P P rogramme rogramme of m of m otorways and expressways otorways and expressways construction in Poland construction in Poland in in 2008 2008 - - 2013 in the context 2013 in the context of Transeuropean Transport Network of Transeuropean Transport Network (TEN (TEN - - T) T) corridors corridors Zbigniew Kotlarek Zbigniew Kotlarek President of Managing Board President of Managing Board Polish Road Congress Association Polish Road Congress Association e e - - mail: [email protected] mail: [email protected] Helsinki, 11.06.2008 Helsinki, 11.06.2008
26

Programme construction in Poland in 2008-2013 in the context of

Sep 12, 2021

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Programme construction in Poland in 2008-2013 in the context of

PProgrammerogramme

of mof motorways and expressways otorways and expressways construction in Poland construction in Poland

inin

20082008--2013 in the context 2013 in the context of Transeuropean Transport Network of Transeuropean Transport Network

(TEN(TEN--T)T)

corridorscorridors

Zbigniew KotlarekZbigniew KotlarekPresident of Managing Board President of Managing Board Polish Road Congress AssociationPolish Road Congress Associationee--mail: [email protected]: [email protected]

Helsinki, 11.06.2008Helsinki, 11.06.2008

Page 2: Programme construction in Poland in 2008-2013 in the context of

Road transport due to its role in goods and persons deliveries bRoad transport due to its role in goods and persons deliveries belongs to most elongs to most

important elements of the national economyimportant elements of the national economy

In 2005 vehicle transportation’s share in overall goods deliveriIn 2005 vehicle transportation’s share in overall goods deliveries reached 55%es reached 55%

It is estimated to rise 2% every year until 2020It is estimated to rise 2% every year until 2020

In 2013 the transportation load will rise 37In 2013 the transportation load will rise 37--44% as compared with 200544% as compared with 2005

In the same period the demand for vehicle transportation in the In the same period the demand for vehicle transportation in the Polish foreign Polish foreign

trade will rise some 150trade will rise some 150--190%190%

In 2020 the will be 60% more cars than in 2005 In 2020 the will be 60% more cars than in 2005

Page 3: Programme construction in Poland in 2008-2013 in the context of

Better communicational accessibility of Poland calls for establiBetter communicational accessibility of Poland calls for establishing effective shing effective

transportation connections with European countries with statetransportation connections with European countries with state--ofof--thethe--art motorway, art motorway,

expressways and other national roads.expressways and other national roads.

Transitional location of Poland demands that road corridors shouTransitional location of Poland demands that road corridors should play an ld play an

important role in carrying international transportation between important role in carrying international transportation between Western Europe, Western Europe,

Baltic states, Scandinavian Peninsula, Ukraine and Central Asia.Baltic states, Scandinavian Peninsula, Ukraine and Central Asia.

Also important Also important

is servicing transport between Scandinavian states and Europe’s is servicing transport between Scandinavian states and Europe’s South (the South (the

BalBalkkans)ans)

Page 4: Programme construction in Poland in 2008-2013 in the context of

Crucial shortcomings Crucial shortcomings of Polish road networkof Polish road network::

No coherent network of motorways and expresswaysNo coherent network of motorways and expressways

Roads not adjusted to load capacity of 115kN/axleRoads not adjusted to load capacity of 115kN/axle

Roads lead through urban settlementsRoads lead through urban settlements

Poor safety of the road trafficPoor safety of the road traffic

Poor keeping in repairPoor keeping in repair

Page 5: Programme construction in Poland in 2008-2013 in the context of

Main development goals until 2015Main development goals until 2015

The main objective is to build a network of roads representing hThe main objective is to build a network of roads representing high technological igh technological

parameters which will establish a high capacity transportation fparameters which will establish a high capacity transportation framework ramework

connecting economical centers of the countryconnecting economical centers of the country

Ensuring fluent transit traffic on road corridorsEnsuring fluent transit traffic on road corridors

Reduction by 2013 the number of fatal accidents by 50%Reduction by 2013 the number of fatal accidents by 50%

Page 6: Programme construction in Poland in 2008-2013 in the context of

TENTEN--T T corridors in corridors in

PolandPoland

TranseuropeanTranseuropeanRoad transport Road transport

corridorscorridors

Page 7: Programme construction in Poland in 2008-2013 in the context of

Integrating Integrating rroad corridors in Poland oad corridors in Poland with TENwith TEN--T Transeuropean NetworksT Transeuropean Networks

TENTEN--T network in Poland covers 4,816 kilometresT network in Poland covers 4,816 kilometres

In the period 2008In the period 2008--2012 the most important road building investment 2012 the most important road building investment

concentrates in following corridors:concentrates in following corridors:

Corridor I Corridor I ––

Budzisko Budzisko ––

WarszawaWarszawa

Corridor IICorridor II----

Świecko Świecko --

Kukuryki Kukuryki

Corridor III Corridor III ----

Olszyna / Zgorzelec Olszyna / Zgorzelec ––

KorczowaKorczowa

Corridor VI GdańskCorridor VI Gdańsk--

Gorzyczki/Cieszyn/ZwardońGorzyczki/Cieszyn/Zwardoń

Page 8: Programme construction in Poland in 2008-2013 in the context of

Investments Investments and acitvitiesand acitvities

NorthNorth--eastern Poland mapeastern Poland map

Roads:16, 61, 19, 8

Page 9: Programme construction in Poland in 2008-2013 in the context of

Road network Road network iin the Northernn the Northern--Eastern Region of Poland Eastern Region of Poland

and its implicationsand its implications

National Road Nr. 16 Olsztyn National Road Nr. 16 Olsztyn ––

AugustówAugustów

National Road Nr. 61 Łomża National Road Nr. 61 Łomża ––

AugustówAugustów

National Road Nr. 8 Budzisko National Road Nr. 8 Budzisko ––

Augustów Augustów ––

Białystok Białystok

National Road Nr 19 (Budzisko National Road Nr 19 (Budzisko ––

Augustów Augustów ––

Wasilków) Kuźnica Białostocka Wasilków) Kuźnica Białostocka

––

Wasilków Wasilków ––

Białystok Białystok ––Lublin Lublin ––Rzeszów Rzeszów --

Barwinek (The Lancut agreement)Barwinek (The Lancut agreement)

ConConcclusion: the bylusion: the by--pass of Augustów is a key issue of road network pass of Augustów is a key issue of road network

in the Regionin the Region

Page 10: Programme construction in Poland in 2008-2013 in the context of
Page 11: Programme construction in Poland in 2008-2013 in the context of

The Program of National Roads Construction in 2008-2012The program covers expenses on:

1.Investments due to start in 2008-20122.Investments under construction (started before 2008)3.Investments finished (securing means for settlement of accounts)

Basic sources of Program’s financing:

The national budget

EU funds:Infrastructure and Environment Operational ProgrammeDevelopment of Eastern Poland Operational ProgrammeCohesion Fund 2004-2006European Regional Development Found 2004-2006

National Road Fund

Page 12: Programme construction in Poland in 2008-2013 in the context of

Spending volume in consecutive years:Spending volume in consecutive years:

Total: Total: PLNPLN

121121

billionbillion

Page 13: Programme construction in Poland in 2008-2013 in the context of

Motorways network in 2008 and 2012Motorways network in 2008 and 2012

March 2008 –

699 kilometers of motorways

June 2012 –

around 1,700 kilometers of motorways

Page 14: Programme construction in Poland in 2008-2013 in the context of

Expressways network in 2008 and 2012Expressways network in 2008 and 2012

March 2008317 kilometers of expressways

June 2012 –

around 1,800 kilometers of expressways

Page 15: Programme construction in Poland in 2008-2013 in the context of

Euro 2012Euro 2012

European competition European competition

––

PolishPolish

investmentsinvestments

Page 16: Programme construction in Poland in 2008-2013 in the context of

EU funds distribution to various branches of transport within EU funds distribution to various branches of transport within the framework of the Infrastructure and Environment the framework of the Infrastructure and Environment

Operational ProgramOperational Programmeme

Page 17: Programme construction in Poland in 2008-2013 in the context of
Page 18: Programme construction in Poland in 2008-2013 in the context of
Page 19: Programme construction in Poland in 2008-2013 in the context of

Operational plan for 2008Operational plan for 2008

Construction of expressways Construction of expressways initiated in consecutive 2008initiated in consecutive 2008--

2013 years2013 years

Construction of motorways initiated Construction of motorways initiated in consecutive 2008in consecutive 2008--2013 years2013 years

Page 20: Programme construction in Poland in 2008-2013 in the context of

Strona 2Strona 2

Page 21: Programme construction in Poland in 2008-2013 in the context of

Strona 3Strona 3

Page 22: Programme construction in Poland in 2008-2013 in the context of

Environmental protectionEnvironmental protection We take up the challengeWe take up the challenge

Stage I -

completed

Project of the Strategy of I Pan-European Corridor’s Development

The scope of Strategic Environmental Assessment report

•Minister of Environment's consent for the SEA report scope•The General Sanitary Inspector’s consent for the SEA report scope

Stage II –

in progress

Project of the Strategic Environmental Assessment report, including (among others):

•Feasibility study•Social analyses•SEA administrative procedure

Minister of Environment's opinion for the SEA reportThe General Sanitary Inspector’s opinion for the

SEA reportOpinion of the National Commission for

Environmental Impact Assessments - session open for public (NGOs)Public participation in the SEA procedure

Stage III

Strategy of I Pan-European Corridor’s Development Strategic Environmental Assessment Report

•after implementation of the opinions of all administrative organs as well as public and the conclusions of the SEA report

Page 23: Programme construction in Poland in 2008-2013 in the context of

Via Baltica Current situation

Page 24: Programme construction in Poland in 2008-2013 in the context of

Via BalticaVia BalticaVia Baltica is another name for Corridor I of TEN-T network in Poland

(Budzisko –

Augustów –

Białystok -

Warszawa)

The corridor connects Western Europe and Poland with Lithuania, Latvia and

Estonia and leads to Helsinki

It is of crucial importance for Baltic States and Nordic states, even more than

for the Polish road network

Polish problems with Via Baltica:

Budzisko (on the border of Poland and Lithuania) and the real distribution of

traffic destinations

Research shows traffic cannot be channeled into one corridor according to the

travel destination

Page 25: Programme construction in Poland in 2008-2013 in the context of

Opportunities:Opportunities: Threats:Threats:

Preparations for construction well Preparations for construction well in progressin progress

Huge financial means allotted to Huge financial means allotted to those projectsthose projects

Potential problems well identifiedPotential problems well identified

Functioning of the organization Functioning of the organization constantly improvedconstantly improved

Legal regulations make preparation and Legal regulations make preparation and realization of investment difficultrealization of investment difficult

Highly complicated bureaucratic procedures Highly complicated bureaucratic procedures (Ministry of Infrastructure, Ministry of Environment, (Ministry of Infrastructure, Ministry of Environment, Ministry of Finances, Ministry of Regional Ministry of Finances, Ministry of Regional Development)Development)

Financial cuts on existing roads management and Financial cuts on existing roads management and maintenancemaintenance

Personnel instability (high rate of fluctuation)Personnel instability (high rate of fluctuation)