Top Banner
Procurement of Bulk Materials Handling Machines Richard Morgan Director
39

Procurement of bulk materials handling machines

Jan 15, 2017

Download

Engineering

rmorgan1209
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Procurement of bulk materials handling machines

Procurement of Bulk Materials Handling

MachinesRichard Morgan

Director

Page 2: Procurement of bulk materials handling machines

• Stackers• Reclaimers• Stacker/Reclaimers• Shiploaders• In-pit systems

Equipment Types

Page 3: Procurement of bulk materials handling machines
Page 4: Procurement of bulk materials handling machines
Page 5: Procurement of bulk materials handling machines
Page 6: Procurement of bulk materials handling machines
Page 7: Procurement of bulk materials handling machines

• Custom designed• Long lead Time• High cost• Critical elements in supply chain

Features

Page 8: Procurement of bulk materials handling machines

Identifying requirements

• Configuration• Specification & procurement documents• Modularisation

Page 9: Procurement of bulk materials handling machines

Configuration

Page 10: Procurement of bulk materials handling machines
Page 11: Procurement of bulk materials handling machines
Page 12: Procurement of bulk materials handling machines
Page 13: Procurement of bulk materials handling machines
Page 14: Procurement of bulk materials handling machines

Specification

• Define design, material and quality requirements

• Ensure configuration and performance can be met realistically

• Good knowledge of the design standards• Industry experts should be consulted to

ensure that problems are not repeated• Operators and maintainers should review

Page 15: Procurement of bulk materials handling machines

• Common practice for shiploaders • Now possible for land based machines such as

stackers and reclaimers • Considerable savings in onsite labour. • Allows procurement from overseas where

costs are lower than in Australia. • Include transport load cases and sea

fastenings

Modularisation

Page 16: Procurement of bulk materials handling machines
Page 17: Procurement of bulk materials handling machines
Page 18: Procurement of bulk materials handling machines
Page 19: Procurement of bulk materials handling machines
Page 20: Procurement of bulk materials handling machines
Page 21: Procurement of bulk materials handling machines
Page 22: Procurement of bulk materials handling machines

Type of contract

• Design and Construct (EPC) - Single Contract• Design and Supply – (Installation &

Commissioning Separate)• Design Contract – (Supply, Installation &

Commissioning Separate)

Page 23: Procurement of bulk materials handling machines

Challenges with overseas procurement• Design

– Design by Experienced OEM - Fabrication Overseas

– Design by new entrant OEM - Fabrication Overseas

Page 24: Procurement of bulk materials handling machines

Challenges with overseas procurement

• Standards• Materials Substitution• Fabrication

– Main Structure– Access– Machining– Protective Coatings– Trial Assembly

Page 25: Procurement of bulk materials handling machines

Challenges with overseas procurement

• Vendor Items• Electrical Installation• Commissioning

Page 26: Procurement of bulk materials handling machines
Page 27: Procurement of bulk materials handling machines
Page 28: Procurement of bulk materials handling machines
Page 29: Procurement of bulk materials handling machines
Page 30: Procurement of bulk materials handling machines

Overseas procurement - lessons• Detailed review of specifications pre award• Australian Standards discussed pre-award• Review of the 3D model is needed• Adequate translation resources needed • Access design considered throughout the

design phase, not at the end.• Supplier design 100% prior to placing orders • Constructability review of design

Page 31: Procurement of bulk materials handling machines

Effective quality control and supervision

• Design Phase– Effective Specification Key Dimensions properly thought out Interfaces Well Defined Machine Loads required by other designers– Owners Engineer Role– Design Audit

Page 32: Procurement of bulk materials handling machines

• AS 4324.1 Appendix K guidance for engagement of a design audit engineer

• Engage Design audit engineer before specification for machine is finalized

• Involve audit engineer in tender review

Design Audit

Page 33: Procurement of bulk materials handling machines

Effective quality control and supervision

• Fabrication Phase– Owners Engineer Role– Local Inspectors

Page 34: Procurement of bulk materials handling machines

Shipment, site erection and commissioning

• Modular Construction• Packing• Road Transport o/s• Shipment• Road Transport in Country• Erection/Installation Phase• Cut in

Page 35: Procurement of bulk materials handling machines

Shipment, site erection and commissioning

• Commissioning• Deconstruction

Page 36: Procurement of bulk materials handling machines

Shipment•

Page 37: Procurement of bulk materials handling machines

Installation

Page 38: Procurement of bulk materials handling machines

Deconstruction

Page 39: Procurement of bulk materials handling machines

THANK YOU