Top Banner
Managing time ‘Time is nature’s way of stopping everything happening at once’ Hughes & Cotterell 2002 Production Process
25

Production Process

Jan 03, 2016

Download

Documents

ivor-cervantes

Managing time ‘Time is nature’s way of stopping everything happening at once’ Hughes & Cotterell 2002. Production Process. Lecture content. Recap on last week Scheduling What is Critical Path Analysis? Why use CPA? Problems associated with CPA How to perform CPA. Recap on last week. - PowerPoint PPT Presentation
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Production Process

Managing time

‘Time is nature’s way of stopping everything happening at once’

Hughes & Cotterell 2002

Production Process

Page 2: Production Process

Lecture content

Recap on last week Scheduling What is Critical Path Analysis?

– Why use CPA?– Problems associated with CPA– How to perform CPA

Page 3: Production Process

Recap on last week

Stakeholders Identifying the goals of the project Defining tasks

– Activity based approach– Product based approach– Hybrid approach

Page 4: Production Process

Scheduling

Scheduling is the process of assigning tasks to a set of resources.

It is an important concept in many areas such as computing and production processes.

In mathematical terms, a scheduling problem is often solved as an optimisation problem, with the objective of maximising a measure of schedule quality.

Page 5: Production Process

Scheduling

Forward scheduling

planning the tasks from the start date.

Reverse scheduling

planning the tasks from the due date.

Page 6: Production Process

CPA & PERT

Critical Path Analysis and PERT are powerful tools that help you to schedule and manage complex projects.

Developed in the 1950s to control large defense projects.

Have been used routinely since then.

Page 7: Production Process

Why use CPA?

Shows the sequence of activities Shows dependencies Aids scheduling resources & financial

planning Used as a basis of control Diagrammatic therefore easier to read

Page 8: Production Process

What is Critical Path Analysis?

1. Using intertask dependencies, determine every possible path through the project.

2. For each path, sum the durations of all tasks in the path.

3. The path with the longest total duration is the critical path.

Page 9: Production Process

Problems associated with CPA

Pay too much attention to critical path Experience needed to gauge durations Difficulties in separating tasks Only deals with numbers Doesn’t guarantee good project

management, nothing does!!!

Page 10: Production Process

Start & Finish times

Activity = a task or action with a recognisable start/finish time e.g. ‘write report software’

Earliest start (ES) Earliest finish (EF) = ES + duration Latest finish (LF) = latest task can be completed without

affecting project end Latest start = LF – duration

Earliest startLatestfinish

Earliest finishLatest start

activity

Page 11: Production Process

Example

Earliest start = 5 days Latest finish = day 30 Duration = 10 days

Float = LF-ES-Duration

Earliest finish =? Latest start = ?

Float = ?

The total float of an activity is the amount of time by which the task may be extended or delayed without delaying completion of the project.

Page 12: Production Process

Notation

Activity description

Activity label duration

ES

LS

EF

LF

Activity span Float

Page 13: Production Process

Earliest start time/date

Earliest start date for the current activity = earliest finish date for the previous

When there is more than one previous activity, take the latest earliest finish

Note ‘day 7’ = end of work on day 7

Page 14: Production Process

Example

EF = day 7

EF = day10

ES = day 10

Page 15: Production Process

What is the ES for G?

A

B

C

D

F

E

G

ES = day 0

Duration 5

Duration 6

Duration 10

Duration 9

Duration 8

Duration 3

Duration 4

Page 16: Production Process

Complete the table

Activity ES duration EFABCDEFG

Page 17: Production Process

Latest start date

Start from the last activity Latest finish (LF) for last activity = earliest finish (EF) work backwards Latest finish for current activity = Latest start for the

following More than one following activity - take the earliest LS Latest start (LS) = LF for activity - duration

Page 18: Production Process

LS for all activities?

A

B

C

D

F

E

G

ES = day 0

Duration 5

Duration 6

Duration 10

Duration 9

Duration 8

Duration 3

Duration 4

Page 19: Production Process

Complete the table

Activity ES Dur EF LS LFABCDEFG

Page 20: Production Process

Now add the float!

Act-ivity

ES Dur EF LS LF Float

ABCDEFG

Page 21: Production Process

Answer

Page 22: Production Process

Find the Critical path

Note the path through network with zero floats

Critical path: any delay in an activity on this path will delay whole project

Can there be more than one critical path? Can there be no critical path? Sub-critical paths

Page 23: Production Process

Estimating task duration

1. minimum amount of time it would take to perform the task = optimistic duration (OD).

2. maximum amount of time = pessimistic duration (PD).

3. expected duration (ED) 4. Calculate the most likely duration (D) as follows:

D = (1 x OD) + (4 x ED) + (1 x PD) 6

Page 24: Production Process

Something to think about…

Can we truly say that by adding more human resource to a project it will reduce the time it takes to perform the task?

Page 25: Production Process

Further Reading

http://www.mindtools.com/pages/article/newPPM_04.htm

http://www.mis.coventry.ac.uk/~nhunt/cpa/listof.htm

http://www.waa-inc.com/projex/PERT/cpa.htm

http://www.gamedev.net/reference/business/features/criticalpath/default.asp