ABSTRACT This study focused on public procurement system and management of public funds, a case
study of Gisagra district. The different reports show that the public institutions in Gisagara
district did not perform well because many of them did not explain how they used funds,
and others did not follow the regulations on the use of money. Moreover, reports also
revealed that donors took back a lot of money intended for development because of the
ineffectiveness of beneficiaries to use them appropriately while ensuring authentic
accountability. It is therefore within these gaps that this study aims to investigate into the
extent of effectiveness of procurement system and public funds management in Rwanda.
The main objective of this study is to assess the correlation between public procurement
and management of public fund in Rwanda.. The specific objectives are to assess the public
procurement process in Gisagara District; to evaluate the Public Procurement techniques
used in Gisagrara (2010-2013) to manage public fund; to establish the relationship between
public procurement assessment and management of public fund. This study should benefit
by researcher and public institutions. This research was designed both quantitatively and
qualitatively; both descriptive and correlational statistics were used. It used questionnaires
to collect primary data and documentary technique to collect secondary data. The Target
population was190 employees of Gisagara District and 30 contactors. The Sample Size was
composed of 86 employees and 30 contractors. The purposive sampling technique was
utilized to select the respondents. After data collection, the data was analyzed used SPSS
program. Concerning the first research objective, the Public Procurement methods used in
Gisagrara (2010-2013) to manage public fund, out of 86 respondents, 68 (79.1%) strongly
agreed that requirement identification is the factors influence public procurement process
in Gisagara District and 18 (i.e 20.9%) agreed that requirement identification is one of the
factors influence public procurement process in Gisagara District. Concerning the second
research objective, the factors influence public procurement process in Gisagara District,
out of 86 respondents, 73 (i.e 84.9%) of respondents strongly agreed that National
Competitive Bidding (NCB) is one of the Public Procurement methods used in Gisagrara
to manage public fund. Concerning the third objective, challenges faced by contactors in
Gisagra District, out of 30 respondents, 23 respondents (i.e76.7%) strongly agreed delay
of payment is among of the challenges faced by contractors in Gisagra District. This
research used Pearson correlation coefficient and found that correlation coefficient (r)
equals to 0.565 i.e 56.5%. Therefore, there is a positive relationship between procurement
system and public funds management. Regarding lower managerial skills of some Gisagara
District employees, the researcher recommends that Gisagara District should improve
mobilization in the field of managerial skills and competitive tendering, whereby these
should leads to the increase in competition.
Page 2
ii
TABLE OF CONTENTS
ABSTRACT ............................................................................................................................................ i
TABLE OF CONTENTS ....................................................................................................................... ii
LIST OF TABLES ................................................................................................................................ iv
LIST OF FIGURES ................................................................................................................................ v
LIST OF ABREVIATIONS AND ACRONYMS ................................................................................. vi
DEFINITIONS OF KEY TERMS ....................................................................................................... vii
CHAPTER ONE: INTRODUCTION .................................................................................................... 1
1.0 Introduction .................................................................................................................................. 1
1.1 Background of the Study ........................................................................................................ 1
1.2 Statement of the Problem ............................................................................................................. 2
1.3 Objectives of the Study ................................................................................................................ 2
1.4 Research Questions ...................................................................................................................... 3
1.5 Significance of the Study.............................................................................................................. 3
1.6 Limitations .................................................................................................................................... 3
1.7. Scope of the Study ....................................................................................................................... 4
1.8 Organization of the Study ............................................................................................................. 4
CHAPTER TWO: REVIEW OF RELATED LITERATURE ............................................................... 4
2.0 Introduction .................................................................................................................................. 4
2.1 Theoretical Literature ................................................................................................................... 5
2.1.1 Overview of Procurement .......................................................................................................... 5
2.1.2 Types of public Procurement ..................................................................................................... 6
2.1.3 The Public Procurement Process ............................................................................................... 6
2.1.4 How to Improve Procurement Function .................................................................................. 11
2.1.5 Overview of Management Of Public Fund.............................................................................. 11
2.1.6 Methods for Procurement of Goods and Services ................................................................... 12
2.1.7 Importance of Public Procurement in Public Fund Management ............................................ 14
2.2 Empirical Literature.................................................................................................................... 15
2.3. Critical Review and Research Gap Identification ..................................................................... 17
2.4 Conceptual Framework .............................................................................................................. 18
Page 3
iii
2.5. Summary ................................................................................................................................... 18
CHAPTER THREE: RESEARCHMETHODOLOGY ........................................................................ 19
3.0 Introduction ................................................................................................................................ 19
3.1. Research Design ........................................................................................................................ 19
3.2 Target Population ....................................................................................................................... 19
3.3 Sample Design ............................................................................................................................ 19
3.4 Data collection Methods ............................................................................................................. 20
3.4.3 Validity And Reliability .......................................................................................................... 21
3.5 Data Analysis Methods............................................................................................................... 21
3.6 Ethical Consideration ................................................................................................................. 21
CHAPTER FOUR: RESEARCH FINDINGS AND DISCUSION ...................................................... 22
4.0 Introduction ................................................................................................................................ 22
4.1 Demographic Characteristics of Respondents ............................................................................ 22
4.2 Presentation of Findings ............................................................................................................. 24
4.2.1 The Factors Influence Public Procurement process in Gisagara District ................................ 24
4.2.2 The Public Procurement Methods Used in Gisagrara to Manage Public Fund ....................... 28
4.3 Perception of Contractors On Competitive Tendering And Challenges Faced .......................... 34
4.3.2 Challenges Faced By Contactors in Gisagra District .............................................................. 34
4.3.3 Relationship Between Procurement System and Public Funds Management ......................... 38
CHAPTER FIVE: SUMMARY, CONCLUSIONS AND RECOMMENDATIONS ...................... 39
5.0 Introduction ................................................................................................................................ 39
5.1 Summary of Findings ........................................................................................................... 39
5.1.1 The Public Procurement Methods Used In Gisagrara (2010-2013) to Manage Public Fund
40
5.1.2 The Factors Influence Public Procurement Process in Gisagara District ................................ 40
5.1.3 Challenges Faced By Contactors in Gisagra District .............................................................. 41
5.1.4 The Relationship Between Public Procurement And Management Of Public Fund ............. 41
5.2 Conclusions .......................................................................................................................... 42
5.3 Recommendations ...................................................................................................................... 43
5.4 Suggestions for Further Study .................................................................................................... 44
REFERENCES ..................................................................................................................................... 44
QUESTIONNAIRE ................................................................................................................................ a
Page 4
iv
LIST OF TABLES Table 3.1: Target population and sample size determination ................................................. 20
Table 4.2: Distribution of respondents by level of education ................................................. 22
Table 4.3: Distribution of respondents by Job experience ...................................................... 23
Table 4.4: Distribution of respondents by occupation ............................................................ 23
Table 4.5:Procurement planning ............................................................................................. 25
Table 4.6: Solicitation document ............................................................................................ 25
Table 4.7:Pre-bid..................................................................................................................... 26
Table 4.8: Submission of bids ................................................................................................. 26
Table 4.9: Publication ............................................................................................................. 26
Table 4.10: Contract award ..................................................................................................... 27
Table 4.11: National Competitive Bidding (NCB) ................................................................. 28
Table 4.12: International tendering ......................................................................................... 28
Table 4.13: Restricted tendering ............................................................................................. 29
Table 4.14: Request for quotations ......................................................................................... 30
Table 4.15: Single source procurement .................................................................................. 31
Table 4.16:Force Account ....................................................................................................... 32
Table 4.17: Community Participation ..................................................................................... 33
Table 4.18: Delay of payment ................................................................................................. 34
Table 4.19: Time for getting contract ..................................................................................... 34
Table 4.20: Views of contactors on lack of Skills .................................................................. 35
Table 4.21: Lack of transparence ............................................................................................ 36
Table 4.22: Time of contract implementation........................................................................ 36
Table 4.23: Incomplete specification ...................................................................................... 37
Table 4.24: Inefficiency of supervision .................................................................................. 38
Table 4.25: Relationship between procurement system and public funds management ........ 38
Page 5
v
LIST OF FIGURES Figure 2.1: Conceptual framework ......................................................................................... 18
Figure 4.2: The process of using competitive tendering in Gisagara District ........................ 27
Figure 4.3: The tendering methods adopted by Gisagara District ......................................... 33
Page 6
vi
LIST OF ABREVIATIONS AND ACRONYMS
EDPRS: Economic Development and Poverty Reduction Strategy
GNP Gross National Product
GoR: Government of Rwanda
IBRD: International Bank for Reconstruction Development
ICB: International Competitive Bidding
IDA: International Development Association
LED: local economic development
LIB: Limited International Bidding
MINECOFIN: Ministry of planning, Economic and finance
NCB: National Competitive bidding
OECD : Organization for Economic Co-operation and Development
Page 7
vii
RPPA: Rwanda Public Procurement Authority
WTO: World Trade Organization
DEFINITIONS OF KEY TERMS Procurement is a process of identifying and obtaining goods and services. It includes
sourcing, purchasing and covers all activities from identifying potential suppliers through to
delivery from supplier to the users or beneficiary.
Public procurement is a process to purchase or acquire the products, services such as simple
office items to sophisticated high-tech equipment from outside the organization to perform the
work in the public institutions.
Management of public fund Management of public fund is an optimal use and allocation of
public resources. In this research, the researcher needs to focus on public inventory control and
its management.
Page 8
CHAPTER ONE: INTRODUCTION
1.0 Introduction
This chapter contains the background of the study in which we give specific problems of the
research, statement of the problem in which we show what the research seeks to solve,
objectives of the study global and specific, research questions which is the provision of
response to the problem, significance of the study where is the benefit of the research,
limitation and scope of the study.
1.1 Background of the Study
Procurement management is a process to purchase or acquire the products, services such as
simple office items to sophisticated high-tech equipment from outside the organization to
perform the work (Velnampy & Kamalarupan , 2009). Procurement management includes the
processes to purchase or acquire the products, services, or results needed from outside the
organization to perform the work. Procurement management also includes administering any
contract issued by an outside organization (The Buyer) that is acquiring the organization from
the performing organization (the seller), and administering contractual obligations placed on
the organization by the contract (George , Cynthia, Berg, Judith & Doll, 2004). Prior to World
War I, purchasing was regarded as primarily clerical. During World War I & II; the function
increased due to the importance of obtaining raw materials, supplies, and services needed to
keep the factories and mines operating.1950s & 1960s purchasing continued to gain stature as
the techniques for performing the function became more refined and as the number of trained
professionals increased. With introduction of major public bodies and intergovernmental
organizations, such as United Nations, procurement becomes a well-recognized science.1970s
& 1980s more emphasis was placed on purchasing strategy as the ability to obtain needed items
from suppliers at realistic prices increased (Weele , 2010).
Nowadays in the public finance literature, different governments are involved in four major
economic activities: (a) providing the legal framework for all economic activities, (b)
redistributing income through taxation and spending; (b) providing public goods and services
freely available to the public such as national defense, public safety, education, and
infrastructure (bridges and roads); and (c) purchasing goods, services and capital assets (Thai,
2011).
In recent years, the Government of Rwanda has made impressive progress in rebuilding its
public financial management system, which like so much of the country was largely destroyed
during the genocide against Tutsi of 1994. Rwanda Public Procurement Authority mainly
focuses on regulatory measures, monitoring and building capacity in public procuring entities.
The Rwanda Public Procurement Authority is a Public body established on February 20, 2008
by the law N° 63/2007 of 30/12/2007. It was created to replace the National Tender Board
during a reform process in Public financial management launched by the Government of
Rwanda (GoR), in which Public procurement reform was one of the most important
components (Transparency Rwanda, 2012).
As part of public financial management reform, the Government of Rwanda has been engaged
in a number of initiatives aimed at streamlining its public procurement system in order to align
Page 9
2
it with fundamental principles of transparency, competition, economy, efficiency, fairness and
accountability (Organization for Economic Co-operation and Development [OECD], 2007).
Procurement Management is the third pillar of the Government of Rwandan Public Financial
Management Reforms Strategy. The main objective of this reform was to establish sound
public procurement policies and practices that ensure good governance and value for money
(Ministry of planning, Economic and finance [MINECOFIN], 2007). Thus, the researcher
carried out the research called Rwanda Public Procurement Authority and management of
public fund, a case study of Gisagara district.
1.2 Statement of the Problem
According to Thai (2011), although public procurement is perceived as a major function of
government, and although governmental entities, policy makers and public procurement
professionals have paid a great deal of attention to procurement improvements or reforms,
public procurement has been a neglected area of academic education and research in the least
developing countries like Rwanda. Measuring government procurement for a large number of
countries, in a consistent manner, is not a trivial task and careful attention must be paid to
ensure that national data is gathered on the basis of harmonized procedures in all countries
covered (Audet, 2002). The Government of Rwanda initiated and implemented reforms in
Public Finance Management including its Public Finance Reform Strategy of 2008-2012. The
ultimate goal of these reforms is to ensure efficient, effective and accountable use of public
resources as a basis for economic development and poverty reduction through improved
service delivery which is consistent with both the Economic Development and Poverty
Reduction Strategy (EDPRS) and the Vision 2020 (MINECOFIN, 2008).
Despite of the progress made, creation of Sustainable capacity building to implement these
reforms has remained a challenge. According to Rwanda Public Procurement Authority
[RPPA], (2012), other pillars for a sound, effective and efficient procurement system have
been achieved i.e. the creation of a legal and regulatory procurement framework, the ability of
the market place to participate in procurement given the growth and development of private
sector in Rwanda and the integrity of the country by looking at the fact that Rwanda is now a
role model in terms of zero tolerance towards corruption. The pillar that remains partially a
challenge is procurement management capacity. Thus, Public procurement has been a
neglected area of academic education and research in Rwanda. The researcher came up with
an idea to carry out this research called Rwanda Public Procurement system and management
of public fund, a case study of Gisagara district.
1.3 Objectives of the Study
1.3.1 Main Objective
The main objective of this study is to assess the relationship between procurement policy and
management of public fund in Rwanda.
1.3.2 Specific Objectives
To achieve the main objective, the following specific objectives will be accomplished:
Page 10
3
(i) To evaluate the Public Procurement methods used in Gisagrara (2010-2013) to manage
public fund;
(ii) To assess the factors influence public procurement process and public fund in Gisagara
District;
(iii)To analyze the challenges faced by Gisagara District contractors in tendering process;
(iv) To establish the relationship between public procurement and management of public fund.
1.4 Research Questions
The following questions will guide us while carrying out our study.
(i) Is there any public procurement methods used in managing public tenders?
(ii) What are the factors that influence public procurement process and public fund in
Gisagara District?
(iii) What are the challenges faced by Gisagara District contractors in tendering process?
(iv) Is there any relationship between public procurement and public fund management?
1.5 Significance of the Study
This project is to help and address the factors that lead to the improper or poor procurement in
RPPA and how the problem can be solved or minimized through efficient management of the
resources available. The project also served as a reference material for any person that would
like to conduct research on public procurement control. This study is of great importance
basing on the fact that the procurement plays big role in the public institutions. Therefore, the
findings of this study provide literature that is important for the individuals, public and private
institutions.
To the researcher: The study is beneficial to the researcher himself; this is because the
researcher was able to understand properly, how public procurement can be used to influence
public institutions performance through better management of public fund. This study is also
beneficial to the researcher because it provides to him with the knowledge on how to manage
resources of public institution through better procurement.
To other researchers: Regarding individuals, the information collected and analyzed after the
study added to the existing literature which assisted other researchers more specifically
students writing their projects in the same or related area.
1.6 Limitations
The first limitation of the study is dealing with people who do not want to release information
thinking that the research is going to be commercial. This was addressed by telling them that
the information is going to be confidential and purely academic. The study was expensive as
it involved a lot of spending such as transport and report production costs. There can be a
problem of getting full information from managers, team leaders and supervisors because
they can think that information can be used by competitors. For gaining the attention of
filling the questionnaire, researcher convinced them by explaining the importance of the study
and the recommendations which help them to improve their performance.
Page 11
4
1.7. Scope of the Study
In order to ensure that the research remains focused on its objectives, it put up in content,
geography and time.
1.7.1 Content Scope
The research focused on the Rwanda public procurement authority and management of public
fund. The researcher focused in this field because, he recognized that sometimes those people
(contractors) with low income do not benefit tendering.
1.7.2 Geographical Scope
The research was carried out in Gisagara district, located in Sothern province.
1.7.3 Time Scope
The research was included fiscal period of 4 years from 2010 to 2013.The researcher has
chosen this period because, it is in this period whereby Rwanda Public procurement Authority
faced problems of fluctuating resources, inaccurate forecasts and low utilization of inventory
and then it is in this period whereby the researcher gets updated data .The research will be
carried out during 6 months.
1.8 Organization of the Study
The research work is divided into five main chapters, chapter one is compose of the general
introduction, background of the study, statement of the problem, purpose, objectives of the
study, research questions, and identification of the study variables, scope, significance and
organization of the study. Chapter two involved the review of relevant literature with reference
to different sources of data, definition of terms and concepts and framework of the study.
Chapter concerned with the methodology to be used in carrying out this study. Research
designs, techniques of data collection and methods used. Chapter four analyzed and presented
the study findings. It attempts to summarize the views from the questionnaires and
documentary review interprets them and then presents them as findings of the research.
Chapter five was a summary, suggestions for further studies and conclusion of results. The
research at the end attached references and appendices used in undertaking this study.
CHAPTER TWO: REVIEW OF RELATED LITERATURE
2.0 Introduction
This chapter is broadly aimed at reviewing the existing research and literature that is relevant
to the study under question. It represents different literature related to procurement, reviewed
the theoretical, empirical and critical literature on the subject related to the study. The over all-
purpose of this chapter is to identify gaps that this study will fill and contribute approaches to
better performance of public procurement.
Page 12
5
2.1 Theoretical Literature
2.1.1 Overview of Procurement
Procurement is a process of identifying and obtaining goods and services. It includes sourcing,
purchasing and covers all activities from identifying potential suppliers through to delivery
from supplier to the users or beneficiary. It is favorable that the goods/services are appropriate
and that they are procured at the best possible cost to meet the needs of the purchaser
in terms of quality and quantity, time, and location (Mangan, Lalwani & Butcher, 2008).
According to Weele (2010), procurement is the acquisition of goods, services or works
from an external source. It is favorable that the goods, services or works are appropriate
and that they are procured at the best possible cost to meet the needs of the purchaser in terms
of quality and quantity, time, and location. Corporations and public bodies often define
processes intended to promote fair and open competition for their business while minimizing
exposure to fraud and collusion.
Governments are significant purchasers of goods and services and these markets represent
huge opportunities for international trade. Measuring government procurement for a large
number of countries, in a consistent manner, is not a trivial task and careful attention must be
paid to ensure that national data is gathered on the basis of harmonized procedures in all
countries covered (Audet, 2002). Maurer (2004) argues that there is one important question to
ask when dealing with procurement. The question is; “How is the organization seeking
continuous improvement in its approach to procurement for new development, planned and
responsive maintenance?” To ensure improvement in procurement, he prescribes that
organizations should use ‘best value’ techniques, which embody aspects such as challenging
what organizations do and how they do it, making comparisons with others, consulting people
affected by the organization’s services, and establishing that value for money is obtained
during procurement.
The purpose of an effective and dynamic public procurement is to ensure among other things,
timeliness, efficiency, transparence, economy and accountability in the use of public funds for
the acquisition of works, goods and services. The rational of public procurement system
therefore refers to the reason that justifies public procurement system to be better option in the
development of country (OECD, 2007).
The procurement and contract administration process are prone to risks. There are risks in
determining need and planning procurements, developing specifications, selecting the
appropriate procurement methods, preparing solicitation documents and calling for offers,
evaluation and selection of firms and individuals, negotiating the contract, and contract
administration. Procurement management is about solving problems and managing risks.
Customers need supplies and services to solve immediate and future needs. They usually have
little understanding of procurement and unrealistic expectations about the procurement
process. Procurement planning and strategy development are important to reduce risk in the
procurement process. A comprehensive understanding of the procurement process, principles
and guidelines is also important to finding appropriate solutions and minimizing risks
(Benslimane, Plaisent, & Bernard, 2005).
Page 13
6
2.1.2 Types of public Procurement
Procurement of goods means objects of every kind and description including raw materials,
products, equipment and objects in solid, liquid or gaseous form, and electricity, as well as
services incidental to the supply of the goods if the value of those related services does not
exceed that of the goods themselves (Brackus, 2000). Procurement of service refers to any
services other than consultant services. This includes related services. “Related Services” is
used to denote services such as transportation, insurance, installation and commissioning,
training and initial maintenance, etc. which are included in the goods and works being procured
(Audet, 2002).
Procurement of works means all work associated with the construction, reconstruction,
demolition, repair or renovation of a building, structure or works, such as site preparation,
excavation, erection, building, installation of equipment or materials, decoration and finishing,
as well as services incidental to works such as drilling, mapping, satellite photography, seismic
investigations and similar services provided pursuant to the procurement contract, if the value
of those related services does not exceed that of the works itself; “Consultant Services” refers
to activities or services of an intellectual or of immaterial nature. It refers to services which
require professional skills in the execution of assignments with non-physical output, such as
studies, designs, etc. to be undertaken by individual consultants, consulting firms and other
specialists (Bovis, 2007).
2.1.3 The Public Procurement Process
All procurement requirements begin with the perception of a need; the need to cross a body
of water could create a requirement to build a bridge, a ferry, or other transportation systems.
At this stage it is necessary to clearly define the need, and this may be done by way of a study
to determine the best mode to cross the body of water (given the present situation and
forecasted future need), then the type of bridge to be constructed, or a comparative cost/benefit
analysis to determine the best solution between a bridge and other alternatives. The study
should include if the need can be satisfied in-house or contracted out, quantification of the
initial budgetary estimate, and an idea of the procurement lead-time. The conformation of the
study team should be multidisciplinary in order to address the different questions to be
answered to facilitate a comprehensive understanding of the need so as to clearly define the
actual requirement.
Jorge (2012) assumed that the role of procurement practitioners at this stage is primarily to
estimate the procurement lead time given the most appropriate procurement method that would
be suitable for such a requirement. Of course, the perceived need is not always as complex as
in the example above. There are also needs for goods and services, and those should also
undergo an analysis to clearly define requirements. At the end of the requirements definition
stage, a clear determination of the terms of reference, technical specifications or statement of
work (depending on the procurement category) should be possible, including an estimate of
the budget, and, most importantly, the procurement lead-time. This requirement definition
analysis is essential not only for new procurement requirements, and project initiation and
concept development, but also for requirements needed for maintaining existing operations.
Determining procurement method, during the requirement identification stage, the entity with
the need determines when they want the goods delivered, services rendered or construction
works completed. It is important to consult with the procuring entity at this early stage in order
Page 14
7
to determine the most appropriate procurement method for their specific need. The
procurement method should be determined at this early stage because of the impact it has on
the procurement lead-time, and also to ensure that the responsible entity is able to set realistic
timeframes and expectations for contract award in the initial stages of development and
definition of their procurement requirement (Saunders, Levin, & Thornhill, 2009).
This simple exercise of obtaining the assistance of the procuring entity early on helps to avoid
disappointments, unrealistic expectations and frustrations when, due to poor planning, it is
impossible to meet expectations set during the requirement definition phase. At this stage of
the process, it is also important to decide if a competitive or non-competitive procurement
method will be used. The complexity of a requirement, procurement category, and monetary
value are all important factors to consider when deciding on the procurement method. A
decision to use a particular procurement method must be based on the stipulations of the
procurement rules (Burguet & Che, 2004 ).
Caldwell ,Roehrich and Davies (2009) mentioned that it’s difficult to talk about procurement
planning without mentioning procurement strategy, because procurement strategy is developed
in conjunction with and during the procurement planning phase and is a key factor in
determining the most appropriate procurement method given the complexity and monetary
value of the requirement, and market availability. While procurement planning deals with
“when”, procurement strategy looks at “what”, “how”, “where” and “why”; which need to be
decided before the ‘when”
Procurement planning and strategy development procurement Planning is one of the most
important steps in the public procurement cycle. The procurement plan is expected to list all
the requirements that are under the responsibility of a particular procurement entity and that
are expected to be procured over a period of time (usually one year, but could be longer when
dealing with project procurement).There are instances where some items that are below a
certain monetary threshold are not listed on the procurement plan; however, effort should be
made to have everything that a particular procurement entity is responsible for procuring listed
on the procurement plan of that procurement entity. The procurement plan should also be
update at least every six months (or more if required), but constant updating should be avoided.
The fact that the procurement plan needs updating is an indication that it is not expected to be
a static document. This, however, should not lessen the importance of procurement planning
as the primary tool used for triggering procurement actions. This means that all procurement
actions taken by a particular procurement entity should be guided by an approved procurement
plan (Jorge, 2013).
The procurement plan isn’t only useful for determining what needs to be procured, and by
when, but it’s also for determining the need for additional manpower to support the preparation
of specifications and bid documents, requesting, receiving and evaluating offers, contract
negotiations and award, and contract administration, given the number of procurement
requirements within a certain period of time. Once the procurement plan is prepared and
approved after allocation of funds and consolidation (bundling) of similar requirements to
attract a broader pool of suppliers and for economies of scale, it should only be allowed to
change through approved amendments; and all requirements procured by the responsible
Page 15
8
procurement entity should be found on the approved procurement plan. Only for exceptional
reasons should a particular procurement be allowed to commence without being listed on the
approved procurement plan or on an approved amendment of the procurement plan (Burguet
& Che, 2004 ).
Procurement requisition processing, once the procurement plan is prepared and approved, the
requesting entities should begin submitting their requirements accordingly to the procuring
entity for processing. When a procurement requisition is submitted, the first step in processing
the request for procurement action is to determine exactly what is required. Although a general
idea would already exists as a result of the requirements determination and procurement
planning phases, it is at this point that the completed technical specifications or terms of
reference should be sent to the procuring entity to start the procurement requisition process.
The procuring entity in turn reviews the technical specification or terms of reference for
completion (Jorge, 2013).
Completing the technical specifications and terms of reference later than scheduled will have
an adverse impact on the execution of the procurement plan and the award of the contract,
which in turn will cause delays in acquiring the goods and services. It is important for the
procuring entity, in coordination with the requesting entity, to determine in advance if technical
expertise will be required to draft the technical specifications or terms of reference and if this
expertise exists in-house or will also have to be procured. Independent of the technical
expertise existing in-house, when technical specifications or terms of reference are unclear or
lacking in other important elements, the procuring entity must seek clarification in an effort to
resolve any apparent discrepancies before completing the solicitation documents. Ideally, the
requesting entity should maintain an open dialogue with the procuring entity while preparing
their technical specifications and terms of reference. Sharing informal versions and getting
feedback from the procuring entity up until the final version is ready for formal submission.
When the procuring entity receives the technical specifications or terms of reference in a
manner suitable for requesting offers, and with the proper fiscal authorization to commit the
allocated funds, the procuring entity can begin preparing the solicitation documents (Thai,
2011).
Solicitation documents preparation and publication, upon receipt of an approved procurement
requisition, and after reviewing the technical specifications or terms of reference for
completeness, the procuring entity is in a position to begin preparing the solicitation
documents; otherwise, the procuring entity needs to establish contact with the requesting entity
in order to get any missing information to complete the technical specifications or terms of
reference before they can begin preparing the solicitation documents. Solicitation documents
are prepared from a template called standard bidding or tender documents, and information
specific to the particular requirement, such as observed below, is used to complete the
solicitation documents. Assuming that the requirement is on the procurement plan, pertinent
information needs to be obtained and agreed with the requesting entity prior to completing the
solicitation documents (Burguet & Che, 2004 ). Once the solicitation documents are complete
and approved, a procurement notice is prepared and posted to approved websites and internet
portals, and also published in local and (if necessary) international newspapers.
Page 16
9
Pre-bid/proposal meeting and site visit, pre-bid meetings are usually held, if previously
mentioned in the solicitation documents, during the bid/proposal preparation period. Their
purpose is to clarify any concerns bidders may have with the solicitation documents, scope of
work and other details of the requirement. These meetings are formal and the results are made
available in writing to all prospective bidders that registered interest in the requirement be it
through requesting, buying or downloading the solicitation documents from an official website.
Prospective bidders are permitted to request clarifications by a date and time stipulated in the
solicitation documents (Jorge, 2013).
It is most beneficial to hold pre-bid meetings prior to formally responding to the request for
clarifications, that way the responses to the request for clarifications can be sent along with the
results of the pre-bid meeting, including a copy of the minutes of the pre-bid meeting. Although
prospective bidders should be encouraged to get as much information as possible (including
visiting the site) on a specific or upcoming requirement of a procuring entity, formal site visits
are usually planned and carried out for works procurement and more complex goods
requirements. When a site visit is planned, the details of the date and time must be stated in the
solicitation documents. And the site visit should take place before (but not too far in advance
of) the pre-bid meeting. The results are also formally sent to all prospective bidders that
expressed interest in the requirement, by way of minutes of the site visit and pre-bid meeting,
including consolidated responses to request for clarifications, also from prospective bidders.
The pre-bid meeting is usually open to all interested prospective bidders; however, in cases
where pre-qualification or short-listing is carried out, only pre-qualified or short-listed bidders
are invited to attend the pre-bid meeting. Site visits, as mentioned above, can and should
preferable be held prior to the pre-bid meeting.
During the site visit the prospective bidders survey the site and ask questions to clarify any
doubts or information provided in the solicitation documents. Sometimes, as a result of the site
visit/pre-bid meeting there might be a need to extend the bid/proposal submission date by way
of Addendum to the solicitation documents to give bidders sufficient time to address any
changes made to the solicitation documents as a result of the site visit and/or pre-bid meeting
(Shaw, 2010).
Bid/proposal submission and opening, the Lead Agency must receive the Bid Proposal at the
Issuing Officer's address identified on the bid cover sheet before the "Bid Proposals Due" date
listed on the bid cover sheet. This is a mandatory requirement and will not be waived by the
Lead Agency. Any Bid Proposal received after this deadline will be rejected and returned
unopened to the Contractor. Contractors mailing Bid Proposals must allow ample mail delivery
time to ensure timely receipt of their Bid Proposals. It is the Contractor's responsibility to
ensure that the Bid Proposal is received prior to the deadline. Postmarking by the due date will
not substitute for actual receipt of the Bid Proposal. Electronic mail and faxed Bid Proposals
will not be accepted (Bovis, 2007)
Contractors must furnish all information necessary to evaluate the Bid Proposal. Bid proposals
that fail to meet the mandatory requirements of the bid may be disqualified. Verbal information
provided by the Contractor shall not be considered part of the Contractor's Bid Proposal unless
it is reduced to writing. The Lead Agency will open Bid Proposals after the deadline for
Page 17
10
submission of Bid Proposals has passed. The Bid Proposals will remain confidential until the
Evaluation Committee has reviewed all of the Bid Proposals submitted in response to the bid
and the Lead Agency has announced a notice of intent to award a contract. See Iowa Code
Section 72.3. However, the names of Contractors who submitted timely Bid Proposals will be
publicly available after the Bid Proposal opening. The announcement of Contractors who
timely submitted Bid Proposals does not mean that an individual Bid Proposal has been
deemed technically compliant or accepted for evaluation (Shaw, 2010).
Bid Evaluation and Awarding, the evaluation of tenders and awarding of contracts to suppliers
is an important phase of the procurement process (Maurer, 2004). It is the process that
determines the actual quality, reliability, delivery, etc. of the goods and services. The
procurement department coordinates the following: Analyzing and evaluating the bids against
set criteria, specification requirements presenting the analysis to an procurement appointed
committee, Verification of supplier capability and quality control/ assurance processes,
Reviewing product inspection results where necessary, Verification of technical evaluation
reports where applicable, Negotiates with vendors where it is recommended by the committee
and Placing orders and expediting the delivery.
In addition, Shaw (2010) contended that it is very important for the procurement department
to assess and consult on any big price variations, to avoid potential conflict of interest, undue
influence, price fixing and favoritism, and to ensure consultative decision making and sharing
of responsibilities. Also, the tender box should not be opened by one person only, and the
criteria used to evaluate bids should be tested and validated by the committee before
Contract Negotiations and award recommendation at the conclusion of the evaluation process,
the evaluation panel must both recommend and justify either the rejection of all offers,
proceeding with contract negotiations, or contract award. The evaluation panel’s
recommendation is made to the approving authority. Contracts for goods and works
procurement are not usually negotiated, except under exceptional circumstances, depending on
the complexity of the requirement. Complex requirements for supply, installation and
commissioning may be better procured through negotiations with the highest technically
qualified firm, as determined by the results of the evaluation of their technical proposals.
Similarly, under works procurement, design and build requirements may also need to be
negotiated; as well as, turnkey contract requirements (International Bank for Reconstruction
and Development[IBRD] &International Development Association [IDA], 2004).
According to IBRD & IDA (2004) in the case of consulting services, there are consulting firms
and individual consultants. Contracts for these two categories of consultants are negotiated
slightly differently. For individual consultants, after the technical evaluation, the highest
ranked consultant is invited to submit a financial offer and to negotiate the terms of the
contract. If for some reason an agreement isn’t reached, the next highest ranked consultant may
be invited, depending on the procedures, to submit a financial offer and to contract
negotiations. The focus of the negotiations should be to reach an agreement on the Terms of
Reference of the assignment, with minor modifications if necessary. Price negotiations should
be kept to a minimum and should only take place if the financial offer is considered
unreasonable based on documentary and/or historical evidence.
Page 18
11
Post contract award considerations, contract award are the beginning of the contract
management phase where the Client/Procurement entity will supervise the performance of
contractor/consultant. In the case of goods, given that finished goods are usually being
received, contract administrations limited to inspecting goods received to ensure their comply
with requirement, and are fit for their intended purpose (Audet, 2002).
2.1.4 How to Improve Procurement Function
Lewis and Roehrich (2008) point out that in order to improve procurement, practitioners should
guard and mitigate against risk, understand the market, build relationships with Suppliers, meet
needs in a timely manner and constantly monitor performance to improve service provision. It
is also vital for organizations to have clearly defined procurement policies that are well
understood. Organizations should always ensure that sufficient procedures are done to check
that work has been satisfactorily done before payment is made (Shaw, 2010).
Organizations should have clear written guidelines that define when board members or officers
must declare a personal interest that may be deemed to be in conflict with their office (Mangan,
Lalwani & Butcher, 2008). Shaw (2010) says that procurement policies will vary from
organization to organization but are the organizational rules and regulations governing the
procurement function. The policies determine how different aspects of procurement will be
carried out in the organization and how people working in procurement should behave
(Nakamura, 2004).
In the past organizations have usually determined that the value for money was achieved by
accepting the lowest price tendered by suppliers of goods and services. Lately there is an
emphasis on the basis of the overall value for money offered, including the consideration for
nonmonetary factors and not on the basis of lowest price alone (Shaw, 2010).It is also essential
that the governments compare itself with other comparable organizations partly to test that
value for money is being achieved, but also as part of the process of Seeking continuous
improvement and identification of good practice. This is often done through a benchmarking
process (Maurer, 2004).
The primary purpose of benchmarking is to improve the performance of the company by
testing how it is performing, whether it is achieving better performance and the rate at which
its performance is improving. Without measuring the company’s performance, it is not possible
to check whether the targets that the company has set are being achieved. Benchmarking is
therefore critical to the process of continuous improvement.
The company among other indicators can use such comparisons as cost, time, and quality .The
involvement of the Logistics function in assessments will enable Logistics to plan for the
delivery of services, but for Logistics to succeed, the procurement plan must be well integrated
and visible in the overall response plan. In emergency situations, easily accessible logistics
preparedness and response will help to fast track the development of a response plan, tailored
for a specific situation (Shaw, 2010).
2.1.5 Overview of Management Of Public Fund
Management of public fund is an optimal use and allocation of public resources. In this
research, the researcher needs to focus on public inventory control and its management.
Page 19
12
Inventory control involves the coordinating of materials availability, controlling, utilization
and procuring of materials. Inventory control is the direction of activities with the purpose of
getting the right inventory in the right place at the right time and in the right quantity and it’s
directly linked to production function of any organization which implies that the inventory
management system operated will affect the performance of an organization directly and
indirectly (Alm, 2000).
According to Kotler (2002), inventory management refers to all the activities involved in
developing and managing the inventory levels of raw materials, semi-finished materials
(working-progress) and finished good so that adequate supplies are available and the costs of
over or under stocks are low. The nature of inventory depends upon the type of activity carried
on. In the case of a manufacturing unit, inventory will generally include all types of
inventories mentioned above, while in the case of a trading concern, it will comprise only
finished goods or stock -in-trade owned by it for sale to customers in the normal course of
business. Inventory needs proper control as it is one of the largest assets of a business (Deloof,
2003).
Inventories should neither be excessive nor inadequate. If inventories are kept at a high level,
higher interest and storage costs would be incurred; on the other hand, a low level of
inventories may result in frequent interruption in the production schedule resulting in under-
utilization of capacity and lower sales (Falope & Ajilore, 2009). The objective of inventory
management is therefore to determine and maintain the optimum level of investment in
inventories which help in achieving the required objective. Inventories are the stock of raw
materials, work in progress, finished goods and supplies held by a business organization to
facilitate operations in the production process. Also if the company fails to manage its
inventory efficiently, it is likely to face profitability problems.
The goal of inventory management therefore is to provide the inventories required to sustain
operations at minimum costs (Brackus, 2000). Inventory is the stock stored that has a resale
value in order to gain profit. It represents the largest cost of the company especially for the
trading firms, wholesalers and retailers. It is mentioned as “piles of money” on the shelf.
According to (Raheman& Nasr , 2009) said that, in normal circumstances, it consists of the
20% - 30% of the total investment.
Therefore, the inventory should be properly managed in order to facilitate the company
operation. Inventory control is primarily about specifying the shape and percentage of stocked
goods. It is required at different locations within a facility or within many locations of a supply
network to precede the regular and planned course of production, trading and stock of
materials. Inventory conversion period is the average amount of time that a business
holds its (Kotabo, 2002).This study intends to measure the management of public funds using
accountability, positive balance of revenue and expenditures, teamwork and ownership of
budgetary implementation.
2.1.6 Methods for Procurement of Goods and Services
Methods for procuring goods and services in externally financed institutions vary widely
according to the nature of projects and financing institutions. However, donor agree that award
Page 20
13
of procurement contracts most agree with efficiency, economy and transparence
considerations, procurement methods to be used are determined by during the project
preparation and appraisal and included in the project agreement. According to world bank (
2011) the methods widely used in procurement are:
National Competitive Bidding (NCB) is the competitive bidding procedure normally used for
public procurement in the country of the Borrower, and may be the most appropriate method
of procurement of goods, works, and non-consulting services which, by their nature or scope,
are unlikely to attract foreign competition. NCB may be the most appropriate method of
procurement where foreign bidders are not expected to be interested because (a) of the size
and value of the contract, (b) works are scattered geographically or spread over time, (c)
works are labor intensive, or (d) the goods, works and non-consulting services are available
locally at prices below the international market. NCB procedures may also be used where the
advantages of ICB are clearly outweighed by the administrative or financial burden involved.
Limited International Bidding (LIB) is essentially ICB by direct invitation without open
advertisement. It may be an appropriate method of procurement where (a) there is only a
limited number of suppliers, or (b) other exceptional reasons may justify departure from full
ICB procedures. Under LIB, Borrowers shall seek bids from a list of potential suppliers broad
enough to assure competitive prices, such list to include all suppliers when there are only a
limited number. Domestic preferences are not applicable in the evaluation of bids under LIB
(Thai, 2011).
Direct contracting is contracting without competition (single-source) and may be an
appropriate method under the following circumstances. The Borrower shall submit to the Bank
for its review and no objection a sufficiently detailed justification, including the rationale for
direct contracting instead of a competitive procurement process and the basis for
recommending a particular firm in all such cases, except for contracts below a threshold
defined on the basis of risks and the scope of the project, and set forth in the Procurement Plan
(Kunzlik, 2003).
Force Account, which are works such as construction and installation of equipment and non-
consulting services carried out by a government department of the Borrower’s country using
its own personnel and equipment. The use of Force Account requires that the Borrower sets
maximum aggregate amounts for the use of Force Account (Wardani, 2004). Performance
Based Procurement, also called Output Based Procurement, refers to competitive procurement
processes, resulting in a contractual relationship where payments are made for measured
outputs instead of the traditional way where inputs are measured. The technical specifications
define the desired result and which outputs will be measured including how they will be
measured. Those outputs aim at satisfying a functional need in terms of quality, quantity, and
reliability. Payment is made in accordance with the quantity of outputs delivered, subject to
their delivery at the level of quality required. Reductions from payments (or retentions) may
be made for lower-quality level of outputs and, in certain cases; premiums may be paid for
higher quality level of outputs (Audet, 2002).
Restricted tendering is another variation of formal bidding in which only those issued
invitations from the procuring entity’s restricted list of potential bidders are permitted to submit
bids. With these variations in mind, the procedures to be followed for each of these methods
Page 21
14
of procurement are essentially the same. Restricted tendering (also known as limited bidding)
is essentially competitive bidding by direct invitation, without open advertisement. Restricted
tendering is an option generally where there is a limited number of possible potential bidders
or where contract values are small or other special circumstances that may justify departure
from competitive bidding. In open and restricted procedures contracting authorities may
request further information from tenderers in order to facilitate assessment of their offers, but
it is forbidden to negotiate the terms of such offers.
This important aspect of the transparency of open and restricted procedures has been stated
clearly by the Council and the Commission in the following terms: "In open and restricted
procedures all negotiations with candidates or tenderers on fundamental aspects of contracts,
variations in which are likely to distort competition, and in particular on prices, shall be ruled
out; however, discussions with candidates or tenderers may be held only for the purpose of
clarifying or supplementing the content of their tenders or the requirements of the contracting
authorities, and provided this does not involve discrimination. In an open procedure any
interested service provider may submit an offer in response to the publication of the contract
notice. In a restricted procedure there are two stages. In the first stage any interested service
provider may submit a request to participate in response to the publication of the contract
notice. Such service provider is called a "candidate". In the second stage the contracting
authority invites the submission of tenders from selected candidates (Burguet & Che, 2004 ).
Request for quotations is a procurement method used for small and routine purchases. It is also
defined as a method of procurement used primarily for procurement of goods or low value
procurement in which the procuring entity evaluates and makes award to the winning bidder
submitting a quotation on the basis of price alone. Request for quotations is an appropriate
method for procuring readily available off-the-shelf goods or standard commodities in
quantities of small value and in some cases, small simple works. Request for quotations does
not require formal bidding documents, and is carried out by requesting written. In evaluating
quotations submitted by bidders under request for quotations, price and ability to meet required
delivery requirements are usually the main selection considerations for these simple purchases
(Ogunsanmi, 2013).
Single Source (Also known as Direct Procurement or Direct Contracting) is a method of
procurement in which the procuring entity determines not to use competitive procurement on
grounds of urgency or some other legal principle and negotiates a contract with a single
qualified bidder Force Account. Direct contracting without competition is the method of
procurement open to procuring entities in a limited number of circumstances. In all cases where
direct contracting is proposed, procuring entities must ensure that it would not be feasible to
apply a competitive bidding procedure. The contractors or suppliers hired by direct contracting
must be qualified to perform the works or supply of goods on time, meeting specifications and
fulfilling the special requirements of the sole source contract (Brammer & Walker, 2011).
2.1.7 Importance of Public Procurement in Public Fund Management
Large share in public expenditure, it is apparent that even modest efficiency improvement in
the workings of the procurement system could potentially yield substantial savings. In addition,
public procurement in Rwanda is currently a primary source of revenue for the private sector
Page 22
15
and an important tool in promoting the governance agenda which is one of the government’s
priorities (Ministry of planning, Economic finance [MINECOFIN], 2007).
Public procurement has in economic and social role in the development of a country. In
Rwanda for example, a great amount of national budget is channeled directly through local
governments. Procurement could be used to advance the social policy and local economic
development (LED) agenda. This can be done through tailor made guidelines on local
preference by local governments procuring entities. The level expenditure and the attempt to
direct the expenditure at local producers can be a major macroeconomic instrument to tackle
poverty. Additionally, procurement policy might be used to boost domestic industries or
encourage development in specific sectors of national interest. Social objectives could also be
advanced by preferences for specific groups or communities, especially the marginalized ones
(World Bank, 2011). The procurement is a service function that supports the activities of other
areas of the business; to perform the procurement function must flow between the procurement
department and other department (Audet, 2002).
Every purchase made represent an expenditure or commitment of company funds. It sets in
motion a series of accounting operations, much as changing the expense to the proper contract
or department account, the verification and approval of the invoice, payment of the change and
final audit. For proper cash flow planning, finance department needs regular reports from the
purchasing department on its outstanding commitments. Both departments should also
cooperate on cash discount policy. Depending on current interest rates, it may be more
advantages to the company to take the maximum to pay suppliers’ invoice clerks in the
purchasing department usually handle certain accounting operations. These would include
verifications of extensions and totals as well. In other institutions, invoices go directly to be
matched with the accounting purchase order and receiving reports copies. Any discrepancies
noted are then referred to the appropriate buyer in the purchasing department for resolution
(Bovis, 2007)
Starr (1989) asserts that, it is critical to know how to select supplier and what to expect of
them. Purchasing managers must supply basic methods of selection analytically and
aggressively. Maurer ( 2004) contents that there are four stages of supplier selection which
include: The survey, in which possible sources of product are exported; the inquiry stage, in
which the relative qualifications and advantages of potential sources are analyzed; Negotiation
and selection, leading to the issue of an initial order; Experience, in which a continuing vender-
suppliers relationship is established or the earlier steps are reviewed in the research for more
satisfactory source.
2.2 Empirical Literature
Different studies have confirmed the use of various types of procurement methods for the
project delivery. Ogunsanmi (2013) investigated the effects of procurement related factors of
procurement selection criteria, tendering methods and variation orders on project performance.
Purpose of the study was to evaluate the effects of procurement related factors on project
performance procurements have impacts on project performance. He confirmed that
procurements have impacts on project performance. He concluded that procurement selection
criteria, tendering methods and variation orders have impacts on project performance. Cost,
Page 23
16
time, quality related factors, tendering methods and variation orders strongly affect project
performance.
Rainer and Veiko (2010) carried out a research on public procurement as an industria tool.
They used qualitative research design and found that government procurement should not be
seen only as an indirect support measure for development, but also as a direct vehicle for
promoting innovation and industries and, thus, growth and development. They also showed
that using public procurement for development assumes high levels of policy capacity, which
most developing countries lack.
Burguet and Che (2004) demonstrated the disadvantageous role of corruption through studying
the competitive procurement administered by a corrupt agent who is willing to manipulate his
evaluation of contract proposals in exchange for bribes. The authors used qualitative research
and documentary review argued that the inefficiency cost of bribery is in the same order of
magnitude as the agent’s manipulation capacity and found that corruption is among the factors
affect the level of procurement and public funds management.
Arozamena and Weinschelbaum (2009) focused on the existence of corruption and its effect
makes an honest buyer behave more aggressively during procurement. In their research, they
provided theoretical model for the effects of corruption on the behavior of honest buyers in
sealed-bid auctions that are mainly used during public procurement tenders in Ukraine. The
findings demonstrate that the first-price auction becomes inefficient with corruption. They
have also established that corruption hurts honest bidders, whereas the members of the
partnership always have a positive expected surplus to be divided between them.
Mulwa, Jeremiah, and Joash (2013) established the determinants of implementation of public
procurement regulations by headteachers in public secondary schools in Migwani District,
Kenya. The study was conducted in 27 secondary schools. The study employed descriptive
survey design and used questionnaires for 27 headteachers, 27 deputy headteachers, 27
accounts clerks, members of procurement committees and District Schools Auditors. Simple
random sampling procedure was used to select the procurement committee members.
Their findings indicated low level of compliance in the implementation of public procurement
regulations.
Stephen and Imeh (2013) stipulated that there is a significant difference between the rank-
order of procurement methods against selection criteria by averaging and outranking-satisfying
techniques. The use of outranking-satisfying analysis revealed that, the use of arithmetic mean
to determine the utility factors can lead to inappropriate association of procurement routes with
differing utility coefficients. They also argued that the measure of performance (i.e. utility
factors) of each procurement method has been an important issue in this research for the
appropriate procurement method for a particular project. The utility factor is a relative
measurement of suitability of a particular procurement method against a criterion.
Kalubanga (2012) stipulated that the need to improve organizational efficiency, reduce waste,
overcome supply chain risk, and achieve competitive position has made companies to start
considering environmental issues from a competitive view point. Procuring organizations are
more seriously involved in designing and implementing sustainable procurement policies
focusing on how environmental issues and issues relating to other aspects of the sustainable
Page 24
17
development pillars (society and economy) can be integrated in the procurement process
activities. Reflecting broader concerns to achieve sustainable development, sustainable
procurement has recently acquired a high degree of salience in policy circles internationally.
Sustainable procurement builds on the traditional procurement practice which it seeks to
extend through the adoption of sustainability principles. Procurement is defined as acquisition
of goods, works and/or services from the supplier (this may be an individual or organization).
The procurement process is viewed as involving sourcing (planning: needs identification and
assessment, supplier selection) contracting, monitoring and evaluation (Brammer & Walker,
2011).
Kiage ( 2013) ascertained that the determinants of procurement performance in public entities
a case of Ministry of Energy. Specifically the study sought to establish the impact of
procurement planning on procurement performance; ascertain the influence of resource
allocations on procurement performance; discern the impact of staff competency on
procurement performance and finally reveal the extent to which contract management in the
procurement cycle affects procurement performance. Efficient public procurement system is
vital to the advancement of African countries and is a concrete expression of their national
commitments to making the best possible use of public resources. In both private and public
sectors, there is increasing pressure from customers, clients, government and the public to put
sustainable procurement into practice. The 2002 World Summit on Sustainable Development
stated that relevant authorities at all levels should: "promote public procurement policies that
encourage development and diffusion of environmentally sound goods and services". In
response to this, Business Operators and Professionals have been very fast to institute policies
and strategies embedding sustainable development concerns. Organizations practicing
sustainable procurement meet their needs for goods, services, utilities and works not on a
private cost-benefit analysis, but with a view to maximizing net benefits for themselves and
the wider world. In so doing they must incorporate extrinsic cost considerations into decisions
alongside the conventional procurement criteria of price and quality.
2.3. Critical Review and Research Gap Identification Rainer and Veiko (2010) carried out a research on public procurement as an industria tool.
Burguet and Che (2004) demonstrated the disadvantageous role of corruption through studying
the competitive procurement administered by a corrupt agent who is willing to manipulate his
evaluation of contract proposals in exchange for bribes. Arozamena and Weinschelbaum
(2009) focused on the existence of corruption and its effect makes an honest buyer behave
more aggressively during procurement. In their research, they provided theoretical model for
the effects of corruption on the behavior of honest buyers in sealed-bid auctions that are mainly
used during public procurement tenders in Ukraine. Mulwa, Jeremiah, and Joash (2013)
established the determinants of implementation of public procurement regulations by
headteachers in public secondary schools in Migwani District, Kenya. During their
research, they only focused on the detrminants of of implementation of public procurement
regulations, but they did not focused on their effect on management on public fund. Therefore,
the study of Fayomi and Ikeoluwapo ( 2013); Rainer and Veiko (2010) and other criical
studiies focused on public procurement and development of developing countries,but they did
not establish the methods that could be used to well manage the public fund and then they didd
not establish relationship between variables under study.
Page 25
18
2.4 Conceptual Framework
Figure 2.1: Conceptual framework
Independent variable Dependent variable
Source: Researcher Developed
2.5. Summary
The literature review reviewing the existing research and literature that is relevant to the study
under question. Procurement is a critical activity in investment and inevitably contributes to
the success of plans..It is very crucial to assure a sound and transparent system of public
procurement because of its impact on the economic and governance issue. It represents
different literature related to procurement, reviewed the theoretical, empirical and critical
literature on the subject related to the study. Theoretical literature explained the process of
procurement and methods of procurement. This section focused also on other studies carried
out by other research on procurement and public funds management. From the critical review,
Public procurement
Procurement method
Procurement planning
Tender document
Publication
Bids opening
Evaluation of bids
Notification
Contract award
public fund Management
Accountability
Positive balance of revenue
& expenditures
Expenses rate
Teamwork and ownership
of budgetary implementers
Leadership style
Budgeting
Intervening variable
Government policies to promote private
sector
Participation of bidders
Political, socio-economic stability
Knowledge of private sector in business
competition
Procurement policies
Page 26
19
it is indicated that the better application of procurement procedures leads to good management
of state funds and improve the competiveness among private sector. This is a basis for
evaluation of procurement system and procedures used by public institutions. The role of the
private sector and civil society has to be strengthened. Even if some researchers like Burguet
and Che (2004) used qualitative research and found that the inefficiency cost of bribery is in
the same order of magnitude as the agent’s manipulation capacity. Arozamena and
Weinschelbaum (2009) focused on the existence of corruption and its effect makes an honest
buyer behave more aggressively during procurement using theoretical model and then they
concluded that corruption affect price and cost of procurement. Mulwa,Jeremiah and Joash
(2013) research was very important in the region,but they did not think about their impact on
management of public fund.Thus,from the this gap,the present researcher intents to build a
bridge by carrying out a research called Public Procurement system and Public Fund
management ;on the case of study of Gisagara district.
CHAPTER THREE: RESEARCHMETHODOLOGY
3.0 Introduction
This chapter sets out and describes the methodology that was used to investigate and determine
the contribution of public procurement to management of public fund. It includes the design
of the study, the target population, sample design, data collection procedures and instruments,
study reliability, data processing procedures and data analysis.
3.1. Research Design
The researcher uses a descriptive-analytical research design in order to get in depth
information of the research topic. In addition, both qualitative and quantitative methods were
used. The researcher collected primary data and makes documentary analysis for secondary
data. The design of this research is descriptive research design with the aim of getting all the
required qualitative and quantitative information. This research design helped to describe the
relationship between public procurement and management of public fund.
3.2 Target Population
The study population was composed of 7 employees from tender committee of Gisagara
District,2 from executive secretary,7 from finance,1 from logistic,4 from administration,4 from
planning, monitoring and evaluation and then 143 from sectors .The study population will be
consisted of 190 employees of Gisagara District and 30 contractors .
3.3 Sample Design
A sample is subset or portion of the total population under study. This part concerns the sample
size and sampling procedures used to come up with the sample size. This study used non-
probability sampling methods to select sample size.
3.3.1 Sample Size
Page 27
20
The researcher could not investigate the total population of 190 employees and 30
contractors; hence the sample of employees was selected using Yamane formula. n=
2(e)*N1
N 190
1+190∗(0.082)=
190
1+190∗0.0064=
190
2.216= 86
Where:
n = 86 employees, N = 190 = Level of confidence or error margin = 0.08, Using the formula
above the sample size is86respondents
Table 3.1: Target population and sample size determination
Category
Target
population
size
Sample size Purposive sampling method
District level 24 16 Executive secretary office
7 7 Tender committee
7 5 Finance
1 1 Logistic
4 3 Administration
4 2 Planning, monitoring and evaluation
Sector level 143 52 Accountant and executive secretary
Total employees 190 86
Contractors 30 30
Source: Gisagara District, 2014
3.3.2 Sampling Techniques
Apart from the sample size, the selection should detail how the researcher intends to select the
sample, ensuring representativeness of the target or parent population. The choice of sampling
technique was based on the feasibility and sensibility of collecting data to answer the research
questions and to address the objectives. Quantitative researches usually ensure sample
representativeness using “scientific, mathematical, and statistical/probabilities or random
sampling as quantitative research therefore, this study uses purposive sampling method.
The researcher used purposive sampling method in this research, because he needs the
employees who have skills in public procurement policies and public fund management.
Therefore Purposive sampling technique was used to question 86 employees and Census was
used to question 30 contractors, summarized in Table 3.1.
3.4 Data collection Methods
To make this research successful, the data to be collected included both primary and secondary
data. Primary data obtained through the use of self-administered questionnaires
3.4.1. Data Collection Instruments
Page 28
21
To collect primary data, the researcher used a questionnaire as data collection instrument to
obtain the information that relates to the opinions, perceptions, intensions, and thoughts of the
members of the tender committee on procurement attribution. The questionnaire was prepared
in English.
3.4.2 Administration of Data Collection Instruments
The researcher distributed the questionnaires to the respondents and wait for them for three
days. And then the researcher made sure the number of questionnaire distributed has been filled
by all respondents.
3.4.3 Validity And Reliability
Therefore, the researcher first carried out a pilot study by testing questionnaires to at least six
members from the respondents in Gisagara District before going into data collection and then.
And then, in order to make sure that language and research instrument is arranged according
to research objectives, the research looked for experts for verifying them.
3.5 Data Analysis Methods
Data analysis techniques have been developed deal with manipulation of the information that
has been gathered so as to present the evidence. The contents of these tables are usually,
percentages, frequencies or some summary statistical measures. This study, both quantitative
and qualitative means of analyzing data was adopted. The researcher used Statistical packaging
for social science during data analysis.
Qualitative variables are used extensively in observation studies. The procedure of analysis
applied while dealing with unqualified responses. With this, the research made clear
observations on the views of respondents on the exciting phenomena.
The tools that were applied here by the research were data collection techniques. The
researcher analyzed qualitatively and quantitatively. For purpose of quantitative data analysis,
the collected data was expressed in different tables especially the responses from the
representative sample under the study. With reference to this study, the researcher analyzed
the data collected, basing on the number of responses. This was calculated in percentages on
which the researcher based while designing the conclusion.
3.6 Ethical Consideration
With regard to this study, the aims and objectives was conveyed to all the relevant authorities
during the process of acquiring permission to do research, and to the employees and managers
involved during the data collection stage. Respondent’s participation was voluntary and they
had the right to withdraw from the study at any time.
Page 29
22
CHAPTER FOUR: RESEARCH FINDINGS AND DISCUSION
4.0 Introduction
In this chapter, the researcher presents analysis and interprets the findings of the research.
Using tables the researcher did presentation of the collected data and figures while analysis
and interpretation were done based on frequencies, percentages and correlation coefficient.
The researcher used a sample of 86 respondents as indicated in chapter three. Those
questionnaires were distributed to 86 employees of Gisagara District and all questionnaires
were completed.
4.1 Demographic Characteristics of Respondents
In this section, the researcher presents the findings of the research extracted from the data
collection instruments. The researcher focused on distribution of respondents by level of
education, distribution of respondents by experience and distribution of respondents by
position in Gisagara District.
Table 4.2: Distribution of respondents by level of education
Page 30
23
Frequency Percent
Valid Bachelor’s degree 76 88.4
Secondary level 5 5.8
Others certificates 5 5.8
Total 86 100.0
Source: Field Data
Table 4.2 shows the distribution of respondents by level of education, this study revealed that
out of 86 respondents, 76 (88.4%) were Bachelor’s degree, 5(5.8) were secondary level and 5
(5.8) of respondents had other certificates.
Table 4.3: Distribution of respondents by Job experience
Frequency Percent
Valid 1 to two years 3 3.5
3 years and above 83 96.5
Total 86 100.0
Source: Field Data
Concerning the distribution of respondents by job experience, Table 4.3 indicates that out of
86 respondents, 96.51 % of respondent work in Gisagara District above 3 years and 3.49% of
respondents worked in Gisagara District between 1 to 2 years.
Table 4.4: Distribution of respondents by occupation
Page 31
24
Frequency Percent
Valid Executive Secretary Office 16 18.6
Tender Committee 7 8.1
Finance 5 5.8
Logistic 1 1.2
Administration 3 3.5
PM&E 2 2.3
Accountant and executive
secretary on the sector level 52 60.5
Total 86 100.0
Source: Field Data
Table 4.4 indicates that out of 86 respondents, 16 (18.6%) of respondents were from Executive
Secretary Office, 7 (8.1%) were from tender committee, 5 (5.8%) were from finance
department, 1 (1.2%) were from logistic department, 3 (3.5%) were from administration
department, and 2 (2.3%) were from PM&E, 52 (60.5%) were from Accountant and executive
secretary on the sector level.
4.2 Presentation of Findings
This subsection focuses on the objectives of the study, such as to evaluate the Public
Procurement methods used in Gisagrara (2010-2013) to manage public fund, to assess the
factors influence public procurement process in Gisagara District and to establish the
relationship between public procurement and management of public fund.
4.2.1 The Factors Influence Public Procurement process in Gisagara District
This subsection focuses on the factors influence public procurement process in Gisagara
District, such as Requirement identification, Invitation to tender, Procurement method,
Procurement planning, Solicitation document, Pre-bid, Submission of bids, Publication and
Contract award.
Page 32
25
Table 4.5:Procurement planning
Frequency Percent
Valid Strongly agree 10 11.6
Agree 2 2.3
Disagree 69 80.2
Strongly disagree 5 5.8
Total 86 100.0
Source: Field Data
Table 4.5 indicates that out of 86 respondents, 10 (i.e11.6%) strongly agreed that procurement
planning is one of the factors influence public procurement process in Gisagara District, 2 (i.e
2.3%) agreed that procurement planning is one of the factors influence public procurement
process in Gisagara District, 69 (i.e80.2%) of respondents disagreed with the statement and 5
(5.8%) strongly disagreed with the statement.
Table 4.6: Solicitation document
Page 33
26
Frequency Percent
Valid Strongly agree 4 4.7
Agree 5 5.8
Disagree 69 80.2
Strongly disagree 8 9.3
Total 86 100.0
Source: Field Data
Table 4.6 indicates that out of 86 respondents, 4 (i.e4.7%) of respondents strongly agreed that
Solicitation document is one of the factors influence public procurement process in Gisagara
District, 5 (i.e 5.8%) agreed that Solicitation document is one of the factors influence public
procurement process in Gisagara District, 69 (i.e 80.2%) of respondents disagreed with the
statement and 8 (9.3%) strongly disagreed with the statement.
Table 4.7:Pre-bid
Frequency Percent
Valid Strongly agree 86 100.0
Source: Field Data
Table 4.7 indicates that out of 86 respondents, all respondents strongly agreed that Pre-bid is
one of the factors influence public procurement process in Gisagara District.
Table 4.8: Submission of bids
Frequency Percent
Valid Strongly agree 86 100.0
Source: Field Data
Table 4.8 presents that out of 86 respondents, all respondents strongly agreed that Submission
of bids is one of the factors influence public procurement process in Gisagara District.
Table 4.9: Publication
Page 34
27
Frequency Percent
Valid Strongly agree 86 100.0
Source: Field Data
Table 4.9 shows that out of 86 respondents, all respondents strongly agreed that Publication is
one of the factors influence public procurement process in Gisagara District.
Table 4.10: Contract award
Frequency Percent
Valid Strongly agree 86 100.0
Source: Field Data
Table 4.10 presents that out of 86 respondents, all respondents strongly agreed that Contract
award is one of the factors influence public procurement process in Gisagara District.
Figure 4.2: The process of using competitive tendering in Gisagara District
Source: Field Data
Figure 4.2 presents the process of using competitive tendering in Gisagara District. Concerning
submission of bids evaluation, awarding and publication the majority of respondents perceived
that they are useful elements in the process of using competitive tendering. Referring to the
53.3
46.7
66.7
53.3
66.7
33.3
40
26.7
13.3
20
26.7
46.7
6.7
13.3 13.3
6.713.3
20
13.313.3
6.7
0
10
20
30
40
50
60
70
80
Requirementidentification
Invitation totender
Procurementplanning
Submission ofbids
Bid Evaluationand Awarding
Publication
SA
A
NA/ND
D
SD
Page 35
28
law NO 12 / 2007 of 27/ 03 / 2007 in article 6 for procurement planning; this study revealed
that during the procurement planning, the following processes requirement identification,
invitation to tender, submission of bids, bid evaluation and awarding, and the publication of
results should be taken into consideration and ensure that there is a sufficient budget allocation
. Therefore, Gisagara District follows the rules and regulations of Rwanda Public Procurement
Authority in order to improve the efficiency and effectiveness of competitive tendering in
public institutions.
4.2.2 The Public Procurement Methods Used in Gisagrara to Manage Public Fund
This subsection focuses on the Public Procurement methods used in Gisagrara to manage
public fund, such as National Competitive Bidding (NCB), International tendering, Restricted
tendering, Request for quotations, Single source procurement, Force Account and Community
Participation.
Table 4.11: National Competitive Bidding (NCB)
Frequency Percent
Valid Strongly agree 73 84.9
Agree 9 10.5
Disagree 4 4.7
Total 86 100.0
Source: Field Data
Table 4.11 presents that out of 86 respondents, 73 (i.e 84.9%) of respondents strongly agreed
that National Competitive Bidding (NCB) is one of the Public Procurement methods used in
Gisagrara to manage public fund, 9 (i.e 10.5%) agreed that National Competitive Bidding
(NCB)is one of the Public Procurement methods used in Gisagrara to manage public fund and
4 (i.e 4.7%) of respondents disagreed with the statement.
Table 4.12: International tendering
Page 36
29
Frequency Percent
Valid Strongly agree 14 16.3
Agree 16 18.6
Disagree 52 60.5
Strongly disagree 4 4.7
Total 86 100.0
Source: Field Data
Table 4.12 presents that out of 86 respondents, 14 (i.e 16.3%) of respondents strongly agreed
that International tendering is one of the Public Procurement methods used in Gisagrara to
manage public fund, 16 (i.e 18.6%) agreed that International tendering is one of the Public
Procurement methods used in Gisagrara to manage public fund, 52 (i.e 60.5%) of respondents
disagreed with the statement and 4 (4.7%) strongly disagreed with the statement.
Table 4.13: Restricted tendering
Page 37
30
Frequency Percent
Valid Strongly agree 14 16.3
Agree 16 18.6
Disagree 52 60.5
Strongly disagree 4 4.7
Total 86 100.0
Source: Field Data
Table 4.13 shows that out of 86 respondents, 14 (i.e 16.3%) of respondents strongly agreed
that Restricted tendering is one of the Public Procurement methods used in Gisagrara to
manage public fund, 16 (i.e 18.6%) agreed that Restricted tendering is one of the Public
Procurement methods used in Gisagrara to manage public fund, 52 (i.e 60.5%) of respondents
disagreed with the statement and 4 (4.7%) strongly disagreed with the statement.
Table 4.14: Request for quotations
Frequency Percent
Valid Strongly agree 14 16.3
Agree 5 5.8
Disagree 52 60.5
Strongly disagree 15 17.4
Total 86 100.0
Page 38
31
Source: Field Data
Table 4.14 shows that out of 86 respondents, 14 (i.e 16.3%) of respondents strongly agreed
that Restricted tendering is one of the Public Procurement methods used in Gisagrara to
manage public fund, 16 (i.e 18.6%) agreed that Restricted tendering is one of the Public
Procurement methods used in Gisagrara to manage public fund, 52 (i.e 60.5%) of respondents
disagreed with the statement and 4 (4.7%) strongly disagreed with the statement.
Table 4.15: Single source procurement
Frequency Percent
Valid Strongly agree 12 14.0
Agree 7 8.1
Disagree 52 60.5
Strongly disagree 15 17.4
Total 86 100.0
Source: Field Data
Table 4.15 indicates that out of 86 respondents, 12 (i.e 14.0%) of respondents strongly agreed
that Single source procurement is one of the Public Procurement methods used in Gisagrara to
manage public fund, 7 (i.e 8.1%) agreed that Single source procurement is one of the Public
Procurement methods used in Gisagrara to manage public fund, 52 (i.e 60.5%) of respondents
disagreed with the statement and 15 (17.4%) strongly disagreed with the statement.
Page 39
32
Table 4.16:Force Account
Frequency Percent
Valid Strongly agree 7 8.1
Agree 7 8.1
Disagree 52 60.5
Strongly disagree 20 23.3
Total 86 100.0
Source: Field Data
Table 4.16 indicates that out of 86 respondents, 7 (i.e 8.1%) of respondents strongly agreed
that Force Account is one of the Public Procurement methods used in Gisagrara to manage
public fund, 7 (i.e 8.1%) agreed that Force Account is one of the Public Procurement methods
used in Gisagrara to manage public fund, 52 (i.e 60.5%) of respondents disagreed with the
statement and 20 (23.3%) strongly disagreed with the statement.
Page 40
33
Table 4.17: Community Participation
Frequency Percent
Valid Strongly agree 73 84.9
Agree 9 10.5
Disagree 4 4.7
Total 86 100.0
Source: Primary data, 2014
Table 4.17 indicates that out of 86 respondents, 73 (i.e 84.9%) of respondents strongly agreed
that Community Participation is one of the Public Procurement methods used in Gisagrara to
manage public fund, 9 (i.e 10.5%) agreed that Community Participation is one of the Public
Procurement methods used in Gisagrara to manage public fund and 4 (i.e 4.7%) of respondents
disagreed with the statement.
Figure 4.3: The tendering methods adopted by Gisagara District
Source: Field Data
Figure 4.3 presents the tendering methods adopted by Gisagara District. Findings in Figure 4.4
implies that Gisagara District follow law NO 12 / 2007 of 27/ 03 / 2007 in article 23 – 28, where
this law announced that “except where provided otherwise by the law, the procuring entity
shall apply open competitive bidding to supplies, works, goods and other services.. Therefore,
Gisagara District focuses on open competitive tender method to allow different bidders to
participate in the open competitive bidding to give equal chance to the competitors.
73.3
20
53.3
66.7
80
13.320
13.3
26.7
13.3 13.36.76.7 6.7
6.7 6.7
40
13.320
40
26.7 33.3
0
10
20
30
40
50
60
70
80
90
NationalCompetitive
Bidding (NCB)
Internationaltendering
Restrictedtendering
Request forquotations
Single sourceprocurement
CommunityParticipation
SA
A
NA/ND
D
SD
Page 41
34
4.3 Perception of Contractors On Competitive Tendering And Challenges Faced
4.3.2 Challenges Faced By Contactors in Gisagra District
Table 4.18: Delay of payment
Frequency Percent
Valid Strongly agree 23 76.7
Agree 3 10.0
Non agree nor disagree 1 3.3
Disagree 2 6.7
Strongly disagree 1 3.3
Total 30 100.0
Source: Primary data, 2015
Table 4.18 indicates the views of contractors on delay of payment. Out of 30 respondents, 23
respondents (i.e76.7%) strongly agreed delay of payment is among of the challenges faced by
contractors in Gisagra District, 3 respondents (i.e10.0%) agreed, 1 respondent (i.e 3.3%) non
agreed nor disagreed, 2 respondents (i.e 6.7) disagreed and 1 respondents (i.e 3.3%) strongly
disagreed . This implies that, there is a big challenge concerning payment of contactors in
Gisagara District. Therefore, there is a need for Gisagara District to pay on time their contactors
in order to increase the level of integrity in tendering process and encourage competition.
Table 4.19: Time for getting contract
Page 42
35
Frequency Percent
Valid Strongly agree 8 26.7
Agree 2 6.7
Non agree nor disagree 3 10.0
Disagree 8 26.7
Strongly disagree 9 30.0
Total 30 100.0
Source: Field Data
Table 4.19 indicates the time for getting contracts. Out of 30 respondents, 8 respondents
(i.e26.7%) strongly agreed that time for getting contracts is a challenge, 2 respondents
(i.e6.7%) agreed, 3 respondent (i.e10 %) non agreed nor disagreed, 8 respondents (i.e26.7)
disagreed and 9 respondents (i.e30 %) strongly disagreed . This implies that even if majority
of respondents disagreed that the time of getting a contract is not a challenge, but some of
contractors fails to get contract on time and this can affect the contract execution, Gisagara
District have to manage and award contracts on time in order to facilitate contractors in
execution of contracts which encourages competition for future tenders published by Gisagara
District.
Table 4.20: Views of contactors on lack of Skills
Frequency Percent
Valid Strongly agree 7 23.3
Agree 23 76.7
Total 30 100.0
Source: Field Data
Table 4.20 indicates the views of contactors on lack of Skills as among of the factors faced
by the contractors. Out of 7 respondents, 23.3% strongly agreed and 76.7% agreed with the
statement. All respondents confirmed that lack of skills is among of the challenges faced by
contactors in Gisagara District. Therefore, there is a need of capacity building in order to
improve the level of understanding in the District.
Page 43
36
Table 4.21: Lack of transparence
Frequency Percent
Valid Strongly agree 7 23.3
Agree 16 53.3
Disagree 2 6.7
Strongly disagree 5 16.7
Total 30 100.0
Source: Field Data
Table 4.21 indicates that out of 30 respondents, 23.3% strongly agree that lack of transparence
is among of the challenges faced by contactors in Gisagra District, 53.3% agree, 6.7% disagree
and 16.7% strongly disagree.
Table 4.22: Time of contract implementation
Page 44
37
Frequency Percent
Valid Strongly agree 4 13.3
Agree 7 23.3
3.00 = "Non agree nor disagree" 4 13.3
Disagree 7 23.3
Strongly disagree 8 26.7
Total 30 100.0
Source: Field Data
Findings in Table 4.22 indicate time of contract implementation, where out of 30 respondents.4
respondents (i.e 13.3 %) strongly agreed, 7 respondents (i.e 23.3%) agreed, 4 respondent
(i.e13.3%) non agreed nor disagreed, 7 respondents (i.e23.3) disagreed and 8 respondents
(i.e26.7 %) strongly disagreed . This implies that the majority of respondents said that contract
implementation should not affect the competitive tendering in Gisagara District, but there are
some of them who said that contract implementation affect competitive tendering in Gisagara
District. Hence, Gisagara District should improve the level of time of contract implementation
in order to attract and retain new contractors.
Table 4.23: Incomplete specification
Frequency Percent
Valid Strongly agree 8 26.7
Agree 14 46.7
Disagree 5 16.7
Strongly disagree 3 10.0
Total 30 100.0
Source: Field Data
Table 4.23 indicates incomplete specification, out of 30 respondents, 8 respondents (i.e26.7
%) strongly agreed incomplete specification as a challenge faced by contractors, 14
respondents (i.e46.7%) agreed, 5 respondents (i.e16.7%) disagreed and 3 respondents (i.e10.0
%) strongly disagreed. This shows that in Gisagara District, during competitive tendering, the
Page 45
38
contactors face problems concerning specification, and may lead to the supply of poor quality
items, and the procuring entity will be forced to accept the supplies which do not meet the
standards. Incomplete specification misleads the budget allocation, and can also lead to
encoring unnecessary cost and jeopardize the principle of economy in public procurement.
Therefore this study revealed that Gisagra District lacks competent employee to establish
specification in order to manage resources during procurement of goods, works and services.
Table 4.24: Inefficiency of supervision
Frequency Percent
Valid Strongly agree 17 56.7
Agree 10 33.3
Disagree 2 6.7
Strongly disagree 1 3.3
Total 30 100.0
Source: Field Data
Results in Table 4.24 indicate inefficiency of supervision, Outof 30 respondents.17
respondents (i.e56.7 %) strongly agreed with the statement, 10 respondents (i.e33.3%) agreed,
2 respondents (i.e6.7%) disagreed and 1 respondent (i.e 3.3 %) strongly disagreed. This implies
that, the contactors contacted revealed that the ability of supervision during execution of
contact awarded through competitive tendering is not accurate. Poor supervision can
discourage competition in Gisagara District tendering process.
4.3.3 Relationship Between Procurement System and Public Funds Management
This subsection focuses on the relationship between procurement system and public funds
management using Pearson correlation coefficient and SPSS program. The researcher used
perception and opinions of respondents and found relationship between procurement system
and public funds management.
Table 4.25: Relationship between procurement system and public funds management
Page 46
39
Procurement Policy
Public Funds
Management
Procurement Policy Pearson Correlation 1 .565**
Sig. (2-tailed) .000
N 86 86
Public Funds
Management
Pearson Correlation .565** 1
Sig. (2-tailed) .000
N 86 86
**. Correlation is significant at the 0.01 level (2-tailed).
Source: Field Data
Table 4.25 presents the relationship between variables under study, such as procurement
system and public funds management. This research used Pearson correlation coefficient and
found that correlation coefficient (r) equals to 0.565 i.e 56.5%. Therefore, there is a positive
relationship between procurement system and public funds management.
CHAPTER FIVE: SUMMARY, CONCLUSIONS AND RECOMMENDATIONS
5.0 Introduction
This chapter focuses on summary, conclusions, and recommendations. It highlights summary
of findings according to three research objectives, conclusions where the study answer the
research questions, recommendations and ends with suggestions for further study.
5.1 Summary of Findings
This study carried out on procurement systems and public management fund in local
government of Rwanda. The summary of findings are classified according to the research
objectives, such as the Public Procurement methods used in Gisagrara (2010-2013) to manage
Page 47
40
public fund; the factors influence public procurement process in Gisagara District and the
relationship between public procurement and management of public fund.
5.1.1 The Public Procurement Methods Used In Gisagrara (2010-2013) to Manage
Public Fund
Concerning the first research objective, the Public Procurement methods used in Gisagrara
(2010-2013) to manage public fund, out of 86 respondents, 68 (79.1%) strongly agreed that
requirement identification is the factors influence public procurement process in Gisagara
District and 18 (i.e 20.9%) agreed that requirement identification is one of the factors influence
public procurement process in Gisagara District; all respondents strongly agreed that invitation
to tender is the factors influence public procurement process in Gisagara District; out of 86
respondents, 81 (94.2%) strongly agreed that Procurement method is one of the factors
influence public procurement process in Gisagara District, 2 (i.e 2.3%) agreed that
Procurement method is one of the factors influence public procurement process in Gisagara
District and 3 (i.e3.5%) of respondents disagreed with the statement; out of 86 respondents, 10
(i.e11.6%) strongly agreed that procurement planning is one of the factors influence public
procurement process in Gisagara District, 2 (i.e 2.3%) agreed that procurement planning is one
of the factors influence public procurement process in Gisagara District, 69 (i.e80.2%) of
respondents disagreed with the statement and 5 (5.8%) strongly disagreed with the statement;
out of 86 respondents, 4 (i.e4.7%) of respondents strongly agreed that Solicitation document
is one of the factors influence public procurement process in Gisagara District, 5 (i.e 5.8%)
agreed that Solicitation document is one of the factors influence public procurement process
in Gisagara District, 69 (i.e 80.2%) of respondents disagreed with the statement and 8 (9.3%)
strongly disagreed with the statement; all respondents strongly agreed that Submission of bids
is one of the factors influence public procurement process in Gisagara District; all respondents
strongly agreed that Publication is one of the factors influence public procurement process in
Gisagara District and then all respondents strongly agreed that Contract award is one of the
factors influence public procurement process in Gisagara District
5.1.2 The Factors Influence Public Procurement Process in Gisagara District
Concerning the second research objective, the factors influence public procurement process in
Gisagara District, out of 86 respondents, 73 (i.e 84.9%) of respondents strongly agreed that
National Competitive Bidding (NCB) is one of the Public Procurement methods used in
Gisagrara to manage public fund, 9 (i.e 10.5%) agreed that National Competitive Bidding
(NCB)is one of the Public Procurement methods used in Gisagrara to manage public fund and
4 (i.e 4.7%) of respondents disagreed with the statement; out of 86 respondents, 14 (i.e 16.3%)
of respondents strongly agreed that International tendering is one of the Public Procurement
methods used in Gisagrara to manage public fund, 16 (i.e 18.6%) agreed that International
tendering is one of the Public Procurement methods used in Gisagrara to manage public fund,
52 (i.e 60.5%) of respondents disagreed with the statement and 4 (4.7%) strongly disagreed
with the statement; out of 86 respondents, 14 (i.e 16.3%) of respondents strongly agreed that
Restricted tendering is one of the Public Procurement methods used in Gisagrara to manage
public fund, 16 (i.e 18.6%) agreed that Restricted tendering is one of the Public Procurement
methods used in Gisagrara to manage public fund, 52 (i.e 60.5%) of respondents disagreed
with the statement and 4 (4.7%) strongly disagreed with the statement; out of 86 respondents,
Page 48
41
14 (i.e 16.3%) of respondents strongly agreed that Restricted tendering is one of the Public
Procurement methods used in Gisagrara to manage public fund, 16 (i.e 18.6%) agreed that
Restricted tendering is one of the Public Procurement methods used in Gisagrara to manage
public fund, 52 (i.e 60.5%) of respondents disagreed with the statement and 4 (4.7%) strongly
disagreed with the statement; out of 86 respondents, 12 (i.e 14.0%) of respondents strongly
agreed that Single source procurement is one of the Public Procurement methods used in
Gisagrara to manage public fund, 7 (i.e 8.1%) agreed that Single source procurement is one of
the Public Procurement methods used in Gisagrara to manage public fund, 52 (i.e 60.5%) of
respondents disagreed with the statement and 15 (17.4%) strongly disagreed with the
statement; out of 86 respondents, 7 (i.e 8.1%) of respondents strongly agreed that Force
Account is one of the Public Procurement methods used in Gisagrara to manage public fund,
7 (i.e 8.1%) agreed that Force Account is one of the Public Procurement methods used in
Gisagrara to manage public fund, 52 (i.e 60.5%) of respondents disagreed with the statement
and 20 (23.3%) strongly disagreed with the statement; out of 86 respondents, 73 (i.e 84.9%) of
respondents strongly agreed that Community Participation is one of the Public Procurement
methods used in Gisagrara to manage public fund, 9 (i.e 10.5%) agreed that Community
Participation is one of the Public Procurement methods used in Gisagrara to manage public
fund.
5.1.3 Challenges Faced By Contactors in Gisagra District
Concerning the third objective, challenges faced by contactors in Gisagra District, out of 30
respondents, 23 respondents (i.e76.7%) strongly agreed delay of payment is among of the
challenges faced by contractors in Gisagra District, 3 respondents (i.e10.0%) agreed, 1
respondent (i.e 3.3%) non agreed nor disagreed, 2 respondents (i.e 6.7) disagreed and 1
respondents (i.e 3.3%) strongly disagreed, Out of 30 respondents, 8 respondents (i.e26.7%)
strongly agreed that time for getting contracts is a challenge, 2 respondents (i.e6.7%) agreed,
3 respondent (i.e10 %) non agreed nor disagreed, 8 respondents (i.e26.7) disagreed and 9
respondents (i.e30 %) strongly disagreed. Concerning time of contract implementation, out of
30 respondents.4 respondents (i.e 13.3 %) strongly agreed, 7 respondents (i.e 23.3%) agreed,
4 respondent (i.e13.3%) non agreed nor disagreed, 7 respondents (i.e23.3) disagreed and 8
respondents (i.e26.7 %) strongly disagreed; out of 30 respondents, 8 respondents (i.e26.7 %)
strongly agreed incomplete specification as a challenge faced by contractors, 14 respondents
(i.e46.7%) agreed, 5 respondents (i.e16.7%) disagreed and 3 respondents (i.e10.0 %) strongly
disagreed, out of 30 contractors, 27 (i.e 90%) of respondents confirmed that Gisagara District
advertise its tenders, while 3 (10%) respondents did not confirm the advertisement of tender;
out of 30 contractors, 17 respondents confirmed that they are satisfied with the tenders
approaches for Gisagara District, while 13 respondents were not satisfied. Even if, the majority
of respondents were satisfied, they are some contractors who were not satisfied; out of 30
contractors, 23 respondents consider the tendering approach open and competitive in Gisagara
District, while 7 respondents do not consider the approach open and competitive.
5.1.4 The Relationship Between Public Procurement And Management Of Public
Fund
This subsection focuses on the relationship between procurement system and public funds
management using Pearson correlation coefficient and SPSS program. The researcher used
Page 49
42
perception and opinions of respondents and found relationship between procurement system
and public funds management. This research used Pearson correlation coefficient and found
that correlation coefficient (r) equals to 0.565 i.e 56.5%. Therefore, there is a positive
relationship between procurement system and public funds management.
5.2 Conclusions
Gisagara District advertises through newspapers as it is requested that “the procurement
method shall advertise the tender notice in at least one newspaper of nation- wide circulation.”
This is confirming the information, where Gisagara District follows Rwanda Public
Procurement Authority laws, the processes of competitive tendering in Gisagara District
optimize procurement cost and time consuming for both sides. Procurement in Gisagara
District gave procurement entity the best values for money through competitive tendering.
Gisagara Distrcit employees analyze the cost and expenses that occurred during competitive
tendering process compared to the budget allocated to procurement for works, goods and
services in procurement plan for the fiscal year and found that some savings accrued due to the
competition, where different bidders compete and optimize prices in order to win the tender.
Gisagara Distrcit employees analyze the cost and expenses that occurred during competitive
tendering process compared to the budget allocated to procurement for works, goods and
services in procurement plan for the fiscal year and found that some savings accrued due to the
competition, where different bidders compete and optimize prices in order to win the tender.
Even if the majority of respondents said that Gisagara District humanize corruption and
irregularities through Competitive tendering, there was some employees of Gisagara District
who said that there was no humanization of corruption and irregularities. This implies that,
there should be some tendering that tend to corruption and irregularities in Gisagara Distrcit.
Concerning submission of bids, bid evaluation, awarding and publication the majority of
respondents perceived that they are useful elements in the process of using competitive
tendering.
Referring to the law NO 12 / 2007 of 27/ 03 / 2007 in article 6 for procurement planning; this
study revealed that during the procurement planning, the following processes requirement
identification, invitation to tender, submission of bids, bid evaluation and awarding, and the
publication of results should be taken into consideration and ensure that there is a sufficient
Page 50
43
budget allocation . Therefore, Gisagara District follows the rules and regulations of Rwanda
Public Procurement Authority in order to improve the efficiency and effectiveness of
competitive tendering in public institutions.
Gisagara District follow law NO 12 / 2007 of 27/ 03 / 2007 in article 23 – 28, where this law
announced that “except where provided otherwise by the law, the procuring entity shall apply
open competitive bidding to supplies, works, goods and other services.. Therefore, Gisagara
District focuses on open competitive tender method to allow different bidders to participate in
the open competitive bidding to give equal chance to the competitors. Concerning quality of
Service, competition between suppliers and kind of transparency, the majority of respondents
perceived that, these are the advantages of competitive tendering in Gisagara District.
Therefore, the researcher perceives that competitive tendering facilitate goals achievement
and performance contact in Gisagara District.
The study also concluded that, there is a big challenge concerning payment of contactors in
Gisagara District. Therefore, there is a need for Gisagara District to pay on time their contactors
in order to increase the level of integrity in tendering process and encourage competition.
During competitive tendering, the contactors face problems concerning specification, and may
lead to the supply of poor quality items, and the procuring entity will be forced to accept the
supplies which do not meet the standards. Incomplete specification misleads the budget
allocation, and can also lead to encoring unnecessary cost and jeopardize the principle of
economy in public procurement. Therefore this study revealed that Gisagara District lacks
competent employee to establish specification in order to manage resources during
procurement of goods, works and services.
5.3 Recommendations
The study findings yielded the following recommendations in view of procurement and public
funds management. To enable meaningful participation, even if majority of respondents
disagreed that the time of getting a contract is not a challenge, but some of contractors fails to
get contract on time and this can affect the contract execution, Gisagara District have to manage
and award contracts on time in order to facilitate contractors in execution of contracts which
encourages competition for future tenders published by Gisagara District. the majority of
respondents said that contract implementation should not affect the competitive tendering in
Gisagara District, but there are some of them who said that contract implementation affect
competitive tendering in Gisagara District. Hence, Gisagara District should improve the level
of time of contract implementation in order to attract and retain new contractors. Lastly, this
study recommends that;
Regarding lower managerial skills of some Gisagara District employees, the researcher
recommends that Gisagara District should improve mobilization in the field of managerial
skills and competitive tendering, whereby these should leads to the increase in competition.
This research also recommends that RPPA should make follow up on the rules, regulations and
policies procurement in local government. This study revealed that Gisagara District used
Newspaper during advertisement process. Hence, it should increase the means of
advertisement, by using Radios and Televisions.
Page 51
44
Government of Rwanda is among of the world wide country with zero tolerance country in
corruption; therefore, this study recommends Gisagara District to follow the strategies set for
fitting against corruption.
5.4 Suggestions for Further Study
This study focused on procurement and public funds management; hence future researchers
should focus on; the contribution of procurement to the financial performance of institutions,
procurement and good governance, the contribution of procurement to employee performance
in private institutions, the contribution of procurement to the value of money.
REFERENCES Alm, N. (2000). Bank Management (4th Ed ed.). London: Dryden Press.
Arozamena, L. & Weinschelbaum, F. (2009). The effect of corruption on biddingbehavior in
first-price auctions. European Economic Review, vol.52, pp.645-657.
Audet, D. (2002). Government Procurement. Journal of bugdeting, vol.2(3), pp.149 - 194.
Benslimane, Y.; Plaisent, M. & Bernard, P. (2005). Investigating Search Costs and
Coordination Costs in Electronic Markets: A Transaction Costs Economics
Perspective. London, UK: Electronic market.
Bovis, C.H. (2007). European Union Public ProcurementLaw, Elgar European Law series.
London: Edward Elgar.
Brackus, D. (2000). A Model of US financial and Non – financial economic Bahaviour. journal
of money, vol.12, pp. 259-293.
Page 52
45
Brammer & Walker. (2011). Sustainable Procurement In The Public Sector: An International
Comparative Study. International Journal Of Operations And Production
Management, Vol.31(4), Pp.452-476.
Burguet, R. & Che, Y.K. (2004 ). Competitive procurement with corruption. Journal of
economics, pp.108 - 119.
Caldwell, N.D., Roehrich, J.K. & Davies, A.C. (2009). Procuring Complex Performance in
Construction: London Heathrow Terminal 5 and a Private Finance Initiative Hospital.
Journal of Purchasing and Supply Management, pp.118 - 11- 24.
Deloof, D. (2003). Does Working Capital Management affect Profitability of Belgian Firms.
Journal of Business Finance and Accounting, Vol 30 (3 & 4), pp.573 – 587.
Falope, O.I. & Ajilore, O.T. (2009). Working capital management and corporate profitability:
evidence from panel data analysis of selected quoted companies in Niberia. Research
Journal of Business Management, pp.3:73 – 84.
Fayomi & Ikeoluwapo, O. (2013). Public procurement and due process policy in Nigeria:
Thrust, prospects and challenges. Peak Journal of Social Sciences and Humanities,
Vol.1(4), PP. 39-45.
George, B., Cynthia, A., Berg, Judith, A., Doll. (2004). A guide to the project management
body of knowledge (3 ed.). New York, USA: Project management institute.
International Development Association[IBRD]&International Development Association
[IDA] . (2004). Procurement of Goods. Washington ,D.C: Consulting services.
Jorge, E. (2012). Understanding Iraq’s Understanding Iraq’s. Barghdad / Iraq: New Frontiers
Business Consulting.
Kalubanga, M. (2012). Sustainable Procurement: Concept, And Practical Implications For The
Procurement Process. International Journal Of Economics And Management Science,
Vol.1(7), Pp.01-07.
Kiage, J. O. (2013). Factors Affecting Procurement Performance: A Case Of Ministry Of
Energy. International Journal Of Business And Commerce, Vol.3(1), Pp.54-70.
Kotabo, K. (2002). Management of Finance Company (Sixth Edition ed.). London:
International Thomson Business Press.
Kotler, P. (2002). Marketing Management (2nd ed.). India: The Millennium Edition.
Lewis, M.A. & Roehrich, J.K. (2008). Contracts, Relationships and Integration: Towards a
Model of the Procurement of Complex Performance,. International Journal of
Procurement Management, 112 - 124.
Mangan, J., Lalwani, C. & Butcher, T. (2008). Global Logistics and Supply Chain
management. New Jersey: John Wiley and Sons.
Maurer, R. (2004). One Small Step Can Change Your Life. Workman: Kaizen.
Page 53
46
Ministry of planning, Economic finance [MINECOFIN]. (2007). Economic development and
poverty reduction strategy 2008-2012. Kigali: Government of Rwanda.
Mulwa, J. K., Jeremiah, M.& Joash, M. (2013). Determinants of implementation of public
procurement regulations in Kenya’s secondary schools. International Journal of
Educational Research and Reviews, vol.2(1), pp. 9-16.
Nakamura, D. (2004). Untrained Staffers Blamed for Costing City Thousands. Washington :
Washington Post.
Ogunsanmi, O. (2013). Effects Of Procurement Related Factors On Construction Project
Performance In Nigeria. Ethiopian Journal Of Environmental Studies And Mana,
Vol.6(2), Pp.215 - 222.
Organization for Economic Co-operation and Development [OECD]. (2007). Bribery in Public
Procurement : Methods, actors and counter-measures. Kigali: OECD.
Raheman, A & Nasr, M. (2009). Working capital managementand profitability – case of
Pakistani firms. International Review of Business Research Papers, vol., pp.279 – 300.
Rainer, K. & Veiko, L. (2010). Public Procurement As An Industrial Policy Tool:An Option
For Developing Countries. Journal Of Public Procurement, Vol.10(3), pp.368-404.
Rwanda Public Procurement Authority [RPPA]. (2010). Public Procurement User Guide.
Kigali: Rwanda Public Procurement Authrority.
Rwanda Public Procurement Authority [RPPA]. (2012). Information, Education and
Communication Strategy for RPPA. Kigali: Government of Rwanda.
Saunders, M., Levin, P., & Thornhill, A. (2009). Research Methods for Business student.
London: Prentice-Hall.
Shaw, F. (2010). the Power to Procure: A Look inside the City of Austin Procurement Program
Applied Research Projects. Texas: Texas State University.
Stephen, O. & Imeh, J. (2013). Determining The Performance Of Procurement Methods
Against Selection Criteria Using Outranking – Satisfying Methodology. Journal Of
Engineering, Project, And Production Management, Vol.3(2), Pp.74-84.
Thai, K. V. (2011). Public Procurement Re-Examined In Nigeria. Journal Of Public
Procurement, Vol.1(1), PP.9-50.
Transparency Rwanda. (2012). Annual Report 2011 / 2012. Kigali: Government of Rwanda.
Velnampy, T & Kamalarupan,K. (2009). Evaluation of factors influencing effective
procurement management system of public sectors evaluation. Jaffna: University of
Jaffna.
Wardani, M. A. (2004). Comparing Procurement Methods. Pennsylvania: The Pennsylvania
State University.
Page 54
47
Weele, A. (2010). Purchasing and Supply Chain Management: Analysis, Strategy, Planning
and Practice. Washington, DC: World bank.
World Bank. (2011). The International Bank for Reconstruction and Development.
Washington, D.C, USA: World bank.
Page 55
QUESTIONNAIRE
QUESTIONAIRE ADDRESSED TO GISAGARA DISTRICT EMPLOYEES
A. QUESTIONS REGARDING TO RESPONDENT PROFILE
1. Level of education
PHD
Masters
Bachelors
Secondary level
Others
2. Job experience:
Less than 1 year
1-2 years
3- 5 years
Above 5 years
3. Occupation category within Gisagara district
Executive Secretary Office
Tender Committee
Finance
Logistic
Administration
Planning, monitoring and evaluation
Fill the following tables using Strongly Agree (SA), agree (A), Disagree (D) and Strongly
Disagree
4. Factors affect Public Procurement
process in Gisagara SA A D SD
Procurement planning Solicitation document Pre-bid Submission of bids
Page 56
b
Bid Evaluation and Awarding Publication Contract award
What are the other factors should influence public procurement process in Gisagara District?
The Public Procurement methods used in Gisagara to manage public funds
The Public Procurement methods used
in Gisagara to manage public funds
SA A D SD
National Competitive Bidding (NCB) International tendering Restricted tendering Request for quotations Single source procurement/direct
contracting
Force Account Community Participation
Are there other public procurement methods used in Gisagara to manage public funds?
If yes, what are they?
Thank you
QUESTIONAIRE ADDRESSED TO GISAGARA DISTRICT CONTRACTORS
Page 57
c
1. What are challenges do you face in Tendering Process
List of challenges SA A NA/ND D SD Delay of payment Time for getting contract Time of contract implementation Incomplete specification Lack of skills
2. Does Gisagara district advertise the tender? Yes No
3. Are you satisfied with the tender approaches? yes No
4. Do you consider the approach open and competitive? Yes No