Top Banner
This page has been reformatted by Knovel to provide easier navigation. Project and Contract Management 33 P A Thompson BSc(Eng), MSc, CEng, FICE, MIWES University of Manchester Institute of Science and Technology Contents 33.1 Introduction 33/3 33.2 Project and contract organization 33/3 33.2.1 Introduction 33/3 33.2.2 Organization of design and construction 33/5 33.2.3 Decision making and control 33/5 33.2.4 Project management 33/5 33.2.5 Project objectives 33/5 33.2.6 Safely 33/6 33.3 Commercial considerations and cashflow 33/6 33.3.1 Cashflow 33/7 33.3.2 Contract cashflow 33/7 33.4 Construction planning 33/8 33.4.1 Compiling a programme 33/8 33.4.2 Resource scheduling 33/8 33.4.3 Programming techniques 33/10 33.5 Cost Estimating 33/10 33.5.1 Requirements of an estimate 33/10 33.5.2 Cost-estimating 33/11 33.6 Project appraisal 33/11 33.6.1 Risk and uncertainty 33/12 33.6.2 Project evaluation 33/12 33.7 Engineering contracts 33/14 33.7.1 Contract strategy 33/14 33.7.2 Choice of contract type 33/14 33.7.3 The main types of contract 33/15 33.7.4 Management contracting 33/15 33.8 Contractual measurement and valuation 33/15 33.8.1 Bills of quantities 33/15 33.8.2 The concepts incorporated in the traditional bills of quantities 33/16 33.8.3 Development of the bills of quantities 33/16 33.8.4 Method-related charges 33/16 33.8.5 Pricing and tendering policy 33/16 33.9 Project management 33/16 33.9.1 Guidelines for project management 33/17 References 33/18 Bibliography 33/18
17

Project and 33 Management Contract - Freenguyen.hong.hai.free.fr/EBOOKS/SCIENCE AND ENGINEERING/ENGINNEERING... · report Project appraisal and definition. Conceptual design Design

Oct 26, 2019

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Project and 33 Management Contract - Freenguyen.hong.hai.free.fr/EBOOKS/SCIENCE AND ENGINEERING/ENGINNEERING... · report Project appraisal and definition. Conceptual design Design

This page has been reformatted by Knovel to provide easier navigation.

Project andContractManagement33P A Thompson BSc(Eng), MSc, CEng,FICE, MIWESUniversity of Manchester Institute of Scienceand Technology

Contents

33.1 Introduction 33/3

33.2 Project and contract organization 33/333.2.1 Introduction 33/333.2.2 Organization of design and construction 33/533.2.3 Decision making and control 33/533.2.4 Project management 33/533.2.5 Project objectives 33/533.2.6 Safely 33/6

33.3 Commercial considerations and cashflow 33/633.3.1 Cashflow 33/733.3.2 Contract cashflow 33/7

33.4 Construction planning 33/833.4.1 Compiling a programme 33/833.4.2 Resource scheduling 33/833.4.3 Programming techniques 33/10

33.5 Cost Estimating 33/1033.5.1 Requirements of an estimate 33/1033.5.2 Cost-estimating 33/11

33.6 Project appraisal 33/1133.6.1 Risk and uncertainty 33/1233.6.2 Project evaluation 33/12

33.7 Engineering contracts 33/1433.7.1 Contract strategy 33/1433.7.2 Choice of contract type 33/1433.7.3 The main types of contract 33/1533.7.4 Management contracting 33/15

33.8 Contractual measurement and valuation 33/1533.8.1 Bills of quantities 33/1533.8.2 The concepts incorporated in the

traditional bills of quantities 33/1633.8.3 Development of the bills of quantities 33/1633.8.4 Method-related charges 33/1633.8.5 Pricing and tendering policy 33/16

33.9 Project management 33/1633.9.1 Guidelines for project management 33/17

References 33/18

Bibliography 33/18

Page 2: Project and 33 Management Contract - Freenguyen.hong.hai.free.fr/EBOOKS/SCIENCE AND ENGINEERING/ENGINNEERING... · report Project appraisal and definition. Conceptual design Design

33.1 Introduction

Management is concerned with the setting and achievement ofrealistic objectives for the project or contract. This will demandeffort - it will not happen as a matter of course - and it willrequire the dedication and motivation of people. The provisionand training of an adequate management team is therefore anessential prerequisite for a successful job for it is their drive andjudgement, their ability to persuade and lead, which will ensurethat the project objectives are achieved.

Managers of projects and contracts involving engineeringconstruction will frequently encounter a mixture of technical,environmental, logistical and physical problems. The style ofmanagement required for such work will therefore differ inmany ways from that required in the relatively static surround-ings of line management in a factory. The temporary nature ofthe organization and the considerably greater element of uncer-tainty associated with construction projects will be particularlysignificant.

Uncertainty is the source of many of the problems encoun-tered in construction work and will influence project appraisal,estimating, planning, the form of contract and the proceduresfor contractual measurement and valuation. Excessive uncer-tainty which leads to continuous or multiple changes to designwill reduce productivity and will almost certainly affect adver-sely the morale of the workforce. It will also result in extra costto both client and contractor. All parties involved in construc-tion projects and contracts would therefore benefit greatly fromreduction in uncertainty prior to financial commitment. Effortshould be devoted to risk management and the person(s)ultimately responsible for the financial outcome should beappraised fully of the full risk spectrum before committing hisor her organization to the project or contract.

When considering planning techniques, construction con-tracts and their valuation and other aspects of management inthis chapter there may be a tendency for the reader to think ofeach system as a separate entity. He or she is advised toremember that the purpose of all these techniques and pro-cedures is to help people make the judgements and decisions and

to perform the administrative functions which are necessary forthe successful accomplishment of the project or contract. Theproject or contract manager is primarily concerned with thedirection and motivation of other human beings.

33.2 Project and contractorganization

33.2.1 Introduction

There are many steps between the inception of a new capitalproject and its successful operation and maintenance. Forefficient project management it is helpful to group these stepstogether into the following project stages, which are alsoidentified in Figure 33.1:

APPRAISAL Assess alternative strategies for meetingneedsEstablish technical and economic feasibi-lityDerive the master plan

DEFINITION Statement of project objectivesConceptual design and associated costestimatesDesign reviewArrange project fundingSanction

DESIGN Detailed designDesign reviewContract strategy report and definition ofcontract packagesDetailed cost estimatesProcurement/tenderingContract award

CONSTRUCTION Site constructionOffsite fabrication and manufactureInstallationQuality control

Figure 33.1 Precedence diagram for new manufacturingplant. This simple network will later be developed into atime-and-money model for appraisal of the project

Feasibilitystudy

Considerreport

Project appraisaland definition.Conceptual design

Design and construction Commissioningand acceptance

Operation andmaintenance

Notes: (1) Only one year of operation shown(2) 86.01 is January 1986

Landpurchase

Planningpermission Services

Designloadingbay

Constructloadingbay

Designtank farm

Designprocess plant

Operate

Commission

Constructtank farm

Constructprocess plant

Page 3: Project and 33 Management Contract - Freenguyen.hong.hai.free.fr/EBOOKS/SCIENCE AND ENGINEERING/ENGINNEERING... · report Project appraisal and definition. Conceptual design Design

Figure 33.2 Flow chart for new manufacturing plant. Theprecedence diagram is developed and extended as the frameworkfor cost/benefit analysis

ACTIVITIES

Forecastoutput

Limits ofvariance

Limit of 2nd stage output

Limit of 1st stage output

Month

OperateOperate

Commissionstage 11

Constructstage (I

Commissionstage I

Designstage Il

Constructloadingbay

Constructoffices

Services

Constructtank farm

Constructprocess plant

Landpurchase

Designloadingbay

Designoffice labs

Planningpermission

Designtank farm

Designprocess plant

Considerreport

Feasibilitystudy

LEGENDFixed costsTime — relatedcostsQuantity -proportional costs

Overheads

Indirect production costs

Construction

HAMMOCKSDesign office overheads

Page 4: Project and 33 Management Contract - Freenguyen.hong.hai.free.fr/EBOOKS/SCIENCE AND ENGINEERING/ENGINNEERING... · report Project appraisal and definition. Conceptual design Design

ExpeditingConstruction managementContract administration

COMMISSIONING Engineering and performance testsAcceptance

OPERATION Organization for operation and mainten-anceProject review

These stages may frequently overlap and their relative durationscan vary greatly. For public works projects the early stages ofappraisal and definition are likely to extend over many yearsand the facility, say a road or a water-treatment plant, will alsobe utilized over a period frequently exceeding 25 years. Com-mercial projects, such as the new manufacturing plant illus-trated in Figure 33.2, are more likely to be appraised, sanctionedand implemented rapidly before a competitor enters the market.

33.2.2 Organization of design and construction

In the traditional system for the procurement of civil engineer-ing works1 it is normal for the client to employ an experiencedconsulting engineer to assist him with project development andimplementation. The consultant is likely to play an importantrole in project appraisal and definition, to undertake the designand contract documentation, to oversee tendering by contrac-tors, to supervise construction work on site and administer theconstruction contracts. A contractor or group of contractorscomplete the fabrication and construction of the works.Management of design and construction is therefore the respon-sibility of different organizations.

This well-established system is still widely used but manyvariations are adopted to meet the particular requirements ofthe client, particularly in the private sector. In general, thesereflect alternatives used in the related process plant, offshoreand building industries2 and frequently respond to pressure forquicker and timely completion to reduce the payback period.There is also increasing emphasis on effective project manage-ment and on the overall management of design and construc-tion.

33.2.3 Decision making and control

Control is concerned with regulation of the future. This impliesthe ability to predict the consequences of specific courses ofaction and necessitates decision making under conditions ofuncertainty. That is to say that the decision maker must choosea specific course of action from those available to him eventhough the consequences of the possible courses of action willdepend on events that cannot be predicted with certainty.Decision making on construction projects is inextricably linkedwith uncertainty and also frequently encounters conditions ofurgency and constraint. Many decisions are required duringeach of the stages listed above and may be influenced by a needto keep options open or a need to reduce uncertainty.

The scope for control diminishes as the project proceeds. Thekey events for the client are sanction - when he commits himselfto a project of particular characteristics - and contract award -when he commits himself to specific contractors and to majorcost expenditure. The contractor's commitment is, of course,made in his tender: thereafter he will exert control mainlythrough the allocation and use of resources.

33.2.4 Project management

The role of project management is to exercise overall control ofthe project from its inception through to the completion ofcommissioning. Thus, the ultimate responsibility for project

management lies squarely with the client. His primary functionis to define the parameters of the project and thereafter toprovide decisions, approvals and guidance. Several reports onthe performance of the construction industry over the last 10 to20 years have concluded that good project management by theclient is an essential ingredient for a successful project.3 Regret-tably, it was found that many projects lacked an appropriateproject management structure, resources and expertise.

For each project, a single individual from within the client'sorganization should be named as project manager, and giventhe necessary authority and responsibility.4 His role, therefore,is to manage the client's investment, and he should havesufficient seniority to exercise effective control both within andoutside the client organization. For most projects he will needthe support of a small project management team.

Brief guidelines for effective project management are given insection 33.9.

33.2.5 Project objectives

The client will have a number of overall objectives for undertak-ing the project. These may be commercial, reflect the perceivedneeds of society and/or have political overtones. Specific projectmanagement objectives must be compatible with the overallobjectives and should be clearly formulated early in the defini-tion stage of project development.

The dominant considerations must be fitness for purpose ofthe completed project and safety during both the constructionand operational phases. Thereafter cost, time and functionalperformance form a minimum set of values from which theprimary objectives will be drawn. The potential for conflictbetween these objectives, as problems arise during projectimplementation, is obvious.5 The disasters which beset theMontreal Olympics stadium - a prestige project of novel designwith an unrealistic budget and a fixed time constraint - offersalutory reading to all project managers.6

Consequently, it is necessary for the project objectives to beranked in terms of their relative importance. Tolerances mustalso be specified - as range of acceptable variation in perfor-mance, float in the programme and tolerance and contingencyallowances in the estimate. The greater the perceived uncer-tainty, the more flexible these criteria must be. Unclear or ill-defined objectives will have a detrimental effect on decisionmaking and progress.

Thereafter, the monitoring of progress and performanceagainst these objectives will determine the need for replanning,revision of estimates and changes in project scope and specifica-tions. The latter are normally reductions in work content orquality which are accepted in order to meet stringent financialconstraints. This approach is prevalent in public works pro-jects,7 is disruptive, has an adverse effect on morale, and is likelyto lead to client or public dissatisfaction with the projecthowever well the remainder of the work may be completed. Farbetter to expose the uncertainties, allow for them in the estimateand adopt realistic objectives in the first place.

Quality control demands effective liaison between designoffice and the project management team both in terms ofspecification and verification of client requirements. Effectiveinspection and testing procedures should be established andagreed by all parties. There is a tendency for some clients toeconomize in the allocation of engineering staff to inspectfabrication and supervise construction. When this follows theaward of a contract to a low bidder without prequalification itdoes not surprise the Author that the client may be dissatisfiedwith the completed works.

Quality Assurance systems can assist project management inthe setting and achievement of project objectives. According to

Page 5: Project and 33 Management Contract - Freenguyen.hong.hai.free.fr/EBOOKS/SCIENCE AND ENGINEERING/ENGINNEERING... · report Project appraisal and definition. Conceptual design Design

a recent Construction Industry Research and Information Asso-ciation (CIRIA) report:8

Quality Assurance is a systematic way of ensuring thatorganised activities happen the way they are planned. It is amanagement discipline concerned with anticipating problemsand with creating the attitudes and controls which preventproblems arising.

The report continues:

Quality Assurance is concerned with systematically providingevidence to the client that all reasonable actions have beentaken to achieve the required quality. But it is also concernedwith spelling out the risks involved in any civil engineeringproject, and advising the client on operation and mainten-ance.

Properly practised, the system requires precision of communica-tion and this, in the Author's opinion, is its greatest value toproject management.

Quality Assurance is usually associated with manufacturedproducts and with complex multi-disciplinary projects wheresafety and quality of plant operation are the primary objectives.The application of such systems to any project should dependon whether there is benefit. In the civil engineering context, caremust be taken to ensure that the adoption of a Quality Assur-ance system does not result in rigid adherence to unnecessarilydemanding specifications. Neither must the system inhibit theflexibility and judgement required for the management of theuncertainties associated with the one-off job.

33.2.6 SafetyThe nature of construction work makes it vulnerable to acci-dents and project management must at all times enforce safetyprocedures. This is an area where great benefit to the physicalwell-being of staff, to morale and to the progress of the workscould be achieved by the adoption of effective safety QualityAssurance programmes.9-10

33.3 Commercial considerations andcashflow

Projects and contracts involving engineering construction arecommercial ventures. Both the client promoting a project and acontractor employed by him are investing money and takingfinancial risks in order to achieve some desired return. Projectand contract management is concerned with the control of bothinvestment and risk with the aim of achieving this return.

The client invests money in the realization of the project toprovide either a service or the production of goods. The projectis conceived and developed to meet a predicted demand for theservices or goods: a motorway, a hospital, a power station and ashoe factory are all examples of projects. In the first two cases,the return obtained from the investment is represented bybenefit to the users, whereas the unit price charged for theproduct of a commercial factory will be calculated to ensure anattractive profit to the investors. The power station must bothprovide a statutory service and make a small profit.

The client may also be called the promoter or the employer.He is concerned with the flow of money to and from the project- the project cashflow - throughout the life of the project fromits conception to the end of some defined period of operation, aperiod that may extend over many years. Projects are conse-quently capital intensive, i.e. a large amount of investment isrequired over a long period of time before a substantial benefit isachieved. This is well illustrated in Figure 33.3. Even in thatmanufacturing project with a relatively short life cycle of 12years, the client will have capital committed for almost 7 yearsbefore a positive balance is shown in the project account.

He may also enter into a legal agreement or contract with acontractor, or a number of contractors, for the construction ofthe project. Contractors are commonly specialists in a particularfield and may also undertake the detailed design of their work ifso required by the client.

A contractor's pattern of investment is very different and thetime-scale of his involvement is much shorter. His cashflow maywell comprise a substantial investment in construction plant,

Period number (months)Figure 33.3 Cashflow diagram for new manufacturingplant. Delay in commissioning the plant generates a significantincrease in capital investment

Reduced productiongrowth rate

6 month delay incommissioning

Base case

Payback—periodCum

ulat

ive v

alue

milli

on)

Targ

et c

ompl

etio

n da

te

Page 6: Project and 33 Management Contract - Freenguyen.hong.hai.free.fr/EBOOKS/SCIENCE AND ENGINEERING/ENGINNEERING... · report Project appraisal and definition. Conceptual design Design

labour, and materials, particularly in the early stages of acontract, offset by regular monthly payments received from theclient for work completed. The contractor must apply hisexpertise to produce a method statement for construction,assess the risks, and submit a tender that is both realistic andcompetitive. His targets are defined in his estimate and tender;thereafter he controls against them. The plan on which thetender is based will represent the most efficient use of thecontractor's resources to achieve the work defined in the con-tract documents. It follows that any delay or change in the workcontent may also affect the timing of the flow of money to andfrom the contractor, and may involve additional funding fromhis capital as illustrated in the contract cashflow example givenin section 33.3.2 below. If the disruption is caused by the client,the contractor will expect to be recompensed.

At any time, a contractor will probably be employed on avariety of contracts in different locations for different clients andwill also be tendering for future work. His commercial skill is toutilize a relatively small amount of capital and to 'turn it over'as many times as possible by employing it to finance severalcontracts. The corporate cashflow and total financial risk will bevery sensitive to changes in the timing of flows of money. It isimportant to appreciate the very different investment patternsexperienced by clients and contractors as these greatly influenceboth attitudes and procedures adopted within the contractualrelationship.

33.3.1 Cashflow

In order to quantify both the demand for money to meet theproject or contract costs and the pattern of income it willgenerate it is necessary to predict the cashflow. A cashflow is afinancial model of the project or contract which quantifies theactual flow of money, i.e. it takes account of delays betweenincurring a commitment and making a money transaction. Themodel is compiled simply by adding the costs and revenues toevery activity on a bar chart programme which extends over theentire life-cycle of the project or contract.

When developing cashflow it is vital to distinguish betweendifferent categories of charge:

(1) Fixed charges which occur when certain stages are reached,e.g. a mobilization payment at the start of a constructioncontract.

(2) Time-related charges which are paid or received in regularincrements over a period of time, e.g. the cost of siteoverheads, the weekly hire charge for a crane and pay-ments to employees.

(3) Quantity proportional charges which are related to thequantity of material used or to the number of units ofproduction of a factory or power station.

Only in this way will it be possible to use the model to predictrealistically the effect on investment or return of such diversefactors as variations in output, delay, disruption, cost or wast-age of materials.

33.3.2 Contract cashflow

The significance to the contractor's cashflow of different pat-terns of payment from the client and of delays is illustrated inFigure 33.4 by consideration of a small hypothetical contract of2 years' duration.

The estimated cost curve (1) is seen in Figure 33.4(a) to be aflat 'S' due to the dominance of time-related costs for resourcesand overheads. The anticipated predicted revenue (2) assumesmonthly payments for work completed and a 4-week delaybetween certification and payment by client. The shaded area

Contract duration (weeks)(c)

Figure 33.4 Contract cashflow. The contractors' investment issensitive to change in payment and to delay

between the curves represents the funding to be provided by thecontractor. This would be considerably reduced if the clientagreed to a 10% advance mobilization payment (3), or increasedif payments were received late (4), as illustrated in Figure33.4(b).

The effect of delay in completion is also serious as costincreases and payment for completed work is delayed (seeFigure 33.4(c)). If the delay was caused by factors outside thecontractor's control, an extension of time may be granted andpayment increased but this will depend on the circumstancesand the contract conditions.

Delayedrevenuepayment

Delay

Contract duration (weeks)

Revenue with mobilization fee (3

Revenue payment delayedbv 6 weeks (4)

Contract duration (weeks)

Predictedrevenue (2)

Total priceTotal cost

Cumu

lative

value

(£ m

illion

)Cu

mulat

ive va

lue (£

milli

on)

Cumu

lative

value

(£ m

illion

)

Cont

ract

com

pletio

nPla

nned

com

pletio

n

Actu

al co

mple

tion

Page 7: Project and 33 Management Contract - Freenguyen.hong.hai.free.fr/EBOOKS/SCIENCE AND ENGINEERING/ENGINNEERING... · report Project appraisal and definition. Conceptual design Design

In all cases, the effect on the contractor's investment issignificant. The cumulative effects of reduction of credit bysuppliers, delay in payment by the client, perhaps on severalcontracts, can be that a contractor will be led quickly intobankruptcy!

33.4 Construction planning

The success of a project or contract will depend greatly oncareful and continuous planning. The activities of designers,manufacturers, suppliers and contractors must be organizedand integrated to meet the objectives set by the client and/or thecontractor. Sequences of activities will be defined and linked ona time-scale to form the programme to ensure that priorities areidentified and that efficient use is made of expensive and/orscarce resources within the perceived physical constraints affect-ing the job.

Remember, however, that because of the uncertain nature ofconstruction work it should be expected that the plan willchange. It must therefore be updated quickly and regularly if itis to remain a guide to the most efficient way of completing thejob. The programme should therefore be simple - so thatupdating is straightforward and does not demand the feedbackof large amounts of data from busy men - and flexible, so thatall alternative courses of action are obvious.

The purposes of planning are therefore:

(1) To persuade people to perform their tasks before theydelay the operations of other groups of people, and in sucha sequence that the best use is made of available resources.

(2) To communicate with those people.(3) To provide a framework for decision making in the event

of change.

It is difficult to enforce a plan which is conceived in isolation,and it is therefore essential continually to involve the peopleresponsible for the constituent operations and to encouragetheir commitment as the plan is developed and revised. Ideally,it should provide a flexible framework within which they canexercise their own initiative.

Programmes are required at various stages in the contract;when considering feasibility or sanction, at the precontract stageand during the contract. They are required by the client and thecontractors. They may be used for initial budget control or forday-to-day construction work. They may pertain to one con-tract, or a number of contracts in one large project.

Before compiling a programme, the planner is therefore facedwith a number of decisions and must decide on:

(1) The appropriate level of detail for the programme. Thegolden rule is to keep it simple. A programme of 100activities is easy to comprehend; one of 1000 activities isnot. Initially, divide the job into the minimum number oflarge work packages and develop detajft later only inspecific areas where it is required due to^the complexity ofthe work or when there is need to determine preciseresource requirements.

(2) The choice of programming technique. Particularly import-ant in this choice is the level of management at which theprogramme is to be used, and the level of detail required.The main programming techniques are given in section33.4.3 below.

33.4.1 Compiling a programme

This is a process of repeated refinement. Before sketching outthe first draft, the planner must be familiar with the objectives

and priorities defined for the job and be aware of constraints.These will include: (1) restrictions on access to parts of theworks; (2) likely periods of bad weather which may inhibitparticular operations; and (3) availability of resources.Although the efficient use of key resources will be considered indetail at a later stage of the refining process, awareness of levelsof skills, machines and materials likely to be available will, ofcourse, aid the preparation of a realistic first draft.

Assumptions are invariably made as the plan is developedand it is essential that these should be stated clearly so thateveryone using it is aware of its validity.

When compiling the programme the planner is concernedwith:

(1) Resources: with the allocation and utilization of peoplewith expertise and skills, fabrication facilities, constructionplant and materials.

(2) Activities: packages of work which consume resources andare defined by considerations of:(a) the type of work (and therefore the type of resource

required);(b) the location of the work;(c) any restraints on the continuity of the activity.Each activity will be identified and appear as a bar or othersymbol on the programme.

(3) Logic: with the relationships and links between activitieswhich will be represented by lines or arrows on theprogramme. Most programmes will contain obvious se-quences of activities which will provide the basic shape ofthe diagram. It is also advantageous to identify anyopportunity to overlap activities, i.e. an activity may startbefore the preceding one is completed. In this way theoverall duration of the job may be minimized, frequentlywith consequential savings in cost. Initially each activityshould be shown at its earliest possible start.

(4) Duration of each activity which is a function of thequantity of work to be done, the number of units ofresource allocated to the activity, and their predictedoutput.

It is important to think of duration in this way as allthese factors may be variable. The quantity of work, e.g.volume of excavation or number of drawings, may be moreor less than originally estimated, one or more teams may beallocated to the activity, and their predicted productionmay or may not be achieved. Any change will affect theactivity duration and in turn alter the overall demand forresources, the total duration of the job, the cost and thecashflow.

The initial allocation of resources to an activity will be a matterof judgement and is quite likely to be changed subsequently.

(5) Potential problems and uncertainties must be identified andthe implications and possible responses considered. Thegreater the uncertainty, the more flexible the programmemust be in order to provide alternative courses of action.This may be achieved either by allocating additional re-sources or by extending the contract duration. In eithercase, the estimated cost will increase and it is thereforeessential to link the programme with the cost forecast.

(6) Overall duration of the job calculated when all the activitiesat their assumed durations have been assembled within theoverriding constraints which form the framework of theprogramme.

33.4.2 Resource scheduling

Whichever programming technique is used, the next important

Page 8: Project and 33 Management Contract - Freenguyen.hong.hai.free.fr/EBOOKS/SCIENCE AND ENGINEERING/ENGINNEERING... · report Project appraisal and definition. Conceptual design Design

Figure 33.5 Bar chart programme. The work is organized toachieve the project objectives and efficient use of resources

HISTOGRAM SHOWINGDEPLOYMENT OFBRICKLAYERS

Establish siteDivert drainBlock /A/ Foundations

BrickworkCarpentryFinishing

Block 'B' Foundations

BrickworkCarpentryFinishing

Block 1C' FoundationsBrickworkCarpentryFinishing

Block 'D' FoundationsBrickworkCarpentryFinishing

5 storeY Foundationsblock Concrete

frame ~Brickwork _._Finishing

Shops & Foundationsmaisonettes Concrete

frameBrickworkFinishing

Miscellaneous

KEYFoundations

Bricklaying

Carpentry

Finishing

Concrete frame

Page 9: Project and 33 Management Contract - Freenguyen.hong.hai.free.fr/EBOOKS/SCIENCE AND ENGINEERING/ENGINNEERING... · report Project appraisal and definition. Conceptual design Design

step in refining the plan would be to consider the overalldemand for key resources. The definition of key resources islikely to differ for different types of project and particularly fortheir location. Consideration will be given especially to thoseresources which are scarce and/or expensive. It is clear that theadjustment, or levelling, of one resource will have an effect onthe usage of others. Generally, resource levelling is only appliedto a few resources, particularly if it is being done manually. Theuse of a computer can allow greater sophistication.

33.4.3 Programming techniques

33.4.3.1 Bar charts

The best form of plan for site use is the bar chart (a simpleexample is shown in Figure 33.5). In this example the plannerwas required to give priority to construction of blocks A and Band to complete the housing development in 82 weeks. Brick-layers were seen to be the key resource. Note the followingaspects of the diagram:

(1) Each activity is shown in its scheduled position whichresults in efficient use of resources. The histogram showscontinuous use of the same teams of bricklayers.

(2) The logic of the inter-relationship of activities and move-ment of resource teams is shown clearly.

(3) The space within the bars can be used for figures of outputor resource demand, and there is room beneath to markactual progress.

(4) Important constraints and key dates are marked to ensurethat these are clearly communicated to all concerned withthe project.

(5) Five weeks of float have been allowed.

33.4.3.2 Line of balance

This simple technique was developed for house building and isalso useful for other forms of repetitive work, such as producingand distributing prefabricated units. The axes are the number ofcompleted units and time: the work of each gang appears as aninclined line, the inclination being related to the output of thegang.11

33.4.3.3 Location—time diagram

In cross-country jobs such as major roadworks, the erection oftransmission lines, or pipelaying, the performance of individualactivities will be greatly affected by their location and thevarious physical conditions encountered. Restricted access tothe works, the relative positions of cuttings and embankments,sources of materials from quarries and temporary borrowpits,the need to provide temporary or permanent crossings forwatercourses, roads and railways, and the nature of the ground,will all influence the continuity of the construction work. Theoutput achieved by similar resources of men and machines mayvary when they are working in different locations. In suchcircumstances the programme may best be developed on axes oflocation and time on which all obstacles or features may bemarked. The work of each resource team will again appear as aninclined bar with inclination related to the output of the gang.12

33.4.3.4 Network analysis

These techniques are used to evaluate programmes where com-plex or multiple relationships exist between a number of activi-ties. The greatest benefit is the discipline imposed on the plannerwhen compiling the logic of the network, i.e. when specifyingthe individual activities and the links between them. A further

major advantage is that the computer may be utilized to exploremany possible combinations of the timing of individual activi-ties in order to achieve really efficient use of resources. Networksare rarely the best method of communication with the peopleactually responsible for performing the constituent activities,and the results of the analyses will normally be translated intosome other form of working programme such as a bar chart.

Precedence diagrams and activity networks. The Author advo-cates the use of a simple precedence system which is illustratedin Figure 33.1. This system utilizes preprinted node-sheets andthereby enables the engineer to devote less time to drawing andmore to planning. It also offers a simple method of overlappingactivities and is easy to update and revise. Individual activitiesare represented by rectangular nodes which are linked bydependency lines to form the network.

Several overlaps are shown in the example. The figure 7 on thedependency line between activities 7 and 13 indicates thatconstruction of the plant should start a maximum of 7 monthsbefore completion of design. It has been the Author's experiencethat it is the activity durations and overlaps which change mostfrequently when updating a programme. Consequently, he hasfound that definition of overlaps in this simple manner simpli-fies revision of the programme.

Float is also identified quickly from the diagram. The imposi-tion of fixed start and completion dates in this example hasresulted in all activities displaying at least 1 month of totalfloat - as calculated from the difference between earliest andlatest start of any activity.

Precedence diagrams provide an excellent basis for the deve-lopment of cost models as illustrated when Figure 33.1 isextended to cover the operational phase of the project in Figure33.2.

33.5 Cost estimating

Estimates of cost and time are prepared and revised at manystages throughout the development of a project or contract.They are all predictions of the final outcome of the job and thedegree of realism and confidence achieved will depend on thelevel of definition of the work and the extent of risk anduncertainty. Consequently, the accuracy of successive estimatesshould improve as the project or contract develops. The mostimportant estimates prepared are probably for a project, atsanction, and for a contract, at tender, for it is at these pointsthat the client and contractor become committed.

33.5.1 Requirements of an estimate

The requirements of an estimate are:

(1) To predict the most probable cost of the works and also todefine the range within which the final cost is likely to lie.

(2) To produce a forecast of expenditure: the cashflow basedon the project programme.

These predictions will be influenced by factors peculiar to theparticular project under consideration. Location, logistics,weather, availability and capacity of resources and marketfactors will all affect the final price. The estimate must thereforebe compiled with the circumstances of the project clearly inmind and all assumptions, uncertainties and exclusions shouldbe stated. Ideally, any estimate should be presented as a mostprobable value and a tolerance together with a range of lesslikely values to emphasize that it is an estimate.

It is important to realize that the precise value of a specificsingle-figure estimate made at an early stage of the project or

Page 10: Project and 33 Management Contract - Freenguyen.hong.hai.free.fr/EBOOKS/SCIENCE AND ENGINEERING/ENGINNEERING... · report Project appraisal and definition. Conceptual design Design

contract is most unlikely to be achieved due to the uncertaintyassociated with civil engineering work.

33.5.2 Cost-estimating techniques

All these techniques rely on historical data of some kind and it isprudent to note the following points:

(1) Ideally, the data should be from a sufficiently large sampleof similar work in a similar location and constructed insimilar circumstances. Unfortunately, this is rarely the caseand corrections have to be applied.

(2) Cost data needs to be related to a specific historical date,chosen with care. Historical costs must be corrected forinflation, changes in exchange rates and market factors.

The five basic estimating techniques available to the estimatorare summarized below.

(1) Global. This term describes the 'broadest brush' categoryof technique which is derived from libraries of achievedcosts of similar projects related to the overall size orcapacity of the asset provided. This technique may also beknown as 'rule-of-thumb' or 'ballpark' estimating. Ex-amples are:(a) cost per square metre of building floor area or per

cubic metre of building volume;(b) cost per megawatt capacity of power stations;(c) cost per kilometre of roads;(d) cost per tonne of output for process plants.The technique relies entirely on historical data and there-fore must be used in conjunction with inflation indices anda judgement of the influence of the construction marketappropriate to the envisaged timing of the project. Globalestimates can only be used to give a rough indication of theorder of cost in the appraisal and definition stages ofproject development.

(2) Factorial. These techniques are used widely for earlyestimates of the cost of process plants, power stations, etc.where the core of the project consists of major items ofplant which can be identified and for which current budgetprices may be obtained from suppliers.

The techniques provide factors for a comprehensive listof peripheral costs such as pipework, electrics, instruments,structures and foundations. The estimate for each peri-pheral will be the product of its factor and the estimate forthe main plant item.13

A detailed programme is not a necessity but it is recom-mended that one is prepared. This will be valuable particu-larly in identifying problems of construction which will goundetected if the technique is applied in a purely arithmeti-cal way, and is required for cashflow prediction. Thetechnique has the considerable advantage of being predo-minantly based on current costs, thereby taking account ofmarket conditions and needing little, if any, reliance oninflation indices. Factorial techniques are not normallyreliable for site works.

(3) Manhours. This technique is only suitable for labour-intensive construction, design-office activities, and opera-tions such as mechanical erection work where reliablerecords of hourly productivity of different trades areavailable. The total manhours estimated for a given opera-tion are then costed at the current labour rates and addedto the costs of materials and equipment. The advantages ofworking in current costs is obtained.

(4) Unit rates. The estimator selects historical rates or pricesfor each item in the bill of quantities using either informa-tion from recent similar contracts, or published informa-

tion, or 'built-up' rates from his own analysis. As thetechnique relies on historical data it is subject to thegeneral dangers outlined above.

The technique is most appropriate to building andrepetitive work where the allocation of costs to specificoperations is reasonably well-defined. It is essential thatthe rates are selected from an adequate sample of similarwork with reasonably constant levels of productivity andlimited distortions arising from construction risks anduncertainties, e.g. access problems. The technique is lessappropriate for civil engineering where the method ofconstruction is more variable and where the uncertaintiesof ground conditions are more significant.

The unit rate technique does not demand an examina-tion of the programme or method of construction and theestimate is frequently compiled by the direct application ofhistorical 'prices'. It therefore does not require an analysisof the real costs of the work, neither does it encourageconsideration of the peculiarities, constraints and risksaffecting the particular project. Nevertheless, unit rateestimating is probably the most frequently used technique.It can result in reliable estimates when practised by exper-ienced estimators with good, intuitive judgement and theability to assess the realistic programme and circumstancesof the work.

(5) Operational (resource-cost). This is the fundamental esti-mating technique wherein the total cost of the work iscompiled from consideration of the constituent operationsor activities defined in the construction method statementand programme and from the accumulated demand forresources. Labour, plant and materials are costed at cur-rent rates. The advantage of working in current costs isobtained.

The most difficult data to obtain are the productivities oflabour and construction plant in the geographical locationand special circumstances of the project under consider-ation. Claimed outputs of plant are obtainable from sup-pliers' handbooks but these need to be reviewed in the lightof actual experience. Labour productivities will vary fromsite to site depending on management, organization, indus-trial relations, site conditions, etc. and also from country tocountry.

The operational technique is, by far, the best method ofevaluating uncertainties and risks, particularly those likelyto cause delay.12 Because the technique exposes the basicsources of costs, the sensitivities of the estimate to alterna-tive assumptions/methods can be investigated easily andthe reasons for variations in cost appreciated. It alsoprovides a detailed current cost/time basis for the applica-tion of inflation forecasts and, hence, the compilation of aproject cashflow.

This is the most reliable estimating technique for civilengineering work. Compilation is relatively painstakingand time consuming compared with other techniques, butwhen preparing an operational estimate the estimator willgain a realistic appreciation of the risk and special circum-stances of the project.

33.6 Project appraisal

Project appraisal is a process of investigation, review, andevaluation undertaken as the project or alternative concepts ofthe project are defined. This study is designed to assist the clientto reach informed and rational choices concerning the natureand scale of investment in the project. The core of the process isan economic evaluation - based on a cashflow analysis of all

Page 11: Project and 33 Management Contract - Freenguyen.hong.hai.free.fr/EBOOKS/SCIENCE AND ENGINEERING/ENGINNEERING... · report Project appraisal and definition. Conceptual design Design

costs and benefits which can be valued in money terms - whichis also therefore called cost/benefit analysis.

Appraisal is likely to be a cyclical process repeated as newideas are developed, additional information received and uncer-tainty reduced until the client is able to make the criticaldecision to sanction implementation of the project and committhe investment in anticipation of the predicted return.

33.6.1 Risk and uncertainty

The greatest degree of uncertainty about the future is encoun-tered early in the life of a new project. Decisions taken duringthe appraisal stage can have a very large impact on final cost,duration and benefits. The extent and effects of change arefrequently underestimated during this phase although these areoften considerable, particularly in developing countries andremote locations.

At this stage, the engineering and project management inputwill normally concentrate on providing:

(1) Realistic estimates of capital and running costs.(2) Realistic time-scales and programmes for project imple-

mentation.(3) Appropriate specifications for performance standards.

At appraisal, the level of project definition is likely to be low andtherefore risk response should be characterized by a broad-brush approach.14 It is recommended that effort should beconcentrated on:

(1) Seeking solutions which avoid/reduce risk.(2) Considering whether the extent or nature of the major risks

are such that the normal transfer routes may be unavail-able or particularly expensive.

(3) Outlining any special treatments which may need to beconsidered for risk transfer, e.g. for insurance or uncon-ventional contractual arrangements.

(4) Setting realistic contingencies and estimating tolerancesconsistent with the objective of preparing the best estimateof anticipated total project cost.

(5) Identifying comparative differences in the riskiness ofalternative project schemes.

Engineers/project managers will usually have less responsibilityfor identifying the revenues and benefits from the project: this isusually the function of marketing or development planningdepartments. The involvement of engineers/project managers inthe planning team is recommended as the appraisal is essentiallya multi-disciplinary brainstorming exercise through which theclient seeks to evaluate all alternative ways of achieving hisobjectives.

For many projects this assessment is complex, as not all thebenefits/disbenefits may be quantifiable in monetary terms. Forothers it may be necessary to consider the development in thecontext of several different scenarios (or views of the future). Inall cases, the predictions are concerned with the future needs ofthe customer or community. They must span the overall periodof development and operations of the project which is likely torange from a minimum of 8 or 10 years for a plant manufactur-ing consumer products, to 30 years for a power station andmuch longer for public works projects. Phasing of the develop-ment should always be considered.

33.6.2 Project evaluation

The process of economic evaluation and the extent of uncer-tainty associated with project development is illustrated by theappraisal of a hypothetical new manufacturing plant.

The simple precedence diagram (Figure 33.1) has been de-veloped into a flow chart (Figure 33.2) and extended to include9 years of plant operation. The diagram also gives someindication of the patterns of costs and revenue.

The plant is designed for development in two stages, the firstwith a manufacturing capacity of 5000 units and the secondraising this to the maximum of 8000 units. During an appraisalstudy, uncertainty frequently exists with regard to the demandfor the product and is indicated by the definition of a range ofpossible output. The forecast curve assumes a 20% per annumgrowth in the market but a range of 15 to 25% is consideredpossible. If the growth rate fell below the favoured 20% it islikely that stage 2 would not be implemented.

If all the predictions of costs, revenues, markets and pro-gramme over the 12-year project life were correct, the projectwould require maximum investment of £4.96 million and wouldultimately generate a surplus of £18.5 million as shown in thebasecase cumulative cashflow curve (the full line in Figure 33.3).

Other parameters used to quantify this investment could be:

Payback period 80 monthsNet present value @ 10% discount rate £6.13 millionInternal rate of return (i.r.r.) 27.6%

and it is strongly advised that a similar range of criteria areemployed when determining any investment.

It is, of course, most unlikely that those precise values will beachieved due to all the risks and uncertainties which exist at theearly stage of project development. The chain line in Figure 33.3indicates that, should the market growth rate be only 15%, thesurplus would be reduced to £12.8 million and i.r.r. to 22.9%.The obvious effect of a 6-month delay in completion of theplant, shown by the broken line in Figure 33.3 would be toreduce the surplus to £15.9 million and i.r.r. to 23.7%. A farmore serious consequence could be loss of the market to acompetitor.

% change in variable

Figure 33.6 New manufacturing plant: sensitivity diagram.This 'spider' diagram communicates the relative effect of majorvariables on the viability of the project

Inte

rnal

rate

of r

etur

n (%

)

Page 12: Project and 33 Management Contract - Freenguyen.hong.hai.free.fr/EBOOKS/SCIENCE AND ENGINEERING/ENGINNEERING... · report Project appraisal and definition. Conceptual design Design

The effect on the investment of variation in a whole range offactors is well shown in the sensitivity diagram (Figure 33.6).Each variable is considered independently and it is obvious thatmarket factors are dominant. Delay in completion is also shownto have a serious effect on the return obtained from theinvestment. The great value of this diagram is that it indicateswhere further effort is needed to reduce uncertainty, perhaps byadditional market surveys in this case. It also suggests thatmanagement policy must give priority to timely completion ofthe plant.

In practice, a combination of all these uncertainties and risksis likely to be experienced and a better prediction of theprobable range of outcome of this project can be obtained fromthe cumulative probability diagram (Figure 33.7). This diagramis generated by substituting 1000 combinations of these factorsin the basic model on a random basis in a Monte Carlosimulation.14-16 The base case prediction is seen to be optimisticwhen uncertainties are taken into account as there is a 77%probability that i.r.r. will be less than 27.6%. It is predicted thatthere is 50/50 chance of achieving an i.r.r. of 21% but thatextreme values of zero and 40% are just possible. Althoughanalyses of this type require judgement to be made on the likelyrange and probability distribution of each variable, the Authorstrongly recommends that this discipline of a rigorous riskanalysis is adopted for all major projects.

The output of power and market factors is also seen todominate the sensitivity diagram for a real project, the proposedSevern tidal power scheme,15 (see Figure 33.8). Again, the mostsensitive engineering factors are delays in completion of theworks and installations of the turbines.

Internal rate of return (%)

Figure 33.7 New manufacturing plant: cumulativeprobability diagram. There is a 77% probability that the internalrate of return will be less than the base case prediction of 27.6%

NPV (£ million)

Figure 33.8 Severn tidal power scheme: sensitivityanalysis. The amount of power produced, the selling price, and thedelay in completion of the project again have the most seriouseffect on project viability

Cost of turbinesInstallation of turbinesDelay in constructionMaterial embankment costDredging and foundation costTransmission costEnergy outputMechanical maintenanceCivil maintenance

Variable

Chan

ge in

var

iabl

e (%

)

Prob

abilit

y (%

)

Origi

nal

pred

iction

27.6

%

Page 13: Project and 33 Management Contract - Freenguyen.hong.hai.free.fr/EBOOKS/SCIENCE AND ENGINEERING/ENGINNEERING... · report Project appraisal and definition. Conceptual design Design

33.7 Engineering contracts

Construction work of all types is normally undertaken by acontractor, a specialist in the particular field of work, who isemployed for this purpose by the client. In most cases, the clientwill invite a number of suitable contractors to submit tendersand subsequently will award the contract on the basis of thelowest realistic and acceptable tendered price.

This approach is adopted worldwide and has led to thedevelopment of well-defined systems of working and StandardConditions of Contract for different types of work. Each ofthese traditional procedures has been developed to meet aparticular set of circumstances and will work well, providedtheir limitations are accepted, as the associated case law is wellestablished.

It is, however, important for engineers to realize that, becauseof the diversity of both construction work and clients' require-ments, no single uniform approach to contractual arrangementscan be specified or advocated. A number of alternative strategiesare available to the client and each contract should be formu-lated with the specific job in mind. For example, a client maywish to be directly involved in site management or may prefer todelegate this responsibility entirely to the contractor, the needfor early completion of the work may dictate that the contractoris appointed before design is completed, risks may be appor-tioned in various ways between the parties, the contractor maybe required to undertake the detailed design or to providevarying amounts of finance - these and many other consider-ations will all influence the client's contract strategy.

Obviously, this strategy will also be greatly affected by thenature of the work to be completed under the contract. Thefabrication and positioning of an offshore oil production plat-form is a high-risk venture which may involve advanced or newtechnology and will be subject to severe time constraints. Thecontract for building a chemical plant may include the provisionof unique process know-how offered by the contractor who willconsequently undertake detailed design, construction and com-missioning of the plant. Tunnelling implies uncertainty - andtherefore risk - about ground conditions, whilst minor road-works or house building are likely to involve repetitive use oftraditional techniques with relatively little financial risk and theoverriding requirement of minimum cost.16

33.7.1 Contract strategy

The term 'contract strategy' is used to describe the organizatio-nal and contractual policies chosen for the execution of aspecific project.17 The development of a contract strategy is animportant task for the client or his project manager. It com-prises a thorough assessment of the choices available for theimplementation and management of design and construction. Apattern of inter-related decisions is required which seeks tomaximize the likelihood of achievement of key project objec-tives. The selected strategy is likely to be optimal in that it mustsatisfy a variety of constraints and be sufficiently robust towithstand the uncertainty associated with the project.

The decisions taken during the development of a contractstrategy affect: (1) the responsibilities of the parties; (2) theyinfluence the control of design, construction and commissioningand, hence, the co-ordination of the parties; (3) they allocaterisk and define policies for risk management; and (4) they definethe extent of control transferred to contractors. Therefore, theyaffect cost, time and quality.

The first step in the development of a contract strategy is toidentify the areas which constitute the strategic choices. Theseare:

(1) The project management objectives as defined by theclient.

(2) The organizational system for design and construction.(3) The type of contract.(4) The Conditions of Contract and other contract docu-

ments.(5) The tendering procedure.

The project manager must then choose from the optious avail-able within each of these five strategic areas.

33.7.2 Choice of contract type

There are three essential requirements of any contract:

(1) Incentive. The aim is to provide an adequate incentive forefficient performance from the contractor. This must bereflected by an incentive for the client to provide appropri-ate information and support in a timely manner.

(2) Flexibility. The aim is to provide the client with sufficientflexibility to introduce change which can be anticipated butnot defined at the tender stage. An important and relatedrequirement is that the contract should provide for syste-matic and equitable evaluation of such changes.

(3) Risk sharing. The aim should be to allocate all risk betweenclient and contractor. This must take account of themanagement and control of the effects of risks whichmaterialize. The contractor will include a risk contingencysum in his tender as protection against the risks he has beenasked to carry.

The inter-relationship of these requirements with the type ofcontract is demonstrated in Figure 33.9 in which the require-ments are expressed in terms of contractor's incentive, client'sflexibility and exposure to risk. It is apparent that, generally, acontractor's incentive and a client's flexibility tend to be incom-patible. For example, a lump-sum contract imposes maximumincentive on the contractor but also implies a very high level ofconstraint on the client against introducing change. The con-verse is true at the other extreme of a cost-reimbursable pluspercentage fee contract.

There are many detailed points of difference between thevarious types of contract. Those of most importance to theclient in making an appropriate choice are summarized below.

Figure 33.8 Characteristics of different types ofconstruction contract

Employer's risk Max.

Contractor's MJn.incentive

Cost +% fee

Cost + fixed fee

Target cosl

Schedule of rates

Bills of quantities

Lump sum + variationsLump SUIT

Empl

oyer

's fle

xibi

lity

Page 14: Project and 33 Management Contract - Freenguyen.hong.hai.free.fr/EBOOKS/SCIENCE AND ENGINEERING/ENGINNEERING... · report Project appraisal and definition. Conceptual design Design

33.7.3 The main types of contract

Types of contract are virtually classified by their paymentsystem: (1) price-based - lump sum and admeasurement (pricesor rates are submitted by the contractor in his tender); and (2)cost-based - cost-reimbursable and target cost (the actual costsincurred by the contractor are reimbursed, together with a feefor overheads and profit).

33.7.2.1 Price-based contracts

Lump-sum contracts. Lump-sum contracts are based on asingle price tendered for the whole works. Payment may bestaged at time intervals or related to achieved milestones. Lumpsum does not necessarily imply a fixed price; in particular, pricemay be adjusted for cost escalation.

The implications are that complete, final design is available attender and that minimal changes or variations are expected. Nocontractual mechanism is specified for price adjustment andsuch contracts are therefore rarely used in engineering construc-tion.

A high degree of tender competition may be achieved and theprice may include a high level of financing by contractor.

Admeasurement contracts. These are based on bills of quanti-ties or schedules of rates in which items of work are specifiedwith quantities. Contractors then tender unit rates or pricesagainst each item. Payment is usually monthly and is derivedfrom measuring quantities of completed work and valuing atrates in the tender, or new rates negotiated from tender rates.

Mechanisms are provided for adjusting both price and time,as discussed in section 33.8 in the likely event of change. Thisfacility to introduce limited variation is frequently abused anddesign may be only partially complete at tender. Extensivechange and delay will generate claims and the final price isinvariably different from the tender total. The price will includean allowance for any financing required by the contractor and arisk contingency.

Cost-reimbursable contracts. These are based on payment ofactual cost incurred by the contractor plus a specified fee foroverheads and profit. The contractor's cost accounts are open toaudit by the client (Openbook Accounting). Payments may bemonthly in advance, in arrears, or from an imprest account.

Cost-reimbursible contracts are normally used when theclient wishes to employ a contractor at an early stage of projectdefinition and design, or when there are major risks associatedwith the contract. There is little contractual incentive for thecontractor to perform and the final price will depend both onthe extent to which risks materialize and on the efficiency of thecontractor. The client carries the risk and will therefore requireto participate in contract management.

Target-cost contracts. Target cost is based on the setting of aprobable (or target) cost for the work. The target cost willsubsequently be adjusted for major changes in the work and costinflation. The contractor's actual costs are monitored andreimbursed as in a cost-reimbursable contract. Any differencebetween actual cost and target cost is shared in a specified waybetween the client and the contractor. There is a separate fee foroverheads and profit.

By using target-cost contracts, it has been possible to achievea high degree of collaboration between the parties. They aremost suitable for high-risk contracts where the work content iswell defined, such as tunnels.18

33.7.4 Management contracting

Various forms of management contract are widely used in

building construction but are rarely appropriate to civil engi-neering works. In these systems, an external organization - themanagement contractor or construction manager - is employedspecifically to manage and co-ordinate design and constructionon behalf of the client. The systems are frequently adopted toachieve early completion of the project by 'fast tracking' or byoverlapping and integrating design and construction. They aremost appropriate for construction which can be split into aseries of well-defined contract packages, each of which isawarded immediately the relevant design is completed.

The management contractor is normally employed on a cost-reimbursable basis and, although the construction contracts areof the familiar admeasurement form, it is important to realizethat the allocation of risk between the parties may be considera-bly changed.2

33.8 Contractual measurement andvaluation

The type of contract, the level of detail required in contractualmeasurement and the method of valuation of the work are inter-related.

Several procedures are provided in admeasurement contractsfor civil engineering works for valuation and payment in respectof changes to the work defined in the contract documents.

(1) Changes to quantities of measured work listed in the bill ofquantities are priced on a pro rata basis, the actualquantity of work completed being substituted for theoriginal estimated figure in the final account. Under theInstitution of Civil Engineers19 and Federation Internatio-nale des Ingenieuers Confeils (FIDIC). Conditions ofContract there is, in theory, no limit to the adjustmentpermitted to any quantity but it should be noted that underClause 56(2) of the former (fifth edition) the tendered ratemay be varied following such adjustment. In some otherConditions of Contract, a definite range of adjustment toquantity, over which the tendered rate is deemed to bevalid, is specified.

(2) Variations to the work defined in the contract may beordered by the Engineer who will issue a written variationorder. The Engineer is empowered to fix the value of thework covered by the variation order after consultationwith the contractor and, wherever possible, utilizing ten-dered rates in the bill of quantities. Should the contractordispute the engineer's valuation, the contractor may claimadditional payment.

(3) The contractor may also claim additional payment and/orextension of time should he incur additional cost onaccount of 'unforeseen conditions' or delay. The Engineerwill assess the value of each claim from evidence submittedby the contractor.

The Engineer is empowered to settle all disputes betweenthe client and the contractor. If either party is dissatisfiedwith his decision they may then resort to arbitration.

33.8.1 Bills of quantities

The conventional British and international civil engineeringcontracts are of the admeasurement type wherein the contractprice is accumulated in the bills of quantities. These list andquantify the constituent items of work, each of which is pricedindividually by a tendering contractor. The quantities of workare stated to be the best estimate which can be made by theEngineer prior to tender: all work items are subsequentlyremeasured during the course of the contract and valued at therates tendered by the successful contractor.

Page 15: Project and 33 Management Contract - Freenguyen.hong.hai.free.fr/EBOOKS/SCIENCE AND ENGINEERING/ENGINNEERING... · report Project appraisal and definition. Conceptual design Design

The bill of quantities is one of the contract documents and hasseveral main functions:

(1) To itemize and quantify the elements of work to becompleted within the contract.

(2) To facilitate comparison of tender prices.(3) Interim and final valuation of completed work.(4) Evaluation of change and variation.

33.8.2 The concepts incorporated in the traditionalbills of quantities

The admeasurement contract developed from the lump-sumcontract in order to provide essential flexibility as jobs becomelarger and more complex and the traditional admeasurementprocedures and bills of quantities have been developed from thefollowing simple concepts:

(1) All prices are deemed to be proportional to the quantity ofwork completed: all quantities are remeasured on comple-tion of the contract.

(2) The client will pay only for completed permanent works.(3) The payment lines are specified.(4) The contractor can price the component items in any way

he wishes.(5) The tender price is to be the total price for completing the

works specified in the contract documents.

33.8.3 Development of the bills of quantities

The simple and expedient procedures outlined above provedacceptable and equitable for repetitive and labour-intensivework. They are rarely adequate nowadays for the evaluation ofplant-intensive work or for contracts including significent itemsof temporary work when there is a significant incidence ofvariation or delay. There are several reasons for this. The pricesentered in the traditional bill of quantities rarely represent thetrue cost of completing the work defined in the individual itemsas the contractor's costs are not all directly related to thequantity of work completed. It follows that any adjustment ofprice resulting from a change in quantity of a particular item isunlikely to represent the true variation in cost.

A significant part of a contractor's costs are time-related andit is these costs which are affected by disruption or delay. Time-related charges are not, however, separated in the traditional billof quantities and it is therefore not possible to evaluate systema-tically the very issues which are a major source of contractualclaims.

As the incidences of change and variation have increased,various attempts to improve measurement and valuation pro-cedures have included:

(1) Additional 'preliminary' items for overheads and specifiedfacilities to be provided by the contractor.

(2) Separation of major temporary works items.(3) Limits on the range of permissible variation for individual

billed items and for the total extent of variation within thecontract.

(4) Separation of 'method-related' charges.

33.8.4 Method-related charges

Systematic evaluation of a range of changes and variations,including delays, may be achieved by the separation of method-related charges in the bill of quantities. This approach wasintroduced in the British Civil Engineering Standard Method ofMeasurement (CESMM) in 197620 and moves away from theconcept that all charges are proportional to quantities of

completed work. Method-related charges are introduced topermit tenderers to enter their own items in the first section ofthe bill of quantities for any operations whose costs are notdirectly linked to the quantities of permanent works. The ratesentered against the bill of quantities are consequently morerealistic and are dominated by material costs.

The principal improvements in measurement procedures areseen to be:

(1) Items and prices take account of method of construction.(2) Systematic evaluation of variations and claims arising

from disruption and delay.(3) Greater similarity between cost and price.

The production of estimates in an operational form which isdirectly related to his programme has greatly facilitated costforecasting by the contractor. Similarly the separation ofmethod-related charges in the bill of quantities permits themeaningful correlation of price and time which is essential forcashflow forecasts by the contractor, budget forecasts by theclient and the mutual evaluation of contractual changes.

Important points to note are:

(1) Method-related charges are specified as either fixed ortime-related and are entered in the Preliminary and Generalsection of the bill of quantities. They are all priced as LumpSums.

(2) Where the contractor enters such method-related itemsarising from his method of construction, they must bedefined in sufficient detail for the Engineer to be able toidentify the particular resource.

(3) It is most important to note what method-related chargesare not subject to remeasurement. They may, however, beadjusted where relevant under a variation order.

33.8.5 Pricing and tendering policy

The contractor may translate cost into the priced items in thebill of quantities in any way he wishes, i.e. he may separate all orsome of his method-related charges and 'weight' items toimprove cashflow. In doing so, he must consider both the effecton his investment and the possible consequences of variations tothe work defined in the bill of quantities. The incentive for acontractor to separate method-related charges normally stemsfrom an improvement in cashflow; in consequence, he providesless investment and may reduce his tender price.

33.9 Project managementThe responsibility of the project manager normally spans de-sign, construction and commissioning. His function is to controlthe sequence of events and decisions leading to the completionof the project. Indecision is costly, as resources - design teams,manufacturers and contractors - are employed and will requirecompensation if their work is disrupted. Nevertheless, change isa characteristic of the engineering phase of projects involvingconstruction and the project manager must be prepared to takethe necessary corrective action.

If he is to fulfil his task of control of the realization of theproject on behalf of the client, the project manager cannotdivorce decisions taken on engineering matters from all otherfactors affecting the investment. Control may only be achievedby regular reappraisal of the project as a whole so that thecurrent situation in the design office, on fabrication, on thesupply of materials, and on site may be related to the latestmarket predictions. If this is done the advantage to be gained,say, from early access of land may be equated with any

Page 16: Project and 33 Management Contract - Freenguyen.hong.hai.free.fr/EBOOKS/SCIENCE AND ENGINEERING/ENGINNEERING... · report Project appraisal and definition. Conceptual design Design

additional costs in full knowledge of the value of early or timelycompletion. The continual updating of a simple 'time andmoney' model of the project originally compiled for appraisal asillustrated in section 33.6 will greatly facilitate effective controlduring the engineering phase.21

33.9.1 Guidelines for project management

The project management process is briefly summarized below:

(1) The success of a project or contract depends greatly onthe management effort expended by the client prior tosanction and by both parties prior to award of a contract.

(2) The client commits himself to investment in the project onthe basis of the appraisal completed prior to sanction.The appraisal must be realistic and identify all risk,uncertainties and potential problem areas. Single-figureestimates are misleading and should be supported byfigures showing the range of likely outcome of the invest-ment.

(3) The client has a crucial role to play during implemen-tation of the project, and the early appointment of anexperienced project manager to pursue his interests isessential. He must be supported by an adequate projectteam set up in good time. The function of this team is co-ordination of all aspects of the project and particularlythe contribution of the client organization.

The prime roles of the project manager are to drive theproject forward and to think ahead; he must thereforedelegate routine functions and concern himself with anyproblem areas.

(4) It is essential that project management ensures that theclient clearly defines the project objectives together withthe ranking of their relative importance. The likelihood ofa successful project is greatly improved when all keymanagers of design, construction and supporting groupsare fully informed and committed to these objectives. Theproject objectives should also be communicated to theother parties (contractors, consultants, etc.) involved inproject implementation.

The dominant considerations must be fitness for pur-pose of the completed project and safety during both theconstruction and operation phases. Thereafter, the nor-mal primary project objectives are concerned with cost,time and quality. These are inter-related and may conflict.

The fact that the client does not see any return on hisinvestment until the project is commissioned suggests thattimely completion should be a prime objective.

(5) Engineering projects are normally of short duration andare completed against a demanding time-scale. Adequatestaff of the right quality must therefore be appointed andgiven training in the appropriate techniques and pro-cedures. All staff concerned with contract managementmust be familiar with the contractual proceduresemployed.

(6) Although the scope of the project will be agreed atsanction it is probable that conceptual design, which willdetermine the final layout and size of the functional units,will follow early in the engineering phase. It is recom-mended by the Author that the conceptual design isrigorously reviewed as this is the main opportunity bothfor cost saving and for ensuring that the proposals meetthe client's objectives. Particular attention should begiven at this stage to subsequent operation and mainten-ance of the project.

(7) Effective control of the project or contract will only beachieved through continual planning and replanning.Management effort should be concentrated on the present

and the future: time devoted to the reporting and collec-tion of historical data should be kept to a minimum.

In his planning, the client must take a broad view of theproject and aim to co-ordinate design, construction,commissioning and subsequent operation and mainten-ance. Interaction of contractors, access, statutory require-ments and public relations must all be considered.

A contractor will plan in more detail and aim to achievecontinuous and efficient deployment of his resources.Because of the greater likelihood of change, the contrac-tor's programme should be flexible and subject to con-stant review.

(8) The plan used by senior staff should clearly show thefinancial consequences of alternative courses of actionand of indecision. It is therefore convenient to develop theplan as a time-and-money model of the project or con-tract which will react realistically to changes in timing,method, content and cost of work. Realism is largelydependent on the correct definition and allocation ofcosts and revenues as either fixed, time-related or quan-tity-proportional charges.

Time-related costs are significant in all types of con-struction work and predominate in many civil engineeringprojects. Adherence to the programmed time schedule forthe work will therefore also control both cost and invest-ment.

(9) Time lost at the beginning of a project can rarely berecovered: particular attention must therefore be given tothe start-up of the project. Similarly, sufficient time mustbe allowed for mobilization by each contractor.

(10) Consideration of alternative contract strategies will fre-quently focus attention on deficiency of information andon the problems which will hinder the project objectives.Selection of an appropriate contract strategy at an earlystage of project implementation is perhaps the mostimportant single activity of the project management team.

(11) Appointment of a contractor on the sole criterion oflowest bid price will not necessarily lead to a harmoniouscontractual relationship. The lowest tender may not pro-duce the lowest contract price.

Both parties are making their commitment at this pointand should be fully aware of both the client's objectivesand the contractual responsibilities.

Selective tendering followed by rigorous bid appraisal,including study of the contractor's programme and re-source allocation, will do much to ensure that the con-tractor has not misjudged the job and that his price isrealistic. The production of his own operational type ofcost estimate will greatly aid the project manager in thisappraisal.

The client must check that all his obligations can behonoured before award of the contract.

(12) The items in the bill of quantities or other contractualfinancial document should reflect the method of construc-tion. Similarity between the tendered prices and thecontractor's costs will greatly aid evaluation of changeand equitable adjustment of price for inflation.

(13) Throughout the implementation period of the project theclient or his representative will inspect and approve thequality of workmanship of contractors and manufac-turers. Again, an adequate number of staff with relevantexperience must be employed. Prior definition and agree-ment of acceptable standards is essential and all partiesshould be aware of tolerances. There is a tendency fordesign engineers to specify unnecessarily high standards,the achievement of which may prove difficult and/orexpensive. The desired quality of workmanship mustalways be considered in relation to the client's other prime

Page 17: Project and 33 Management Contract - Freenguyen.hong.hai.free.fr/EBOOKS/SCIENCE AND ENGINEERING/ENGINNEERING... · report Project appraisal and definition. Conceptual design Design

objective, usually timely completion and economical cost.(14) Clients frequently underestimate both the extent and

consequence of change. The project manager shouldassess rigorously the cost and benefit of all design changesbefore they are implemented. Priority should be given totimely completion of the project.

The better organized the contractor, the more likely itis that he is working to a tight, well-resourced pro-gramme. The disruptive effect of variation may thereforebe serious.

Modifications to manufacturing plant are sometimesbest implemented during some future shutdown of theplant for maintenance.

(15) Involvement in prolonged bargaining over claims is a signof failure. Evaluate and agree payment for variations andclaims as the job progresses. The valuation should bebased on prices, resource output and efficiencies similar tothose incorporated in the contractor's tender.

(16) Projects and contracts are managed by people who aredirecting and communicating continuously with otherhuman beings. Great attention must be paid to theselection and motivation of staff. Personality and abilityto think ahead are as important as technical know-how.

Project and contract management staff must be givenadequate authority to manage in their dynamic workingenvironment without continual reference to head office.

For both the client and contractor, one man in eachorganization - the project/contract manager - must ulti-mately be responsible and be known to be responsible, forthe realization of the project or contract. Each must beidentified with, and committed to, the project.

References

1 Institution of Civil Engineers (1979) Civil engineering procedure.Thomas Telford, London.

2 Hayes, R. W., Perry, J. G. and Thompson, P. A. (1983)Management contracting. Construction Industry Research andInformation Association, Report No. 100, CIRIA, London.

3 National Economic Development Office (1983) Faster building forindustry. HMSO, London.

4 Ninos, F. E. and Wearne, S. H. (1986) 'Control of projects duringconstruction, Proc. Instn Civ. Engrs, 80, 931.

5 Barnes, N. M. L. (1978) 'Human factors in cost control.' Proc. 5thInternational Cost Engineering Congress. Danish Association ofCost Engineers, Utrecht, pp. 244-248.

6 Neil, J. M. (1982) Construction cost estimating for project control.Prentice-Hall, Englewood Cliffs, New Jersey.

7 National Economic Development Office (1975) The public clientand the construction industries. HMSO, London.

8 Power, R. D. (1985) Quality Assurance in civil engineering.

Construction Industry Research and Information Association,Report No. 109, CIRIA, London.

9 Davies, V. J., Dodd, L. A., Mills, T. R., Tietz, S. B., Woods, D.R., Barker, J. E., King, F. W., Harlow, W. A., Summersgill, L,Rust, C. E., Eye, D. and Beagley, C. (1986) 'Conference onEngineering for safety.' Proc. Instn Civ. Engrs, 80, 13-119;(discussion, February 1987).

10 New Civil Engineer (1986) 'ICE to press for greater safetyenforcement', New Civ. Engr, no. 718.

11 Lumsden, P. (1968) The line of balance method. Pergamon Press,Oxford.

12 Thompson, P. A. (1981) Organization and economics ofconstruction. McGraw-Hill, Maidenhead.

13 Institution of Chemical Engineers (1979) A new guide to capitalcost estimating. Institution of Chemical Engineers, London.

14 Perry, J. G. and Hayes, R. W. (1985) 'Risk and its management inconstruction projects'. Proc. Instn Civ. Engrs, 78, 499-520.

15 University of Manchester Institute of Science and Technology(1980) Severn tidal power: sensitivity and risk analysis. ProjectManagement Group. UMIST, Manchester.

16 Science and Engineering Research Council (1987) Riskmanagement in engineering construction. SERC, Thomas Telford,London.

17 Perry, J. G. (1988) Contract strategies for construction. Collins,London.

18 Perry, J. G., Thompson, P. A. and Wright, M. (1982) Target andcost-reimbursable construction contracts. Construction IndustryResearch and Information Association, Report No. 85, CIRIA,London.

19 Institution of Civil Engineers (1979) Conditions of contract, 5thedn. ICE, London.

20 Institution of Civil Engineers (1985) Civil engineering standardmethod of measurement. Thomas Telford, London.

21 Thompson, P. A. and Willmer, G. (1985) 'Caspar - a program forengineering project appraisal and management. Proc. Civ. Comp.,1,83.

Bibliography

Abrahamson, M. W. (1984) 'Risk management.' Intnl. Const. Law Rev. 1,241-264.

Darnell, H. et al. (1986) Total project management. Booklets 1 to 3, TheAsset Management Group, British Institute of Management, London.

Derrington, J. A. and Barnett, M. J. N. (1986) 'Civil engineering projects- what is value for money?' Proc. Instn Civ. Engrs, 80, 1589-1596.

Franks, J. (1984) Building procurement systems. Chartered Institute ofBuilding, London.

Gaisford, R. W. (1986) 'Project management in the North Sea. IntnlJ.Project Mangmnt, 4, 1.

Harris, F. and McCaffer, R. (1977) Modern construction management.Crosby Lock wood Staples, London.

Harrison, F. L. (1983) Advanced project management. Gower, London.Kennawry, A. (1984) 'Errors and failures in building: why they happen

and what can be done to reduce them.' Intnl Const. Law Rev. 2, 5779.Pilcher, R. (1985) Project cost control in construction. Collins, London.