Banekonferencen 2015 Integration of ETCS in the Danish fleet Agenda: o Signalling Programme overview o Scope of the onboard project o Survey process o Fitment process o Main challenges o Lessons learned 2015
15

Programme Board Theme meeting 3 with DSB

Feb 14, 2017

Download

Documents

phungquynh
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Programme Board Theme meeting 3 with DSB

Banekonferencen 2015

Integration of ETCS in the Danish fleet

Agenda:

o Signalling Programme overview

o Scope of the onboard project

o Survey process

o Fitment process

o Main challenges

o Lessons learned

2015

Page 2: Programme Board Theme meeting 3 with DSB

Signalling programme overview

o S-bane (technology)

o TCC (Civil Works)

o Training

o Operational Rules

o GSM-R Voice

o Fjernbane infrastructure East

o Fjernbane infrastructure West

o Onboard

o STM

o Fjernbane IT

o GSM-R Voice & Data

o TCC (Civil Works)

o Training

o Operational Rules

2

S-bane Railway Fjernbane Railway

Page 3: Programme Board Theme meeting 3 with DSB

Banekonferencen 2015

Integration of ETCS in the Danish fleet

Agenda:

o Signalling Programme overview

o Scope of the onboard project

o Survey process

o Fitment process

o Main challenges

o Lessons learned

2015

Page 4: Programme Board Theme meeting 3 with DSB

Banekonferencen 2015

Scope of the onboard project

4

671 Passenger and Freight Trains 21 First of Class

89 Yellow Machines 21 First of Class

Banekonferencen 2015

Page 5: Programme Board Theme meeting 3 with DSB

Banekonferencen 2015 5

Scope of the onboard project

– Design:

o Implement ERTMS Baseline 3

o Integration of DK- and SE-STM

o Installation design for 42 First Of Class

o Training tools (Driving Simulator)

– Installation, test and approval for about 750 trains:

o Installation

o Lab tests, site tests (test trains, FoC, series)

o Safety and interoperability approvals

– Training: train the trainers or direct training

– Decommissioning of ATC and STM

– Maintenance

Banekonferencen 2015

Page 6: Programme Board Theme meeting 3 with DSB

Scope Contract structure

6 Banekonferencen 2015

• Operators with public traffic agreement

- Compensated

- Banedanmark owns the equipment

Supplier

RU’s Operators

BDK Signalling

Programme

Contract Subcontracts

Back to Back

Agreement

Rental Agreement

• Others

- Not Compensated

- Own their own equipment

•Equipment delivery

•Installation and Test of

Rollout trains (including

approvals)

•Decommissioning of

STM

•Actual training

•Maintenance, spare parts

•Generic Design

•Installation and Test

of FoC trains

(including approvals)

•Training concepts

and tools

•System Tests

•Safety Approvals

•Software

maintenance

Page 7: Programme Board Theme meeting 3 with DSB

Banekonferencen 2015

Integration of ETCS in the Danish fleet

Agenda:

o Signalling Programme overview

o Scope of the onboard project

o Survey process

o Fitment process

o Main challenges

o Lessons learned

2015

Page 8: Programme Board Theme meeting 3 with DSB

Banekonferencen 2015

Overall design process

Light Survey

Detailed Survey

Draft FoC

Design

FoC Designed Approved

Decide preliminary

location of equipment

Confirm location

of equipment +

Engineer the

detailed design

(cable paths…etc.)

Review by BDK and

Operators

Banekonferencen 2015

Page 9: Programme Board Theme meeting 3 with DSB

Banekonferencen 2015

Survey process

9

Documentation Survey Installation

design

RFI process

Documentation review

Expert meetings

Survey planning

Train variance

Components locations

3D scanning

Installation constraints

Train interfaces

Survey report

Mechanical design

Electrical design

Variance meetings

Hot spot approach

RU/BDK review

Design freeze

Banekonferencen 2015

Page 10: Programme Board Theme meeting 3 with DSB

Banekonferencen 2015

Integration of ETCS in the Danish fleet

Agenda:

o Signalling Programme overview

o Scope of the onboard project

o Survey process

o Fitment process

o Main challenges

o Lessons learned

2015

Page 11: Programme Board Theme meeting 3 with DSB

Banekonferencen 2015

Fitment process

11

Train handover to

Alstom Installation

Test & commissioning

Train Handback to

RU

HO protocol

Location check

Function check

Installation procedure

RU inspection

T&C procedure

RU witnessing

HB protocol

”HO + ETCS”

Banekonferencen 2015

Page 12: Programme Board Theme meeting 3 with DSB

Banekonferencen 2015

Integration of ETCS in the Danish fleet

Agenda:

o Signalling Programme overview

o Scope of the onboard project

o Survey process

o Fitment process

o Main challenges

o Lessons learned

2015

Page 13: Programme Board Theme meeting 3 with DSB

13

Main challenges and lessons learned

What did BDK buy?

0 % 100 %

-------------------------------------------------------------

Generic ETCS solution RU/litra optimisation

”One size fits all” Respecting train philosophy

Efficient roll out Less efficient roll out

Lessons learned:

Aligning of expectations

Common understanding of funding

”Adaptation scale challenge”

Page 14: Programme Board Theme meeting 3 with DSB

Banekonferencen 2015

Main challenges and lessons learned

Challenges

– ”3 part” project

– Diversity of the Danish fleet

– Non compensated RU’s

– Train documentation

– Train variance

Lessons learned

– Align on scope and expectations

– RU involvement

– F2F meetings

– Use of 3D scans

– Business culture http://geert-hofstede.com

14 Banekonferencen 2015