Project: ACT Acorn Feasibility Study Terms of Use The ACT Acorn Consortium partners reserve all rights in this material and retain full copyright. Any reference to this material or use of the material must include full acknowledgement of the source of the material, including the reports full title and its authors. The material contains third party IP, used in accordance with those third party’s terms and credited as such where appropriate. Any subsequent reference to this third party material must also reference its original source. The material is made available in the interest of progressing CCS by sharing this ACT work done on the Acorn project. Pale Blue Dot Energy reserve all rights over the use of the material in connection with the development of the Acorn Project. In the event of any questions over the use of this material please contact [email protected].
68
Embed
Project: ACT Acorn Feasibility Study · The current assessment of both the onshore environmental impact and offshore environmental impact indicates minimal impact beyond current activities.
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Project: ACT Acorn Feasibility Study
Terms of Use
The ACT Acorn Consortium partners reserve all rights in this material and retain full copyright. Any reference to
this material or use of the material must include full acknowledgement of the source of the material, including
the reports full title and its authors. The material contains third party IP, used in accordance with those third
party’s terms and credited as such where appropriate. Any subsequent reference to this third party material
must also reference its original source. The material is made available in the interest of progressing CCS by
sharing this ACT work done on the Acorn project.
Pale Blue Dot Energy reserve all rights over the use of the material in connection with the development of the
Acorn Project. In the event of any questions over the use of this material please contact [email protected].
ACT Acorn, project 271500, has received funding from BEIS (UK), RCN (NO) and RVO (NL), and is co-funded by the European Commission under the ERA-Net instrument of the Horizon 2020 programme. ACT Grant number 691712.
Prepared by: Frances Harding supported by Tim Dumenil, Charlie Hartley and Tiana Walker (all Pale Blue Dot Energy)
Approved by: Steve Murphy, ACT Acorn Project Director
Disclaimer:
While the authors consider that the data and opinions contained in this report are sound, all parties must rely upon their own skill and judgement when using it. The authors do not make
any representation or warranty, expressed or implied, as to the accuracy or completeness of the report. The authors assume no liability for any loss or damage arising from decisions
made on the basis of this report. The views and judgements expressed here are the opinions of the authors and do not reflect those of the client or any of the stakeholders consulted
during the course of this project.
The ACT Acorn consortium is led by Pale Blue Dot Energy and includes Bellona Foundation, Heriot-Watt University, Radboud University, Scottish Carbon Capture and Storage (SCCS),
University of Aberdeen, University of Edinburgh and University of Liverpool.
Amendment Record
Rev Date Description Issued By Checked By Approved By
01 29/05/18 First issue C Hartley T Dumenil S Murphy
13.0 CONTENTS OF THE ENVIRONMENTAL STATEMENT ................................................................................................................................................................ 61
14.0 CONCLUSIONS AND NEXT STEPS ............................................................................................................................................................................................... 64
TABLE OF CONTENTS .................................................................................................................................................................................................................................... 4
ACORN DEVELOPMENT CONCEPT ..................................................................................................................................................................................................... 14
LAYOUT OF THE ENVIRONMENTAL SCOPING REPORT ......................................................................................................................................................................... 18
5.3.1 Existing CO2 Capture Plant .................................................................................................................................................................................................... 19
5.3.2 New CO2 Capture Plant ......................................................................................................................................................................................................... 20
5.3.3 Compression and Dehydration .............................................................................................................................................................................................. 20
5.3.4 Material Selection .................................................................................................................................................................................................................. 20
LANDSCAPE AND TOPOGRAPHY ........................................................................................................................................................................................................ 22
SITE DESCRIPTION AND EXISTING LANDSCAPE CHARACTER ............................................................................................................................................................... 22
POTENTIAL LOCATIONS FOR A NEW BUILD CAPTURE PLANT ............................................................................................................................................................... 26
7.2.1 Ecology Rattray to Kirkton Head SINS .................................................................................................................................................................................. 27
7.2.2 Water Resources River Blackwater ....................................................................................................................................................................................... 27
7.2.4 Traffic and Transport .............................................................................................................................................................................................................. 28
7.2.5 Air Quality ............................................................................................................................................................................................................................... 28
7.2.6 Noise and Vibration ................................................................................................................................................................................................................ 28
TRANSPORT .................................................................................................................................................................................................................................... 30
8.2.1 Facilities Re-use Versus New Infrastructure .......................................................................................................................................................................... 30
8.2.2 New 16” Infield Pipeline to the Acorn CO2 storage site Manifold .......................................................................................................................................... 32
APPROACH FOR OFFSHORE FACILITIES ............................................................................................................................................................................................. 32
8.3.3 Control System and Umbilical ................................................................................................................................................................................................ 33
9.4.1 Fish Populations .................................................................................................................................................................................................................... 37
PROTECTED AREAS ......................................................................................................................................................................................................................... 39
SEABED AND HABITAT DISTURBANCE ................................................................................................................................................................................................ 42
DISCHARGES TO SEA ....................................................................................................................................................................................................................... 43
PREVIOUS AND ON-GOING CONSULTATION........................................................................................................................................................................................ 59
SUMMARY OF CONSULTEES ............................................................................................................................................................................................................. 59
13.0 CONTENTS OF THE ENVIRONMENTAL STATEMENT ................................................................................................................................................................ 61
14.0 CONCLUSIONS AND NEXT STEPS ............................................................................................................................................................................................... 64
NEXT STEPS ................................................................................................................................................................................................................................... 64
FIGURE 2-2: KEY AREAS OF INNOVATION ......................................................................................................................................................................................................... 12
FIGURE 2-3: ACT ACORN WORK BREAKDOWN STRUCTURE .............................................................................................................................................................................. 12
FIGURE 2-4: ACORN OUTLINE MINIMUM VIABLE DEVELOPMENT PLAN ............................................................................................................................................................... 14
FIGURE 2-5: ACORN BUILD OUT SCENARIO FROM THE 2017 PCI APPLICATION ................................................................................................................................................... 15
FIGURE 6-1: AERIAL PHOTOGRAPH OF THE ST FERGUS TERMINAL (TOTAL, 2009) ............................................................................................................................................. 22
FIGURE 6-3: ECOLOGICAL DESIGNATINS, ADAPTED FROM (ERM, 2007) ............................................................................................................................................................ 25
FIGURE 7-1: APPROXIMATE BOUNDARIES OF THE FOUR OPERATIONS (ADAPTED FROM GOOGLE MAPS, 2017) .................................................................................................... 26
FIGURE 7-2: AVAILABLE LAND SOUTH OF THE NSMP PHASE 3 PLANT, (NSMP, 2017) ....................................................................................................................................... 27
FIGURE 8-1: PIPELINE ROUTE FOR ACORN CO2 STORAGE SITE (ATLANTIC PIPELINE IS SHOWN IN GREEN) ........................................................................................................... 31
FIGURE 8-2: INFIELD PIPELINE ROUTE FOR ACORN CO2 STORAGE SITE (NEW 16” PIPELINE SHOWN IN BLACK) ..................................................................................................... 32
TABLE 2-1: ACT ACORN MILESTONES AND DELIVERABLES .............................................................................................................................................................................. 13
TABLE 8-1: UTM COORDINATES FOR ACORN CO2 STORAGE SITE MANIFOLD AND SUBSEA WELL ......................................................................................................................... 30
The circalittoral mixed sediments in the nearshore sections of the Atlantic &
Cromarty export pipeline are relatively biodiverse. The communities appear to
have recovered after the installation of the Atlantic pipeline and adapted to its
presence. BG completed stakeholder engagement with the JNCC, (BG Group,
2016), which suggested that further disturbance of the habitat in this area, for
example by removing a buried pipeline, would be undesirable as it would initiate
a further recovery period. The presence of sabellaria spinulosa accumulations
at the extreme of their geographic and depth range, even if they are not
considered at present to form a continuous reef, suggests that unnecessary
disturbance of this habitat should be avoided. Thus, consideration of the above
must be made within the Acorn EIA to address the impact of laying the umbilical.
D14 Outline Environmental Impact Assessment Permits and Consents
ACT Acorn Consortium Page 46 of 68
11.0 Permits and Consents
An initial consents register has been prepared for the capture plant, onshore
infrastructure and offshore infrastructure. The register forms part of D14 ACT
Acorn Outline Environmental Impact Assessment (Pale Blue Dot Energy, 2018).
This register is reflective of the current stage of the project and therefore may
not represent a comprehensive list of all permit, licences, application
notifications and consents that would be required through the full life cycle of the
project. Many of these are developed and understood through design
development of the project. It is recommended that this register provides a basis
to understand the project needs from business planning to concept select stage.
This document should be subject to detailed review at each project stage gate
to allow it to be updated and brought in line with the project concept and
understanding at that stage.
The onshore element of the project will take place on an existing Control of Major
Accident Hazards (COMAH) regulated industrial site. The consents register
covers key terrestrial authorisations required to construct and operate the
capture plant in terms of planning, environmental and health and safety based
on the current regulatory framework. At this stage, 13 key terrestrial
authorisations have been identified. These are listed in Table 16-1.
The offshore element of the project will take principally at the Acorn injection site
which is currently planned to be approximately 80 north west of St Fergus. The
consents register covers key terrestrial and marine authorisations required to
construct and operate the capture plant in terms of planning, environmental and
health and safety based on the current regulatory framework. At this stage, 26
key terrestrial and marine authorisations have been identified. These are listed
Table 16-1.
D14 Outline Environmental Impact Assessment Permits and Consents
ACT Acorn Consortium Page 47 of 68
Onshore Consents Register
Aspect Requirement Determining Body Comment
Planning Permission
Planning permission for capture plant under the Town and Country Planning (Scotland) Act (TCPA) 1997 (as amended by the Planning etc. (Scotland) Act 2006).
Aberdeenshire Council (AC).
Planning permission for the transmission pipeline under the Pipeline Act 1962 and TCPA 1997.
AC.
Due to the small scale of the pipeline ~1km and low environmental sensitivity we assume that the pipeline would not be EIA development and could either be rolled up into the application for the capture plant or be subject to its own planning application.
Based on the assumption that the proponent is not a public gas transporter and the proponent can apply under the Gas Transporter Pipe-line Works (Environmental Impact Assessment) (Amendment) Regulations 2007.
Environmental Impact Assessment (EIA)
Subject to the EIA screening opinion / direction EIA for the capture plant under the Town and Country Planning (Environmental Impact Assessment) (Scotland) Regulations 2011.
AC. It may be possible to screen the capture plant out of the need for EIA particularly if the existing SAGE facility is used. This will be confirmed during the next phase.
Environmental Permit
Environmental Permit for the operation of the capture plant under the Pollution Prevention and Control (Scotland) Regulations 2012.
The Scottish Environment Protection Agency (SEPA).
Application to vary an existing permit or a new permit subject to agreement with SEPA.
The competent authority will vary for planning and permitting. For planning AC; for permitting SEPA.
The need for, and level of assessment will vary depending on potential (if any) pathways for effects to occur on nature sites.
Water Abstraction
A water abstraction license is subject to the Water Environment (Controlled Activities) (Scotland) Regulations 2011 more commonly known as the Controlled Activity Regulations (CAR).
SEPA. On the assumption that there is not sufficient ‘headroom’ within the existing license it may also be possible to use the existing terminal operator extraction license.
Hazardous Substance Consent
Consent for Hazardous Substances under the Planning (Hazardous Substances) (Scotland) Regulations 2015.
AC. Subject to the capture technology included within the project e.g. amines.
European Protected Species
European protected species license (i.e. for badgers, bats, Great Crested Newts etc.) under The Conservation of Habitats and Species Regulations 2010 and Habitats Regulations 2010
Scottish Natural Heritage (SNH) and if applicable Marine Scotland
May be required depending on which species, if any are present within and around the project area and the effect of the projects upon those species present.
Building Regulations Approval
Building Regulations Approval under Building (Scotland) Regulations 2017 (as amended).
AC. Detailed design to be completed before Building Regulations application(s) can be made.
D14 Outline Environmental Impact Assessment Permits and Consents
ACT Acorn Consortium Page 48 of 68
Aspect Requirement Determining Body Comment
EU ETS Permit EU ETS Greenhouse Gas Emissions Trading Permit under the Greenhouse Gas Emissions Trading Scheme Regulations 2012.
The Greenhouse Gas Emissions Trading Scheme Regulations 2012.
Installations covered by the Scheme are required to monitor and report their emissions. At the end of each year they are required to surrender allowances to account for their installation’s actual emissions. They may use all or part of their allocation and have the flexibility to buy additional allowances or to sell any surplus allowances generated from reducing their emissions below their allocation.
REACH Registration Evaluation, Authorisation and restrictions of Chemical Regulations.
The Competent Authority is hosted by the Health and Safety Executive (HSE), working with SEPA and other government departments.
Subject to the capture technology included within the project. There could be a requirement to register as a downstream user of chemicals, e.g. amines.
COMAH Variation to COMAH Safety Report under the Control of Major Accident Hazards Regulations 2015.
The HSE and SEPA are jointly the Competent Authority (CA) for COMAH in Scotland.
The CO2 stripping process uses chemicals such as amines that, depending upon the characteristics and the volumes stored and used in process, may be a qualifying substance under COMAH. The CA has published guidance on the storage of bulk hazardous materials. If the amine to be used falls under the COMAH regulations, the detailed design will need to incorporate specific consideration on secondary and tertiary containment provisions.
Pipeline Operational Safety
SI 1996/825 The Pipeline Safety Regulations 1996 (PSR) - Major Accident Emergency Plan and notification prior to construction.
HSE.
PSR require a local authority to prepare emergency plans for pipelines which have the potential to cause a major accident for pipelines conveying ‘dangerous fluids’, defined in Schedule 2 of the Regulations. The Regulations also require a pipeline operator to establish emergency procedures for such pipelines.
CDM The Construction (Design and Management) Regulations 2015.
HSE.
During the design and construction phase of a project there are key responsibilities for safety management that lie with the Client, the appointed Construction Design and Management Coordinator (CDMC), designers and the appointed principal contractor. Provided that these responsibilities are implemented in line with regulation, all relevant safety management considerations should be met.
Table 11-1: Onshore consents register
D14 Outline Environmental Impact Assessment Permits and Consents
ACT Acorn Consortium Page 49 of 68
Offshore Consents Register
Reference Consent / License Title
Statutory Instrument
Consent to: Key
Project Elements
Determining Authority
Summary of Key Consent / License Aspects
S01.0 Planning Permission
Town and Country Planning (Scotland) Act 1997 (as Amended by the Planning etc. (Scotland) Act 2006).
Add new pipework / new pipeline
St Fergus to Atlantic & Cromarty link
Aberdeenshire Council
S02.0 Pipelines Work Authorisation
Petroleum Act 1998
Add new pipework / new pipeline
St Fergus to Atlantic & Cromarty Link
Department of Business, Energy and Industrial Strategy (BEIS)
Need to provide Pipeline/flowline details, details on rock dumping, chemical discharges etc. Approval of PWA may be linked to Environmental Statement approval, therefore approval period may be extended.
S03.1 PON15C Approval
Offshore Petroleum Production and Pipelines (Assessment of Environmental Effects) Regulations 1999 (SI 1999/360)
Change Atlantic & Cromarty pipeline to CO2 duty
CO2 export pipeline
OGREP/EMT
1. Uncertain if required for change of use of pipeline to CO2 duty.
2. Linked to Environmental Statement for overall Project. Even if the pipeline was included in an approved Environmental Statement, a PON15C may still be required.
3. OGA currently advise 6 months maximum approval process for oil and gas Environmental Statement.
4. PON15C also used for Chemical Permit application. Currently, if a preliminary environmental investigation indicates that the project or modification is unlikely to have a significant adverse effect on the environment, and none of the mandatory conditions apply, then the operator may apply for a dispensation from the requirement to undertake the full Environmental Statement process (i.e. a Direction). The procedure for doing this is to complete a Petroleum Operations Notice 15 (PON15) and submit this to BEIS.
The PON 15 requires detail about the proposed project and the environmental sensitivities of the area. It may be useful to prepare a preliminary environmental assessment as background to the PON. If a Direction is wanted, then it must be explicitly requested as part of the PON 15 submission.
Relevant Considerations will be included within the Offshore Environmental Statement.
S03.2
Chemical Permit (PON15C Approval)
Offshore Chemicals Regulations 2002 (SI2002/1355)
Use / Discharge of chemicals during pipeline installation, commissioning, maintenance, repair and
Atlantic & Cromarty export pipeline
OGA
D14 Outline Environmental Impact Assessment Permits and Consents
ACT Acorn Consortium Page 50 of 68
Reference Consent / License Title
Statutory Instrument
Consent to: Key
Project Elements
Determining Authority
Summary of Key Consent / License Aspects
decommissioning operations.
S03.3
Approval of updated Major Accident Prevention Document
SI 1996/825 The Pipeline Safety Regulations 1996 (PSR)
Re-use Atlantic & Cromarty pipeline
Atlantic & Cromarty export pipeline
Health & Safety Executive (HSE)
1. Existing MAPD to require update/ re-development and submission to reflect changes due to CCS.
S03.4
Notification before use / re-use of a major accident hazard pipeline
1. Notification anticipated to be required prior to commencement of re-use of pipeline
2. Minimum 14-day notification required.
S03.5 Notification in other cases
SI 1996/825 The Pipeline Safety Regulations 1996 (PSR) Reg 22
Atlantic & Cromarty export pipeline
Health & Safety Executive (HSE)
1. Notification anticipated to be required for change of use to CO2 duty.
2. Minimum 3-month approval period.
3. Some uncertainty surrounding requirements for change of use from natural gas to CO2 and associated legislation.
S04.0 Greenhouse Gas Permit
Greenhouse Gas Emissions Trading Scheme Regulations 2012
Transport Greenhouse Gas
Combustion activity
SEPA
D14 Outline Environmental Impact Assessment Permits and Consents
ACT Acorn Consortium Page 51 of 68
Reference Consent / License Title
Statutory Instrument
Consent to: Key
Project Elements
Determining Authority
Summary of Key Consent / License Aspects
S05.1 Exploration Licence
Energy Act 2008 / Petroleum Act 1998
Explore the store OGA
1. Non-intrusive exploration activities, in areas below the low water mark, are already regulated under the Petroleum Act 1998. Since the activities involved in such exploration do not depend on its ultimate purpose, BEIS have adapted the existing Exploration Licence, issued under the Petroleum Act, so that it becomes a combined licence issued under the Petroleum Act and the Energy Act 2008;
2. The amended exploration licence covers any combination of exploratory activities relating to petroleum, carbon dioxide storage, or storage and gas unloading of natural gas as applicable (e.g. cover seismic, gravity and magnetic surveys, sample collection and shallow drilling).
3. An Exploration Licence is currently valid for three years, and it is renewable on request. The cost of the licence is currently £500, which covers the internal departmental costs of administering the regime.
4. Agreement to the award of an Exploration Licence does not in any way replace the need for consents, in relation to these activities, required by the Offshore Marine Conservation (Natural Habitats &c.) Regulations 2007.
5. For the purposes of such exploration a developer will not be required to have a Crown Estate lease or a carbon storage licence.
Offshore Petroleum Activities (Conservation of Habitats) Regulations 2001, (SI 2001/1754)
Store data gathering
OGA
1.These Regulations cover seismic survey or geological survey in offshore waters and require written consent from the Secretary of State before undertaking a seismic or geological survey.
2. Amendments made under the 2007 Regulations extend this requirement to include all UK waters. New Guidance incorporating the 2007 amendments is currently being drafted.
3. Consent for survey is required for all seismic surveys and high resolution seismic site surveys on the UKCS. Additional requirements may also apply within licence conditions.
4. Application for Consent must be made using the PON14A. If the survey involves several survey techniques, a single PON14A should be submitted.
5. Relevant Considerations will be included within the Offshore Environmental Statement
D14 Outline Environmental Impact Assessment Permits and Consents
ACT Acorn Consortium Page 52 of 68
Reference Consent / License Title
Statutory Instrument
Consent to: Key
Project Elements
Determining Authority
Summary of Key Consent / License Aspects
S05.3 Combined Operations Notification
SI 2005/3117 Offshore Installations (Safety Case) Regulations 2005 (SCR05)
Operation of mobile drilling rig alongside existing fixed installation
Acorn
Health & Safety Executive (HSE)
1. Required for use of mobile drilling rig during workovers ops and drilling.
2. Required at least 21 days prior to combined operation.
S06.1
Chemical Permit (PON15B Approval)
Offshore Chemicals Regulations 2002 (SI2002/1355)
Chemical use / discharge when drilling for new or sidetracked wells, including exploration, appraisal, injection and monitoring wells
Drilling new wells
OGA 1. Submission of PON 15B.
2. WONS notification (PON 4 - Consent to drill) also required prior to drilling.
S06.2 OPPC Permit
Offshore Petroleum Activities (Oil Pollution Prevention and Control) Regulations 2005 (SI2005.2055), as amended
Discharge or reinjection of any aqueous well work-over, intervention and service fluids contaminated with reservoir hydrocarbons when drilling new or sidetracked wells, including exploration, appraisal, injection and monitoring wells
Drilling new wells
OGA 1. Submission of OPPC Permit Application. 2. WONS notification (PON 4 - Consent to drill) also required prior to drilling.
D14 Outline Environmental Impact Assessment Permits and Consents
ACT Acorn Consortium Page 53 of 68
Reference Consent / License Title
Statutory Instrument
Consent to: Key
Project Elements
Determining Authority
Summary of Key Consent / License Aspects
S06.3 PON15B Approval
Offshore Petroleum Production and Pipelines (Assessment of Environmental Effects) Regulations 1999 (SI 1999/360) (and Offshore Petroleum Activities (Conservation of Habitats) Regulations 2001, (SI 2001/1754))
Drilling new or sidetracked wells, including exploration, appraisal, injection and monitoring wells
Drilling new wells
OGA
1. Linked to Environmental Statement for overall project. Even if the wells were included in an approved Environmental Statement, a PON15B will still be required in support of each of the well consents. 2. Uncertain if drilling for CO2 injection / monitoring several years into the project will trigger requirement for full Environmental Statement. 3. WONS notification (PON 4 - Consent to drill) also required prior to drilling. 4. PON15B also used for chemical permit application. 5. Conservation of Habitats Regulations require that an environmental assessment identify any habitats or species covered by the Conservation (Natural Habitats &c) Regulations 1994, determine the likely impacts on them and where an adverse impact on a site integrity are likely, propose mitigation and propose an appropriate system to manage the mitigation measures and other commitments identified to remove of reduce the potential impacts. These findings should be documented in the Environmental Statement as well as providing sufficient information to inform any Appropriate Assessment which may be undertaken by BEIS.
Currently, if a preliminary environmental investigation indicates that the project or modification is unlikely to have a significant adverse effect on the environment, and none of the mandatory conditions apply, then the operator may apply for a dispensation from the requirement to undertake the full Environmental Statement. process (i.e. a Direction). The procedure for doing this is to complete a Petroleum Operations Notice 15 (PON15) and submit this to BEIS. The PON 15 requires detail about the proposed project and the environmental sensitivities of the area. It may be useful to prepare a preliminary environmental assessment as background to the PON. If a Direction is wanted then it must be explicitly requested as part of the PON 15 submission.
D14 Outline Environmental Impact Assessment Permits and Consents
ACT Acorn Consortium Page 54 of 68
Reference Consent / License Title
Statutory Instrument
Consent to: Key
Project Elements
Determining Authority
Summary of Key Consent / License Aspects
S07.1 Carbon Storage licence
Storage of Carbon Dioxide (Licensing etc) (Scotland) Regulations 2011
Appraisal of the store. Drilling and test injection of CO2
Intrusive exploration and test injection activities
OGA
1. Further to the obligations of the EU CCS Directive the UK Government made provisions in the 2008 Energy Act for a regulatory regime for carbon dioxide storage in the UK offshore area. The Act also provides for certain relevant existing offshore oil and gas legislation to be applied to facilities used for carbon storage.
2. Intrusive exploration, including test injection, may be undertaken during the agreed appraisal phase of a carbon storage licence. This licence will allow deep drilling and test injection of carbon dioxide in addition to the activities permissible under a general Exploration Licence (above).
3. The potential award of a carbon storage licence will require prior assessment under the Habitats Regulations as is the case for Petroleum Production Licences. Drilling and test injection would also need to be assessed and approved under the Habitats Regulations and the Offshore Petroleum Production and Pipe-lines (Assessment of Environmental Effects) Regulations 1999 “the EIA Regulations” (as extended to include carbon storage) as is also the case for petroleum drilling.
4. Where the licensee intends intrusive exploration, the licence will specify a work programme to be undertaken within the appraisal term defined by the licence. The work programme will be agreed with the developer at the time of the award of the licence and will be detailed in a Schedule appended to the Licence. This phase of the licence corresponds to the “exploration permit” within the meaning of the Directive and will be issued for a limited time period to prevent unnecessary blocking of territory for potential developments.
5. Subject to the outcome of an ongoing consultation BEIS propose that the duration of the appraisal period of the carbon storage licence could have a benchmark period of four years where a depleted petroleum reservoir is in question.
6. In addition the Operator will also need to enter into an agreement with The Crown Estate (Scotland) to secure a corresponding 'Agreement for Lease'. It is the intention of The Crown Estate (Scotland) and BEIS that the lease will not be issued until the terms of the licence are agreed, and that the licence will not be issued until the terms of the lease are agreed.
S07.2 PON15D Approval
Offshore Petroleum Production and Pipelines (Assessment of Environmental Effects) Regulations 1999 (SI 1999/360)
Injection of CO2 OGA
1. Linked to Environmental Statement for overall Project. Even if the facilities development/ operations were included in an approved Environmental Statement, a PON15D may still be required.
2. BEIS currently advise 6 months maximum approval process for oil and gas Environmental Statement.
3. Issues of timing related to CO2 Storage Licence to be resolved.
Currently, if a preliminary environmental investigation indicates that the project or modification is unlikely to have a significant adverse effect on the environment, and none of the mandatory conditions apply, then the operator may apply for a dispensation from the requirement to undertake the full Environmental Statement process (i.e. a Direction). The procedure for doing this is to complete a Petroleum Operations Notice 15 (PON15) and submit this to BEIS. The PON 15 requires detail about the proposed project and the environmental sensitivities of the area. It may be useful to prepare a preliminary environmental assessment as background to the PON. If a Direction is wanted then it must be explicitly requested as part of the PON 15 submission. Relevant considerations will be included within the Offshore Environmental Statement
D14 Outline Environmental Impact Assessment Permits and Consents
ACT Acorn Consortium Page 55 of 68
Reference Consent / License Title
Statutory Instrument
Consent to: Key
Project Elements
Determining Authority
Summary of Key Consent / License Aspects
S07.3
Chemical Permit (PON15D Approval)
Offshore Chemicals Regulations 2002 (SI2002/1355)
Use or discharge of chemical offshore
OGA
1. Permit currently required for use and discharge of production chemicals offshore.
2. Anticipated to be required for use of MEG offshore as a pressure control fluid. Requirements needs clarifying as proposal is for MEG use in a closed system.
S07.4 PON 6 Metering 'non-objection'
Petroleum Act 1987 and in the Petroleum (Production) Regulations 1988, as amended
Determination that our proposed metering is adequate
CO2 injection
OGA
1. Depends on terms of CO2 Storage Licence
2. Model Clauses of the Schedules in the Petroleum Act 1987 and in the Petroleum (Production)
Regulations 1988 currently set requirements on metering oil and gas production. The PON6 sets out the procedure to be followed by Licensees in order that their proposals for a 'Method of Measurement' may be reviewed by BEIS.
S08.1
Carbon Storage Permit (new legislation)
Storage of Carbon Dioxide (Licensing etc) (Scotland) Regulations 2011
Store Carbon Dioxide
Licensed area, surface facilities and CCS operations
OGA
1. A storage permit would convey permission to construct facilities, including any offshore installation which might be necessary and to conduct storage operations. It would also provide the necessary legal framework for obligations to ensure that the storage operations will secure permanent geological containment of the carbon dioxide, that the facilities are properly decommissioned after use, and that the behaviour of the stored material is adequately monitored during and after storage operations.
2. In accordance with the requirements of the Directive, the consultation document makes clear that obtaining a storage permit will be conditional upon BEIS approval of the following from the applicant:
• Storage Development Plan
• Environmental Impact Assessment
• Monitoring Plan
• Corrective Measures Plan
• Financial security
• Site closure / post-closure plan
In addition, BEIS will need to approve the proposed Operator and will need to be satisfied that the applicant(s) have secured a seabed lease from the Crown Estate.
3. The potential award of a consent for storage operations will need to assess under the EIA and Habitats Regulations and may require approval under other environmental regulations that will be applied to carbon storage. The procedure will be similar to that applied in the case of oil and gas Field Development Plans.
D14 Outline Environmental Impact Assessment Permits and Consents
ACT Acorn Consortium Page 56 of 68
Reference Consent / License Title
Statutory Instrument
Consent to: Key
Project Elements
Determining Authority
Summary of Key Consent / License Aspects
S08.2
Environmental Statement & PON16 Approval
Offshore Petroleum Production and Pipelines (Assessment of Environmental Effects) Regulations 1999 (SI 1999/360) (and Offshore Petroleum Activities (Conservation of Habitats) Regulations 2001 (SI 2001/1754)
Develop the project, as designed within the constraints of the EIA
Licensed area, seabed and surface facilities including pipeline
BEIS
1. Environmental Statement approval anticipated to be required prior to Storage Permit issue
2. BEIS currently advise 6 months maximum approval process for oil and gas Environmental Statement
3. Conservation of Habitats Regulations require that an environmental assessment identify any habitats or species covered by the Conservation (Natural Habitats &c) Regulations 1994, determine the likely impacts on them and where an adverse impact on a site integrity are likely, propose mitigation and propose an appropriate system to manage the mitigation measures and other commitments identified to remove of reduce the potential impacts. These findings should be documented in the Environmental Statement as well as providing sufficient information to inform any Appropriate Assessment which may be undertaken by BEIS.
Currently, if a preliminary environmental investigation indicates that the project or modification is unlikely to have a significant adverse effect on the environment, and none of the mandatory conditions apply, then the operator may apply for a dispensation from the requirement to undertake the full Environmental Statement process (i.e. a Direction). The procedure for doing this is to complete a Petroleum Operations Notice 15 (PON15) and submit this to BEIS. The PON15 requires detail about the proposed project and the environmental sensitivities of the area. It may be useful to prepare a preliminary environmental assessment as background to the PON. If a Direction is wanted then it must be explicitly requested as part of the PON15 submission.
Relevant Considerations will be included within the Offshore Environmental Statement
S09.1 Marine Licence (new legislation)
Marine and Coastal Access Act 2009 & The Marine (Scotland) Act 2010
Locate drilling well or deposit substances in the sea or under the seabed (FEPA) Surface facilities (CPA)
Marine Scotland
The Marine Licensing regime came into force on 06 April 2011 and relates to all activities within Scottish Seas. The Licence subsumes all previous consenting requirements under the Food and Environmental Protection Act (FEPA) and Coastal Protection Act (CPA).
D14 Outline Environmental Impact Assessment Permits and Consents
ACT Acorn Consortium Page 57 of 68
Reference Consent / License Title
Statutory Instrument
Consent to: Key
Project Elements
Determining Authority
Summary of Key Consent / License Aspects
S09.2
Environmental Impact Assessment Approval
Marine Works (EIA) Regulations 2007, as amended
Locate Drilling Well or Deposit of any articles or substances in the sea or under the seabed (FEPA) Surface facilities (CPA)
Marine Scotland
1. Considered unlikely to apply on assumption that EIA Rags (SI199/360) would apply to full scope of project.
2. Would only be required to support applications under the Marine & Coastal Access Act 2009 / Marine (Scotland) Act 2010, and Harbour Works 1999 involving deposits in the sea and works to ensure navigational safety if the activity is not sufficiently covered by other EIA legislation.
S10.1
Agreement for Lease for Carbon Storage
Energy Act 2008 / 1982 United Nations Convention on The Law of the Sea
Scotland Act 2016
Storage of carbon dioxide
Licensed three-dimensional subsurface volume, seabed and surface facilities
Crown Estate Scotland
1. The Energy Act 2008 provides for a regulatory regime for carbon dioxide (CO2) storage within the limit of the territorial sea and beyond into a newly designated Gas Importation and Storage Zone (GISZ). The exclusive right to store CO2 offshore has been vested in the Crown within an area extending from the seaward limits of the territorial sea to the boundaries of the GISZ. The Crown Estate already has the right to grant leases for any purpose within the area of the territorial sea.
2. Crown Estate Scotland was established following the Scotland Act 2016. The vesting provisions of the Energy Act allow Crown Estate Scotland to grant similar authorisations in respect of carbon storage activities beyond the territorial sea but within the area of the GISZ. The new licensing scheme will operate in parallel to the leases and authorisations granted by Crown Estate Scotland, by regulating those activities within both the territorial sea and the GISZ.
3. Crown Estate Scotland has confirmed its intention to lease specific sub-seabed formations defined by three-dimensional coordinates, together with related areas of the seabed and water column for the platform/subsea infrastructure (The position will therefore differ from traditional oil and gas licences which give exclusive rights for petroleum exploitation within an area defined by reference to a two-dimensional plan view).
4. The Agreement for Lease will cover intrusive drilling, test injection and other exploration activities covered by a concurrent Carbon Storage Licence.
D14 Outline Environmental Impact Assessment Permits and Consents
ACT Acorn Consortium Page 58 of 68
Reference Consent / License Title
Statutory Instrument
Consent to: Key
Project Elements
Determining Authority
Summary of Key Consent / License Aspects
S10.2 Lease for Carbon Storage
Energy Act 2008 / 1982 United Nations Convention on The Law of the Sea
Scotland Act 2016
Storage of carbon dioxide
Licensed three-dimensional subsurface volume, seabed and surface facilities
Crown Estate Scotland
1. The Energy Act 2008 provides for a regulatory regime for carbon dioxide (CO2) storage within the limit of the territorial sea and beyond into a newly designated Gas Importation and Storage Zone (GISZ). The exclusive right to store CO2 offshore has been vested in the Crown within an area extending from the seaward limits of the territorial sea to the boundaries of the GISZ. The Crown Estate already has the right to grant leases for any purpose within the area of the territorial sea.
2. Crown Estate Scotland was established following he Scotland Act 2016. The vesting provisions of the Act allow Crown Estate Scotland to grant similar authorisations in respect of carbon storage activities beyond the territorial sea but within the area of the GISZ. The new licensing scheme will operate in parallel to the leases and authorisations granted by Crown Estate Scotland, by regulating those activities within both the territorial sea and the GISZ.
2. Crown Estate Scotland has confirmed its intention to lease specific sub-seabed formations defined by three-dimensional coordinates, together with related areas of the seabed and water column for the platform/ subsea infrastructure (The position will therefore differ from traditional oil and gas licences which give exclusive rights for petroleum exploitation within an area defined by reference to a two-dimensional plan view).
3. Lease granted by Crown Estate Scotland will have defined geographical boundaries. As a condition of the lease, the developer will be required to apply to OGA for a licence for storage which will provide the framework for regulatory consent for the physical activities at the site, for example drilling and facilities construction.
4. The Lease will cover construction activities, carbon injection and storage operations, and the post closure monitoring phase of a project. The lease, and responsibility for long-term liabilities, will return to Crown Estate Scotland only when the project developer has satisfied the conditions for handover.
S11.1 Pipeline Crossing Agreements
General Property Law
Atlantic export pipeline
Crown Estate Scotland
1. Confirmation required that existing agreements will remain in place.
2. Any specific new requirements for the CO2 storage project will be progressed in parallel with negotiations for the CO2 storage lease for the Acorn site.
S11.2
Crown Estate seabed lease for pipeline section in Scottish Territorial waters
General Property Law
Offshore CO2 pipeline within Scottish Territorial Waters