    Antes de empezar

    Si aparece una barra de seguridad amarilla en la partesuperior de la pantalla en PowerPoint, haga clic enHabilitar edicin.

    Se necesita PowerPoint 2010 para ver estapresentacin. Si no tiene PowerPoint 2010, descargueel Visor de PowerPoint(vea la direccin URL en elpanel de notas).

    http://www.microsoft.com/downloads/es-es/details.aspx?displaylang=es-es&FamilyID=cb9bf144-1076-4615-9951-294eeb832823http://www.microsoft.com/downloads/es-es/details.aspx?displaylang=es-es&FamilyID=cb9bf144-1076-4615-9951-294eeb832823http://www.microsoft.com/downloads/es-es/details.aspx?displaylang=es-es&FamilyID=cb9bf144-1076-4615-9951-294eeb832823http://www.microsoft.com/downloads/es-es/details.aspx?displaylang=es-es&FamilyID=cb9bf144-1076-4615-9951-294eeb832823
  • 5/23/2018 Project 2010

    2/21

    Curso de MicrosoftProject 2010

    Introduccin a Project 2010

  • 5/23/2018 Project 2010

    3/21

    Contenido del curso

    Informacin general: aprender los conceptosbsicos de Project

    Leccin: incluye cuatro pelculas informativas

    Tareas de prctica sugeridas

    Prueba

    Tarjeta de referencia rpida

    Introduccin a Project 2010

  • 5/23/2018 Project 2010

    4/21

    Informacin general: aprender los

    conceptos bsicos de Project

    Introduccin a Project 2010

    Necesita administrar un proyecto perono est seguro de cmo comenzar conProject 2010?

    En este curso, aprender a comenzar unproyecto nuevo en blanco, crearalgunas tareas de proyectos y dar unaestructura a su proyecto mediante la

    creacin de esquemas de tareas y lavinculacin de una tarea con otra.

  • 5/23/2018 Project 2010

    5/21

    Objetivos del curso

    Crear un nuevo proyecto rpida y eficientemente.

    Crear una nueva tarea y cambiar una tarea deprogramada manualmente a programada

    automticamente. Crear relaciones, o vnculos, entre tareas.

    Crear esquemas de tareas para agregar estructura al

    proyecto.

    Introduccin a Project 2010

  • 5/23/2018 Project 2010

    6/21

    Crear un nuevo proyecto

    Introduccin a Project 2010

    Seale a la parte inferior del vdeo para ver los controles de vdeo.Arrastre o mueva el puntero por la barra de progreso para avanzar oretroceder.

    Necesito montar un stand en un sitio de exposicin de

    productos.

    Me dijeron que Microsoft Project 2010 es especialmente

    bueno para organizar y programar tareas

    independientemente de la magnitud del proyecto.

    Este es mi proyecto con algunas tareas para empezar.

    A la derecha, hay una lista de tareas del proyecto

    y, a la izquierda, hay una vista que muestra las barras donde

    se indica la duracin de las tareas en das.

    En la parte superior estn las caractersticas que se pueden

    usar en el proyecto.

    Ahora, bienvenido a la cinta de opciones.

    Dediquemos un segundo a esta cinta antes de pasar

    especficamente a la tarea de crear un proyecto nuevo.

    La cinta de opciones tiene caractersticas que se agrupan

    segn los tipos de actividades

    que normalmente se realizan cuando se crea y administra un

    proyecto.

    En este momento, se muestra la ficha Tarea.

    Aqu encontramos varios comandos y caractersticas que se

    pueden aplicar a una tarea;

    como por ejemplo, formato, programacin y administracin,

    entre otros.

    Presentar estas caractersticas con mayor detalle en otros

    vdeos de este curso.

    En la ficha 'Vista', puedo cambiar la forma en la que deseo ver

    mi proyecto.

    Por ejemplo, ahora estoy usando una vista Diagrama de Gantt

    que muestra las tareas a un lado y una barra con la duracin

    de las tareas, al otro lado.

    Es la vista predeterminada que se abre cada vez que se crea

    un proyecto nuevo.

    Si deseo ver mi tarea en la vista Calendario,

    puedo hacer clic en 'Calendario', en la ficha 'Vista'.

    Ahora, regresemos a la vista Diagrama de Gantt para crear

    algunas tareas ms y explicar ms detalles.

    Agregar dos tareas ms. A esta le asignar una duracin de

    dos das.

    Agregar la tarea Demoler

    con una duracin de tres das.

    Observe las barras adicionales de la derecha que reflejan los

    cambios que acabo de hacer.

    Ahora pasar a la vista Calendario y ver cmo se muestran

    estos cambios en el calendario.

    Obtendr ms informacin acerca de tareas en el siguiente

    vdeo de esta serie de cursos.

    Volvamos ahora a la vista de Diagrama de Gantt.

    Veo mi lista de tareas otra vez con las barras a la derecha.

    Una vez que se familiarice con la cinta de opciones empezar

    a disfrutarla porque es rpida

    y permite encontrar exactamente el comando que necesita

    para un trabajo determinado de Project.

    Ahora creemos un proyecto nuevo. Hago clic en la pestaa

    'Archivo'

    donde puedo ver comandos familiares para llevar a cabo

    distintas acciones,

    como abrir un proyecto existente,

    cerrar este proyecto, imprimir o enviar un proyecto a otra

    persona.

    Ahora quiero crear un proyecto nuevo, y hago clic en 'Nuevo'.

    Aqu encuentro varias formas en las que puedo crear un

    proyecto nuevo. Podra empezar un proyecto en blanco,

    o bien, si deseo ahorrar varios pasos, podra empezar con una

    plantilla que me ayude a iniciar un proyecto a partir de un

    proyecto existente o, en caso de tenerlo, usar un proyecto de

    Microsoft Excel como base de mi proyecto nuevo.

    Otra posibilidad es que si mi organizacin usa SharePoint

    2010 y ya hay creada una lista de tareas,

    puedo importar esa lista en Project y comenzar con ella.

    Por ahora, iniciar un proyecto en blanco y crear las tareas

    para mi exposicin.

    Este es mi nuevo proyecto en blanco.

    Y ya estoy listo para empezar a agregar tareas a mi sitio de

    exposicin de productos.

    En la prxima leccin, obtendr ms informacin acerca de

    cmo trabajar y administrar tareas en Project.

    http://office.microsoft.com/es-es/project-help/practice-RZ101831071.aspx?section=6http://office.microsoft.com/es-es/project-help/practice-RZ101831071.aspx?section=6http://office.microsoft.com/es-es/project-help/practice-RZ101831071.aspx?section=6http://office.microsoft.com/es-es/project-help/practice-RZ101831071.aspx?section=6http://office.microsoft.com/es-es/project-help/practice-RZ101831071.aspx?section=6http://office.microsoft.com/es-es/project-help/practice-RZ101831071.aspx?section=6http://office.microsoft.com/es-es/project-help/practice-RZ101831071.aspx?section=6http://office.microsoft.com/es-es/project-help/practice-RZ101831071.aspx?section=6http://office.microsoft.com/es-es/project-help/practice-RZ101831071.aspx?section=6http://office.microsoft.com/es-es/project-help/practice-RZ101831071.aspx?section=6http://office.microsoft.com/es-es/project-help/practice-RZ101831071.aspx?section=6http://office.microsoft.com/es-es/project-help/practice-RZ101831071.aspx?section=6http://office.microsoft.com/es-es/project-help/practice-RZ101831071.aspx?section=6http://office.microsoft.com/es-es/project-help/practice-RZ101831071.aspx?section=6http://office.microsoft.com/es-es/project-help/practice-RZ101831071.aspx?section=6http://office.microsoft.com/es-es/project-help/practice-RZ101831071.aspx?section=6http://office.microsoft.com/es-es/project-help/practice-RZ101831071.aspx?section=6http://office.microsoft.com/es-es/project-help/practice-RZ101831071.aspx?section=6http://office.microsoft.com/es-es/project-help/practice-RZ101831071.aspx?section=6http://office.microsoft.com/es-es/project-help/practice-RZ101831071.aspx?section=6http://office.microsoft.com/es-es/project-help/practice-RZ101831071.aspx?section=6http://office.microsoft.com/es-es/project-help/practice-RZ101831071.aspx?section=6http://office.microsoft.com/es-es/project-help/practice-RZ101831071.aspx?section=6http://office.microsoft.com/es-es/project-help/practice-RZ101831071.aspx?section=6http://office.microsoft.com/es-es/project-help/practice-RZ101831071.aspx?section=6http://office.microsoft.com/es-es/project-help/practice-RZ101831071.aspx?section=6http://office.microsoft.com/es-es/project-help/practice-RZ101831071.aspx?section=6http://office.microsoft.com/es-es/project-help/practice-RZ101831071.aspx?section=6http://office.microsoft.com/es-es/project-help/practice-RZ101831071.aspx?section=6http://office.microsoft.com/es-es/project-help/practice-RZ101831071.aspx?section=6http://office.microsoft.com/es-es/project-help/practice-RZ101831071.aspx?section=6http://office.microsoft.com/es-es/project-help/practice-RZ101831071.aspx?section=6http://office.microsoft.com/es-es/project-help/practice-RZ101831071.aspx?section=6http://office.microsoft.com/es-es/project-help/practice-RZ101831071.aspx?section=6http://office.microsoft.com/es-es/project-help/practice-RZ101831071.aspx?section=6http://office.microsoft.com/es-es/project-help/practice-RZ101831071.aspx?section=6http://office.microsoft.com/es-es/project-help/practice-RZ101831071.aspx?section=6http://office.microsoft.com/es-es/project-help/practice-RZ101831071.aspx?section=6http://office.microsoft.com/es-es/project-help/practice-RZ101831071.aspx?section=6http://office.microsoft.com/es-es/project-help/practice-RZ101831071.aspx?section=6http://office.microsoft.com/es-es/project-help/practice-RZ101831071.aspx?section=6http://office.microsoft.com/es-es/project-help/practice-RZ101831071.aspx?section=6http://office.microsoft.com/es-es/project-help/practice-RZ101831071.aspx?section=6http://office.microsoft.com/es-es/project-help/practice-RZ101831071.aspx?section=6http://office.microsoft.com/es-es/project-help/practice-RZ101831071.aspx?section=6http://office.microsoft.com/es-es/project-help/practice-RZ101831071.aspx?section=6http://office.microsoft.com/es-es/project-help/practice-RZ101831071.aspx?section=6http://office.microsoft.com/es-es/project-help/practice-RZ101831071.aspx?section=6http://office.microsoft.com/es-es/project-help/practice-RZ101831071.aspx?section=6http://office.microsoft.com/es-es/project-help/practice-RZ101831071.aspx?section=6http://office.microsoft.com/es-es/project-help/practice-RZ101831071.aspx?section=6http://office.microsoft.com/es-es/project-help/practice-RZ101831071.aspx?section=6http://office.microsoft.com/es-es/project-help/practice-RZ101831071.aspx?section=6http://office.microsoft.com/es-es/project-help/practice-RZ101831071.aspx?section=6http://office.microsoft.com/es-es/project-help/practice-RZ101831071.aspx?section=6http://office.microsoft.com/es-es/project-help/practice-RZ101831071.aspx?section=6http://office.microsoft.com/es-es/project-help/practice-RZ101831071.aspx?section=6http://office.microsoft.com/es-es/project-help/practice-RZ101831071.aspx?section=6http://office.microsoft.com/es-es/project-help/practice-RZ101831071.aspx?section=6http://office.microsoft.com/es-es/project-help/practice-RZ101831071.aspx?section=6http://office.microsoft.com/es-es/project-help/practice-RZ101831071.aspx?section=6http://office.microsoft.com/es-es/project-help/practice-RZ101831071.aspx?section=6http://office.microsoft.com/es-es/project-help/practice-RZ101831071.aspx?section=6http://office.microsoft.com/es-es/project-help/practice-RZ101831071.aspx?section=6http://office.microsoft.com/es-es/project-help/practice-RZ101831071.aspx?section=6http://office.microsoft.com/es-es/project-help/practice-RZ101831071.aspx?section=6http://office.microsoft.com/es-es/project-help/practice-RZ101831071.aspx?section=6http://office.microsoft.com/es-es/project-help/practice-RZ101831071.aspx?section=6http://office.microsoft.com/es-es/project-help/practice-RZ101831071.aspx?section=6http://office.microsoft.com/es-es/project-help/practice-RZ101831071.aspx?section=6http://office.microsoft.com/es-es/project-help/practice-RZ101831071.aspx?section=6http://office.microsoft.com/es-es/project-help/practice-RZ101831071.aspx?section=6http://office.microsoft.com/es-es/project-help/practice-RZ101831071.aspx?section=6http://office.microsoft.com/es-es/project-help/practice-RZ101831071.aspx?section=6http://office.microsoft.com/es-es/project-help/practice-RZ101831071.aspx?section=6http://office.microsoft.com/es-es/project-help/practice-RZ101831071.aspx?section=6http://office.microsoft.com/es-es/project-help/practice-RZ101831071.aspx?section=6
  • 5/23/2018 Project 2010

    7/21

    Agregar tareas a un proyecto

    Introduccin a Project 2010

    Seale a la parte inferior del vdeo para ver los controles de vdeo.Arrastre o mueva el puntero por la barra de progreso para avanzar oretroceder.

    Todos los proyectos comienzan con la primera tarea. Por lo

    tanto, empecemos.

    Este es mi proyecto Exposicin y necesito tener algunas

    tareas para emprender la marcha.

    Primero agregar tareas a la izquierda de la vista de Diagrama

    de Gantt, en la columna Nombre de tarea.Crear cuatro tareas para mi proyecto Exposicin.

    En Project 2010, se pueden crear dos tipos de tareas: tareas

    programadas manualmente y tareas programadas

    automticamente.

    Veamos estos dos tipos de tareas con especial atencin

    porque sus diferencias pueden crear confusiones en un

    principio.

    De manera predeterminada, cuando las tareas se crean por

    primera vez, se establecen como programadas manualmente.

    Las tareas programadas manualmente son una caracterstica

    nueva de Project 2010.

    Conceden al jefe de proyecto un control completo sobre

    cundo debe llevarse a cabo una tarea.

    Despus de todo, cuando se empieza un proyecto, las fechas

    exactas pueden ser confusas.

    La duracin de una tarea programada manualmente no

    necesariamente debe ser un nmero;

    por ejemplo, podra ser una palabra o frase como Un par de

    das.

    Har esto. Hasta puedo escribir Hablar con Bob como

    segunda tarea

    y una palabra como Pronto en la columna Iniciar, o puedo

    dejar la duracin y la fecha en blanco.

    Observe que Project an no coloca ninguna barra a la

    derecha de la vistaporque no sabe qu hacer con fechas como Pronto.

    Pero eso no es problema porque estamos en los comienzos

    de una programacin poco clara

    en la que an no se ha determinado la informacin bsica de

    la tarea.Observe adems los iconos en la columna Modo de tarea.Reflejan el modo de programacin que estoy usando ahora,

    que es el modo de programacin manual, con tareas que

    estn ancladas hasta que yo elija moverlas.Veamos la tercera y la cuarta tarea.

    Las establecer como programadas automticamente porque

    tengo ms informacin sobre estas tareas.

    Conozco la duracin que deben tener o cundo deben

    comenzar. Seleccionar estas tareas y las establecer en

    Autoprogramar.

    Sin embargo, si escribo Un par de das en la columna

    Duracin, me da error.

    Debo escribir un nmero como 1s para 1 semana o 5d

    para 5 das.

    Observe que Project ha establecido de forma automtica las

    fechas de inicio y finalizacin.

    Las versiones de Microsoft Project anteriores a Project 2010

    usaban tareas programadas automticamente.Para la ltima tarea, cuyo inicio y duracin conozco,

    coloquemos nmeros y veamos qu sucede en la fecha de

    finalizacin.

    Veo que la fecha de finalizacin se calcula de forma

    automtica.

    Ahora veo que el motor de programacin de Project

    comienza a trabajar duramente.

    Observe las barras a la derecha. Nuestro proyecto ahora tiene

    suficiente informacin para crear barras.

    Antes, para las primeras dos tareas, Project no mostraba

    barras porque todava no tena suficientes datos para hacerlo.

    Las tareas programadas automticamente permiten

    aprovechar la eficacia del motor de programacin de Project

    para que nos ayude a prever la fecha de una tarea en funcin

    de los valores de fecha y nmero en las columnas Iniciar y

    Duracin.

    Lo mismo sucede con los elementos que no se ven, como el

    calendario del proyecto, los calendarios de tareas,los calendarios de recursos

    o las relaciones entre tareas y vnculos a otras tareas, entre

    otros.Ahora que sabe cmo agregar tareas a su programacin,

    est listo para el siguiente paso: crear relaciones entre tareas.Aprenderemos este tema en el siguiente vdeo de esta serie

    de cursos.

    http://office.microsoft.com/es-es/project-help/quick-reference-card-RZ101831071.aspx?section=9&mode=printhttp://office.microsoft.com/es-es/project-help/quick-reference-card-RZ101831071.aspx?section=9&mode=printhttp://office.microsoft.com/es-es/project-help/quick-reference-card-RZ101831071.aspx?section=9&mode=printhttp://office.microsoft.com/es-es/project-help/quick-reference-card-RZ101831071.aspx?section=9&mode=printhttp://office.microsoft.com/es-es/project-help/quick-reference-card-RZ101831071.aspx?section=9&mode=printhttp://office.microsoft.com/es-es/project-help/quick-reference-card-RZ101831071.aspx?section=9&mode=printhttp://office.microsoft.com/es-es/project-help/quick-reference-card-RZ101831071.aspx?section=9&mode=printhttp://office.microsoft.com/es-es/project-help/quick-reference-card-RZ101831071.aspx?section=9&mode=printhttp://office.microsoft.com/es-es/project-help/quick-reference-card-RZ101831071.aspx?section=9&mode=printhttp://office.microsoft.com/es-es/project-help/quick-reference-card-RZ101831071.aspx?section=9&mode=printhttp://office.microsoft.com/es-es/project-help/quick-reference-card-RZ101831071.aspx?section=9&mode=printhttp://office.microsoft.com/es-es/project-help/quick-reference-card-RZ101831071.aspx?section=9&mode=printhttp://office.microsoft.com/es-es/project-help/quick-reference-card-RZ101831071.aspx?section=9&mode=printhttp://office.microsoft.com/es-es/project-help/quick-reference-card-RZ101831071.aspx?section=9&mode=printhttp://office.microsoft.com/es-es/project-help/quick-reference-card-RZ101831071.aspx?section=9&mode=printhttp://office.microsoft.com/es-es/project-help/quick-reference-card-RZ101831071.aspx?section=9&mode=printhttp://office.microsoft.com/es-es/project-help/quick-reference-card-RZ101831071.aspx?section=9&mode=printhttp://office.microsoft.com/es-es/project-help/quick-reference-card-RZ101831071.aspx?section=9&mode=printhttp://office.microsoft.com/es-es/project-help/quick-reference-card-RZ101831071.aspx?section=9&mode=printhttp://office.microsoft.com/es-es/project-help/quick-reference-card-RZ101831071.aspx?section=9&mode=printhttp://office.microsoft.com/es-es/project-help/quick-reference-card-RZ101831071.aspx?section=9&mode=printhttp://office.microsoft.com/es-es/project-help/quick-reference-card-RZ101831071.aspx?section=9&mode=printhttp://office.microsoft.com/es-es/project-help/quick-reference-card-RZ101831071.aspx?section=9&mode=printhttp://office.microsoft.com/es-es/project-help/quick-reference-card-RZ101831071.aspx?section=9&mode=printhttp://office.microsoft.com/es-es/project-help/quick-reference-card-RZ101831071.aspx?section=9&mode=printhttp://office.microsoft.com/es-es/project-help/quick-reference-card-RZ101831071.aspx?section=9&mode=printhttp://office.microsoft.com/es-es/project-help/quick-reference-card-RZ101831071.aspx?section=9&mode=printhttp://office.microsoft.com/es-es/project-help/quick-reference-card-RZ101831071.aspx?section=9&mode=printhttp://office.microsoft.com/es-es/project-help/quick-reference-card-RZ101831071.aspx?section=9&mode=printhttp://office.microsoft.com/es-es/project-help/quick-reference-card-RZ101831071.aspx?section=9&mode=printhttp://office.microsoft.com/es-es/project-help/quick-reference-card-RZ101831071.aspx?section=9&mode=printhttp://office.microsoft.com/es-es/project-help/quick-reference-card-RZ101831071.aspx?section=9&mode=printhttp://office.microsoft.com/es-es/project-help/quick-reference-card-RZ101831071.aspx?section=9&mode=printhttp://office.microsoft.com/es-es/project-help/quick-reference-card-RZ101831071.aspx?section=9&mode=printhttp://office.microsoft.com/es-es/project-help/quick-reference-card-RZ101831071.aspx?section=9&mode=printhttp://office.microsoft.com/es-es/project-help/quick-reference-card-RZ101831071.aspx?section=9&mode=printhttp://office.microsoft.com/es-es/project-help/quick-reference-card-RZ101831071.aspx?section=9&mode=printhttp://office.microsoft.com/es-es/project-help/quick-reference-card-RZ101831071.aspx?section=9&mode=printhttp://office.microsoft.com/es-es/project-help/quick-reference-card-RZ101831071.aspx?section=9&mode=printhttp://office.microsoft.com/es-es/project-help/quick-reference-card-RZ101831071.aspx?section=9&mode=printhttp://office.microsoft.com/es-es/project-help/quick-reference-card-RZ101831071.aspx?section=9&mode=printhttp://office.microsoft.com/es-es/project-help/quick-reference-card-RZ101831071.aspx?section=9&mode=printhttp://office.microsoft.com/es-es/project-help/quick-reference-card-RZ101831071.aspx?section=9&mode=printhttp://office.microsoft.com/es-es/project-help/quick-reference-card-RZ101831071.aspx?section=9&mode=printhttp://office.microsoft.com/es-es/project-help/quick-reference-card-RZ101831071.aspx?section=9&mode=printhttp://office.microsoft.com/es-es/project-help/quick-reference-card-RZ101831071.aspx?section=9&mode=printhttp://office.microsoft.com/es-es/project-help/quick-reference-card-RZ101831071.aspx?section=9&mode=printhttp://office.microsoft.com/es-es/project-help/quick-reference-card-RZ101831071.aspx?section=9&mode=printhttp://office.microsoft.com/es-es/project-help/quick-reference-card-RZ101831071.aspx?section=9&mode=printhttp://office.microsoft.com/es-es/project-help/quick-reference-card-RZ101831071.aspx?section=9&mode=printhttp://office.microsoft.com/es-es/project-help/quick-reference-card-RZ101831071.aspx?section=9&mode=printhttp://office.microsoft.com/es-es/project-help/quick-reference-card-RZ101831071.aspx?section=9&mode=printhttp://office.microsoft.com/es-es/project-help/quick-reference-card-RZ101831071.aspx?section=9&mode=printhttp://office.microsoft.com/es-es/project-help/quick-reference-card-RZ101831071.aspx?section=9&mode=printhttp://office.microsoft.com/es-es/project-help/quick-reference-card-RZ101831071.aspx?section=9&mode=printhttp://office.microsoft.com/es-es/project-help/quick-reference-card-RZ101831071.aspx?section=9&mode=printhttp://office.microsoft.com/es-es/project-help/quick-reference-card-RZ101831071.aspx?section=9&mode=printhttp://office.microsoft.com/es-es/project-help/quick-reference-card-RZ101831071.aspx?section=9&mode=printhttp://office.microsoft.com/es-es/project-help/quick-reference-card-RZ101831071.aspx?section=9&mode=printhttp://office.microsoft.com/es-es/project-help/quick-reference-card-RZ101831071.aspx?section=9&mode=printhttp://office.microsoft.com/es-es/project-help/quick-reference-card-RZ101831071.aspx?section=9&mode=printhttp://office.microsoft.com/es-es/project-help/quick-reference-card-RZ101831071.aspx?section=9&mode=printhttp://office.microsoft.com/es-es/project-help/quick-reference-card-RZ101831071.aspx?section=9&mode=printhttp://office.microsoft.com/es-es/project-help/quick-reference-card-RZ101831071.aspx?section=9&mode=printhttp://office.microsoft.com/es-es/project-help/quick-reference-card-RZ101831071.aspx?section=9&mode=printhttp://office.microsoft.com/es-es/project-help/quick-reference-card-RZ101831071.aspx?section=9&mode=printhttp://office.microsoft.com/es-es/project-help/quick-reference-card-RZ101831071.aspx?section=9&mode=printhttp://office.microsoft.com/es-es/project-help/quick-reference-card-RZ101831071.aspx?section=9&mode=printhttp://office.microsoft.com/es-es/project-help/quick-reference-card-RZ101831071.aspx?section=9&mode=printhttp://office.microsoft.com/es-es/project-help/quick-reference-card-RZ101831071.aspx?section=9&mode=printhttp://office.microsoft.com/es-es/project-help/quick-reference-card-RZ101831071.aspx?section=9&mode=printhttp://office.microsoft.com/es-es/project-help/quick-reference-card-RZ101831071.aspx?section=9&mode=printhttp://office.microsoft.com/es-es/project-help/quick-reference-card-RZ101831071.aspx?section=9&mode=printhttp://office.microsoft.com/es-es/project-help/quick-reference-card-RZ101831071.aspx?section=9&mode=printhttp://office.microsoft.com/es-es/project-help/quick-reference-card-RZ101831071.aspx?section=9&mode=printhttp://office.microsoft.com/es-es/project-help/quick-reference-card-RZ101831071.aspx?section=9&mode=printhttp://office.microsoft.com/es-es/project-help/quick-reference-card-RZ101831071.aspx?section=9&mode=printhttp://office.microsoft.com/es-es/project-help/quick-reference-card-RZ101831071.aspx?section=9&mode=printhttp://office.microsoft.com/es-es/project-help/quick-reference-card-RZ101831071.aspx?section=9&mode=printhttp://office.microsoft.com/es-es/project-help/quick-reference-card-RZ101831071.aspx?section=9&mode=printhttp://office.microsoft.com/es-es/project-help/quick-reference-card-RZ101831071.aspx?section=9&mode=printhttp://office.microsoft.com/es-es/project-help/quick-reference-card-RZ101831071.aspx?section=9&mode=print
  • 5/23/2018 Project 2010

    8/21

    Agregar vnculos entre tareas en el proyecto

    Introduccin a Project 2010

    Seale a la parte inferior del vdeo para ver los controles de vdeo.Arrastre o mueva el puntero por la barra de progreso para avanzar oretroceder.

    En el vdeo anterior, he creado cuatro tareas. Ahora,

    aprenderemos a crear relaciones o vnculos entre tareas.

    Empecemos preguntndonos por qu debemos vincular las

    tareas.

    La vinculacin de tareas muestra las relaciones que existen

    entre ellas.

    Muestra que una tarea debe completarse antes de que

    empiece la otra.O que las dos deben comenzar al mismo tiempo.Este es mi proyecto de exposicin con cuatro tareas.

    Estas cuatro tareas van a comenzar al mismo tiempo, lo cual

    es utpico en la mayora de los proyectos.

    Seguramente no querr montar una exposicin sin antes

    disearla.

    Vincular las primeras dos tareas para indicar que una

    comienza despus de la otra.

    Primero necesito seleccionar las dos tareas y para hacerlo, las

    arrastro.

    A continuacin, en la ficha Tarea, en el grupo

    Programacin, har clic en el botn Vincular.Aqu veo que Project ha hecho algo prudente.

    Asumi que una tarea empieza una vez terminada la otra,

    como se puede ver en las barras de la derecha.Observe la lnea de vnculo entre las dos tareas.

    Esta lnea representa lo que se denomina un vnculo de Fin a

    comienzo,que significa que cuando una tarea finaliza, la otra comienza.

    Esta es la relacin predeterminada que se crea cuando se

    vinculan dos tareas.

    Puedo cambiar esto haciendo doble clic sobre la lnea y

    seleccionando otra relacin.Por ejemplo, Comienzo a comienzo.

    En el cuadro de dilogo, en la lista Tipo, selecciono

    Comienzo a comienzo y hago clic en Aceptar.

    Veo que las barras se adaptaron para representar una

    relacin Comienzo a comienzo.

    No tiene mucho sentido asignar a estas dos tareas una

    relacin Comienzo a comienzo.

    Pero dos tareas como Disear y Registrar cabina podran

    comenzar al mismo tiempo.

    Por ahora, volver a cambiar la relacin de las tareas a la

    relacin predeterminada Fin a comienzo.

    Har clic otra vez en la lnea que une a las dos tareas y, en el

    cuadro de dilogo, seleccionar Fin a comienzo.

    Observe tambin que no tuve que poner datos en las fechas

    de inicio para programar estas dos tareas,

    porque estn establecidas en el modo de programacin

    automtica.

    Por lo tanto, las fechas de inicio y finalizacin de la

    programacin se determinaron despus de haberseespecificado las duraciones.

    En el vdeo anterior realic una introduccin a la

    programacin automtica y manual.

    Veamos qu sucede cuando vinculo tareas que estn

    programadas manualmente.Seleccionar estas dos filas,y en el grupo Programacin har clic en el botn Vincular.Observe la diferencia de color en las barras.

    Esta es una forma rpida de ver qu tipo de programacin de

    tareas se aplica.

    Cuando vinculo inicialmente estas tareas, se mueven de una

    forma predecible...

    de manera un tanto similar a las tareas programadas

    automticamente.

    No obstante, all terminan las similitudes porque ahora,

    cuando muevo estas tareas, la tarea vinculada no se mueve.

    Trasladar la tercera tarea unos das ms adelante, porque se

    necesita que la promocin de la exposicin comience ms

    tarde.Arrastrar la tarea al lado derecho de la vista.

    Observe que la accin de mover esta tarea no mueve la tarea

    a la que est vinculada.

    En el mundo real de administracin de proyectos, las tareas

    normalmente se superponen o realizan en paralelo

    y, si lo hacen, puedo decidir si mantener o no la

    superposicin.

    En este ejemplo, con una programacin que incluye solo una

    pocas tareas,

    sera muy sencillo manipular las tareas si estuvieran todas

    establecidas en programacin automtica.Pero imagine un proyecto con 50 1000 tareas.

    En este caso, quizs desee tener mayor control sobre dnde y

    cundo se movern las tareas vinculadas, a travsde la programacin manual.

    En el siguiente vdeo, mostrar cmo dar a sus tareas una

    mayor estructura mediante la creacin de esquemas.

  • 5/23/2018 Project 2010

    9/21

    Crear un esquema para tareas en el proyecto

    Introduccin a Project 2010

    Seale a la parte inferior del vdeo para ver los controles de vdeo.Arrastre o mueva el puntero por la barra de progreso para avanzar oretroceder.

    En el vdeo de este curso, quisiera mostrar cmo dar

    estructura a un proyecto mediante la esquematizacinde tareas.

    Por ejemplo, quizs desee mostrar que mi proyecto tiene

    fases que incluso deben dividirse en fases ms pequeas.

    Esto se denomina Tareas de resumen y Subtareas, y el

    proceso que se usa para crearlas se denomina

    Esquematizacin.

    Veamos cmo funciona. Este es mi proyecto compuesto por

    tareas y fases que deben dividirse an ms.

    Pero antes de esquematizar las tareas, vincular estas fases, o

    Tareas de resumen, para mostrar que una fasesigue a la otra.

    Primero seleccionar estas cuatro tareas arrastrndolas. A

    continuacin, en la ficha Tarea, har clic enVincular tareas en el grupo Programacin.Ahora estoy lista para esquematizar algunas tareas.

    La fase Disear necesita algunas subtareas. Har clic en el

    lugar donde deseo insertar una tarea

    y, a continuacin, en la ficha Tarea, har clic en Tareas, en

    el grupo Insertar, y ver que se ha insertadouna tarea nueva.

    Volver a hacer clic en Insertar tarea para agregar una

    segunda tarea. Ahora asignar un nombre a estas dos tareas.

    Denominar a la primera Contrato y le asignar una

    duracin de 3 das.

    A la segunda, la llamar Planos y tambin le asignar una

    duracin de 3 das en la columna Duracin.

    Establecer estas tareas como programadas

    automticamente porque deseo que Project realice la

    programacin por m.

    Selecciono la primera tarea y, a continuacin, en la ficha

    Tarea, hago clic en Autoprogramar,

    en el grupo 'Tareas'. Selecciono la otra tarea y vuelvo a hacer

    clic en 'Autoprogramar'.

    Ahora comenzar el esquema con la aplicacin de sangra en

    estas dos tareas. Las selecciono haciendo clic y arrastrando.

    A continuacin, en el grupo Programacin, hago clic en

    Sangra.

    Las tareas se mueven levemente a la derecha para mostrar

    que ahora son subtareas de la fase 'Disear'.O de la tarea de resumen 'Disear'.

    Observe las barras de la derecha. Ahora veo dos barras para

    estas nuevas tareas debajo de una barra de resumende color negro que corresponde a la fase 'Disear'.

    Esta Barra de resumen resume las duraciones de las

    subtareas para indicar la duracin global de la fase de diseo.Si aumentara la duracin de una de las subtareas,la barra de resumen tambin aumentara para reflejarlo.Aumentar la duracin de la subtarea 'Planos' a cinco das.Hago clic en la columna 'Duracin' de la tarea 'Planos',

    y veo que la barra de la subtarea aument, al igual que la

    barra de la tarea de resumen.

    De manera similar, si vinculara estas dos tareas, tal y como se

    mostr en el vdeo anterior,

    la duracin de la tarea de resumen aumentara para mostrar

    el resumen acumulado de las duraciones de las subtareas.

    Selecciono las dos tareas arrastrndolas. A continuacin, en el

    grupo Programacin, hago clic en 'Vincular tareas'.

    Veo que la barra de las subtareas aument, al igual que la

    barra de la tarea de resumen.

    Dado que estas tareas estn programadas automticamente,

    Project sabe adonde moverlas.

    Esto est bien para las tareas programadas automticamente

    pero, qu ocurre con las tareas programadas manualmente?Recuerde que en el vdeo anterior de esta serie de cursos

    se explicaba la diferencia entre las tareas programadas

    automticamente y las tareas programadas manualmente.

    La duracin de las tareas en modo de programacin manual

    se restringe a nmeros.

    Puedo escribir una frase para la duracin de tareas, como

    pronto. Har esto para la fase de edificacin.

    Asimismo, crear ahora dos subtareas programadas

    manualmente en esta fase.

    Selecciono la tarea debajo de la cual deseo insertar algunas

    tareas.

    A continuacin, en el grupo 'Insertar', hago clic en 'Insertar

    tarea' y vuelvo a hacer clic para

    agregar dos tareas. Denominar a estas tareas Pedir

    materiales y Construir.

    En la columna 'Modo de tarea' veo que ya estn establecidas

    como programadas manualmente.

    Colocar la duracin Pronto a la tarea Pedir materiales y

    Pronto a la tarea Construir.

    Ahora les aplico sangra para que sean subtareas de la tarea

    de resumen o fase Edificar.

    Las selecciono arrastrndolas y, a continuacin, en el grupo

    'Programacin' hago clic en 'Sangra'.

    Dado que estas dos subtareas estn programadas

    manualmente, la tarea de resumen 'Edificar' no las resume.

    Despus de todo, cmo podra hacerlo? Hablando en

    trminos matemticos, no es posible resumir valores deduracin que no son nmeros.

    Si agregara duraciones en formato de nmero a una de las

    tareas programadas manualmente,

    entonces estos nmeros se resumiran en la tarea de

    resumen. Permtame hacerlo.Cambio la duracin de la subtarea 'Pedir materiales' a 3 das.

    Hago esto usando la columna 'Duracin' y lo repito para la

    columna 'Construir'.

    Veo que la barra de resumen cambia para reflejar el aumento

    de valor que se produjo en la duracin de estas dos tareas.

    Hay otra posibilidad con las tareas programadas

    manualmente.

    En este momento, la tarea de resumen 'Edificar' aparece

    como programada automticamente.

    Sin embargo, qu sucedera si cambiara y estableciera la

    tarea de resumen en programacin manual?Hagmoslo con la fase 'Edificar'.

    Selecciono la tarea y, a continuacin, en el grupo 'Tarea', hago

    clic en 'Programar manualmente'.

    Observe que se ha agregado una barra de color gris debajo de

    la barra 'Tarea de resumen'.

    Esta barra es exclusiva de las tareas de resumen programadas

    manualmente.Me dice de qu manera se resumen las subtareas.Ahora las barras tienen la misma longitud,

    pero como la barra de resumen superior est programada

    manualmente,

    puedo moverla manualmente sin mover las subtareas

    relacionadas.Mover el extremo de la barra de resumen, arrastrndolo.

    Veo que la segunda barra adjunta a la barra de resumen no se

    ha movido.

    Todava sigue reflejando la informacin acerca del efecto

    combinado de las subtareas.

    Esto es til para aquellos proyectos en los que puedo

    aumentar la duracin de una fasesin especificar cunto deben durar las subtareas.

    Por ejemplo, si me dicen que la duracin de la fase 'Edificar'

    puede extenderse, simplemente extender la barra de esta

    fase

    y ver la diferencia en la longitud de la barra y en la posicin

    de la fecha de finalizacin de la fase y lasltimas fechas de las subtareas.

    Puedo empezar a mover las subtareas para administrar mejor

    de qu manera se distribuye el tiempo durante esta fase.

    Ahora ya sabe cmo iniciar un proyecto, agregar algunas

    tareas

    y crear una estructura mediante vinculacin y

    esquematizacin.Use la sesin de prctica de esta serie de cursos

    para comprobar personalmente qu fcil es iniciar un nuevo

    proyecto con Project 2010.

  • 5/23/2018 Project 2010

    10/21

    Sugerencias para practicar

    1. Cree algunas tareas.

    2. Cree relaciones mediante la vinculacin de tareas.

    3. Esboce tareas.

    Introduccin a Project 2010

    Prctica en lnea(se necesita Project 2010)

    http://office.microsoft.com/es-es/project-help/practice-RZ101831071.aspx?section=6http://office.microsoft.com/es-es/project-help/practice-RZ101831071.aspx?section=6
  • 5/23/2018 Project 2010

    11/21

    Pregunta de prueba 1

    Si especifica duraciones para tareas programadasmanualmente, Project crea las fechas de inicio yfinalizacin automticamente. (Elija una respuesta).

    Introduccin a Project 2010

    1. Verdadero.2. Falso.

  • 5/23/2018 Project 2010

    12/21

    Pregunta de prueba 1

    Introduccin a Project 2010

    Especificar duraciones para las tareas programadasmanualmente no implica la creacin automtica de fechasde inicio y finalizacin para las tareas.

    Si especifica duraciones para tareas programadas manualmente,Project crea las fechas de inicio y finalizacin automticamente.

    Respuesta:

    2. Falso.

  • 5/23/2018 Project 2010

    13/21

    Pregunta de prueba 2

    Las tareas programadas manualmente tienen duracionesadems de fechas de inicio y finalizacin. (Elija una respuesta).

    Introduccin a Project 2010

    1. Verdadero.

    2. Falso.

  • 5/23/2018 Project 2010

    14/21

    Pregunta de prueba 2

    Introduccin a Project 2010

    Las tareas programadas manualmente no requierenduraciones ni fechas. Pueden existir sin ningunainformacin de programacin.

    Las tareas programadas manualmente tienen duracionesadems de fechas de inicio y finalizacin.

    Respuesta:

    2. Falso.

  • 5/23/2018 Project 2010

    15/21

    Pregunta de prueba 3

    Las tareas de resumen siempre resumen la duracin totalde las subtareas. (Elija una respuesta).

    Introduccin a Project 2010

    1. Falso.

    2. Verdadero.

  • 5/23/2018 Project 2010

    16/21

    Pregunta de prueba 3

    Introduccin a Project 2010

    Solo las tareas de resumen que estn programadasautomticamente resumen la duracin total de lassubtareas.

    Las tareas de resumen siempre resumen la duracin totalde las subtareas.

    Respuesta:

    1. Falso.

  • 5/23/2018 Project 2010

    17/21

    Pregunta de prueba 4

    Cul de los siguientes valores de duracin est permitido en lastareas programadas automticamente? (Elija una respuesta).

    Introduccin a Project 2010

    1. 4.

    2. Cuatro das.

    3. Pronto.

  • 5/23/2018 Project 2010

    18/21

    Pregunta de prueba 4

    Introduccin a Project 2010

    Las tareas programadas automticamente usan valoresnumricos. En este caso, puede escribir 4d o 4.

    Cul de los siguientes valores de duracin est permitidoen las tareas programadas automticamente?

    Respuesta:

    1. 4.

  • 5/23/2018 Project 2010

    19/21

    Pregunta de prueba 5

    Las tareas programadas manualmente pueden tener comofecha de inicio el valor Pronto. (Elija una respuesta).

    Introduccin a Project 2010

    1. Verdadero.

    2. Falso.

  • 5/23/2018 Project 2010

    20/21

    Pregunta de prueba 5

    Introduccin a Project 2010

    Las tareas programadas manualmente pueden tener valoresde fecha en palabras, nmeros o fechas.

    Las tareas programadas manualmente pueden tenercomo fecha de inicio el valor Pronto.

    Respuesta:

    1. Verdadero.

  • 5/23/2018 Project 2010

    21/21

    Tarjeta de referencia rpida

    Para ver un resumen de las tareastratadas en este curso,vea la Tarjeta de referencia rpida.

    Introduccin a Project 2010

    http://office.microsoft.com/es-es/project-help/quick-reference-card-RZ101831071.aspx?section=9&mode=printhttp://office.microsoft.com/es-es/project-help/quick-reference-card-RZ101831071.aspx?section=9&mode=printhttp://office.microsoft.com/es-es/project-help/quick-reference-card-RZ101831071.aspx?section=9&mode=print