas:
CV = Cost Variance = EV- ACCV = Cost Variance = EV- ACNegativeNegative is over budget, Positive is under budget is over budget, Positive is under budget
SV = Schedule Variance = EV- PVSV = Schedule Variance = EV- PVNegativeNegative is behind schedule, Positive is ahead schedule is behind schedule, Positive is ahead schedule
CPI = Cost Performance Index = EV / ACCPI = Cost Performance Index = EV / AC SPI = Schedule Performance Index = EV / PVSPI = Schedule Performance Index = EV / PV EAC = Estimate At Completion =EAC = Estimate At Completion =
BAC / CPI BAC / CPI Most often used formula Most often used formula AC + ETCAC + ETC AC + BAC - EVAC + BAC - EV AC + (BAC - EV) / CPIAC + (BAC - EV) / CPI
EAC = Estimate At Completion = EAC - ACEAC = Estimate At Completion = EAC - AC VAC = Variance At Completion = BAC - EACVAC = Variance At Completion = BAC - EAC
Cost Types Cost Types
Direct Costs Direct Costs
Related “Directly” to the projectRelated “Directly” to the project
ex. Labor hours, material, equipment, ex. Labor hours, material, equipment, food, travel. . .food, travel. . .
Indirect Costs Indirect Costs
Overhead used for more than one projectOverhead used for more than one project
ex. Building rent, taxes, janitorial ex. Building rent, taxes, janitorial servicesservices
Cost TypesCost Types
A cost by any other name, really isn’t the same!A cost by any other name, really isn’t the same!• Variable Cost – Changes with volume Variable Cost – Changes with volume • Fixed Cost – Stay the same, regardless of volumeFixed Cost – Stay the same, regardless of volume
COSTCOST
Volume Volume
TC = VC+FC
VC
FC
Cost Types Cost Types
Project Costs Project Costs Are incurred while the project is being Are incurred while the project is being
fulfilled.fulfilled.
Life Cycle CostsLife Cycle CostsIncludes the costs after project completion.Includes the costs after project completion.
There may be temptation to lower project costs at There may be temptation to lower project costs at the expense of long term costs. Life Cycle the expense of long term costs. Life Cycle Costing gives the PM a way to consider costs Costing gives the PM a way to consider costs outside of the scope of project fulfillmentoutside of the scope of project fulfillment