Programme Business Case Report DRAFT Released 21 June 2019
P r o g r a m m e B u s i n e s s C a s e R e p o r t
DRAFT Released 21 June 2019
Let’s Get Wellington Moving Programme Business Case – Draft Released 21 June 2019
This report and supporting LGWM technical documents are being released in draft on Friday 21st June 2019 for the purposes of public information and to inform LGWM partner decision making processes. This programme business case has not been approved by the NZ Transport Agency, the Wellington City Council, and Greater Wellington City Council, nor has funding approval for any further stages been given. The contents of this draft report may change and do not necessarily represent the final position of LGWM or its partner organisations.
Copyright information
This publication is copyright © NZ Transport Agency on behalf of the LGWM partners. Material in it may be reproduced for personal or in-house use without formal permission or charge, provided suitable acknowledgement is made to this publication and Let’s Get Wellington Moving as the source. Requests and enquiries about the reproduction of material in this publication for any other purpose should be made to:
Manager, Information NZ Transport Agency Private Bag 6995 Wellington 6141
The permission to reproduce material in this publication does not extend to any material for which the copyright is identified as being held by a third party. Authorisation to reproduce material belonging to a third party must be obtained from the copyright holder(s) concerned.
Disclaimer
The NZ Transport Agency, Greater Wellington Regional Council, and Wellington City Council have endeavoured to ensure material in this document is technically accurate and reflects legal requirements. However, the document does not override governing legislation. The NZ Transport Agency, Greater Wellington Regional Council, and Wellington City Council do not accept liability for any consequences arising from the use of this document. If the user of this document is unsure whether the material is correct, they should refer directly to the relevant legislation and contact the NZ Transport Agency.
More information
NZ Transport Agency Published June 2019
If you have further queries, call our contact centre on 0800 699 000 or write to us:
NZ Transport Agency Private Bag 6995 Wellington 6141
This document is available from the NZ Transport Agency on request.
Content
Let’s Get Wellington Moving Programme Business Case – Draft Released 21 June 2019
Foreword .................................................................................................................................................. i
Recommended Programme of Investment .......................................................................................... ii
Cost Estimates .................................................................................................................................... iv
Programme Outcomes & Next Steps .................................................................................................. iv
Part A – The Strategic Case...................................................................................................................... 1
1. Introduction ..................................................................................................................................... 1
1.1. Purpose ................................................................................................................................... 1
1.2. Background and Programme History....................................................................................... 2
1.3. Programme Partners ............................................................................................................... 4
1.4. LGWM Governance and Management .................................................................................... 4
1.5. Programme Stakeholders ........................................................................................................ 5
2. Programme Context ......................................................................................................................... 7
2.1. Geographic Context ................................................................................................................. 7
2.2. Land Use and Urban Form ....................................................................................................... 7
2.3. Growth Projections.................................................................................................................. 7
2.4. Current Transport System Design ............................................................................................ 8
2.5. Role of the Transport System ................................................................................................ 12
2.6. Current Transport System Pressures ..................................................................................... 12
2.7. National Strategic Context..................................................................................................... 15
2.8. Regional Strategic Context .................................................................................................... 15
2.9. Local Strategic Context .......................................................................................................... 16
3. Strategic Assessment ..................................................................................................................... 18
3.1. Investment Logic ................................................................................................................... 18
3.2. Transport System Causes ...................................................................................................... 19
3.3. Transport System Effects ....................................................................................................... 22
3.4. Transport System Consequences .......................................................................................... 22
3.5. Transport System Opportunities ........................................................................................... 23
4. Programme Objectives ................................................................................................................... 26
4.1. Urban Design and Transport Principles ................................................................................. 26
4.2. LGWM Investment Objectives ............................................................................................... 28
Part B – Developing the Programme ..................................................................................................... 29
Overview ............................................................................................................................................ 29
Part B1 – Strategic Response ................................................................................................................. 31
5. Potential Interventions................................................................................................................... 31
5.1. Intervention Development and Assessment ......................................................................... 31
Content
Let’s Get Wellington Moving Programme Business Case – Draft Released 21 June 2019
6. Test Scenarios ................................................................................................................................ 32
6.1. Test Scenario Development (2016) ....................................................................................... 32
6.2. Test Scenario Assessment ..................................................................................................... 35
6.3. Test Scenarios Conclusion ..................................................................................................... 36
6.4. Community and Stakeholder Workshops (early 2017) .......................................................... 37
7. Developing the Strategic Response ................................................................................................ 38
8. Scenarios for Engagement ............................................................................................................. 40
8.1. Engagement Scenarios Development .................................................................................... 40
8.2. Engagement Scenarios Assessment ...................................................................................... 41
8.3. Engagement Feedback .......................................................................................................... 44
8.4. LGWM Response to Engagement Scenarios Feedback .......................................................... 44
9. SMART Objective Development ..................................................................................................... 46
Part B2 – Analysis of Programme Elements ........................................................................................... 47
10. Programme Development Analysis ............................................................................................ 47
10.1. LGWM as an enabler for urban development ....................................................................... 47
10.2. Pricing .................................................................................................................................... 48
10.3. Alternative Futures and Technology ...................................................................................... 49
10.4. Mass Transit .......................................................................................................................... 51
10.5. State Highway 1 corridor through Te Aro .............................................................................. 53
10.6. Basin Reserve Area ................................................................................................................ 55
11. Further Analysis .......................................................................................................................... 58
11.1. State Highway 1 Corridor ...................................................................................................... 58
11.2. State Highway 1 corridor through Te Aro .............................................................................. 58
11.3. State Highway 1 corridor through Mt Victoria ...................................................................... 58
Part B3 – Programme Development ...................................................................................................... 59
12. Longlist Programme Options ...................................................................................................... 59
12.1. Longlist Programme Development ........................................................................................ 59
12.2. Longlist Programme Options ................................................................................................. 61
12.3. Longlist Programme Assessment ........................................................................................... 61
13. Shortlist Programme Options ..................................................................................................... 63
13.1. Shortlist Programme Development and Options................................................................... 63
13.2. Shortlist Programme Assessment .......................................................................................... 66
14. Recommended Programme ....................................................................................................... 67
14.1. Recommended Programme Development ............................................................................ 67
14.2. Recommended Programme of Investment Summary ........................................................... 68
14.3. Recommended Programme Detail ........................................................................................ 69
14.4. Whole of Network Solution ................................................................................................... 81
Content
Let’s Get Wellington Moving Programme Business Case – Draft Released 21 June 2019
14.5. Recommended Programme of Investment Sequencing ........................................................ 82
14.6. Recommended Programme Assessment ............................................................................... 86
14.7. Programme Risks and Uncertainties ...................................................................................... 95
Part C – Preferred Way Forward ........................................................................................................... 97
15. Affordability Contraints .............................................................................................................. 97
16. Indicative Package ...................................................................................................................... 98
16.1. Funding and Financing the Indicative Package .................................................................... 100
16.2. Assessment of the Indicative Package ................................................................................. 100
16.3. Whole of System Solution ................................................................................................... 103
16.4. Sequencing, Interdependencies and Trigger Points ............................................................ 103
17. Management Case .................................................................................................................... 105
17.1. Delivery Model .................................................................................................................... 105
17.2. Next Steps for Delivery ........................................................................................................ 105
17.3. Programme Monitoring and Reviews .................................................................................. 107
17.4. Programme Funding ............................................................................................................ 109
17.5. Risks and Uncertainties ....................................................................................................... 109
18. Commercial Case ...................................................................................................................... 111
APPENDIX A – STRATEGIC ALIGNMENT
APPENDIX B – INVESTMENT LOGIC MAP
APPENDIX C – INVESTMENT OBJECTIVE KPIS AND RPI ASSESSMENT
APPENDIX D – NOTE 1: INTERVENTION LONGLIST SCREEN
APPENDIX E – NOTE 2: SCENARIO LONGLIST DEVELOPMENT
APPENDIX F – LONGLIST SCENARIOS MULTI-CRITERIA ANALYSIS REPORT
APPENDIX G – ENGAGEMENT SCENARIOS TECHNICAL SPECIALIST ASSESSMENT
APPENDIX H – LONGLIST PROGRAMME ASSESSMENT WORKSHOP NOTES
APPENDIX I – SHORTLIST PROGRAMME OPTIONS WORKSHOP NOTES
APPENDIX J – COST REPORT
APPENDIX K – ECONOMICS REPORT
APPENDIX L – INVESTMENT ASSESSMENT FRAMEWORK ASSESSMENT
APPENDIX M – MONITORING PLAN
APPENDIX N – TECHNICAL DOCUMENTS
Foreword
Let’s Get Wellington Moving Programme Business Case – Draft Released 21 June 2019 i
FOREWORD Wellington City Council, Greater Wellington Regional Council, and
the NZ Transport Agency have worked together to deliver a
transformational city-shaping programme for Wellington that
supports the community’s aspirations for how Wellington City will
look, feel and function. It does this by providing a holistic transport
system that enables and supports future growth and builds upon
Wellington’s unique character as one of the world’s great cities.
The resultant Recommended Programme of Investment (RPI),
outlined in this Programme Business Case, aims to improve the
way people get around, while enhancing liveability and access,
reducing reliance on private vehicles, and improving safety and
resilience.
The focus of the RPI is on the area from Ngauranga Gorge to the
airport, including the Wellington Urban Motorway and
connections to the central city, hospital, and the eastern and
southern suburbs. This focus area should be seen in the context of
the wider Wellington regional transport system, as many of the
journeys in the central city start and finish outside the focus area.
The RPI and this associated Programme Business Case has been developed with a strong focus on people and
the desire to enable an improved quality of life. As such, significant public and stakeholder engagement was
undertaken to inform the place-making approach, which has been used to integrate the transport outcomes
with the land use and urban development outcomes of the RPI. In doing so, the RPI can act as a catalyst for
quality and sustainable urban renewal and growth.
While recognised as one of the world’s most liveable cities, Wellington’s transport system is starting to
constrain the city and region’s liveability, economic growth and productivity. The Programme Business Case
clearly outlines how we started with the kind of city and region our community wants and defined a transport
system and associated investment needed to enable that:
Foreword
Let’s Get Wellington Moving Programme Business Case – Draft Released 21 June 2019 ii
Artist’s impression: Lambton Quay
The overall strategic approach used to establish the RPI and respond to the investment and programme
objectives were as follows:
STRATEGIC APPROACH
Make the most of what we have
Optimise the transport system and make it safer
Encourage people to walk, cycle, and use public transport more, and use cars less
Deliver a step change in public transport
Substantially improve public transport capacity, quality and performance
Encourage urban intensification near public transport
Improve journeys to, from and in the central city
Prioritise people walking, cycling, and using public transport on key corridors
Improve accessibility and amenity of places and streets
Ensure goods and services journeys are reliable
Improve journeys through and around the central city
Reduce conflicts between different transport users and traffic flows
Increase the resilience and reliability of our transport corridors, especially to the hospital, port, and airport
Recommended Programme of Investment
The Recommended Programme of Investment establishes the proposed long-term vision and aspiration for
Wellington’s transport system and urban transformation. While aspirational, this Programme Business Case
confirms the benefits envisaged based on the level of analysis appropriate to this stage of the process. It
recognises that the investment required is significant and that further investigation into the funding and
financing strategy is required. Importantly the RPI is a series of integrated interventions and investments that
create a whole system transformation. As such, caution needs to be applied if certain elements are considered
in isolation i.e. the RPI is a kit of parts not a shopping list.
The transformational, multifaceted RPI achieves the following:
High-quality walking and cycling so our streets are safer and better places for people:
Safer speeds in and around the city Walking improvements though the
central city including: o Footpath widening o Improved crossing facilities and
reduced waiting times o Better shelters, signage, lighting
New dedicated walking access through Mt Victoria
Public space improvements, for example, Dixon, Mercer, through Te Aro, Basin Reserve
A network of connected cycleways through the central city New dedicated cycleways connecting through Mt Victoria, along Adelaide Rd, and Vivian St New pedestrian crossings, including Cobham Drive
tist’s impression: Lambton Quay
Foreword
Let’s Get Wellington Moving Programme Business Case – Draft Released 21 June 2019 iii
Artist’s impression: Taranaki Street
Artist’s impression: Basin Reserve Northern Entrance
Artist’s impression: Corner of Willis & Mercer Streets
Better public transport with high-capacity mass transit so people have more travel choices, and buses and trains are more reliable and attractive:
High-capacity mass transit from the railway station to the airport via a new waterfront spine, Taranaki Street, the hospital, Newtown, Kilbirnie, and Miramar
Bus priority improvements: o Golden Mile spine, with possible
general traffic removal on Willis and parts of Lambton and Courtenay
o Core routes into the city such as Thorndon Quay and Hutt Road High quality, high frequency buses Increased rail network capacity (Implemented outside of LGWM) Integrated ticketing (Implemented outside of LGWM)
Urban development land use changes integrated with transport so people have better travel options where they live and work:
Inform district plan changes Other tools to increase housing Building where the market can’t deliver Capturing increases in land value to
support infrastructure investment
Smarter transport network with road pricing so people and goods make better use of our transport system without more cars:
Smarter pricing (e.g. parking/cordon charges)
Mobility as a Service for Wellington Network optimisation, safety and
operations improvements Enhanced Travel Demand Management (TDM) Integrated network operating system Align parking policy and management with the programme
Multimodal State Highway improvements to relocate cars out of the central city and enable better public transport, walking and cycling, and so people can get to key destinations, such as the hospital and airport, more reliably:
Basin Reserve improvements Extra Mt Victoria Tunnel and widening
Ruahine St/Wellington Rd Reconfiguring SH1 into a tunnel under a
new city park in Te Aro Extra Terrace Tunnel SH1 Southbound widening between
Ngauranga and Aotea Quay
Foreword
Let’s Get Wellington Moving Programme Business Case – Draft Released 21 June 2019 iv
Cost Estimates
A rough order of costs has been developed for the elements of the RPI as shown in the table below. These
estimates should be considered indicative based on 2018 uninflated figures and are inclusive of management
costs, construction costs and professional fees. Contingency has been qualitatively assessed and applied to the
base estimates. Funding risk has not been applied at this stage.
Recommended Programme of Investment Cost Assessment
RPI ELEMENT ESTIMATED COST $M
(2018 UNINFLATED)
Walkable City 70*
Connected Cycleways 30
Public Transport to the north and to/through the city ** 300
Mass Transit – City to Newtown*** 990
Mass Transit – Newtown to Airport*** 450
Smarter Transport Network 30
Smarter Pricing 30
Extra Mt Victoria Tunnel – Duplicate Ruahine St. / Wellington Rd. 480
Basin Reserve Improvements 130
Extra Terrace Tunnel and 4th lane Southbound 400
Te Aro Tunnel and Park 1,100
TOTAL 4,010
* Cost reflects an allocation to undertake early improvements and commence an ongoing programme of larger scale public space improvements ** Excludes rail improvements (funded currently outside of LGWM) *** Cost estimates based on a Light Rail Transit style for Mass Transit
Programme Outcomes & Next Steps
The RPI assessment confirms that it will deliver strongly against the investment objectives. In particular, the
RPI will enable and support future growth by enhancing Wellington’s liveability and transport accessibility,
safety and adaptability.
The economic assessment in this business case quantifies several billion dollars of benefit in realising these
outcomes, but at a correspondingly high cost. The latter presents a challenge to LGWM partners, and
therefore an Indicative Package has been identified by the government as a more affordable way forward that
performs well against the investment objectives.
This Programme Business Case therefore recommends proceeding with detailed investigation of the Indicative
Package and the RPI to ensure LGWM delivers and realises the identified outcomes and vision.
PART A – The Strategic Case
Let’s Get Wellington Moving Programme Business Case – Draft Released 21 June 2019 1
PART A – THE STRATEGIC CASE
1. INTRODUCTION 1.1. Purpose
Let’s Get Wellington Moving (LGWM) is an alliance between Wellington City Council (WCC), Greater
Wellington Regional Council (GWRC), and the New Zealand Transport Agency (the Transport Agency).
LGWM seeks to deliver an integrated transport system that supports the community’s aspirations for
how Wellington City will look, feel and function.
Figure 1 LGWM regional and national location (LINZ, NZ Transport Agency)
This Programme Business Case summarises LGWM’s integrated transport planning process between
2015 and 2018. The purpose of the programme business case is to enable decisions on the best way
forward for investing in the central Wellington transport system over the long term. Supporting
documents containing more details about the development of the programme are published on the
LGWM website.
In developing this Programme Business Case, LGWM has followed the Transport Agency’s business
case guidelines. LGWM has had a strong focus on public and stakeholder engagement, and the need
for close integration with land use planning.
PART A – The Strategic Case
Let’s Get Wellington Moving Programme Business Case – Draft Released 21 June 2019 2
1.2. Background and Programme History
The 2007 Ngauranga to Airport Strategic Study identified the following emerging issues facing the
Ngauranga to Wellington Airport Corridor (see map of the corridor at Figure 2):
Increasing travel demand as a result of increasing population and predicted increases in vehicle usage
in the Wellington Region, in particular with respect to the Wellington CBD and associated major
regional facilities (such as the airport and port), will put pressure on the existing transport network and
services, parts of which are already at, or very close to capacity at peak times.
The key ‘high-level’ challenges identified in the 2007 study were:
Accommodating an overall increase in transport demand
Accommodating an increasing number of commuter trips to the CBD
Increasing the level of ‘penetration’ of passenger transport into the CBD to
facilitate/encourage a change in transport mode choices
Providing relief to existing (and future) ‘choke points’
Accommodating an increasing number of trips to/from the port and airport as passenger and
freight movements increase
Enhanced opportunities to cater for active modes of transport such as walking and cycling
The need to integrate urban form considerations into transport planning.
The 2008 Ngauranga to Wellington Airport Corridor Plan was developed to respond to these issues. It
defined a number of packages for improvements to the transport network within the corridor.
A key element of the plan was design and construction of major highway improvements at the Basin
Reserve to improve passenger transport, walking and cycling by separating north-south flows from
east-west traffic. The Transport Agency developed a Basin Bridge proposal to deliver this element of
the plan but, when this was considered by a Board of Inquiry in July 2014, resource consent was
declined. In August 2015 the High Court issued a ruling dismissing the Transport Agency’s appeal of
the Board of Inquiry decision.
Following the Basin Bridge decision, a partnership (LGWM) was established between WCC, GWRC and
the Transport Agency to develop an integrated and multi-modal improvement programme for the
whole Ngauranga to Airport corridor, to respond to Wellington’s long-term transport needs. This
Programme Business Case summarises the business case for investing in the improvement
programme LGWM has developed.
PART A – The Strategic Case
Let’s Get Wellington Moving Programme Business Case – Draft Released 21 June 2019 3
Figure 2 LGWM Ngauranga to Airport corridor map (LINZ, NZ Transport Agency)
PART A – The Strategic Case
Let’s Get Wellington Moving Programme Business Case – Draft Released 21 June 2019 4
1.3. Programme Partners
This programme development project has been undertaken collaboratively by the partners, WCC,
GWRC, and the Transport Agency as outlined in Table 1 and described in more detail in the following
subchapters.
Table 1 Let’s Get Wellington Moving Programme Partners
1.3.1. Wellington City Council WCC is the local authority responsible for Wellington City. The geographic scope of LGWM is within
the Wellington City territorial boundary. As a territorial local authority, Wellington City Council is
responsible for planning land use, managing urban growth, and the provision and operation of the
walking network, cycling network, and local road network within Wellington City.
1.3.2. Greater Wellington Regional Council GWRC is the organisation primarily responsible for overall regional transport planning and civil
emergency management. GWRC is also responsible for managing public transport services across the
Wellington region, including arranging funding and contracts for service delivery.
1.3.3. New Zealand Transport Agency The Transport Agency is the crown entity responsible for planning and investing in the land transport
system. It also manages the State Highway network and provides access to, and use of, the land
transport system (for example, through licensing drivers and vehicles, and collecting road user
charges).
1.4. LGWM Governance and Management
LGWM has been established as a partnership with governance arrangements as set out in Table 2.
The programme team has been led by an independent programme director (Barry Mein) and the
team members drawn from the member organisations. The programme team has commissioned
technical support work undertaken by a range of consultants.
PARTNERS KNOWLEDGE AREAS / RESPONSIBILITIES
Wellington City Council (WCC) Planning land use and managing urban growth
Provision and operation of walking network, cycling network, and
local road network
Greater Wellington Regional Council
(GWRC)
Strategic transport planning for the region
Provision of public transport services (buses and passenger rail)
Civil defence emergency management
New Zealand Transport Agency
(the Transport Agency)
Investor in land transport system through allocating the National
Land Transport Fund
Provision and operation of the State Highway network
Regulator of access to and use of the land transport system
PART A – The Strategic Case
Let’s Get Wellington Moving Programme Business Case – Draft Released 21 June 2019 5
Table 2 LGWM Governance (as at November 2018)
1.5. Programme Stakeholders
LGWM has met and interacted with representatives at stakeholder briefings, workshops, and one-on-
one meetings of the organisations set out in Table 3 below.
Table 3 LGWM Stakeholder Groups
GOVERNANCE GROUP (STRATEGIC DECISION MAKING AND OVERSIGHT)
Raewyn Bleakley (NZ Transport Agency) Mayor Wayne Guppy (UHCC)
Councillor Chris Calvi-Freeman (WCC) Councillor Chris Laidlaw (GWRC)
Councillor Barbara Donaldson (GWRC) Mayor Justin Lester (WCC)
Fergus Gammie (NZ Transport Agency)
ALLIANCE BOARD (SUPERVISE THE DEVELOPMENT OF LGWM PROGRAMME)
Pete Clark (NZ Transport Agency) Kevin Lavery (WCC)
Greg Campbell (GWRC)
PROGRAMME DIRECTOR
Barry Mein (Independent)
Stakeholder Group
Description Stakeholder Group
Description
Automobile Association (Wellington District Council)
Membership organisation representing people with motoring interests in the Wellington Region
NZ Police National police force response for enforcing criminal law, enhancing public safety, and keeping the peace
Architectural Centre Independent, voluntary organisation of architects, artists, designers and others
OraTaiao Association of health professionals concerned about climate change
Centreport Intermodal freight hub, linking road, rail, domestic and international shipping services
Our CBD Group of Wellington retail and hospitality stakeholders with an interest in the city CBD
Chorus Telecommunications infrastructure company
Porirua Chamber of Commerce
Community of business people in Porirua
Congestion Free Wellington
Coalition of many groups aiming to promote a more liveable Wellington city, responsive to climate change, by reducing reliance on the private car
PowerCo Owner and operator of Wellington's gas distribution network
Cycle Aware Wellington Cycling advocacy group that aims to get more people on bikes, more often, in Wellington
Retail NZ Retail trading associating representing over 65% of NZ's retail turnover
Cycle Action Network National voice for people on bicycles in NZ
Road Transport Forum
National association representing the commercial road freight industry
East by West Ferries Wellington's harbour ferry service running up to 16 return harbour crossings daily
Save the Basin A group advocating against building a flyover at the Basin Reserve and for better region-wide transport solutions
PART A – The Strategic Case
Let’s Get Wellington Moving Programme Business Case – Draft Released 21 June 2019 6
STAKEHOLDER
GROUP DESCRIPTION
STAKEHOLDER
GROUP DESCRIPTION
Fair Intelligent Transport
Group of professionals advocating for all-electric light rail in Wellington
Taxi Federation National body for taxi companies
First Retail Group Retail consultants, planners, and strategists
TramsAction Group advocating for the introduction of tram-train in Wellington to extend the current rail system
Generation Zero Youth-led environmental advocacy organisation that focuses on climate change
Vodafone Telecommunications company
Hack Miramar Group of Miramar residents that organises technology events
WCC Accessibility Advisory Group
Advisory committee providing the Council with feedback and advice from the view of people living with impairment
Hutt Valley Chamber of Commerce
Society of business people based in the Hutt Valley
WCC Environmental Reference Group
Forum for advice to Council during the developmental stages of urban design and transport projects
Inner City Association Group of residents, organisations, and property owners in Wellington's inner city
WCC Youth Council Advisory committee to the Council on issues that affect the city's youth
Kapiti Coast Chamber of Commerce
Collective voice for business in Kapiti Wellington Chamber of Commerce
Group encouraging regional development and representing the region's businesses
KiwiRail State-owned enterprise responsible for NZ's rail network and the Interislander ferries
Wellington Cable Car The operator of Wellington's cable cars
Heavy Haulage Association
National trade association for companies that transport overweight or overdimension loads
Wellington Civic Trust
Organisation working to help make Wellington the best of all possible places to live and work
Living Streets Aotearoa (Wellington)
Organisation for people on foot, promoting walking-friendly communities
Wellington Combined Taxis
Provider of Wellington taxi services
Light Rail Transit Association (NZ)
An international association concerned with better public transport through light rail and other systems
Wellington Electricity
Distributor of electricity to about 166,000 homes and business in the Wellington region
Mana Coach Services Provider of urban and chartered passenger transport
Wellington Free Ambulance
Provider of free paramedic care to the people of Greater Wellington and the Wairarapa
Motor Trade Association
National industry organisation representing over 4000 automotive businesses around NZ
Wellington Property Council
Collective voice for the commercial property industry in Wellington
Mt Cook Mobilised Community group advocating for residents of Mt Cook
Wellington Regional Hospital (CCDHB)
Wellington's regional hospital in Newtown
Mt Victoria Residents Association
Community group advocating for Mt Victoria residents
Wellington Tenths Trust
Ahu Whenua Trust administering Maori reserve lands in urban Wellington, Kaitoke and Upper Hutt
Mt Victoria Historical Society
Community group advocating for the protection and preservation of natural and built heritage in Mt Victoria
Wellington Water Manager of drinking water, stormwater, and wastewater services in the Wellington region
Ngāti Toa Rangātira Mana whenua and Kaitiaki of the Wellington region along with other iwi
Wellington International Airport Limited
Owner and operator of Wellington's international airport in Rongotai
NZ Bus Provider of urban passenger transport services in Wellington
WREDA Regional economic development agency for the lower North Island
NZ Couriers Nationwide courier service
PART A – Programme Context
Let’s Get Wellington Moving Programme Business Case – Draft Released 21 June 2019 7
2. PROGRAMME CONTEXT 2.1. Geographic Context
The scope of LGWM is to identify improvements to the transport system and associated urban
development opportunities in the focus area shown in Figure 2 (Section 0). This focus area should be
seen in the context of the wider Wellington regional transport system, as many of the journeys in the
central city start and finish outside the focus area.
Wellington’s transport system enables movement of people, goods and services. It is multi-modal in
nature, encompassing walking, cycling, public transport (buses, taxis, trains, ferries, cable cars, ride-
sharing), rail freight, and motor vehicles. The transport system also includes other elements such as
network management, information services, and parking provision.
2.2. Land Use and Urban Form
Land use, urban form and the economy are the primary drivers of demand for transport services in
the Greater Wellington region as a whole and in the central city area in particular.
In recent decades, major cities – such as Auckland, Sydney and Melbourne – have dominated
economic and population growth in Australasia, attracting ever greater shares of skills, business and
investment. Smaller cities have had to find ways to stand out and position themselves. What a city can
offer, in terms of quality of life and quality of jobs, is driving the decisions of mobile, skilled
populations about where they want to live.
Wellington has a world-class quality of life, a physical environment of outstanding beauty, a highly
skilled population, high incomes, healthy communities, and a reputation for creativity and quality
events. This is reflected in its reputation as a liveable city1. However, there is a need for Wellington to
constantly improve itself to continue competing internationally. To do this, the Wellington of the
future will need to be:
A resilient city and region capable of supporting intensified land uses
A growing and dynamic Wellington with world-class, inclusive place-making
Well-designed walkable neighbourhoods connected by a smart transport system
An attractive and compact city that’s more sustainable, accessible and safe
A city which attracts high value jobs and opportunities.
The right transport decisions and investments are fundamental to supporting this future vision for
Wellington. This will benefit the central city, the Wellington region, and the nation.
2.3. Growth Projections
The population of the Wellington Region currently stands at around 510,000 people. Under medium
projections the population is forecast to grow by 15% over the next 30 years, equating to 75,000
extra residents.
The distribution of this growth is estimated to be as follows:
30% will be focused around Wellington’s central city and inner suburbs
20% will occur in Wellington City’s northern suburbs 1 2018 Deutsche Bank named Wellington City as the most liveable city out of 50 global cities
PART A – Programme Context
Let’s Get Wellington Moving Programme Business Case – Draft Released 21 June 2019 8
13% will occur in other areas of Wellington City
The remainder (37%) will be around urban centres outside Wellington City, relatively evenly
split across the Kapiti Coast, Porirua, Upper Hutt and Lower Hutt, with a lesser proportion in
the Wairarapa.
Over 40% of the current 235,000 jobs in the Wellington region are located in the central city. The high
concentration of employment in the central city attracts commuters from the wider Wellington
region. The employment projections show regional employment growing by between 15% and 20%
over the next 30 years. The employment projections suggest that between 55% and 60% of future
growth in employment is likely to be focused in the central city, potentially increasing the number of
jobs there from the current 99,000 to between 114,000 and 131,000 over the next 30 years.
2.4. Current Transport System Design
2.4.1. Transport Corridors from the North North of the central city, State Highway 1 and Hutt Road run parallel to the main rail lines (the North
Island Main Trunk, the Johnsonville Line, and the Hutt Valley and Wairarapa Lines), with the primary
bus routes running along Hutt Road and Thorndon Quay.
Figure 3 Transport corridors to the north of Wellington Central City (LINZ, NZ Transport Agency)
PART A – Programme Context
Let’s Get Wellington Moving Programme Business Case – Draft Released 21 June 2019 9
2.4.2. Access to the Central City from the North
Public Transport Access The railway lines terminate at the Wellington Railway Station, located at the northern end of the CBD.
There are rail sidings to the north of the station and there is access for rail freight to CentrePort from
Waterloo Quay at-grade.
Rail passengers arriving at Wellington station, wishing to proceed southwards through the CBD, must
do so on foot, by bike, or by bus using the waterfront route (Waterloo and Customhouse Quays), or
along Featherston Street, Victoria Street, Willis Street, Lambton Quay and the Terrace.
Figure 4 Public Transport on the ‘Golden Mile’ within the central city (LINZ, NZ Transport Agency)
Most of the suburban bus services from the north and west run along Lambton Quay and Willis Street
(the Golden Mile shown in Figure 4), providing a convenient connection through the heart of the city.
The Cable Car terminal is also located on Lambton Quay. Taxi services operate from taxi ranks
throughout the central city.
PART A – Programme Context
Let’s Get Wellington Moving Programme Business Case – Draft Released 21 June 2019 10
Motor Vehicle Access Motor vehicles from the north enter the central city (or traverse it) by travelling along three routes –
State Highway 1, Hutt Road/Thorndon Quay and the Aotea Quay/Waterfront route. Road access to
CentrePort and the Cook Strait ferry terminals is from Aotea Quay.
State Highway 1 is a motorway until it enters the Terrace Tunnel, after which it traverses the local city
street network and connects to Mt Victoria Tunnel via a one-way system through Te Aro, comprising:
Vivian Street/Kent Terrace to Basin Reserve eastbound
Basin Reserve via the Arras Tunnel and along Karo Drive westbound
Figure 5 General traffic routes within the central city (LINZ, NZ Transport Agency)
While State Highway 1 provides a through route for vehicles passing through the central city and
towards the airport and hospital, the Vivian Street/Karo Drive one-way system also acts as a
distributor for the majority of vehicles (70%-75%) that use State Highway 1 to access the central city
or southern and eastern suburbs. Local routes that connect this part of State Highway 1 to the CBD
include Willis Street, Victoria Street, Taranaki Street, and the Cambridge/Kent Terraces. The principal
connections to the western suburbs are via Bowen/Glenmore Street, Salamanca Road and Aro Street.
PART A – Programme Context
Let’s Get Wellington Moving Programme Business Case – Draft Released 21 June 2019 11
2.4.3. Access to the Central City from the South and East The main access from the eastern suburbs and the airport is via the two-lane State Highway 1 Mt
Victoria road tunnel, Constable Street in Newtown, and the single lane Hataitai bus tunnel. Oriental
Parade and Evans Bay Parade provide an alternative waterfront route following the harbour’s edge
“Round the Bays” at the foot of Mt Victoria. This is also one of Wellington’s main cycle routes.
Figure 6 Transport corridors to the south and east of Wellington City (LINZ, NZ Transport Agency)
The main connections from the Hospital and Newtown to the CBD are along Adelaide Road/Kent and
Cambridge Terraces, Taranaki Street, Willis Street and Victoria Street. Bus services from the southern
suburbs use these routes, together with general traffic, pedestrians and cyclists. These routes
intersect at grade with State Highway 1 as they pass through Te Aro, both at the Basin Reserve and
Karo Drive/Vivian Street.
Other key transport services include harbour ferries, which connect the waterfront, Seatoun and
Eastbourne.
PART A – Programme Context
Let’s Get Wellington Moving Programme Business Case – Draft Released 21 June 2019 12
2.4.4. Network Operating Systems State Highway 1 is operated by the Transport Agency traffic operations centre at Johnsonville. Other
traffic signals within the city are managed from the traffic operations room at WCC. Rail services are
operated from the Wellington Railway station by Kiwirail and Transdev. Buses are managed by the
operators, generally under contract to GWRC.
2.5. Role of the Transport System
In the past, the development of tramways, passenger rail and bus services and, later, private motoring
allowed the city to develop in certain ways. This gave people the opportunity to live in suburbs away
from the central city, whilst still allowing them to access high value employment opportunities in the
CBD. However, in recent years there has been a strong trend for people to move back to living within
the central city, and this has led to more people enjoying the health benefits of walking and cycling to
work, and so avoiding the need to travel by motorised transport along increasingly congested
commuter routes.
The transport system has a key role to play in facilitating further growth in Wellington, in particular
supporting further intensification of the central city and the high quality of life it has to offer. Enabling
more people to live and move around the central city is desirable economically as it supports an
increasingly productive economy by matching innovative businesses with a highly skilled labour pool.
Good job opportunities and a high quality of life tend to attract talented people to the city.
Intensification in the central city and around public transport hubs is also desirable as it reduces the
environmental impacts of travel to and from the central city.
2.6. Current Transport System Pressures
In recent years, most of the growth in travel demand to, from and within the central city has been
accommodated by people choosing more sustainable ways to travel, by walking, cycling and using rail
and bus services. Private vehicle activity within the central city has been held in check by constrained
road corridor capacity, traffic congestion on the approaches to the central city, and the relatively high
cost of commuter car parking within the central city itself.
At peak times, parts of the central city network and routes to the central city operate at capacity for
general traffic. Buses are caught up in the traffic congestion so that service efficiency and reliability
are severely compromised. Traffic impacts negatively on amenity within the central city, and on the
safety and convenience of those moving around on foot and on bikes.
The passenger rail services are not caught up in traffic congestion because trains operate on their
own dedicated corridors. However, because the trains terminate at Wellington Station at the
northern end of the CBD, journeys to destinations further south can involve a lengthy walk or
transferring to bus services that stop frequently as they pass through the central city. This means that
car travel often provides the quickest journey through the central city to destinations to the south
and east of the CBD, despite the congestion of the road network during peak travel times.
Transport routes to access the central city and key regional destinations are limited in number and
constrained by the geography of the harbour and hills. The compact urban form resulting from this
challenging topography has helped to encourage relatively high use of public transport, walking, and
cycling as modes of travel. However, the reliance on a small number of corridors creates issues for
accessibility and resilience.
PART A – Programme Context
Let’s Get Wellington Moving Programme Business Case – Draft Released 21 June 2019 13
Overall, the system provides little ‘slack’ for unplanned events such as vehicle crashes, rail service
outages, and severe weather. The system is particularly vulnerable to seismic events, with several
fault lines in the area.
Figure 7 2016 and forecast 2036 Population (pink) and Employment (blue) in the Wellington Region (WCC)
PART A – Programme Context
Let’s Get Wellington Moving Programme Business Case – Draft Released 21 June 2019 14
Figure 8 Hazard risks to the transport system, blue and yellow areas represent evacuation zones (WCC)
PART A – Programme Context
Let’s Get Wellington Moving Programme Business Case – Draft Released 21 June 2019 15
2.7. National Strategic Context
LGWM has had regard to a number of national strategic documents and policies to ensure alignment.
The key national document is summarised below, with more detailed assessment of alignment
outlined in Appendix A.
2.7.1. Government Policy Statement on Land Transport (2018) The Government Policy Statement (GPS) 2018 sets out the Government’s priorities for the land
transport sector, including the outcomes the government expects through investment of the National
Land Transport Fund (NLTF). The GPS identifies safety and access as key priorities, supported by the
priorities of the environment and value for money.
The GPS strategic objectives are to provide a land transport system that:
Is a safe system, free of death and serious injury
Provides increased access to economic and social opportunities
Enables transport choice and access
Is resilient
Reduces greenhouse gas emissions, as well as adverse effects on the local environment and
public health
Delivers the right infrastructure and services to the right level at the best cost.
Themes have also been included in the GPS to assist understanding of how to effectively deliver on
the priorities. The themes influence how the results should be delivered to ensure the best transport
solutions for New Zealand are achieved. The themes for GPS 2018 are:
A mode-neutral approach to transport planning and investment decisions
Incorporating technology and innovation into the design and delivery of land transport
investment
Integrating land use and transport planning and delivery.
2.8. Regional Strategic Context
LGWM has had regard to a number of regional strategic documents and policies to ensure alignment.
The key regional documents are summarised below, with more detailed assessment of alignment
outlined in Appendix A.
2.8.1. Wellington Regional Land Transport Plan The Regional Land Transport Plan (RLTP) is a statutory document prepared under the Land Transport
Management Act that provides the agreed strategic direction for development of the region’s land
transport network. The 2015 Wellington RLTP identifies four key transport problem statements for
the region:
Transport inefficiencies lead to suppressed regional economic growth and productivity
Transport infrastructure deficiencies and poor user behaviour leads to a sub-optimal regional
road safety performance
Regional infrastructure that is vulnerable to disruption by unplanned events is potentially
resulting in an unacceptable cost of severance and restricted ability to recover over time
Poor delivery of transport and land use can result in a deteriorating living environment and
reduced transport choices for the region’s population.
PART A – Programme Context
Let’s Get Wellington Moving Programme Business Case – Draft Released 21 June 2019 16
The RLTP identifies eight strategic objectives in response to the above problems:
A high quality, reliable public transport network
A reliable and effective strategic road network
An effective network for the movement of freight
A safe system for all users of the regional transport network
An increasingly resilient transport network
A well planned, connected and integrated transport network
An attractive and safe walking and cycling network
An efficient and optimised transport system that minimises the impact on the environment.
The overall strategic approach in the RLTP recognises that the transport system has different roles
and uses at different times of the day and week, and that there are often trade-offs between
transport objectives. The goal is to have more people using public transport, walking, and cycling as
modes of travel - particularly at peak times when the transport network is in high demand. The
strategy however recognises that public transport, walking or cycling will not be feasible for every trip.
Multi-modal solutions are needed to effectively support the region’s economic growth and liveability.
2.8.2. Ngauranga to Airport Strategy The 2015 RLTP includes a Ngauranga to Airport Strategy chapter, which identifies the key problems,
benefits, and strategic responses specific to the LGWM focus area. This is under review as part of
LGWM, but currently promotes a multi-modal approach with four strategic principles:
A high quality and high frequency passenger transport ‘spine’
A reliable and accessible ‘ring’ or bypass route for vehicles
Inter-connected, safe, and convenient local street, walking, cycling and passenger transport
networks
Highly accessible and attractive ‘activity’ or shopping streets.
2.9. Local Strategic Context
LGWM has had regard to a number of local strategic documents and policies to ensure alignment. The
key local documents are summarised below, with more detailed assessment of alignment outlined in
Appendix A.
2.9.1. Wellington Urban Growth Plan: Urban Development and Transport Strategy 2014-43 Adopted in 2015, the plan is the Wellington City Council’s growth management strategy. The plan
seeks to deliver four key outcomes: a compact city, a liveable city, a city set in nature, and a resilient
city.
The plan integrates land use and transport planning, complemented by environmental and resilience
considerations. It focuses intensification in the central city and in areas with good access to public
transport and local services; this has significant impacts on transport planning through or around the
central city. Improvements to cycling, walking and public transport are integral to the strategy.
More recently, a document titled “Future City Vision: A Great Harbour City” has been developed
simultaneously with LGWM2. It explores the potential for the transport system to support Wellington
2 The document is independent advice commissioned by WCC to inform growth planning; it is not a formally
adopted document.
PART A – Programme Context
Let’s Get Wellington Moving Programme Business Case – Draft Released 21 June 2019 17
City’s future vision and urban development goal. The document highlights the role of LGWM as a
catalyst for urban renewal and growth, enhancing the capital city as a place to live, work and invest.
The city plans to accommodate its population and economic growth through a mix of intensification in
existing urban areas, which have good transport links, infrastructure and community facilities, and
limited urban expansion into greenfield areas.
The main projected growth areas identified in the 2015 Wellington Urban Growth Plan are:
The central city: around 20,000 more residents are expected to be accommodated in Te Aro,
Wellington Central, Pipitea and Thorndon by 2043
The Adelaide Road corridor, Newtown and the sub-regional centres (Johnsonville and
Kilbirnie): over 11,000 more people are expected to accommodate in these areas by 2043
New urban areas north of the city: over 11,000 new residents are expected in Lincolnshire
Farm, Woodridge, Churton Park and Stebbings Valley by 2043 (part of northern suburbs).
The forecasts reflect the significant potential for accommodating additional growth within the central
city and surrounding areas. This would reduce the need for people to travel longer distances for work
and leisure purposes, and make for a more compact, vibrant and environmentally responsible city.
2.9.2. Towards 2040: Smart Capital Adopted in 2011, Towards 2040 aims to “position Wellington as an internationally competitive city
with a strong and diverse economy, a high quality of life and healthy communities.” The vision has
four goals: People-centred city, Connected city, Eco-city, Dynamic central city.
The document envisages that “Wellington's people-centred city will be healthy, vibrant, affordable
and resilient, with a strong sense of identity and 'place'. This will be expressed through urban form,
openness and accessibility for its current and future populations.” The Dynamic central city goal
imagines that the central city will be a vibrant and creative place offering the lifestyle, entertainment
and amenities of a much bigger city, and that the central city will continue to drive the regional
economy.
2.9.3. Central City Framework The Central City Framework was adopted in 2011 and is a supporting document to Towards 2040. The
Framework contains a series of projects related to street structure, landscape and built form, which
seeks to influence the future shape of the central city.
2.9.4. Wellington City District Plan – Central Area The central area chapter of the District Plan (last amended October 2013) describes the desired
future for the central city. The District Plan sets a vision for a vibrant, prosperous, liveable city with a
Central Area comprising a commercial core with a mix of related activities. The plan’s central area
provisions are based on a list of principles that will guide future development.
PART A – Strategic Assessment
Let’s Get Wellington Moving Programme Business Case – Draft Released 21 June 2019 18
3. STRATEGIC ASSESSMENT 3.1. Investment Logic
An investment logic map was originally developed by LGWM in August 2016. The investment logic
map was subsequently reviewed in December 2017 to reflect insights and public engagement carried
out in October and November 2017. This updated investment logic is shown in Appendix B.
Further work carried out in late 2017 and in 2018 analysed the problem definition in the headings of
causes, effects and consequences as summarised in Table 4.
Table 4 LGWM Case for Change: problems and opportunities
The following sections present a brief overview of the causes, effects and consequences associated
with the problems and opportunities identified by LGWM, with supporting evidence. A
comprehensive evidence base is available in the ‘Case for Change’ and ‘Data Report’ documents.
3 Subsequent to the problems being finalised as part of the LGWM Progress Report, LGWM has an increased
focus on urban development and land use that is not fully captured within the problem causes and effects as presented.
PROBLEMS - CAUSES3 PROBLEMS - EFFECTS
Growing demand for travel to, from, through and
within the central city
Transport modes competing for limited space on
constrained corridors
Cross-directional movements creating conflicts
between movements and modes
Poor and declining levels of service
Increasing congestion and unreliable journey times
Vulnerability to disruption from unplanned events
Safety issues especially for active modes
PROBLEMS - CONSEQUENCES OPPORTUNITIES
Reduced amenity (e.g. noise, pollution, and
severance) for people living, visiting and working in
the central city
Lack of transport system capacity, particularly on rail
and bus services, constraining Wellington’s growth
Slower and less predictable travel time for journeys
to, from, within and through the central city
Increase in disrupted journeys for people and freight
and slower recovery
Deaths and serious injuries, especially for
pedestrians and cyclists
Enhance travel choice for access to, from, within
and through the central city
Make city streets more attractive and safer places
to be
Shape urban growth and activate urban
regeneration
Support increased productivity
Improve community health and wellbeing
Support enhanced environmental outcomes
PART A – Strategic Assessment
Let’s Get Wellington Moving Programme Business Case – Draft Released 21 June 2019 19
3.2. Transport System Causes
Wellington’s transport system is coming under pressure from economic growth, population growth
and changing land use patterns as shown in Figure 11. Intensification of both residential and
commercial land use in the central city, and an increase in the number of visitors, is leading to a
growth in short journeys and demand for a safe and convenient central city street network with a
high level of amenity. The growth in the number of jobs in the central city is also leading to an
increase in the number of longer distance commuters who need to travel into the central city at peak
times, especially from the north where new housing development is taking place.
Meanwhile the Wellington region as a whole is growing, and this is driving demand for journeys to the
central city and port, and through the central city to reach important destinations such as the airport
and hospital. This latter demand results in increased car travel through the central city as the public
transport system’s design is mainly focused on moving people into and out of the CBD.
These significant movements conflict with the increasing number of buses, pedestrian and cyclists
accessing the central city and moving around within it (as shown in Figure 9), adversely affecting the
amenity of the central city. Many through journeys use the same routes as commuter journeys (e.g.
Vivian Street and the waterfront quays).
In the absence of further improvements to the transport system capacity, the system will struggle to
accommodate growth because:
Growth in walking and cycling will not be supported by the current infrastructure which is
already crowded along key pedestrian routes and lacks a network of safe cycle routes
Growth in public transport demand will soon outstrip capacity (as shown in Figure 12). For
example, it is estimated that the capacity of the train services to the north will be exceeded
by demand within five years without investment. Constrained bus capacity within the CBD is
already affecting reliability and it is estimated that demand will exceed supply within the next
decade. If left unchecked, lack of public transport capacity will result in reduced job growth in
the central city and some people going back to commuting by cars
Growth in vehicular traffic within the LGWM focus area cannot be accommodated by State
Highway 1 in its current form, as some sections of State Highway 1 are already at capacity at
peak times. The few alternative routes to State Highway 1, such as the waterfront quays, have
limited additional capacity and pass through sensitive urban environments.
PART A – Strategic Assessment
Let’s Get Wellington Moving Programme Business Case – Draft Released 21 June 2019 20
Figure 9 Cross-movements in Te Aro – morning peak
Figure 10 Travel time variability for some journeys
PART A – Strategic Assessment
Let’s Get Wellington Moving Programme Business Case – Draft Released 21 June 2019 21
Figure 11 Number of people entering the central city during the 2016 morning peak (left) and programme forecast 2036 (right)
Figure 12 Public transport capacity and forecast demand
PART A – Strategic Assessment
Let’s Get Wellington Moving Programme Business Case – Draft Released 21 June 2019 22
3.3. Transport System Effects
Without remedial action, the net result will be that levels of service will progressively deteriorate for
all modes of transport, resulting in unpredictable journey times (as shown in Figure 10). There will
also be environmental issues, less safe cycling conditions and walking becoming a less attractive
option.
This will create the potential for increased safety risks at conflict points (as shown in Figure 13) and
intensify the impact of unplanned events on the transport system. The limited ability of the transport
system to accommodate growth will undermine the future success of Wellington City and the wider
region.
The relatively low number of corridors that provide access to and within Wellington City, combined
with the potential for natural hazards like earthquakes and storms, and increasing risks resulting from
climate change, mean that hazard events have the potential to disrupt access to the CBD and
surrounding communities. It could take a long time to recover some of these connections as was
illustrated by the recent prolonged closure of State Highway 1 near Kaikoura.
Figure 13 Heatmap of fatal and serious injury crashes 2000-2017 (WCC, NZ Transport Agency)
3.4. Transport System Consequences
In the absence of investment to address the above problems (both causes and effects) the following
consequences are expected:
There will be an increase in crowding on rail and bus services, and the road network will
become increasingly congested. The transport system will be unable to support even the ‘do
minimum’ growth scenario. This will affect housing affordability and people’s choices of
where to live and work
PART A – Strategic Assessment
Let’s Get Wellington Moving Programme Business Case – Draft Released 21 June 2019 23
Travel time variability will increase for all modes of transport. This will impact negatively on
the reliability of the system to get people to their destinations on time, leading to losses in
productivity and reduced leisure and personal time. It will also reduce the reliability of goods
reaching the port, airport and other destinations on time
The number of deaths and serious injuries to pedestrians and cyclists will remain
unacceptably high. This will result in social and economic costs, including social trauma, lost
productivity, and increased healthcare costs
Reductions in safety, amenity and convenience will deter walking and cycling, impacting
negatively on the health benefits that come from using active modes and the associated
environmental benefits of reduced transport emissions
Increased noise, pollution and severance will affect the amenity and attractiveness of
Wellington’s central city as a place in which to live, do business and visit
The transport system will remain vulnerable to disruption from day to day incidents and
large-scale hazard events. Smaller disruption events will have more far reaching impacts
because the transport system will be operating at capacity for more of the day. Large scale
hazard events will result in long recovery times for the region’s key lifelines.
3.5. Transport System Opportunities
Addressing the problems identified above creates the opportunity to improve a number of social,
economic and environmental outcomes for the city and region. These key opportunities are to:
Shape urban growth and activate urban regeneration – by significantly increasing accessibility
to the central city and amenity within it, land use intensification will be facilitated in locations
that support compact and sustainable urban form, boosting agglomeration benefits and land
value uplift
Create city streets that are more attractive places to be – through less traffic, slower traffic
speeds, less noise and air pollution, and enhanced street level amenity, city streets will be
safer and more pleasant places for people
Enhance travel choice for access to, from, within and through the central city – through a
range of travel options that provide safe, convenient, attractive, and reliable journeys
Support increased productivity – through more reliable and predictable journey times, people
will be able to use their time more productively and freight efficiencies can be unlocked. Less
disruption from incidents affecting the transport network will mean less lost time and
economic cost to the region. Technology advances will help to unlock the full potential of
transport investment and support more efficient movement of people and freight
Improve community health and wellbeing – through more people walking, cycling and using
public transport, with significant associated health benefits. Better access to employment,
education, services and facilities will contribute to social inclusion and community wellbeing
Support enhanced environmental outcomes – through more people using low or no emission
transport options (walking, cycling and public transport) and through increasing urban
densities near the city centre and other key centres so that more destinations will be within
convenient walking and cycling distances.
PART A – Strategic Assessment
Let’s Get Wellington Moving Programme Business Case – Draft Released 21 June 2019 24
Key pieces of evidence for these opportunities and consequences include:
Wellington CBD has the most productive jobs and highest employment density in New
Zealand, with a wage premium of between $13,000 and $20,000.
During the morning peak, 50% of rail passengers arrive between 7:50am and 8:20pm and
40% of people arriving by bus do so between 8:00am and 8:30am. Several public
transport services that arrive during this time are at capacity. Forecast growth will mean
that more services operate at capacity and people will increasingly respond by changing
their travel behaviour.
The commuter rail network is forecast to reach capacity by 2028. The bus network is
forecast to reach capacity by 2026. This could result in 3000 jobs being deferred or
located elsewhere.
Cyclists account for 1% of distance travelled and 20% of transport related deaths and
serious injuries in Wellington City. Nearly 1 in 3 people would prefer to cycle, less than 1
in 10 regularly do. 55% of people say they would cycle more if infrastructure was
improved.
Three out of the ten assessed CBD streets have Very Poor levels of urban amenity
(influenced by traffic volumes, traffic speed, footpath area, vehicle traffic area, footpath
and road material, density of street furniture, and green space coverage).
A large-scale hazard event could disrupt road access to and through Wellington City for
up to three months. Even a relatively small-scale event can come at a significant cost,
with the storm event in June 2013 estimated to cost the region $43M4.
3.5.1. Technological changes Transport technology advances are likely to bring significant benefits to Wellington’s transport
system. For example:
Modern vehicle safety systems will enable vehicles to travel at an optimum distance for any
given speed. In conjunction with autonomous braking this will improve safety outcomes for
vehicle occupants and for pedestrians and cyclists
The advent of autonomous vehicles could make the system more energy efficient through
smoother acceleration and braking. In conjunction with more advanced network
management systems this will make better use of transport infrastructure by keeping traffic
flowing smoothly and reducing ‘stop-start’ events on the network
The increased availability and use of electric vehicles (including electrically assisted bicycles)
will bring major benefits from reduced greenhouse and other emissions
The increased use of mobility-as-a-service (the use of information systems to enable
customers to have more flexibility to choose the mode of travel for particular journeys on a
pay-per-use basis) may lead to reduced car ownership, and a willingness to use other modes
more often than is currently the case.
4 The transport impacts of the 20 June 2013 storm (Ministry of Transport, NZ Transport Agency, KiwiRail,
GWRC)
PART A – Strategic Assessment
Let’s Get Wellington Moving Programme Business Case – Draft Released 21 June 2019 25
While technological change will bring major benefits, it also has the potential to be major
‘disruptor’ of the transport system, producing negative results that are not sought by LGWM.
For example:
The advent of autonomous vehicles may lead to more vehicle kilometres travelling on the
network, increasing greenhouse gas emissions and other pollutants. It may also act as a
disincentive for people to use public transport, adding to congestion
The increased use of mobility-as-a-service may lead to the increased circulation of taxis and
ride sharing vehicles around the network waiting to pick up passengers. This could worsen
congestion
A particular issue will be the impact of autonomous vehicles and ride-sharing on the
effectiveness of parking controls. At present the high cost of parking in the central city plays a
crucial role in managing demand for private vehicle use, particularly for commuting journeys.
The use of ride-sharing and potentially autonomous vehicles could see a reduction in the
effectiveness of this pricing mechanism as the main demand management tool.
In summary, technological changes may be helpful in addressing key problems, but there is
uncertainty about the net effect of technological changes on the key issue of growing demand for
trips with constrained network capacity. It seems very unlikely that technology will solve this problem
alone without other changes also being made to the way the transport system is configured and
operated.
PART A – Programme Objectives
Let’s Get Wellington Moving Programme Business Case – Draft Released 21 June 2019 26
4. PROGRAMME OBJECTIVES 4.1. Urban Design and Transport Principles
Feedback from early public engagement in mid-2016 indicated that people want a liveable city that is
easy to get around. They also want less traffic and congestion, together with good public transport,
walkability, and the ability to cycle safely. Access to the waterfront and harbour, and availability of
parking are also key issues for many people.
Using the results from public feedback the LGWM team developed 12 urban design and transport
principles, which are summarised under the key elements of the Wellington future vision in Figure 14.
PART A – Programme Objectives
Let’s Get Wellington Moving Programme Business Case – Draft Released 21 June 2019 27
Wellington Future Vision
Let’s Get Wellington Moving Guiding Principles
Figure 14 Alignment between Wellington future vision and LGWM guiding principles
PART A – Programme Objectives
Let’s Get Wellington Moving Programme Business Case – Draft Released 21 June 2019 28
4.2. LGWM Investment Objectives
Based on initial feedback from the public in 2016 and the formulation of the 12 guiding principles, a
set of programme objectives was developed. Following further engagement with the public in 2017,
these objectives were refined and developed into investment objectives through the addition of Key
Performance Indicators (KPIs).
The five investment objectives with their associated KPIs are summarised below:
OBJECTIVE: A transport system that…
KEY PERFORMANCE INDICATOR
Description
Enhances the liveability of the central city
Amenity Index
A measure of the quality of the urban environment including greenspace, urban
design, traffic volumes/speeds, and pedestrian space
Carbon dioxide emissions
Transport-related CO2 emissions in the central city
Urban development
potential
An assessment of the opportunities for urban development and value uplift
Provides more efficient and reliable access to support growth
Network catchment
The number of people living and working within 30 minutes of key locations
Travel time reliability
The reliability of travel time for journeys by different modes to key regional locations
Reduces reliance on private vehicle travel
System occupancy
The ratio of people travelling to the central city (by all modes) against private vehicles travelling
to the central city
Level of service for walking
Delays for people walking in the central city
Level of service for cycling
An assessment of the quality of cycling facilities
Improves safety for all users
Safety for walking and
cycling
An estimate of the safety benefits for people walking and cycling in and around the central
city
Is adaptable to disruptions and future uncertainty
Network resilience
An assessment of the network’s resilience to disruption caused by large-scale natural hazards
These investment objectives were subsequently developed into SMART objectives (Specific,
Measurable, Attributable, Realistic, Time bound), as shown in Section 9 and Appendix C.
PART B – Developing the Programme
Let’s Get Wellington Moving Programme Business Case – Draft Released 21 June 2019 29
PART B – DEVELOPING THE PROGRAMME Overview
An integrated and multi-modal improvement programme includes changes to infrastructure, services,
operations and policies. The key challenge in developing a recommended LGWM investment
programme was to carefully consider the many different ways of combining interventions into
potential investment programmes, before narrowing down the options to a shortlist, and finally
reaching conclusions on the preferred way forward.
Developing the programme was carried out in several stages. The first stage (summarised in Part B1)
was to develop an overall strategic response to address the problems and opportunities set out in
Part A. Part B2 summarises some of the analysis done during and following the programme
development. The final stage (summarised in Part B3) was to iteratively develop and assess
programme options through a longlist and shortlist assessment process to arrive at a recommended
programme of investment.
Summary of Part B1
The following methodology was followed to develop the strategic response (summarised in Figure
15):
Identify a wide range of interventions and select ones that could be effectively combined into
investment scenarios to address the problems and opportunities identified in Part A
Compile the selected interventions into ‘test scenarios’ that explore the key dimensions of
choice for addressing the problems and opportunities at a system level
Assess the test scenarios qualitatively against the objectives, and use the insights from this
assessment to develop the overall strategic response
Develop illustrative investment scenarios for the purpose of engaging with the public about
the strategic response and the scale of investment they would like to see
Develop KPIs that underpin the programme objectives in order to create SMART investment
objectives
Figure 15 Programme Development Methodology – Part B1
Potential Interventions
Test Scenarios Strategic Response Engagement
Scenarios SMART Objectives
PART B – Developing the Programme
Let’s Get Wellington Moving Programme Business Case – Draft Released 21 June 2019 30
Summary of Part B2
The following analyses were undertaken as LGWM developed and refined programme options
(summarised in Figure 16):
Analysis of emerging programme components that was undertaken during the longlist and
shortlist programme option development.
Ongoing further analysis of recommended programme of investment components to refine
and inform the programme.
Figure 16 Programme Development Methodology – Part B2
Summary of Part B3
The following actions were undertaken to develop and assess programme options (summarised in
Figure 17):
Develop a longlist of programme options and assess these for their performance against the
investment objectives
Select a short list of programme options and refine the assessment of their performance
against the investment objectives
Identify a recommended investment programme, optimise the programme detail, assess the
programme, and identify key risks, uncertainties and opportunities.
Figure 17 Programme Development Methodology – Part B3
Programme Development Analysis Further Analysis
Longlist Programme Options Shortlist Programmes Options Recommended Programme of
Investment
PART B1 – Strategic Response: Potential Interventions
Let’s Get Wellington Moving Programme Business Case – Draft Released 21 June 2019 31
PART B1 – STRATEGIC RESPONSE This part summarises the process that was followed to develop the overall strategic response to
address the problems and opportunities set out in Part A.
5. POTENTIAL INTERVENTIONS 5.1. Intervention Development and Assessment
The initial process of identifying possible interventions is summarised below. A more detailed
explanation can be found in Note 1 – Intervention Longlist Screen in Appendix D.
5.1.1. Identification An initial list of interventions was developed in a LGWM workshop. The process took into account
feedback from the LGWM website, the LGWM phone survey, panel surveys from Greater Wellington
Regional Council and Wellington City Council and feedback collected from stakeholders by the New
Zealand Transport Agency. LGWM also looked at earlier work on Wellington’s transport options, such
as the 2013 Wellington Public Transport Spine Study.
5.1.2. Categorisation The second stage in narrowing down the choices was to group the potential interventions by
categories. The categories were simple groupings by common characteristics – for example, bringing
together all of the potential interventions related to public transport.
The set of categories adopted was:
Land-use intensification Land-use dispersal Manage demand: financial Manage demand: non-financial Enhance supply: high investment in road capacity Enhance supply: high investment in public transport Incremental improvements: road network Incremental improvements: public transport network Enhance interventions to motor vehicle use Resilience-specific.
5.1.3. Assessment The potential interventions were subsequently assessed by a transport planning and evaluation group
to determine which interventions should be candidates to be included in possible scenarios and
programme options. The large majority were classified as ‘keep’ i.e. candidates for inclusion in the
scenarios and long-list programme options.
The possible reasons not to consider a potential intervention further were:
Fatal Flaw – A potential intervention had some characteristic that, in the professional
judgment of the evaluators, meant it could not contribute to a possible programme option.
Such reasons included expected cost being disproportionate to possible benefits,
impracticality, or the concept having been tried previously without worthwhile results.
Exclude – Outside the programme scope or not an intervention that could be influenced by
the programme.
Given – An intervention that had already been committed.
PART B1 – Strategic Response: Test Scenarios
Let’s Get Wellington Moving Programme Business Case – Draft Released 21 June 2019 32
6. TEST SCENARIOS The standard business case methodology for this stage would have been to develop a longlist of
programme options that would be compiled from a subset of the interventions. However, this would
have resulted in the production in a very large number of programme options due to the complexity
of the Wellington transport system.
In order to narrow down the range of programme options to a manageable number, ‘test’ scenarios
were developed to explore the likely range of realistic programme options at a high level. Scenarios
were developed comprising interventions that were indicative in nature, but sufficiently detailed to
explore interdependencies and enable qualitative assessment.
6.1. Test Scenario Development (2016)
Development of a series of test scenarios began by considering the qualitative gap in the level of
service for each mode, for each of four problem statement areas: reliability and economic
productivity, liveability, safety, and resilience. Different scenarios focusing on each of the four
problem areas were then created by considering the relative scale of different types of intervention
that might achieve the desired outcomes for the emphasised problem area.
The different intervention areas were:
Walking
Cycling
Public Transport
Commuter and Through Traffic
Local Streets Traffic
Hard TDM (pricing-based travel demand management)
Soft TDM (encouragement-based travel demand planning e.g. school travel planning)
Operations.
This resulted in 15 test scenarios, targeted at achieving outcomes in LGWM problem areas and with
each scenario focusing on a different approach to addressing the problems and opportunities. Some
of the scenarios were intentionally extreme in order to test whether focusing on a single type of
investment (such as additional road capacity or strengthened demand management) would perform
well in addressing the problem areas. Table 5 sets out the relative scale of interventions to achieve
outcomes in each of the problem areas for the fifteen test scenarios. Appendix E shows the types of
interventions that might be expected to deliver these outcomes.
PART B1 – Strategic Response: Test Scenarios
Let’s Get Wellington Moving Programme Business Case – Draft Released 21 June 2019 33
Table 5 Summary of Longlist Test Scenarios
EMPHASIS ANTICIPATED OUTCOME AND RELATIVE SCALE OF INTERVENTION
Rel
iab
ility
an
d E
con
om
ic P
rod
uct
ivit
y
Test Scenario A - An economically
productive and inclusive city has a high
level of motorised and public transport
mobility, allowing its citizens and
employees convenient, direct and rapid
access to all parts of the city and wider
region. Any excess demand to the city
centre is self-managed.
Test Scenario B - An economically productive,
modern city has very high standards of pedestrian
connectivity and a high quality environment,
especially in its city centre. The city is served with a
very effective public transport system, while the
roads have sufficient capacity for essential traffic.
Test Scenario C - An economically
productive city has an effective,
high capacity strategic road and
public transport network, with a
vibrant people-focused city centre.
Test Scenario D - An economically productive city has a high
level of motorised mobility and good public transport,
allowing its citizens and employees convenient and direct
access to most parts of the city and wider region.
Test Scenario E - A productive, economically rational city has very high
standards of pedestrian connectivity and a high quality environment,
especially in its city centre. The city is served with a very effective public
transport system, while road use is managed with advanced systems to
ensure availability for essential traffic.
Live
abili
ty
Test Scenario F - A liveable city is one where there are low
levels of road traffic and most peoples' needs for travel are
met through walking, cycling and public transport. Roads
are prioritised for more sustainable modes and managed
with advanced systems to ensure availability for essential
traffic.
Test Scenario G - A highly liveable city has easy, affordable access for all,
with excellent public transport, many shared use and calmed streets and a
strong feeling of safety.
Test Scenario H - A highly liveable city is one where local
streets are prioritised for people and separated from high
levels of motorised traffic
Test Scenario I - A city has high liveability when people and freight heading
to essential facilities throughout the city have high levels of vehicular access
while the city centre is more served by other modes that don't compete for
space with through traffic.
PART B1 – Strategic Response: Test Scenarios
Let’s Get Wellington Moving Programme Business Case – Draft Released 21 June 2019 34
EMPHASIS ANTICIPATED OUTCOME AND RELATIVE SCALE OF INTERVENTION
Safe
ty
Test Scenario J - A safe city is one where
the evidential safety issues are
addressed as a priority. Vulnerable
modes enjoy high levels of protection.
Test Scenario K - A safe city has vulnerable users
separated from general traffic with road space
prioritised for active modes and public transport.
Traffic is managed to reduce higher speed crashes
with advanced systems that also ensure sufficient
availability for essential traffic.
Test Scenario L - A safe city is one
where people are unlikely to have
a serious crash on the roads as
they are designed and operated to
the appropriate standard for their
use. People feel secure when
travelling on public transport.
Res
ilien
ce
Test Scenario M - A resilient city has
focused on the evidential transport
network issues and prioritised measures
to address them.
Test Scenario N - A more resilient city is one where
there are multiple transport options and where the
transport networks are suitably engineered.
Effective preparations have been made for
recovery.
Test Scenario O - A resilient city is
secure against a variety of natural
threats. It has redundancy in its
transport system which is well-
built and unlikely to suffer
catastrophic failure.
PART B1 – Strategic Response: Test Scenarios
Let’s Get Wellington Moving Programme Business Case – Draft Released 21 June 2019 35
6.2. Test Scenario Assessment
High level multi-criteria analysis (MCA) was then carried out on 12 of the test scenarios to assess their likely performance in achieving the investment objectives and their underpinning key result areas (shown as Tier 2 criteria in Table 6 below)5. Three scenarios developed to focus on resilience outcomes were not included in this assessment as it was deemed unrealistic to pursue a programme focused solely on resilience outcomes.
Table 6 Test scenario MCA criteria
TIER 1 TIER 2
A transport system
that enhances the
liveability of the
central city
Improved walkability in the CBD with better access to the waterfront
Enhanced urban environment
Reduced impact of motorised transport in CBD
Minimised adverse effects on natural environment
Minimised impacts on built environment
No increase to number of vehicles in the CBD
A transport system
that provides more
efficient and reliable
access to support
growth
Increased reliability and improved access to and from CBD
Consistency with the Urban Growth Plan and Wellington Regional
Strategy
Improved throughput of people and goods on strategic corridors
Increased reliability of access to and from the airport, hospital and port
Transport demand is able to be spread across the day (not just in peaks)
Reduced PT travel time variability
A transport system
that reduces reliance
on private vehicle
travel
Increased PT catchment
Improved pedestrian mode share
Improved cycling mode share
Increased vehicle occupancy
Improved PT mode share
A transport system
that improves safety
for all users
Reduced deaths and serious injuries for road users
Improved safety for pedestrians and cyclists
5 Key result areas were initially developed as a way of developing performance measures for each of the
objectives and were superseded with the development of SMART investment objective KPIs.
PART B1 – Strategic Response: Test Scenarios
Let’s Get Wellington Moving Programme Business Case – Draft Released 21 June 2019 36
A transport system
that is adaptable to
disruptions and future
uncertainty
Adaptability to be able to respond and recover from unplanned events
Adaptability and flexibility to cope with future uncertainty and
technologies
Implementability Consentability
Feasibility
Cost Capital cost
Operational cost
The MCA results and accompanying report are shown in Appendix F. The MCA process outcomes
were summarised as:
Scenario B and C were the equal best performing scenarios against all of the criteria assessed
Scenario C was the best performing scenario against the second efficiency and growth criteria
(Consistency with the Urban Growth Plan and Wellington Regional Strategy)
Scenario H was the third ranked scenario in the assessment
Scenario E performed best against the third criteria, reducing reliance on private vehicles, due
to the combination of pricing and PT enhancements
Scenario J was the most implementable scenario
Scenario L was one of the poorer performing scenarios as whilst it did not have significant
impact, it also did not score highly against the majority of the assessment criteria
Scenarios A and D were the lowest ranked of those assessed, however scenarios A and D also
performed well against the criteria associated with and efficient and reliable transport system
that supports growth.
6.3. Test Scenarios Conclusion
The assessment of the test scenarios produced useful insights, and these were used as a basis for
developing the LGWM Strategic Response.
The key insights were:
The performance of the test scenarios was variable across the full range of key result areas.
Extreme scenarios did not perform well against the key result areas. Wellington has a
complex transport system that is highly interdependent. Focusing on specific outcomes of the
transport system means that other outcomes may not also improve or may become worse as
trade-offs occur. It was concluded that a holistic multi-modal approach was needed
A pricing-only approach (with optimised use of the existing system), would not on its own
address the fundamental issue that transport demand is increasing because the city is
growing, and the current transport system will not have the capacity to accommodate the
extra journeys in the long term
Increasing the capacity of State Highway 1 in isolation would not produce acceptable levels of
service for traffic accessing the central city due to the already constrained nature of the CBD
PART B1 – Strategic Response: Test Scenarios
Let’s Get Wellington Moving Programme Business Case – Draft Released 21 June 2019 37
street network. Additional capacity and parking within the street network would be
undesirable from an urban amenity and place-function perspective
Movement within the central city is important but there is also a need to enable people to
access the central city from more distant areas. This would need to be by walking, cycling, a
high-quality public transport network, and supported by travel demand management
There are opportunities to improve the management and operation of the existing transport
system and the way in which people use it. For example, optimising traffic signals to provide
more green time to pedestrians near the railway station when trains arrive. These
opportunities could be tailored to maximise the benefits of whichever wider scenario was
eventually selected.
In light of these insights, a decision was made by LGWM to develop a set of multimodal scenarios that
would integrate the best performing elements from the test scenarios to produce a range of
illustrative scenarios that would perform more consistently across all the key result areas.
6.4. Community and Stakeholder Workshops (early 2017)
In March and April 2017 LGWM held a series of community and stakeholder workshops on key issues,
facilitated by an independent research company. The purpose of the workshops was to seek feedback
on whether the work was heading in the right direction, and views on what was needed to be covered
by the scenarios for public engagement later in the year.
The test scenarios that were assessed as performing well in the MCA assessment were used as a basis
for identifying focus areas to seek feedback on:
Better public transport
Improving the State Highway
Active transport improvements (walking and cycling)
Managing travel demand.
Attendees identified the following information as something that would like to see covered by
scenarios for public engagement later in 2017:
Evidence that supports each scenario
Which interventions have been rejected and why
Descriptions of land use and planning constraints
Costs for each scenario
How each scenario fits into an integrated and holistic plan for the city and the region
More information about specific interventions.
PART B1 – Strategic Response: Developing the Strategic Response
Let’s Get Wellington Moving Programme Business Case – Draft Released 21 June 2019 38
7. DEVELOPING THE STRATEGIC RESPONSE LGWM developed a strategic response to the problems and opportunities identified above. The
strategic response is summarised in Table 7.
It sets out the overall approach to improving Wellington’s transport system that would address the
identified problems and opportunities in a way that best achieves the programme objectives. It also
provides examples of high level ‘strategic interventions’ that will help transform the current transport
system into the desired one.
The strategic response acknowledges that Wellington will be able to meet the challenge of growth –
to absorb additional residents and to continue to sustainably perform its core economic function –
only if the transport system can move more people, goods and services reliably without more
vehicles, as part of an integrated urban strategy for the city. This means:
Supporting a safe and liveable city where many more people will live, work and play
Recognising and balancing the needs of all transport users and those affected by the
transport system
Increasing resilience to incidents, natural events and disruptive technology
Encouraging development in a way that supports more sustainable transport choices.
Without implementing such an integrated strategy, the challenges facing Wellington’s transport
system will threaten to derail its productivity, liveability and attractiveness.
PART B1 – Strategic Response: Developing the Strategic Response
Let’s Get Wellington Moving Programme Business Case – Draft Released 21 June 2019 39
Table 7 Strategic Response Table
TRANSPORT SYSTEM ATTRIBUTES STRATEGIC APPROACH STRATEGIC INTERVENTIONS
A transport system that moves more people, goods and services reliably with fewer vehicles, while:
Supporting a safe and liveable city where many more people will live, work and play
Recognising and balancing the needs of all transport users and those affected by the transport system
Increasing resilience to incidents, natural events and disruptive technology
Encouraging development in a way that supports more sustainable transport choices.
Make the most of what we have
Optimise the transport system and make it safer
Encourage people to walk, cycle, and use public transport more, and use cars less
Deliver a step change in public transport
Substantially improve public transport capacity, quality and performance
Encourage urban intensification near public transport
Improve journeys to, from and in the central city
Prioritise people walking, cycling, and using public transport on key corridors
Improve accessibility and amenity of places and streets
Ensure goods and services journeys are reliable
Improve journeys through and around the central city
Reduce conflicts between different transport users and traffic flows
Increase the resilience and reliability of our transport corridors, especially to the hospital, port, and airport
Encourage mode shift to walking, cycling, and public transport
Enable mode shift with improvements to walking, cycling and public transport infrastructure, and land use policies
Create dedicated/priority routes to support key changes
Reduce road space for general traffic in the central city and along dedicated/ priority routes
Manage the network to limit increases in general traffic and operate the network safely and efficiently
Encourage through traffic to relocate away from the central city and other sensitive locations
PART B1 – Strategic Response: Scenarios for Engagement
Let’s Get Wellington Moving Programme Business Case – Draft Released 21 June 2019 40
8. SCENARIOS FOR ENGAGEMENT 8.1. Engagement Scenarios Development
To illustrate how the strategic response might be translated into a programme of interventions,
LGWM developed four future scenarios with differing levels of transport intervention. The scenarios
formed the basis of a public engagement exercise in late 2017. Public and stakeholder feedback was
sought on the scenarios, and the willingness to accept increasing impacts (on-street parking, built
environment and heritage, environment, construction disruption, cost) in order to achieve increasing
benefits against the objectives.
The scenarios were incremental, as shown in Table 8.
Scenario A included making most of what we have got by prioritising walking, public transport
and cycling in the central city, and improving amenity and safety in the CBD
Scenario B included additional investment, reducing conflicts at the Basin Reserve enabling
current bus services to be transformed into a mass transit system on spine routes, and
providing better access to the east
Scenario C included additional investment, reducing conflicts with vehicle traffic for
pedestrians, public transport services and cyclists in Te Aro, improving access to the airport
and other regional destinations from the north, and unlocking redevelopment opportunities
in Te Aro
Scenario D included additional investment, increasing capacity through the Terrace Tunnel,
enabling less through traffic on waterfront quays, improving safety and amenity in the CBD,
and improving access to the port from the north.
A more complete description of the scenarios can be found in the publicly available engagement
material6.
Table 8 Summary of Engagement Scenarios
SCENARIO RATIONALE KEY INTERVENTIONS
Scenario
A
Prioritise walking, public transport and
cycling in the central city
Improve amenity and safety in the CBD
Dedicated bus lanes on the Golden Mile, improved walking
and cycling environment in the central city, with lower CBD
speed limits
Use traffic signalling and other intelligent transport systems
to align waiting times at junctions and crossings with agreed
priorities for different users of the transport system
Scenario B
As above plus:
Reduce conflicts at the Basin Reserve
enabling current bus services to be
transformed into a mass transit system on
spine routes
Provide better access to the east
Scenario A plus:
Basin Reserve grade separation, Mt Victoria tunnel
duplication and Ruahine/Wellington St widening (with public
transport, active mode and high occupancy vehicle priority),
enables extension of continuous prioritised public transport
spine to the hospital, Kilbirnie and the airport
6 http://getwellymoving.co.nz/public-engagement/
PART B1 – Strategic Response: Scenarios for Engagement
Let’s Get Wellington Moving Programme Business Case – Draft Released 21 June 2019 41
Scenario C
As above plus:
Reduce conflicts with vehicle traffic for
pedestrians, public transport services and
cyclists in Te Aro
Improve access to the airport and other
regional destinations from the north
Unlock redevelopment opportunities in Te
Aro
Scenario B plus:
Shift eastbound State Highway 1 from Vivian St to Karo Drive
alignment with cut and cover sections
Change priorities on Vivian Street to reduce severance and
improve amenity
Scenario D
As above plus:
Remove Terrace Tunnel bottleneck, enabling
less through traffic on waterfront quays
Improve safety and amenity in the CBD
Improve access to the port from the north
Scenario C plus:
Duplication of Terrace Tunnel, an additional southbound lane
on State Highway 1 between Ngauranga and Aotea Quay and
removal of traffic lane on waterfront quays
8.2. Engagement Scenarios Assessment
Prior to beginning engagement, LGWM undertook a high-level assessment of the four shortlisted
scenarios against the programme guiding principles and programme objectives so that the
engagement would have context on the relative scale of benefits and impacts of the four scenarios.
The assessment was based on feedback from a panel of technical specialists, using a combination of
both qualitative and quantitative measures. The technical specialist assessment is shown in Appendix
G. The assessment was indicative only as the scenarios were high level approaches. Their purpose was
to help understand how different large improvement projects might perform as a package.
A summary of the assessment is shown in Table 9 and Table 10. A more complete description of the
scenario’s assessment can be found in the publicly available engagement material7.
7 http://getwellymoving.co.nz/public-engagement/
PART B1 – Strategic Response: Scenarios for Engagement
Let’s Get Wellington Moving Programme Business Case – Draft Released 21 June 2019 42
Table 9 Engagement Scenarios benefits
PART B1 – Strategic Response: Scenarios for Engagement
Let’s Get Wellington Moving Programme Business Case – Draft Released 21 June 2019 43
Table 10 Engagement Scenarios impacts
PART B1 – Strategic Response: Scenarios for Engagement
Let’s Get Wellington Moving Programme Business Case – Draft Released 21 June 2019 44
8.3. Engagement Feedback
The key messages from the engagement were:
Broad support for the interventions in Scenario A – but most thought it did not go far enough
This suggests an initial focus should be on the following as a minimum:
o Optimising operation of existing infrastructure (“early improvements”)
o Lowering speeds in central city
o Restricting private vehicle access on the Golden Mile
o Improving walkability and cycling in central city
o Prioritising buses on the spine route through the central city
There is a need to assess options for:
o Mass transit
o Basin and Mt Victoria
o Karo Drive/Te Aro
o Pricing.
This engagement also highlighted several key themes which are summarised as follows:
Immediate refinement and long-term changes are sought for public transport
Reduction of congestion is universally supported
Widespread support for active transport infrastructure and prioritisation
Opposition to infrastructure development which increases car use
A regional, integrated approach is required
It is time to act, while being mindful of cost
Predicted changes require future-focused solutions
Basin traffic flow issues need to be solved, but diverse views are held
Wellington-specific solutions required.
The engagement feedback, and the Global Research summary of the feedback is publicly available
online8.
8.4. LGWM Response to Engagement Scenarios Feedback
LGWM developed a response to the engagement feedback to demonstrate how the insights from
engagement would be taken forward. This is summarised below in Table 11. A more complete
explanation of this summary is publicly available9.
8 https://getwellymoving.co.nz/about/public-engagement/feedback/
9 https://www.getwellymoving.co.nz/home/response-to-nov-dec-2017-public-engagement/
PART B1 – Strategic Response: Scenarios for Engagement
Let’s Get Wellington Moving Programme Business Case – Draft Released 21 June 2019 45
Table 11 LGWM response to key themes from engagement scenarios feedback
THEME WORK REQUIRED PROPOSED DIRECTION
1. Support for better public transport – now and long term
Complete “early improvements”, including those proposed in feedback (which are not already committed to in public transport programmes).
Identify public transport improvements that can proceed without major investment.
Include early improvements in earlier stages of the Recommended Programme of Investment (RPI) where they align with LGWM objectives.
Ensure early public transport interventions are compatible with wider RPI.
Investigate routes and options for mass transit to the airport, and consider:
Network planning (including interaction with bus network)
Urban development/demand
Feasibility and costing
Incorporate preferred mass transit into RPI, and identify infrastructure to support it.
Identify options for accelerated delivery.
Highlight city-building potential of mass transit.
2. Universal support for less congestion
Use feedback to help set targets for travel time and variability KPIs for RPI.
Develop KPIs for “amenity” and “system occupancy” (ratio of people to vehicles).
Consider congestion charging.
Include interventions to reduce negative impacts of congestion on the city.
Indicate potential impact of congestion charging as part of the RPI narrative.
3. Widespread support for walking and cycling improvements and priority
Develop a more comprehensive programme of walking improvements, guided by feedback where practical
Include more detailed walking improvements in earlier stages of RPI.
Include improvements beyond the CBD (e.g. Cobham Drive crossing).
Describe a connected cycling network in the city, guided by feedback where practical Include a more detailed programme of cycling improvements into the earlier stages of the recommended programme
4. Opposition to new infrastructure that encourages car use
Ensure analysis provides info on multi-modal and redevelopment benefits.
Develop a central narrative that better describes our multi-modal approach
Ensure new infrastructure supports LGWM multi-modal priorities, and is not just for cars.
Note that focus is on a nil net increase in vehicles.
5. A regional, integrated approach is required Report on wider regional issues that have helped shape RPI.
Undertake further work, either as LGWM or in parallel (by partners), to:
Improve public transport to the north and west
Develop complementary measures to improve public transport uptake around region
Reduce overall regional trip demand and spread peak demand
Ensure the RPI includes reference to the type of interventions needed beyond the LGWM area.
6. It is time to act, while being mindful of cost Complete work on the early improvements programme
Include economic analysis in assessment
Review LGWM objectives and KPIs against the new Government Policy Statement
Bring all improvements practical into the earlier stages of the RPI.
Demonstrate how the RPI contributes to the new GPS.
7. Future-proofed solutions are required Review technology improvements that are consistent with LGWM objectives and can be incorporated into recommended programme.
Report on technology issues that have helped shape RPI.
Explain how RPI will enable the network to adapt to/facilitate technology change.
Include review/decision points in RPI that allow for technology change.
8. Basin traffic flow issues need to be solved, but diverse views are held
Use the feedback to help define parameters in the RPI around the Basin improvements. Include a preferred approach to Basin issues in the RPI, and outline what needs to be addressed
in the next stage.
Describe a process to enable public input into design at Basin.
9. Wellington-specific solutions required Use the feedback on resilience, topography, and Wellington-specific issues to help develop and refine the recommended programme.
Ensure the RPI illustrates how interventions are responding to Wellington-specific issues.
PART B1 – Strategic Response: SMART Objective Development
Let’s Get Wellington Moving Programme Business Case – Draft Released 21 June 2019 46
9. SMART OBJECTIVE DEVELOPMENT Based on initial feedback from the public in 2016 (which culminated in the formulation of the 12
guiding principles), a set of benefit statements/programme objectives was developed by LGWM for
further engagement with the public in 2017.
These objectives were then developed into SMART objectives (Specific, Measurable, Attributable,
Realistic, Time bound) through the refinement of KPIs. Appendix A, Table v shows a close alignment
between the objectives and the principles, reflecting the importance given to public views about what
the programme should deliver for Wellington.
The five investment objectives with their associated KPIs are set out below with a more complete
presentation shown in Appendix C. KPIs 1-I0 are intended to be used to assess the performance of
different programme options and guide decision making. The remaining (unnumbered) KPIs are
intended to help monitor programme success.
Investment Objective 1: A transport system that enhances the liveability of the central city
KPI 1: Amenity Index - The quality of the urban environment, including greenspace, urban
design, traffic volumes/speeds and pedestrian space
KPI 2: Transport-related CO2 emissions in the central city
KPI 3: Opportunities for urban development and value uplift
KPI: Monitor traffic Noise
KPI: Monitor liveability Survey – Quality of Road Network, Quality of Public Transport
(Economist Intelligence Unit Global)
KPI: Monitor air quality – particulates, NO2
Investment Objective 2: A transport system that reduces reliance on private vehicle travel
KPI 4: Improve the system occupancy - The ratio of people travelling to the central city (by all
modes) against the number of private vehicles
KPI 5: Delays for people walking in the central city
KPI 6: The quality of cycling facilities - ‘Danish method’ cycling infrastructure level of service
KPI: Monitor mode share within CBD / VKT within the CBD
Investment Objective 3: A transport system that provides more efficient and reliable access to support growth
KPI 7: The number of people living and working within 30 mins of key destinations
KPI 8: The reliability of travel time by different modes to key regional destinations
KPI: Monitor number of people travelling to CBD
Investment Objective 4: A transport system that improves safety for all users
KPI 9: Deaths and serious injuries for people walking and cycling in and around the
central city
KPI: Monitor total casualties by severity and by mode
Investment Objective 5: A transport system that is adaptable to disruptions and future uncertainty
KPI 10: Network resilience to disruption caused by large-scale natural hazards
KPI: Monitor lane availability reductions due to unplanned events
PART B2 – Analysis of Programme Elements: Programme Development Analysis
Let’s Get Wellington Moving Programme Business Case – Draft Released 21 June 2019 47
PART B2 – ANALYSIS OF PROGRAMME ELEMENTS This part summarises some of the technical analysis undertaken and commissioned by LGWM in developing
and refining the recommended programme of investment. High level analysis was undertaken to build
confidence that interventions could address the issues identified. Sufficient options were considered in order
to move forward to more detailed investigation and a thorough optioneering process.
10. PROGRAMME DEVELOPMENT ANALYSIS Engagement, ongoing investigations, and discussion between LGWM programme partners highlighted a need
to undertake further investigation in urban development potential, pricing, future uncertainty and technology,
mass transit, State Highway 1 through Te Aro, and the transport system near the Basin Reserve. The
development of this work was iterative during the longlist and shortlist programme option development. A
summary of some of the technical documents referenced in this section can be found in Appendix N.
10.1. LGWM as an enabler for urban development
Transport improvements impact on urban development potential and property values in a number of ways:
Transport improvements result in improvements to the accessibility of locations (considering both speed
and capacity) and the amenity / quality of travel and the urban environment (i.e. nicer vehicles, urban
realm improvements). These benefits are ‘capitalised’ into land values – i.e. people are willing to pay more
to live in more accessible places or more attractive environments.
Improved accessibility may also make locations more productive by increasing their ‘economic mass’, e.g.
number of jobs, level of economic activity. Economic theory and evidence on agglomeration economies
finds that spatial concentrations of economic activity are associated with higher levels of economic
productivity resulting from enhanced ‘sharing’, ‘learning’ and ‘matching’ mechanisms. This may lead to
further benefits that are in turn (partly) capitalised into land values.
Firms and workers may respond by relocating to areas that have experienced improved productivity /
accessibility. This may in turn strengthen agglomeration forces (albeit potentially at the cost of some
increased congestion) and lead to increased land value uplift.
Work was undertaken to understand the potential impact of LGWM on land use changes (mainly population
and jobs distribution) and property values. The relevant papers are summarised below.
10.1.1. Possible Impacts of LGWM Interventions on Land Values (LGWM, June 2018) This paper examines the possible impacts of two LGWM interventions on land values in Wellington City. One
intervention is a vehicle tunnel in Te Aro which removes eastbound State Highway traffic from Vivian Street
and allows an urban park to be created on top of the tunnel. The other intervention is mass transit from
Wellington Station to the Airport. The paper considers two forms of mass transit: light rail and bus rapid
transit.
The paper finds that mass transit could increase surrounding land values by up to $1 billion. The level of
increase depends on the amenity improvements and District Plan zoning changes that are included in the
project and the nature of the mass transit system that is provided. Rezoning can result in significant value
uplift where land use is currently low density and interventions spur development to higher density levels.
Given that the CBD and Te Aro are already zoned for high density, there is little additional potential benefit to
be realised in these locations. The value uplift associated with mass transit assumes that rezoning in Newtown
through to Rongotai could achieve mixed use, higher density development alongside mass transit.
PART B2 – Analysis of Programme Elements: Programme Development Analysis
Let’s Get Wellington Moving Programme Business Case – Draft Released 21 June 2019 48
In contrast, the paper concludes that removal of State Highway traffic from Vivian Street is unlikely to
significantly increase surrounding property values. However, the opportunity to increase green space in Te Aro
through the creation of a new park above the tunnel may improve property values, but will likely have a
localised and small impact. The potential total land value benefit of a Te Aro tunnel could be up to $19 million
in 2043 (undiscounted).
This work was then externally peer reviewed in June 2018.
10.1.2. Land use change arising from the Let’s Get Welly Moving programme (MRCagney, July 2018) This report analyses the potential impact of LGWM on the future distribution of population and employment
in Greater Wellington. It draws upon recently published guidance in the UK’s Transport Analysis Guidance
(WebTAG) as well as a recent NZ Transport Agency research report on ‘dynamic WEBs’ (Volterra Partners,
2017).
The authors estimate that there may be annual economic benefits on the order of $5,000 to $10,000 per
additional city centre job that is ‘unlocked’ by the LGWM programme. These benefits are additional to
conventional transport benefits and wider economic benefits measured under a ‘static’ land use scenario.
The authors have assumed that LGWM will affect how projected future growth is distributed, but that it will
not increase the overall regional growth rate. Under their ‘composite’ scenario for land use change:
The city centre’s population is predicted to be slightly lower than in LGWM’s ‘base case’ scenario, while
employment is predicted to be slightly higher
The remainder of Wellington City would experience increases in both population and employment
Other territorial authorities would experience reductions in population and employment.
These changes are expected to have the following impacts:
Increase demand for the new rapid transit spine by increasing the residential population along the
corridor and increasing city centre employment
Increase economic productivity by moderately increasing the share of regional employment located in the
city centre and in the Newtown area
Potentially generate other land use change benefits through revitalisation in the Newtown area.
Note that the modelling does not include the effect a cordon charge would have on land uses and values.
10.2. Pricing
Managing demand, particularly at peak times, is an intervention that can improve the efficiency and operation
of the system without adding significant system capacity. This can be achieved in a number of ways. One
option that LGWM has considered at a high level is pricing. The Wellington central city lends itself to pricing to
a certain extent, due to its urban form and function, network characteristics, travel patterns, and public
transport alternatives.
Pricing could take many forms, including a parking levy, an inner cordon charge, an outer cordon charge, a
State Highway 1 toll, a GPS based charge, or some combination. LGWM testing of these pricing tools has
assumed changes to the current legislative framework, and limited consideration was given to the
practicalities of implementation and enforcement at this stage of investigation.
Pricing could deliver significant benefits, such as reduced congestion, reduced emissions and improved
amenity values. It could also defer or remove the need for significant highway infrastructure interventions and
provide revenue that could be used to invest in public transport, walking and cycling facilities. However, if not
PART B2 – Analysis of Programme Elements: Programme Development Analysis
Let’s Get Wellington Moving Programme Business Case – Draft Released 21 June 2019 49
carefully considered and planned, pricing can result in undesirable outcomes such as re-routing traffic to
sensitive areas.
10.3. Alternative Futures and Technology
10.3.1. Alternative Futures Forecasting the effects of land use and transport change is an inherently uncertain activity. As such, LGWM
has tested a number of alternative future scenarios to understand how the programme performs under a
range of conditions. These have included both medium and high population and employment growth
scenarios, redistributing the growth along core public transport spines, and scenarios with variable growth
rates between different transport modes. As the programme develops further, additional analysis will be
undertaken to ascertain how uncertainty might affect future outcomes and incorporate this work into
developing a programme that is flexible and adaptable to change.
In order to account for uncertainty in relation to future travel behaviour and preferences, two future
outcomes have been represented and used to assess the programme:
‘Trend future’ - Continuation of recent trend growth with reference to commuter trips to Wellington
CBD in morning peak - all future growth in peak hour trips to Wellington CBD assigned to active modes
or public transport
‘Balanced future’ - A more balanced future with small increases in peak period car demand but more
significant increases in PT and active mode trips to the CBD.
In order to account for uncertainty in relation to future growth and land use, two future outcomes have been
represented and used to assess the programme:
A medium growth and land use scenario developed from Profile ID population projections which are
themselves developed in collaboration with regional territorial authorities and broadly correspond to
Statistics NZ medium population projections. This scenario is ‘probable, plausible and achievable’ -
analysis undertaken by the territorial authorities shows that the capacity (of land) exists to cater for
the level of development envisaged
An alternative high growth and land use scenario that assumes higher population and employment
growth. This is distributed according to current forecast distributions, with some re-distribution of
population growth to areas that benefit from improved accessibility resulting from the LGWM
programme. No substantive work has been undertaken to understand whether the capacity (of land)
and other constraints (e.g. water infrastructure, plan changes) could accommodate the level of
development envisaged.
10.3.2. Technology As discussed in Section 3.5.1, the potential impacts of technological advances in the medium-long term can be
used as a catalyst for improving transport outcomes, for example, in the areas of safety and emissions. LGWM
has not identified any specific items that are required to facilitate these changes.
However, there are areas of technological change where LGWM as identified an opportunity to support or
facilitate in order to maximise transport outcomes as follows:
Digital Connectivity
Use of digital connectivity to avoid unnecessary journeys where economic, through continued and
increased working with employers and schools to plan travel.
PART B2 – Analysis of Programme Elements: Programme Development Analysis
Let’s Get Wellington Moving Programme Business Case – Draft Released 21 June 2019 50
Shared Mobility
Integrating all the region’s mobility service providers into an integrated payment and journey planning
platform (mobility-as-a-service) to optimise use of the vehicle fleet and improve vehicle occupancy –
signalling Wellington as wishing to be an early adopter of any mobility-as-a-service national initiatives
Further collaborations such as the NEC Smart Cities initiative
Implementing LGWM may result in infrastructure that could encourage shared mobility, including
hubs where people interchange from shared services onto mass transit or other shared modes
(allowing seamless transfers).
Autonomous Vehicles
As aspects of any preferred programme advance in detail and investigation, it is important to consider
how autonomous vehicles can integrate with the transport system; especially given that mass transit
vehicles are likely early adopters of full automation. Regulatory impacts are best addressed at the
national level.
Electric Vehicles
Further stages of LGWM will consider how any proposed electric public transport vehicles could be
charged (e.g. while in motion or at signals)
Consider on-street parking with charging facilities to raise the visibility of electric vehicles along with
shared mobility.
On-street parking
Use of parking occupancy data to responsively price (e.g. by time of day, level of demand), and
identify opportunities to reassign parking to other uses either permanently or dynamically e.g.
assigning a carshare park, providing a peak time mass transit lane, supporting cycle lanes that reduce
parking or reassigning space for non-transport uses.
Most of these tactical decisions only need to be taken at the strategic level at this stage. Actual improvements
and changes can be accommodated within the LGWM programme as it is developed, through normal
Regional/National Land Transport Plan cycles. For example, the technology for charging electric vehicles at
traffic lights could be implemented simultaneously with normally scheduled road resealing as the new
charging technology becomes available. It is important that LGWM maintains forward visibility of technological
changes and how they can contribute towards maximising transport outcomes.
Accordingly, LGWM’s approach is to proactively harness technology in a way that enables the full potential of
investments in infrastructure and services to be achieved. In particular, LGWM’s focus is harnessing
technology change in the following areas:
Prioritising the use of the network for active modes and public transport vehicle through, for example,
dynamic management of corridors for bus priority
Encouraging increased electric vehicle uptake through, for example, the provision of more charging
stations
Encouraging use of shared vehicles and public transport through, for example, the coordinated roll out
of mobility-as-a-service
Managing networks and travel demand to ensure the transport system operates reliably through, for
example, improved on-street parking management.
It is also worth noting that several technology aspects and opportunities are best delivered outside of LGWM
(e.g. nationally led autonomous vehicle testing legislation).
PART B2 – Analysis of Programme Elements: Programme Development Analysis
Let’s Get Wellington Moving Programme Business Case – Draft Released 21 June 2019 51
10.4. Mass Transit
10.4.1. Background A mass transit system was identified as a key element of the 2008 Ngauranga to Airport Corridor Strategy. The
Strategy highlighted the need for a high quality, high frequency public transport spine through central
Wellington city between Wellington railway station and the southern and eastern suburbs. The 2014
Wellington Public Transport Spine Study (PTSS) investigated this further, focusing on the feasibility of mode
and route options to deliver a core public transport spine and achieve a step change in public transport level
of service through this corridor. In 2017 bus rapid transit (BRT) investigations considered the
recommendations of the PTSS in greater detail, focusing on the feasibility of BRT along the spine further.
The PTSS was reviewed in 2017, looking at whether earlier recommendations were still valid, given changes
that had occurred since its completion, and provided commentary about how international experience of
mass transit planning and implementation could relate to Wellington. This work informed the presentation of
mass transit in the LGWM engagement scenarios, which showed mass transit along a single CBD spine (via the
Golden Mile) and branching off to the south and east at the Basin Reserve in three of the four scenarios.
10.4.2. LGWM further work following engagement Engagement feedback suggested other route options for consideration and prompted consideration of how
mass transit should fit with the wider public transport network. Detailed network planning investigations were
completed to understand options for delivering an integrated public transport network that would best
leverage the benefits of mass transit within the LGWM study area. The key findings were:
Mass transit in Wellington should have the following characteristics
o High frequency (at least 10-minutes all-day, every day)
o Fast and reliable compared to car
o High quality infrastructure
o High capacity vehicles
o High quality electric vehicles
Two primary public transport spines are required through Wellington CBD (Golden Mile and
Quays/Waterfront) to accommodate future passenger demand while ensuring reliable journey times
and avoiding forced transfers at the CBD fringe
A number of key corridor trade-offs have been identified.
A piece of work was completed to examine the possible impacts of potential LGWM interventions on land
values in Wellington City (see Section 10.1.1). This research concluded that by improving amenity and
accessibility, mass transit projects can increase property values, potentially providing a revenue stream to help
finance investments.
A shared vision of the city’s future was developed to help inform the mass transit elements and to underpin
the LGWM programme (see Section 2.9.1). The future opportunities and issues for the city were mapped. A
number of potential ‘activation areas’ including the waterfront, Te Aro and Newtown were identified; all of
which have influenced the route alignment preference for the mass transit route.
Work was commissioned to provide advice on high level engineering feasibility and issues along the mass
transit route. This work considered different route choices and an indication of their potential impacts on land
requirements, cost, feasible gradients, parking, other transport modes, and utility service assets.
A further review was commissioned to provide expert advice on the mass transit issues and assumptions
under consideration (Review of Wellington LRT Concept – Risks and Opportunities). The review provided a
PART B2 – Analysis of Programme Elements: Programme Development Analysis
Let’s Get Wellington Moving Programme Business Case – Draft Released 21 June 2019 52
summary of the high-level risks and opportunities associated with implementing LRT in Wellington, based on
international experience of planning and delivering LRT systems. To maximise the opportunities for Wellington
it was recommended that clear objectives for LRT be determined to deal with the expected compromises
(trade-offs) and that considerations of potential urban regeneration, place-making and future patronage were
all key factors in deciding an appropriate route.
The review also highlighted some significant technical challenges for implementing LRT in the Wellington
context, particularly due to topography. Beyond the CBD/central city engineering solutions are likely to be
relatively expensive and the lower patronage potential, due to more dispersed development patterns south
and east of Newtown, make it more difficult to justify the high cost of investment. The likely spatial extent of
light rail in Wellington is limited by topography and urban form. Further detailed work was recommended
before any firm conclusions could be made on whether LRT is a viable investment solution for Wellington, and
on the most appropriate route and network form it should take.
10.4.3. Identification of a preferred mass transit route and mode for evaluation The various pieces of further work outlined above were used to inform identification of a preferred mass
transit system route for evaluation as part of the recommended programme of investment. Light rail was
assumed as it represented the highest cost option that delivered the greatest opportunities for urban
development.
The LRT component followed one of the two central city spines from Wellington railway station to Wellington
airport. The route and technology choices – LRT along the waterfront, Taranaki Street, Adelaide Road, Mt
Albert tunnel, Rongotai Road, Cobham Drive - were included in this option for the purpose of evaluation. The
other central city spine along the Golden Mile would be upgraded to service the many bus routes that would
form the rest of the public transport system for Wellington.
Consideration of the LRT corridor on the second central city spine as a preferred route included:
Maximising urban development potential
Creating an attractive public transport service with good patronage
Resilience to seismic events
Fit with the existing network and minimising conflict with other traffic movements
Avoiding challenging corners, geometry and other engineering constraints
Parking impact
Impact on retail activity
Access to key land uses such as schools
Cost and ability to deliver
Property impacts
PART B2 – Analysis of Programme Elements: Programme Development Analysis
Let’s Get Wellington Moving Programme Business Case – Draft Released 21 June 2019 53
Figure 18 Preferred route for mass transit between Wellington Railway Station and Wellington International Airport
Necessarily there is a level of uncertainty of the preferred LRT route at this PBC stage. Several key route
options and alternatives will be investigated in detail and confirmed at the next stage of the business case.
This further work will also consider options for stabling, technology choice, and stations.
10.5. State Highway 1 corridor through Te Aro
Preliminary investigations and community engagement highlighted the Vivian Street and Karo Drive corridors
as areas of conflict between State Highway 1 east-west movements and local north-south movements. There
was also the perception that the State Highway corridors have severance impacts on the adjoining urban areas
i.e. they act as barriers that deter movements across the corridor. This derives from the delay to north-south
movements, particularly pedestrians waiting to cross the State Highway, and from the low amenity of the
PART B2 – Analysis of Programme Elements: Programme Development Analysis
Let’s Get Wellington Moving Programme Business Case – Draft Released 21 June 2019 54
corridors. Lastly, some respondents expressed the desire to remove through-traffic from Vivian Street as a
way to reduce overall traffic on this street and in the central city.
Further investigations were undertaken to test whether a relocation of State Highway 1 traffic from Vivian
Street to Karo Drive and possible undergrounding of a two-way State Highway along Karo Drive would help
address these issues. The alternatives investigated include the following:
A contraflow system using existing tunnels
A series of short tunnels
A longer, continuous tunnel
Contraflow using existing tunnels
This alternative would involve introducing a contraflow system on the existing State Highway corridor along
the Terrace Tunnel trench, Karo Drive (at-grade) and Arras Tunnel. This would re-allocate one existing
westbound traffic lane to eastbound through-traffic that does not have a destination within Te Aro. The logic
behind this approach is that 25% to 30% of traffic on Vivian Street has a destination to the east and could
bypass Te Aro, and be accommodated by a single eastbound lane along Karo Drive. Other traffic movements
would continue to use Vivian Street similar to the current operation.
The investigations revealed significant constraints at the existing trench just south of the Terrace Tunnel which
is not wide enough to accommodate one eastbound lane and two westbound lanes, and elsewhere along the
Karo Drive alignment. Reducing the number of westbound lanes to create an eastbound lane would also be
likely to cause queuing along Karo Drive westbound and increase congestion and environmental impacts in
this area.
Making Karo Drive two-way would also require additional traffic signal phases and introduce new intersection
conflicts. This would decrease the level of service of the route in the westbound direction, as well as decrease
the level of service for walking, cycling, bus and general traffic movements in the north-south directions.
Series of short tunnels
This alternative would involve undergrounding State Highway 1 (eastbound and westbound) between the
Terrace Tunnel and Basin Reserve along the Karo Drive alignment and beside the existing Arras Tunnel). ‘Lids’
(covered tunnel sections) would be constructed over selected parts of the alignment to maintain the local
north-south streets at grade (Abel Smith, Willis, Victoria, Cuba and Taranaki streets), to create green spaces
and to improve pedestrian connectivity. Open trenches would be located in between the covered tunnel
sections. The open trenches would help to minimise the cost of the undergrounding and reduce the need for
ventilation stacks and other infrastructure required in longer tunnels, but would not create a consistent
covered area.
Longer, continuous tunnel
This alternative would be a variation on the above, involving longer lids and fewer open trenches to create a
continuous cut-and-cover tunnel from Willis St to the Basin Reserve. The space on the tunnel lid between
Willis Street and the Basin Reserve would be used to maintain the north-south streets at grade and to create a
series of open spaces in between the local streets. Ventilation stacks and control buildings would likely be
required to service this longer tunnel.
PART B2 – Analysis of Programme Elements: Programme Development Analysis
Let’s Get Wellington Moving Programme Business Case – Draft Released 21 June 2019 55
Preliminary investigations of the tunnel alternatives indicated that they would not result in the majority of
traffic being removed from Vivian Street without other complementary interventions. This is because the
majority (70% to 75%) of traffic on Vivian St is bound for local destinations, rather than passing through to
reach destinations elsewhere, and therefore is unlikely to use the eastbound Karo Drive route. However,
separating local movements from through-traffic has the potential to improve the performance of the
transport network and urban form in this part of Wellington.
The investigations also indicated that a large infrastructure-based intervention has the potential to achieve
programme outcomes, enhance amenity in Te Aro and create opportunities to divert traffic from the central
city and from along the waterfront. However, it is likely to incur high costs, reflecting the complexity of tunnel
systems and underground utilities and services. More work would be required to quantify the benefits of
these alternatives and consider detailed interdependencies with other programme elements.
10.6. Basin Reserve Area
The Basin Reserve is another area of conflict between State Highway 1 east-west movements and local north-
south movements.
The LGWM preferred approach for the Basin would respond to a number of design principles including:
Achieves transport outcomes and addresses conflicting transport movements for all modes
Is sympathetic to the local geography, character and existing street network
Enhances amenity values and the use of the Basin.
LGWM has ruled out the previous Basin Bridge proposal which was rejected by the Board of Inquiry in 2014.
Initial analysis suggests that there are other less intrusive options to separate conflicting transport movements
and improve flows at the Basin. Some of these alternatives were considered at a high level from an urban
design, transport and engineering perspective to understand key risks and feasibility. The alternatives
investigated are set out below.
At-grade improvements
This alternative would involve a series of at-grade changes including localised widening, the removal or
relocation of a limited number of on-street parking bays, the creation of additional traffic lanes, restricting the
Ellice Street exit, and giving priority for public transport at traffic signals. The changes would be designed to
have minimal land take or other impacts.
Undergrounding of State Highway 1 north of the Basin Reserve
This alternative would involve undergrounding of State Highway 1 (two-way) in a cut-and-cover tunnel
between Paterson St and Arras Tunnel, north of the Basin Reserve. North-south local movements would
continue to operate at-grade.
A cut-and-cover tunnel along the north side of the Basin Reserve would create risks around the re-routing and
pumping of the underground Waitangi Stream which runs below the Basin area, from Adelaide Road to the
Canal Reserve (the green strip between Cambridge and Kent terraces). A continuous tunnel from Patterson St
to Arras Tunnel would effectively act as a ‘dam’ against the stream flow path. This option was therefore not
considered feasible.
PART B2 – Analysis of Programme Elements: Programme Development Analysis
Let’s Get Wellington Moving Programme Business Case – Draft Released 21 June 2019 56
Undergrounding of State Highway 1 south and west of Basin Reserve
This alternative would involve undergrounding of State Highway 1 (two-way) in a cut-and-cover tunnel
between Paterson St and Arras Tunnel, under Dufferin, Rugby and Sussex streets to the south and west of the
Basin Reserve. It makes use of the elevated grounds on the western side of the Basin, which are around seven
metres higher than either Cambridge Tce or Adelaide Rd and can therefore accommodate a tunnel above the
level of a relocated Waitangi Stream. This option does however require the regrading of Paterson Street from
the entrance of the Mt Victoria Tunnel to bring the State Highway below Dufferin St. North-south local
movements would continue to operate at-grade, over the State Highway.
This alternative was not considered feasible due to the excessive steepening of Paterson Street that would be
required to connect the undergrounded State Highway to Mt Victoria Tunnel.
Extension of Sussex Street over State Highway 1
Grade-separation of State Highway 1 traffic below local traffic near the Arras Tunnel. This involves:
Extension of Sussex Street for two-way local traffic (including any public transport) to cross over a
lowered State Highway by the north-west corner of the Basin Reserve
The relocation of westbound State Highway 1 traffic to the north of the Basin Reserve
The relocation of eastbound State Highway 1 traffic from Vivian Street and Kent Terrace to the Buckle
Street alignment and the north of the Basin Reserve (assumes State Highway 1 is undergrounded in
both directions through Te Aro).
Pedestrian and cycle movements could either follow the local traffic, over State Highway 1 and along the
western side of the Basin Reserve, or cross under State Highway 1, directly connecting the Basin Reserve with
Kent and Cambridge Terraces.
The relocation of local southbound movements and westbound state highway movements creates
opportunities to traffic-calm the area around the entrances of St Mark’s Church School, Wellington College
and Government House. Access to the schools would continue to be provided on Dufferin St with an access
lane and bus turning loop.
This alternative (Figure 19) was adopted by LGWM for evaluation as part of the recommended programme of
investment. Necessarily there is a level of uncertainty of the final layout at this PBC stage. Alternative options
will be investigated in detail at the next stage of the business case. This further work will also consider
integration with the wider LGWM programme, the ability to accelerate some improvements for early delivery,
and a formal decision-making process.
Engagement with the community will be needed to explore and develop a design that achieves transport
outcomes, is sympathetic to the local geography, enhances the use of the Basin, and improves amenity around
the reserve.
PART B2 – Analysis of Programme Elements: Programme Development Analysis
Let’s Get Wellington Moving Programme Business Case – Draft Released 21 June 2019 57
Figure 19 Indicative layout for the transport system near the Basin Reserve (Artist’s impression of indicative concept below)
PART B2 – Analysis of Programme Elements: Further Analysis
Let’s Get Wellington Moving Programme Business Case – Draft Released 21 June 2019 58
11. FURTHER ANALYSIS While engaging with the Ministry of Transport, further analysis was carried out into how the State Highway 1
corridor could contribute to achieving LGWM objectives within an affordable funding envelope. This work built
on the investigations summarised in Section 10.5. A summary of some of the technical documents referenced
in this section can be found in Appendix N.
The State Highway corridor was considered in three sections (Ngauranga to Aotea Quay, Terrace Tunnel to
Basin Reserve, and Mt Victoria Tunnel to Airport). Options were considered for each section and assessed at a
high level, with logical combinations considered as connected routes within the context of the wider
programme. This initial assessment did not develop firm recommendations; the intent was to indicate
whether a reduced level of investment could still be effective in achieving programme outcomes. The
investigation assumed that other programme elements were unchanged, including mass transit, Basin grade-
separation, road pricing, walking, cycling and public transport improvements.
11.1. State Highway 1 Corridor Ngauranga to Aotea Quay
Consideration of the State Highway 1 section between Ngauranga and Aotea Quay focused on the potential
Multi-User Ferry Terminal that is being investigated outside of LGWM. In summary, none of the potential
access arrangements under consideration by the Multi-User Ferry Terminal were found to be incompatible
with the LGWM programme. Widening of State Highway 1 southbound between Ngauranga and Aotea Quay
was considered unlikely to be required as part of the LGWM programme without an identified need as part of
Multi-User Ferry Terminal planning.
11.2. State Highway 1 corridor through Te Aro
As part of the RPI development several options for this section of State Highway 1 were considered including
contraflow using the existing tunnels, a series of short tunnels, and a longer continuous tunnel with varying
lengths of covered and open trenches. Further investigation considered the presence/absence of a duplicate
Terrace Tunnel, different forms of contraflow operation, relatively lower cost optimisation and enhancement
changes, reduced extent of undergrounding to a single intersection, and different methodologies for
tunnelling.
High level consideration of different tunnelling methodologies highlighted that a different tunnelling approach
such as machine excavation (rather than cut and cover or a tunnel boring machine) could be delivered at a
reduced cost, with lesser disruption, and over a similar timeframe, if found to be feasible.
This analysis highlighted the importance of robust optioneering during detailed investigation phases.
11.3. State Highway 1 corridor through Mt Victoria
The RPI assumed widening and duplication in line with previous NZ Transport Agency proposals. Different
options considered different ways of utilising additional capacity from an extra tunnel, using the Hataitai bus
tunnel, creation of an additional walking and cycling tunnel, and different tunnelling methodologies such as
widening the existing tunnel rather than excavating a new tunnel.
Widening excavation techniques had several identified potential issues including constructability challenges,
reduced resilience outcomes, and lower fire and life safety performance. However, it was identified to
potentially represent a lower cost investment.
Again, this analysis highlighted the importance of robust optioneering during detailed investigation phases.
PART B3 – Programme Development: Longlist Programme Options
Let’s Get Wellington Moving Programme Business Case – Draft Released 21 June 2019 59
PART B3 – PROGRAMME DEVELOPMENT This part summarises the process that was followed to iteratively develop and assess programme options
through a longlist and shortlist assessment process to arrive at a recommended programme of
investment.
12. LONGLIST PROGRAMME OPTIONS 12.1. Longlist Programme Development
The longlist of programme options was developed within the context of the strategic response, and
having regard to feedback from the engagement scenarios.
Six packages of interventions (‘elements’) were developed that could potentially be implemented in a
standalone manner and progressively combined to address aspects of the strategic approach. These
elements were then used to build up longlist of programme options for testing. The six programme
packages are set out below.
Priority for public transport and active modes in the central city Improving priority for buses on key routes to improve journey times and reliability
Improving walkability and creating more people-focused spaces in the central city
Creating a network of safe cycleways throughout the central city
Optimising operation of existing infrastructure through ‘Early Improvements’ (including lowering
speeds in the central city).
This package reflected the strong support in the engagement scenarios feedback for the types of
interventions illustrated in Scenario A, but with higher investment in public transport (excluding large
scale infrastructure investment), walking, and cycling.
Distributed bus priority / bus lanes A distributed mass transit service on three core routes in Wellington City
Design of the wider public transport network to complement mass transit
Some infrastructure changes that may be required to support mass transit or manage trade-offs
with other parts of the transport network.
Mass Transit focused on a single spine A high priority mass transit service on a single spine through Wellington City
Design of the wider public transport network to complement mass transit
Significant infrastructure changes that may be required to support mass transit or manage trade-
offs with other parts of the transport network. This could include:
o Grade separation near the Basin Reserve or on the Taranaki Street corridor
o New tunnels including potentially a duplicated Mt Victoria Tunnel or a new tunnel
through Mt Cook and/or Mt Albert
The package could enable active mode connections as part of any new tunnels.
Infrastructure to reduce conflict and increase amenity in Te Aro Relocation of the State Highway 1 corridor through Te Aro, potentially into an underground
structure, enabling pedestrian and amenity improvements throughout Te Aro.
PART B3 – Programme Development: Longlist Programme Options
Let’s Get Wellington Moving Programme Business Case – Draft Released 21 June 2019 60
Wider network capacity
Depending on the net impacts of other improvements, pricing, and the realisation of any number
of future uncertainties, one approach may be to increase the capacity of the wider road
network.
This could include:
o Reducing congestion at the Basin
o Duplicating the Mt Victoria Tunnel and widening Ruahine Street
o Duplicating the Terrace Tunnel
o Increasing capacity of the Inner City Bypass
Enabling walking and cycling improvements along the waterfront quays, Vivian Street, and in the
Lambton and Thorndon areas.
Pricing to manage demand Each programme option would be assessed with or without congestion pricing that would be
aimed at managing demand to optimise network performance, such as changes to parking
charges and a cordon charge.
Programme elements common to all longlist options A number of other areas for improvement have been identified which would feature to some
degree in any preferred programme. These include:
Improved access to the port, once a port programme has been defined
Improved accessibility to/from north of the LGWM area
Improved network operations
Improved resilience of the transport network
Increased focus on use of travel demand management measures to encourage more effective
use of the transport network
Accounting for future uncertainty Technological change is expected to occur, but the form and timeframe is unknown and largely
unpredictable. Any programme will need to adapt to these changes in the medium to long term. In the
short term, technological change is not considered a differentiator for selecting a preferred programme.
PART B3 – Programme Development: Longlist Programme Options
Let’s Get Wellington Moving Programme Business Case – Draft Released 21 June 2019 61
12.2. Longlist Programme Options
A longlist of 13 programme options was developed using the intervention elements outlined in Section
12.1, as shown in Table 12 below.
Table 12 Longlist Programme Options
Programme Element Longlist Programme Options
1 2 3 4 5 6 7 8 9 10 11 12 13
Priority for PT and active modes
in the central city X X X X X X X X X X X X X
Distributed bus priority / bus
lanes X X
Mass Transit focused on a single
spine X X X X X X X X
Infrastructure to reduce conflict
and increase amenity in Te Aro X X X X X X
Wider network capacity X X X X* X*
Pricing to manage demand X X X X X X
*Mt Victoria Tunnel Duplication, Improvements near the Basin Reserve, and Ruahine St Widening only
The longlist of programmes was refined over time. The versions shown above were as assessed during
the longlist workshop (see below).
12.3. Longlist Programme Assessment
A workshop was held with attendees from the LGWM team, chaired by an independent facilitator. This
workshop confirmed the longlist of programme options subject to adding additional options, and
qualitatively assessed the longlist options against the SMART Objective KPIs. This assessment used a
qualitative 7-point scale as outlined below:
7-Point Scale
+3 Major Benefit
+2 Moderate Benefit
+1 Minor Benefit
0 Neutral
-1 Minor Disbenefit
-2 Moderate Disbenefit
-3 Major Disbenefit
PART B3 – Programme Development: Longlist Programme Options
Let’s Get Wellington Moving Programme Business Case – Draft Released 21 June 2019 62
Workshop attendees broke into specialised groups, each with assigned KPIs, to assess the programme
options using the preliminary scoring as a starting point, and report back on key considerations and
differentiators. Results of this assessment process are shown in Table 13. Workshop participants were
also invited to comment on any other significant aspects that might impact decision making at a high
level, including Key Risks, Urgency, Interdependencies, and Economic and Social impacts. Documentation
of this assessment process is shown in Appendix H.
Investment Objective KPI
Longlist Programme Options
Do-Min
1 2 3 4 5 6 7 8 9 10 11 12 13
Amenity Index 0 0.5 1 0.5 1 1.5 2 2.5 3 2.5 2.5 0 1.5 2
CO2 and particulate emissions
0 0 1 1 2 1.5 2.5 1.5 2.5 1 2 -1 1 2
Ratio people: vehicles entering CBD
0 1 1.5 2 3 2 3 2 3 1.5 2.5 -2 1.5 2.5
Number of pedestrians and cyclists
0 2 3 2 3 2 3 2 3 2 3 1 2 3
Pedestrian and public transport travel times
0 1.5 2 2 2.5 2 2.5 2.5 3 2.5 3 1 2.5 3
Cycling infrastructure level of service
0 2 2 2 2 3 3 3 3 3 3 2 3 3
Network catchment walking & public transport
0 1 2 2 3 2.5 3 2.5 3 3 3 0 2.5 3
Travel time reliability all modes
0 0.5 2 1 3 2 3 2.5 3 2.5 3 1.5 2.5 3
Improved safety all modes 0 1 1.5 1.5 2 1.5 2 2.5 3 3 3 1 2 2.5
Improved resilience 0 0 0 0 0 1 1 1 2.5 2 2 2 1 1
Urban Development Potential
0 0.5 1 0.5 1 1.5 2 2 2.5 2 2.5 1 2 2.5
Table 13 Longlist Programme Option Assessment
PART B3 – Programme Development: Shortlist Programme Options
Let’s Get Wellington Moving Programme Business Case – Draft Released 21 June 2019 63
13. SHORTLIST PROGRAMME OPTIONS 13.1. Shortlist Programme Development and Options
As a result of the assessment described in Section 12.3, a short list of programme options was
developed. The workshop participants modified some of the longlist programmes in order to optimise
their performance, based on the learnings from the assessment process. This resulted in the shortlist
programmes as set out below. A more detailed presentation of the shortlist options is shown in
Appendix I.
Candidates for shortlist and their variants are shown in Table 14, and can be summarised as:
Programme 3 includes a dispersed investment in bus based public transport across the
network
Programme 5 includes a focused investment in a high-quality mass transit route supported by
a bus network with lesser priority
Programme 12 includes a step-change in public transport similar to either programme 3 or 5,
improved accessibility to the east and south, and reduced severance and conflict in Te Aro
Programme 9 includes a step-change in public transport similar to either programme 3 or 5,
improved accessibility to the north, east and south, and reduced severance and conflict in Te
Aro.
Table 14 Shortlist Programme Options
Interventions Shortlist Programmes
3 5 12 9
Two dedicated public transport spine routes10 through the CBD
- Golden Mile and Waterfront - with high levels of priority and
segregation
BRT11 on both CBD public transport spines and on key public
transport routes to the north, east, south and west, to support
high quality, high frequency, high capacity bus services
* * High level of public transport priority and service along one of
the public transport spines from Wellington Station to the
Airport via Newtown / Kilbirnie with a lesser level of priority on
a supporting BRT network using the secondary public transport
spine in the CBD
Improvements to pedestrian access and amenity to and
through the central city, and easy access to public transport
services
10
Section 10.4.2 summarises the analysis that suggested two public transport spines 11
At this stage of programme development the term ‘BRT’ was used to refer to bus services with a high level of priority.
PART B3 – Programme Development: Shortlist Programme Options
Let’s Get Wellington Moving Programme Business Case – Draft Released 21 June 2019 64
Creating safe cycleways throughout the central city connecting
to the wider cycle network towards the north, south, east and
west
Walking/cycling tunnel parallel to the Mt Victoria Tunnel
Duplication of Mt Victoria Tunnel for motorised vehicles,
people walking and people on bikes
Grade separation of the Basin Reserve **
Moving the State Highway 1 eastbound alignment from Vivian
Street to a cut-and-cover two-way tunnel along Karo Drive with
a single eastbound lane
Moving the State Highway 1 eastbound alignment from Vivian
Street to a cut-and-cover two-way tunnel along Karo Drive with
two eastbound lanes
Amenity and cycling improvements on Vivian Street
Duplication of the Terrace Tunnel, reconfiguration of State
Highway 1 on and off-ramps, and an additional southbound
lane on State Highway 1 between Ngauranga and Aotea Quay
Consider road pricing mechanism(s) to manage private vehicle
demand and promote alternative modes
Early Improvements – Suite of geographically packaged
improvements that can be implemented in the short term
*Programmes 12 and 9 included a step change in public transport (Similar to programme 3 or 5) **If mass transit route uses Kent/Cambridge Terraces instead of Taranaki Street
All short list programmes also included:
Improving priority for buses on key routes, improving walkability and creating more people-
focused spaces in the central city, and creating a network of safe cycleways throughout the
central city
Early Improvements - optimising operation of existing infrastructure, including lowering
speeds in the central city
Improving access to the port, once a port programme has been defined
Improving accessibility to/from the northern suburbs and the wider region in the northern
part of the LGWM programme area
Improving network operations
Improving resilience of the transport network
More use of travel demand management measures to encourage more effective use of the
transport network.
PART B3 – Programme Development: Shortlist Programme Options
Let’s Get Wellington Moving Programme Business Case – Draft Released 21 June 2019 65
The following figure shows how the short list programmes might look if implemented.
Figure 20 Shortlist programme option maps
Programme 12 Programme 9
Programme 5
Suite of 17 early improvements packages including speed limit reviews
Legend
Walking
Cycling
Public Transport
Road
Clearways on Vivian Street, optimise Karo/Vivian corridors
At-grade improvements to Basin Reserve
Create Distributed Bus Mass Transit Network
Programme 3
PART B3 – Programme Development: Shortlist Programme Options
Let’s Get Wellington Moving Programme Business Case – Draft Released 21 June 2019 66
13.2. Shortlist Programme Assessment
The shortlist options were qualitatively assessed against the SMART Objective KPIs at a workshop with
attendees from the LGWM team. This assessment used a qualitative 7 point scale as below:
7-Point Scale
+3 Major Benefit
+2 Moderate Benefit
+1 Minor Benefit
0 Neutral
-1 Minor Disbenefit
-2 Moderate Disbenefit
-3 Major Disbenefit
Workshop attendees broke into specialised groups each with assigned KPIs to assess programme
options using the preliminary scoring as a starting point, and report back on key considerations and
differentiators. The results of this assessment process are shown in Table 15 (note that the KPIs used
at this workshop refined versions of those used at the longlist assessment stage). Workshop
participants were also invited to comment on any other significant aspects that might impact decision
making, including Key Risks, Urgency, Interdependencies, and Economic and Social impacts.
Documentation of this assessment process is shown in Appendix I.
Table 15 Shortlist Programme Assessment against KPIs
Table 15 also shows an indicative capital cost range for the programmes in 2018 dollars. It should be
noted that these cost estimates are indicative only and reflect the uncertainty around how each
intervention might look when actually implemented.
PART B3 – Programme Development: Recommended Programme
Let’s Get Wellington Moving Programme Business Case – Draft Released 21 June 2019 67
14. RECOMMENDED PROGRAMME Following the assessment of the short list, Programme 5 was assessed by workshop attendees to be superior
to the other options because it performed well against both the KPIs and strategic objectives at a lesser cost
than Programme 9 and 12. Subsequent to this assessment LGWM decided that Programme 9 should be
chosen as the recommended programme as it performed better than Programme 5 against the amenity index,
network catchment, travel time variability, resilience and potential for urban development KPIs.
Following this decision, a Recommended Programme of Investment (RPI) was developed as a variant of
Programme 9. The key components of the RPI are summarised in Section 14.2 and described in more detail in
Section 14.3.
The RPI is an integrated, whole-of-system programme that includes a comprehensive range of investments
across the full range of transport modes. Given the scale of the RPI, it is expected to take at least 15 years to
fully implement, depending on funding availability.
14.1. Recommended Programme Development
Table 16 shows how the RPI was developed from the components of the shortlist programmes, as a variant of
programme 9.
Table 16 Recommended Programme of Investment (RPI) description
Interventions RPI
Shortlist Programmes (repeated for comparison)
3 5 12 9
Two dedicated public transport spine routes through the CBD - Golden Mile and Waterfront - with high levels of priority and segregation
Dispersed bus priority
Mass transit supported by dispersed bus priority
Improvements to pedestrian access and amenity to and through the central city, and easy access to public transport services
Creating safe cycleways throughout the central city connecting to the wider cycle network towards the north, south, east and west
Walking/cycling tunnel parallel to the Mt Victoria Tunnel
Duplication of Mt Victoria Tunnel for motorised vehicles, people walking and people on bikes
Grade separation of the Basin Reserve
Moving the State Highway 1 eastbound alignment from Vivian Street to a cut-and-cover two-way tunnel along Karo Drive with a single eastbound lane
PART B3 – Programme Development: Recommended Programme
Let’s Get Wellington Moving Programme Business Case – Draft Released 21 June 2019 68
Moving the State Highway 1 eastbound alignment from Vivian Street to a cut-and-cover two-way tunnel along Karo Drive with two eastbound lanes
Amenity improvements on Vivian Street
Duplication of the Terrace Tunnel, reconfiguration of State Highway 1 on and off-ramps, and an additional southbound lane on State Highway 1 between Ngauranga and Aotea Quay
Road pricing mechanism(s) to manage private vehicle demand and promote alternative modes
Carefully planned transport system transformation
Urban development
14.2. Recommended Programme of Investment Summary
High-quality walking and cycling so our streets are safer and better places for people
A walkable city - Better walking priority and facilities
Connected cycleways - Creating a connected and safe cycling network
Better public transport with high-capacity mass transit so people have more travel choices, and buses and
trains are more reliable and attractive
Public transport to the north - Better connections to the north
Public transport to/through the city - High priority access to and through Wellington including a dual
spine
Mass Transit from Station to Airport supporting urban regeneration and a step change in service
quality
Urban development land use changes integrated with transport, so people have better travel options where
they live and work
Urban development - Create accessible neighbourhoods
Smarter transport network with road pricing so people and goods make better use of our transport system
without more cars
Smarter transport system - Technology, integrated operations, and demand management (excluding
pricing)
Smarter pricing - Changing travel behaviour by charging more to drive into the city at peak times
Multimodal State Highway improvements to relocate cars out of the central city and enable better public
transport, walking and cycling, and so people can get to key destinations, such as the hospital and airport,
more reliably
Improving the Basin - Reducing conflict between movements and modes
Better access to the East - Extra Mt Victoria tunnel and Ruahine Street widening
Reclaiming Te Aro - Shifting State Highway 1 off Vivian St into a tunnel unlocking development
potential
More reliable access from the North - Ngauranga to Aotea Quay widening and Second Terrace Tunnel
PART B3 – Programme Development: Recommended Programme
Let’s Get Wellington Moving Programme Business Case – Draft Released 21 June 2019 69
14.3. Recommended Programme Detail
The following sections set out the components of the RPI in more detail.
14.3.1. A Walkable City Pedestrian accessibility improvements – including widened footpaths, improved crossings and priority,
shelter, signage and lighting across the central city
Setting safer speeds for vehicles in the central city and on State Highway 1 east of Mount Victoria
Safe crossing of State Highway 1 on Cobham Drive
Larger scale pedestrian improvements, to support a high quality public realm on key pedestrian routes
within the central city.
Rationale Walking is the most efficient mode of travel for short distances, contributing to the economic vitality of central
city streets and delivering environmental and health benefits. Continued population growth in Te Aro and
other areas within walking distance of the Wellington CBD needs to be supported by better pedestrian
facilities and priority.
Walking is also the end-of-journey mode for most people travelling by public transport and private vehicle
from the wider region to the CBD for work, shopping and leisure. LGWM seeks to ensure the central city
continues to be safe and attractive for people through the provision of better public spaces.
RPI proposals The RPI includes a range of measures to improve walkability and create more people-focused spaces in the
central city:
Early improvements to pedestrian safety, amenity and accessibility in the central city
These include works such a widening footpaths in areas of high demand and poor provision; adding
crossing facilities where they are missing; reducing the waiting times and/or increasing the ‘green’ time for
pedestrians at key crossings; installing pedestrian countdown displays at selected signalised intersections;
providing shelters where building verandas are missing; improving signage, especially to key tourist
destinations; and improving lighting along off-street walkways to improve personal safety.
Safer speeds
As part of the early improvements, the RPI includes a review of the speed limits on central city streets and
on the State Highway east of Mount Victoria tunnel. Lower traffic speeds help to reduce the risk of injuries
to pedestrians and makes this mode of transport more attractive to a wide range of people.
In conjunction with the review of speed limits on the State Highway east of Mount Victoria, the RPI
includes a formal crossing facility for pedestrians and cyclists across Cobham Drive. This is expected to help
address the safety concerns in this part of the network and improve accessibility to the ASB Sports Centre
and community facilities in Kilbirnie.
Public space improvements
Changes to the street network, such as the introduction of dedicated lanes for public transport and the
introduction of mass transit, open up opportunities to re-think the design of key streets and public spaces.
The RPI includes improvements to the pedestrian environment (e.g. paving, seating and planting) as part of
these wider works.
Other parts of the pedestrian network can be improved independently of improvements to the wider
transport network. Examples of such works include improvements to Dixon Street to support regeneration
PART B3 – Programme Development: Recommended Programme
Let’s Get Wellington Moving Programme Business Case – Draft Released 21 June 2019 70
in this area. Other areas which could be refreshed to improve pedestrian amenity include Cuba Street,
Stout Street, Allen and Blair Streets, Mercer Street and The Terrace.
These works would help improve the amenity of areas with high levels of pedestrian movements and
street-level businesses.
14.3.2. Connected Cycleways Implement cycleways as part of corridor improvements on Featherston Street, Thorndon Quay,
Courtenay Place/Dixon Street, Taranaki Street, Willis Street, Victoria Street
Setting safer speeds for vehicles in the central city and on State Highway 1
Implement cycleways as part of public transport focused corridor improvements on Kent and
Cambridge Terraces, and Adelaide Road.
Rationale Cycling has become more popular as a mode of transport in the Wellington region. This has been helped by
the advent of electric bikes which ease the challenges of Wellington’s hilly topography. There are however
many people who would like to cycle but do not feel safe cycling on the current road network. To give
everyone the option to cycle if they wish to, a network of safe and connected cycle routes is needed.
Cycling has the potential to replace a number of vehicle journeys, thus helping to relieve congestion. It also
delivers environmental and health benefits.
RPI proposals
The RPI includes a range of measures to improve provisions for cycling, with a focus in the central city:
Safer speeds
As part of the early improvements, the RPI includes review of the speed limits on central city streets and on
the State Highway east of Mount Victoria tunnel. Lower traffic speeds help to reduce the risk of injuries to
cyclists and makes this mode of transport more attractive to a wide range of people.
Early improvements creating a network of safe cycleways
The RPI includes cycleways on a number of central city streets such as Thorndon Quay, Taranaki,
Featherston, Victoria, Willis and Dixon Streets, Kent and Cambridge Terraces, and Courtenay Place. The
design of these facilities will be developed with the affected communities in the next phase of the
programme.
Connection to the east
A high quality cycleway, between the Basin Reserve and Evans Bay Parade, including a new Mount Victoria
tunnel. This will provide the eastern suburbs with a more pleasant, attractive and safe way of reaching the
CBD while reducing conflicts with pedestrians.
Connection to the south
In conjunction with the investment in high quality public transport along Adelaide Road, LGWM anticipates
provision of a high quality cycling facility between John Street and the Basin Reserve. This will support the
growth of safer cycle travel between the southern suburbs and the central city.
Vivian Street improvements
Changes to the central city bypass route could create opportunities to re-think the design and role of Vivian
Street. If so, creating a new east-west cycling connection across Te Aro as part of these wider changes will
be an option.
PART B3 – Programme Development: Recommended Programme
Let’s Get Wellington Moving Programme Business Case – Draft Released 21 June 2019 71
14.3.3. Better Public Transport Connections to the North Increased bus priority on Hutt Road and Thorndon Quay
Increased rail network capacity and service frequencies (to be progressed outside LGWM)
Higher frequencies and service levels for bus routes to northern suburbs
Integrated ticketing (to be progressed outside LGWM).
Rationale Current and projected growth in demand for travel to the central city is greatest from the north. The public
transport network (rail lines and bus routes) that serve these existing and new journeys to and from the north
will require increases in capacity to improve service quality and reliability. Without investment in these
networks, public transport could become less attractive, reducing the number of viable travel choices for
people to access central Wellington and its regional destinations. This has the potential to impact Wellington’s
economic performance and competitiveness, as well as affecting the ability to support social opportunities.
The transport networks towards the north of the central city are at capacity during peak times for both road
and rail-based modes. This means that even small disruption events have wide reaching effects across multiple
modes with regional consequences. Increased public transport capacity to the north can therefore significantly
improve the resilience of Wellington’s transport network.
RPI proposals The RPI includes a range of measures to improve public transport capacity and priority to the north of the
central city:
Early improvements to bus priority
As part of early improvements, trialling bus priority enhancements on Thorndon Quay and Hutt Road have
the potential to reduce delays from conflicts with general traffic on this corridor. This will need to be
designed to integrate with the trial of cycling facilities and improved pedestrian crossing opportunities.
Bus priorities on Thorndon Quay, Hutt Road, and other main routes to northern suburbs
Following the early improvements trial, a more permanent configuration for Hutt Road and Thorndon Quay
and service improvements will respond to changes in transport system demands that will result from other
programme elements.
Increased rail network capacity and service frequencies (progressed outside LGWM)
Work to provide increased capacity and service frequencies on the Hutt Valley/Wairarapa, Kapiti Coast, and
Johnsonville rail lines that connect Wellington City to the wider region is currently being progressed by
Greater Wellington Regional Council. These infrastructure changes include double tracking, turn back
facilities, additional crossovers and connections at Wellington Station, overhead power supply upgrades,
freight loops and signalling changes. Together with changes to services and timetabling, this will help to
create a more reliable ‘turn up and go’ public transport service across the busiest parts of the network.
Integrated ticketing (progressed outside LGWM)
Greater Wellington Regional Council and the Transport Agency are involved in a national rollout of an
advanced integrated ticketing system across all public transport networks. This has the potential to make
the overall network more attractive and seamless, by speeding up boarding and making transfers between
different public transport modes and services easier.
14.3.4. Better Public Transport Priority To and Through the Central City Bus priority enhancements on Kent/Cambridge Terraces, Adelaide Road, Taranaki Street, Kilbirnie
Crescent, Bowen Street, Hamilton Road, Victoria Street, Willis Street, and along the Golden Mile
PART B3 – Programme Development: Recommended Programme
Let’s Get Wellington Moving Programme Business Case – Draft Released 21 June 2019 72
Trial removal of general traffic from sections of Willis Street, Lambton Quay and Courtenay Place
Providing high quality and high frequency bus services along higher priority core public transport
corridors into and out of the city.
Rationale To cater for growth, the transport system needs to move more people with fewer vehicles coming into the
central city. The main way to achieve this for longer distance journeys will be through increased numbers of
people travelling by public transport. This step change in public transport will require a significant increase in
public transport capacity. To ensure that public transport provides an attractive travel choice, services will
need to be more reliable and this will require increased priority on congested parts of the network,
particularly in the central city.
RPI proposals
The RPI includes a range of public transport priority measures in and around the central city:
Early improvements by enhancing bus priority
As part of early improvements, bus priority enhancements along the Golden Mile could support the
improvements already introduced as part of the new Wellington City bus network. Other corridors where
bus priority enhancements have been identified to help reduce the delays that buses experience include
Kent and Cambridge Terraces, Adelaide Road, Taranaki Street, Kilbirnie Crescent, Bowen Street, Hamilton
Road, Willis Street, and Victoria Street. These priority enhancements encompass a range of interventions
including signal timing and detection changes, increased lengths and hours of operation of bus lanes, and
rationalisation of bus stops.
In addition, there are approximately 9 bus stops on the core routes of the new bus network that do not
meet minimum design standards for length, meaning that buses cannot stop adjacent to the kerb.
Improving these stops could address issues related to traffic flows, potential safety issues, and providing an
effective service for mobility impaired users.
In order to improve the flow of buses it is proposed to trial further restrictions on general traffic in sections
of Willis Street, Lambton Quay and Courtenay Place. This measure could also improve conditions for
pedestrians and cyclists.
A dual public transport spine through the central city
The new Wellington City bus network is intended to improve bus reliability along the Golden Mile by
rationalising services and utilising higher capacity vehicles. As bus frequencies increase to accommodate
growing demand, travel time reliability will deteriorate due to capacity constraints on the Golden Mile.
Therefore, a second public transport spine through the central city is recommended to increase public
transport capacity to support growth, and to further improve service reliability. The proposed route for this
second spine is along the waterfront quays and Taranaki Street. A dual spine will enable mass transit to be
introduced on the waterfront route (as discussed in Section 14.3.5).
Providing high quality and high frequency bus services
To maintain reliable services, the core bus routes outside of the Golden Mile will also require additional bus
priority as ridership grows and service frequency increases. In addition, the creation of a mass transit route
will require the wider bus network to be reconfigured to provide effective connections between the central
city and other parts of Wellington.
PART B3 – Programme Development: Recommended Programme
Let’s Get Wellington Moving Programme Business Case – Draft Released 21 June 2019 73
The core corridors currently being considered for improvements to provide high priority connections
include Hutt Road, Thorndon Quay, Glenmore Street, Bowen Street, Chaytor Street, Brooklyn Road, Willis
Street, Victoria Street, Courtenay Place, Elizabeth Street, Brougham Street, Pirie Street, Waitoa Road,
Moxham Avenue, Kilbirnie Crescent, Rongotai Road, Adelaide Road, Riddiford Street, and Constable Street.
14.3.5. Mass Transit Supporting Urban Regeneration
Provide high-capacity, high-quality, high-frequency public transport (using either light rail (LRT) or a
technology with similar characteristics) from Wellington Railway Station along the waterfront quays,
Taranaki Street, and Adelaide Road to the Hospital, Newtown and Airport as part of the wider public
transport network.
Rationale
Mass transit enables high passenger volumes to be carried down defined corridors in an efficient and practical
way. In the Wellington context, this will improve both access to destinations in the CBD and journeys for
longer regional trips. To achieve this will require the mass transit services to be well integrated with the heavy
rail and bus networks, including the provision of quality interchanges.
Mass transit also has the potential to encourage more intensive land use development along its route. The
degree to which this is achieved depends on a variety of factors such as land use zoning and other policies,
commercial and residential demand in the locations concerned, and the perceived permanence and quality of
the mass transit route, the service provided, and the stations.
To support the goal of having a vibrant, prosperous and compact city, the LGWM programme aims to
encourage urban intensification, including both residential and workplace growth, within easy reach of the
central city. Intensification along mass transit routes is desirable from a transport perspective because it
allows growth in travel demand to be accommodated by public transport rather than driving, reducing
congestion and emissions. The corridor to the south of the CBD, from Te Aro to Newtown, has been identified
as having the greatest potential for this growth, with less but still notable potential through Kilbirnie and in
Miramar. A mass transit route has the potential to support intensification and development along this
corridor, reducing the need to travel long distances.
RPI proposals
The RPI includes a mass transit route for Wellington, providing:
A high-quality, high-frequency mass transit route from Wellington Railway Station to the Hospital, Newtown
and Airport as part of the wider public transport network
A central focus of the RPI is investment in mass transit, to improve public transport mode share and
encourage urban development in the growth areas to the south of the central city.
As summarised in Section 10.4, LGWM has a preference for a mass transit system with the characteristics
of light rail. It will include high frequency services (every 10 mins or less), modern high capacity (e.g.
articulated) electric vehicles with superior ride quality, fast loading and unloading, dedicated lanes with
signal priority, and high quality stations with level boarding.
This will enable a high quality public transport corridor, from Wellington Railway Station along the
waterfront quays, Taranaki Street, and Adelaide Road to Newtown, and extending to Kilbirnie, Miramar and
the Airport via a new Mount Albert tunnel.
Supporting changes to land use and policy settings will be needed to enable urban development and
support mass transit investment (as discussed further in Section 10.1).
PART B3 – Programme Development: Recommended Programme
Let’s Get Wellington Moving Programme Business Case – Draft Released 21 June 2019 74
14.3.6. Urban Development Land Use Changes Integrated with Transport
Enable intensification along mass transit corridors through District Plan changes and new regulatory
tools
Possible market interventions such as amalgamation of parcels through an urban development agency
in Te Aro, Adelaide Road, and parts of Newtown, Kilbirnie and Miramar.
Rationale
The CBD, Te Aro, Adelaide Road and Newtown are expected to be amongst the fastest growing
neighbourhoods in the city and region over the next 30 years. Residential intensification in these areas is
desirable because it places residents near their place of employment, education, shopping and leisure. This
reduces the need to travel and makes walking, cycling and public transport viable alternatives to travel by car.
Such intensification is already happening, albeit at a relatively slow pace. Many factors hinder the rate of
development including regulatory restrictions, fragmented land ownership and the lack of certainty for
developers and lenders. Mass transit investment can act as a catalyst for increased intensification, but it
requires a supportive land use planning and regulatory environment. At the same time, more intensive
development along the mass transit corridor is desirable to ensure the city receives the most benefit from the
mass transit investment. In the absence of such land use changes in the growth corridor(s), it is unlikely that
high levels of investment in transport infrastructure would be justified.
RPI proposals
The RPI includes the following interventions to facilitate urban development integrated with transport
investment:
District Plan changes to enable intensification along mass transit corridors
A full review of the Wellington City District Plan is expected to start shortly. LGWM recommends that the
Wellington City Council continues to integrate future land use with the future location of mass transit
routes when considering the settings that guide residential and employment intensity. For examples, this
could mean relaxing the maximum building height and site coverage to enable greater housing density and
urban development to be built within walking distance of mass transit stops.
Additional regulatory tools
In order to speed up private investment (and enabling development along mass transit routes), we
recommend that Wellington City Council continues to work with central government on new or extended
regulatory tools. For example, Special Housing Areas or similar precinct masterplan frameworks that have
been helpful in providing investment confidence and greater certainty in the regulatory process.
Possible market interventions
When development is unlikely to be delivered by the private market, central government and the City
Council may need to intervene directly, for example to amalgamate small parcels that are in separate
ownerships and not economical to redevelop individually. This could be facilitated by an urban
development agency/authority, where such entities have been helpful internationally in urban
regeneration and development, especially when leveraging off infrastructure investment.
Value capture mechanisms
Investment in transport and amenity improvements by central and local government is likely to lead to
benefits such as increases in value for those properties located nearby. It may be possible to capture some
PART B3 – Programme Development: Recommended Programme
Let’s Get Wellington Moving Programme Business Case – Draft Released 21 June 2019 75
of this windfall uplift in land values to fund part of the RPI. We recommend that the City Council works with
central government to develop mechanisms enabling appropriate value capture.
Safer speeds
As part of the early improvements, the RPI includes a review of the speed limits on central city streets.
Lower traffic speeds have the potential to support improved amenity and urban realm, encouraging more
place-based function of the road corridor such as retail and leisure activity.
14.3.7. Smarter Transport System
Applying the Mobility as a Service platform to the Wellington context
Optimisation and minor safety and operational improvements including the Golden Mile, Cobham
Drive, the Terrace, Tinakori Road, and the waterfront quays
Enhancement of existing travel demand management programmes
Transition to an integrated transport network operating system
Design of transport system transformation - travel demand management measures and temporary
infrastructure and services to manage disruption and ensure a smooth transition to the future
transport system e.g. park and ride facilities, high occupancy vehicle lanes, public transport subsidies,
road network changes and travel behaviour change.
Rationale
Technological advances, in particular the increased use of smartphones and other technologies, is already
enhancing the ability of transport users to make more efficient use of the transport system. This trend is likely
to continue and accelerate over the next few years.
These developments will provide the opportunity to maximise the return on investment in the transport
system by making better use of existing and future network assets. They also make the overall system more
flexible and adaptable in responding to unforeseen changes.
In conjunction with these technological advances, enhanced integrated management of the transport system
will make the system more user friendly (for example, in providing up to date travel information and advice),
and more resilient in dealing with disruption such as weather events.
Use of smart technology will be particularly important in managing the implementation of the RPI, for example
in directing traffic away from areas of construction disruption.
Letting technology enabled transport disruption happen without strategic oversight and direction poses a risk.
For example, the increasing permeation of ride-hailing in many cities has led to a decrease in public transport
patronage and increased vehicle kilometres travelled.
RPI proposals
The RPI includes the following improvements:
Early improvements towards a smarter transport network
These early improvements include applying the Mobility as a Service (MaaS) platform that is being
nationally developed to the Wellington context. For example, tailoring MaaS to use the existing smart
parking system. The early improvements also include optimisation and minor safety and operations
improvements on the Golden Mile, Cobham Drive, the Terrace, Tinakori Road, and the waterfront quays.
The RPI also includes increased resource allocation for travel demand management programmes such as
school travel planning and e-bike uptake encouragement.
PART B3 – Programme Development: Recommended Programme
Let’s Get Wellington Moving Programme Business Case – Draft Released 21 June 2019 76
Transition to an integrated transport network operating system
The current transport system includes a number of networks that are largely operated independently such
as the local street network and the rail network. There is an opportunity to better integrate these
operations in order for the transport system to work towards shared outcomes. What this might look like in
reality is currently being considered nationally, and Wellington would particularly benefit from such an
operational approach given that the different transport networks already have complex overlaps (e.g.
diverting traffic around a rail level crossing in real time). The integration of new transport components
from the RPI into such an operating system, such as the mass transit service, would also help to deliver
optimised returns on investment.
Design of transport system transformation
All projects should include appropriate measures to minimise disruption during construction and to
manage a smooth transition for people using the transport system on a day to day basis. For the LGWM
RPI, designing and managing the transition is significant enough to be recognised as a key component of
the programme itself. This is because central Wellington’s transport system:
Is complex and its elements are highly interdependent
Operates close to, at or over capacity at peak times
Is likely to undergo a series of major changes simultaneously (e.g. mass transit construction,
Golden Mile changes, Te Aro changes, and shared streets).
Design of transport system transformation will include a suite of travel demand management measures
and temporary infrastructure and services to create a smooth transition to the future transport system e.g.
park and ride facilities, high occupancy vehicle lanes, public transport subsidies, road network changes, and
travel behaviour change.
Design of transport system transformation is highly interdependent with the wider programme as some
elements of the RPI may need to be brought forward or sequenced to manage the system change. For this
reason the design of transport system transformation needs investigation in parallel with the development
of other programme components.
14.3.8. Smarter Pricing
A suite of travel demand management measures including greater use of pricing mechanisms, such as
changes to parking charges and the introduction of congestion charging.
Rationale
Pricing mechanisms are already used in managing transport demand for the use of Wellington’s transport
system, particularly at busy times. These mechanisms include on-street parking charges and subsidised public
transport fares.
Demand management has a key role to play in ensuring the RPI achieves optimal results in performing against
the investment objectives. For example, congestion charging would help to reduce congestion to efficient
levels on strategic road corridors to, from and through the central city. It would also be used to encourage use
of more space-efficient modes and reduce the impact of traffic flows on sensitive areas in the city, such as the
waterfront.
PART B3 – Programme Development: Recommended Programme
Let’s Get Wellington Moving Programme Business Case – Draft Released 21 June 2019 77
RPI proposals
The RPI includes:
Travel demand management and pricing
As part of the suite of travel demand management measures there is an opportunity to better manage
demand through pricing mechanisms. The RPI includes congestion pricing. This will include one or a
number of tools that charge motorists to drive into the central city, such as a central city cordon charge or
parking levies.
There are several ways in which pricing mechanisms could operate. It could vary temporally, have multiple
staggered cordons, or have exemptions for certain user groups. As such, there is a need to further
investigate pricing to inform any legislative change. The RPI has assumed a cordon charge for entering the
central city in the order of $5 to $10 that is focused on busy times. This modelling has indicated that pricing
will significantly contribute towards achieving the objectives of LGWM.
Pricing has the potential to result in social equity issues, particularly when travel choice is limited. The
provision of improved public transport alternatives, as proposed in the RPI, is therefore an important pre-
requisite to the introduction of any new pricing schemes.
To support the introduction of increased use of pricing mechanisms, other demand management tools that
will be considered include providing high occupancy vehicles lanes, or increased priority for non-car modes.
14.3.9. More Reliable Access from the North
Optimisation and minor safety improvements on State Highway 1
Southbound widening of State Highway 1 between Ngauranga and Aotea Quay (potentially for buses,
high occupancy vehicles and/or freight vehicles)
Duplication of the Terrace Tunnel, enabling two southbound lanes and provision of shoulder areas within
the tunnels, and potentially including a cycling connection between The Terrace and Willis Street.
Rationale
The State Highway network provides access for people and goods to the central city, as well as other key
destinations such as the port, hospital, and airport. Access to these destinations is complex and would
substantially change as key elements of the RPI are implemented. For example, the waterfront quays route
will not be able to cater for current volumes of general traffic once the dual public transport spine is in place.
It will be difficult to accommodate these major road capacity reductions – even with congestion charging –
without impacting negatively on travel time reliability for peak time journeys to the key regional destinations.
This will be particularly so during transition to the new system as key RPI elements are constructed.
The network operates at capacity in some locations during peak times, resulting in unreliable journey times
and use of less suitable local streets for longer distance movement. Growth will exacerbate these issues.
Creating an improved bypass route (in conjunction with improved walking, cycling and public transport
options) will enable use of stronger demand management measures to reduce the number of vehicles using
less suitable local streets.
Improving the resilience of the land transport system through the central city has the potential to speed up
reconnection of key recovery centres including the airport, hospital, and port, and the wider region following a
large natural hazard event. Sections of State Highway 1 would play a key role in this as some local roads have
the potential to be disrupted due to the risk of adjacent buildings collapsing.
PART B3 – Programme Development: Recommended Programme
Let’s Get Wellington Moving Programme Business Case – Draft Released 21 June 2019 78
RPI proposals
The RPI includes the following improvements:
Early improvements on State Highway 1
This includes a selection of optimisation and minor safety improvements to State Highway 1, particularly
focused on areas of interface with local streets or sensitive adjacent land uses. Areas for consideration
include near the Aotea Quay off-ramp, the Terrace Tunnel approaches, Karo Drive, Wellington Road,
Cobham Drive, and Tinakori Road and the Terrace off-ramps.
Southbound widening of State Highway 1 between Ngauranga and Aotea Quay
Widening of State Highway 1 southbound through the addition of a fourth lane between the Ngauranga
Interchange merge and the Aotea Quay off-ramp could be tailored to deliver a variety of benefits. It could
be allocated to high-occupancy vehicles and/or buses to support a direction of moving more people with
fewer vehicles. It could be allocated to freight only movements to improve access to the port and any new
multi-user ferry terminal. As such, further investigation of this item would need to consider the
interdependencies outside of LGWM as well as the strategic approach and objectives of LGWM.
Duplication/widening of the Terrace Tunnel
Duplicating the Terrace Tunnel has the potential to support increased capacity of the State Highway 1
corridor, which can work as part of the wider programme to achieve a variety of outcomes, including
shifting through-traffic away from central city streets and maintaining reliable access to key regional
destinations. A second tunnel will create the potential to have shoulder widths within the tunnels, reducing
the effects of breakdowns and other minor disruptions, as well as the potential to create a cycling
connection between Willis Street and The Terrace.
14.3.10. Reclaiming Te Aro
Short-term improvements including restricted parking on Vivian Street and optimisation of Vivian Street
and Karo Drive
Undergrounding of the State Highway at Karo Drive to create a transformational green space, urban
development opportunities and removing through traffic from Vivian Street.
Rationale
Vivian Street is an unusual State Highway in that it connects to and looks much like the rest of the local street
network. It is used and crossed by high numbers of private vehicles, buses, people walking, and people on
bikes. The priority given to its east-west flow over north-south flows at traffic signals can lead to conflicts. This
is particularly noticeable during peak periods where the number of pedestrians, cyclists, public transport
passengers and local vehicles crossing the State Highway corridor can significantly exceed those travelling
along it, leading to delays to many users. These conflicts are duplicated along Karo Drive, the westbound
counterpart to Vivian Street.
The State Highway provides regional access to the airport and the hospital, and is a key route for vehicles by-
passing the CBD. Maintaining reliable traffic flows along the State Highway network is therefore important.
Reducing conflicts between local and regional traffic, and generally lowering the level of vehicular traffic on
central city streets has the potential to increase the attractiveness of Te Aro and stimulate regeneration in and
around the central city.
PART B3 – Programme Development: Recommended Programme
Let’s Get Wellington Moving Programme Business Case – Draft Released 21 June 2019 79
RPI proposals
The RPI includes the following interventions to improve Te Aro:
Early improvements to optimise Vivian Street and Karo Drive
This includes restricting parking along Vivian Street and changes to traffic signals and lane allocation along
Karo Drive to ease movements both on the State Highway and on local north-south streets.
Reconfiguration of State Highway 1 through Te Aro
This investment would enable eastbound State Highway through traffic to be removed from Vivian Street
and relocated to a tunnel running alongside Karo Drive. Karo Drive itself would also be undergrounded and
the surface over both tunnels used for local movements and to create a series of new open spaces. This
would help separate through traffic from the local road network, reducing conflicts.
Access and egress between the local network and State Highway 1 requires more work to get the best
balance of benefits between attracting traffic away from the central city streets, improving amenity along
Vivian St and Karo Drive, facilitating access to regional destinations and enabling mass transit along
Taranaki Street. The one-way use of Vivian will need to be reviewed as part of the wider network redesign.
These changes would improve the amenity in Te Aro and attract further urban development in the area.
They would also facilitate local north-south movements, separated from east-west State Highway
movements.
14.3.11. Improving the Basin
A short-term package of minor at-grade changes to improve reliable access for all modes
Basin Reserve grade separation between north-south movements and east-west movements with a short
bridge extension to Sussex Street (over State Highway 1).
Rationale
The Basin Reserve area is home to an important sports facility and reserve, to a number of schools and
colleges, and to buildings and features of heritage and cultural importance. The area is physically constrained,
accommodating the State Highway, main arterial roads, public transport services as well as walking and cycling
routes from the surrounding residential neighbourhoods.
The Basin Reserve area sits at the confluence of the main transport corridors from the southern and eastern
suburbs to the central city. These corridors provide the main access routes to the Wellington Regional Hospital
and the airport. The current road layout at the Basin results in conflicts between these transport movements.
Reducing the conflicts between competing movements around the Basin would help provide more reliable
access for all modes of travel.
RPI proposals
The RPI includes improvements to the transport network in the vicinity of the Basin Reserve:
Early improvements at-grade to improve reliable access for all modes
These improvements include localised widening and the removal or relocation of a limited number of on-
street parking bays to create four continuous traffic lanes between Kent Terrace and Paterson Street (two
eastbound to Mt Victoria tunnel and two southbound) and between Paterson Street and Adelaide Road
(two southbound to Adelaide Rd and two westbound). They may also include ‘queue-jump’ facilities for
public transport at traffic signals.
PART B3 – Programme Development: Recommended Programme
Let’s Get Wellington Moving Programme Business Case – Draft Released 21 June 2019 80
These changes are minor and low cost. They are designed to have minimal impacts on the Basin Reserve
and adjoining properties. They are expected to provide value for money and help relieve pressure around
the Basin in the short term but are not expected to provide a long-term solution.
Grade Separation
‘Grade separation’ (whereby one flow of traffic passes either over or under another) would significantly
reduce conflicts between the east-west State Highway movements and north-south local road movements
(the latter includes substantial bus movements). Safe and more convenient routes for pedestrians and
cyclists would also be accommodated as part of a design. Providing easy access to the local schools would
also be a priority.
There are a number of possible design configurations for grade separation at the Basin. The LGWM
preference is for an approach that uses the natural topography of the Basin to achieve a sympathetic
design that minimises the extent of any structures required. LGWM has identified a possible approach that
would see the extension to Sussex Street at its current level (over a lowered State Highway 1) with an at-
grade signalised junction where the SH1 eastbound exit meets Sussex Street.
Close collaboration with LGWM stakeholders would be needed at the next stage of the programme to
refine this approach. This would consider a number of issues, such as walking and cycling access to and
around the Basin. It would also seek to avoid or minimise adverse impacts on property, heritage and
cultural values, and improve the function of the Basin Reserve and the character of the surrounding area.
14.3.12. Better Access to the East
Extra Mount Victoria tunnel, including new dedicated walking and cycling facilities, and widening of
Ruahine Street and Wellington Road to improve access for bus/high occupancy vehicles, and dedicated
walking and cycling facilities.
Rationale
Although the existing Mt Victoria tunnel includes a walking and cycling connection, it is of poor quality due to
its sub-standard width and proximity to vehicles, resulting in noise and air quality pollution issues and conflict
between users. A new facility could encourage more people to walk and cycle between the eastern suburbs
and the central city.
The Mt Victoria tunnel operates at or near capacity for much of the day. It acts as a gate that restricts the
number of vehicles entering the central city from the east during peak times. It also operates, in conjunction
with the transport network around the Basin Reserve, to meter the amount of traffic that is released from the
central city towards the east. This function results in queuing traffic, creating unreliable journeys to the
regionally significant destinations of the central city and the airport, and causing some traffic to divert along
less suitable routes such as around the bays or through Newtown. This issue will become more critical as the
available capacity on these other routes is increasingly prioritised away from cars to other modes, including
mass transit.
An additional Mt Victoria tunnel will enable the transport system to cater for growth and improve journey
reliability on this corridor. To align with the LGWM strategic approach of moving more people without more
vehicles, the additional capacity would need to be managed to give priority to walking, cycling, public
transport, and high occupancy vehicles, and reduce traffic on alternative routes, such as Oriental/Evans Bay
Parade and Constable Street in Newtown. This could increase the person-carrying capacity of the corridor
while minimising the increase in vehicles.
PART B3 – Programme Development: Recommended Programme
Let’s Get Wellington Moving Programme Business Case – Draft Released 21 June 2019 81
An additional tunnel will also improve the resilience of the land transport system by creating the potential to
more quickly reconnect the key recovery centres of the airport, hospital, port, and wider region following a
large natural hazard event. Sections of State Highway 1 would play a key role in this as some local roads have
the potential to be disrupted due to the risks associated with adjacent buildings and slopes.
RPI proposals
The RPI includes improving access to the east of the central city:
Extra Mount Victoria Tunnel and Widening Ruahine Street – Wellington Road
An extra Mt Victoria tunnel with a new dedicated and separated walking and cycling connection; and
widened Ruahine Street and Wellington Road with new walking and cycling facilities, to create a higher
quality and more reliable connection for all modes. Allocating the additional lane capacity to public
transport and/or high occupancy vehicles can support a demand management approach that enables an
increase in the throughput of people without significantly increasing the number of vehicle movements.
14.4. Whole of Network Solution
The RPI has been developed as an integrated whole-of-network solution as shown in Figure 21. This
demonstrates a need for a mix of activities in order to create an optimised programme.
Success relies on each component being delivered in an appropriate sequence. A lack of integrated
implementation, meaning that some elements of the integrated programme are put on hold, may result in
lower benefits or poor value for money.
Figure 21 RPI as a whole-of-network solution
Walking improvements
Connected cycleways
Better PT to the north
Dual spine through city
Mass transit station to
airport
Land use & planning
changes
Encourage
through traffic to relocate
away from the central city and
other sensitive locations
Manage the network
to limit increases
in general traffic and operate the
network safely and efficiently
Create dedicated/
priority routesto support key
changes
Enable mode shift
with improvements
to walking, cycling
and public
transport infrastructure, and
land use policies
Encourage mode shiftto walking,
cycling, and public transport
Moving
more
people with
fewer
vehicles
Better access to the
East
Improving the Basin
Reclaiming Te Aro
More reliable access
form the north
Technology
Travel demand
management
Smarter pricing
Safer and more
attractive walking
and cycling
More reliable and
attractive public
transport
Integrated land use
and public transport
On-street parking
CBD
Hutt Road
Golden Mile
Waterfront Quays &
Evans Bay
Newtown
Cycleways through central city
Main routes to the central city
including north
Waterfront and Golden Mile
Mass transit route station-to-airport
Reduce road space
for general traffic in the central city and
along dedicated/
priority routes
PART B3 – Programme Development: Recommended Programme
Let’s Get Wellington Moving Programme Business Case – Draft Released 21 June 2019 82
14.5. Recommended Programme of Investment Sequencing
Much of the programme will take several years to investigate, design, and consent, and then several years to
construct, so making sure that the programme is delivered to minimise risks and at the same time bring about
early and long-lasting benefits is essential. Careful staging and sequencing of the programme delivery is
needed to manage a number of these critical risks including failure to deliver key programme elements, cost
and time escalations, unacceptable social and economic impacts, failure to realise the programme benefits
and loss of social licence.
This will require an ongoing process of testing and revaluation as the programme moves forward, which will
need to balance a range of strategic and pragmatic considerations such as:
Alignment with the LGWM programme principles and objectives
Actual changes in population and employment, and updated forecasts
Value for money (right things, right way, right time, right price)
Enable and facilitate customer behaviour change and positive experiences of the system as the RPI is
implemented - take people on the journey and help to change to new ways of moving
Manage the system disruption to the communities of Wellington over the life of the construction and
delivery process
Programme constraints such as market capacity to deliver, consenting and approvals processes and
social and environmental impacts. For example, how much capacity the construction industry has to
deliver at any one time
Work within the critical interdependencies of the programme elements.
LGWM has had to carefully consider how these various factors are balanced. For example, sequencing public
transport improvements to the dual spines through the city so that they do not occur simultaneously,
balancing the desirability of implementing public transport improvements as soon as possible against avoiding
unacceptable disruption of the transport system.
Based on critical interdependencies and expected project lead times (and informed by the wider
considerations noted above), an initial sequence has been developed and is set out below in Table 17. It is
important to note that the detailed investigation of the RPI elements and how they fit together may lead to
changes in the sequencing.
Table 17 Indicative RPI sequencing
Programme elements Total years to complete
Key assumptions12
Early improvements 3 to 4 years Assumes large corridor work (e.g. Golden Mile and Hutt Road/Thorndon Quay) is undertaken to a trail installation level of finish. Does not implement place-making or beautification initiatives.
Large volume of simultaneous work assumes that industry has capacity and disruption is manageable.
Walkable City 4 to 7 years Assumes some typical urban improvements like lighting and areas of paving, improved access across roads.
12
If any of these assumptions prove incorrect, this has the potential to impact significantly on timeframes, risks and scope of programme elements
PART B3 – Programme Development: Recommended Programme
Let’s Get Wellington Moving Programme Business Case – Draft Released 21 June 2019 83
Connected cycleways 3 to 4 years Intended to be delivered as part of early improvements packages.
Public transport to the North (Hutt Road / Thorndon Quay)
3 to 5 years Assume corridor width reallocation, minor priority and civils. Scope includes cycling improvements and some pedestrian improvements. Assume no widening beyond road reserve, hence no designation.
Public transport to / through the city
6 to 8 years Assumes minor civil work, some signal changes, and associated place-making enhancements (Golden Mile assumes full place-making enhancement). Assumes moderate level of complexity for related services work but not full service relocation/upgrade. Assumes only WCC land is needed.
Mass transit to Newtown 10 to 14 years Assumes LRT along LGWM preferred alignment with no feasibility issues.
Assume investigation includes entire mass transit system and related bus changes. Assume a planning alliance to deliver planning and consenting. Assume once consents are granted the physical works are procured separately.
Assume simplified construction sequence of services, slab and stations, track and rolling stock.
Assume that three different sections can be worked on simultaneously.
Assume funding for property available from outset, and acquisition starts on properties that are highly likely to be required (risk of alignment change as part of BC). Assume property industry capacity (risk).
Assume planning alliance is procured to undertake planning, consenting and reference design for route to Newtown.
Assume traditional consenting path as nationally significant without legislation (board of inquiry without high/supreme court appeals).
This programme is courageous, there is an extreme risk of rework and sunk cost from design acceleration and service relocation prior to obtaining consents.
Assume road closures through Newtown township and centre are accepted by community.
Assume two large TOD style stations and one medium station between station and Newtown (railway station, Te Aro Park, Basin respectively). Assume interdependencies between slab and large stations are well understood and mapped.
Mass transit Newtown to Airport
11 to 15 years Assumes LRT along LGWM preferred alignment with no feasibility issues.
Assume investigation includes entire mass transit system and related bus changes. Assume a planning alliance to deliver planning and consenting. Assume once consents are granted the physical works are procured separately.
Assume simplified construction sequence of tunnel, services, slab and stations, track and rolling stock.
Assume that three different sections can be worked on simultaneously.
Assume funding for property available from outset, and acquisition starts on properties that are highly likely to be required (risk of alignment change as part of BC). Assume property industry capacity
PART B3 – Programme Development: Recommended Programme
Let’s Get Wellington Moving Programme Business Case – Draft Released 21 June 2019 84
(risk).
Assume planning alliance is procured to undertake planning, consenting and reference design for route to Airport.
Assume traditional consenting path as nationally significant without legislation (board of inquiry without high/supreme court appeals).
Assume one medium station at the Airport.
Ngauranga to Aotea Quay southbound 4 laning
5 to 7 years Assume scope is four-laning with rebuilt Aotea Quay off-ramp lane drop and additional work to provide specialised port access (Thorndon overbridge seismic performance out of scope).
Assume a simple process with no property issues and related delays with GWRC and Kiwirail.
Terrace tunnel duplication
8 to 10 years Assumes some variation of duplication scheme.
Assume minor property requirements resulting from additional investigation. Main risk is potential to need town belt land.
Reclaiming Te Aro 12 to 16 years Assume funding for property available from outset, and acquisition starts on properties that are highly likely to be required (risk of alignment change as part of BC).
Assume alliance delivery model that is lined up during BC approvals. Alliance scope to deliver planning, consenting, design and construction.
Assume traditional consenting path as nationally significant without legislation (board of inquiry without high/supreme court appeals).
Potential fatal flaw in traditional consenting pathway as Heritage not covered by Board of Inquiry process and project likely to have significant heritage impact.
Assume cut and cover methodology due to grades and access points.
Improving the Basin 9 to 11 years Assume that scope includes a structure, and grade separation of westbound movements as a minimum.
Assume Board of Inquiry consenting process with some opposition.
Mt Victoria tunnel duplication and Ruahine St widening
10 to 12 years Assume duplication methodology similar to previous scheme.
Assume Board of Inquiry consenting process with some opposition.
Several key trade-offs in this sequencing require further investigation before they can be resolved. In
particular:
Whether demand management and extra buses on other routes can create sufficient modal shift to
enable the start of construction of mass transit (and necessary general traffic capacity reductions on
the waterfront quays and through Newtown)
The optimal timing of pricing measures to achieve modal shift, having regard to social equity issues
and availability of transport choices
If sufficient modal shift cannot be achieved through demand management, whether relocation of
general traffic capacity to an improved bypass route can provide a practical alternative in providing
effective access to key destinations.
A resulting indicative sequence is shown in Figure 22.
Let’s Get Wellington Moving Programme Business Case – Draft Released 21 June 2019 85
Figure 22 Recommended Programme of Investment indicative sequencing, key activities and decision points
PART B3 – Programme Development: Recommended Programme
Let’s Get Wellington Moving Programme Business Case – Draft Released 21 June 2019 86
14.6. Recommended Programme Assessment
14.6.1. Cost Assessment A rough order of costs has been developed for the elements of the RPI. These costs are shown in
Table 18 and should be considered indicative as outturn costs (client managed costs, construction
costs and professional fees). Contingency has been qualitatively assessed and applied to the base
estimate. Funding risk has not been applied at this stage.
Detailed design for the large interventions has not been undertaken and there will be a range of
possible options for most of the interventions. This report bases the cost estimation at this stage on
one of the possible options for each intervention. In addition, there a number of significant
assumptions that will require testing as part of more detailed option development, particularly those
related to underground services, cultural heritage, contaminated land and property purchase.
The summary report for cost assessment is shown in Appendix J.
Table 18 Recommended Programme of Investment Cost Assessment
RPI ELEMENT ESTIMATED COST $M
(2018 UNINFLATED)
Walkable City 70*
Connected Cycleways 30
Public Transport to the north and to/through the city ** 300
Mass Transit – City to Newtown*** 990
Mass Transit – Newtown to Airport*** 450
Smarter Transport Network 30
Smarter Pricing 30
Extra Mt Victoria Tunnel – Duplicate Ruahine St. / Wellington Rd. 480
Basin Reserve Improvements 130
Extra Terrace Tunnel and 4th lane Southbound 400
Te Aro Tunnel and Park 1100
TOTAL 4010
* Cost reflects an allocation to undertake early improvements and commence an ongoing programme of larger scale public space improvements ** Excludes rail improvements (funded currently outside of LGWM) *** Cost estimates based on a Light Rail Transit style for Mass Transit
PART B3 – Programme Development: Recommended Programme
Let’s Get Wellington Moving Programme Business Case – Draft Released 21 June 2019 87
14.6.2. Investment Objective Assessment The RPI has been assessed against LGWM investment objectives and other key impact areas using both qualitative and quantitative measures and a variety of assessment tools including modelling. The current assessment contains a degree of uncertainty, reflecting the current state of programme development. This uncertainty will be reduced as different RPI components are investigated and designed in more detail.
Table 19 summarises the assessment of the RPI against the LGWM Investment Objective KPIs. A more complete and detailed assessment is shown in Appendix C.
Table 20 summarises other key impacts of the RPI that have been identified.
PART B3 – Programme Development: Recommended Programme
Let’s Get Wellington Moving Programme Business Case – Draft Released 21 June 2019 88
Table 19 Summary of RPI Assessment against Investment Objectives
Objective: Key Performance Indicator Description Comment
Liveability
Amenity Index Measure of the quality of the urban environment including
greenspace, urban design, traffic volumes/speeds, and pedestrian
space
Amenity improvements across the central city due to increased pedestrian space along Golden Mile, urban activation along side streets, enhancements to the urban realm along the mass transit route, and new open space above Karo Drive. Reduced traffic speeds (to 30km/h) and a reduction in traffic volumes in the central city, particularly along the Waterfront and Vivian Street due to reallocation of capacity.
Carbon dioxide emissions
Transport-related CO2 emissions in the central city
Transport generated emissions in the Wellington region are projected to continuously decrease over time (50% reduction by 2036) due to changes in the vehicle fleet (fuel efficiency and electric vehicles).
The RPI contributes a further 18% emission reduction per capita within the CBD. Road pricing will have the biggest impact on emissions and the public transport, walking and cycling improvements in the RPI are critical foundations to enable introduction of pricing. Mass transit will support more intensive development in the central city and key centres, meaning more people use public transport and more destinations are within convenient walking and cycling distances.
Urban development
potential
An assessment of the opportunities for urban
development and value uplift
Mass transit will facilitate urban regeneration and more intensive development around stops and key centres. This will contribute to land value increase from additional residential homes, and jobs facilitated by intensification. The RPI will increase the combined value of property along the Mass Transit route by up to $560m.
Efficient and reliable access
Network catchment
The number of people living and working within 30 minutes of key
locations
Accessibility to the central city and key regional destinations will improve by all modes:
General traffic – 34% increase in population catchment within 30 mins of airport
Public transport – 19% increase in population catchment within 30 mins of CBD.
Travel time reliability
The reliability of travel time for journeys by different modes to
key regional locations
Travel time reliability to and through the central city and to key regional destinations will improve by all modes:
Dual dedicated public transport spines through the CBD improve public transport reliability by 50-80% through this part of the network
Up to 50% improvement in travel time reliability for traffic accessing the city from the North
Up to 35% improvement in travel time reliability for traffic accessing the airport from across the city
50-80% improvement in travel time reliability for public transport journeys to the
PART B3 – Programme Development: Recommended Programme
Let’s Get Wellington Moving Programme Business Case – Draft Released 21 June 2019 89
central city from the airport or eastern suburbs.
Reduced reliance on private vehicles
System occupancy
The ratio of people travelling to the central city (by all modes)
against private vehicles travelling to the central city
System occupancy will increase due to increased public transport and active mode use and more intensification in the central city /Te Aro
Public transport mode share increases from around 35% to 45% in the morning peak
15-20% reduction in vehicle numbers entering the central city during the morning peak.
Level of service for walking
Delays for people walking in the central city
People walking in the central city will be delayed less due to reduced traffic volumes. Pedestrian crossing priority will be enhanced along key pedestrian routes in the central city.
Level of service for cycling
An assessment of the quality of cycling facilities
The level of service for cycling will improve from poor to good or very good throughout the central city and for connections to the east via Mt Victoria tunnel. Some improvement for cyclists when connecting to the north and the south.
Safety
Safety for walking and
cycling
An estimate of the safety benefits for people walking and cycling in and around the central
city
There will be fewer fatal and serious injury crashes (estimated 30% reduction) for pedestrians and cyclists due to less traffic and slower traffic speeds in central city, and less conflicts. Improved pedestrian priority and crossing facilities will also contribute to safer city streets.
Adaptable to disruptions
Network resilience
An assessment of the network’s resilience to disruption caused by
large-scale natural hazards
Access between communities and key regional facilities (hospital, airport, port) will be more secure following a large-scale natural hazard event. The transport network will be more resilience to small scale disruption due to additional capacity on both traffic and public transport networks.
PART B3 – Programme Development: Recommended Programme
Let’s Get Wellington Moving Programme Business Case – Draft Released 21 June 2019 90
OTHER IMPACTS
The following impacts have not yet been specifically quantified due to the recommended programme of investment being in the early stages of development with a high level of uncertainty around some elements of the RPI, however it is important that they are flagged at this stage as their scale could be significant.
Table 20 Summary of RPI Assessment – other impacts
IMPACT: Type of impact Scale Mitigation
Parking
What: On-street car parks will need to be removed
Where: Through the central city and along main corridors to south, east, north
Why: To reallocate space to moving people
The number of parks affected and where will be determined as detailed design progresses.
City wide along key corridors Around 1100 – 1300 on-street parking spaces lost over duration of RPI
Parking mitigation strategy will be a key element of the programme
Improvements to public transport and walking and cycling links, coupled with pricing, will reduce the demand for parking
Built environment and heritage
What: Private property and heritage items affected
Where: Along main corridors to south and east – mass transit and SH1 routes
Why: To provide space for mass transit and other key infrastructure works
Exact nature of impacts are not currently known. May include land take, impact on property frontage or setting, or require a building to be changed or moved.
Localised
Urban design improvements will be incorporated into designs for transport improvements
Detailed design will progress cognisant of the requirement to preserve heritage features and enhance the overall built environment
Construction disruption
What: Road or lane closures, reduced speeds, stop/start conditions
Where: Through the central city and along main corridors to south & east – mass transit & SH1
Why: To accommodate construction of new and improved infrastructure
City wide
Sequencing will be important to manage demand and available capacity
Travel demand management techniques will be employed
PART B3 – Programme Development: Recommended Programme
Let’s Get Wellington Moving Programme Business Case – Draft Released 21 June 2019 91
14.6.3. Economic Assessment A high-level economic analysis has been undertaken to understand the likely scale of economic
benefits that can be expected from implementation of the RPI. This economic analysis is summarised
in Appendix K.
Two scenarios have been evaluated and are outlined below:
Medium Growth Scenario
This scenario assumes a medium level of population growth in the region, equivalent to 50,000
additional residents in Wellington City in 2046 compared to 2013 and population growth of around
100,000 across the region during the same time period. This approach is consistent with assumptions
made for other transport and land use planning projects across the Wellington Region. It assumes
static land use distribution, in alignment with current projections.
The construction period is assumed to be approximately 18 years and the evaluation period is 40
years. Benefits have been modelled from 2026 to 2036 and are assumed to increase at 1% per annum
from 2036 to 2059.
High Growth Scenario
The high growth-redistributed scenario assumes 80,000 additional residents in Wellington City in the
Do Minimum in 2046 compared to 2013 (equivalent figure for medium growth is 50,000) and re-
distribution of growth as a result of the programme. This is a project specific scenario reflecting the
fact that an improvement programme of this scale may catalyse additional growth and result in re-
distribution of population and employment. The high growth scenario also assumes that there are no
other constraints to growth in terms of land and other infrastructure, benefits increase at 2% pa post
2036, and a longer construction period that delays high-cost components.
Initial analysis suggests that benefits in 2036 could be between 20% and 35% greater than the
medium growth scenario as a result of the following:
Additional population growth, compounded by re-distribution of population / employment
growth to the corridor where investment is focussed
A Do Minimum scenario that has higher levels of congestion results in a programme that
delivers higher benefits per person
Lack of capacity on the public transport and private vehicle network constrains growth and
the RPI delivers significantly higher benefits by removing capacity constraints.
A summary of the key elements of the RPI, along with their estimated costs is shown in Table 21.
PART B3 – Programme Development: Recommended Programme
Let’s Get Wellington Moving Programme Business Case – Draft Released 21 June 2019 92
Table 21 RPI costs – low and high estimates (undiscounted, includes opex)
Programme Component Low (90% of
central) Central
High (120% of central)
Walkable City $60 $70 $80
Connected Cycleway $30 $30 $40
Public transport (City and North) $400 $440 $530
Mass Transit - Station to Newtown $1,000 $1,120 $1,340
Mass Transit - Newtown to Airport $500 $500 $600
Mt Victoria Tunnel and Ruahine Street $450 $500 $600
Improving Basin $120 $130 $160
Terrace Tunnel and 4th southbound lane $370 $410 $490
Karo Drive undergrounding $1,000 $1,120 $1,340
Smarter Transport Network $30 $35 $40
Smarter Pricing $30 $35 $40
Total $3,940 $4,380 $5,260
A peer review of these costs concluded that the process for estimating them was sound and that at
the next stage there is scope for value engineering to reduce costs without reducing benefits. Due to
the complexity of the programme and its significance beyond a pure transport project, a wide range
of benefits have been counted to assess the impact of the programme, not only traditional travel time
benefits but also on wider outcomes for the city.
Benefits quantified include:
Health benefits from increases in cycling, walking, and walking to public transport that
increases physical activity and overall health
Liveability benefits from reduced severance and increased green space
Safety benefits for people walking, on bikes, and in cars due to fewer and less serious crashes
Environmental benefits, including reduced carbon emissions, noise, and water pollution
Economic benefits from increased productivity and a transport system that supports growth
More reliable, more pleasant and less crowded travel offered by mass transit that delivers
benefits above and beyond traditional travel time benefits
Changes in the future distribution of housing and employment in the city and region as a
result of the programme
Wider economic benefits from increases in productivity, agglomeration and land values.
Accordingly, the economic assessment of the RPI has used elements of traditional transportation
economic analysis, coupled with analysis to understand the potential linkages between transport
interventions and land use development. The benefit streams assessment shows:
Medium growth scenario - Total benefits quantified are between $1.4 and $2.7 billion
High growth – redistributed scenario - Total benefits quantified are between $1.7 and $3.3
billion
Total travel time benefits for the medium growth scenario of $1.0bn and $1.8bn (high growth
– redistributed scenario: $1.2bn and $2.2bn) split roughly 50:50 between private vehicle and
public transport
PART B3 – Programme Development: Recommended Programme
Let’s Get Wellington Moving Programme Business Case – Draft Released 21 June 2019 93
Wider economic benefits in the range $600m to $1.3bn (High Growth – Redistributed: $800m
to $1.6bn)
Combined health and safety benefits of $200m to $400m
Table 22 provides a summary of the Benefit Cost Ratio (BCR) ranges for the RPI across both of the
scenarios (where the lower benefits come from the medium growth scenario and the higher benefits
come from the higher growth scenario).
Two BCR ranges have been produced. The first captures the total cost of the RPI, the second captures
the reduced cost to the government (BCR-G) on the assumption that a proportion of the cost can be
funded through alternative funding streams (such as developer contributions).
Table 22 Benefit Cost Ratio Summary (costs and benefits discounted)
Full Cost BCR Cost to Government BCR-G
Lower benefits
Central Higher benefits
Lower benefits
Central Higher benefits
Full Programme with cordon
charge
Costs $2,350 $2,350 $2,350 $2,000 $2,000 $2,000
Benefits $1,350 $2,350 $3,300 $1,350 $2,350 $3,300
BCR 0.6 1.0 1.4 0.7 1.2 1.7
Table 22 can be summarised as follows:
The ‘central’ assessment assumes a level of benefits between the middle of what is
achievable under a medium growth scenario and the middle of what is achievable under a
high growth scenario
The full cost RPI BCR is likely to be in the range of 0.6 to 1.4, reflecting the programme’s high
benefits, as well as high costs
If third party funding of 15% of totals costs can be identified, the cost to government (BCR-G)
is likely to be in the range of 0.7 to 1.7.
The major opportunities for improvement and refinement at the next stage relate to:
Further detailed modelling and planning of programme timing and sequencing to optimise
the benefits and mitigate construction impacts
More detailed assessment of costs to understand whether there are areas where costs could
be saved whilst preserving benefits
Benchmarking against other jurisdictions to be more certain about where the benefits and
costs might sit within the currently reported range
More detailed investigation for the programme elements that are relatively unknown in New
Zealand, such as a more robust assessment of the benefits and impacts of pricing.
Further investigation will allow the BCR to be assessed more accurately, but it is unlikely to result in a
BCR outside the current reported range.
When estimating the BCR in the next stage of the project, it will be important to consider any
additional interventions to what is currently proposed in the RPI that emerge from further detailed
investigations. Further sensitivity analysis will be needed in relation to:
Costs that are significantly lower than currently expected. This could potentially be achieved
through use of alternative or emerging technologies
PART B3 – Programme Development: Recommended Programme
Let’s Get Wellington Moving Programme Business Case – Draft Released 21 June 2019 94
Possible deferral of higher cost components of the programme without significantly affecting
the shorter to medium term benefits that may result for further work on sequencing.
Potentially higher levels of population and employment growth – effectively a continuation of
recent population trends for a 15 to 20 year period – as has been assumed for the High
Growth – Redistributed scenario
Higher wider economic benefits than have currently been calculated, driven to a certain
extent by higher growth, accepting the fact that the wider economic benefits (WEBS) as
currently estimated contribute around 30%-40% of overall benefits, a figure which is broadly
in line with projects of a similar size and nature and reflecting the transformational nature of
the RPI.
14.6.4. Investment Assessment Framework (2018-21) Results Alignment Assessment
The results alignment assessment as set out in the Investment Assessment Framework (2018-21)
considered several different activity classes, reflecting the wide nature of the RPI. This assessment is
shown in Appendix L, and can be summarised as:
Road safety promotion and demand management programmes – High Results Alignment
Walking and cycling improvement activities –High Results Alignment
Public transport improvement activities, including rapid transit and transitional rail – Very
High Results Alignment
Road improvement activities – High Results Alignment
Although road improvement RPI elements have High results alignment, they are enablers to mitigate
and manage the impacts of the Very High elements in order to achieve LGWM objectives and the
future vision for Wellington.
Therefore, having regard to the integrated nature of the LGWM investment programme, the RPI is
indicated as having High/Very High results alignment overall. It delivers strong outcomes against GPS
result areas:
Metropolitan and high growth urban areas are better connected and accessible
Better access to markets, business areas, and supporting tourism
Increased mode shift from private vehicle trips to walking, cycling and public transport
Improved network resilience for the most critical connections
Reduce transport’s negative effects on the local environment and public health
Costs and Benefits Appraisal
As discussed in Section 14.6.3, the RPI BCR is likely to be in the range of 0.6 to 1.4. Achieving a BCR
greater than 1 would be dependent upon a number of conditions, such as population and
employment growth, increased wider economic benefits, and reduced costs, each of which will be
investigated in further detail during the next stage of investigations.
Therefore, the RPI is assessed as having an indicative Low costs and benefits appraisal rating, which
will need to be confirmed during later business case development phases. This reflects the uncertain
nature of the economics, and potential to achieve a benefit-cost ratio in the 1 to 3 range.
PART B3 – Programme Development: Recommended Programme
Let’s Get Wellington Moving Programme Business Case – Draft Released 21 June 2019 95
Urgency Assessment
There are several reasons why detailed investigation cannot be deferred beyond the 2018/21 NLTP
period.
Public transport services in Wellington will approach capacity within the next ten years. In
reality, more and more services within the core of the peak will reach capacity. As the
perception of public transport as a viable travel choice erodes, people and businesses will
increasingly respond by changing behaviour.
A step change in public transport through implementation of a mass transit system will
require a long lead time due to the complexities of Wellington’s compact urban form.
Uncertainty around the detail of the projects proposed by LGWM (e.g. property impacts) can
result in reduced levels of development and investment. Developer investment will be
required to maximise the land use changes that are integrated with the transport
components of LGWM.
In addition, the rationale for commencing early improvements within the current NLTP period is that
they:
Provide significant benefits relative to their cost.
Can start to create travel behaviour change in a smooth way. Encouraging use of walking,
cycling, and public transport as viable travel choices prior to the mass transit system being
implemented.
Enable disruption from construction of larger programme elements to be managed through
providing improved alternative choices in the interim.
14.7. Programme Risks and Uncertainties
The key risks identified at this stage of the programme’s development are summarised in Table 23
below.
Table 23 Risks, potential consequences, and management strategy
RISK TYPE POTENTIAL CONSEQUENCES MANAGEMENT STRATEGY
The growth in regional population and employment may be lower or higher than forecast
The distribution of growth between the central city and the rest of the region may be different to that forecast
As the growth forecasts are the key drivers of transport demand, the need for changes to the transport system may be less urgent or more urgent than currently forecast
A wide range of growth forecasts is being assumed so as to ensure there is a high probability that the actual growth will be within the range
Precise sequencing for several elements of the RPI will be informed by monitoring
The modal preferences of customers may be changing due to economic, social or technological changes
The transport modelling carried out to date may be over-estimating or under-estimating the demand for travel by private vehicles in relation to travel by other modes
Precise sequencing for several elements of the RPI will be informed by monitoring
Funding priorities of central and local government may change over time
The RPI may not reflect funding priorities, and the programme may not deliver anticipated benefits if only partially implemented
The RPI has been developed to be flexible to funding priorities
Precise sequencing for several elements of the RPI will be informed by monitoring
PART B3 – Programme Development: Recommended Programme
Let’s Get Wellington Moving Programme Business Case – Draft Released 21 June 2019 96
The RPI will draw substantial funding from a number of sources, and some of these may not eventuate e.g. economic downturn
Parts of the RPI may not receive funding, and the programme may not deliver anticipated benefits if only partially implemented
Ongoing collaborative and integrated business case development, design, consenting and implementation
The RPI has been developed to be flexible to funding availability
Major infrastructure elements within the programme will have long lead times for planning and consenting processes
Wellington City may fall behind other competitor cities as a result of the transport system not addressing the problems or facilitating the opportunities in a timely manner
Using a programme business case in which all agencies are well coordinated should speed up any pre-construction phases and reduce the overall time needed to implement the investment programme
Ongoing collaborative and integrated business case development, design, consenting and implementation
Forecasting for large scale natural hazard events is an uncertain process
Investment in transport system resilience may prove to be insufficient to facilitate timely recovery following a larger than anticipated event
Investment in transport system resilience may prove to be unnecessary if an event does not occur
Align with ongoing resiliency planning within the region, including exploring appetite for risk
The RPI assumes complementary land use planning changes e.g. district plan changes which may not eventuate
The opportunity to leverage investment in the transport system to facilitate urban development will be lost
The RPI may not represent a value for money investment if it does not facilitate urban generation in the central city and Newtown
Decision points prior to implementation of major infrastructure that will reflect monitoring of land use policy
Ongoing collaborative and integrated business case development, design, consenting and implementation
Risk that investment will not be integrated with shift in transport system from technological advances
Potential to reinforce Wellington’s technological and innovative reputation is lost
Introducing unproven systems may result in sub-optimal outcomes or abortive investment
Staying flexible in reviewing the programme to incorporate changing technologies when they are judged to be sufficiently mature
A lack of integrated implementation e.g. resulting from opposition to potential intervention impacts
Key elements of the programme may be put on hold, undermining the effectiveness of the programme as a whole
Ongoing collaborative and integrated business case development, design, consenting and implementation
Ongoing engagement and consultation with the public and stakeholders
Resource and/or funding constraints may result in programme elements being delayed/deferred
Delaying elements of the programme may make it difficult or impossible to satisfactorily manage disruption to the transport system during construction phases (e.g. closure of lanes to allow mass transit infrastructure construction)
High priority given to maintaining transport system performance through early design of transport system transformation programme element
There may be pressures to change the balance of central and local government funding arrangements over the implementation of the RPI
Key elements of the programme may not be implemented, undermining the effectiveness of the programme as a whole
Build a high level of support for the programme at local, regional and central government levels
Significant cost of RPI may preclude other transport investments in region
The Wellington region has a limited ability to invest in transport projects outside of LGWM
The RPI has been developed to be flexible to changing transport demand
PART C – Preferred Way Forward: Affordability Constraints
Let’s Get Wellington Moving Programme Business Case – Draft Released 21 June 2019 97
PART C – PREFERRED WAY FORWARD
15. AFFORDABILITY CONTRAINTS (2019) The recommended programme of investment (RPI) as developed in Part B has been endorsed by the Transport
Agency’s Board as a programme business case, indicating that the strategic approach and outcomes sought
are valid, and that the RPI was the preferred way forward at that point in time (November 2018). This support
did not include commitment to progressing to the next stage (development of detailed business cases and
implementing early improvements) until further work had been carried out on the funding and financing
arrangements. LGWM partners were not able to commit to funding the full RPI because of the programme’s
high costs and the competing funding demands of other infrastructure investment projects in Wellington and
other regions over the next 20 years.
Given the scale of LGWM, the funding of the programme will have significant implications for the levels of fuel
excise duty and road user charges over that period. There may also be a need to use long term borrowing to
finance any residual gap between the cash flow requirements of LGWM and what the NLTF can fund on a pay-
as-you-go basis. These NLTF revenue and borrowing decisions are for the Government to decide rather than
the Transport Agency.
The Minister of Transport worked with the WCC Mayor and GWRC Chair (with advice from the Ministry of
Transport and LGWM) to develop an “Indicative Package” of their preferences that would fit within a fundable
envelope, aimed at making optimal progress towards the LGWM vision. The Indicative Package that emerged
from these discussions is set out in Section 16.
Following announcement of the Indicative Package, LGWM released a number of technical documents and
material that has underpinned the programme business case. This material and the way in which it relates to
this Programme Business Case and LGWM summary material is shown in Appendix N.
PART C – Preferred Way Forward: Indicative Package
Let’s Get Wellington Moving Programme Business Case – Draft Released 21 June 2019 98
16. INDICATIVE PACKAGE (2019) The Indicative Package, when formally supported by the LGWM partners and central government, will
represent the preferred way forward for implementing LGWM. The Indicative Package comprises the
following components from the RPI:
A walkable city - accessibility and amenity improvements, setting safer speeds for vehicles, walking
improvements include in major components
Connected cycleways - cycleways on Featherston St, Thorndon Quay, Courtenay Place – Dixon St,
Taranaki St, Willis St, Victoria St, Kent and Cambridge Terrace and Bowen St
Public transport (city and north) - dual public transport spine through the central city on the Golden
Mile and Waterfront Quays; rail network improvements; and bus priority on Thorndon Quay and Hutt
Rd
Smarter transport network - full integrated ticketing; transition to integrated transport network
operating systems; travel demand management measures including Mobility as a Service, parking
policy improvements and education and engagement
Mass (Rapid) Transit - provide mass transit as part of the wider public transport network from the
railway station to Newtown, and Newtown to the airport
Unblocking the Basin Reserve - package of minor at-grade changes to improve reliable access for all
modes; Basin Reserve grade separation between north-south movements, east-west movements and
any mass transit corridors
An extra Mount Victoria Tunnel and widening at Ruahine Street - extra Mount Victoria Tunnel and
widening of Ruahine St and Wellington road to improve access for buses and dedicated walking and
cycling facilities.
The extra Mt Victoria tunnel project is included in the package, and is expected to proceed late in the first
decade once:
Mass transit to Newtown has been delivered and is operational
The detailed business case for the project has been undertaken and updated demand modelling
confirms that the projects will support a reduction in single occupant vehicle journeys, during peak
periods, and mode shift to public and active transport.
The total capital cost of the Indicative Package is estimated as $3,665M (2019 risk adjusted capital costs).
Table 24 sets out a more detailed description of the Indicative Package components, the estimated capital
cost of each component and the objectives the components are aimed at achieving.
PART C – Preferred Way Forward: Indicative Package
Let’s Get Wellington Moving Programme Business Case – Draft Released 21 June 2019 99
Table 24 Indicative Package of Investments and Costs
COMPONENT DESCRIPTION OBJECTIVES 2019 ESTIMATED
CAPITAL COST ($M)13
A walkable city Accessibility and amenity improvements, setting safer speeds for vehicles, and
walking improvements.
A city that is safe and attractive to walk around. 95
Connected cycleways Cycleways on Featherston Street, Thorndon Quay, Courtenay Place, Dixon Street,
Taranaki Street, Willis Street, Victoria Street, Kent and Cambridge Terraces and
Bowen Street
A connected and safe central city cycleway network integrated with the wider cycleway
network.
40
Public transport (city and north) Dual public transport spine through the central city on the Golden Mile and
Waterfront Quays, rail network improvements and bus priority on Thorndon Quay
and Hutt Road.
A reliable public transport system that enables Wellington to grow and encourages public
transport mode shift, better public transport choices to the north and enables a 30
percent increase in rail peak patronage.
360
Smarter transport network Full integrated ticketing, transition to integrated transport network operating
systems, travel demand management measures including Mobility as a Service,
parking policy improvements and education and engagement.
A well-managed transport system that makes best use of infrastructure and helps smooth
transition through implementation of the Indicative Package.
80
Rapid transit Provide rapid transit as part of the wider public transport network from the railway
station to Newtown, and Newtown to the airport.
Improves travel choice through the city with an attractive public transport option to the
hospital and airport and creates an opportunity to share a more compact and sustainable
Wellington City.
2,200
Unblocking the Basin Reserve Package of minor at-grade changes to improve reliable access for all modes, Basin
Reserve grade separation between north-south movements, east-west movements
and any rapid transit corridors.
Reduces conflict between different movements and modes creating more reliable access
for all modes.
190
Extra Mount Victoria Tunnel
and widening of Ruahine Street
Extra Mount Victoria Tunnel and widening of Ruahine Street/Wellington Road to
improve access for buses and dedicated walking and cycling facilities.
Improves access reliability and travel choice from the east for all modes, relocates through
traffic away from Evans Bay route and Constable Street, onto the state highway, and
ensures network function while rapid transit is constructed in Newtown.
700
Total 3,665
13
Capital costs only. Cabinet cost estimates vary from LGWM estimates as they represent risk adjusted estimates.
PART C – Preferred Way Forward: Indicative Package
Let’s Get Wellington Moving Programme Business Case – Draft Released 21 June 2019 100
16.1. Funding and Financing the Indicative Package
16.1.1. Funding Shares The Indicative Package proposes that Wellington City Council and Greater Wellington Regional Council will
together contribute 40 percent of the costs of the Indicative Package, and central government will contribute
60 percent through the National Land Transport Fund (NLTF).
The share of NLTF funding for each project in the Indicative Package may differ from the overall 60:40 split.
For example, projects in the package that align closely with the results identified in the GPS may be eligible for
a targeted enhanced Funding Assistance Rate to accelerate their delivery. State Highway projects within the
Indicative Package are unlikely to receive more than 50 percent funding from Central Government.
Over 30 years, the Government share of the Indicative Package is estimated to be $3.8 billion, based on total
capital expenditure of $2.2 billion (60% share of total 2018 capital cost). This amount allows for cost increases,
inflation and the cost of financing.
The ability for the NLTF to fund central government’s share of the LGWM Indicative Package assumes the
Wellington region will receive 10.5 percent of NLTF revenues over 30 years. The basis for this allocation is that
the Wellington region currently has 10.7 percent of New Zealand’s population, although this is expected to
drop slightly in the medium term.
In addition to this, it is proposed that the rapid transit component of the Indicative Package will be financed
and repaid over a 50-year period.
16.2. Assessment of the Indicative Package
Preliminary assessment of the Indicative Package has been undertaken at a high level, and is less
comprehensive than the evaluation of the RPI. To enable evaluation, LGWM has made a number of
assumptions on the form and function of the Indicative Package elements that are likely to change as a result
of further investigation and design.
Key findings include:
Evaluation of the Indicative Package shows a slight increase in mode shift to public transport
compared with the RPI
Reduction in capacity on road network results in increased travel time and variability on the state
highway and local road networks
o Relative to base, do minimum and RPI
o Mitigated by the assumed effectiveness of a pricing mechanism
Sensitivity tests show:
o An effective pricing mechanism is required to support the Indicative Package
o A cordon charge is likely to be more effective than a parking levy, but further analysis is
required to confirm this
A pricing mechanism is essential for the effectiveness of the Indicative Package
o The modelling assumes the pricing mechanism is effective and has been deployed to deliver
outcomes, rather than as a means to calculate the appropriate charging level. Further analysis
needs to be done to determine the level of pricing and preferred pricing approach.
o Sensitivity testing shows that a cordon charge is likely to be more effective than a parking levy.
A cordon charge would further reduce trips through the CBD. Further analysis is required to
confirm this.
PART C – Preferred Way Forward: Indicative Package
Let’s Get Wellington Moving Programme Business Case – Draft Released 21 June 2019 101
16.2.1. Key Performance Indicators Assessment
KPI 1: Amenity Index
The Indicative Package will improve amenity in the central city compared with the Do Minimum. But this
improvement will not be as great as the RPI on Vivian Street, Karo Drive, and local streets, such as the
waterfront Quays and Taranaki St, due to higher traffic volumes.
KPI 2: Transport-related CO2 emissions in the central city
Lesser improvement in CBD Vehicle Kilometres Travelled for the Indicative Package (compared to RPI) due to a
higher number of through trips.
Less improvement in CBD CO2 emissions under the Indicative Package (compared to RPI) due to a parking levy
being less effective at managing travel demand through the city than a cordon charge.
KPI 3: Opportunities for urban development and value uplift
Under the RPI:
Mass transit with a high degree of separation/priority will deliver strong urban development potential
Te Aro improvements will deliver modest urban development potential but provide significant urban
amenity benefits.
Under the Indicative Programme:
Mass transit with a high degree of separation/priority will deliver strong urban development potential
No improvements in urban development potential in Te Aro.
KPI 4: System occupancy
Table 25 shows the slight improvement in occupancy for the Indicative Package (4.0) relative to the RPI (3.9).
Table 25 System occupancy assessment for the Indicative Package
ENTERING THE CENTRAL CITY IN THE MORNING PEAK 2016 DO-MINIMUM RPI INDICATIVE PACKAGE
Number of People 82,000 95,000 98,000 98,000
Number of Vehicles 31,000 31,000 25,500 24,500
Occupancy (People per Vehicle) 2.7 3.1 3.9 4.0
KPI 5: Delays for people walking in the central city
The Indicative Package will deliver similar walking benefits to the RPI with a few exceptions:
The Te Aro tunnel in the RPI delivers benefits to pedestrians by removing severance and providing a
higher amenity pedestrian corridor. Under the Indicative Package these benefits won’t be available
Vivian Street in the RPI becomes a two-way city street delivering opportunities for improved
pedestrian facilities along and across the street. In the Indicative Package improvements for people
walking on Vivian Street are likely to be less effective due to higher traffic volumes.
PART C – Preferred Way Forward: Indicative Package
Let’s Get Wellington Moving Programme Business Case – Draft Released 21 June 2019 102
KPI 6: The quality of cycling facilities
The quality of cycling facilities resulting from the Indicative Package is likely to be similar to the RPI, noting
some impact as a result of likely higher traffic volumes but further design is required to understand the
implications of not including the Te Aro improvements.
KPI 7: The number of people living and working within 30 mins of key destinations
Table 26 shows a reduction in network catchment for private vehicles for the Indicative Package relative to the
RPI. Public transport catchment is likely to be similar.
Table 26 Network catchment assessment for the Indicative Package
NUMBER OF PEOPLE LIVING… DO-MINIMUM RPI INDICATIVE PACKAGE
…within 30 minutes driving time of the central city 274,000 356,000 314,000
…within 30 minutes public transport travel time to central city 179,000 221,000 221,000
KPI 8: The reliability of travel time by different modes to key regional destinations
The Indicative Package delivers less improvement in travel time variability for private vehicles than the RPI.
More detailed work is required to confirm the overall network impact.
Improvements to public transport travel time variability are similar for the Indicative Package and the RPI,
assuming that public transport has sufficient capacity to meet extra demand. An implied assumption is that
pricing brings an opportunity to reallocate road space to public transport and makes it more reliable.
KPI 9: Deaths and serious injuries for people walking and cycling in and around the central city
Safety for people walking and cycling was qualitatively assessed:
The current accident rate is relatively low
Safety issues are generally at intersections
Intersection improvements (at detailed design) are likely to result in safety improvements
Removal of general traffic, or reduction in traffic speed is likely to result in safety improvements
The Indicative Package does not perform as strongly as the RPI as it addresses fewer conflicts,
particularly in Te Aro and for some sections of the local network such as Taranaki Street and the
Waterfront, which will see relatively higher numbers of vehicle through-trips.
KPI 10: Network resilience to disruption caused by large-scale natural hazards
An extra Mt Victoria tunnel and a possible new tunnel at Mount Albert will deliver resilience and operational
flexibility benefits. Resilience improvements on the key northern corridor will be limited without the 4th lane
southbound, the second Terrace Tunnel, and improvements through Te Aro.
Other Significant Impacts
Compared with the RPI, the Indicative Package will deliver:
A similar reduction to on-street parking
Reduced built environment and heritage impacts due to the absence of a tunnel through Te Aro
PART C – Preferred Way Forward: Indicative Package
Let’s Get Wellington Moving Programme Business Case – Draft Released 21 June 2019 103
Reduced construction disruption impact due to absence of a tunnel through Te Aro, Terrace Tunnel
duplication and 4th lane southbound.
16.2.2. Economic Assessment
A preliminary assessment has been undertaken for the Indicative Package. While this assessment was coarser
than the level of assessment undertaken for the RPI, the assessment indicates the following relative economic
benefits at a high level:
Similar levels of benefit for public transport
Similar levels of benefit for value uplift along the mass transit corridor, assuming a similar mass transit
system as the RPI
Reduced agglomeration benefits, in part due to less improvement in accessibility via the state highway
Reduced levels of benefit for walking, cycling, safety, health, and amenity due to higher number of
vehicle through-trips in the central city
For road network travel time:
o Initial modelling suggests the Indicative Package delivers approximately 25% of RPI benefits
o Modelling of road network travel time is optimistic and likely underestimates increase in
congestion in central city
o Further work is needed at the detailed business case stage to quantify the impacts.
The benefit-cost-ratio of the Indicative Package is likely to be in a similar range to the BCR range reported for
the RPI (0.6 – 1.4 full cost BCR). Further analysis, modelling and optimisation of the Indicative Package will be
required to confirm this.
16.3. Whole-of-System Solution
While the Indicative Package has the potential to deliver on the strategic intent of the RPI, a whole-of-system
solution similar to that presented in Section 14.4 will still be needed to unlock all benefits and deliver an
optimised programme. Indicative Package programme elements are interdependent, meaning that it is still
important to retain flexibility to review programme elements with regard to each other in future phases.
16.4. Sequencing, Interdependencies and Trigger Points
LGWM has not undertaken any additional detailed consideration of sequencing, interdependencies and trigger
points following the announcement of the Indicative Package. However, many of the findings and identified
risks from sequencing the RPI are still relevant, as is the need to continue reviewing these issues as LGWM
develops into a new entity and moves closer to delivering the programme. Key recommendations for moving
forward include:
A focus on staging, sequencing and transport system transformation must be embedded in the design,
resourcing and funding of the LGWM delivery vehicle. It must also form part of the scope of all
detailed business case (DBC) processes with coordination and alignment managed as an ongoing
process across these elements
A range of principles and criteria to inform the programme staging and sequencing needs to be
identified and agreed. Draft principles and criteria were identified in the LGWM Staging report and
these should be tested and reconfirmed in the next phase of work linked to the DBC processes
Engage with other major infrastructure programmes in the Wellington region. This should include
processes and some form of working relationships to map programme timing and delivery to consider
both opportunities and constraints
PART C – Preferred Way Forward: Indicative Package
Let’s Get Wellington Moving Programme Business Case – Draft Released 21 June 2019 104
Engage with and learn from other similar transformative transport programmes to ensure lessons and
tools from these are drawn upon and utilised as part of the LGWM programme
Consider, plan and deliver broader opportunities to minimise the disruptive impacts of change
through engaging with communities to understand how to provide alternative business and people
place opportunities during the delivery of the programme. This will require dedicated resourcing and
funding
Develop a step change in capability to manage operations planning and coordination. This needs to be
across all three partners to ensure that this capability can link from a strategic long-term view to day
to day operations management. This needs to be integrated with the mandate and scope of the
integrated delivery vehicle of the programme and will require full buy-in from all three programme
partners
Engage early with utilities operators and develop a strategic approach to managing the impacts on
utilities – this should also inform the scope, location and detail of projects as outlined in the first
recommendation. This needs to be well resourced and prioritised.
PART C – Preferred Way Forward: Management Case
Let’s Get Wellington Moving Programme Business Case – Draft Released 21 June 2019 105
17. MANAGEMENT CASE Achieving the benefits sought by LGWM in an optimised way will require a significant commitment of
resources and important policy decisions. This will include:
Increased funding allocations through Long Term Plan and NLTP amendments
Agreement to use new funding mechanisms to generate revenue needed to meet local share
requirements
Changes to land use planning settings to enable urban intensification to complement new
transport infrastructure
Agreement to an integrated delivery model.
In addition, some central government decisions will be needed to enable the programme to progress.
These include:
Funding commitments via the GPS and other mechanisms as appropriate
Enabling legislation to permit new funding, pricing and delivery mechanisms
Partnering with local government to explore new and innovative ways of financing and
delivery (e.g. an urban development agency).
Regional partner support for the programme will also be important. This will include:
Support to implement the programme, including wider regional connections
Continued commitment to supporting land use policies that reinforce a shift to public
transport, walking and cycling.
17.1. Delivery Model
There are several options for how to implement a programme of investment. These range from
delivery of different pieces of the programme by the three partner agencies under ‘business as usual’
arrangements, through to collaborative agreements, or even formation of a new agency charged with
delivery. LGWM, having completed the programme business case phase, is restructuring into a more
delivery focused entity to deliver the bulk of the programme.
While transitioning from the programme business case to detailed investigation and delivery, several
tasks will be ongoing. These include establishing the new delivery entity, undertaking detailed
investigations, and the early delivery of less complicated programme elements. Governance and
oversight arrangements will continue in the interim with high level involvement from the three
partners.
17.2. Next Steps for Delivery
The programme has been initially arranged into indicative discrete elements (as shown in Figure 23)
based on their interdependencies. Common aspects such as programming and modelling are shown
as work streams that sit across all the programme elements to ensure consistency of information and
delivery as illustrated in Figure 24.
PART C – Preferred Way Forward: Management Case
Let’s Get Wellington Moving Programme Business Case – Draft Released 21 June 2019 106
Figure 23 Indicative Packaging of Programme Elements
Figure 24 Indicative Structure of Packages
Place-making
Pedestrian improvements
Cycling improvements
Bus improvements on main routes to northern suburbs
Bus improvements to and through the central city
Unlocking rail network capacity (GWRC/KR led outside programme)
Safer speeds
Thorndon Quay and Hutt Road
Golden Mile
Technology and network enhancements
Suburban bus priority measures
Central city bus priority measures
Early delivery
Reconfigure urban corridors
Mass transit route from Wellington Railway Station to Newtown
Mass transit route to the Airport
Complimentary bus/train changes to optimise the entire public
transport system
Mass Transit / Public Transport system
Travel Demand Management
Integrated transport operating system
Managing travel demand
Programme Elements Details
Ngauranga to Aotea Quay widening (if included)
Terrace Tunnel to Te Aro (if included)
Improving the Basin
Mt Vic Tunnel and Ruahine Street
Regional highway access
Technical leadership
and review
Urban development and design
Modelling and monitoring
Programme Coordination and Delivery Sequencing, system transformation, system performance, business case integration and benefits realisation
Communications and engagement
Mass Transit / Public
Transport system
Regional highway access
Re-configure
urban corridors
Managing travel
demand
Early delivery
PART C – Preferred Way Forward: Management Case
Let’s Get Wellington Moving Programme Business Case – Draft Released 21 June 2019 107
17.3. Programme Monitoring and Reviews
There are several reasons for a robust monitoring plan14 that is updated as LGWM progresses. A
monitoring plan can be used:
As a basis for post implementation tracking of success, which can importantly generate
lessons for other projects
To create awareness of potential effects of the programme that may be influenced
To inform trigger points and decisions during programme implementation
As a basis for other investment and management decisions, such as enabling the DTST to
affect behaviour change through temporary interventions.
Several measures are suggested for monitoring in addition to the programme KPIs as part of the
monitoring plan shown in Appendix M. It is worth noting that these measures will need refinement
moving forward, particularly as more detailed investigation improves understanding of forecast
impacts.
17.3.1. Measures Identified
Measures that are identified for annual monitoring to keep awareness of unintended outcomes
include:
Transport CO2 Emissions in Central City
System Occupancy (including movement into the central city, mode split, and vehicle
occupancy)
Pedestrian signalised crossing delays on key routes
Network catchment (average travel times) and travel time reliability on key routes
Total deaths and serious injuries, and pedestrian and cyclist representation, in a local,
regional, and national context
Expand the temporal scope of the cordon survey to improve understanding of movement for
non-commuting purposes
Traffic Noise on streets identified for high pedestrian amenity, potentially predictive through
use of the NZ Transport Agency traffic noise calculator
Economist Intelligence Unit Global Liveability Survey – particularly scoring of Quality of Road
Network and Quality of Public Transport – to help understand consequences on larger picture
perception
Air quality and concentration of non-CO2 emissions – particulates, NO2
Lane availability reductions due to unplanned events (potentially expand the geographic
scope beyond the State Highway to record some of the key local arterials
Measures that are identified for annual monitoring to inform implementation and sequencing
decisions include:
System Occupancy (including movement into the central city, mode split, and vehicle
occupancy)
Network catchment (average travel times) and travel time reliability on key routes
14
Note that monitoring referred to in this section is separate from monitoring that is planned and undertaken under the Resource Management Act and consenting processes.
PART C – Preferred Way Forward: Management Case
Let’s Get Wellington Moving Programme Business Case – Draft Released 21 June 2019 108
Growth in population and employment
Qualitative understanding of market demand for higher density housing within the city,
underpinned by quantitative monitoring of residential completions by type, development
trends, and housing affordability already undertaken by WCC.
Measures that are identified for post implementation monitoring include:
Amenity Index on key corridors
Transport CO2 Emissions in Central City
System Occupancy (including movement into the central city, mode split, and vehicle
occupancy)
Pedestrian signalised crossing delays on key routes
Cycling level of service on key routes
Network catchment (average travel times) and travel time reliability on key routes
Pedestrian and cyclist deaths and serious injuries
Qualitative assessment of resilience to large scale hazard events.
Some other specific uses of measures include:
Continually update the resilience measure as part of the investigation and detailed design
processes. Assess how any interventions performed following any large events that occur
Use the cycling level of service assessment and amenity assessment as a tool to help guide
design considerations.
17.3.2. Next Steps and Ownership
It is suggested that the LGWM delivery vehicle is charged, not only with delivering the programme,
but also undertaking programme monitoring with support from the partner agencies.
Most of the detailed monitoring will be undertaken as part of existing commitments by the LGWM
partner agencies. New monitoring systems will need to be established for:
Potential adjustments to the existing WCC cordon counts, particularly expanding hours of
operation to include weekend and shoulder peak periods
Lane availability monitoring for identified key local roads to supplement State Highway 1
reporting – to be established as part of early improvements or transition to integrated
transport operating system business cases.
Business case phases subsequent to this PBC will need to integrate monitoring at a programme-
element level with programme-wide monitoring and ensure appropriate targets and means of
monitoring are put in place. As detailed understanding of programme elements is developed through
these business cases, there may also be a need to update the programme-level outcome targets.
PART C – Preferred Way Forward: Management Case
Let’s Get Wellington Moving Programme Business Case – Draft Released 21 June 2019 109
17.4. Programme Funding
As mentioned in Section 16.1.1 the Minister of Transport has expressed an intention for how the
programme might be funded and financed. This high-level funding still requires agreement from WCC,
GWRC, and the NZ Transport Agency.
In addition, there is a need to understand and agree how funding splits might vary between different
programme elements, between different programme stages, and reflect the different funding sources
and funding nature for the three programme partners. This work is currently ongoing.
17.5. Risks and Uncertainties
The key risks identified at this stage of the programme’s development are summarised in Table 27
below.
Table 27 Risks, potential consequences, and management strategy
RISK TYPE POTENTIAL CONSEQUENCES MANAGEMENT STRATEGY
The growth in regional population and employment may be lower or higher than forecast
The distribution of growth between the central city and the rest of the region may be different to that forecast
As the growth forecasts are the key drivers of transport demand, the need for changes to the transport system may be less urgent or more urgent than currently forecast
A wide range of growth forecasts is being assumed so as to ensure there is a high probability that the actual growth will be within the range
Precise sequencing for several elements of the RPI will be informed by monitoring
The modal preferences of customers may be changing due to economic, social or technological changes
The transport modelling carried out to date may be over-estimating or under-estimating the demand for travel by private vehicles in relation to travel by other modes
Precise sequencing for several elements of the RPI will be informed by monitoring
Funding priorities of central and local government may change over time
The RPI may not reflect funding priorities, and the programme may not deliver anticipated benefits if only partially implemented
The RPI has been developed to be flexible to funding priorities
Precise sequencing for several elements of the RPI will be informed by monitoring
The RPI will draw substantial funding from a number of sources, and some of these may not eventuate e.g. economic downturn
Parts of the RPI may not receive funding, and the programme may not deliver anticipated benefits if only partially implemented
Ongoing collaborative and integrated business case development, design, consenting and implementation
The RPI has been developed to be flexible to funding availability
Major infrastructure elements within the programme will have long lead times for planning and consenting processes
Wellington City may fall behind other competitor cities as a result of the transport system not addressing the problems or facilitating the opportunities in a timely manner
Using a programme business case in which all agencies are well coordinated should speed up any pre-construction phases and reduce the overall time needed to implement the investment programme
Ongoing collaborative and integrated business case development, design, consenting and implementation
PART C – Preferred Way Forward: Management Case
Let’s Get Wellington Moving Programme Business Case – Draft Released 21 June 2019 110
Forecasting for large scale natural hazard events is an uncertain process
Investment in transport system resilience may prove to be insufficient to facilitate timely recovery following a larger than anticipated event
Investment in transport system resilience may prove to be unnecessary if an event does not occur
Align with ongoing resiliency planning within the region, including exploring appetite for risk
The RPI assumes complementary land use planning changes e.g. district plan changes which may not eventuate
The opportunity to leverage investment in the transport system to facilitate urban development will be lost
The RPI may not represent a value for money investment if it does not facilitate urban generation in the central city and Newtown
Decision points prior to implementation of major infrastructure that will reflect monitoring of land use policy
Ongoing collaborative and integrated business case development, design, consenting and implementation
Risk that investment will not be integrated with shift in transport system from technological advances
Potential to reinforce Wellington’s technological and innovative reputation is lost
Introducing unproven systems may result in sub-optimal outcomes or abortive investment
Staying flexible in reviewing the programme to incorporate changing technologies when they are judged to be sufficiently mature
A lack of integrated implementation e.g. resulting from opposition to potential intervention impacts
Key elements of the programme may be put on hold, undermining the effectiveness of the programme as a whole
Ongoing collaborative and integrated business case development, design, consenting and implementation
Ongoing engagement and consultation with the public and stakeholders
Resource and/or funding constraints may result in programme elements being delayed/deferred
Delaying elements of the programme may make it difficult or impossible to satisfactorily manage disruption to the transport system during construction phases (e.g. closure of lanes to allow mass transit infrastructure construction)
High priority given to maintaining transport system performance through early design of transport system transformation programme element
There may be pressures to change the balance of central and local government funding arrangements over the implementation of the RPI
Key elements of the programme may not be implemented, undermining the effectiveness of the programme as a whole
Build a high level of support for the programme at local, regional and central government levels
Significant cost of RPI may preclude other transport investments in region
The Wellington region has a limited ability to invest in transport projects outside of LGWM
The RPI has been developed to be flexible to changing transport demand
In announcing LGWM the Minister of Transport has also indicated that there are available funds for other projects in the region.
Actual project costs become greater than those forecast and exceed allocated budgets
Several risks could cause project costs to escalate in unforeseen/unaccounted for ways e.g. complex geotechnical conditions
Undertake robust risk identification as part of cost estimation during business case phases
Use of risk adjusted forecasting as part of budgeting processes
PART C – Preferred Way Forward: Commercial Case
Let’s Get Wellington Moving Programme Business Case – Draft Released 21 June 2019 111
18. COMMERCIAL CASE Given the scale of LGWM, consideration of commercial implications will be critical as the programme
moves closer to implementation.
The capacity and capability of industry, both professional services and physical works contractors, will
be a significant consideration. There may be a need to take a national and potentially international
view as business case development progresses. One example would be opportunities to align with
other mass transit projects around New Zealand, potentially creating physical works and cash-flow
efficiencies through national coordination.
In the more immediate term, there are several risks associated with professional services availability
and potential for stakeholder fatigue that may result in a need to stagger business case processes
with suitable hold points so that interdependencies can be understood.
There are several procurement and financing opportunities presented by the programme. For
example, a procurement approach for mass transit may be to adopt an outcome based public private
partnership arrangement whereby different tenderers offer different mass transit modes.
Let’s Get Wellington Moving Programme Business Case – Draft Released 21 June 2019
APPENDIX A – STRATEGIC ALIGNMENT
Let’s Get Wellington Moving Programme Business Case – Draft Released 21 June 2019
APPENDIX B – INVESTMENT LOGIC MAP
Let’s Get Wellington Moving Programme Business Case – Draft Released 21 June 2019
APPENDIX C – INVESTMENT OBJECTIVE KPIS AND RPI ASSESSMENT
Let’s Get Wellington Moving Programme Business Case – Draft Released 21 June 2019
APPENDIX D – NOTE 1: INTERVENTION LONGLIST SCREEN
Let’s Get Wellington Moving Programme Business Case – Draft Released 21 June 2019
APPENDIX E – NOTE 2: SCENARIO LONGLIST DEVELOPMENT
Let’s Get Wellington Moving Programme Business Case – Draft Released 21 June 2019
APPENDIX F – LONGLIST SCENARIOS MULTI-CRITERIA ANALYSIS REPORT
Let’s Get Wellington Moving Programme Business Case – Draft Released 21 June 2019
APPENDIX G – ENGAGEMENT SCENARIOS TECHNICAL SPECIALIST ASSESSMENT
Let’s Get Wellington Moving Programme Business Case – Draft Released 21 June 2019
APPENDIX H – LONGLIST PROGRAMME ASSESSMENT WORKSHOP NOTES
Let’s Get Wellington Moving Programme Business Case – Draft Released 21 June 2019
APPENDIX I – SHORTLIST PROGRAMME OPTIONS WORKSHOP NOTES
Let’s Get Wellington Moving Programme Business Case – Draft Released 21 June 2019
APPENDIX J – COST REPORT
Let’s Get Wellington Moving Programme Business Case – Draft Released 21 June 2019
APPENDIX K – ECONOMICS REPORT
Let’s Get Wellington Moving Programme Business Case – Draft Released 21 June 2019
APPENDIX L – INVESTMENT ASSESSMENT FRAMEWORK ASSESSMENT
Let’s Get Wellington Moving Programme Business Case – Draft Released 21 June 2019
APPENDIX M – MONITORING PLAN
Let’s Get Wellington Moving Programme Business Case – Draft Released 21 June 2019
APPENDIX N – TECHNICAL DOCUMENTS