Project and Production Management Module 9 Tactical Decisions and Review Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical Engineering, Indian Institute of Technology, Delhi module 9:Tactical Decisions and Review Back to main index exit
143

Project and Production Management

Mar 19, 2016

Download

Documents

Weldon

module 9:Tactical Decisions and Review Back to main index exit continue. Project and Production Management. Module 9 Tactical Decisions and Review. Prof Arun Kanda & Prof S.G. Deshmukh , Department of Mechanical Engineering, Indian Institute of Technology, Delhi. - PowerPoint PPT Presentation
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Project and Production Management

Project and Production Management

Module 9Tactical Decisions and Review

Prof Arun Kanda & Prof S.G. Deshmukh, Department of Mechanical Engineering,Indian Institute of Technology, Delhi

module 9:Tactical Decisions and Review

Back to main index exit continue

Page 2: Project and Production Management

MODULE 9: Tactical Decisions and Review

1.Basic Inventory Principles

2.Inventory Modeling3.Material

Requirements Planning

4.Job shop scheduling

5.Course Summary and Review

6. Illustrative Examples 7. Self Evaluation Quiz 8. Problems for

Practice 9. Further exploration

module 9:Tactical Decisions and Review

Back to main index exit

Page 3: Project and Production Management

1. Basic Inventory Principles

module 9:Tactical Decisions and Review

Back to main index exit back to module contents

Page 4: Project and Production Management

FUNCTIONS OF INVENTORIESInventories are Idle Resources maintained in various forms:

- Raw materials- Purchased & manufactured parts- Subassemblies- Finished productsSince inventories represent a sizable

investment in a logistic system, we must be aware of the functions they perform

module 9:Tactical Decisions and Review

Back to main index exit back to module contents

Page 5: Project and Production Management

FIVE CATEGORIES OF STOCKSPIPELINE stock (in process stock, in transit stock)

CYCLE stocks (batch production owing to - economies of scale - technological requirements)

SEASONAL stocks ( time varying requirements of an item)

SAFETY stocks (supply and demand uncertainties, lead time uncertainties)

Stocks held for OTHER REASONS (- decoupling stages of production - price, quantity discounts, - speculation)

module 9:Tactical Decisions and Review

Back to main index exit back to module contents

Page 6: Project and Production Management

INVENTORY RELATED COSTS • Procurement cost

Cost/order generally fixed (not dependent on order qty)

• Costs associated with existence of inventories

(supply exceeds demand) Cost/unit/unit time i C (i = inventory carrying cost rate)

• Costs associated with stock outs (demand exceeds supply) (cost/unit) (cost/unit/unit time)

module 9:Tactical Decisions and Review

Back to main index exit back to module contents

Page 7: Project and Production Management

PROCUREMENT COSTSProcurement cost Cost of goods

Cost/order generally fixed Ordering cost(not dependent on order qty)

- Administrative component - Handling - Transportation - Inspection of arrivals

module 9:Tactical Decisions and Review

Back to main index exit back to module contents

Page 8: Project and Production Management

INVENTORY HOLDING COSTS

Costs associated with existence of inventories (supply exceeds demand) Cost/unit/unit time i C (i = inventory carrying cost rate)

- Storage and handling - Interest on tied up capital - Property taxes - Insurance - Spoilage - Obsolescence - Pilferage

module 9:Tactical Decisions and Review

Back to main index exit back to module contents

Page 9: Project and Production Management

SHORTAGE COSTSCosts associated with stock outs

(demand exceeds supply) (cost/unit) (cost/unit/unit time)

- Additional costs of special order - Backorder, if possible - Loss of customer goodwill - Lost sales

module 9:Tactical Decisions and Review

Back to main index exit back to module contents

Page 10: Project and Production Management

SELECTIVE INVENTORY CONTROL

In a large number there are

Typical organisations deal with a large variety of stocked items

PARETO’s Law

(10,000 – 100,000 …is not uncommon)Depending on rankings of• VALUE ((Annual demand X unit price)) ABC Analysis

(Always Better Control)• CRITICALITY (Vital, Essential, Desirable) VED Analysis

• USAGE FREQUENCY FSN Analysis(Fast moving, Slow moving, Non moving)

Based on product characteristics, suitable policies can be chosen

USAGE FREQUENCY

significant few insignificant many

A B C

NS

F

VED

module 9:Tactical Decisions and Review

Back to main index exit back to module contents

Page 11: Project and Production Management

ABC ANALYSIS

5-10% items account for about 75% value15-20% items account for about 15% valueBalance items account for about 10% value (or A class ≥ 6 items average annual usage C class ≤ 0.5 items average annual usage B in between)

Where, Average Annual usage= ofitemsoTotayeartialTotalMater

.ln/cos

25

50

75

90100

25 50 75 10010

Percent of number of inventory items

A

B

C

Perc

ent o

f ave

rage

inve

ntor

y in

vest

men

t

module 9:Tactical Decisions and Review

Back to main index exit back to module contents

Page 12: Project and Production Management

OBJECTIVE OF ABC ANALYSIS:Rationalization of Ordering Policies

EQUAL TREATMENT TO ALLItem no. Annual Consumption

Value (Rs.)Number of

OrdersValue per order Average inventory

123

60,000 4,000 1,000

444

15,000 1,000 250

7500 500 125

Total Inventory: Rs. 8125

PREFERENTIAL TREATMENT on basis of ABC analysis123

60,000 4,000 1,000

831

7,5001,3331,000

3750 667 500

Total Inventory Rs 4917

The optimum no of orders can be arrived at by using models of inventory control eg. EOQ

Q* =icdo2

time

inve

ntor

y

Ann

ual c

ost

Q*

Total cost

carriage

ordering

Page 13: Project and Production Management

DETERMINATION OF REORDER POINTReorder point = Max. reasonable demand during lead time

= expected demand during lead time + safety stock

(usually pre specified by management)

K= 0; risk of shortage = 50% service level = 50%K= 0; risk of shortage = 15.87% service level = 84.13% K= 0; risk of shortage = 2.28% service level = 97.72% K= 0; risk of shortage = 0.13% service level = 99.87%

Higher safety stockA class items have relatively low service levels (0.8 or so)

- Lower safety stocks- Tighter control & efficient expediting

B class items handled routinely with service levels of 0.95 or so

C class items should be present in ample supply, minimum records, controls, procedure very high service levels (0.95 to 0.98)

Prob. of stockout

Total demand in lead timexL + kLxL

kL

module 9:Tactical Decisions and Review

Back to main index exit back to module contents

Page 14: Project and Production Management

POLICY IMPLICATIONS OF SELECTIVE INVENTORY CONTROL

ABC analysisA class items need continuous rigourous control

(use of mathematical models justified)B class items – relaxed control (periodic review)C class items – simple rules of thumb

V class items call for a high level of serviceE class items call for medium level of serviceD class items call for tolerable level of servicejointly determine service levels

FSN analysisFast most inventory models apply to this classSlow ( spare parts etc)Non – moving (dead stock) (optimal stock disposal rules)

VED analysis

% riskOf shortage

(min)

(max)

ABC

VED

module 9:Tactical Decisions and Review

Back to main index exit back to module contents

Page 15: Project and Production Management

A SAMPLE SET OF SERVICE LEVELS FORDIFFERENT CATEGORIES OF ITEMS

V E DA 0.80 0.75 0.6B 0.95 0.90 0.85C 0.99 0.97 0.95

V E DA 0.7 0.6 0.5B 0.9 0.8 0.7C 0.95 0.9 0.85

High cost ofstockout

Low cost ofstockout

decr

easi

ngde

crea

sing

decreasing

decreasing

module 9:Tactical Decisions and Review

Back to main index exit back to module contents

Page 16: Project and Production Management

OBJECTIVE OF INVENTORY MANAGEMENT SYSTEM

An inventory system consists of a set of rules and procedures that allow

for routine decisions on when & how much to order of each item needed

in the manufacturing or procurement process,

which call attention to the non-routine situations, the rules do not cover &

which provide managers with the necessary information to make these

decisions effectively.

The objective of a well designed procedure should be the minimization

of the costs incurred in the inventory system, attaining at the same time

the customer service level specified by the company policies.

1

2

3

module 9:Tactical Decisions and Review

Back to main index exit back to module contents

Page 17: Project and Production Management

STRUCTURE OF A TYPICAL COMPUTERISED

INVENTORY MANAGEMENT SYSTEM

Basic sub systems or modules:-• Transactions and file maintenance module

• Decision rules module

• System integrative module

• System-management interaction and evaluation module

module 9:Tactical Decisions and Review

Back to main index exit back to module contents

Page 18: Project and Production Management

TRANSACTIONS ANDFILE MAINTENANCE MODULE

Book keeping of inventory control – Entry, auditing, control and processing of inventory transactions

NECESSITY: Continuous updating to provide accurate information on -Available stock (on hand and on order)-Customer order status-Cost of items-Delivery lead times-Source of acquisition-Ordering restrictions- …

DEVELOPMENT: mainly the area of data processing.

module 9:Tactical Decisions and Review

Back to main index exit back to module contents

Page 19: Project and Production Management

THE DECISION RULES MODULEThis is concerned with the fundamental components of inventory planning and control procedures aimed at answering when and how much to order of each item to maintain inventories at the right level.

A forward looking system should include forecasting capabilities safety stocks (to account for unavoidable in accuracies) decision rules are needed to guarantee some desired level of customer service.

EOQ, q* =icdo2

Use EOQ and continuous monitoring

Order in lots of 3 months demand if stock at hand is less than ROP

Order in lots of 6 months demand if stock on hand is less than ROP

A-class C-classB-class

ITEM

module 9:Tactical Decisions and Review

Back to main index exit back to module contents

Page 20: Project and Production Management

SYSTEM INTEGRATIVE MODULE

The various items being controlled, depending on their

inherent characteristics require specific degree of

management attention and service levels that can be

achieved by using some appropriate stock policy

Decision rules Distinct inventory policies

module 9:Tactical Decisions and Review

Back to main index exit back to module contents

Page 21: Project and Production Management

SYSTEM MANAGEMENT INTERACTION AND EVALUATION MODULE

Intended to provide management with such information as to permit evaluation Evaluation of operating performance Identify problem areasAllow for management selection of policy

variables (system parameters)

module 9:Tactical Decisions and Review

Back to main index exit back to module contents

Page 22: Project and Production Management

SUMMARY & CONCLUSIONS

- Omnipresence of inventories (‘necessary evil’)

- Nature of inventory related costs

- Principles of selective inventory management

ABC analysis

VED analysis

FSN analysis

- Ordering rules and reorder point determination

- Policy implications of selective inventory management

- Features of a computerized inventory management system

- Relevance ? – independent vs. dependent demand systems

- MRP vs. conventional inventory management

module 9:Tactical Decisions and Review

Back to main index exit back to module contents

Page 23: Project and Production Management

2. Inventory Modelling

module 9:Tactical Decisions and Review

Back to main index exit back to module contents

Page 24: Project and Production Management

LOT SIZING- When to order ?- How much to order ?

Decision variables are Order quantity, q per lot Maximum backorder level, b (in class III, IV)

Reorder point

Lead time

Order qty., q

NO

BA

CK

LOG

GIN

GPURCHASE

Inv.

I

module 9:Tactical Decisions and Review

Back to main index exit back to module contents

Page 25: Project and Production Management

PRODUCTION

q

Inv.

II

LOT SIZING- When to order ?- How much to order ?

Decision variables are Order quantity, q per lot Maximum backorder level, b (in class III, IV)

module 9:Tactical Decisions and Review

Back to main index exit back to module contents

Page 26: Project and Production Management

LOT SIZING- When to order ?- How much to order ?

Decision variables are Order quantity, q per lot Maximum backorder level, b (in class III, IV)

q

bBA

CK

LOG

GIN

GInv.

III

module 9:Tactical Decisions and Review

Back to main index exit back to module contents

Page 27: Project and Production Management

LOT SIZING- When to order ?- How much to order ?

Decision variables are Order quantity, q per lot Maximum backorder level, b (in class III, IV)

b

Inv.

IV

module 9:Tactical Decisions and Review

Back to main index exit back to module contents

Page 28: Project and Production Management

ANALYSIS

BROAD APPRAOCH(1) Identify the cost components in each cycle (of length t)

(2) Express costs in terms of decisions variables (order qty, q and backorder level, b)

(3) Develop annual cost by multiplying (1) by number of cycles/year

(4) Optimize to find q*, b*

Carrying cost Shortage cost Set up or order cost

module 9:Tactical Decisions and Review

Back to main index exit back to module contents

Page 29: Project and Production Management

VARIATIONS IN THE LOT-SIZE FORMULE

WITHOUT BACKLOGGING

021

3 *b,

CdC*q

C = unit cost (Rs/piece)C1 = i X C = carrying cost (Rs/unit/time)C2 = shortage/backlogging cost (Rs/unit/time)C3 = order cost (Rs/order)

module 9:Tactical Decisions and Review

Back to main index exit back to module contents

Page 30: Project and Production Management

VARIATIONS IN THE LOT-SIZE FORMULE

C = unit cost (Rs/piece)C1 = i X C = carrying cost (Rs/unit/time)C2 = shortage/backlogging cost (Rs/unit/time)C3 = order cost (Rs/order)

012

1

3

*b,)p/d(C

dC*q

module 9:Tactical Decisions and Review

Back to main index exit back to module contents

Page 31: Project and Production Management

VARIATIONS IN THE LOT-SIZE FORMULE

C = unit cost (Rs/piece)C1 = i X C = carrying cost (Rs/unit/time)C2 = shortage/backlogging cost (Rs/unit/time)C3 = order cost (Rs/order)

b

WITH BACKLOGGING

2

21

1

32C

CCC

dC*q

21

1

CC*qC*b

module 9:Tactical Decisions and Review

Back to main index exit back to module contents

Page 32: Project and Production Management

VARIATIONS IN THE LOT-SIZE FORMULE

C = unit cost (Rs/piece)C1 = i X C = carrying cost (Rs/unit/time)C2 = shortage/backlogging cost (Rs/unit/time)C3 = order cost (Rs/order)

b

2

21

1

3

12

CCC

)p/d(CdC*q

21

1 1CC

)p/d(*qC*b

module 9:Tactical Decisions and Review

Back to main index exit back to module contents

Page 33: Project and Production Management

1. Demand fixed at constant rate of d units/unit time

2. Replenishments made when inventory reaches zero level so that no shortages occur.

3. Fixed lot size q.

4. Infinite replenishment rate

5. Lead time is known

6. The unit carrying cost, c, is constant Rs/unit/unit time.

7. The replenishment cost, C3 is constant Rs/Order.

ASSUMPTIONS inCLASSICAL LOT-SIZE SYSTEM

module 9:Tactical Decisions and Review

Back to main index exit back to module contents

Page 34: Project and Production Management

SENSITIVITY STUDIES ON CLASSICAL LOT-SIZE MODEL

AN

NU

AL

CO

STS

LOT SIZE qq1

q*

q2

TC

TCmin

Total costCarrying cost

Order cost

221 iCqqC

qdC3

q

Inv.Level

Avg

. Inv

ento

ry =

q/2

qdCqC)q(K 31

2

1

32CdC*q

312 CdCTCmin

Sensitivity Q = bq*, b > 0

b 0.5 0.8 0.9 1.0 1.1 1.2 1.5 2.0TC/TCmin 1.250 1.025 1.006 1.000 1.005 1.017 1.083 1.29

bb)b(

TCTC

bmin 21

21 2

1

module 9:Tactical Decisions and Review

Back to main index exit back to module contents

Page 35: Project and Production Management

EOQ WITH QUANTITY DISCOUNTS

Total annual cost = dCCqdqC 31

2Annual usage

ExampleAnnual demand = 5000 partsOrder cost = Rs 49Inventory carrying cost = Re 1 per part/year

7001

4950002 )(EOQ

Discount scheduleOrder quantity Unit cost/part

0 – 9991000 – 24992500 – over

Rs 5Rs 4.85Rs 4.75

module 9:Tactical Decisions and Review

Back to main index exit back to module contents

Page 36: Project and Production Management

TOTAL ANNUAL COSTS for THREE ORDERING POLICIESORDER

QTY.ANNUAL HOLDING

COSTANNUAL

ORDER COSTPURCHASE

COSTTOTAL

70010002500

350 5001250

350245 98

25,00024,25023,750

25,70024,99525,098

OPERATING AT A LOT-SIZE of 1000 rather than EOQ of 700 is WARRANTED HERE

ANNUALCOSTS

q700 2500

25,700

TAC(Rs 5)

1000

TAC(Rs 4.85)

TAC(Rs 4.75)

25,098

24,995

module 9:Tactical Decisions and Review

Back to main index exit back to module contents

Page 37: Project and Production Management

AN EXAMPLE ILLUSTRATING SHIFT OF EOQs

991Quantity

100 and over2Rs

tcosUnit

Re 1

D = 250/yrC3 = Rs 5/orderi = 20%

79220

525022 )(.XX)Rs(EOQ 112

120525021

)(.XX)Rs(EOQ

IN THIS CASE A LOT SIZE OF 112 RESULTS IN MINIMUM COST

ANNUALCOSTS

qEOQ=79 112100

module 9:Tactical Decisions and Review

Back to main index exit back to module contents

Page 38: Project and Production Management

DETERMINISTIC SINGLE ITEM MODEL

NOTATIONd = demand rate (units per unit time)P = production rate (unit per unit time)Q = order/production quantityT = cycle lengthB = maximum backorder level permittedImax = maximum on-hand inventory levelC = unit item costC1 = inventory carrying cost in Rs/unit/unit time = iCC2 = shortage cost in Rs/unit/unit time (back logged demand)C2 = shortage cost/unit short independent of time (lost sales)C3 = set up cost per order/batch

t1 t2

tp

t3 t4

t

Imax

0

-b

Rate of fall, dRate of rise p-d

module 9:Tactical Decisions and Review

Back to main index exit back to module contents

Page 39: Project and Production Management

Cycle time t = q/d

Time to produce a lot, tp = q/p max. inventory, Imax =

t1 = time for backorder b to be cleared once production starts

t2 = time for inventory level to build up from zero to Imax

t3 = time for inventory level to drop to zero from Imax at constant demand, d

t4 = time for backlog b to buildup at a demand rate, d

dpb

dpImax

db

dImax

b)dp(pq b)

pd(q 1

module 9:Tactical Decisions and Review

Back to main index exit back to module contents

Page 40: Project and Production Management

COSTS/CYCLE

During (t2 + t3) there is inventory andcarrying costs = ½ Imax (t2 + t3) c1

During ( t1 + t4) there is shortage cost = ½ b (t1 + t4) C2 + C’2 b

Ordering / replenishment cost per cycle = C3

Notice that

)dp(dpb

ddpb)tt(

1141

)dp(dpI

ddpI)tt( axmaxm

11

32

bpdqI& axm

1

t1 t2 t3 t4

module 9:Tactical Decisions and Review

Back to main index exit back to module contents

Page 41: Project and Production Management

AVERAGE ANNUAL COSTS K (q, b)

K (b, q) = t

Ctb'C

tttbC

tttIC axm 3

241

232

122

Substituting for t, (t1 + t4), (t2 + t3) & Imax in terms of q, b we obtain

K (b, q) = qdC

qbd'C

)p/d(qbC

)p/d(qb)p/d(qC 32

221

12121 2

module 9:Tactical Decisions and Review

Back to main index exit back to module contents

Page 42: Project and Production Management

OPTIMAL RESULTSAnnual cost is K (b, q)

The solution of these simultaneous equations yields the optimum values q* and b* as follows:

0

bK

qK

2

21

2111

3

)()/1(2*

)'( 22

CCC

CCCpdCdCq

dC

21

21 1CC

)p/d)(d'C*qC(*b

and

module 9:Tactical Decisions and Review

Back to main index exit back to module contents

Page 43: Project and Production Management

FAST vs SLOW MOVING ITEMSSlow moving items• Low level of demand• Frequent periods of no usage

Likely to be between 50-100 units/yr

Peterson & Silver (1979) recommend classifying items according to demand over the replenishment lead time:

An expected lead time demand of 10 units or larger puts the item in the fast mover’s class, while an expected lead time demand of less than 10 units defines a slow mover

Thresholds difficult to define [ depend on item nature]

module 9:Tactical Decisions and Review

Back to main index exit back to module contents

Page 44: Project and Production Management

CONTINUOUS (PERPETUAL) REVIEW SYSTEM WITH REPLENISHMENT ORDER QTY. Q AND REORDER LEVEL R

Amt. of inventory on hand

Reorder level, R

Safety stock (s s)

Avg. lead time usage (U)

Amt. used during Lead time

Amt. of inventory on hand

Amt. of inventory on hand

Amt. of inventory on handAmt. of inventory on hand

Amt. of inventory on hand

Amt. of inventory on hand

U1 U2 U3

Q

LT1

LT2

LT3

QOrder qty, Q

Time

module 9:Tactical Decisions and Review

Back to main index exit back to module contents

Page 45: Project and Production Management

COMPUTATIONS FOR RU = Lead time demandLT = Lead time (working days)D = daily demand

Z is obtained from the NORMAL TABLES based on

• A pre specified stockout probability, P

• Optimal stockout frequency based on costs of shortage and carrying inventory

LT__

d_

U_

2)d_

)(VarLT(LT__

)Vard()U(Var

)U(Varu

uZUR

)u,U(N 2

Z Probability of stockout

either

or

module 9:Tactical Decisions and Review

Back to main index exit back to module contents

Page 46: Project and Production Management

EXAMPLE (p305, ch. 10)Per unit holding cost = Re 1/yrOrdering policy : 4 times a yrPre specified service level : 1 stockout/3 yrs

SQ/yr = 0.33

LEAD Times from SUPPLIER

Orderplaced

1/7 2/3 3/16 4/6 5/2 6/2

Order received 1/18 2/21 4/20 4/28 5/20 6/23

Lead timesCalendar daysWorking days

117

1812

3525

2216

1814

2115

Month/day

module 9:Tactical Decisions and Review

Back to main index exit back to module contents

Page 47: Project and Production Management

Similar data on demands for last six months yield

EXAMPLE (p305, ch. 10)

d = 40 units/day

Var (d) = 30 (units/day)2

LT = 7 + 12 +25 + 16 + 14 + 156

= 14.83 days

Var (LT) = (7 – 14.83)2 + (12 – 14.83)2 + …6 -1

= 34.97 (day)2

(contd.)

module 9:Tactical Decisions and Review

Back to main index exit back to module contents

Page 48: Project and Production Management

EXAMPLE (contd.)

3975640 29734831430 ,)().().)(()U(Var

08304330 ..

nyr/SO

3593831440 .).)((U Units demanded per lead time

523739756 .,u Units per lead time

Desired SO/yr = 0.33 (as stated earlier)

P = desired probability of stockout per order cycle

From tables Z = 1.39

SS = 1.39 (237.5) = 330.1

R = 593.3 + 330.1 = 923.4

Z

0.083

Order cycles/yr = 4 (given) = n

module 9:Tactical Decisions and Review

Back to main index exit back to module contents

Page 49: Project and Production Management

IMPROVING RELIABILITY OF LEAD TIME

Safety stock = 1.39 (21.09) = 29 ( compared to 330 earlier) R = 622 (compared to 923 earlier)

Inventory lowered by 301 units Annul savings = Rs 1 X 301 = Rs 301

Thus it is worthwhile to improve reliability of lead time

If var (LT) = 0Then var (U) = 30 X 14.83 = 444.9

u = 444.9 = 21.09 units per lead time

(compared to the original 237.5)

module 9:Tactical Decisions and Review

Back to main index exit back to module contents

Page 50: Project and Production Management

OPTIMAL STOCKOUT FREQUENCY AND IMPLIED BACKORDER COSTS

Cost of shortage X Optimal SO/yr = Inventory carrying costShortage cost = Rs 10

Z = 1.96 (from normal tables)

R* = 593.3 + 1.96(237.5) = 593.3 + 465.5 = 1058.8For R = 926

SO/yr = C1/shortage cost0.33 = 1/shortage costCB = 1/0.33 = Rs 3 (implied shortage cost)

optimal SO/yr = 1/10 = 0.10

P* = SO/yr = 0.01 = 0.025n 4

module 9:Tactical Decisions and Review

Back to main index exit back to module contents

Page 51: Project and Production Management

INVENTORY CONTROL POLICIESCONTINUOUS REVIEW SYSTEMS

• (S, Q) policy – when available inventory reaches level s, order Q • (s, S) policy – when available inventory becomes equal to or less

than s, order upto level S

PERIODIC REVIEW SYSTEMS• (nQ, s, R) policy – If at a review time the available inv. < s, an amt. nQ is ordered (n=1,2,3) n is such that after the order is placed, the avail. Inv. Reaches a level

in (s, s+Q)• (S, R) policy – At each review time a sufficient qty. is ordered

to bring the level of ave. inv. upto S.• (s, S, R) policy – If at a review time, the available inv. < s a

sufficient qty. is ordered to bring level upto S, otherwise no order is placed

Available inventory = inventory on hand + amount on order - Units back ordered

module 9:Tactical Decisions and Review

Back to main index exit back to module contents

Page 52: Project and Production Management

Lead time

Reorder point

Avg.Lead time consumption

Reserve stock

Safety stock

Demand uncertainties

Lead time uncertainties

Stoc

k

Avg. demand for maximum delay

Probability of delay

a) Avg. demand during avg. lead time (buffer)

b) Variations in demand during avg. lead time, depending on service level (reserve stock)

a) Avg. demand during delivery delays (safety stock)

)LXD(

)kx( LD

module 9:Tactical Decisions and Review

Back to main index exit back to module contents

Page 53: Project and Production Management

EXAMPLEFor the following data work out the costs under both• A continuous review, fixed order qty (Q system)• A periodic review, variable order qty (P system)• Avg. annual demand = 20,000 units• Std. deviation of demand per week = 50 units• Unit price = Rs 10• Ordering cost = Rs 100• Inventory carrying cost rate = 20%• Avg. lead time = 4 weeks• Max. delay = 3 week• Probability of delay = 0.31• Service level = 95% (prob. Of stockout during lead

time = 5%)

module 9:Tactical Decisions and Review

Back to main index exit back to module contents

Page 54: Project and Production Management

Q systemunits 1414

x).(x,x qty Order

1020100000202

Safety Reserve Buffer point reorder

units 1540 4 x 52

20,000 time lead during demand avg. Buffer

time lead during demand of deviation std. x k stock Reserve units 164 50) x 4( 1.64

delay of yprobabilit x delay max during demand Avg. stock Safety

units .x.x)3 x 20,000( 358310115431052

units 2062 358 164 1540 point Reorder

time

S2062

Stock level

Q = 1414

Lead time = 4 weeks1.64

Mean,

0.95

module 9:Tactical Decisions and Review

Back to main index exit back to module contents

Page 55: Project and Production Management

P system

wks.3.7 weeks52 x,

years,Demand

EOQ periodReview 00020

141400020

1414

Can be rounded off to either 3 or 4 weeks depending on cost consideration

3 weeks1733 Rs 100 Rs x

352 cost ordering Annual

1,154 Rs .xxx17.3320,000 cost carrying inventory Annual 20010

21

Total inv. Cost = 1733 + 1154 = Rs 2887

module 9:Tactical Decisions and Review

Back to main index exit back to module contents

Page 56: Project and Production Management

4 weeks1300 Rs 100 x

452 cost ordering Annual

1,154 Rs .xxx13

20,000 cost carrying inventory Annual 2001021

Total inv. Cost = 1300 + 1154 = Rs 2840

Review period is 4 weeks

Desired inventory level = Buffer + Reserve + safety = 3668

units 3080 8 x52

20,000 Buffer

units 230 1.64 x 50 x 8 Reserve

units 350 0.31 x 3 x )(20,000/52 Safety

P system module 9:Tactical Decisions and Review

Back to main index exit back to module contents

Page 57: Project and Production Management

SAFETY STOCK DETERMINATIONIssues

1) What is the optimal level of protection ?How often do we tolerate running out of stock ?

Tradeoff between holding costs & shortages

2) What reorder level should we set to achieve to achieve this theoretically optimal protection ?

Practical question answered through statistics.

Chosen reorder level

Distribution of lead time demand

Prob. Of stockout

module 9:Tactical Decisions and Review

Back to main index exit back to module contents

Page 58: Project and Production Management

SUMMARYThe EOQ formula with sensitivity analysis was discussedMany variations of the lot size formula with and without backlogging for purchase and production situations were consideredQuantity discounts were exploredThe P & Q policies for inventory control were comparedSafety stock determination in inventory systems was considered

module 9:Tactical Decisions and Review

Back to main index exit back to module contents

Page 59: Project and Production Management

3. Material Requirements Planning

module 9:Tactical Decisions and Review

Back to main index exit back to module contents

Page 60: Project and Production Management

WHAT MRP DOES ?

•Dependent demand•lumpy

MRP

DETAILED SCHEDULE FOR RAW MATERIALS &

COMPONENTS

USED IN THE END PRODUCTS

MASTER SCHEDULE

FOR END ITEMS

module 9:Tactical Decisions and Review

Back to main index exit back to module contents

Page 61: Project and Production Management

Independent Demand:

• Demand unrelated to demand of other products (end products, spare parts)

• Usually forecast• Conventional inventory control (EOQ,

Wagner/Whitin) applicable.

INDEPENDENT VS DEPENDENT DEMAND

module 9:Tactical Decisions and Review

Back to main index exit back to module contents

Page 62: Project and Production Management

.Dependent Demand:Demand directly related to demand of some

other product (components, raw materials, subassemblies)

• Requirements derived from delivery schedule of end items.

• MRP is the appropriate tool for planning & control of manufacture inventories raw materialsWIPComponent partsSubassemblies

INDEPENDENT VS DEPENDENT DEMAND

module 9:Tactical Decisions and Review

Back to main index exit back to module contents

Page 63: Project and Production Management

LUMPY DEMANDCONTINUOUS DEMANDAssumed in economic lot size formula

LUMPY DEMANDTYPICAL OF MRP APPLICATIONS(raw materials, components sub-assemblies consumed in Large increments corresponding to a certain batch of final product)

TIME

Avg.rate ofdemand

Inv.LEVEL

TIME

Inv.LEVEL t1 t2 t3 t4 t5 t6

module 9:Tactical Decisions and Review

Back to main index exit back to module contents

Page 64: Project and Production Management

LEAD TIMES

In MRP, lead times are used to determine starting dates for assembling final products and subassemblies, for producing

component parts, and for ordering raw materials.

Ordering Lead Time:(for purchased parts)

Initiation of purchase requisition

Receipt of item from vendor(off shelf / fabricate)

Manufacturing Lead Time:

Place order Item deliveredProcess part through sequence of machines as given on route sheet (operation + non-productive times)

module 9:Tactical Decisions and Review

Back to main index exit back to module contents

Page 65: Project and Production Management

• The master production schedule and other

order data.

• The bill of materials file. (The product

structure)

• The inventory record file.

INPUTS TO MRP module 9:Tactical Decisions and Review

Back to main index exit back to module contents

Page 66: Project and Production Management

COMMON USE ITEMS

MRP collects the common use items from different products to effect economics in ordering the raw materials and manufacturing the components/sub assemblies

C1 C2 C3 Cn

P1 P2 P3 PN

BASIC RAW MATERIAL

COMPONENTS

PRODUCTS

module 9:Tactical Decisions and Review

Back to main index exit back to module contents

Page 67: Project and Production Management

STRUCTURE OF AN MRP SYSTEM

Gross &Net requirementsreport

Capacity vsLoad report

Shop floorPlanningreport

Production OrderStatus & exceptionsreport

ServiceParts

requirements

Salesforecasts

Customerorders

Inventorytransactions

MasterProductionschedule

Engg.changes

InventoryRecord

file

MRPPROCESSOR

Bill ofMaterials

file

OUT PUTREPORTS

Back to main index exit back to module contents

Page 68: Project and Production Management

MASTER PRODUCTION SCHEDULE

(a) What end products are to be produced?

(b) How many of each product to be produced?

(c) When the products are to be ready for shipment?

TYPICAL INFORMATION IN MPS:

DEMANDOften excluded from MPS, since it does not include

end product demand.

Demand for individual component Parts (for repair and service)

Firms customer orders

Forecasted demand

Week no 6 7 8 9 10Product P1 50 100

Product P2 70 80 25

Etc.

module 9:Tactical Decisions and Review

Back to main index exit back to module contents

Page 69: Project and Production Management

BILL OF MATERIALS (BOM) FILE

C1 C2 C3 C4 C5 C6

S1 S2

P1

(1) (2)

(1) (4) (1) (2) (2) (1)

Level 0(product)

Level 1(sub-assemblies)

Level 2(raw materials)

Sub assembly S1 is the PARENT of components C1, C2 & C3. Any engg. Changes affecting product

structure must be fed to BOM file.

module 9:Tactical Decisions and Review

Back to main index exit back to module contents

Page 70: Project and Production Management

• Accurate current data on inventory status

• Generally computerized (item master file)

• Lead times must be established in inventory

Record file

INVENTORY RECORD FILE

• INVENTORY TRANSACTIONS (issue, arrivals, order placement/realization) MUST BE KEPT CURRENT

OrderingLead time

ManufacturingLead time

Purchasingrecords

ProcessRoutesheets

module 9:Tactical Decisions and Review

Back to main index exit back to module contents

Page 71: Project and Production Management

INPUTS FOR MRP EXAMPLE

C1 C2 C3 C4 C5 C6

S1 S2

P1

(1) (2)

(1) (4) (1) (2) (2) (1)C4 C6 C7 C2 C8

S3 S4

P2

(1) (1)

(1) (4) (2) (2) (1)M4

PRODUCT STRUCTURE FOR PRODUCTS P1 & P2

MasterProductionSchedule

Initial inventory status for M4

Assembly Manufacturing Ordering

P1 = 1P2 = 1S2 = 1S3 = 1

C4 = 2 M4 = 3

Lead times (in weeks)

258070P2

10050P1

109876Week

PLANNED ORDER RELEASESNET REQUIREMENTS

90ON HAND40SCHEDULED RECEIPTS

GROSS REQUIREMENTSITEM RAW MATERIAL M4

654321PERIOD

50

Page 72: Project and Production Management

BASIC MRP LOGICInput MPS, BOM, Inventory Status, Lead timesDo Parts ExplosionOffset requirements by lead timesNetting of requirements from Gross by considering availabilitiesLot sizing of net requirements for procurement or production

module 9:Tactical Decisions and Review

Back to main index exit back to module contents

Page 73: Project and Production Management

PERIOD 1 2 3 4 5 6 7 8 9 10

ITEM PRODUCT P150 100GROSS REQUIREMENTS

SCHEDULED RECEIPTS

ON HAND 0

NET REQUIREMENTS 50 100

PLANNED ORDER RELEASES 50 100

ITEM PRODUCT P270 80 25GROSS REQUIREMENTS

SCHEDULED RECEIPTS

ON HAND 0

NET REQUIREMENTS 70 80 25

PLANNED ORDER RELEASES 70 80 25

module 9:Tactical Decisions and Review

Back to main index exit back to module contents

Page 74: Project and Production Management

PERIOD 1 2 3 4 5 6 7 8 9 10

ITEM SUB ASSEMBLY S2100 200GROSS REQUIREMENTS

SCHEDULED RECEIPTS

ON HAND

NET REQUIREMENTS 100 200

PLANNED ORDER RELEASES 100 200

ITEM SUB ASSEMBLY S370 80 25GROSS REQUIREMENTS

SCHEDULED RECEIPTS

ON HAND

NET REQUIREMENTS 70 80 25

PLANNED ORDER RELEASES 70 80 25

module 9:Tactical Decisions and Review

Back to main index exit back to module contents

Page 75: Project and Production Management

PERIOD 1 2 3 4 5 6 7 8 9 10

ITEM COMPONENT C470 280 25 400GROSS REQUIREMENTS

SCHEDULED RECEIPTS

ON HAND

NET REQUIREMENTS 70 280 25 400

PLANNED ORDER RELEASES 70 280 25 400

ITEM RAW MATERIAL M470 280 25 400GROSS REQUIREMENTS

SCHEDULED RECEIPTS 40

ON HAND 50 90 20

NET REQUIREMENTS -20 260 25 400

PLANNED ORDER RELEASES 260 25 400

module 9:Tactical Decisions and Review

Back to main index exit back to module contents

Page 76: Project and Production Management

1. Order release notice, to place orders that have been

planned by the MRP system

2. Reports showing planned orders to be released in future

periods.

3. Rescheduling notices, indicating changes in due dates for

open orders.

4. Cancellation notices, including cancellation of open orders

because of changes in the master schedule

5. Reports on inventory status.

MRP OUTPUT REPORTSPrimary Outputs:

module 9:Tactical Decisions and Review

Back to main index exit back to module contents

Page 77: Project and Production Management

1. Performance reports of various types – costs, item usage,

actual vs planned lead times and other measures of

performance.

2. Exceptions reports showing – deviations from schedule,

overdue orders, scrap, and so on.

3. Inventory forecasts indicating projected inventory levels

(both aggregate inventory as well as item inventory) in

future periods.

MRP OUTPUT REPORTSSecondary Outputs

module 9:Tactical Decisions and Review

Back to main index exit back to module contents

Page 78: Project and Production Management

1. Reduction in inventory (30-50% in WIP)

2. Improved customer service (late orders reduced by 90%)3. Quicker response to changes in demand and master

schedule.

4. Greater productivity

5. Reduced set up and product changeover costs

6. Better machine utilization

7. Increased sales and reductions in sales price.

BENEFITS OF MRP module 9:Tactical Decisions and Review

Back to main index exit back to module contents

Page 79: Project and Production Management

EVOLUTION OF MRP

Manufacturing ResourcePlanning

• Links up the closed loop MRP system with the financial systems of the company

(Links functions-Capacity planning-Inventory management-Shop floor control-MRP)

Improved computational efficiency of computers

Unrealistic M/c schedules, ignoring plant capacities

Not only plans priorities but provides feedback to executing the priority plan

AN IMPROVED ORDERING METHOD

PRIORITY PLANNING

CLOSED LOOP MRP

MRP II

module 9:Tactical Decisions and Review

Back to main index exit back to module contents

Page 80: Project and Production Management

Uses closed loop MRP Integrated System has MRP, Capacity planning, shop

floor, control, vendor scheduling etc. MRP system used to help plan sales, engg, production,

purchasing, etc

No shortage lists of override the production schedules.

System has MRP, capacity planning shop floor control, but no vendor scheduling

Used as a production control system

Needs help from shortage list

Inventory higher than need be

FOR CLASSES OF MRP USERSClass A (most advanced)

Class B

module 9:Tactical Decisions and Review

Back to main index exit back to module contents

Page 81: Project and Production Management

System used for inventory Ordering rather than scheduling

Scheduling by shortage list

Master schedule over loaded

MRP working in the data processing department only

Inventory records are poor

Master schedule, if it exists at all is overstated and

mismanaged

Relies on shortage list & expediting rather than MRP

FOR CLASSES OF MRP USERSClass C

Class D (beginner)

module 9:Tactical Decisions and Review

Back to main index exit back to module contents

Page 82: Project and Production Management

IT IS AN OPERATIONAL & FINANCIAL SYSTEM Company wide, Sales, Production, Engineering,

inventories, cash flows

All operating data expressed in money terms

IT IS A SIMULATOR “What if” questions Simulate probable outcomes of alternative production

plans and management decisions.

ADDITIONAL FUNCTIONS OF MRP II

module 9:Tactical Decisions and Review

Back to main index exit back to module contents

Page 83: Project and Production Management

SUMMARYDependent vs Independent DemandMRP is useful for planning requirements of components and parts knowing end item demandMajor inputs to MRP include Master Production Schedule, BOM, Inventory and Lead TimesThe MRP logic goes through Explosion, Offsetting, Netting and Lot sizing

module 9:Tactical Decisions and Review

Back to main index exit back to module contents

Page 84: Project and Production Management

SUMMARY (Contd)Major benefits of MRP include improved planning, lesser inventories, shorter lead timesHowever MRP does not integrate cost functions in different departmentsMRPII (Manufacturing Resource Planning)

links the financial functions across the organization

module 9:Tactical Decisions and Review

Back to main index exit back to module contents

Page 85: Project and Production Management

4. Job Shop Scheduling

module 9:Tactical Decisions and Review

Back to main index exit back to module contents

Page 86: Project and Production Management

NATURE OF JOB PRODUCTION

Variety of jobs producedBoth nature and demand of jobs is unpredictableConsists of general purpose machinesEach job depending on its technological requirements, demands processing on machines in a certain orderJobs queue before machines or there may be idle machines

module 9:Tactical Decisions and Review

Back to main index exit back to module contents

Page 87: Project and Production Management

OBJECTIVES IN JOB SHOP SCHEDULING

Minimize total processing time or makespanMinimize mean flow timeMinimize idle time of machinesMinimize mean lateness/earlinessMinimize mean tardinessMinimize number of tardy jobs Minimize mean queue time Minimize the number of jobs in the system

module 9:Tactical Decisions and Review

Back to main index exit back to module contents

Page 88: Project and Production Management

COMPLEXITY OF THE PROBLEM

With n jobs to be processed on m machines the number of possible sequences is (n!)mn 5 10 15 20

m 2 4 5 5

(n!)m 14400 1,73x1026 3.8x1060 8.5x1091

module 9:Tactical Decisions and Review

Back to main index exit back to module contents

Page 89: Project and Production Management

PRELIMINARY DEFINITIONSA job shop is characterised byNo of jobs (n)Number of Machines (m)Pattern of arrival of jobs (static/dynamic)Objective of scheduling(minimise

inventory, makespan, maximum tardiness, lateness…)

Sequencing rule (FCFS, LIFO, SPT, LPT, EDD ...)

module 9:Tactical Decisions and Review

Back to main index exit back to module contents

Page 90: Project and Production Management

DEFINITIONS-I

Job arrivaltime, ai

Start ofprocessing

Completiontime ,Ci

Waiting time, wi

Processing time, ti

Flow time, Fi = wi + ti = Ci - ai = Time job spends on the shop floor, waiting and being processed

module 9:Tactical Decisions and Review

Back to main index exit back to module contents

Page 91: Project and Production Management

DEFINITIONS II

Job arrivaltime, ti

Start ofProcessing

Completiontime, Ci

Due Date, di

Job lateness, Li = Ci- di (could be positive or negative)Job earliness, Ei = max (0, -Li)Job tardiness, Ti = max (0, Li)

module 9:Tactical Decisions and Review

Back to main index exit back to module contents

module 9:Tactical Decisions and Review

Back to main index exit back to module contents

Page 92: Project and Production Management

N/1 PROBLEMAll sequences for the n/1 problem have the same makespanTherefore other objectives are relevantmean flowtimeaverage inventorymean latenessmean completion time

module 9:Tactical Decisions and Review

Back to main index exit back to module contents

Page 93: Project and Production Management

RELATIONSHIP BETWEEN F AND OTHER VARIABLES

Fi = Ci -ai = wi + tiLi = Ci - diFrom these equations it is easy to see that a sequence that minimises mean F also simultaneously minimisesmean Completion timesmean Waiting timesmean Lateness

module 9:Tactical Decisions and Review

Back to main index exit back to module contents

Page 94: Project and Production Management

INVENTORY VARIATION FOR AN ARBITRARY N/1 SEQUENCE

Inventory

1 2 3 n-1 n

Job under process (Total Time T)

nn-1 n-2

21

Avg inventory = [nt1+ (n-1)t2 + … 1 tn]/TAvg inventory I = Area /TSumming horizontal strips:Area = F1 + F2 + … +Fn= n avg Flow timeThus T(avg inventory) = n (avg flow time)

module 9:Tactical Decisions and Review

Back to main index exit back to module contents

Page 95: Project and Production Management

SPT vs LPT

n

T

LPT

SPT

LPT maximizes what SPT minimises

module 9:Tactical Decisions and Review

Back to main index exit back to module contents

Page 96: Project and Production Management

SPT RULEThus the rule that minimizes mean flow time also minimises the mean inventoryIt is seen that the SPT (Shortest Processing Time Rule) minimisesmean inventory mean flow timemean waiting timemean completion timemean lateness

module 9:Tactical Decisions and Review

Back to main index exit back to module contents

Page 97: Project and Production Management

AN EXAMPLESix jobs with processing times4, 8 5, 9, 2 and 6 respectivelyDue dates 10, 8, 12, 15, 9 and 20 respectivelySolutionThe SPT sequence is 5(2), 1(4), 3(5), 6(6), 2(8) , 4(9)

module 9:Tactical Decisions and Review

Back to main index exit back to module contents

Page 98: Project and Production Management

EXAMPLE (Contd)The SPT sequence is 5(2), 1(4), 3(5), 6(6), 2(8) , 4(9)Completion (Flow Times) are 2, 6, 11, 17, 25, 34Due Dates are job (due date)5(9), 1(10), 3(12), 6(20), 2(8) , 4(15)Lateness values are-7, -4, -1, -3, 17, 19

module 9:Tactical Decisions and Review

Back to main index exit back to module contents

Page 99: Project and Production Management

RESULTSSPT sequence: 5 1 3 6 2 4 Mean Flow time: 95/6 =15.833Average Inventory : (6*95)/(6*34)= 2.794Mean Lateness: 21/6 =3.5Mean Tardiness: 36/6 =6Mean Earliness: 15/6 =2.5

module 9:Tactical Decisions and Review

Back to main index exit back to module contents

Page 100: Project and Production Management

Task Processing time

Due date

Slack time

1 5 15 102 8 10 23 6 15 94 3 25 225 10 20 106 14 40 267 7 45 388 3 50 47

EXAMPLE 2 module 9:Tactical Decisions and Review

Back to main index exit back to module contents

Page 101: Project and Production Management

Rule Objective

Mean Flow Time

Weighted Mean Flow time

Mean Lateness

Maximum Tardiness

No of Tardy jobs

Mean Tardiness

SPT MFT,AVG INV,

23.9 29.0 -3.6 22 4 7.8

WSPT WMFT 27.0 27.5 -0.5 36 4 10.6

EDD Max job lateness/tardiness

32.0 31.7 4.5 9 6 5. 0

Hodgson No of tardy jobs

29.1 29.9 1.6 36 2 9.0

SLACK Mean tardiness (heuristic)

32.1 31,1 4.6 9 6 5,0

module 9:Tactical Decisions and Review

Back to main index exit back to module contents

Page 102: Project and Production Management

n/2 PROBLEMn job 2 machine Flowshop Different sequences now have different completion times (makespan)Therefore unlike the n/1 problem minimizing the makespan is a legitimate objectiveJohnson’s Rule is commonly used to solve the problem

A B

module 9:Tactical Decisions and Review

Back to main index exit back to module contents

Page 103: Project and Production Management

AN EXAMPLETime on M/c A Time on M/c B

Job1 10 2

Job2 5 7

Job3 4 10

Job 4 12 8

Job 5 9 6

module 9:Tactical Decisions and Review

Back to main index exit back to module contents

Page 104: Project and Production Management

JOHNSON’S SEQUENCE

M/c AM/c B

module 9:Tactical Decisions and Review

Back to main index exit back to module contents

Page 105: Project and Production Management

n/3 FLOWSHOPNotion of dominance

M/c A

M/c B

M/c C

1 10 4 5

2 12 6 2

3 8 8 5

4 9 7 4

5 14 3 8

module 9:Tactical Decisions and Review

Back to main index exit back to module contents

Page 106: Project and Production Management

n/3 FLOWSHOPWhen Dominance does not exist

M/c A

M/cB

M/cC

1 10 8 6

2 4 6 9

3 8 4 4

4 6 2 8

5 5 8 3

module 9:Tactical Decisions and Review

Back to main index exit back to module contents

Page 107: Project and Production Management

COMPUTATIONSM/c A+B M/c B+C

1

2

3

4

5

module 9:Tactical Decisions and Review

Back to main index exit back to module contents

Page 108: Project and Production Management

COMPUTATIONSM/c A+B M/c B+C

1

2

3

4

5

module 9:Tactical Decisions and Review

Back to main index exit back to module contents

Page 109: Project and Production Management

2/m/JJOBSHOP module 9:Tactical Decisions and Review

Back to main index exit back to module contents

Page 110: Project and Production Management

PRACTICAL SOLUTIONS TO JOBSHOP TRAINING

Priority Dispatching Rules FCFS SPT EDD SLACK RANDOM LRPT (Least Remaining Processing Time) S/OPR (Min Ratio oof job slack time to the number of operations

remaining LCFS DS (Least Dynamic Slack) DS/PT Minimum ratio of Dynamic Slack to remaining Processing

Time

module 9:Tactical Decisions and Review

Back to main index exit back to module contents

Page 111: Project and Production Management

SUMMARY AND CONCLUSIONS

The complexity of Job Shop Schedulingn/1 problem n/2 flow shop problemn/ 3 problem2/m/job shopGeneral job shops Simulation

module 9:Tactical Decisions and Review

Back to main index exit back to module contents

Page 112: Project and Production Management

5. Course Summary and Review

module 9:Tactical Decisions and Review

Back to main index exit back to module contents

Page 113: Project and Production Management

PROJCT MANAGEMENT (CONTENTS)

A. PROJECT MANAGEMENT (19 Lectures)a.1 Project conception and appraisal ( 5 lectures)Concept of a project, historical perspective, various issues: Time, cost, Quality, Project Identification and Screening: Various methods and frameworks, Factors for project appraisal, Criteria for project selection, Financial measures, some examplesa.2 Project Planning ( 4 lectures)Project representation, network concepts, Consistency and Redundancy in Project Networks, Activity on arc representation, concept of scheduling, Critical Path Method, Basic Scheduling with A-O-A, Activity on node representation, Basic Scheduling with A-O-N Networksa.3 Project crashing and Resource considerations ( 5 lectures )Probabilistic Scheduling: Uncertainty and probabilistic considerations in project, PERT, Three-estimate approach, Project Scheduling with Probabilistic Activity Times, Heuristic approach for Linear Time-Cost Tradeoffs in Projects, Resource Profiles and leveling, Limited Resource Allocationa.4 Project Implementation:( 5 lectures ) Considerations in implementation, Project Monitoring and Control with PERT / Cost, Behavioral and human issues, Team Building, Desirable attributes of project leader, computers in project management , Project Completion, Review

module 9:Tactical Decisions and Review

Back to main index exit back to module contents

Page 114: Project and Production Management

PRODUCTION MANAGEMENT(CONTENTS)b.1 Strategic decisions in production management (5 lectures )

Concept of a production system, historical perspectives on production system, a generalized model of production system, Concept of a life cycle, various stages in life cycle, implications for managerial decision making vis-à-vis life cycle, Financial Evaluation Of Production Related Decisions: Typical Performance Measures of a Production System, Criteria such as net present value, rate of return, Financial Evaluation of Capital Decisions, concept of a decision tree, evaluation of riskb.2 Product and process selection ( 4 lectures )Designing Products and Services: Factors for New product/service introduction, product mix decisions using linear programming approach, stochastic product mix decisionsb.3 Facility Location and Layout ( 4 lectures )Considerations in Plant Location, various models for location (gravity etc.), Process Layouts, Product Layouts, comparison of process and product layout, concept of Assembly Line Balancing, heuristic approaches for assembly line balancing (rank position weight etc.), Cellular Layoutsb.4 Production planning over the short Term Horizon ( 4 lectures )Demand Forecasting, various methods for forecasting (qualitative and quantitative), Aggregate Production Planning (APP), models for APPb.5 Tactical decisions and review (5 lectures )Inventory: necessity, and costs involved, deterministic inventory models, Dependant demand systems, Material Requirements Planning, Scheduling of Job Shops, various heuristics for scheduling, course review

module 9:Tactical Decisions and Review

Back to main index exit back to module contents

Page 115: Project and Production Management

Project and Production Management

Project Conception and AppraisalProject Management: An OverviewProject Identification and ScreeningProject Appraisal: Part IProject Appraisal: Part IIProject Selection

module 9:Tactical Decisions and Review

Back to main index exit back to module contents

Page 116: Project and Production Management

Project ManagementProject PlanningProject RepresentationConsistency and Redundancy in Project NetworksBasic Scheduling with A-O-A NetworksBasic Scheduling with A-O-N Networks

module 9:Tactical Decisions and Review

Back to main index exit back to module contents

Page 117: Project and Production Management

Project Management

Project Crashing and ResourcesProject Scheduling with Probabilistic Activity TimesLinear Time-Cost Tradeoffs in Projects: A Heuristic ApproachResource Profiles and levelingProject crashing with multiple objectivesLimited Resource Allocation

module 9:Tactical Decisions and Review

Back to main index exit back to module contents

Page 118: Project and Production Management

Project ManagementProject ImplementationProject Monitoring and Control with PERT / CostTeam Building and Leadership in ProjectsOrganizational and behavioral issuesComputers in project managementProject Completion and Review

module 9:Tactical Decisions and Review

Back to main index exit back to module contents

Page 119: Project and Production Management

Project & Production Management

Project Conception and AppraisalProject Management: An OverviewProject Identification and ScreeningProject Appraisal: Part IProject Appraisal: Part IIProject SelectionProject PlanningProject RepresentationConsistency and Redundancy in Project NetworksBasic Scheduling with A-O-A NetworksBasic Scheduling with A-O-N NetworksProject Crashing and ResourcesProject Scheduling with Probabilistic Activity TimesLinear Time-Cost Tradeoffs in Projects: A Heuristic ApproachResource Profiles and levelingProject crashing with multiple objectivesLimited Resource AllocationProject ImplementationProject Monitoring and Control with PERT / CostTeam Building and Leadership in ProjectsOrganizational and behavioral issuesComputers in project managementProject Completion and Review

module 9:Tactical Decisions and Review

Back to main index exit back to module contents

Page 120: Project and Production Management

Production ManagementStrategic Decisions in Production ManagementIntroduction to Production Systems and a Generalized Model of ProductionLife cycle of a Production System and Major managerial DecisionsPerformance Measures of a Production SystemFinancial Evaluation of Capital Decisions Decision Trees and evaluation of risk

module 9:Tactical Decisions and Review

Back to main index exit back to module contents

Page 121: Project and Production Management

Production ManagementProduct and Process SelectionIntroducing New Products and Services I Introducing new products and services IIProduct Mix Decisions

module 9:Tactical Decisions and Review

Back to main index exit back to module contents

Page 122: Project and Production Management

Production ManagementFacility Location and LayoutPlant LocationProcess LayoutsProduct Layouts and Assembly Line BalancingCellular Layouts

module 9:Tactical Decisions and Review

Back to main index exit back to module contents

Page 123: Project and Production Management

Production ManagementProduction Over the Medium Term HorizonDemand Forecasting: General considerationsModels for forecasting Aggregate Production Planning IAggregate Production Planning II

module 9:Tactical Decisions and Review

Back to main index exit back to module contents

Page 124: Project and Production Management

Production ManagementProduction Over the Medium Term HorizonDemand Forecasting: General considerationsModels for forecasting Aggregate Production Planning IAggregate Production Planning II

module 9:Tactical Decisions and Review

Back to main index exit back to module contents

Page 125: Project and Production Management

Production ManagementTactical Decisions over the Short Term HorizonInventory considerations and various factors Inventory modelingMaterial Requirements Planning`Scheduling of Job ShopsCourse summary and review

module 9:Tactical Decisions and Review

Back to main index exit back to module contents

Page 126: Project and Production Management

WHAT IS A PROJECT?PURPOSE

An undertaking or venture to accomplish some objective or goal

STRUCTURE A set of interrelated jobs whose accomplishment leads to the completion of the project

COMPONENTSJobs or activities consume time and resources and are governed by precedence relations

module 9:Tactical Decisions and Review

Back to main index exit back to module contents

Page 127: Project and Production Management

PROJECTS AS AGENTS OF CHANGE

State A

State B

Alternative Projects(Paths)

module 9:Tactical Decisions and Review

Back to main index exit back to module contents

Page 128: Project and Production Management

FEATURES OF PROJECTS

Well defined collection of jobs

Generally non-repetitive, one time effort

Jobs interrelated through precedence

Jobs otherwise independent

module 9:Tactical Decisions and Review

Back to main index exit back to module contents

Page 129: Project and Production Management

PROJECT FEATURES (Continued)

Jobs consume time and resources

Coordination needed between individuals, groups & organisations

Constant pressure of conformance to time/cost /performance goals

module 9:Tactical Decisions and Review

Back to main index exit back to module contents

Page 130: Project and Production Management

A Project as a Production SystemMass production

Batch Production

Job Production

QQuantity

to be Made

P (No. of Products or “VARIETY”)

Projects

1

module 9:Tactical Decisions and Review

Back to main index exit back to module contents

Page 131: Project and Production Management

LIFE CYCLE OF A PROJECTSelection of the projectProject Planning Scope of work & network development

Basic Scheduling Time Cost tradeoffs Resource Considerations in projects

Project ImplementationProject Completion and Audit

module 9:Tactical Decisions and Review

Back to main index exit back to module contents

Page 132: Project and Production Management

Motivation in Introducing New Products

To satisfy need

For profit

module 9:Tactical Decisions and Review

Back to main index exit back to module contents

Page 133: Project and Production Management

CONTRIBUTION TO NEW PRODUCT IDEAS

Sales and Marketing (close touch with customer)Top management (Active listener to visitor and customer feedback)Production department (limited to production ease and economics)Research and Development (prompted by new developments in materials & technology)

module 9:Tactical Decisions and Review

Back to main index exit back to module contents

Page 134: Project and Production Management

GENERATION OF NEW PRODUCT IDEAS

Brain storming (preferably by interdisciplinary team)

Team apprised of Company objectives & long term goals Current economic scenario Preferred field of activity (expertise) Approximate budget for new product

Each one generates ideas which are recorded without criticism or evaluation

module 9:Tactical Decisions and Review

Back to main index exit back to module contents

Page 135: Project and Production Management

EVALUATION OF NEW PRODUCT IDEAS

The evaluation of the new product ideas could be done on a number of criteria Likely demand and pattern of growth Ease of raw material availability Availability of Production technology Competition and likely market share Likely revenues and costs of operation The product life cycle

An example to illustrate this process is taken up next

module 9:Tactical Decisions and Review

Back to main index exit back to module contents

Page 136: Project and Production Management

AN EXAMPLE OF SCREENING OF IDEAS

Idea/ factor

Demand Competition

Ease of Raw Mtl

Cost of processing

Likely profit

Score

Computer peripherals

6 3 6 5 6 26

Fast food 8 6 9 7 5 35Fashion clothing

4 5 7 4 4 24

Soaps and detergents

9 2 7 6 4 28Each factor evaluated on a scale of 1(least desirable) – 10 (most desirable)

module 9:Tactical Decisions and Review

Back to main index exit back to module contents

Page 137: Project and Production Management

Undesirable outputs

Economic/Social/Political

Environment -dynamic -uncertain

Transformation

FEED BACK

INPUT(S) OUTPUT(S)

-Men -Machines

-Materials

-Money

-Information -Energy ----------

Useful Goods or Services

(Effluents, Fumes etc.)

A PRODUCTION SYSTEM AS AN INPUT-OUTPUT SYSTEM

module 9:Tactical Decisions and Review

Back to main index exit back to module contents

Page 138: Project and Production Management

AN EXAMPLE OF SCREENING OF IDEAS

Idea/ factor

Demand Competition

Ease of Raw Mtl

Cost of processing

Likely profit

Score

Computer peripherals

6 3 6 5 6 26

Fast food 8 6 9 7 5 35Fashion clothing

4 5 7 4 4 24

Soaps and detergents

9 2 7 6 4 28Each factor evaluated on a scale of 1(least desirable) – 10 (most desirable)

module 9:Tactical Decisions and Review

Back to main index exit back to module contents

Page 139: Project and Production Management

CUSTOMER NEEDS AND DESIRES

Desires Natural, as hunger,

shelter, love and security

Generated by exposure to circumstances and temptations(as in advertisements on media, TV,neighbour)

Needs When a desire becomes

strong enough and warrants fulfilment, it becomes a need.

Customer demand is based on real or artificially generated needs

Needs are constantly changing

module 9:Tactical Decisions and Review

Back to main index exit back to module contents

Page 140: Project and Production Management

MORTALITY OF IDEASScreening Economic evaluation Development Testing Commercialization Number

of ideas

Time

35-40 ?

3-24 months ?

module 9:Tactical Decisions and Review

Back to main index exit back to module contents

Page 141: Project and Production Management

Price Quality

COMPETITION

Reduced Customerlead times satisfaction

NEW CHALLENGES IN PRODUCTION

• More producers• Demanding customers

Greater variety

module 9:Tactical Decisions and Review

Back to main index exit back to module contents

Page 142: Project and Production Management

PRODUCTION AS A PART OF THE SUPPLY CHAIN

Transformation process

Vendors Warehouses Retailers

module 9:Tactical Decisions and Review

Back to main index exit back to module contents

Page 143: Project and Production Management

CONCLUSIONSThis course has focussed on the Life Cycle issues in Projects and Production SystemsThe Strategic, Operational and Tactical Issues in Projects and Production Systems have been discussedThe approach has been on conceptual issues as well as modelling of key processes and decisions

module 9:Tactical Decisions and Review

Back to main index exit back to module contents

module 9:Tactical Decisions and Review

Back to main index exit back to module contents

module 9:Tactical Decisions and Review

Back to main index exit back to module contents