LABOR PRODUCTION TABLE ITEM NO. WORK DESCRIPTION .H./ UNIT MANHOURS LOW A. FORM WORKS INSTALLATION WALL ON THE GROUND SQ.M. 4.00 WALL ABOVER GROUND SQ.M. 4.70 BEAMS SQ.M. 6.16 COLUMN SQ.M. 4.70 SUSPENDED SLAB 0 TO 18' SQ.M. 3.34 18' TO 36' UP SQ.M. 6.66 ELEVATED AND SHORED SLAB FORMING FORMING ONLY SQ.M. 17.20 FORMING AND SHORING SQ.M. 22.00 WOOD WALL AND PARTITION SQ.M. 1.00 B. FORMWORKS FABRICATION SQ.M. 2.15 C. STRIPPING OF FORMS WALL ON GROUND SQ.M. 0.50 WALL ABOVE 10' SQ.M. 2.58 BEAMS SQ.M. 2.06 COLUMNS SQ.M. 1.70 SUSPENDED SLAB SQ.M. 0 TO 18' SQ.M. 1.67 18' TO 36' UP SQ.M. 2.16 ELEVATED AND SHORED SLAB FORMING SQ.M. STRIP OF FORMS SQ.M. 7.00 FLOOR SLAB AT GRADE STRIP OF FORMS SQ.M. 5.60 D INSTALLION OF CARPENTRY WORKS PLYWOOD PARTITION PC 2.00 T & G FLOORING AND SHORING B.F. 0.29 CEILING FRAME B.F. 0.30 SIDING FRAME B.F. 0.53 FLOORING FRAME B.F. 1.94 WOODEN POSS ERECTION B.F. 0.85 TRUSS FABRICATION B.F. 0.70 TRUSS INSTALLATION B.F. 1.60 GIRTS INSTALLTION B.F. 0.43 PLATES INSTALLATION B.F. 0.27 PURLINS INSTALLATION B.F. 0.53 FASCIA BOARD INSTALLATION B.F. 0.91 1/4" or 3/4" thk PLYWOOD CUTTING BY MANUAL PC 2.00 ASSEMBLY S.F. 0.83 CEILNG:
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
LABOR PRODUCTION TABLE
ITEM NO. WORK DESCRIPTION M.H./ UNITMANHOURS PER QUANTITY (M.H./UNIT)
LOW
A. FORM WORKS INSTALLATIONWALL ON THE GROUND SQ.M. 4.00 WALL ABOVER GROUND SQ.M. 4.70 BEAMS SQ.M. 6.16 COLUMN SQ.M. 4.70 SUSPENDED SLAB0 TO 18' SQ.M. 3.34 18' TO 36' UP SQ.M. 6.66 ELEVATED AND SHORED SLAB FORMINGFORMING ONLY SQ.M. 17.20 FORMING AND SHORING SQ.M. 22.00 WOOD WALL AND PARTITION SQ.M. 1.00
B. FORMWORKS FABRICATION SQ.M. 2.15
C. STRIPPING OF FORMSWALL ON GROUND SQ.M. 0.50 WALL ABOVE 10' SQ.M. 2.58 BEAMS SQ.M. 2.06 COLUMNS SQ.M. 1.70 SUSPENDED SLAB SQ.M.0 TO 18' SQ.M. 1.67 18' TO 36' UP SQ.M. 2.16 ELEVATED AND SHORED SLAB FORMING SQ.M.STRIP OF FORMS SQ.M. 7.00 FLOOR SLAB AT GRADE STRIP OF FORMS SQ.M. 5.60
D INSTALLION OF CARPENTRY WORKSPLYWOOD PARTITION PC 2.00 T & G FLOORING AND SHORING B.F. 0.29 CEILING FRAME B.F. 0.30 SIDING FRAME B.F. 0.53 FLOORING FRAME B.F. 1.94 WOODEN POSS ERECTION B.F. 0.85 TRUSS FABRICATION B.F. 0.70 TRUSS INSTALLATION B.F. 1.60 GIRTS INSTALLTION B.F. 0.43 PLATES INSTALLATION B.F. 0.27 PURLINS INSTALLATION B.F. 0.53 FASCIA BOARD INSTALLATION B.F. 0.91 1/4" or 3/4" thk PLYWOODCUTTING BY MANUAL PC 2.00 ASSEMBLY S.F. 0.83 CEILNG:
E. DOORS AND WINDOWSW-PANEL INSTALLATION PC. 0.80 STEEL WINDOWS INSTALLATION PC. 4.00 LOUVER WINDOWS INSTALLATION:FIXED ASBESTOS SQ.M. 9.26 FIXED METAL LOUVERS SQ.M. 6.24 FIXED GI SHEETS SQ.M. 9.26 FIXED GLASS SQ.M. 6.34 FIXED WOODEN SQ.M. 6.76 ALUMINUM FRAME WINDOWS EACH 20.00 SLIDING GLASS DOOR EACH 24.00 HOLLOW METAL DOOR EACH 20.00 ROLLING DOORS EACH 50.00 FIXED WINDOW S.F. 0.63 DOOR LOCKSET SET 3.20 DOOR JAMB FABRICATION B.F. 0.44 DOOR JAMB INSTALLATION B.F. 0.66 CYCLONE WIRE INSTALLATION SQ.M. 6.24
LAVATORY EACH 16.00 WATER CLOSET EACH 24.00 URINAL UTILITY STALL EACH 48.00 URINAL PEDESTRAL TYPE EACH 32.00 SHOWER AND INSTALL EACH 20.00 5 MAN GROUP SHOWER EACH 72.00 BAH TUBS EACH 48.00 SLOPE SINK EACH 28.00 HOT WATER HEATER EACH 28.00 16 PERSON WASH SINK EACH 52.00 DRINKING FOUNTAIN EACH 26.00 EYE WASH EACH 16.00 MISC. FIXTURES EACH 4.00 PARTITIONS EACH 16.00 LAYING OF 24"Ø RCP PIPE 8.00 LAYING OF 36"Ø RCP PIPE 12.80 LAYING OF 48"Ø RCP PIPE 21.32
L. TRADE INSULATIONEQUIPMENT INSTALLATIONVESSEL, EXCHANGE & TANKSFIELD FABRICATION INSULATION S.M. 5.00 FIELD FABRICATION SHEET METAL COVER S.M. 24.00 APPLY INSULATION S.M. 10.00 APPLY SHEET METAL COVER S.M. 10.00 PUMPS, COMPRESSORS & TURBINESFABRICATE S.M. 34.00 APPLY S.M. 60.00 PIPINGS AND COMPONENT INSULATIONFIELD FABRICATE FLG. 8.00 FIELD FABRICATESHEET METAL COVER S.M. 1.60 APPLY INSULATION L.M. 5.40 APPLY SHEET METAL COVER OR METAL COVER EACH 3.00 FABRICATE INSTRUMENT COVER EACH 16.00 INSTALL INSTRUMENT COVER EACH 12.00 INSULATE PIPE HANGERS EACH 8.00 FOR STREAM TRACED LINES L.M. 7.40 REMOVAL OF OLD OR EXISTING INSTALLATION L.M. 3.00
M. TRADE:FIRE PROOFINGINSTALL STUDS EACH 1.00 INSTALL MESH S.M. 2.40
POUREDFORMING S.M. 28.00 STRIP FORMS S.M. 12.00 POUR CONCRETE S.M. 140.00 CURING/PATCHING S.M. 1.20 FINISHING S.M. 1.40 TROWEL, PLASTERED S.M. 5.40 PNEUMATIC APPLICATIONGUNITE S.M. 2.40 APPLY FINEBRICK OR BLOCK PC. 1.60 REMOVAL OF EXISTING OR OLD FIREPROOFING S.M. 5.00 APPLY FIREPROOFING PAINT S.M. 6.00 FIRE PROTERCTION:FIRE PROTECTION EQUIPMENT INSTALLATION:MONITOR EACH 10.00 HOSE REELS AND CARTS EACH 30.00 FIRE EXTINGUISHERS EACH 10.00 PERSONAL EQUIPMENT:EYE WASH EACH 20.00 SAFETY SHOWERS EACH 20.00 BREATHING APPARATUS EACH 10.00 SPRINKLER SYSTEMSPRAY NOZZLES EACH 2.00 WATER CANNONS EACH 10.00
N. TRADE:PERMANENT FENCINGINSTALL FENCE L.M. 2.40 INSTALL GATES L.M. 6.00 TO RAIL L.M. 0.60 BARBE WIRE, 3 STRANDS L.M. 0.60
O. TRADE:PAINTING WORKSNEW STRUCTURAL STEEL TON 20.00 OLD STRUCTURAL STEEL S.M. 1.10 NEW FLAT FLAT PLATES S.M. 0.64 SURFACE PREPARATION:IN TERMS OF WEIGHT TON 16.00 IN TERMS OF AREA S.M. 0.86 SAND PREPARATION TON 60.00
P. TRADE:HEATING VENTILATING AND CONDITIONINGHEAVY PIPING L.M. 7.00 DUCT WORK INSTALL S.M. 12.00 DUCT WORK FAB. S.M. 36.00 PACKAGE UNIT AIR CONDITIONER EACH 48.00 UNIT HEATER EACH 24.00 FINNED CONVERTER EACH 10.00 EXHAUST FAN PROPELLER EACH 16.00 GRAVITY ROOF PAINT L.M. 14.00 POWER ROOF VENT EACH 48.00 ROUND ROOF VENT EACH 16.00
PLUMBING PIPING L.M. 7.00
Q. MISCELLANEOUSWATER STOP INSTALLATION L.M. 1.34 CAULKING SLAB JOINT L.M. 0.40 ASPHALTING S.M. 1.60 GROUTNG AND TOOL PLASTERING S.M. 3.34 WATER PROOFING RUBBERIZED S.M. 1.10 COPPER CLADDING ROOF DECK L.M. 1.00 WATER PROOFING FLINKOTE S.M. 0.54 DEMOLITION OF ADOBE WALL CU.M. 3.20 PAINTING S.M. 0.68 COPPER WATER STOP CUT AND SHAPE L.M. 11.00 COPPER WATER STOP CUT AND INSTALLATION L.M. 22.00 SETTING ANCHOR BOLT KG 97.00 SETTING ANCHOR BOXES CU.M. 3.64