Alford Community Campus Progress Report No 15 January 2015
25

Progress Report No 15 - Aberdeenshireaberdeenshire.gov.uk/media/4136/alfordprogressreportjan...1.00 Progress Report 1.02 Overall Programme Position: • Progress affected by adverse

Mar 14, 2020

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Progress Report No 15 - Aberdeenshireaberdeenshire.gov.uk/media/4136/alfordprogressreportjan...1.00 Progress Report 1.02 Overall Programme Position: • Progress affected by adverse

Alford Community Campus

Progress Report No 15

January 2015

Page 2: Progress Report No 15 - Aberdeenshireaberdeenshire.gov.uk/media/4136/alfordprogressreportjan...1.00 Progress Report 1.02 Overall Programme Position: • Progress affected by adverse

View from Playing Fields

Page 3: Progress Report No 15 - Aberdeenshireaberdeenshire.gov.uk/media/4136/alfordprogressreportjan...1.00 Progress Report 1.02 Overall Programme Position: • Progress affected by adverse

Block C Cladding

Page 4: Progress Report No 15 - Aberdeenshireaberdeenshire.gov.uk/media/4136/alfordprogressreportjan...1.00 Progress Report 1.02 Overall Programme Position: • Progress affected by adverse

Blocks B& C

• GF Partitions 2nd side

boarding in progress

• Ames taping in progress

• 1st Floor Partitions 1st fix

in progress

• M&E ahead of schedule

• Ceilings to commence

1.00 Progress Report

Page 5: Progress Report No 15 - Aberdeenshireaberdeenshire.gov.uk/media/4136/alfordprogressreportjan...1.00 Progress Report 1.02 Overall Programme Position: • Progress affected by adverse

Block F

• Library enclosed

• Stonework continues

• Theatre blockwork being completed

• M&E services in progress

Page 6: Progress Report No 15 - Aberdeenshireaberdeenshire.gov.uk/media/4136/alfordprogressreportjan...1.00 Progress Report 1.02 Overall Programme Position: • Progress affected by adverse

Block D

• Partitions progressing

• M&E progressing

• Underfloor heating / screeds in

progress

Page 7: Progress Report No 15 - Aberdeenshireaberdeenshire.gov.uk/media/4136/alfordprogressreportjan...1.00 Progress Report 1.02 Overall Programme Position: • Progress affected by adverse

Block A

• M&E in progress

• Internal partitions 1st fix completed first floor

• Blockwork completed

• Pool plant being installed

• Pool high level walls in progress

Page 8: Progress Report No 15 - Aberdeenshireaberdeenshire.gov.uk/media/4136/alfordprogressreportjan...1.00 Progress Report 1.02 Overall Programme Position: • Progress affected by adverse

Block E

• Roofing progress affected by adverse

weather

• SFS to complete around Gym area

(when safety nets removed)

• Internal blockwork in progress

• M&E in progress

Page 9: Progress Report No 15 - Aberdeenshireaberdeenshire.gov.uk/media/4136/alfordprogressreportjan...1.00 Progress Report 1.02 Overall Programme Position: • Progress affected by adverse

Marked-up Programme

Page 10: Progress Report No 15 - Aberdeenshireaberdeenshire.gov.uk/media/4136/alfordprogressreportjan...1.00 Progress Report 1.02 Overall Programme Position: • Progress affected by adverse

Marked-up Programme

Page 11: Progress Report No 15 - Aberdeenshireaberdeenshire.gov.uk/media/4136/alfordprogressreportjan...1.00 Progress Report 1.02 Overall Programme Position: • Progress affected by adverse

Marked-up Programme

Page 12: Progress Report No 15 - Aberdeenshireaberdeenshire.gov.uk/media/4136/alfordprogressreportjan...1.00 Progress Report 1.02 Overall Programme Position: • Progress affected by adverse

Marked-up Programme

Page 13: Progress Report No 15 - Aberdeenshireaberdeenshire.gov.uk/media/4136/alfordprogressreportjan...1.00 Progress Report 1.02 Overall Programme Position: • Progress affected by adverse

1.00 Progress Report

1.02 Overall Programme Position:

• Progress affected by adverse weather Jan 15

• Roofing / external fabric – some areas still to complete

• M&E progressing ahead of schedule

• Partitions progressing on programme

• External works ahead of schedule

Contract Programme CP / 001: On programme

Page 14: Progress Report No 15 - Aberdeenshireaberdeenshire.gov.uk/media/4136/alfordprogressreportjan...1.00 Progress Report 1.02 Overall Programme Position: • Progress affected by adverse

1.00 Progress Report

1.03 Main Activities Planned Next Month

• Block E – last section of SFS

• Continue cladding works

• Commence ceiling grids

• Additional joiners to progress partitions

• Continue M&E all areas

• Pool high level boarding / taping

• Topsoil prep /spreading

Page 15: Progress Report No 15 - Aberdeenshireaberdeenshire.gov.uk/media/4136/alfordprogressreportjan...1.00 Progress Report 1.02 Overall Programme Position: • Progress affected by adverse

2.00 Design Report

2.01 Design:

DTMs continue on a fortnightly basis to coordinate design and sub-contractor input.

Review of Access Control Requirements for resubmission of RDD 15.

First pass submission for all RDD items now complete (including second pass for Room Layouts).

Revision of status C & D RDD feedback is ongoing for Wings B & C.

Workshop with ACC to resolve some RDD feedback matters such sanitary ware, landscape etc.

Proposals for wet wall and hygienic wall resolved with ACC. Meeting arranged to resolve recording studio, AV, sound

and stage lighting matters. RFIs to clarify ACC requirements at the pool area.

Page 16: Progress Report No 15 - Aberdeenshireaberdeenshire.gov.uk/media/4136/alfordprogressreportjan...1.00 Progress Report 1.02 Overall Programme Position: • Progress affected by adverse

2.00 Design Report

2.02 Planning Conditions:

• Condition 02 – Notification of Completion to be issued (final inspection clears

remainder of Condition 03 confirmation of completion of car parking provision &

Condition 12 confirmation of completion of landscaping).

• Condition 05 – Traffic Calming / Cycling Provision on Greystone Road to be

completed prior to occupation (Aberdeenshire Council action)

• Condition 06 – Speed Limits / Signage as TRO’s to be implemented in surrounding

area prior to occupation (Aberdeenshire Council action)

• All other planning conditions have been closed.

Page 17: Progress Report No 15 - Aberdeenshireaberdeenshire.gov.uk/media/4136/alfordprogressreportjan...1.00 Progress Report 1.02 Overall Programme Position: • Progress affected by adverse

3.00 Health and Safety

3.01 Safety Report:

Item Period Total

Reportable Accidents 0 0

HSE Visits 0 0

Near Miss Incident 0 0

• Two first aid incidents recorded during period.

• Challenging Beliefs, Affecting Behaviour – initiatives being implemented.

• Safety audit 28/1/15.

• Security cameras operational.

Page 18: Progress Report No 15 - Aberdeenshireaberdeenshire.gov.uk/media/4136/alfordprogressreportjan...1.00 Progress Report 1.02 Overall Programme Position: • Progress affected by adverse

4.00 Community

• We currently have two work experience placements.

• Site will participate in UKCG Open Doors event 6th/7th March 15.

• A school visit / artist’s review took place on 16th January 15.

• Site is re-registered with CCS for this year.

Current CCS score 42.

Page 19: Progress Report No 15 - Aberdeenshireaberdeenshire.gov.uk/media/4136/alfordprogressreportjan...1.00 Progress Report 1.02 Overall Programme Position: • Progress affected by adverse

5.00 Quality

• Temperatures being monitored / work rescheduled if required

• Underfloor heating loop pressure tests being checked

• Technical Services inspections ongoing

• F&G (M&E) inspections commenced

• AC Clerk of Works visits ongoing / comments being addressed

• Floor levels being checked – remedial works as required

Page 20: Progress Report No 15 - Aberdeenshireaberdeenshire.gov.uk/media/4136/alfordprogressreportjan...1.00 Progress Report 1.02 Overall Programme Position: • Progress affected by adverse

6.00 Utilities

Item Current Progress Target Installation Date Critical ‘live’ date

Electricity Substation installed and cables laid.

Work in delay awaiting clearance of wayleave – progress made

by AC to arrange re-routing of cable.

In progress (on hold) 8th May 15

(required earlier for

temp supplies)

Water Connection approved.

Dialogue continuing to finalise connection.

20th Feb – 20 Mar 15 8th May 15

(required earlier for

temp supplies)

Gas AC to arrange. 20th Feb – 20 Mar 15 8th May 15

Telecom AC to arrange.

BT have requested additional ducts / boxes to a new connection

point.

20th Feb – 20 Mar 15 8th May 15

Page 21: Progress Report No 15 - Aberdeenshireaberdeenshire.gov.uk/media/4136/alfordprogressreportjan...1.00 Progress Report 1.02 Overall Programme Position: • Progress affected by adverse

7.00 Procurement

Package Contractor

Mass cut and fill / Stabilisation Ground Developments Limited

Ground works / Concrete / Drainage Carey

Structural Steelwork / Decking BSB

Roofing & Cladding Curtis Moore

SFS Veitchi

Precast Concrete Bison (supply only)

Glulam Beams Glulam Solutions

Swimming Pool Barr and Wray

Lifts Kone

Windows & Curtain Walling Glassolutions

Mechanical & Electrical CHES

Louvres Colt

Page 22: Progress Report No 15 - Aberdeenshireaberdeenshire.gov.uk/media/4136/alfordprogressreportjan...1.00 Progress Report 1.02 Overall Programme Position: • Progress affected by adverse

Package Contractor

Fire Protection Orr FP

Brickwork Fairways

Stonework Stirling Stone

Natural Ventilation JRF Chimney Specialists

Landscaping Ground Control

Chemical Hoist Stannah Lift Services

Kitchens James Scott & Sons

Rooflights Lareine Engineering

Sports Pitches Malcolm Construction

Metalwork Miller Fabrications

Kalwall SD Systems 96

Page 23: Progress Report No 15 - Aberdeenshireaberdeenshire.gov.uk/media/4136/alfordprogressreportjan...1.00 Progress Report 1.02 Overall Programme Position: • Progress affected by adverse

Package Contractor

IPS Inscape

Siphonic drainage West Siphonics

Roller doors Fortress

FFE ESA

Retractable seating Audience systems

Ceiling mounted hoists Hill-Rom (Liko)

Render Muirfield

Folding partitions Movawall

Revolving door Geze

Pool sports equipment Alpha Sports

Partitions Morrison

Page 24: Progress Report No 15 - Aberdeenshireaberdeenshire.gov.uk/media/4136/alfordprogressreportjan...1.00 Progress Report 1.02 Overall Programme Position: • Progress affected by adverse

Package Contractor

Decoration and Ames Taping Angus Decorators

Suspended Ceilings Hi-Tech Acoustic Services

Flooring Harndec

Signage

Fencing Alpine

Joinerwork Morrison

Bespoke furniture

Tiling

Blinds & Curtains Kaydee

Timber sports flooring MacKay

Hygienic partitions Morrison

Page 25: Progress Report No 15 - Aberdeenshireaberdeenshire.gov.uk/media/4136/alfordprogressreportjan...1.00 Progress Report 1.02 Overall Programme Position: • Progress affected by adverse

8.00 Key Risks

Item Measures Risk

Inclement Weather Lost time during most of Jan 15 due to low temperatures /

high winds.

Medium

Works being undertaken adjacent to site, housing

development, etc

Ongoing dialogue with other parties Low

Electrical connection Work on hold pending resolution of wayleave issues. Medium

Water connection Connection approved – dialogue continuing. Medium

Interface between MCUK activity and work by

others incl. Gas and Telecomm connection

Dependency schedule issued to Hubco Low

Completion of external Road works to enable

interfaces and comply with Planning Conditions

Aberdeenshire Council investigating options Medium

Availability of joiners Aiming to source additional squads to push on partitioning

work.

Medium

List of changes to be formalised / instructed. Ongoing dialogue to formalise changes / instructions. Medium