Page 1
PHILIPPINE BIDDING DOCUMENTS
(As Harmonized with Development Partners)
Procurement of INFRASTRUCTURE PROJECTS
CONSTRUCTION OF GATE FOUR
FAÇADE AND FENCE IN BATANGAS
STATE UNIVERSITY PABLO BORBON
Project ID Number : 2021-138
Project Location : Rizal Avenue Extension,
Batangas City
Government of the Republic of the Philippines
BATANGAS STATE UNIVERSITY
Sixth Edition
July 2020
Page 2
1
Preface
These Philippine Bidding Documents (PBDs) for the procurement of Infrastructure
Projects (hereinafter referred to also as the “Works”) through Competitive Bidding have been
prepared by the Government of the Philippines for use by all branches, agencies, departments,
bureaus, offices, or instrumentalities of the government, including government-owned and/or
-controlled corporations, government financial institutions, state universities and colleges,
local government units, and autonomous regional government. The procedures and practices
presented in this document have been developed through broad experience, and are for
mandatory use in projects that are financed in whole or in part by the Government of the
Philippines or any foreign government/foreign or international financing institution in
accordance with the provisions of the 2016 revised Implementing Rules and Regulations (IRR)
of Republic Act (RA) No. 9184.
The PBDs are intended as a model for admeasurements (unit prices or unit rates in a
bill of quantities) types of contract, which are the most common in Works contracting.
The Bidding Documents shall clearly and adequately define, among others: (i) the
objectives, scope, and expected outputs and/or results of the proposed contract; (ii) the
eligibility requirements of Bidders; (iii) the expected contract duration; and (iv) the obligations,
duties, and/or functions of the winning Bidder.
Care should be taken to check the relevance of the provisions of the PBDs against the
requirements of the specific Works to be procured. If duplication of a subject is inevitable in
other sections of the document prepared by the Procuring Entity, care must be exercised to
avoid contradictions between clauses dealing with the same matter.
Moreover, each section is prepared with notes intended only as information for the
Procuring Entity or the person drafting the Bidding Documents. They shall not be included in
the final documents. The following general directions should be observed when using the
documents:
a. All the documents listed in the Table of Contents are normally required for the
procurement of Infrastructure Projects. However, they should be adapted as
necessary to the circumstances of the particular Project.
b. Specific details, such as the “name of the Procuring Entity” and “address for
bid submission,” should be furnished in the Instructions to Bidders, Bid Data
Sheet, and Special Conditions of Contract. The final documents should contain
neither blank spaces nor options.
c. This Preface and the footnotes or notes in italics included in the Invitation to
Bid, BDS, General Conditions of Contract, Special Conditions of Contract,
Specifications, Drawings, and Bill of Quantities are not part of the text of the
final document, although they contain instructions that the Procuring Entity
should strictly follow.
d. The cover should be modified as required to identify the Bidding Documents as
to the names of the Project, Contract, and Procuring Entity, in addition to date
of issue.
Page 3
2
e. Modifications for specific Procurement Project details should be provided in the
Special Conditions of Contract as amendments to the Conditions of Contract.
For easy completion, whenever reference has to be made to specific clauses in
the Bid Data Sheet or Special Conditions of Contract, these terms shall be
printed in bold typeface on Sections I (Instructions to Bidders) and III (General
Conditions of Contract), respectively.
f. For guidelines on the use of Bidding Forms and the procurement of Foreign-
Assisted Projects, these will be covered by a separate issuance of the
Government Procurement Policy Board.
Page 4
3
TABLE OF CONTENTS
Glossary of Terms, Abbreviations, and Acronyms ..........................................5
Section I. Invitation to Bid .................................................................................8
Section II. Instructions to Bidders .................................................................. 12
1. Scope of Bid ............................................................................................................13
2. Funding Information ...............................................................................................13
3. Bidding Requirements .............................................................................................13
4. Corrupt, Fraudulent, Collusive, Coercive, and Obstructive Practices ....................13
5. Eligible Bidders .......................................................................................................14
6. Origin of Associated Goods ....................................................................................14
7. Subcontracts ............................................................................................................14
8. Pre-Bid Conference .................................................................................................14
9. Clarification and Amendment of Bidding Documents............................................14
10. Documents Comprising the Bid: Eligibility and Technical Components ...............15
11. Documents Comprising the Bid: Financial Component .........................................15
12. Alternative Bids ......................................................................................................16
13. Bid Prices ................................................................................................................16
14. Bid and Payment Currencies ...................................................................................16
15. Bid Security .............................................................................................................16
16. Sealing and Marking of Bids...................................................................................16
17. Deadline for Submission of Bids ............................................................................16
18. Opening and Preliminary Examination of Bids ......................................................17
19. Detailed Evaluation and Comparison of Bids .........................................................17
20. Post Qualification ....................................................................................................17
21. Signing of the Contract ...........................................................................................17
Section III. Bid Data Sheet .............................................................................. 18
Section IV. General Conditions of Contract ................................................. 20
1. Scope of Contract ....................................................................................................21
2. Sectional Completion of Works ..............................................................................21
3. Possession of Site ....................................................................................................21
4. The Contractor’s Obligations ..................................................................................21
5. Performance Security ..............................................................................................22
6. Site Investigation Reports .......................................................................................22
Page 5
4
7. Warranty ..................................................................................................................22
8. Liability of the Contractor .......................................................................................22
9. Termination for Other Causes .................................................................................22
10. Dayworks ................................................................................................................23
11. Program of Work.....................................................................................................23
12. Instructions, Inspections and Audits .......................................................................23
13. Advance Payment....................................................................................................23
14. Progress Payments ..................................................................................................23
15. Operating and Maintenance Manuals......................................................................23
Section V. Special Conditions of Contract..................................................... 25
Section VI. Specifications ................................................................................ 27
Section VII. Drawings ...................................................................................... 28
Section VIII. Bill of Quantities ..................................................................... 120
Section IX. Checklist of Technical and Financial Documents ................... 121
Page 6
5
Glossary of
Terms, Abbreviations, and Acronyms
ABC – Approved Budget for the Contract.
ARCC – Allowable Range of Contract Cost.
BAC – Bids and Awards Committee.
Bid – A signed offer or proposal to undertake a contract submitted by a bidder in response to
and in consonance with the requirements of the bidding documents. Also referred to as
Proposal and Tender. (2016 revised IRR, Section 5[c])
Bidder – Refers to a contractor, manufacturer, supplier, distributor and/or consultant who
submits a bid in response to the requirements of the Bidding Documents. (2016 revised IRR,
Section 5[d])
Bidding Documents – The documents issued by the Procuring Entity as the bases for bids,
furnishing all information necessary for a prospective bidder to prepare a bid for the Goods,
Infrastructure Projects, and/or Consulting Services required by the Procuring Entity. (2016
revised IRR, Section 5[e])
BIR – Bureau of Internal Revenue.
BSP – Bangko Sentral ng Pilipinas.
CDA – Cooperative Development Authority.
Consulting Services – Refer to services for Infrastructure Projects and other types of projects
or activities of the GOP requiring adequate external technical and professional expertise that
are beyond the capability and/or capacity of the GOP to undertake such as, but not limited to:
(i) advisory and review services; (ii) pre-investment or feasibility studies; (iii) design; (iv)
construction supervision; (v) management and related services; and (vi) other technical services
or special studies. (2016 revised IRR, Section 5[i])
Contract – Refers to the agreement entered into between the Procuring Entity and the Supplier
or Manufacturer or Distributor or Service Provider for procurement of Goods and Services;
Contractor for Procurement of Infrastructure Projects; or Consultant or Consulting Firm for
Procurement of Consulting Services; as the case may be, as recorded in the Contract Form
signed by the parties, including all attachments and appendices thereto and all documents
incorporated by reference therein.
Contractor – is a natural or juridical entity whose proposal was accepted by the Procuring
Entity and to whom the Contract to execute the Work was awarded. Contractor as used in these
Bidding Documents may likewise refer to a supplier, distributor, manufacturer, or consultant.
CPI – Consumer Price Index.
DOLE – Department of Labor and Employment.
Page 7
6
DTI – Department of Trade and Industry.
Foreign-funded Procurement or Foreign-Assisted Project – Refers to procurement whose
funding source is from a foreign government, foreign or international financing institution as
specified in the Treaty or International or Executive Agreement. (2016 revised IRR, Section
5[b]).
GFI – Government Financial Institution.
GOCC – Government-owned and/or –controlled corporation.
Goods – Refer to all items, supplies, materials and general support services, except Consulting
Services and Infrastructure Projects, which may be needed in the transaction of public
businesses or in the pursuit of any government undertaking, project or activity, whether in the
nature of equipment, furniture, stationery, materials for construction, or personal property of
any kind, including non-personal or contractual services such as the repair and maintenance of
equipment and furniture, as well as trucking, hauling, janitorial, security, and related or
analogous services, as well as procurement of materials and supplies provided by the Procuring
Entity for such services. The term “related” or “analogous services” shall include, but is not
limited to, lease or purchase of office space, media advertisements, health maintenance
services, and other services essential to the operation of the Procuring Entity. (2016 revised
IRR, Section 5[r])
GOP – Government of the Philippines.
Infrastructure Projects – Include the construction, improvement, rehabilitation, demolition,
repair, restoration or maintenance of roads and bridges, railways, airports, seaports,
communication facilities, civil works components of information technology projects,
irrigation, flood control and drainage, water supply, sanitation, sewerage and solid waste
management systems, shore protection, energy/power and electrification facilities, national
buildings, school buildings, hospital buildings, and other related construction projects of the
government. Also referred to as civil works or works. (2016 revised IRR, Section 5[u])
LGUs – Local Government Units.
NFCC – Net Financial Contracting Capacity.
NGA – National Government Agency.
PCAB – Philippine Contractors Accreditation Board.
PhilGEPS - Philippine Government Electronic Procurement System.
Procurement Project – refers to a specific or identified procurement covering goods,
infrastructure project or consulting services. A Procurement Project shall be described,
detailed, and scheduled in the Project Procurement Management Plan prepared by the agency
which shall be consolidated in the procuring entity's Annual Procurement Plan. (GPPB Circular
No. 06-2019 dated 17 July 2019)
PSA – Philippine Statistics Authority.
SEC – Securities and Exchange Commission.
Page 8
7
SLCC – Single Largest Completed Contract.
UN – United Nations.
Page 9
8
Section I. Invitation to Bid
Notes on the Invitation to Bid
The Invitation to Bid (IB) provides information that enables potential Bidders to decide
whether to participate in the procurement at hand. The IB shall be posted in accordance with
Section 21.2 of the 2016 revised IRR of RA No. 9184.
Apart from the essential items listed in the Bidding Documents, the IB should also indicate
the following:
a. The date of availability of the Bidding Documents, which shall be from the time the
IB is first advertised/posted until the deadline for the submission and receipt of bids;
b. The place where the Bidding Documents may be acquired or the website where it
may be downloaded;
c. The deadline for the submission and receipt of bids; and
d. Any important bid evaluation criteria.
The IB should be incorporated into the Bidding Documents. The information contained in
the IB must conform to the Bidding Documents and in particular to the relevant information
in the Bid Data Sheet.
Page 10
9
Invitation to Bid for
Construction of Gate Four Façade and Fence
in Batangas State Unviersity Pablo Borbon
1. The Batangas State University, through the Supplemental Budget 2021 intends to
apply the sum of Nineteen Million Eight Hundred Thirty One Thousand Sixty pesos
(Php 19,831,060.00) being the Approved Budget for the Contract (ABC) to payments
under the contract for Construction of Gate Four Façade and Fence in Batangas
State University Pablo Borbon. Bids received in excess of the ABC shall be
automatically rejected at bid opening.
2. The Batangas State University, now invites bids for the above Procurement Project.
Completion of the Works is required One Hundred Eighty (180) calendar days.
Bidders should have completed a contract similar to the Project. The description of an
eligible bidder is contained in the Bidding Documents, particularly, in Section II
(Instructions to Bidders).
3. Bidding will be conducted through open competitive bidding procedures using non-
discretionary “pass/fail” criterion as specified in the 2016 revised Implementing Rules
and Regulations (IRR) of Republic Act (RA) No. 9184.
4. A complete set of Bidding Documents may be acquired by interested bidders on May
10, 2021 – June 10, 2021 by downloading the same, free of charge from the website of
PhilGEPS and the Batangas State University website (https://www.batstate-u.edu.ph).
Provided, however, that bidders shall pay the applicable fee for bidding documents,
pursuant to the Guidelines issued by GPPB, not later than the submission of their bids.
The amount of the bidding documents is Twenty Thousand Pesos only (Php 20,000.00)
which should be directly deposited to the account of Batangas State University only upon
coordination to the BAC Secretariat for the details of payment.
5. The Batangas State University will hold a Pre-Bid Conference on May 18, 2021 @ 2:00
PM at Bids and Awards Committee (BAC) Conference Room, Second Floor SSC
Building, Batangas State University, Pablo Borbon Main I, Rizal Avenue Extension,
Batangas City which shall be open to prospective bidders. The Pre – bid conference shall
be done through Zoom Video Conferencing or other video conferencing applications
which shall be announce prior to the pre bid conference. To facilitate the online meeting
requirements prospective bidders must communicate before the schedule his/her
Page 11
10
intention to participate/attend the pre-bid conference. Upon receipt of the
communication, the secretariat shall send online meeting link.
6. All bids must be accompanied by a bid security in any of the acceptable form in the
amount stated in ITB Clause 16.
Bids must be duly received by the BAC Secretariat at the address below on or before
2:00 PM on June 10, 2021. All bids must be accompanied by a bid security in any of
the acceptable forms and in the amount stated in ITB Clause 16.
All bids shall be submitted only through registered mail or private courier. No bid
shall be submitted personally.
All bidders who submitted their bids must notify the BAC through email, telephone and
cellphone calls and text messaging to confirm that they have send their bids and all
documents relative thereto. In the email, the bidder must attach the proof of sending of
the said documents (i.e. actual photo of the envelopes and the official receipt issued by
the post office or by the courier).
The bidders must assure that their bids shall be forwarded by the courier to the University
on the date and time of the bid opening. The bidders have the responsibility to track their
documents with the courier. The date of receipt of bids shall be the date of sending of
documents, provided that the documents are actually received by the Secretariat. The
BAC shall bear no responsibility whatsoever for the delay that the courier may have
caused. Bids sent and/or received after the deadline shall be disqualified.
Bid opening shall be on June 10, 2021; 2:00 PM at Bids and Awards Committee (BAC)
Conference Room Second Floor, SSC Building Batangas State University – Pablo
Borbon, Rizal Avenue Extension, Batangas City. The opening and preliminary
evaluation of the bids shall be done in front of the bidders and BC members through video
conferencing.
Should any of the bid/s fail, the notice shall immediately be sent to the email of the bidder
concerned on the same proceeding. Bidders must acknowledge the receipt of the same. The
physical copy of the notice shall be sent to the bidder through registered mail. Nevertheless,
notices electronically transmitted or transmitted through facsimile are deemed served.
7. The Batangas State University reserves the right to reject any and all bids, declare a
failure of bidding, or not award the contract at any time prior to contract award in
accordance with Sections 35.6 and 41 of the 2016 revised Implementing Rules and
Regulations (IRR) of RA No. 9184, without thereby incurring any liability to the affected
bidder or bidders.
Page 12
11
8. For further information, please refer to:
Batangas State University
Bids and Awards Committee (BAC) Secretariat
2nd Floor SSC Building, Pablo Borbon
Rizal Avenue Extension, Batangas City
Telephone No.: (043) 980-0385 loc. 1549
Telephone No. (043) 984-3275
Cellphone No. 0917-1770606
Email Address: [email protected]
9. You may visit the following websites:
For downloading of Bidding Documents:
https://www.batstate-u.edu.ph/index.invitations-to-bid
https://www.philgeps.gov.ph/
ENRICO M. DALANGIN, Ph.D. BAC Chairperson
Page 13
12
Section II. Instructions to Bidders
Notes on the Instructions to Bidders
This Section on the Instruction to Bidders (ITB) provides the information necessary for
bidders to prepare responsive bids, in accordance with the requirements of the Procuring
Entity. It also provides information on bid submission, eligibility check, opening and
evaluation of bids, post-qualification, and on the award of contract.
Page 14
13
1. Scope of Bid
The Batangas State University invites Bids for the Construction of Gate
Four Façade and Fence in Batangas State University Pablo Borbon with Project
Identification Number BSU Project No. 2021 - 138
The Procurement Project “Construction of Gate Four Façade and Fence in
Batangas State University Pablo Borbon” is for the construction of Works, as
described in Section VI (Specifications).
2. Funding Information
2.1. The GOP through the source of funding as indicated below for Supplemental
2021 in the amount of Nineteen Million Eight Hundred Thirty One
Thousand Sixty Pesos (Php 19,831,060.00)
2.2. The source of funding is:
Supplemental Budget 2021
3. Bidding Requirements
The Bidding for the Project shall be governed by all the provisions of RA No. 9184 and
its 2016 revised IRR, including its Generic Procurement Manual and associated
policies, rules and regulations as the primary source thereof, while the herein clauses
shall serve as the secondary source thereof.
Any amendments made to the IRR and other GPPB issuances shall be applicable only
to the ongoing posting, advertisement, or invitation to bid by the BAC through the
issuance of a supplemental or bid bulletin.
The Bidder, by the act of submitting its Bid, shall be deemed to have inspected the site,
determined the general characteristics of the contracted Works and the conditions for
this Project, such as the location and the nature of the work; (b) climatic conditions;
(c) transportation facilities; (c) nature and condition of the terrain, geological conditions
at the site communication facilities, requirements, location and availability of
construction aggregates and other materials, labor, water, electric power and access
roads; and (d) other factors that may affect the cost, duration and execution or
implementation of the contract, project, or work and examine all instructions, forms,
terms, and project requirements in the Bidding Documents.
4. Corrupt, Fraudulent, Collusive, Coercive, and Obstructive Practices
The Procuring Entity, as well as the Bidders and Contractors, shall observe the highest
standard of ethics during the procurement and execution of the contract. They or
Page 15
14
through an agent shall not engage in corrupt, fraudulent, collusive, coercive, and
obstructive practices defined under Annex “I” of the 2016 revised IRR of RA No. 9184
or other integrity violations in competing for the Project.
5. Eligible Bidders
5.1. Only Bids of Bidders found to be legally, technically, and financially capable
will be evaluated.
5.2. The Bidder must have an experience of having completed a Single Largest
Completed Contract (SLCC) that is similar to this Project, equivalent to at least
fifty percent (50%) of the ABC adjusted, if necessary, by the Bidder to current
prices using the PSA’s CPI, except under conditions provided for in Section
23.4.2.4 of the 2016 revised IRR of RA No. 9184.
A contract is considered to be “similar” to the contract to be bid if it has the
major categories of work stated in the BDS.
5.3. For Foreign-funded Procurement, the Procuring Entity and the foreign
government/foreign or international financing institution may agree on another
track record requirement, as specified in the Bidding Document prepared for
this purpose.
5.4. The Bidders shall comply with the eligibility criteria under Section 23.4.2 of the
2016 IRR of RA No. 9184.
6. Origin of Associated Goods
There is no restriction on the origin of Goods other than those prohibited by a decision
of the UN Security Council taken under Chapter VII of the Charter of the UN.
7. Subcontracts
The Procuring Entity has prescribed that: Subcontracting is not allowed.
8. Pre-Bid Conference
The Procuring Entity will hold a pre-bid conference for this Project on the specified
date and time and either at its physical address Conference Room, Bids and Awards
Committee (BAC), 2nd Flr., Student Services Center Building, Rizal Avenue
Extension, Batangas City through videoconferencing/webcasting as indicated in
paragraph 5 of the IB.
9. Clarification and Amendment of Bidding Documents
Prospective bidders may request for clarification on and/or interpretation of any part of
the Bidding Documents. Such requests must be in writing and received by the
Procuring Entity, either at its given address or through electronic mail indicated in the
Page 16
15
IB, at least ten (10) calendar days before the deadline set for the submission and receipt
of Bids.
10. Documents Comprising the Bid: Eligibility and Technical
Components
10.1. The first envelope shall contain the eligibility and technical documents of the
Bid as specified in Section IX. Checklist of Technical and Financial
Documents.
10.2. If the eligibility requirements or statements, the bids, and all other documents
for submission to the BAC are in foreign language other than English, it must
be accompanied by a translation in English, which shall be authenticated by the
appropriate Philippine foreign service establishment, post, or the equivalent
office having jurisdiction over the foreign bidder’s affairs in the Philippines.
For Contracting Parties to the Apostille Convention, only the translated
documents shall be authenticated through an apostille pursuant to GPPB
Resolution No. 13-2019 dated 23 May 2019. The English translation shall
govern, for purposes of interpretation of the bid.
10.3. A valid PCAB License is required, and in case of joint ventures, a valid special
PCAB License, and registration for the type and cost of the contract for this
Project. Any additional type of Contractor license or permit shall be indicated
in the BDS.
10.4. A List of Contractor’s key personnel (e.g., Project Manager, Project Engineers,
Materials Engineers, and Foremen) assigned to the contract to be bid, with their
complete qualification and experience data shall be provided. These key
personnel must meet the required minimum years of experience set in the BDS.
10.5. A List of Contractor’s major equipment units, which are owned, leased, and/or
under purchase agreements, supported by proof of ownership, certification of
availability of equipment from the equipment lessor/vendor for the duration of
the project, as the case may be, must meet the minimum requirements for the
contract set in the BDS.
11. Documents Comprising the Bid: Financial Component
11.1. The second bid envelope shall contain the financial documents for the Bid as
specified in Section IX. Checklist of Technical and Financial Documents.
11.2. Any bid exceeding the ABC indicated in paragraph 1 of the IB shall not be
accepted.
11.3. For Foreign-funded procurement, a ceiling may be applied to bid prices
provided the conditions are met under Section 31.2 of the 2016 revised IRR of
RA No. 9184.
Page 17
16
12. Alternative Bids
Bidders shall submit offers that comply with the requirements of the Bidding
Documents, including the basic technical design as indicated in the drawings and
specifications. Unless there is a value engineering clause in the BDS, alternative Bids
shall not be accepted.
13. Bid Prices
All bid prices for the given scope of work in the Project as awarded shall be considered
as fixed prices, and therefore not subject to price escalation during contract
implementation, except under extraordinary circumstances as determined by the NEDA
and approved by the GPPB pursuant to the revised Guidelines for Contract Price
Escalation guidelines.
14. Bid and Payment Currencies
14.1. Bid prices may be quoted in the local currency or tradeable currency accepted
by the BSP at the discretion of the Bidder. However, for purposes of bid
evaluation, Bids denominated in foreign currencies shall be converted to
Philippine currency based on the exchange rate as published in the BSP
reference rate bulletin on the day of the bid opening.
14.2. Payment of the contract price shall be made in: Philippine Pesos.
15. Bid Security
15.1. The Bidder shall submit a Bid Securing Declaration or any form of Bid Security
in the amount indicated in the BDS, which shall be not less than the percentage
of the ABC in accordance with the schedule in the BDS.
15.2. The Bid and bid security shall be valid 120 calendar days. Any bid not
accompanied by an acceptable bid security shall be rejected by the Procuring
Entity as non-responsive.
16. Sealing and Marking of Bids
Each Bidder shall submit one copy of the first and second components of its Bid.
The Procuring Entity may request additional hard copies and/or electronic copies of the
Bid. However, failure of the Bidders to comply with the said request shall not be a
ground for disqualification.
If the Procuring Entity allows the submission of bids through online submission to the
given website or any other electronic means, the Bidder shall submit an electronic copy
of its Bid, which must be digitally signed. An electronic copy that cannot be opened or
is corrupted shall be considered non-responsive and, thus, automatically disqualified.
17. Deadline for Submission of Bids
Page 18
17
The Bidders shall submit on the specified date and time and either at its physical address
or through online submission as indicated in paragraph 7 of the IB.
18. Opening and Preliminary Examination of Bids
18.1. The BAC shall open the Bids in public at the time, on the date, and at the place
specified in paragraph 9 of the IB. The Bidders’ representatives who are present
shall sign a register evidencing their attendance. In case videoconferencing,
webcasting or other similar technologies will be used, attendance of participants
shall likewise be recorded by the BAC Secretariat.
In case the Bids cannot be opened as scheduled due to justifiable reasons, the
rescheduling requirements under Section 29 of the 2016 revised IRR of RA No.
9184 shall prevail.
18.2. The preliminary examination of Bids shall be governed by Section 30 of the
2016 revised IRR of RA No. 9184.
19. Detailed Evaluation and Comparison of Bids
19.1. The Procuring Entity’s BAC shall immediately conduct a detailed evaluation of
all Bids rated “passed” using non-discretionary pass/fail criteria. The BAC
shall consider the conditions in the evaluation of Bids under Section 32.2 of
2016 revised IRR of RA No. 9184.
19.2. If the Project allows partial bids, all Bids and combinations of Bids as indicated
in the BDS shall be received by the same deadline and opened and evaluated
simultaneously so as to determine the Bid or combination of Bids offering the
lowest calculated cost to the Procuring Entity. Bid Security as required by ITB
Clause 16 shall be submitted for each contract (lot) separately.
19.3. In all cases, the NFCC computation pursuant to Section 23.4.2.6 of the 2016
revised IRR of RA No. 9184 must be sufficient for the total of the ABCs for all
the lots participated in by the prospective Bidder.
20. Post Qualification
Within a non-extendible period of five (5) calendar days from receipt by the Bidder of
the notice from the BAC that it submitted the Lowest Calculated Bid, the Bidder shall
submit its latest income and business tax returns filed and paid through the BIR
Electronic Filing and Payment System (eFPS), and other appropriate licenses and
permits required by law and stated in the BDS.
21. Signing of the Contract
The documents required in Section 37.2 of the 2016 revised IRR of RA No. 9184 shall
form part of the Contract. Additional Contract documents are indicated in the BDS.
Page 19
18
Section III. Bid Data Sheet
Notes on the Bid Data Sheet (BDS)
The Bid Data Sheet (BDS) consists of provisions that supplement, amend, or specify in
detail, information, or requirements included in the ITB found in Section II, which are
specific to each procurement.
This Section is intended to assist the Procuring Entity in providing the specific information
in relation to corresponding clauses in the ITB and has to be prepared for each specific
procurement.
The Procuring Entity should specify in the BDS information and requirements specific to
the circumstances of the Procuring Entity, the processing of the procurement, and the bid
evaluation criteria that will apply to the Bids. In preparing the BDS, the following aspects
should be checked:
a. Information that specifies and complements provisions of the ITB must be
incorporated.
b. Amendments and/or supplements, if any, to provisions of the ITB as necessitated by
the circumstances of the specific procurement, must also be incorporated.
Page 20
19
Bid Data Sheet ITB Clause
5.2 For this purpose, contracts similar to the Project refer to contracts which have
the same major categories of work, which shall be:
The Bidder must have completed, within the period specified in the Invitation
to Bid and ITB Clause 12.1(a) (ii), a single contract that is similar to this Project,
equivalent to at least fifty percent (50%) of the ABC.
7.1
Subcontracting is not allowed.
10.3
10.4
The key personnel must meet the required minimum years of experience set
below:
Key Personnel General Experience Relevant Experience
10.5 The minimum major equipment requirements are the following:
Equipment Capacity Number of Units
12 No further instructions.
15.1 The bid security shall be in the form of a Bid Securing Declaration or any of the
following forms and amounts:
a. The amount of not less than Three Hundred Ninety Six Thousand Six
Hundred Twenty One pesos & 20/100 (Php 396,621.20) which is
2% of ABC, if bid security is in cash, cashier’s/manager’s check, bank
draft/guarantee or irrevocable letter of credit;
b. The amount of not less than Nine Hundred Ninety One Thousand
Five Hundred Fifty Three pesos (Php 991,553.00) which is 5% of
ABC if bid security is in Surety Bond.
19.2 Partial bids is not allowed. The infrastructure project is packaged in a single lot
and the lot shall not be divided into sub-lots for the purpose of bidding,
evaluation, and contract award.
20 [List of licenses and permits relevant to the Project and the corresponding law
requiring it, e.g. Environmental Compliance Certificate, Certification that the
project site is not within a geohazard zone, etc.]
21
Additional contract documents relevant to the Project that may be required by
existing laws and/or the Procuring Entity, such as construction schedule and S-
curve, manpower schedule, construction methods, equipment utilization
schedule, construction safety and health program approved by the DOLE, and
other acceptable tools of project scheduling.
Page 21
20
Section IV. General Conditions of Contract
Notes on the General Conditions of Contract
The General Conditions of Contract (GCC) in this Section, read in conjunction with the
Special Conditions of Contract in Section V and other documents listed therein, should be a
complete document expressing all the rights and obligations of the parties.
Matters governing performance of the Contractor, payments under the contract, or matters
affecting the risks, rights, and obligations of the parties under the contract are included in
the GCC and Special Conditions of Contract.
Any complementary information, which may be needed, shall be introduced only through
the Special Conditions of Contract.
Page 22
21
1. Scope of Contract
This Contract shall include all such items, although not specifically mentioned, that can
be reasonably inferred as being required for its completion as if such items were
expressly mentioned herein. All the provisions of RA No. 9184 and its 2016 revised
IRR, including the Generic Procurement Manual, and associated issuances, constitute
the primary source for the terms and conditions of the Contract, and thus, applicable in
contract implementation. Herein clauses shall serve as the secondary source for the
terms and conditions of the Contract.
This is without prejudice to Sections 74.1 and 74.2 of the 2016 revised IRR of RA No.
9184 allowing the GPPB to amend the IRR, which shall be applied to all procurement
activities, the advertisement, posting, or invitation of which were issued after the
effectivity of the said amendment.
2. Sectional Completion of Works
If sectional completion is specified in the Special Conditions of Contract (SCC),
references in the Conditions of Contract to the Works, the Completion Date, and the
Intended Completion Date shall apply to any Section of the Works (other than
references to the Completion Date and Intended Completion Date for the whole of the
Works).
3. Possession of Site
3.1 The Procuring Entity shall give possession of all or parts of the Site to the
Contractor based on the schedule of delivery indicated in the SCC, which
corresponds to the execution of the Works. If the Contractor suffers delay or incurs
cost from failure on the part of the Procuring Entity to give possession in accordance
with the terms of this clause, the Procuring Entity’s Representative shall give the
Contractor a Contract Time Extension and certify such sum as fair to cover the cost
incurred, which sum shall be paid by Procuring Entity.
3.2 If possession of a portion is not given by the above date, the Procuring Entity
will be deemed to have delayed the start of the relevant activities. The resulting
adjustments in contract time to address such delay may be addressed through
contract extension provided under Annex “E” of the 2016 revised IRR of RA No.
9184.
4. The Contractor’s Obligations
The Contractor shall employ the key personnel named in the Schedule of Key Personnel
indicating their designation, in accordance with ITB Clause 10.3 and specified in the
BDS, to carry out the supervision of the Works.
The Procuring Entity will approve any proposed replacement of key personnel only if
their relevant qualifications and abilities are equal to or better than those of the
personnel listed in the Schedule.
Page 23
22
5. Performance Security
5.1. Within ten (10) calendar days from receipt of the Notice of Award from the
Procuring Entity but in no case later than the signing of the contract by both
parties, the successful Bidder shall furnish the performance security in any of
the forms prescribed in Section 39 of the 2016 revised IRR.
5.2. The Contractor, by entering into the Contract with the Procuring Entity,
acknowledges the right of the Procuring Entity to institute action pursuant to
RA No. 3688 against any subcontractor be they an individual, firm, partnership,
corporation, or association supplying the Contractor with labor, materials and/or
equipment for the performance of this Contract.
6. Site Investigation Reports
The Contractor, in preparing the Bid, shall rely on any Site Investigation Reports
referred to in the SCC supplemented by any information obtained by the Contractor.
7. Warranty
7.1. In case the Contractor fails to undertake the repair works under Section 62.2.2
of the 2016 revised IRR, the Procuring Entity shall forfeit its performance
security, subject its property (ies) to attachment or garnishment proceedings,
and perpetually disqualify it from participating in any public bidding. All
payables of the GOP in his favor shall be offset to recover the costs.
7.2. The warranty against Structural Defects/Failures, except that occasioned-on
force majeure, shall cover the period from the date of issuance of the Certificate
of Final Acceptance by the Procuring Entity. Specific duration of the warranty
is found in the SCC.
8. Liability of the Contractor
Subject to additional provisions, if any, set forth in the SCC, the Contractor’s liability
under this Contract shall be as provided by the laws of the Republic of the Philippines.
If the Contractor is a joint venture, all partners to the joint venture shall be jointly and
severally liable to the Procuring Entity.
9. Termination for Other Causes
Contract termination shall be initiated in case it is determined prima facie by the
Procuring Entity that the Contractor has engaged, before, or during the implementation
of the contract, in unlawful deeds and behaviors relative to contract acquisition and
implementation, such as, but not limited to corrupt, fraudulent, collusive, coercive, and
obstructive practices as stated in ITB Clause 4.
Page 24
23
10. Dayworks
Subject to the guidelines on Variation Order in Annex “E” of the 2016 revised IRR of
RA No. 9184, and if applicable as indicated in the SCC, the Dayworks rates in the
Contractor’s Bid shall be used for small additional amounts of work only when the
Procuring Entity’s Representative has given written instructions in advance for
additional work to be paid for in that way.
11. Program of Work
11.1. The Contractor shall submit to the Procuring Entity’s Representative for
approval the said Program of Work showing the general methods, arrangements,
order, and timing for all the activities in the Works. The submissions of the
Program of Work are indicated in the SCC.
11.2. The Contractor shall submit to the Procuring Entity’s Representative for
approval an updated Program of Work at intervals no longer than the period
stated in the SCC. If the Contractor does not submit an updated Program of
Work within this period, the Procuring Entity’s Representative may withhold
the amount stated in the SCC from the next payment certificate and continue to
withhold this amount until the next payment after the date on which the overdue
Program of Work has been submitted.
12. Instructions, Inspections and Audits
The Contractor shall permit the GOP or the Procuring Entity to inspect the Contractor’s
accounts and records relating to the performance of the Contractor and to have them
audited by auditors of the GOP or the Procuring Entity, as may be required.
13. Advance Payment
The Procuring Entity shall, upon a written request of the Contractor which shall be
submitted as a Contract document, make an advance payment to the Contractor in an
amount not exceeding fifteen percent (15%) of the total contract price, to be made in
lump sum, or at the most two installments according to a schedule specified in the SCC,
subject to the requirements in Annex “E” of the 2016 revised IRR of RA No. 9184.
14. Progress Payments
The Contractor may submit a request for payment for Work accomplished. Such
requests for payment shall be verified and certified by the Procuring Entity’s
Representative/Project Engineer. Except as otherwise stipulated in the SCC, materials
and equipment delivered on the site but not completely put in place shall not be included
for payment.
15. Operating and Maintenance Manuals
15.1. If required, the Contractor will provide “as built” Drawings and/or operating
and maintenance manuals as specified in the SCC.
Page 25
24
15.2. If the Contractor does not provide the Drawings and/or manuals by the dates
stated above, or they do not receive the Procuring Entity’s Representative’s
approval, the Procuring Entity’s Representative may withhold the amount stated
in the SCC from payments due to the Contractor.
Page 26
25
Section V. Special Conditions of Contract
Notes on the Special Conditions of Contract
Similar to the BDS, the clauses in this Section are intended to assist the Procuring Entity in
providing contract-specific information in relation to corresponding clauses in the GCC
found in Section IV.
The Special Conditions of Contract (SCC) complement the GCC, specifying contractual
requirements linked to the special circumstances of the Procuring Entity, the Procuring
Entity’s country, the sector, and the Works procured. In preparing this Section, the following
aspects should be checked:
a. Information that complements provisions of the GCC must be incorporated.
b. Amendments and/or supplements to provisions of the GCC as necessitated by the
circumstances of the specific purchase, must also be incorporated.
However, no special condition which defeats or negates the general intent and purpose of
the provisions of the GCC should be incorporated herein.
Page 27
26
Special Conditions of Contract
GCC Clause
2 The intended completion date is ________________________
4.1 The start date is on ___________________’
Note: The start date shall be five (5) days after the receipt of the Notice
to Proceed.
6 The site is located at Batangas State University Pablo Borbon, Batangas
City
7.2
[In case of permanent structures, such as buildings of types 4 and 5 as
classified under the National Building Code of the Philippines and other
structures made of steel, iron, or concrete which comply with relevant
structural codes (e.g., DPWH Standard Specifications), such as, but not
limited to, steel/concrete bridges, flyovers, aircraft movement areas,
ports, dams, tunnels, filtration and treatment plants, sewerage systems,
power plants, transmission and communication towers, railway system,
and other similar permanent structures:]
Fifteen (15) years.
10 Dayworks are applicable at the rate shown in the Contractor’s original
Bid.
11.1 The Contractor shall submit the Program of Work to the Procuring
Entity’s Representative within ___________days of delivery of the
Notice of Award.
11.2 The amount to be withheld for late submission of an updated Program of
Work is ______________.
13 The amount of the advance payment is Fifteen percent (15%) of the total
contract price.
14 Materials and equipment delivered on the site but not completely put in
place shall not be included for payment.
15.1 The date by which operating and maintenance manuals are required is
___________.
The date by which “as built” drawings are required is ______________.
15.2 The amount to be withheld for failing to produce “as built” drawings
and/or operating and maintenance manuals by the date required is
_________________.
Page 28
27
Section VI. Specifications
Notes on Specifications
A set of precise and clear specifications is a prerequisite for Bidders to respond realistically
and competitively to the requirements of the Procuring Entity without qualifying or
conditioning their Bids. In the context of international competitive bidding, the
specifications must be drafted to permit the widest possible competition and, at the same
time, present a clear statement of the required standards of workmanship, materials, and
performance of the goods and services to be procured. Only if this is done will the objectives
of economy, efficiency, and fairness in procurement be realized, responsiveness of Bids be
ensured, and the subsequent task of bid evaluation facilitated. The specifications should
require that all goods and materials to be incorporated in the Works be new, unused, of the
most recent or current models, and incorporate all recent improvements in design and
materials unless provided otherwise in the Contract.
Samples of specifications from previous similar projects are useful in this respect. The use
of metric units is mandatory. Most specifications are normally written specially by the
Procuring Entity or its representative to suit the Works at hand. There is no standard set of
Specifications for universal application in all sectors in all regions, but there are established
principles and practices, which are reflected in these PBDs.
There are considerable advantages in standardizing General Specifications for repetitive
Works in recognized public sectors, such as highways, ports, railways, urban housing,
irrigation, and water supply, in the same country or region where similar conditions prevail.
The General Specifications should cover all classes of workmanship, materials, and
equipment commonly involved in construction, although not necessarily to be used in a
particular Works Contract. Deletions or addenda should then adapt the General
Specifications to the particular Works.
Care must be taken in drafting specifications to ensure that they are not restrictive. In the
specification of standards for goods, materials, and workmanship, recognized international
standards should be used as much as possible. Where other particular standards are used,
whether national standards or other standards, the specifications should state that goods,
materials, and workmanship that meet other authoritative standards, and which ensure
substantially equal or higher quality than the standards mentioned, will also be acceptable.
The following clause may be inserted in the SCC.
Sample Clause: Equivalency of Standards and Codes
Wherever reference is made in the Contract to specific standards and codes to be met by the
goods and materials to be furnished, and work performed or tested, the provisions of the
latest current edition or revision of the relevant standards and codes in effect shall apply,
unless otherwise expressly stated in the Contract. Where such standards and codes are
national, or relate to a particular country or region, other authoritative standards that ensure
a substantially equal or higher quality than the standards and codes specified will be accepted
subject to the Procuring Entity’s Representative’s prior review and written consent.
Page 29
28
Differences between the standards specified and the proposed alternative standards shall be
fully described in writing by the Contractor and submitted to the Procuring Entity’s
Representative at least twenty-eight (28) days prior to the date when the Contractor desires
the Procuring Entity’s Representative’s consent. In the event the Procuring Entity’s
Representative determines that such proposed deviations do not ensure substantially equal
or higher quality, the Contractor shall comply with the standards specified in the documents.
These notes are intended only as information for the Procuring Entity or the person drafting
the Bidding Documents. They should not be included in the final Bidding Documents.
C O N T E N T S
Item
No. Description
% of
Total Unit Quantity
1 MOBILIZATION/DEMOBILIZATION 1.20 LOT 1.00
2 CONSTRUCTION SAFETY & HEALTH PROGRAM 2.2 LOT 1.00
3
OTHER GENERAL REQUIREMENTS
(Project Photographs, Project Billboards and Permits,
Clearances and Other Government Taxes)
0.46 LOT 1.00
4 TEMPORARY FACILITIES/FIELD OFFICE 0.42 LOT 1.00
5 SITEWORKS 5.67 LOT 1.00
6 FORMS AND SCAFFOLDINGS 2.76 LOT 1.00
7 REINFORCED CONCRETE WORKS 25.41 cu.m. 275.00
8 MASONRY WORKS 2.64 sq. m. 395.00
9 PLASTERING WORKS 0.6 sq. m. 562.24
10 WATERPROOFING WORKS 0.31 sq.m. 63.00
11 METAL ROOFING WORKS 5.72 LOT 1.00
12 DUCTBANK AND PULLBOX 3.37 LOT 1.00
13 ALUMINUM COMPOSITE PANEL (PVDF) 3.82 sq. m 205.00
Page 30
29
14 ARCHITECTURAL STEEL WORKS 5.13 LOT 1.00
15 ARCHITECTURAL DOORS, WINDOWS AND
CURTAIN WALLS 8.17 LOT 1.00
16 TILEWORKS 4.28 sq. m 602.15
17 CARPENTRY WORKS 3.79 sq. m 319.32
18 PAINTING WORKS 1.12 sq. m 583.18
19 STAINLESS LOGO, LETTERS AND SIGNAGES 1.44 LOT 1.00
20 LANDSCAPE WORKS 5.35 sq.m. 646.13
21 MECHANICAL WORKS 0.62 LOT 1.00
22 ELECTRICAL WORKS 5.31 LOT 1.00
23 ELECTRONICS AND COMMUNICATION WORKS 1.70 LOT 1.00
24 REHABILITATION OF OVERHEAD FEEDER LINE 6.34 LOT 1.00
25 PLUMBING WORKS 0.68 LOT 1.00
26 PLUMBING FIXTURES AND ACCESSORIES 0.53 LOT 1.00
27 CATCH BASINS 0.07 LOT 1.00
28 HAULING OF WASTES AND DEMOLISHED
MATERIALS 0.89 LOT 1.00
C O N S T R U C T I O N 100.0
GENERAL
a) All applicable provisions of the different divisions of the Specifications for each work
shall apply for all items cited in this schedule.
b) Discrepancy arising from this section of the Contract Documents must be brought to
the attention of the Owner or representative Architect/Engineer whose decision shall
be final.
c) Materials deemed necessary to complete the works but not specifically mentioned in
the Specification, Working Drawing, or in the Contract Document shall be supplied
and installed by the Contractor. Such materials shall be of the highest quality and
kind, and installed or applied in a workmanlike manner at prescribed or appropriate
Page 31
30
locations following the Standard Practice of Civil Engineering, National Building
Code of the Philippines and Construction Procedures.
d) All items with specified approved brand, manufacturer, supplier, fabricator, trademark
and the like shall be strictly followed.
e) The Contractor shall coordinate the work with the Project Management Office to
expedite the implementation of the project.
f) The Contractor shall supply all finishing accessories and furnishing fixtures as may be
approved by the owner or representative and shall be installed by the Contractor
whenever required by the Owner or Representative.
1 MOBILIZATION/DEMOBILIZATION
A. Mobilization shall include all activities and associated costs for transportation of
Contractor's personnel, equipment, and operating supplies to the site; and other
necessary general facilities for the Contractor's operations at the site; premiums paid
for performance and payment bonds, including co-insurance and re-insurance
agreements as applicable.
B. Demobilization shall include all activities and costs for transportation of personnel,
equipment, and supplies not required or included in the contract from the site;
including the disassembly, removal and site cleanup of temporary offices and other
facilities assembled on the site specifically for this contract.
2 CONSTRUCTION SAFETY AND HEALTH PROGRAM
A. This item includes provision of Personal Protective Equipment (PPE) (safety harness,
hard hat, safety glasses, gloves, working uniform and safety shoes) for all workers on
the hard hat area.
B. This item covers the provision of safety equipment such as barricades, safety nets and
other similar items that shall be set on throughout the perimeter of the construction
site to ensure the safety of the workers and pedestrians alike.
C. Provision of first aid kit on site at all times.
D. Provision of safety signage’s, appropriate barricades and warning signs, and traffic
management system.
E. All construction personnel shall be required to undergo COVID-19 test, as may be
prescribed, and retested as the need arises.
F. Provision of alcohols, soaps, disinfectants and decontamination areas on site.
G. The contractor shall be required to submit their Construction Safety Guidelines for the
Implementation of the Project during the COVID-19 Public Health Crisis.
Page 32
31
3 OTHER GENERAL REQUIREMENTS (Project Photographs, Project Billboards and
Permits, Clearances and Other Government Taxes)
A. PROJECT PHOTOGRAPHS
Monthly accomplishment report shall be submitted to BatStateU complete
with pictures of on-going projects.
The Contractor must present a report on the project’s progress shown
through photographs.
B. PROJECT BILLBOARDS
Contractor must provide two project billboards showing information about
the project.
The two (2) Project billboards shall be strategically placed within the site
vicinity; (As provided on the General Guidelines and Legal Mandates of the
Commission on Audit to promote good governance through transparency
and accountability, notifications to the public and other forms of
announcement and/or publicity for or otherwise relating to the
Projects/Programs/Activities (PPA) shall be made at the least possible cost.)
Hence, for infrastructure projects, two (2) tarpaulin signboards must be
suitably framed for outdoor display at the project location, and shall be
posted as the award has been made. The design and format of the tarpaulin
as shown below, shall have the following specifications:
Tarpaulin, white, 8ft x 8ft
Resolution: 70 dpi
Font: Helvetica
Font Size: Main Information – 3”
Sub-Information -1”
Font Color: Black
Republic of the Philippines
Batangas State University
Batangas City
PROJECT MANAGEMENT OFFICE
Project: CONSTRUCTION OF GATE FOUR FACADE AND FENCE Cost: _________
Location:
BatStateU – Pablo Borbon, Rizal Ave. Ext., Batangas
City Fund Source/s:________
____________________
Page 33
32
Implementing Agency/ies:
Development Partner/s:
Contractor/Supplier: ______________________________
Brief Description of Project:
Project Date Project Status
Remarks
Duration Started
Target Date
of
Completion
Percentage
of
Completion
As of
(Date)
Cost
Incurred
to Date
Date
Completed
For particulars or complaints about this project, please contact the Regional Office or Cluster
Which has audit jurisdiction on this project:
COA Regional Office No./Cluster:
Address:
Contact No. : _________________ or Text COA Citizen's Desk at 0915-5391957
C. PERMITS, CLEARANCES AND OTHER GOVERNMENT TAXES
The Contractor must secure Fire Safety Evaluation Clearance for Building
Permit and Fire Safety Inspection Certificate for Occupancy Permit.
4 TEMPORARY FACILITIES/ FIELD OFFICE
4.1.1.1 The construction of temporary facilities including electric and water consumption,
barracks, site office, temporary fence, hand wash area, disinfection station, sanitation
tent.
5 SITEWORKS
5.1.1.1 SITE CLEARING
Removal / Relocation of trees and removal of all unnecessary obstructions
within the construction site.
All BatStateU-owned materials shall be turned over to the Maintenance Unit.
Cap all existing utility lines. Consult Owner/ Representative before
commencing work.
Page 34
33
Provision, installation and maintaining of temporary fencing and barricades
to secure work area, as well as necessary gates, pathways and access control
system to the satisfaction of BatStateU.
The Contractor shall assist in clearing and removal of all BatStateU-owned
items, materials and other obstructions within the construction site.
B. DEMOLITION
Demolition, dismantling works and removal of all site existing structures
such as slabs, columns, roofing and other obstructions within the area where
the building/s will be erected. The following structures to be demolished are
as follows:
Existing Fence
Existing One Storey CONAHS Building
Cooperative Building
One Storey Classroom (Baking Room)
Stock Area
Existing Materials Recovery Facility (MRF)
Other existing buildings/structures that may obstruct the proposed
building; such structures shall be identified by BatStateU
Demolition shall be done in a well-organized manner. All demolished
materials and debris shall be removed from site and shall be disposed from
site immediately; all other reusable materials shall be turned over to
BatStateU.
Any damage incurred by the Contractor during demolition/dismantling that is
not within the scope/contract shall be repaired at the expense of the
Contractor and shall not be included in the contract amount.
C. EXCAVATION for building foundations, tie beams and other structures below
ground level shall be done to depth and elevations indicated on the drawings.
Excavation shall be extended until the required bearing capacity is attained. It shall be
leveled properly and must be compacted up to disturbed bottom.
Provision of ground protection such as installation of sheet piles, trenching,
shoring and other excavation protection may be required by the Contractor to
avoid cave-ins or collapse of the ground during excavation.
Page 35
34
Dewatering works may be required for pumping out ground water from or
around the excavation prior construction of building foundation and other
related structures to be constructed below natural grade line.
All excavated materials on-site shall be disposed and shall be
transferred/hauled by the Contractor on a different site or outside the
construction.
D. EARTH WORKS
Fill borrow materials. Granular, non-plastic materials from off-site source;
50mm thk gravel bedding for tie beams, grade beams and slab on grade and
lean concrete for foundations;
Backfilling. Approved and clean materials. Lay backfilling not more than
300mm thick, each layer thoroughly compacted and wetted by tamping or
rolling. This shall extend to area as indicated in the plan.
E. Provision of soil poisoning and termite
control.
F. Provision of soil poisoning perforated
pipe line system including installation
of ½” diameter PVC pipes (blue) with
holes and ½” diameter PVC fittings.
Layout of pipes to be provided.
G. The contractor must conduct Field
Density Test (FDT), one group of 3 in-
situ density tests per layer. Each layer
must be 0.20m compacted fill of 95%
soil compaction.
6 FORMS AND SCAFFOLDINGS
6.1.1.1.1.1 All forms for concrete works shall be
properly braced or connected together so as to maintain the correct position and
shapes of the concrete members. Forms shall be constructed sufficiently tight to
prevent bulging and seepage of water.
6.1.1.1.1.2 Forms shall not be removed until the
concrete has attained sufficient strength to support its own weight and any loads that
may be placed on it. Sides of beams and girder may be removed earlier than the
bottom forms but additional post or shoring must be placed under the beams or girders
until they have attained the strength.
6.1.1.1.1.3 Use Phenolic Board for all formworks.
Page 36
35
6.1.1.1.1.4 Scaffolding shall be of good construction
of sound materials and strength for the purpose for which it is intended.
6.1.1.1.1.5 Scaffolding shall be done in a manner
where it follows the standards for occupational safety and health.
7 REINFORCED CONCRETE WORKS
A. REINFORCING STEEL BARS
All steel reinforcing bars to be used in this construction shall consist of round
deformed bars with lugs or projections on their sides to provide a greater
bond between the concrete and steel.
All reinforcing bars shall be accurately placed and secured against
displacement by tying them together at each bar intersection with gauge no.
16 or 18 tie wire.
The steel reinforcing bars indicated for footings, columns, beams, slabs,
stairs, drop off area, elevated walkways, concrete gutter and other concrete
members shall conform to the number, size and spacing as indicated in the
drawings or schedule of steel reinforcement.
No metal reinforcement shall be installed in place unless it is free from rust
and scale of other coatings, which will destroy or reduce bond with concrete.
All reinforcing bars shall conform to ASTM A615 Grade 60 for 16mm
diameter and larger bars and Grade 40 for 12mm diameter and smaller bars.
The Contractor shall, employ at his own expense, an approved testing
laboratory which shall conduct testing of all reinforcement sizes of each bulk
under the supervision of the supervising Architect or Engineer.
Refer to approved drawings for construction notes regarding reinforcing steel
bars.
B. STRUCTURAL CONCRETE CLASS “A”
All concrete shall develop a minimum compressive strength at the end of
twenty-eight days with corresponding maximum size aggregate and slumps
as follows:
LOCATION 28 DAYS
STRENGTH
MAX. SIZE
AGGREGATE MAX. SLUMP
Drop Off 3,500 PSI /
24MPa 3/4 in (19mm) 4 in (100mm)
Curbs & Slab-on-
Grade
3,000 PSI /
21MPa 3/4 in (19mm) 4 in (100mm)
Page 37
36
Foundation,
Retaining Wall&
Tie Beam
3,000 PSI /
21MPa 3/4 in (19mm) 4 in (100mm)
Columns
3,000 PSI /
21MPa 3/4 in (19mm) 4 in (100mm)
Beams & Slabs
3,000 PSI /
21MPa 3/4 in (19mm) 4 in (100mm)
All concrete works shall be done in accordance with the standard
specifications for plant and reinforced concrete as adopted by the
Government. Cement to be used shall be readily available in the locality.
Alternative cements must be approved by the Architect/Engineer in-charge
of construction.
The fine aggregate for concrete shall consist of natural sand or of inert
material with similar characteristics, having clean, hard and durable grains,
free from organic matter or loam.
The coarse aggregate for concrete shall consist of river run gravel or crushed
stone having maximum size 1/5 of the nearest dimension between sides of
forms of the concrete or ¾ of the minimum clear spacing between
reinforcing bars, or between rebars and forms whichever is smaller.
The Contractor shall employ, at his own expense, an approved Testing
Laboratory which shall make compression and slump tests and immediately
submit copies of test reports to the supervising Architects or Engineers.
Make six (6) standard concrete cylinder samples for every structural concrete
component poured (footings, columns, beams, slabs, etc.) and every two
samples shall be tested according to 7, 14 and 28 days, respectively.
Refer to approved drawings for construction notes regarding reinforced
concrete.
Contractor shall provide required pipe sleeves for all utilities (Electrical,
Plumbing, Mechanical, etc.). Coordinate/Consult with the
Architect/Engineer-in-charge regarding the requirements for pipe sleeves,
unless specified on the approved plans and details. Refer to approved
drawing regarding the locations for the pipe sleeves for all utilities.
Polyethylene sheets – install minimum 6 mils thick polyethylene film under
slabs on grade. Stretch film level and weight edges to maintain position until
concrete is poured. Lap joints to 150mm.
Pre-moulded expansion joints (PEJ) materials. Securely anchor in place
preformed compressible expansion joint fillers board with thickness of
12mm.
Page 38
37
8 MASONRY WORKS
A. All masonry works, exterior and interior walls for offices, fence and Center Island
shall be done based on the approved drawings.
B. Concrete Hollow Blocks must develop a minimum compressive strength of 350psi
with even texture and well-defined edges, unless otherwise mentioned on the
construction notes.
Use 5” x 8” x 16” (125mm thk.) masonry units for all exterior, interior walls
and fence as indicated on the approved floor plans.
C. Masonry units shall be sound, dry, clean and free from cracks when placed and laid on
the structure.
D. All concrete hollow blocks shall be extended unless otherwise specified and anchored
up to the bottom of the slab, beams and columns.
E. Reinforcing bars: use 10mm diameter vertical bars at 400mm on center and 10mm
diameter horizontal bars at 600mm on center. Refer to notes on masonry and concrete
blocks regarding reinforcement for masonry walls.
F. All reinforcing bars shall be accurately placed and secured against displacement by
tying them together at each bar intersection with gauge no. 16 or 18 tie wire.
G. Provide 1 – 16mm diameter extra vertical bars at corners, intersections, end of walls,
and each side of openings as shown.
H. Lintel beams or lintel blocks shall bear at least eight (8) inches (200mm) on each side
of masonry wall opening.
I. Mortar works: With mix and texture as required. Mortar shall be composed of one (1)
part cement and three (3) parts sand.
J. The Contractor shall, employ at his own expense, an approved testing laboratory
which shall conduct testing of all concrete hollow block sizes (3 samples each) under
the supervision of the supervising Architect or Engineer
K. Contractor shall provide required pipe sleeves for all utilities (Electrical, Plumbing,
Mechanical, etc.). Coordinate/Consult with the Architect/Engineer-in-charge
regarding the requirements for pipe sleeves, unless specified on the approved plans
and details. Refer to approved drawing regarding the locations for the pipe sleeves for
all utilities.
L. 30mmØ and 15mmØ backer rod shall be installed as shown on the approved plans.
Compressible rod stock polyethylene foam, neoprene foam or other flexible,
permanent, durable, non-absorptive material as recommended for compatibility with
sealant by the sealant manufacturer; which will control the joint depth for sealant bead
Page 39
38
on the back side, and provide a highly compressible backer to minimize the possibility
of sealant extrusion when joint is compressed.
M. Polyurethane sealant. Low-modulus, high-performance, 1-component, polyurethane-
based, non-sag elastomeric sealant. Apply on joint substrate free from dust, oil and
other impurities that may affect adhesion of sealant to the joint.
9 PLASTERING WORKS
A. Plaster works: With mix and texture as required. Plaster shall be composed of one (1)
part cement and two (2) parts sand.
B. Masonry wall finishes shall be smooth plaster finish.
10 WATERPROOFING WORKS
A. This work includes the application of water proofing materials required by the
projects and as shown on plan to be approved by the owner and authorized
Representative/Architect/Engineer.
B. Cementitious waterproofing system of roof slab and concrete valley gutter and
membrane waterproofing for concrete valley gutter as specified on the drawing plans
and according to specifications.
11 METAL ROOFING WORKS
A. The works include provision and installation of all roofing materials required by the
project and as shown on plans to be approved by the Owner or authorized
representative/engineer.
B. All members shall be in accordance with the approved steel framing plans and these
Specifications, and to the entire satisfaction of the Owner under the direct supervision
and of Architect/ Engineer-in-charge.
C. The drawings are not intended to show every bolted or welded connection. All such
item whether specifically mentioned or not, or indicated on the drawings shall be done
if necessary to complete the structure.
D. Sheets shall be laid with the end and side laps as indicated on the brochures or
supplied drawings. Unless otherwise specified, the minimum side laps shall be
connected to the purlins using the specifications supplied by the manufacturer or other
approved equivalent connector.
E. Welding, shearing, gas cutting, chipping and all other works involved in the
fabrication of structural steel frames shall be done with accuracy and of the highest
quality of workmanship.
F. Use 0.50mm thick Pre-painted Rib-Type Long Span Roofing Sheets. The Contractor
shall provide samples to be approved by BatStateU.
Page 40
39
G. Provide 15mm Polyethylene Foam Insulation with two (2) sides aluminized film.
Insulation shall be secured with heavy duty duct tape. Insulation shall be fastened in-
between the roofing sheets and the wire mesh n top of the purlins.
H. Use LC 175mm x 50mm x 20mm x 1.6mm thk light gauge purlins at 600mm o.c with
12mmØ sagrods threaded both sides with standard nuts and washers installed
staggered at every third point as specified on the approved plans and drawings.
I. Provide 2 pc 150mm x 50mm x 1.50mm thk. LC Purlins (Fascia Board).
J. Use 0.50mm thick stainless steel gutters Type 304.
K. All steel members shall be protected against corrosion using epoxy primer &epoxy
reducer.
12 DUCTBANK AND PULLBOX
A. Ductbanks shall have electrical warning tape, and cable tiles. Conduits shall be
encased in concrete. Conduits shall have spacers. Ductbanks shall go under other
utilities if ever necessary.
B. Concrete shall utilize class A mixture with comprehensive strength of 2000psi
minimum.
C. All reinforcing steel bars shall be new and free from rust, oil, defects or kinks. They
shall conform to the latest requirement of ASTM A-165 “Specifications for Billet
Deformed Bars” minimum grade 40.
D. Pull box cover shall be 65mm thick or as shown in the plan with compressive strength
of 3000 psi.
E. Concrete separator/ spacer shall utilize Class A mixture with compressive strength of
1500psi. Grooves shall be smooth finish. Separators can use the approved PVC
material.
F. Poly-vinyl-chloride (uPVC) conduit shall be PNS14 thick wall, schedule 40, with
factory made coupling and fittings.
G. Warning tape shall be yellow color made of polyethylene or polypropylene. The tape
should have built in black colored markings of “Caution and Electrical Cable Burried
Below”.
13 ALUMINUM COMPOSITE PANEL (PVDF) WORKS
A. For Aluminum Composite panels, use:
ALUMINUM COMPOSITE PANEL (PVDF)
TYPE MATERIAL'S SPECIFICATIONS LOCATION
Page 41
40
ACP
Size 1220mm x 2440mm
PWD Ramp
(Outside &
Inside)
Main Entrance
Column
Branches
Color Varies
Panel thickness 4mm
Aluminum thk 0.30mm
Coating PVDF
Sub-frame
1-1/2” x 1-1/2 x 1/6” thk Aluminum
Tubular
1-1/2” x 1-1/2 x 1/8” thk Aluminum Angle
Bar Bracket
5/16” Dynabolt
Accessories/Finish Silicone Sealant
B. Column Branches framing/support must be securely connected from the column to the
roof frame.
C. Column Branch shall be terminated/ extended as per intersection with the ceiling as
per actual installation.
D. All frame/sub-frame must be hidden of visual perspective.
E. Provide sample and framing mock-upfor approval by Owner/Architect/Engineer.
14 ARCHITECTURAL STEEL WORKS
A. Supply and installation of all Architectural Steel works as per plan details.
B. All steel works except for stainless finishes must be painted primer before top coating.
C. Stainless steel pipes must have a stainless steel escutcheon plate on ends.
D. Provide sample for approval by Owner/Architect/Engineer.
RAILINGS
TYPE MATERIAL'S SPECIFICATIONS LOCATION
Typical Railings
Post: 2" x 3" x 2.00mm thk Stainless
Rectangular Steel Tube
Hand Grab: 1" x 2" x 1.20mm thk
Stainless Rectangular Steel Tube
PWD Ramp (Outside & Inside)
Main Entrance
Railings
Post: 2" x 3" x 2.00mm thk Stainless
Rectangular Steel Tube
Hand Grab: 1" x 2" x 1.20mm thk
Stainless Rectangular Steel Tube
10mm thk Tempered Glass
Stainless Steel Patch Fittings
Main Entrance
Page 42
41
PWD GATE
TYPE MATERIAL'S SPECIFICATIONS LOCATION
PWD Gate
Post: 5" dia. Stainless Steel Pipe
Frame: 2" x 2" x 1.2mm thk x 6m Stainless
Steel Square Tube
Surface: 4' x 8' x 10mm thk Clear High
Impact Acrylic Sheet
Ground Floor
FENCE GRILLS
TYPE MATERIAL'S SPECIFICATIONS LOCATION
Fence Grills 50mm wide x 6m length x 6mm thk Flat
Bar Fence
TRELLIS
TYPE MATERIAL'S SPECIFICATIONS LOCATION
Vertical Trellis 2" x 6" x 1.5mm thk x 6m length
Rectangular Tubular Steel Waiting Shed
VERTICAL PLANTERS
TYPE MATERIAL'S SPECIFICATIONS LOCATION
Vertical Planters
2” x 4” Vertical and Horizontal Steel
Tubular Bars
2”x 2” x 6mm Steel Matting
1” x 1” x 3/16 Standard thk. Angle Bar
Waiting Shed
OTHER MATERIALS
Misc
Welding Rod 1/8" diameter (for stainless steel)
Grinding disc
Cutting disc
Oxygen
Acetylene
15 ARCHITECTURAL DOORS, WINDOWS AND CURTAIN WALLS
A. The works include supply and installation of Doors, windows, curtain walls and
accessories required by the project and as shown on plans to be approved by the
Owner or authorized representative/architect or engineer.
Page 43
42
B. Door Locksets of high quality: Tubular Door Brushed Satin Finish, Unlock by both
knobs satin finish, Sliding Flush Pull Handle Brushed Stainless Finish. Provide
sample for approval by Architect/Owner.
C. For the door hinges, use high quality full mortise flush hinges, glass door top and
bottom hinge, double action spring hinge, use four (4) pieces per door leaf except for
glass door hinge.
D. All Wooden Door Panel and Door Jambs shall have chemical wood termite
treatments.
E. Supply and installation of the following doors, windows and glass partition:
F. Mock-Ups:
15.1 The Contractor shall install at Project site a job mock-up using acceptable
products and manufacturer approved installation methods and obtain the
BSU’s acceptance of finish color, texture and pattern and workmanship
standard.
15.2 Maintain mock-up during construction for workmanship comparison and
remove and legally dispose of mock-up when no longer required. Mock-up
may be incorporated into final construction upon the BSU’s approval.
G. Gaskets shall be provided on jambs, heads or transoms.
H. Door Fabrication Tolerances
15.3 Size:
Thickness: ± 0.8 mm.
Height: ± 0.8 mm.
Width: ± 0.8 mm.
Squareness: Diagonal measures not to exceed 1.6 mm.
Hardware Location: ± 0.8 mm.
DOORS
SCHEDULE MATERIAL'S SPECIFICATIONS LOCATION
D - 1
2.00m X 2.10m - Double Leaf Frameless Door (Double
Swing)Using: 12mm Thk. Tempered Glass On Stainless
Steel Patch Fittings With Complete Accessories And
Hardwares.
Main Entrance
D - 2
2.00m X 2.10m - Double Leaf Frameless Door (Single
Swing) Using: 12mm Thk. Tempered Glass On Stainless
Steel Patch Fittings With Complete Accessories And
Hardwares.
Main Entrance
D - 3
0.70m X 2.10m Kiln Dried (K.D) Tanguile Panel Door
On 2" X 5" Yakal Door Jamb Complete With Heavy
Duty Accessories
CCTV Room
Information Desk/ Guard
Station
Page 44
43
Pantry
D - 4
0.60m X 2.10m Kiln Dried (K.D) Tanguile Panel Door
On 2" X 5" Yakal Door Jamb Complete With Heavy
Duty Accessories
Toilet
WINDOWS
SCHEDULE MATERIAL'S SPECIFICATIONS LOCATION
W - 1
0.60m X 0.60m Awning Window With 1/4" Thk
Tempered Grey In Powder Coated Frame Complete
With Heavy Duty Accessories
Toilet
W - 2
0.70m X 0.70m Awning Window With 1/4" Thk
Tempered Grey In Concealed Powder Coated Frame
Complete With Heavy Duty Accessories
Triage Area/CW2
CURTAIN WALL
SCHEDULE MATERIAL'S SPECIFICATIONS LOCATION
CW - 1
Curtain Wall 1 (CW1) - Seamless type fixed Curtain
Wall using: 10mm thk tempered glass on Powder Coated
HD Plain mullion aluminum framing
Main Entrance
CW - 2
Curtain Wall 2 (CW2) - Seamless type fixed Curtain
Wall using: 10mm thk tempered glass on Powder Coated
HD Plain mullion aluminum framing
Triage Area
ACCESSORIES/FINISHES
TYPE MATERIAL'S SPECIFICATIONS LOCATION
Handle 38mm dia x 1200mm Stainless Steel Glass Door Handle All Glass doors
Hardware 4 x 4 Loose Pin Door Hinge
4 pcs per door leaf All Wooden doors
Finish Cut-out Frosted Sticker All Glass doors and curtain
walls
16 TILEWORKS
1. Tile works include the provision of all necessary fixtures and facilities required by the
project and as shown on plans to be approved by the Owner or authorized
representative/engineer.
2. Tile works cover all floors specified and as scheduled in the Floor pattern Layout.
Page 45
44
3. Appropriate cement, tile adhesive, grout and all necessary tile accessories to be
approved by BatStateU or authorized Representative/Architect/Engineer.
4. All tileworks on the run of stairs shall have mechanical cut lines to be approved by the
Owner/ Architect/ Engineer.
5. Stone cladding must be mechanically fixated, contractor must provide a shop
drawing/ mock up for this process.
6. Mechanical fixation of Cladding shall use 4’ x 8’ x 5mm thk Stainless Steel metal
sheet to be fabricated to 40mm x 120mm Metal Clips which will be screwed/nailed in
to place. (1 Metal Clip for each Stone Cladding)
7. Use heavy duty cement-based tile adhesive to all tile works. Application thickness of
tile adhesive shall be 10mm thk. For vertical applications and 6mm thk for horizontal
applications.
8. Tileworks Schedule:
FLOOR TILES
SCHEDULE MATERIAL'S SPECIFICATIONS LOCATION
FF1 10mm thk. 60cm x 60cm Outdoor Granite Tiles
Color: Shade of Grey
Main Entrance
PWD Ramp
Waiting Shed
FF2 10mm thk60cm x 60cm Polished Granite Tiles
Color: Shade of White
Triage area
CCTV Room
Information Desk/Guard
Station
Pantry
FF3 10mm thk30cm x 30cm Matte Tiles
Color: Shade of Grey Toilet
WALL TILES
SCHEDULE MATERIAL'S SPECIFICATIONS LOCATION
WF1
10mm thk60cm x 60cm Polished Granite Tiles
Color: Galaxy Black
(Mechanical Fixated)
Logo Wall
WF2
3/4" thk. Stone Cladding
(Mechanical Fixated)
Color: Rustic/Castle
Main Entrance Column
WF3 10mm thk 60cm x 60cm Decorative Tiles
Color: Shade of Brown/Grey Information Wall
WF4 10mm thk 60cm x 60cm Polished Tiles
Color: Shade of White Toilet walls
COUNTER TILES
Page 46
45
SCHEDULE MATERIAL'S SPECIFICATIONS LOCATION
COF
60cm x 60cm Polished Granite Tiles
(For Counter Top, Counter edge and Splash Board)
Color: Galaxy Black
Pantry Counter
Wash Area Counter
OTHER MATERIALS
Misc
4’ x 8’ x 5mm Stainless Steel Plate
Tile Grout
Heavy Duty Tile Adhesive
Cutting Disk
Cement
17 CARPENTRY WORKS
A. The work includes the furnishing of materials, tools and equipment, methods and
labor necessary to complete all carpentry work requirements.
B. Carpentry works includes construction of all interior and exterior ceilings and
information counter
C. Provide sample/shop drawing for approval by architect/Owner.
D. Ceiling works specifications:
CEILING
TYPE MATERIAL'S SPECIFICATIONS LOCATION
CF1
0.20mx2.8mx12mm thk Wood Panel Composite
50mm x 35mm Metal Clip
L – Profile Edge Trimming
Double Furring 0.40mm x 19mm x 5m
Wall Angle 50mm x 25mmx 3m
C-Channel 1mm x 12mm x 38mm x 5m
Wall Clip
Suspension Clip
Fiber Cement Board Screw
Mesh Tape
Gypsum Putty
Main Entrance
Waiting Shed
Information Desk/Guard
Station
CF2
4.5mm x 4' x 8' Fiber Cement Board
Double Furring 0.40mm x 19mm x 5m
Wall Angle 50mm x 25mmx 3m
C-Channel 1mm x 12mm x 38mm x 5m
Wall Clip
Suspension Clip
Fiber Cement Board Screw
Mesh Tape
Gypsum Putty
Triage Area
Toilet
CCTV Room
Information Desk/Guard
Station
Pantry
Page 47
46
INFORMATION
TYPE MATERIAL'S SPECIFICATIONS LOCATION
4'x8'x3/4" thk. Machine-Pressed High Pressure Laminate
(HPL) Medium Density Fiber (MDF) Board
PVC Edge Banding
Information Desk
18 PAINTING WORKS
A. All painting materials shall be approved by the architect/owner, unless otherwise
specified. Use first class neutralizer, primer and sealer, putty, tinting color (gloss,
semi-gloss and flat) and thinning solvents.
B. Prior to painting works, all exposed finish hardware, electrical plates & fixtures,
plumbing fixtures, toilet accessories, glasses and the like shall be adequately
insulated/protected that these are not stained with paint and stain materials. All other
surfaces which stain would endanger paint marks should be taped and covered with
paper or equal.
C. Apply the proper number of coats to affect a painted surface which is not transparent,
looks full bodied when dried, and generally as recommended by the manufacturer for
the respective paint types.
D. For all areas specified for moisture protection shall be coordinated with painting
procedures shown on brochures from manufacturers.
E. Painting of entire structure.
F. Provide sample for approval of End User/Owner/Architect/Engineer
G. Paint Specifications:
CONCRETE SURFACES
TYPE MATERIAL'S SPECIFICATIONS LOCATION
Elastomeric Paint
(Semi – Gloss)
Concrete Neutralizer
Acrylic Concrete Primer and Sealer
Putty
Elastomeric Paint (Semi – Gloss)
All Exterior Concrete Walls
Latex Paint
(Semi – Gloss)
Concrete Neutralizer
Acrylic Concrete Primer and Sealer
Putty
Latex Paint (Semi – Gloss)
All Interior Concrete Walls
WOOD SURFACES
TYPE MATERIAL’S SPECIFICATIONS LOCATION
Fiber Cement Board Primer
Glazing Putty
Main Entrance
Waiting Shed
Page 48
47
Latex Paint (Flat) CCTV Room
CCTV Room Toilet
Wooden Panel Doors
Primer
Epoxy Reducer
Quick-Drying Enamel
D3 and D4
STEEL SURFACES
TYPE MATERIAL'S SPECIFICATIONS LOCATION
Enamel Paint (Gloss)
Red Lead Primer
Epoxy Reducer
Quick-Drying Enamel
Fence Grills
Vertical Trellis
19 STAINLESS LOGO, LETTERS AND SIGNAGES
A. This work includes the supply and installation of the following:
TYPE QTY MATERIAL'S SPECIFICATIONS LOCATION
Logo
1 set 1.10m dia 2” depth Stainless Steel Build-
up BatStateU Logo
Logo wall – Main
Entrance
Lettering
20 pcs/letters
0.20m Height 2" Depth Stainless Steel
Lettering:
Font: Century Gothic
Text:
"GATEWAY TO GREATNESS"
60 pcs/letters
0.45m Height 2" Depth Stainless Steel
Lettering:
Font: Century Gothic
Text:
LEADING INNOVATIONS,
TRANSFORMING LIVES
STEAM Library Facade
6 pcs/letters
0.30m Height 2" Depth Stainless Steel
Lettering:
Font: Century Gothic
Text:
BASICS
STEAM Library Facade
11 pcs/letters
0.17m Height 2" Depth Stainless Steel
Lettering:
Font: Century Gothic
INFORMATION
Information Counter
Plate Signage 4 sets 8" X 10" (80 sq.in.) PWD Logo Stainless
Steel Signage PWD Entrance/Exit
Page 49
48
3 sets
6" X 8" (48 sq.in.) Stainless Steel Signage
for:
CCTV Room, Toilet & Pantry
CCTV Room
Toilet
Pantry
20 LANDSCAPE WORKS
A. This item includes all landscaping works that is specified in the Vertical planters,
plant boxes, Floor Plan, Site-Development plan.
B. For garden soil, use loam soil to ensure that plants have a steady supply of moisture
without drowning.
C. Supply and planting of vertical planters, garden soil, grass, landscape stones/pebbles,
mulch, trees and plants to be approved by Owner’s Representative/PMO.
D. Provide necessary equipment and materials for Landscaping.
21 MECHANICAL WORKS
A. All air conditioning and ventilation units to be installed shall be of approved quality
and shall be presented through original catalogue/s and/or physical presentation of
units to the Owner/Representative or consultant for mechanical works of the Project
Management Office of BatStateU for approval prior to installation.
B. Air conditioning and ventilation units and/or brand/s shall be presented and approved
by owner/representative prior to installation.
C. Hangers, supports and pipe sleeves for the entire air conditioning and ventilation
system shall be provided. All hangers and supports shall be hot-dip galvanized after
fabrication to provide high resistance to corrosion.
D. One (1) set of 1.5HP inverter split-type wall-mounted air conditioning units shall be
supplied and installed. 1.5HP inverter split-type wall-mounted air conditioning unit
consists of a pair of indoor unit and outdoor unit. The ACUs shall comply with the
following specifications:
Legend ACU-1
Number of sets to be
supplied and Installed 1 unit
Location to be Served CCTV Room
Nominal Capacity 1.5 HP
Unit Type Inverter
Wall Mounted Type
Page 50
49
Power Supply
Voltage: 230V
Frequency: 60Hz
Phase: Single Phase
Power 1,330 W
Dimension (HxWxD), mm Indoor: 293 x 798 x 240
Outdoor: 550 x 780 x 290
Weight, kg Indoor: 9
Outdoor: 26
Refrigerant R32
Cooling Capacity 3,312 - 14,760 kJ/hr
Sound Level, dB(A) 23
Copper Tube Size
Liquid 1/4 in
Copper Tube Size
Gas 3/8 in
Maximum Interunit Piping
Length, m 20
Maximum Installation
Level Difference, m 12
E. Refrigerant piping, condensate drain lines, control wires and all necessary materials
for the completion of the system shall be provided and installed accordingly.
F. All other materials whether indicated on plans or not, shall be provided if necessary
for the system to operate.
G. One (1) unit of 8” (215mm) ceiling mounted exhaust fans and one (1) unit of 8”
(245mm) wall mounted exhaust fans shall be supplied and installed. Ceiling mounted
exhaust fan shall be installed following the connections of air pipes shown on the
plans. The exhaust units shall comply with the following specifications:
Legend EF-1 EF-2
Number of Units to be
Supplied and Installed 1 unit 1 unit
Locations to be Served Pantry Comfort Room
Nominal Size 8" (215mm) 8" (245mm)
Unit Type Ceiling Mounted Wall Mounted
Page 51
50
Power Supply
220-230V,
60Hz,
Single Phase
220-230V,
60Hz,
Single Phase
Motor Rating 20W 35W
Air Delivery 286 cfm 286 cfm
Nominal Diameter of
Air Pipe 4" (100mm) N/A
H. Ductworks and duct accessories, and necessary hangers and supports for the air pipe
of the exhaust system shall be provided and installed accordingly for the full operation
of the system.
I. Stainless round Louver Wall Air vent, air outlet, ducting, ventilation exhaust grille
cover shall be supplied and installed. Specifications of the material shall be submitted
and shall be approved by the assigned project architect from Project Management
Office of BatStateU.
J. One (1) unit of carbon dioxide fire extinguisher and three (3) units of dry chemical
fire extinguisher shall be supplied and installed as shown on the plans.
Type DRY CO2
Number of Units to be
Supplied and Installed 3 units 1 unit
Locations to be Served
TRIAGE AREA,
GUARD
STATION &
PANTRY
CCTV ROOM
Capacity 10 lbs 10 lbs
Height 25.00 in 25.00 in
Diameter 6 in 6 in
Hose Length 44.00 in 44.00 in
Pressure 1,000 psi 1,000 psi
Discharge Time 13.12 sec 13.12 sec
K. Testing and commissioning shall be performed with the member/s of technical
working group as witness/es prior to turn-over and acceptance.
Page 52
51
22 ELECTRICAL WORKS
A. GENERAL CONDITIONS
All works shall be in accordance with the governing codes and regulations of
the latest edition of the Philippine Electrical Code, with the rules and
regulations of the National and Local Authorities concerned in enforcement
of electrical laws and ordinance and with the rules and regulation of the
utility companies concerned.
Contractor shall furnish all labor, equipment and materials as may be
approved by the owner or his/her representative and shall perform all
operations with electrical system shown in the drawings, their test and
inspection complete in accordance with specifications and drawings and
subject to terms and conditions of the contract and materials not specifically
mentioned to bring the electrical system to operating condition and ready for
use by the owner.
Electrical works shall be under the full supervision of a duly licensed and
registered electrical engineer. Failure to do so shall mean a non-compliance
to the said contract.
All electrical material shall comply with the requirements of the
Underwriter’s Laboratories (UL standards), the ASTM and IPCEA as they
apply in the particular.
Submit and secure approval by the Architect/Engineer or by duly authorized
representative of the owner before procurement, fabrication or delivery or
installation of items to the jobsite. Submittal shall include the sample,
manufacture's name, trade name, place of manufacture, catalog model or
number, nameplate data, size, layout dimensions, ratings and capacity.
Electrical materials shall be as specified herein or electrical drawing details
as shown in the plans. Consult TWG for discrepancies.
B. PANELBOARD
The panel shall be used and assembled on job as much as possible. The panel
shall be of code gauge steel #16 in NEMA 12 flush type enclosure. Two keys
per panel shall be furnished. The trim for all panels shall be finished in
industrial gray enamel over a coat of rust inhibitor.
Panels and cabinets shall be as manufactured by manufacturers with ISO and
BPS Certificates. Manufacturer’s shop drawings shall be submitted before
manufacturing.
Panelboard main bus work shall be ampacity rated to equal or exceed over
current protective device immediately ahead of it. All bus work shall be
properly secured to withstand available short circuit forces at the location.
Page 53
52
All distribution panels shall be provided with permanent panel designation and
directory. Submit sample for approval of Engineer/Architect prior to
fabrication. Panel designation shall be similar to panelboard schedule and panel
directory shall be provided with circuit number, breaker rating, size of wire and
conduit.
Provide grounding strip inside the panel intended for the main feeder, and all
the branches, including one unit for the ground rod or grounding line as
required.
C. INDIVIDUAL BREAKERS AND SWITCHES
Provide individual circuit breakers, safety switches, and disconnect switches
here indicated on plans. Voltage ratings shall be suitable for each case of
service application. Enclosures shall be General Purpose, NEMA Type 12,
except where specifically noted on plans or assembled on panel cabinets.
All protective devices shall meet NEMA and Underwriter’s Laboratories,
Inc. specifications.
Circuit breakers shall consist of a quick-make, quick-break type entirely trip-
free operating mechanism with contacts, arc-interrupter, and thermal
magnetic trip unit for each pole, all enclosed in a molded-phenolic case. The
thermal-magnetic trip unit shall provide time-delayed overload protection in
case of overload or short circuit current in any one pole. Circuit breaker
shall be trip indicating, with the tripped position of breaker handle midway
between “ON” and “OFF” positions.
All circuit breakers shall be bolt-on type. Plug-in circuit breakers are not
acceptable.
Circuit breaker shall be as manufactured by manufactures with ISO and BPS
Certificates. Unless otherwise specified, minimum interrupting level for 220
volts circuit breakers shall be 10,000 amperes.
D. WIRES AND CABLES
All secondary wires shall be copper, soft-drawn and annealed; shall be of
ninety eight percent (98%) conductivity; insulated for 600 volt working
voltage; and with type “THHN/THWN”, “THW” or “THWN” insulation
unless otherwise specified in the Drawings. Insulation shall bear
manufacturer’s trademark, type, rating and wire size and with ISO and BPS
Certificates.
All wires 3.5 mm2 or larger shall be stranded copper. However, solid wires
can be used as required by the manufacturer’s particularly wiring devices
such as the switches and the outlets.
Page 54
53
For lighting and power systems no wire smaller than 3.5 mm2 shall be used
unless otherwise indicated in the plan.
Wire color coding for secondary lines: Phase A - Black, Phase B- Red, Phase
C – Blue and for ground wire use Green Wire and for Neutral use White or
refer to the building color coding requirement.
Splices and Termination Components:
Splices and Termination Components: Connectors for wires
5.5sqmm and smaller shall be insulated pressure-type or twist-on splicing
connector (wire nut) for wire jointing or splicing. Provide solder less terminal
lugs on stranded conductors in termination works. All splices shall be properly
insulated using approved brands of electrical tape. Application of insulation
tape shall be equivalent to the insulation of the wire concerned. However,
rubber tape can be used as required when the area is subject to excessive
moisture or in wet locations.
E. CONDUIT AND FITTINGS
Poly-vinyl-chloride (PVC) conduit shall be PNS14 thick wall, schedule 40,
with factory made couplings and fittings and with ISO and BPS Certificates.
No conduits smaller than 20 mm (½ inch) diameter electric trade size shall be
used in any system. Conduits shall have no more than, four (4) 90-degree
bends in any one run and where necessary, pull boxes shall be provided upon
the discretion and direction of the Site Engineer. If it is not possible to pull
the cable, use only 3 bends.
No wire shall be pulled into any conduit until the conduit system is
completed in all details, in the case of concealed work until all rough
plastering masonry has been completed, and in the case of exposed work
until the conduit work has been completed in every detail.
The ends of all conduits shall be tightly plugged to exclude plaster, dust and
moisture while the construction of building is in progress. All conduits shall
be reamed to remove all burrs.
F. OUTLETS, BOXES AND FITTINGS
At all outlets of whatever kind, for all system, there shall be provided a
suitable fitting, which shall be either a box or other device specially designed
to receive the type of fitting to be mounted thereon.
The Contractor shall use the correct conduit fittings in the metal/PVC boxes’
connections and shall conform strictly in the use of fittings as well as to the
nature of the appliance to be mounted on them so that the work will be
adaptable to the manufacturer’s recommendation.
Page 55
54
At all outlets on concealed conduit work, provide galvanized pressed steel
outlet boxes of standard make. These boxes shall be in all cases standard and
where such boxes are not available on the market, special boxes shall be
secured by the Contractor at his own expense. In general, boxes shall be at
least 100 mm in diameter, 53 mm deep and 2 mm minimum gauge or as
indicated in the plans.
All utility boxes intended for outlet devices shall be especially designed to
receive the particular type of device to be mounted and should be deep
enough to accept and fit the total number of conductors and device required.
Junction and pull boxes, of code gauge steel, galvanized shall be provided as
indicated or as required for facilitating the pulling of wires and cables. Pull
boxes in finished places shall be located and installed with the permission
and to the satisfaction of the Architect and Engineers. Junction and utility
boxes shall be provided with red-oxide paint finish while the pull-boxes or
wire gutters are epoxy paint finish with galvanized
screws/bolts/nuts/washers.
In case of fixtures, their outlet fittings shall be provided with suitable
supports of size and kind required by the fixture to be hung. Fixture studs
shall be 9mm dia.
Automatic Boom Barrier’s devices and controls will be supplied and
constructed by Supplier/Contractor. For the power supply, refer to the plan.
G. WALL RECEPTACLES, SWITCHES & PLATES
Receptacle outlets shall be 16 Ampere, 250V, 3 prong, parallel grounded
type with individual switch. Locking type and other special purpose
receptacle outlets shall be as indicated in the drawings.
Wall switches shall be rated 16A, 250V ratings. Switches shall be for flush
mounting type and of the quiet type, spring operated. The type of switches
shall be tumbler operation and the color, plating and appearance of wall
plates shall be as selected by the Architect. Appropriate samples shall be
submitted prior to the purchase of wall switches and faceplates. Only (1)
brand of wiring devices shall be used for the project.
Type and color of receptacle outlet and plates shall be as selected by the
Architect. Appropriate samples of outlets and plates shall be submitted prior
to purchase of devices.
H. LIGHTING FIXTURES
Light Emitting Diode (LED) fixtures as specified in the plan shall conform to
UL Standards, 220 volts. Lamp receptacle shall be of the pin type installation
or as noted in the plan approved by the Architect. Refer to the Landscape
Architect plan for type and the degree of protection and it shall meet NEMA
and Underwriter’s Laboratories, Inc. specifications.
Page 56
55
Outdoor lighting shall be in approve application and in weatherproof type.
For other type of lighting fixtures, refer to the plans or as required by the
Architect.
23 ELECTRONICS AND COMMUNICATION WORKS
A. CLOSED CIRCUIT TELEVISION (CCTV) SYSTEM
The power supply available other electrical loads of the system is 230V,
AC±10%,60Hz, ±3%,and sufficient isolation shall be provided from the
loads.
The electronic circuits used in the system shall be of solid state fail – safe
design and be provided with proper coating to have resistance to humidity
and corrosion which prevents the operation from being impaired by dust
and dirt.
The cameras shall be tamper– proof and shall alarm during tampering, and
shall log the event to the main database and shall be plug-in type with
suitable locking devices.
The bidders who wish to supply cameras apart from there commended make
shall produce the test/qualification certifications of the cameras. Bidding
without certificates or producing fake certificates may lead to disqualify
the bidder.
The Video Managements of tw are shall be user – friendly and menu driven
with self– checking i.e. all the routines shall be checked periodically for
their proper functioning and integrity.
Diagnostic checks shall be done by the system periodically for the proper
functioning of the Video cameras.
The configuration modifications can be done only from the control room.
The system shall have flexibility for upgrading and expansion in all respects
depending on future requirements.
The supplier may quote for additional items if required for completion of
the system under the heading as optional items.
All the software manuals, hardware manuals, user manuals, training
manuals related to the system shall be supplied in hard copy format (2 sets)
and 2 nos. in CD format.
Page 57
56
The system shall confirm highest standards of the engineering design and
workmanship. The system shall perform well without much degradation for
the service life of 20years.
CCTV Equipment system consisting of 5MP BULLET IP Cameras, sets of
NVR/DVR with minimum of 8TB capacity each complete with all of its
amenities such as cables, conduits, POE ports/switches, pull boxes, junction
boxes, AVR, rack/server cabinet, mouse, keyboard, speakers and etc.
Submit design, shop drawings and full specifications for evaluation and
approval.
CCTV Cameras shall have 5MPx camera for indoors and outdoors.
Detailed QHD (5MPx) resolution of 2560 x 1440 pixels at 25
frames/second. True WDR image enhancement: Clear detail even with
backlighting and strong contrasts. Integrated software motion detection with
H.265 plus provides 6 times more recording capacity. Integrated IR LEDs
for optimal night vision. Capacity to send images by email. Web and mobile
access to live images using the IP Cam Plus app or browser. PoE (Power
over Ethernet)-compatible.
All connector like RJ- 45, LC connect or patch cord etc. required to complete
the system is in supplier s scope.
Inspection, Testing and Commissioning: The purchaser or his authorized
representative shall have access to the supplier's premises at all reasonable
times to the extent necessary to assess compliance with the provisions of this
specification. All the constituent units of IP based CCTV system equipment
supplied to the provisions of this specification shall be subjected to visual,
dimensional and functional inspection and testing to the satisfaction of the
purchaser. Where functional and operating tests are performed, the
equipment shall comply with all the provisions of this specification at the
conclusion of such tests .To this effect written procedures describing the
step wise inspection and testing procedures in-detail shall be submitted to
the purchaser for approval, prior to the commencement of such tests.
CCTV Equipment system consisting of:
1. Fixed Dome Camera
Day/Night Functionality
2 Megapixel IP Camera, 2MP Network IR Fixed Dome Camera,
PoE Type, Web, Smartphone and NVR Interface, Ultra
Compression H.265/H.265/H.264, IR Led range up to 30M,
1P67, Vandal Resistant. ONVIF (Profile S,T).
Standards: IEC and UL
2. Fixed Bullet Camera
Day/Night Functionality
Page 58
57
5 Megapixel IP Camera, 5MP Network IR Fixed Bullet Camera,
PoE Type, Web, Smartphone and NVR Interface, Ultra
Compression H.265/H.265/H.264, IR Led range up to 30M,
IP67. ONVIF (Profile S,T)
Standards: IEC and UL
3. Network Video Recorder Specification (NVR)
4-Channel Input, plug and play with four independent POE
network HDMI and VGA simultaneous output, Support ultra
265/H.265/H.264, 1 SATA HDD, up to 10TB, support cloud
upgrade, third party IP cameras supported with Open Network
Video Interface Forum (ONVIF).
Profile S, G and T. Recording Resolution: 1080P/960P/720P
Standard IIEE 802.3AT, IIEE 802.3AF
4. Smart Uninterruptible Power Supply (UPS)
2.5KVA, 230V, 1PH, 60HZ, 0.90 power factor, graphical CD
Display, intelligent battery management, built-in energy meter,
operate without battery, rack height: 85mm, 2U approx.
dimension: 423mmW x 585mmD, 31kg. IR led range up to
30m, IP67. ONVIF
5. IPS Monitor with HDMI, DP and VGA
27” Full HD monitor, 1920x1080 resolution with HDMI,
DisplayPort, and VGA inputs offer flexible connectivity
options
All connector like RJ-45, LC connector patch cord etc. required to complete
the system is in supplier’s scope.
Inspection, Testing and Commissioning: The purchaser or his authorized
representative shall have access to the supplier's premises at all reason able
times to the extent necessary to assess compliance with the provisions of this
specification. All the constituent units of IP based CCTV system equipment
supplied to the provisions of this specification shall be subjected to visual,
dimensional and functional inspection and testing to the satisfaction of the
purchaser. Where functional and operating tests are performed, the
equipment shall comply with all the provisions of this specification at the
conclusion of such tests. To this effect written procedures describing the
stepwise inspection and testing procedures in-detail shall be submitted to the
purchaser for approval, prior to the commencement of such tests.
I. COMMUNICATION AND DATA SYSTEMS
Telephone and Data system shall consist of an interior system of conduits,
outlets boxes, junction boxes and terminal cabinets, smart switches and
manage switch as shown on the plans. UTP/Category 6, 24 AWG x 4 pairs
cable complete with RJ45 connector shall be used or as indicated on the
Page 59
58
plans. All work materials shall be brand new, free from defects, installed and
constructed in a workmanlike manner according to prevailing standard
practice. All cable shall be tested by the contractor and witness by BatStateU.
Test results shall be submitted for approval. Provide permanent unique
identification at each end of all cables. All conduits for the entire installation
shall be uPVC. Voice & Data cable shall be shall be of approved top brands
in the market today.
Smart switches shall comply with IEEE 802. 3u, IEEE 802.3ab, IEEE
802.3x, IEEE 802.1q, and IEEE 802.1p. interface of 24 10/100/1000 Mbps,
RJ45 ports AUTO Negotiation/AUTO MDI/MDIX 10BASE-T: UTP
category 3, 4, 5 cable (maximum of 100m); Network media of EIA/TIA-568
100Ohm STP (maximum 100m); power supply and consumption of 100-
240VAC, 50/60Hz, 14.86W. Support port based/802.1p/DSCP priority.
Support 4 priority queues, Rate limit, Storm Control, L2 Features: IGMP
Snooping V/V2/V3, Link Aggregation, port Mirroring, Cable Diagnostics,
VLAN: Supports up to 128 VLANs simultaneously (out of 4K VLAN IDs).
Transmission method: Store-And-Forward. With at least 4 POE ports.
Wireless access points shall have has a standard networking interface of
802.11 a/b/g/n/ac; 10/100/1000 Ethernet ports; maximum TX power of
2.4GHz, 20dBm – 5GHz: 20dBm; frequency band of 2.4GHz/5GHz; power
method of Passive Power Over Ethernet (24V), (pairs 4, 5+; 7,8 return);
power supply of 24V, 0.5A Gigabit PoE adapter with wireless security of
WEP, WPA-PSK, WPA-Enterprise (WPA/WPA2, TKIP/AES).
Other items not mentioned in the specifications but are included in the
installation shall be subjected to be pre-approved by the owner.
J. FIELD TESTING & COMMISSIONING OF ELECTRICAL SYSTEM
The Contractor shall provide all test equipment and personnel and submit
written copies of all test results. As an exception to requirements that may
be stated elsewhere in the Contract, the Engineer shall be given 5 working
days’ notice prior to each test.
Devices Subject to Manual Operation. Each device subject to manual
operation shall be operated at least five times, demonstrating satisfactory
operation each time.
All equipment tests shall be done in accordance to the manufacturer’s
recommendation and all test results shall be evaluated by them as well as
their approval for the assurance of the good and safety operation. All
equipment shall have warranty and after-sales technical support.
Test on 600-Volt Wiring: Perform tests after wiring is completed, connected,
and ready for operation, but prior to placing system in service and before any
branch circuit breaker is closed.
Page 60
59
Inspect cables for physical damage and proper connection in accordance with
contract plans and specifications. Check cable color coding for compliance
with contract specifications.
Test cable mechanical connections to manufacturer's recommended values
using a calibrated torque wrench. In the absence of manufacturer's data use
NETA recommended values.
Perform insulation-resistance test on each conductor with respect to ground
and adjacent conductor; applied potential shall be 500 volts DC for 1 minute
for a 230volts system; minimum insulation-resistance values shall not be less
than 250,000 ohms.
Perform continuity test to ensure proper cable connection.
Performance Test and Equipment Setting: It shall be the responsibility of the
Contractor to test all systems of the entire electrical installation for proper
operation as shown on drawings and as stated herein. Setting of timers, level
switches, protective relays and pilot devices, etc. shall conform to specified
operating requirement.
Phase Sequence Test: The Contractor shall determine correct rotations of all
motors to conform with the phase sequence of the power installation before
final connection to the incoming line.
Grounding System Test: Test the grounding system to assure continuity and
the resistance to ground is not excessive. Test ground wire for resistance to
ground. Make resistance measurements in normally dry weather, not less
than 48 hours after rainfall. Submit written results of each test to the
Engineer and indicate the resistance and soil conditions at the time the
measurements were made.
Conduit Test: All newly installed conduits shall undergo mandrel test. It
shall be consistent with its inside diameters throughout the span. Cleanliness
and smoothness of the inside surfaces of the conduits, and the smoothness of
conduits curvature shall be properly observed. This item is also a mandatory
test that was required by the Utilities. The lighting system can be exempted
to this practice and testing. All conduits passing the test shall be sealed
immediately by end plugs. Always be sure that the empty conduits shall have
the guide strings.
The testing and commissioning required by this specification shall be the
responsibility of the contractor. These requirements reflect only the
minimum standards and procedures to be followed before electrical facilities
to be turned over to or as being mechanically complete. It shall be the
responsibility of the contractor to make any additional test or commissioning
checks necessary to provide a safe, reliable and functionally sound electrical
installation.
Test Report Forms shall be submitted by the contractor for approval.
Page 61
60
24 REHABILITATION OF OVERHEAD FEEDER LINE
A. GROUNDING SYSTEM
The contractor shall furnish and install complete grounding system as shown
in the drawings.
Ground wire shall be bare copper stranded 30mm2, with size as shown in the
drawings and shall be of cylindrical form and variation shall be within 1% of
the actual size called for.
All metallic conduits, cabinets and equipment shall be properly grounded and
bonded by means of copper straps. The conduits of each system shall be
grounded by connecting to the ground grid.
B. ELECTRICALSTEEL POLE& LINE HARDWARES
Electrical Steel pole shall be non-corrosive steel Hot Dipped Galvanized.
Electrical Steel pole shall be equipped with grounding (bare
copper/aluminum wire) and aluminum/copper ground rod
Grounding connector shall be done by mechanical means.
Electrical Steel pole shall be supported by guy wire anchored to the ground.
The structures may be used in all environments, from coastal regions to
desert areas. All poles must be hot dip galvanized to ISO 1461 and EN
10240.
The minimum thickness of the steel for the manufacture of poles shall be
4.5 mm. The steel used shall be 300 WA in accordance with SABS 1431 or
equivalent. If other materials are used for manufacture the client must
approve these before manufacture commences.
Galvanizing shall be applied by the hot dip process for all parts other than
steel wires and shall consist of a thickness of zinc coating equivalent to not
less than 60 g of zinc per 1,000 cm2 of surface. The zinc coating shall be
smooth, clean and of uniform thickness and free from defects
All drilling, punching, cutting and bending of parts shall be completed and
all burrs shall be removed before the galvanizing process is applied.
Unless otherwise required, all bolts and screwed rods shall be galvanized
including the threaded portion; all nuts shall be galvanized.
All nuts and pins shall be adequately locked.
All exposed bolts, nuts and washers in contact with non-ferrous metallic
parts shall, unless specifically required otherwise, be stainless steel.
Page 62
61
Insulators shall be alight colored porcelain or toughened glass construction,
shall be suitably rated for the operational voltage of the power-line and
used within the manufacturers design restrictions. All fittings and
ironworks on insulators (except locking clips) shall be heavily galvanized.
Cross- arms shall be 2x3000 x 101 x 51 x 10.4 mm galvanized steel
channel minimum unless specified otherwise. All cross-arms shall be level
when the structures are completed and the conductors tensioned. Cross-arm
straps shall be fitted and secured to ensure that the cross-arms remain level.
All non-current-carrying metal parts on each pole shall be bonded together
and to be connected to the ground. The earth shall be made by running the
overhead earth wire down the pole and connecting it to a 3 m long 15 mm
diameter copper-clad earth rod.
C. CABLE LADDER
Cable ladder shall be Hot Dipped Galvanized heavy-duty ladder type welded
construction consisting of 100mm depth, two longitudinal I-beam side
members of minimum 2mm thickness, and connected by individual transverse
members of minimum 2mm thickness.
Rung shall be full scallop welded on top beam and tag welded at bottom.
Cable ladder to have minimum 75mm loading depth and shall have 5 Nos.
11mm x 11mm square holes at both ends of C-Channel side member.
Rung spaces shall be 229mm on straight runs and 229mm centers to center of
radius and fittings. Rungs to have 30mm minimum cable bearing surface with
radius edges. Rungs shall be perforated for cable ties.
Fittings shall have the same load carrying capacity as straight sections.
Fittings shall be of the continuous concentric arc type with radius as specified,
hinged fittings shall not be utilized.
Each straight section shall be supplied with one pair of splice plates and
necessary bolts, nuts and washers. Each splice plate shall be designed for
eight (8) holding bolts, four (4) in each tray side rail.
Side rails of straight sections and radius fittings shall be compatible to
standard splice plates (75mmTangents).
Cable ladder shall be supplied in 2400mm nominal lengths.
Cable ladder shall be physically and electrically continuous from point of
supply to point of utilization.
A 30mm copper cable with Green insulation with crimped lugs shall be bolted
to the side of the ladder or tray across the jointing plate using 2 bolts and nuts
for bonding purpose only.
Page 63
62
The cable support system shall be complete with joints tightened, fittings
installed, and supports erected before cable is installed on the tray or ladder.
Cable tray and ladder supports shall be fixed by means of standard mild steel
channel and angle welded or clamped to the steel pole.
25 PLUMBING WORKS
25.1.1.1 General
All plumbing works included herein shall be executed according to the
provisions of the National Plumbing Code, National Building Code and the
Rules and Regulations of Batangas City.
The drawings are not intended to show every pipes, fittings, valves and
appliances. All such item whether specifically mentioned or not or indicated
on the drawings shall be finished and installed if necessary, to complete the
system in accordance with the best practice of the Plumbing Trade and to the
satisfaction of the Owner/Representative.
All materials to be used shall be new and shall conform to the Reference
Code and Standards. Use of materials shall further be governed by other
requirements, imposed on other section of these specifications. Materials
shall be subject to test necessary for their fitness if so required.
The Contractor shall furnish all materials, labor and equipment necessary for
the installation of all water lines, fixtures and accessories.
All materials and equipment to be installed shall be of approved quality and
should be presented to BatStateU/Representative Architect/Engineer for
approval prior to installation.
All works must communicate to the Owner/Representative before
commencement.
SYSTEM DESCRIPTION: Provide new plumbing systems, complete and
ready for operation. Plumbing systems including manufacturer’s products
shall be in accordance with the required and advisory of the IAPMO Uniform
Plumbing Code and Philippine National Plumbing Code. Plumbing systems
include piping less than 1.50meters outside of the building.
SUBMITTALS:
Product data:
Pipe and fittings
Valves
Pipe hangers and supports
Water meters
Page 64
63
Drains
Certificate of Conformance:
Pipe and fittings
Valves
Pipe hangers and supports
Water meters
Drains
Shop Drawing (as required)
Detail drawings consisting of schedules, performance, charts,
instructions, diagrams, and other information to illustrate the requirements and
operations of systems that are not covered by the Plumbing Code. Detail
drawings for the complete plumbing system including piping layouts and
locations of connections; dimensions for roughing-in, foundation, and support
points; schematic diagrams and wiring diagrams or connection and
interconnection diagrams. Detail drawings shall be indicated clearances
required for maintenance and operation. Where piping and equipment are to
be supported other than as indicated, details shall include loadings and
proposed support methods. Mechanical drawing plans, elevations, views, and
details shall be drawn to scale.
Test Reports
Test, Flushing and Disinfection
Test reports in booklet form showing all field tests performed to
adjust each component and all fields test performed to proved compliance
with the specified performance criteria, completion and testing of the
installed system. Each test report shall indicate the final position of
controls.
STANDARD PRODUCTS: Specified materials and equipment shall be
standard products of a manufacturer regularly engaged in the manufacture of
such product. Specified equipment shall essentially duplicate equipment
satisfactorily at least two (2) years prior to bid opening. Standard products
shall have been satisfactory commercial or industrial use for two (2) years
prior to bid opening. The two (2) years use shall include applications of
equipment and materials under similar circumstances market through
advertisements, manufacturers’ catalogs, or brochures during the (two) 2
years period.
Delivery, Storage and Handling
Handle, store, and protect equipment and materials to prevent
damage before and during installation in accordance with the manufacturer’s
recommendations, and as approved by contracting officer. Replace damaged
or defective items.
Page 65
64
25.1.1.2 QUALITY ASSURANCE: Plumbing systems including fixtures, materials,
installation, and workmanship shall be in accordance with the plumbing Code except
as modified herein. In the Plumbing code referred to herein, the advisory provisions
shall be considered to be mandatory, as though the word ‘shall’ had been substituted
for the word “should” wherever it appears.
25.1.1.3 MATERIAL’S SPECIFICATION
DWV (DRAIN, WASTE, AND VENT) PIPING: Fittings shall be radius
fittings, except fittings in vent piping which may be short radius fittings.
Minimum size piping shall be 50mm (2”) for buried and aboveground piping.
SANITARY (SEWER) / WASTE LINES – Soil pipes shall be Polyvinyl
Chloride (PVC) Pipes with maximum SDR of 34 per ASTM D3034.
VENT LINES – Branch vent pipes shall be Polyvinyl Chloride (PVC) with
maximum SDR of 34 per ASTM D3034.
CLEANOUTS – ANSI 112.36.2; provide threaded bronze or thermoplastic
cleanouts plugs.
Floor Cleanouts – provide cast-iron floor cleanout with flange,
polished bronze or nickel bronze rim and scoriated floor plate with
CO cast in the plate. Secure floor plate with the counter sunk screws
for installation flush with finished floor.
Ground Cleanouts – provide cast-iron cleanouts and countersunk
plugs. Provide 450 x 450 x 150mm think concrete slab with top
25mm above grade with cleanout located in center of slab.
STORM DRAIN
Drain Pipe: Exterior and Interior Pipes: Exterior and interior storm
drainage pipe shall be Polyvinyl Chloride (PVC) pipe conforming to
the specification of ASTM D 2665 or equivalent for pipes smaller
than 250mm diameter. The engineer reserves the right to inspect
and test the pipe delivered for intended purpose. Defects that are
discovered after acceptance of delivery of the pipes but before
installation shall be cause for rejection without additional cost to the
employer.
DOMESTIC WATER PIPING
Cold Water Line - Embedded pipes shall be Polypropylene Random
(type 3), high resistance to pressure and temperature, conforming to
en ISO 15874, PN 20. Exposed pipes shall be hot-dipped
Galvanized iron pipe conforming to ASTM A53 or ASTM A-120
Schedule 40.
Page 66
65
WATER VALVES: Valves shall have flanged end connections, except sizes
smaller than 65mm (2 ½”) may have threaded end connection with a union
on all but one side of the valve, or solder connection for connections between
bronze valves and polyethylene tubing. Copper alloy and bronze valve body
shall be ASTM B61 or ASTM B62 copper alloy. Ball valves may be
provided in lieu of gate valves.
Valves: MSS SP-80, Class 125 except sizes 65mm and larger shall
Conform to MSS SP-70, Class 125.
Check Valves: MSS SP-81, Class 125, swing check cast-iron or
bronze body.
Water Meters: AWWA C700 positive displacement type, with
register reading in liters and U.S. gallons.
MISCELLANEOUS MATERIALS:
Escutcheon Plates: Provide one piece or split hinges type metal
plates for piping passing through floors, walls, and ceilings in
exposed spaces, chromium-plated finish on plates in finished
spaces, paint finish on plates in unfinished spaces and with set
screws or other approved positive means to anchor plates in place
securely.
Plastic pipes and fitting shall be joined using the solvent cement
joining system (Sanitary, Storm, Vent and Downspout) Polyvinyl
Chloride (PVC) Pipes with maximum SDR of 34 per ASTM D3034.
Pipe Sleeves:
Sleeves in Masonry and Concrete Walls, Floors, and
Roofs: ASTM A53 or ASTM A120, Schedule 40 or
standard weight, hot-dip galvanized steel pipe sleeves.
Sleeves in Partitions and Other Than Masonry and
Concrete Walls, Floors, and Roofs: Hot-dip galvanized
steel sheet having a nominal weight of not less than
4.40kg/m².
Pipe Hangers and Supports: Provide MSS SP-58 or MSS SP-69,
Type 1 or 6, of the adjustable type, except as modified herein or
indicated otherwise. Attachments to steel W or S beams shall be
with Type 21, 28, 29, or 30 clamps. Attachments to steel angles and
channels (with web vertical) shall be with Type 20 clamp with a
beam clamp channel adaptor. Attachment to steel channel (with web
horizontal) shall be with drilled hole on centerline and double nut
and washer. Attachment to concrete shall be with Type 18 insert of
Page 67
66
the hanger threaded diameter. Provide Type 40 insulation protection
shields for insulated piping. Provide steel support rods.
TRAPS
Unless otherwise specified, traps shall be plastic per ASTM F 409.
Traps shall be with a clean-out. Provide traps with removable access
panels for easy clean-out at sink and lavatories. Inlets shall have
rubber washer and copper alloy nuts for slip joints above the
discharge level. Swivel joints shall be below the discharge level and
shall be metal-to-metal or metal-to-plastic type as required for the
application. Nuts shall have flats for wrench grip. Outlets shall have
internal pipe thread, except that when required for the application,
the outlets shall have sockets for solder-joint connections. The depth
of the water seal shall not less than 50mm. the interior diameter
shall be not more than 3.2mm over or under the nominal size, and
interior surfaces shall be reasonable smooth throughout. A copper
alloy “P” trap assembly consisting of an adjustable “P” trap and
threaded trap wall nipple with cast brass wall flange shall be
provided for lavatories. The assembly shall be standard
manufactured unit and may have a rubber-gasketed swivel joint.
25.1.1.4 EXECUTION
Installation: Installation of plumbing system including equipment, materials,
and workmanship shall be in accordance with the IAPMO Uniform Plumbing
Code and Philippine National Plumbing Code except as modified herein.
Threaded Connections: Jointing compound for pipe threads shall be
polytetrafluoroethylene (PTFE) pipe thread tape, pipe cement and oil, or
PTFE powder and oil; apply only on male threads. Provide exposed ferrous
pipe threads with one coat of primer applied to a minimum dry film thickness
of 1.0 mil.
Solder End Valves: Remove stems and washers and other item subject to
damage by heat during installation. Reassemble valve after soldering is
completed. Valves without heat sensitive parts do not require disassembly
but shall opened at least two turns during soldering.
Pipe Supports (Hangers): provide additional supports at the concentrated
loads in piping between supports such as flanged valves.
Maximum Spacing between Supports:
Vertical Piping: Support metal piping at each floor, but at not more
than 3.0 meters intervals. Support plastic piping at each floor and
midpoint between floors, but at not more than 1.5 meters interval.
Page 68
67
Horizontal Piping: Support plastic piping at 1.20 meters intervals,
except for pipe exceeding 1.50-meter length. Provide supports at
intervals equal to the pipe length but not exceeding 3.0 meter.
DISINFECTION: Disinfect the new water piping in accordance with
AWWA C651. Fill the piping system with solution containing minimum of
50 parts per million of available chlorine and allow solution to stand for
minimum of 24 hours. Flush the solution from the system with clean water
until maximum residual chlorine content is not greater than 0.2 parts per
million (ppm).
FIELD TESTING AND FLUSHING: Before final acceptance of the work,
test each system as in service to demonstrate compliance with the contract
requirements. Perform the following tests in addition to the tests specified in
the IAPMO uniform Plumbing Code, and Philippine National Plumbing
Code, except as modified herein. Correct all defects in the work provided by
the contractor, and repeat the tests until the work is in compliance with
contact requirements. Furnish water, electricity, instrument, connecting
devices, and personnel for the tests.
DOMESTIC WATER PIPING: Hydrostatically test each piping system at
not less than 10.50kg/cm sq (150psig) with no leakage or reduction in gage
pressure for 24 hours. Flush piping with potable water. Testing will be done
by sectioning the piping installation during construction period.
DWV Piping: Before the installation of fixtures, cap the ends of each system,
fill the piping with water to the roof, and allow standing until a thorough
inspection has been made. After the plumbing fixtures have been set and
their traps filled with water, subject the entire sanitary system to a final air
pressure test of not more than 25mm (inch) of water column and a smoke
test. Perform the air and smoke test and passage of smoke and air throughout
the entire system. Perform all ball test by flushing. The entire system must be
proven absolutely tight under such test.
26 PLUMBING FIXTURES AND ACCESSORIES
A. Contractor shall furnish all materials, labor and equipment necessary for the
installation of all water lines, fixtures and accessories.
B. All fixtures and accessories shall be new, without defect and shall be presented and
approved by BatStateU/Representative Architect/Engineer prior to installation
C. It includes the provision of:
ITEM MATERIAL'S SPECIFICATIONS LOCATION
Faucet Stainless Steel Wall Mount Tap Faucet Restroom
Page 69
68
Stainless Steel bidet Restroom
Stainless Steel 316 Gooseneck Faucet Pantry
Lavatory Lavatory Wall Hung Type Half Pedestal
35cmx55cm Restroom
Sink Stainless Steel Single Bowl Kitchen Sink Pantry, Wash Area
Water Closets Dual flush push button with complete fittings Restroom
Soap Dispenser Stainless Steel Liquid Soap Dispenser with
complete accessories Restroom
Tissue Holder Stainless Steel Tissue Holder Restroom
Floor Drain 4” x 4” Stainless Steel Restroom, Pantry
Mirror ¼” thick Glass with backing, Class A All Restrooms
Grease Trap Stainless Steel Portable Grease Trap, 4GPM Pantry
Roof Drain 50mm Dome-Type Roof Drain Lower roof Slab
Deck Drain 75mm Stainless Steel Deck Drain Roof Deck
D. Provide samples for Owner’s/Architect approval.
27 CATCH BASINS
A. The Contractor shall supply all materials, labor, and equipment for the construction of
the catch basins.
B. The construction of said catch basins shall be in accordance with the detailed plans.
28 HAULING OF WASTES AND DEMOLISHED MATERIALS
i. Hauling of waste and demolished materials and cleaning of all the excess and
unnecessary materials.
1 INTRODUCTION
The university must be prepared to accommodate and manage bulk students, teachers,
faculty members and visitors in Pablo Borbon Campus, given the situation that COVID-19 will
end soon and service in the university will be normalized. With approximately 14,000 students,
817 employees and faculty members and number of anticipated visitors including parents and
students from Integrated School, it is imperative to look on how to manage the smooth access
Page 70
69
and egress in order to avoid traffic in the university during its usual operation and emergency
situation.
Currently, Pablo Borbon Campus has two pedestrian access and egress points located
near the University Gymnasium and the main gate at the front beside the Student Services Center
Building II. The pedestrian gate near the gymnasium in the main access and exit points of the
students, faculty and employees of Integrated School and CABEIHM while pedestrian gate at
the front is the main entrance and egress points of the students of General Engineering (GE),
College of Teacher Education (CTE), College of Arts and Sciences (CAS) and employees and
staffs at SSC II building. The university also has one access and three egress points for vehicle.
As the Director of ACTION Center looked into current infrastructure of the aforesated
campus that may accommodate a number of occupants, he has found out that the new erected
building, STEAM Library is facing west (Coliseum Building) which could possibly create delay
and traffic requiring immediate evacuation due to disaster and emergency situation. Moreover,
the provision of evacuation site inside the university is also inadequate which could possibly
accommodate the bulk of the evacuees within the university premises. One of the proposed
campus evacuation sites is the open ground near the coliseum that can accommodate students
from the Integrated School and number of students and employees from CABEIHM. To provide
an immediate egress of the evacuees in the campus avoiding delays and traffics, the project
Construction of Façade was proposed.
Also, the University provides excellent services, quality facilities, and globally
competent programs, all of which contribute to the growth of the campus community. The
University acknowledges its need to emphasize the convenience it could offer not only its
students but also every individual in need of their service; hence, the proposal of Façade.
2 SCOPE OVERVIEW
The Scope of Work includes but is not limited to the Proposed Construction of Façade
Gate Four and Fence located at BatStateU – Pablo Borbon, which will sets expectations and
defines the feel of the overall structure. It can also help achieve the goal of blending in with the
surroundings or standing out from the crowd.
3 DESCRIPTION OF THE FACILITY
A. The construction in general will be reinforced concrete framed structure with concrete
hollow blocks (CHB).
B. The proposed façade and fence shall include :
1. Vestibule
2. Turnstile Area
3. Entrance
4. Exit
5. Elevated Walkway
6. Information Desk/Guard Station
7. Pantry
8. CCTV Room
Page 71
70
9. Triage Area
10. Toilet
11. Sidewalk
12. Drop-off Road
13. Waiting Shed
14. Drop Curb
15. PWD Ramp
16. Wash Area
17. Landscape
C. Ancillary works associated with the facility includes but not limited to potable water,
utility water, sanitary and surface drains and electric lighting and power.
4 DURATION
The Contract duration is for a period up to one hundred eighty (180) calendar days. This
includes estimated number of rainy days for the entire project duration.
5 SCOPE OF WORK
The Scope of Work shall include the following but not limited to:
Item
No. Description
% of
Total Unit Quantity
1 MOBILIZATION/DEMOBILIZATION 1.20 LOT 1.00
2 CONSTRUCTION SAFETY & HEALTH PROGRAM 2.2 LOT 1.00
3
OTHER GENERAL REQUIREMENTS
(Project Photographs, Project Billboards and Permits,
Clearances and Other Government Taxes)
0.46 LOT 1.00
4 TEMPORARY FACILITIES/FIELD OFFICE 0.42 LOT 1.00
5 SITEWORKS 5.67 LOT 1.00
6 FORMS AND SCAFFOLDINGS 2.76 LOT 1.00
7 REINFORCED CONCRETE WORKS 25.41 cu.m. 275.00
8 MASONRY WORKS 2.64 sq. m. 395.00
9 PLASTERING WORKS 0.6 sq. m. 562.24
10 WATERPROOFING WORKS 0.31 sq.m. 63.00
Page 72
71
11 METAL ROOFING WORKS 5.72 LOT 1.00
12 DUCTBANK AND PULLBOX 3.37 LOT 1.00
13 ALUMINUM COMPOSITE PANEL (PVDF) 3.82 sq. m 205.00
14 ARCHITECTURAL STEEL WORKS 5.13 LOT 1.00
15 ARCHITECTURAL DOORS, WINDOWS AND
CURTAIN WALLS 8.17 LOT 1.00
16 TILEWORKS 4.28 sq. m 602.15
17 CARPENTRY WORKS 3.79 sq. m 319.32
18 PAINTING WORKS 1.12 sq. m 583.18
19 STAINLESS LOGO, LETTERS AND SIGNAGES 1.44 LOT 1.00
20 LANDSCAPE WORKS 5.35 sq.m. 646.13
21 MECHANICAL WORKS 0.62 LOT 1.00
22 ELECTRICAL WORKS 5.31 LOT 1.00
23 ELECTRONICS AND COMMUNICATION WORKS 1.70 LOT 1.00
24 REHABILITATION OF OVERHEAD FEEDER LINE 6.34 LOT 1.00
25 PLUMBING WORKS 0.68 LOT 1.00
26 PLUMBING FIXTURES AND ACCESSORIES 0.53 LOT 1.00
27 CATCH BASINS 0.07 LOT 1.00
28 HAULING OF WASTES AND DEMOLISHED
MATERIALS 0.89 LOT 1.00
C O N S T R U C T I O N 100.0
6 GUIDELINES IN COSTING
6.1 The Direct Cost shall consists of the following:
A. Cost of materials
B. Cost of labor
C. Equipment Expenses
Page 73
72
D. Cost for Permits, Clearances and other Government Taxes
6.2 The Indirect Cost shall consists of the following:
A. Overhead Expenses includes Engineering and Administrative Supervision,
Transportation allowances, Office Expenses, Premium on Contractor’s All
Risk Insurance (CARI) and Financing Cost.
B. Contingencies include expenses for meetings, coordination with
stakeholders, billboards (excluding Project Billboard which is a pay item
under the General Requirements), stages during ground breaking &
inauguration ceremonies, and other unforeseen events.
C. Miscellaneous Expenses include laboratory tests for quality control and plan
preparation.
D. Contractor’s Project Margin
E. VAT Component
7 CONSTRUCTION
The Contractor shall carry out all the Construction works including the following but not
limited to:
1. MOBILIZATION/DEMOBILIZATION
A. Mobilization shall include all activities and associated costs for
transportation of Contractor's personnel, equipment, and operating supplies
to the site; and other necessary general facilities for the Contractor's
operations at the site; premiums paid for performance and payment bonds,
including co-insurance and re-insurance agreements as applicable;
B. Demobilization shall include all activities and costs for transportation of
personnel, equipment, and supplies not required or included in the contract
from the site; including the disassembly, removal and site cleanup of
temporary offices and other facilities assembled on the site specifically for
this contract.
2. CONSTRUCTION SAFETY & HEALTH PROGRAM
A. The Contractor shall be responsible for site preparation and installation of
necessary gates, safety nets and access control system to the satisfaction of
BatStateU;
B. Construction safety and Health program includes provision of Personal
Protective Equipment (PPE) (safety harness, hard hat, safety glasses, gloves,
working uniform and safety shoes) for all workers on the hard hat area.
C. Provision of first aid kit on site at all times.
Page 74
73
D. Provision of safety signage, appropriate barricades and warning signs, and
traffic management system.
E. All construction personnel shall be required to undergo COVID-19 test, as
may be prescribed, and retested as the need arises.
F. Provision of alcohols, soaps, disinfectants and decontamination areas on site.
G. The contractor shall be required to submit their Construction Safety
Guidelines for the Implementation of the Project during the COVID-19
Public Health Crisis.
3. OTHER GENERAL REQUIREMENTS (Project Photographs, Project
Billboards and Permits, Clearances and Other Government Taxes)
A. PROJECT PHOTOGRAPHS
Monthly accomplishment report including updated project schedule
shall be submitted to BatStateU complete with pictures of on-going
project.
B. PROJECT BILLBOARDS
The two (2) Project billboards shall be strategically placed within
the site vicinity.
C. PERMITS, CLEARANCES AND OTHER GOVERNMENT TAXES
The Contractor must secure Fire Safety Evaluation Clearance for
Building Permit and Fire Safety Inspection Certificate for
Occupancy Permit.
4. TEMPORARY FACILITIES/FIELD OFFICE
A. The construction of temporary facilities including electric and water
consumption, barracks, site office, temporary fence, hand wash area,
disinfection station, sanitation tent.
5. SITEWORKS
A. The Contractor shall be responsible for site preparation and installation of
temporary fencing to secure work area;
B. The Contractor shall make adequate site survey, verification and setting outs;
C. Site clearing which includes removal / relocation of trees and other
unnecessary obstructions;
Page 75
74
D. Demolition, dismantling works and removal of all site existing structures
such as slabs, columns, roofing and other obstructions within the area where
the building/s will be erected;
Existing Fence
Existing One Storey CONAHS Building
Cooperative Building
One Storey Classroom (Baking Room)
Stock Area
Existing Material Recovery Facility (MRF)
Other existing buildings/structures that may obstruct the proposed
building; such structures shall be identified by BatStateU.
E. All earth works including but not limited to excavation, grading, hauling,
backfilling and compaction to the required grades and levels as shown on the
drawings;
F. All excavated materials on-site shall be disposed and shall be
transferred/hauled by the Contractor on a different site or outside the
construction site.
G. Ground protection such as installation of sheet piles, trenching, shoring and
other excavation protection shall be done to prevent disturbing the soil and
grades of neighboring structures including cave-ins and other excavation
related hazards;
H. Dewatering works during excavation prior construction of building
foundation and other related structures to be constructed below natural grade
line due to high water tables of the location;
I. Provision of lean concrete for footing/foundations and gravel bedding for tie
beams, grade beams and slab on grade;
J. Provision of polyethylene sheet (vapor barrier) 6 mils for slab on grade;
K. Provision of soil poisoning and termite control at the excavated surfaces of
footings, tie beams and slab on grade;
L. Provision and installation of soil poisoning perforated pipe line system;
M. The contractor must conduct Field Density Test (FDT), one group of 3 in-
situ density tests per layer. Each layer must be 0.20m compacted fill of 95%
soil compaction.
6. FORMS AND SCAFFOLDINGS
A. Erection of forms and scaffoldings.
Page 76
75
7. REINFORCED CONCRETE WORKS
A. All concrete works shall be done in accordance with the standard
specifications for plain and reinforced concrete as adopted by the
Government.
B. Reinforced concrete works include the installation of reinforcing steel bars
and the pouring of ready-mix concrete mixture for foundations, columns,
beams, slabs, stairs, drop off area, sidewalks, concrete gutter, plant boxes and
other reinforced concrete structures of the building to be approved by
BatStateU.
C. Concrete mix and steel reinforcement shall be approved by the Civil
Engineer of BatStateU.
D. Contractor shall provide required pipe sleeves for all utilities (Electrical,
Plumbing, Mechanical, etc.).
8. MASONRY WORKS
A. Masonry works include the laying of Concrete Hollow Blocks type with even
texture and well-defined edges, with a minimum compressive strength of
350psi.
B. All Concrete Hollow Blocks wall reinforcing at reinforced concrete column,
wall, bottom of slab and bottom of beam shall be installed with backer rod
and elastic/polyurethane sealant.
9. PLASTERING WORKS
A. Masonry wall finishes shall be smooth plaster finish or as specified by the
Architect or Engineer-in-charge.
10. WATERPROOFING WORKS
A. Cementitious waterproofing system of roof slab and concrete valley gutter
and membrane waterproofing for concrete valley gutter as specified on the
drawing plans and according to specifications.
11. METAL ROOFING WORKS
A. Metal Roofing works include provision and installation of all roofing
materials required by the project and as shown on plans to be approved by
BatStateU;
B. All steel members shall be protected against corrosion using epoxy primer &
epoxy reducer.
Page 77
76
12. DUCTBANK AND PULLBOX
A. All concrete works shall be done in accordance with the standard
specifications for plain and reinforced concrete as adopted by the
Government.
B. Concrete works include the in-situ pouring of concrete mixture (2,000 psi, 28
days) for duct bank underground cable, pull boxes and other reinforced
concrete structures to be approved by BatStateU;
C. For reinforcing steel bar: use Grade 40 for 10mmØ.
D. Concrete mix and steel reinforcement shall be approved by the Civil
Engineer of BatStateU;
13. ALUMINUM COMPOSITE PANEL WORKS
A. Supply and installation of Aluminum Composite Panel as specified on plans
and specifications.
14. ARCHITECTURAL STEEL WORKS
A. The work includes the supply, fabrication and installation of all the stair
railings barriers gates (turnstile areas), PWD Ramp Outside, PWD Ramp
Inside, Main Entrance Stairs Outside, Main Entrance Barrier, Main Entrance
Stairs Inside, Main Stairs with Glass Outside, Main Stairs with Glass Inside,
PWD Gate, fence grills, vertical trellis at waiting shed, vertical planters and
others as specified on plans.
15. ARCHITECTURAL DOORS, WINDOWS AND CURTAIN WALLS
A. Supply and installation of glass and wooden panel doors, windows and
tempered curtain walls as specified on plans and specifications.
16. TILEWORKS
A. Tiling of all floors, wall and counters as specified in the drawing plans and
specification.
17. CARPENTRY WORKS
A. The work includes the furnishing of materials, tools and equipment, methods
and labor necessary to complete all carpentry work requirements.
B. Carpentry works includes construction of all ceiling works and information
counter as specified in the drawing plans and specification.
18. PAINTING WORKS
A. Painting works includes interior and exterior walls, perimeter fence , waiting
shed, floors, columns, ceilings, wood door and door jambs, all carpentry
Page 78
77
works and steel works (primer and top coat) as specified in the drawing,
plans and specification.
B. Painting of entire building.
19. STAINLESS LOGO, LETTERS AND SIGNAGES
A. The work includes the supply, fabrication and installation of the Stainless
steel logo, letters and signage as specified in the drawing plans and
specification.
20. LANDSCAPE WORKS
A. This item includes all landscaping works that is specified in the Vertical
planters, plant boxes, Floor Plan, Site-Development plan.
B. For garden soil, use loam soil to ensure that plants have a steady supply of
moisture without drowning.
C. Supply and planting of garden soil and plants to be approved by Owner’s
Representative/PMO.
D. Provide necessary equipment and materials for Landscaping.
21. MECHANICAL WORKS
A. All materials to be used for mechanical works shall be new and shall
conform to the Reference Code and Standards. Use of materials shall further
be governed by other requirements, imposed on the specifications. Materials
shall be subject to necessary tests for their fitness if so required.
B. Supply and installation of all fire extinguisher, air conditioning and
ventilation units and accessories or materials needed for the completion of
the system are covered by the mechanical works.
C. Fire Extinguisher, air conditioning and ventilation units to be installed shall
be approved by the Owner/Representative prior to installation. Approval of
units may be done through submission of original catalogues of the fire
extinguisher, air conditioning and ventilation units (catalogues from the
manufacturer/s). The physical presentation of units for approval shall be
complied whenever requested by the consultant. All these shall be done prior
to installation.
D. Mechanical works are included but not limited to supply and installation of
high-wall inverter split type air conditioning unit, exhaust fans and fire
extinguisher for the areas defined within the plans.
E. Testing and commissioning of the mechanical works shall be performed with
the presence of the owner or representative, prior to turn-over. Report of
testing and commissioning, together with the operational manuals and
Page 79
78
accessories (such as remote controller/s) of the installed and tested units shall
be submitted to the owner or representative.
F. Repair and/or maintenance works are included in the scope for mechanical
works if ever and/or whenever failure/s of the system within the period of
one (1) year from turn-over and acceptance would be encountered.
22. -23. ELECTRICAL AND ELECTRONICS AND COMMUNICATION WORKS
A. All Electrical works shall provide all materials and equipment and perform
all the work necessary for the complete execution of the electrical systems
shown on the electrical drawings with reference to the general construction
drawings as herein specified, or both except as otherwise excluding the
generality of the foregoing, shall include but not limited to the following
principal items of work.
B. Supply and Installation of Panel Boards as detailed in drawing; shop
drawings shall be submitted for review of BSU-TWG prior to fabrication.
C. Supply and Installation of underground uPVC with main feeder cables for LP
Panel board from existing building as detailed in drawing.
D. The Conduit system shall include the roughing-in, fittings, conduit supports,
pull boxes, pull guide wires, utility boxes and junction boxes.
E. Supply and installation of complete lighting systems (lighting fixtures with
complete supports, switches, emergency lights and fire exit signs) as shown
on the electrical plans.
F. Supply and installation of wiring devices and accessories.
G. Supply and installation of complete power systems (receptacles, disconnect
switches, panels and circuit breaker) as shown on the electrical plans and
specifications.
H. Supply and installation of complete power and control wiring to various
mechanical (ACUs & motors) and sanitary equipment (hand drier and
exhaust fan) unless otherwise specified; Schematic diagrams shall be
submitted for sanitary pump motor control and mechanical fire pump motor
controls during materials approval. Failure to do so shall be rejection of
approvals.
.
I. Installation of Data and Communication Systems as indicated on plans and
specifications
J. Supply and installation CCTV Systems and accessories as indicated on plans
and specifications
K. Supply and installation of complete grounding system as shown in the
electrical plans and specifications
Page 80
79
L. Termination of all electrical system.
M. Furnished the Architect/ Engineer shop drawings which shall include details
of proposed installation such as conduit runs, wiring, location of equipment
and other pertinent information to illustrate the deviation and changes from
original plans. All electrical and electronic equipment’s shall be named and
tagged for proper identification and function in the system. Name plates /
tags shall be in traffolyte or stainless steel engravement. Contractor to submit
sample engravement to the engineer / architect in charge for approval.
N. Conduct and record insulation resistance testing for each cable by use of high
impedance insulation tester for the main supply feeder cables and branch
feeders to panel boards (please refer to general specifications for complete
details). Testing to be witnessed TWG for electrical or his representative.
Test result record in tabulated form includes date and time of testing, type of
megger tester used, who tested and witnessed.
O. Complete testing and commissioning of all electrical lighting, power and
auxiliary equipment systems. See Specifications for detailed Field Testing
and Commissioning of Electrical Systems.).
P. If anything has been omitted for any items of work or materials usually
furnished, which are necessary for the completion of the entire work as
outlined herein before, then such items must be and hereby included in this
Section of work.
Q. Hauling of waste and demolished materials includes cleaning of all the
excess and unnecessary materials; and
R. Site house cleaning and demobilization of workforce and equipment.
S. The contractor is advised to visit the site and satisfy himself as to the local
conditions and facilities that may affect his work. He will deemed to have
done this before preparing his proposal and any subsequent claim on the
ground of inadequate or insufficient information shall not be entertained.
T. Furnish the as-built plans One (1)–set of reproducible and Four (5) sets of
marked up as-built signed and sealed plans upon the completion of the
project. These plans shall be submitted by the contractor to the Engineer
prior to the release of final payment. The as-built plans shall show details of
actual site installation and include all deviations from the original plans.
24. REHABILITATION OF OVERHEAD FEEDER LINE
A. Supply and installation of 150mm2 THHN-THWN cable, as indicated in the
plans & specifications. Pulling of 3-sets 3x150mm2 of wire from new steel
pole-1 to pole-2 via ductbank and cable ladder. Connect/ splice new and old
wires end to end using suitable size split bolt inside the splicing box .
Page 81
80
Perform megger test, submit test reports and ensure that test is acceptable or
passed per standard before energization.
B. Supply and Installation of steel pole and hardware assembly complete with
double Cross-Arm and Braces, Truss Guy, Secondary Racks, Supports,
grounding, Accessories, Splicing Box Outdoor Type Nema 4R Stainless
Steel (1000x300x200mm) and split bolt connectors.
C. Supply and installation of cable ladder in the steel pole as detailed in
drawings and specifications.
D. Removal of existing wooden pole, cut/ remove existing overhead feeder line
in obstruction above the Gate-4 Façade.
E. Supply and installation of steel pole grounding system.
F. Demolition of existing concrete pedestal and wooden pole for STEAM
Library service entrance. Re-route/ transfer existing 2-sets feeder wire of
STEAM Library Building from Old wooden pole to new steel pole. Pull
excess wire up to power house.
G. The contractor must visit and conduct survey the site perform visual and site
actual measurements and satisfy himself as to the local conditions and
facilities that may affect his work. He will deem to have done this before
preparing & submission of his proposal.
H. Excluded in the scope;
Removal of data/ fiber optic cables
Pulling of data and fiber optic cables
25. PLUMBING WORKS
A. All plumbing works included herein shall be executed according to the
provisions of the National Plumbing Code, National Building Code and the
Rules and Regulations of Batangas City;
B. The drawings are not intended to show every pipes, fittings, valves and
appliances. All such item whether specifically mentioned or not, or indicated
on the drawings shall be finished and installed if necessary to complete the
system in accordance with the best practice of the Plumbing Trade and to the
satisfaction of the Owner/Representative;
C. All materials to be used shall be new and shall conform to the Reference
Code and Standards. Use of materials shall further be governed by other
requirements, imposed on other section of these specifications. Materials
shall be subject to test necessary for their fitness if so required;
Page 82
81
D. The Contractor shall furnish all materials, labor and equipment necessary for
the installation of all water lines, fixtures and accessories;
E. All works must communicate to the Owner/Representative before
commencement;
F. SYSTEM DESCRIPTION: Provide new plumbing systems, complete and
ready for operation. Plumbing systems including manufacturer’s products
shall be in accordance with the required and advisory of the IAPMO Uniform
Plumbing Code and Philippine National Plumbing Code. Plumbing systems
include piping less than 1.50meters outside of the building;
G. Horizontal sanitary sewer piping shall be run in practical alignment at a
minimum slope of 1% for pipes 4" & larger & 2% for 3"∅& smaller.
H. Horizontal drainage/waste piping shall be run in practical alignment at a
minimum slope of 1% for pipes 4" & larger & 2% for 3"∅& smaller.
I. All fixtures shall be provided with p-trap seal of not to less than 50mm but
not more than 100mm in depth.
J. The contractor shall verify all existing utilities at site, that is, the actual pipe
sizes, locations, and depths, top and invert elevations of all existing pipes and
related structures. The contractors shall provide the necessary excavations,
backfilling and surface restoration of the affected areas in the laying of
sewer, storm drainage and water supply lines.
26. PLUMBING FIXTURES AND ACCESSORIES
A. Contractor shall furnish all materials, labor and equipment necessary for the
installation of all water lines, fixtures and accessories.
B. Supply and installation of all plumbing fixtures and accessories such as water
closet, lavatories, floor drains, bidet, kitchen sink, faucets, soap
dispenser/holder, tissue holder and grease trap;
C. All materials and equipment to be installed shall be of approved quality and
should be presented to the Owner for approval prior to installation;
27. CATCH BASINS
A. Catch basins shall be constructed as shown in the plan.
28. HAULING OF WASTES AND DEMOLISHED MATERIALS
A. Hauling of waste and demolished materials and includes cleaning of all the
excess and unnecessary materials;
Page 83
82
8 CONTRACTOR’S SCHEDULE & PROGRESS REPORTING
a) Progress Reporting. Throughout the Contract duration, the Contractor shall be
responsible for taking detailed and accurate measurements of the actual progress of all
aspects of the works.
b) Monthly Progress Report. The Contractor shall maintain a Master Project Schedule
to summarize the status of the work; work in progress and the percentage completed.
This summary report shall be updated and submitted every last Wednesday of the
month.
c) Contractor shall submit during the entire duration of the contract within five (5) days
from the end of the preceding month, a monthly progress report under cover of a
transmittal sheet and shall include as a minimum the following:
Management/Executive Report (Narrative)
Construction Progress
Forecast for the next one month
Manpower (Management and Workforce)
Areas of Concern
Photographic Report (Two colored copies)
d) Meetings. Contractor Key Personnel shall meet with BatStateU representative every
last Wednesday of the month to discuss matters related to the project. Contractor
shall arrange to record the minutes of meeting and submit for BatStateU approval.
e) Kick Off Meeting. Immediately after the Notice to Proceed, a Kick off meeting shall
be held between BatStateU and Contractor. The initial Kick off meeting and recorded
Minutes shall form the basis of the Project action plan and set such requirements as
Safety and Constructability Reviews. It shall also be used to introduce BatStateU and
Contractor representatives associated with aspects of the work. The objectives of the
kick-off meeting are as follows:
Introduction all of BatStateU’s and Contractor’s Project Management Team,
Engineering and Construction team personnel;
Convey and promote shared commitment of project expectations;
Review and establish understanding of Project Work Scope;
Review overall project schedule;
Establish project meetings requirements and frequency of meetings; and
Establish reporting requirements and frequency of reports.
Page 84
83
f) Minimum Mobilization of Key Personnel
Project Manager: full time from Contract award up to completion of Works,
to be mobilized on site during the construction phase; at least 5 years
experience as Project Manager.
Site/Construction Engineer: full time from initiation of site mobilization
activities up to provisional acceptance of the works; at least 5 years exp. as
general construction experience
Material/QC Engineer – at least 5 years exp. as general construction
experience
MEPF Engineer – at least 3 years exp. as MEPF Engineer
Safety Officer: full time from initiation of site mobilization activities up to
provisional acceptance of the works, at least 3 years exp. as Safety officer
Foreman – At least 2 years experience as foreman
g) Testing Work. The testing work will include all tests and checks on:
All concrete mixtures poured and required tests on structural steel members
and reinforcing bars;
Flushing and cleaning of piping works;
Testing the effectiveness and workability of electrical lines and water &
sewer lines;
House cleaning of the work area in preparation of hand over to BatStateU;
h) Commissioning punch list. This shall be established for the purpose of recording all
discrepancies, damaged or missing materials, malfunctions, missing documents and
any deviation from the design drawings and specifications or normal operating
conditions. All punch list items must be cleared from the system list prior to project
turn over. The contractor shall provide as-build plans, Contractor’s logbook,
Operating and Maintenance Manual (O&M) and Test reports prior to turnover.
i) Project Billing and Project Turn-over. The Contractor shall submit the following:
A. For 15% Mobilization: (Note: Three (3) ORIGINAL Copies each)
Contractor Request Letter for 15% Mobilization
Advance Payment Bond From Insurance Company – 15% Total
Contract Price (TCP)
Narrative and Photographic Report (Current and Previous Photos)
Updated Construction Schedule
List of Updated Key Personnel
List of Tools and Equipment on Site with pictures
Page 85
84
Contractor’s All-Risk Insurance (CARI)
Photographic Report of Installed Water and Electric Sub-meter
Fire Safety Evaluation Clearance to be applied at Fire Department
(if applicable, requirement for approval of building permit)
Construction Safety and Health Program approved by the
DOLE(requirement for application of building permit)
Personal Protective Equipment on site
Project Billboards/Tarpaulin Posted on Site
Temporary Facility
Submitted Construction Forms( for evaluation of PMO)
B. For Progress Billing: (Note: Three (3) ORIGINAL Copies each)
Contractor’s Request Letter for Billing
Narrative and Photographic Report with Updated Construction
Schedule
BOQ with Detailed Backup Computation of Percentage
Accomplishment
Contractor’s Affidavit – duly notarized
Material Testing Result – Certified True Copy if Applicable
___ CHB
___ Compressive/Flexural Strength on Concrete
___ Reinforced Steel Bars
Material Approval Report (Structural, Architectural, Electrical,
Mechanical, Sanitary, ...)
C. For Final Billing and Project Turn – over:
Contractor’s Request Letter for Billing
Narrative and Photographic Report with Updated Construction
Schedule
BOQ with Detailed Backup Computation of Percentage
Accomplishment
Contractor’s Affidavit – duly notarized (for Finance Office)
Certificate of Turn-over
Material Testing Result – Certified True Copy if Applicable
___ CHB
___ Compressive/Flexural Strength on Concrete
___Reinforced Steel Bars
Material Approval Report (Structural, Architectural, Electrical,
Mechanical, Sanitary, ...)
Page 86
85
Contractor’s Testing and Commissioning Result
A. Electrical
I. Functional Testing Result(signed and sealed by
Prof, Electrical Engr. In-Charge of Construction)
___ Lightings
___ Convenience Outlets
___ ACU Outlets
___ Outdoor Circuit Breaker
___Emergency Lights
Others:
___________________________________________________
___
II. Megger Test/Insulation Resistance Test Result
___Main Feeder
___Sub Feeder
___Branch Circuits
___All Panelboards
Others:
___________________________________________________
___
B. Electronics and Communication
___ Closed Circuit Television System (CCTV)
___ Telephone and Data System
Others:
___________________________________________________
___
C. Mechanical
___ Air-Conditioning Units
___ Ventilation Units
___ Fire Protection System
Others:
___________________________________________________
___
Installation Checklist and Start-up and Commissioning
Report:
Page 87
86
___ Air-Conditioning Units
___ Ventilation Units
___ Fire Protection System
D. Sanitary
___ Leak Test
___ Hydro Test
___ Booster Pumps
Others:
___________________________________________________
___
Equipment and Materials Test Results
A. Electrical
___ Panel Boards
B. Sanitary
___ Fixtures
Technical Hands-on Training of BSU representative/s for operation,
maintenance & troubleshooting of major systems:
___ Closed Circuit Television System (CCTV)
___ Telephone and Data System
Others:
__________________________________________________________
***Original Operation and Maintenance (O&M) manuals for major
systems:
___ Closed Circuit Television System (CCTV)
___ Telephone and Data System
___ Air Conditioning and Ventilation System
___ Fire Protection System
Others:
__________________________________________________________
Accomplished Payment for Electric and Water Consumption
Expenses (if applicable with the project) with attached actual photo
of sub-meter reading.
Keys with Clear Specific Tags and ***Masters List
Page 88
87
Documents for Application of Occupancy Permit
___ Certificate of Completion (signed and sealed) (4copies)
___ Certificate of Final Electrical Inspection (CFEI)(signed and
sealed) (4copies)
___ Structural (signed and sealed) (4copies)
___ Architectural (signed and sealed) (4copies)
___ Electronics and Communication (signed and sealed) (4copies)
___ Mechanical (signed and sealed) (4copies)
___ Sanitary/Plumbing (signed and sealed) (4copies)
___ Unified Application Form for Certificate of Occupancy(signed,
sealed and duly notarized) (4copies)
___ Notarized Affidavit of Change of Signatories (In-charge of
Construction) (4copies)
___ Testing and Commissioning Results Witnessed by the Fire
Department
o Fire Detection and Alarm System (FDAS)
o Fire Protection System
___ ***As-built Plans
o Tracing Copy (Original Copy)
o Blueprints (5-copies, signed and sealed)
___ Soft Copy CAD and PDF Files (Flash Drive)
___ Construction Logbook (2-copies, Signed and Sealed)
Note: One (1) Copy Only for items marked ***. Rest, three (3) ORIGINAL copies.
9 CONTRACTOR’S UTILITIES CONSUMPTION
The Contractor shall pay their electric and water consumption bills. Sub meters shall
be installed at the expense of the Contractor to determine their actual consumption.
10 CONFLICT IN REFERENCE DOCUMENTS
In the case of any conflict between the technical requirement and specifications of this
contract and the reference documents, or among the reference documents, the order of
precedence is:
1) Scope of Work/Matrix for Scope of Works
2) Basic Engineering Drawings
3) Technical Specifications
The Contractor shall notify any discrepancy found in the documentation to BatStateU
in writing for clarification. BatStateU will respond to such request in writing.
Page 89
88
M A T R I X F O R S C O P E O F W O R K S
ITEM
NO. DESCRIPTION QTY UNIT SCOPE OF WORKS
1 MOBILIZATION/
DEMOBILIZATION 1.00 lot
MOBILIZATION
Mobilization shall include all activities and associated costs
for transportation of Contractor's personnel, equipment, and
operating supplies to the site; and other necessary general facilities
for the Contractor's operations at the site; premiums paid for
performance and payment bonds, including co-insurance and re-
insurance agreements as applicable;
DEMOBILIZATION
Demobilization shall include all activities and costs for
transportation of personnel, equipment, and supplies not required or
included in the contract from the site; including the disassembly,
removal and site cleanup of temporary offices and other facilities
assembled on the site specifically for this contract.
2
CONSTRUCTION
SAFETY AND
HEALTH
PROGRAM
1.00 lot
The Contractor shall be responsible for site preparation and
installation of necessary gates, safety nets and access control system
to the satisfaction of BatStateU;
Construction safety and Health program includes provision of
Personal Protective Equipment (PPE) (safety harness, hard hat, safety
glasses, gloves, working uniform and safety shoes) for all workers on
the hard hat area.
Provision of first aid kit on site at all times.
Provision of safety signage, appropriate barricades and warning signs,
and traffic management system.
All construction personnel shall be required to undergo COVID-19
test, as may be prescribed, and retested as the need arises.
Provision of alcohols, soaps, disinfectants and decontamination areas
on site.
The contractor shall be required to submit their Construction Safety
Guidelines for the Implementation of the Project during the COVID-
19 Public Health Crisis.
3
OTHER GENERAL
REQUIREMENTS
(Project
Photographs, Project
Billboards and
Permits, Clearances
and Other
Government Taxes)
1.00 lot
Monthly accomplishment report complete with photos
Installation of two Project billboards
The Contractor must secure Fire Safety Evaluation Clearance for
Building Permit and Fire Safety Inspection Certificate for
Occupancy Permit.
Page 90
89
4
TEMPORARY
FACILITIES/
FIELD OFFICE
1.00 lot
The construction of temporary facilities including electric and water
consumption, barracks, site office, temporary fence, hand wash area,
disinfection station, sanitation tent.
5 SITEWORKS 1.00 lot
The Contractor shall be responsible for site preparation and
installation of temporary fencing to secure work area;
The Contractor shall make adequate site survey, verification and
setting outs;
Site clearing which includes removal / relocation of trees and other
unnecessary obstructions;
Demolition, dismantling works and removal of all site existing
structures such as slabs, columns, roofing and other obstructions
within the area where the building/s will be erected;
§ Existing Fence
§ Existing One Storey CONAHS Building
§ Cooperative Building
§ One Storey Classroom (Baking Room)
§ Stock Area
§ Existing Material Recovery Facility (MRF)
§ Other existing buildings/structures that may obstruct the
proposed building; such structures shall be identified by BatStateU.
All earth works including but not limited to excavation, grading,
hauling, backfilling and compaction to the required grades and levels
as shown on the drawings;
All excavated materials on-site shall be disposed and shall be
transferred/hauled by the Contractor on a different site or outside the
construction site.
Ground protection such as installation of sheet piles, trenching,
shoring and other excavation protection shall be done to prevent
disturbing the soil and grades of neighboring structures including
cave-ins and other excavation related hazards;
Dewatering works during excavation prior construction of building
foundation and other related structures to be constructed below
natural grade line due to high water tables of the location;
Page 91
90
Provision of lean concrete for footing/foundations and gravel
bedding for tie beams, grade beams and slab on grade;
Provision of polyethylene sheet (vapor barrier) 6 mils for slab on
grade;
Provision of soil poisoning and termite control at the excavated
surfaces of footings, tie beams and slab on grade;
Provision and installation of soil poisoning perforated pipe line
system;
The contractor must conduct Field Density Test (FDT), one group of
3 in-situ density tests per layer. Each layer must be 0.20m
compacted fill of 95% soil compaction.
M A T E R I A L S
Site Clearing
Demolition of Cooperative Store
Demolition of College of Nursing Building
Demolition of Structures at the Back of Gso Building
Demolition of Existing Fence
Removal of Trees (300 mm dia - 500 mm dia)
Removal of Trees (500mm dia to 750mm dia above)
Dewatering
Excavation (including disposal of excavated materials)
Earthfill , Backfill and Compaction
FDT
Gravel Bedding
Lean Concrete
Polyethylene Sheet (Vapor Barrier) 6mils thick for slab
Soil Poisoning and Termite Control
Soil Poisoning Perforated Pipe Line system including installation
Page 92
91
6 FORMS AND
SCAFFOLDINGS 1.00 LOT
Erection of forms and scaffoldings.
M A T E R I A L S
Phenolic Plywood Forms
Coco Lumber
Common Wire Nail Asstd
Scaffolding Rental
Misc. Consumables
7
REINFORCED
CONCRETE
WORKS
275.00 cu.
M.
All concrete works shall be done in accordance with the standard
specifications for plain and reinforced concrete as adopted by the
Government.
Reinforced concrete works include the installation of reinforcing steel
bars and the pouring of ready-mix concrete mixture for foundations,
columns, beams, slabs, stairs, drop off area, sidewalks, concrete
gutter, plant boxes and other reinforced concrete structures of the
building to be approved by BatStateU.
Concrete mix and steel reinforcement shall be approved by the Civil
Engineer of BatStateU.
Contractor shall provide required pipe sleeves for all utilities
(Electrical, Plumbing, Mechanical, etc.).
M A T E R I A L S
FOUNDATION
Reinforcing Steel Bars Grade 40/60
Ready-Mix Concrete (3,000 psi, 28 days)
GI Tie Wire Ga. 16
COLUMN
Reinforcing Steel Bars Grade 40/60
Ready-Mix Concrete (3,000 psi, 28 days)
GI Tie Wire Ga. 16
SLAB
Page 93
92
Reinforcing Steel Bars Grade 40/60
Ready-Mix Concrete (3,000 psi, 28 days)
GI Tie Wire Ga. 16
BEAMS
Reinforcing Steel Bars Grade 40/60
Ready-Mix Concrete (3,000 psi, 28 days)
GI Tie Wire Ga. 16
STAIRS & RAMP
Reinforcing Steel Bars Grade 40
Ready-Mix Concrete (3,000 psi, 28 days)
GI Tie Wire Ga. 16
SIDEWALK
Reinforcing Steel Bars Grade 40
Ready-Mix Concrete (3,000 psi, 28 days)
GI Tie Wire Ga. 16
DROP OFF ROAD
Reinforcing Steel Bars Grade 40
Ready-Mix Concrete (3,000 psi, 28 days)
GI Tie Wire Ga. 16
CONCRETE VALLEY GUTTER
Reinforcing Steel Bars Grade 40/60
Ready-Mix Concrete (3,000 psi, 28 days)
GI Tie Wire Ga. 16
8 MASONRY
WORKS 395.00
sq.
m.
Masonry works include the laying of Concrete Hollow Blocks type
with even texture and well-defined edges, with a minimum
compressive strength of 350psi.
Page 94
93
All Concrete Hollow Blocks wall reinforcing at reinforced concrete
column, wall, bottom of slab and bottom of beam shall be installed
with backer rod and elastic/polyurethane sealant.
M A T E R I A L S
5" Concrete Hollow Blocks
Cement
Sand
Reinforcing Steel Bars Grade 40/60
GI Tie Wire ga.16
15mmØ Polyurethane Backer Rod (VERTICAL)
30mmØ Polyurethane Backer Rod (HORIZONTAL)
Polyurethane sealant
9 PLASTERING
WORKS 562.24
sq.
m.
Masonry wall finishes shall be smooth plaster finish or as specified
by the Architect or Engineer-in-charge.
M A T E R I A L S
Cement
Sand
10 WATERPROOFING
WORKS 63.00
sq.
m.
Cementitious waterproofing system of roof slab and concrete valley
gutter and membrane waterproofing for concrete valley gutter as
specified on the drawing plans and according to specifications.
M A T E R I A L S
Cement
Cementitious Waterproofings (4 liters)
Membrane Water Proofing ( 1m X 10m / roll)
Miscellaneous Materials
Page 95
94
11 METAL ROOFING
WORKS 1.00 lot
Metal Roofing works include provision and installation of all roofing
materials required by the project and as shown on plans to be approved
by BatStateU;
All steel members shall be protected against corrosion using epoxy
primer & epoxy reducer.
M A T E R I A L S
Metal Roofing Works
0.50mm Prepainted Long Span Rib Type Roofing Sheet
15mm Two-Sided Aluminized Film Polyethylene Foam
Insulation (1m x 50 m per roll)
Roofing Wire Mesh
175mm x 50mm x 20mm x 1.6 mm LC Purlins
12mmØ Sagrods Threaded Both Ends with Standard Nuts
and Washers
4.5mm thk MS Plate Purlin Connector
150 mm x 50mm x 1.50mm thk Fascia Boards
100 x 100 x 6mm thk Angle Bar
10mm dia Anchor Bolt
0.5mm thk. x 36" Stainless Gutter x 2.4m (Type 304)
4' x 8' x 4.5mm thk MS Plate (Purlin Connector)
10mm dia x 200mm Long Anchor Bolt
10mm dia x 40mm Long Bolts w/ STD Nuts and Washers
Tekscrew
Blind Rivet
Epoxy Primer
Epoxy Reducer
Vulcaseal
Welding Electrode
Page 96
95
Oxy-Acethylene Set
Cutting Disc
Grinding Disc
12 DUCTBANK AND
PULLBOX 1.00 lot
All concrete works shall be done in accordance with the standard
specifications for plain and reinforced concrete as adopted by the
Government.
Concrete works include the in-situ pouring of concrete mixture (2,000
psi, 28 days) for duct bank underground cable, pull boxes and other
reinforced concrete structures to be approved by BatStateU;
For reinforcing steel bar: use Grade 40 for 10mmØ.
Concrete mix and steel reinforcement shall be approved by the Civil
Engineer of BatStateU;
M A T E R I A L S
PULLBOX (1000 x 1000 x 1000)
Excavation
Cement
Sand
Gravel
Reinforcing Steel Bars
Gravel bedding
CHB 4"
PULLBOX (600 x 600 x 1000)
Excavation
Cement
Sand
Gravel
Reinforcing Steel Bars
Gravel bedding
CHB 4"
Page 97
96
DUCTBANK
3-WAY Duct Bank (Siteworks and Construction)
6-WAY Duct Bank (Siteworks and Construction)
13
ALUMINUM
COMPOSITE
PANEL (PVDF)
205.00 sq.
m.
Supply and installation of Aluminum Composite Panel as specified on
plans and specifications.
M A T E R I A L S
Main Entrance Roof Edges
4' x 8' x 4mm thk Aluminum Composite Panel with 1" 1 x
1-1/2" x 0.8mm Sub-frame, Silicone sealant and complete
accessories
on 2" x 2" x 4" Steel Angular, 12mm dia x 100m L Dynabolt Steel
Framing
Waiting Shed Roof Edges
4' x 8' x 4mm thk Aluminum Composite Panel with 1" 1 x
1-1/2" x 0.8mm Sub-frame, Silicone sealant and complete
accessories
on 2" x 2" x 4" Steel Angular, 12mm dia x 100m L Dynabolt Steel
Framing
Main Entrance Header (On Glass Wall)
4' x 8' x 4mm thk Aluminum Composite Panel with 1" 1 x
1-1/2" x 0.8mm Sub-frame, Silicone sealant and complete
accessories
on 2" x 2" x 4" Steel Angular, 12mm dia x 100m L Dynabolt Steel
Framing
Column Branches
4' x 8' x 4mm thk Aluminum Composite Panel with 1" 1 x
1-1/2" x 0.8mm Sub-frame, Silicone sealant and complete
accessories
on 2" x 2" x 4" Steel Angular, 12mm dia x 100m L Dynabolt Steel
Framing
14 ARCHITECTURAL
STEEL WORKS 1.00 lot
The work includes the supply, fabrication and installation of all the
stair railings barriers gates (turnstile areas), PWD Ramp Outside,
PWD Ramp Inside, Main Entrance Stairs Outside, Main Entrance
Barrier, Main Entrance Stairs Inside, Main Stairs with Glass Outside,
Main Stairs with Glass Inside, PWD Gate, fence grills, vertical trellis
at waiting shed, vertical planters and others as specified on plans.
M A T E R I A L S
Railings
Page 98
97
PWD Ramp Outside
Post: 2" x 3" x 2.00mm thk Stainless Rectangluar Steel
Tube
Hand Grab: 1" x 2" x 1.20mm thk Stainless Rectangluar
Steel Tube
PWD Ramp Inside
Post: 2" x 3" x 2.00mm thk Stainless Rectangluar Steel
Tube
Hand Grab: 1" x 2" x 1.20mm thk Stainless Rectangluar
Steel Tube
Main Entrance Stairs Outside
Post: 2" x 3" x 2.00mm thk Stainless Rectangluar Steel
Tube
Hand Grab: 1" x 2" x 1.20mm thk Stainless Rectangluar
Steel Tube
Main Entrance Barrier
Post: 2" x 3" x 2.00mm thk Stainless Rectangluar Steel
Tube
Hand Grab: 1" x 2" x 1.20mm thk Stainless Rectangluar
Steel Tube
Main Entrance Stairs Inside
Post: 2" x 3" x 2.00mm thk Stainless Rectangluar Steel
Tube
Hand Grab: 1" x 2" x 1.20mm thk Stainless Rectangluar
Steel Tube
Main Stairs with Glass Outside
10mm thk Tempered Glass on 2" x 1.2mm Stainless Steel
Square/Rectangular Tube Top Rail and Post
Main Stairs with Glass Inside
10mm thk Tempered Glass on 2" x 1.2mm Stainless Steel
Square/Rectangular Tube Top Rail and Post
PWD Gate
Post: 5" dia. Stainless Steel Pipe
Frame: 2" x 2" x 1.2mm thk x 6m Stainless Steel Square
Tube
Page 99
98
Surface: 4' x 8' x 10mm thk Clear High Impact Acrylic
Sheet
Fence Grills
50mm wide x 6m length x 6mm thk Flat Bar
Trellis
Vertical Trellis at Waiting Shed
2" x 6" x 1.5mm thk x 6m length Rectangular Tubular
Steel
Vertical Planters
2" x 4" x 1.5mm thk Rectangular Tubular Steel
4' x 8 ' x 2" x 2"x6mm Steel Matting
1" x 1" x 3/16" thk x 6m Standard thk. Angle Bar
Other Materials
Welding Rod 1/8" diameter (for stainless steel)
Grinding disc
Cutting disc
Welding Rod 1/8" diameter (for ordinary steel)
Oxygen
Acetylene
15
ARCHITECTURAL
DOORS, WINDOWS
AND CURTAIN
WALLS
1.00 LOT
Supply and installation of glass and wooden panel doors, windows
and tempered curtain walls as specified on plans and specifications.
M A T E R I A L S
Doors
D1 - Door 1
D1 - 2.00m x 2.10m - Double Leaf Frameless Door
(Double Swing) using: 12mm thk. Tempered Glass on Stainless
Steel Patch Fittings with complete accessories and hardwares.
D2 - Door 2
Page 100
99
D1 - 2.00m x 2.10m - Double Leaf Frameless Door (Single
Swing) using: 12mm thk. Tempered Glass on Stainless Steel Patch
Fittings with complete accessories and hardwares.
D3 - Door 3
D3 - 0.70m X 2.10m Kiln Dried (K.D) Tanguile Panel
Door On 2" X 5" Yakal Door Jamb Complete With Heavy Duty
Accessories
D4 - Door 4
D4 - 0.60m X 2.10m Kiln Dried (K.D) Tanguile Panel
Door On 2" X 5" Yakal Door Jamb Complete With Heavy Duty
Accessories
Door Accessories
38mm dia x 1200mm Stainless Steel Glass Door Handle
Stainless Steel Door Lockset
4 x 4 Loose Pin Door Hinge
Windows
W1 - 0.60m X 0.60m Awning Window With 1/4" Thk
Tempered Grey In Powder Coated Frame Complete With Heavy
Duty Accessories
W2 - 0.70m X 0.70m Awning Window With 1/4" Thk
Tempered Grey In Concealed Powder Coated Frame Complete With
Heavy Duty Accessories
Curtain Wall
CW-1 Main Entrance
Curtain Wall 1 (CW1) - Seamless type fixed Curtain Wall
using: 10mm thk tempered glass on Powder Coated HD Plain
mullion aluminum framing
CW-2 Triage
Curtain Wall 2 (CW2) - Seamless type fixed Curtain Wall
using: 10mm thk tempered glass on Powder Coated HD Plain
mullion aluminum framing
16 TILEWORKS 602.15 sq.
m.
Tiling of all floors, wall and counters as specified in the drawing plans
and specification.
M A T E R I A L S
Floor Tiles
FF1 - Floor Finish 1
Page 101
100
FF1-60cm x 60cm Outdoor Granite Tiles
FF2 - Floor Finish 2
FF2-60cm x 60cm Polished Granite Tiles
FF3 - Floor Finish 3
FF3-30cm x 30cm Matte Tiles
Wall Tiles/Cladding/Finishes
WF1 - Wall Finish 1 (Logo Wall)
60cm x 60cm Polished Granite Tiles
WF2 - Wall Finish 2 (Column Cladding)
Stone Cladding
WF3 - Wall Finish 3 (Info Desk Decorative Wall)
Stone Cladding
WF4 - Wall Finish 4 (Toilet Wall tiles)
30cm x 30cm Polished Tiles
Pantry/Wash Area Counter Finish
COF - Counter Finish
COF-60cm x 60cm Polished Granite Tiles
Others
4' x 8' x 5mm Stainless Steel Metal Plate
Cement
Tile grout 2kg/bag
Tile adhesive 25kg/bag (Heavy Duty)
Cutting Disk
17 CARPENTRY
WORKS 319.32
sq.
m.
The work includes the furnishing of materials, tools and equipment,
methods and labor necessary to complete all carpentry work
requirements.
Carpentry works includes construction of all ceiling works and
information counter as specified in the drawing plans and
specification.
Page 102
101
M A T E R I A L S
Ceiling
Main Entrance
0.20mx2.8mx12mm thk Wood Panel Composite
Double Furring Channel 0.40mm x 19mm x 5m
Wall Angle 50mm x 25mm x 3m
C-Channel 1mm x 12mm x 38mm x 5m
50mm x 35mm Metal Clip
Waiting Shed
0.20mx2.8mx12mm thk Wood Panel Composite
Double Furring Channel 0.40mm x 19mm x 5m
Wall Angle 50mm x 25mm x 3m
C-Channel 1mm x 12mm x 38mm x 5m
Information
0.20mx2.8mx28mm thk Wood Panel Composite
Double Furring Channel 0.40mm x 19mm x 5m
Wall Angle 50mm x 25mm x 3m
C-Channel 1mm x 12mm x 38mm x 5m
Triage Area
4.5mm x 4' x 8' Fiber Cement Board
Double Furring Channel 0.40mm x 19mm x 5m
Wall Angle 50mm x 25mm x 3m
C-Channel 1mm x 12mm x 38mm x 5m
CCTV Room
4.5mm x 4' x 8' Fiber Cement Board
Page 103
102
Double Furring Channel 0.40mm x 19mm x 5m
Wall Angle 50mm x 25mm x 3m
C-Channel 1mm x 12mm x 38mm x 5m
Toilet
4.5mm x 4' x 8' Fiber Cement Board
Double Furring Channel 0.40mm x 19mm x 5m
Wall Angle 50mm x 25mm x 3m
C-Channel 1mm x 12mm x 38mm x 5m
Pantry
4.5mm x 4' x 8' Fiber Cement Board
Double Furring Channel 0.40mm x 19mm x 5m
Wall Angle 50mm x 25mm x 3m
C-Channel 1mm x 12mm x 38mm x 5m
Information Counter/Table
4'x8'x3/4" thk. HP Laminated MDF Board
18 PAINTING WORKS 583.18 sq.
m.
Painting works includes interior and exterior walls, perimeter fence,
waiting shed, floors, columns, ceilings, wood door and door jambs,
all carpentry works and steel works (primer and top coat) as
specified in the drawing, plans and specification.
Painting of entire building.
M A T E R I A L S
Concrete Surfaces
Fence Wall
Concrete Neutralizer
Acrylic Concrete Primer and Sealer
Latex Putty
Latex Top coat (Semi - Gloss)
LED Screen Base
Page 104
103
Concrete Neutralizer
Acrylic Concrete Primer and Sealer
Latex Putty
Latex Top coat (Semi - Gloss)
Exterior Concrete Walls
Concrete Neutralizer
Acrylic Concrete Primer and Sealer
Latex Putty
Latex Top coat (Semi - Gloss)
Interior Concrete Wall
Concrete Neutralizer
Acrylic Concrete Primer and Sealer
Latex Putty
Latex Top coat (Semi - Gloss)
Wood Surfaces
Triage and CCTV Room Ceiling
Interior Primer and Sealer
Latex Paint (Flat)
Glazing putty
Toilet Ceiling
Interior Primer and Sealer
Latex Paint (Flat)
Glazing putty
Pantry Ceiling
Interior Primer and Sealer
Latex Paint (Flat)
Glazing putty
Page 105
104
Doors
Interior Primer and Sealer
Quick Drying Enamel
Steel Surfaces
Fence Grills
Steel Primer
Quick Drying Enamel
Vertical Trellis
Steel Primer
Quick Drying Enamel
Vertical Planters
Steel Primer
Quick Drying Enamel
Other Materials
Sand paper
Roller brush #7
Paint brush #2
Rags/newspaper
19
STAINLESS LOGO,
LETTERS AND
SIGNAGES
1.00 LOT
The work includes the supply, fabrication and installation of the
Stainless steel logo, letters and signage as specified in the drawing
plans and specification.
M A T E R I A L S
Logo
1.10m dia Stainless Steel BSU Logo
Lettering
0.20m Height 2" Depth Stainless Steel Lettering:
"GATEWAY TO GREATNESS"
Page 106
105
0.17m Height 2" Depth Stainless Steel Lettering:
INFORMATION
0.45m Height " Depth Stainless Steel Lettering:
LEADING INNOVATIONS, TRANSFORMING LIVES
0.30m Height 2" Depth Stainless Steel Lettering:
BASICS
Plate Signages
8" X 10" (80 sq.in.) PWD Logo Stainless Steel Signage
6" X 8" (48 sq.in.) Stainless Steel Signage for:
CCTV Room,Toilet & Pantry
20 LANDSCAPE
WORKS 587.00
sq.
m.
This item includes all landscaping works that is specified in the
Vertical planters, plant boxes, Floor Plan, Site-Development plan.
For garden soil, use loam soil to ensure that plants have a steady
supply of moisture without drowning.
Supply and planting of garden soil and plants to be approved by
Owner’s Representative/PMO.
Provide necessary equipment and materials for Landscaping.
M A T E R I A L S
Landscape
Conrete Pavers
21 MECHANICAL
WORKS 1.00 LOT
All materials to be used for mechanical works shall be new and shall
conform to the Reference Code and Standards. Use of materials shall
further be governed by other requirements, imposed on the
specifications. Materials shall be subject to necessary tests for their
fitness if so required.
Supply and installation of all fire extinguisher, air conditioning and
ventilation units and accessories or materials needed for the
completion of the system are covered by the mechanical works.
Page 107
106
Fire Extinguisher, air conditioning and ventilation units to be
installed shall be approved by the Owner/Representative prior to
installation. Approval of units may be done through submission of
original catalogues of the fire extinguisher, air conditioning and
ventilation units (catalogues from the manufacturer/s). The physical
presentation of units for approval shall be complied whenever
requested by the consultant. All these shall be done prior to
installation.
Mechanical works are included but not limited to supply and
installation of high-wall inverter split type air conditioning unit,
exhaust fans and fire extinguisher for the areas defined within the
plans.
Testing and commissioning of the mechanical works shall be
performed with the presence of the owner or representative, prior to
turn-over. Report of testing and commissioning, together with the
operational manuals and accessories (such as remote controller/s) of
the installed and tested units shall be submitted to the owner or
representative.
Repair and/or maintenance works are included in the scope for
mechanical works if ever and/or whenever failure/s of the system
within the period of one (1) year from turn-over and acceptance
would be encountered.
M A T E R I A L S
Air Conditioning Units
1.5 HP High Wall Split Type (inverter)
Refrigerant Piping, Control Wires, and Condensate Drain
Soft Copper Tube Type L, 1/4", 50ft length
Soft Copper Tube Type L, 3/8", 50ft length
Rubber Insulation 1/4" x 3/4"thk, 3m length
Rubber Insulation 1/8" x 3/4"thk, 3m length
Control Wire
Refrigerant
Polyethylene Tape
Conduit Pipe 20mm dia, 3m length
PVC Blue 3/4", 3m length
Page 108
107
Ventilation Units
Exhaust Fan 245mm x 245mm Wall-mounted
Exhaust Fan 215mm x 215mm Ceiling-mounted
Ductworks and Duct Accessories
4" dia. PVC Pipe, 3m length
4" dia Round Louver Wall Air vent, air outlet, ducting,
ventilation exhaust grille cover Stainless Steel
Duct Accessories and other Fittings
Fire Extinguishers
Fire Extinguishers (Dry Chemical) 10lbs
Fire Extinguishers (Carbon Dioxide) 10lbs
Miscellaneous Works
Hangers and Supports
Consumables
Testing and Commissioning
22-23
ELECTRICAL AND
ELECTRONICS
AND
COMMUNICATION
WORKS
1.00 LOT
All Electrical works shall provide all materials and equipment and
perform all the work necessary for the complete execution of the
electrical systems shown on the electrical drawings with reference to
the general construction drawings as herein specified, or both except
as otherwise excluding the generality of the foregoing, shall include
but not limited to the following principal items of work.
Supply and Installation of Panel Boards as detailed in drawing; shop
drawings shall be submitted for review of BSU-TWG prior to
fabrication.
Supply and Installation of underground uPVC with main feeder
cables for LP Panel board from existing building as detailed in
drawing.
The Conduit system shall include the roughing-in, fittings, conduit
supports, pull boxes, pull guide wires, utility boxes and junction
boxes.
Supply and installation of complete lighting systems (lighting
fixtures with complete supports, switches, emergency lights and fire
exit signs) as shown on the electrical plans.
Page 109
108
Supply and installation of wiring devices and accessories.
Supply and installation of complete power systems (receptacles,
disconnect switches, panels and circuit breaker) as shown on the
electrical plans and specifications.
Supply and installation of complete power and control wiring to
various mechanical (ACUs & motors) and sanitary equipment (hand
drier and exhaust fan) unless otherwise specified; Schematic
diagrams shall be submitted for sanitary pump motor control and
mechanical fire pump motor controls during materials approval.
Failure to do so shall be rejection of approvals.
Installation of Data and Communication Systems as indicated on
plans and specifications
Supply and installation CCTV Systems and accessories as indicated
on plans and specifications
Supply and installation of complete grounding system as shown in
the electrical plans and specifications
Termination of all electrical system.
Furnished the Architect/ Engineer shop drawings which shall include
details of proposed installation such as conduit runs, wiring, location
of equipment and other pertinent information to illustrate the
deviation and changes from original plans. All electrical and
electronic equipment’s shall be named and tagged for proper
identification and function in the system. Name plates / tags shall be
in traffolyte or stainless steel engravement. Contractor to submit
sample engravement to the engineer / architect in charge for
approval.
Conduct and record insulation resistance testing for each cable by
use of high impedance insulation tester for the main supply feeder
cables and branch feeders to panel boards (please refer to general
specifications for complete details). Testing to be witnessed TWG
for electrical or his representative. Test result record in tabulated
form includes date and time of testing, type of megger tester used,
who tested and witnessed.
Complete testing and commissioning of all electrical lighting, power
and auxiliary equipment systems. See Specifications for detailed
Field Testing and Commissioning of Electrical Systems.).
If anything has been omitted for any items of work or materials
usually furnished, which are necessary for the completion of the
entire work as outlined herein before, then such items must be and
hereby included in this Section of work.
Hauling of waste and demolished materials includes cleaning of all
the excess and unnecessary materials; and
Site house cleaning and demobilization of workforce and equipment.
The contractor is advised to visit the site and satisfy himself as to the
local conditions and facilities that may affect his work. He will
deemed to have done this before preparing his proposal and any
subsequent claim on the ground of inadequate or insufficient
information shall not be entertained.
Page 110
109
Furnish the as-built plans One (1)–set of reproducible and Four (5)
sets of marked up as-built signed and sealed plans upon the
completion of the project. These plans shall be submitted by the
contractor to the Engineer prior to the release of final payment. The
as-built plans shall show details of actual site installation and include
all deviations from the original plans.
M A T E R I A L S
ELECTRICAL WORKS
PANEL BOARDS/MDS
LP
LPX
15AT 2P CB
Magnetic Switch Contactor
Manual Disconnect Switch 20 Amps 2PST in Nema-3R
Enclosure
Photoswitch
WIRES/CABLES
Copper Wire, 60mm2 THHN/THWN
Copper Wire, 14mm2 TW
Copper Wire, 3.5mm2 THHN/THWN
Copper Wire, 2.0mm2 TW
Pull box, 0.60m x 0.60m x 0.60m
µPVC CONDUITS
µPVC Pipe, 75mmØ (2½"Ø),Thick wall
µPVC Pipe, 63mmØ (2"Ø),Thick wall
µPVC Pipe, 40mmØ (¾"Ø), Thick wall
µPVC Pipe, 20mmØ (½"Ø), Thick wall
µPVC Assorted Fittings
LIGHTING FIXTURES
1-20W, 2000 Lumens, LED TUBE LAMP FIXTURE, w/
MIRRORZED REFLECTOR AND LOUVERIZED ALUMINUM
DIFFUSER, Flush Mounted
Page 111
110
3" diameter round built in w/ 5w LED Light with glass and
cover
Pinlight socket, 6" diameter round with frosted glass cover
complete w/ 9w downlight LED bulb
Outdoor wall lamp, 2x7watts, LED bulb
3W Weatherproof Step Light
Outdoor bollard with 9watts LED bulb complete with
concrete base
Outdoor spotlight, 20watts LED
Cove lights, 1.2m with 13watts LED
SWITCHES/CONVENIENCE OUTLETS
1-gang switch w/ plate and cover *
2-gang switch w/ plate and cover *
3-gang switch w/ plate and cover *
Duplex Convenience Outlet with ground, Universal and/ or
polarized flat w/ plate and cover *
Emergency light
3W, Green, LED Exit Sign
BOXES
µPVC Utility Box, 2"x4" orange - Omni
µPVC Junction Box with cover, 4" orange octagonal
Electrical Plastic Tape, big - Brand: 3M Tartan (Flame
retardant)
Rubber Tape - Nitto
Other Small items/ mechanical supports &
fittings/hardware needed not mentioned above
GROUNDING SYSTEM
Ground rod 20mmØ x 3000mmL CopperClad
Exothermic Weld Process
Page 112
111
Bare Copper Wire, 30mm2
Other Small items/ mechanical supports &
fittings/hardware needed not mentioned above
ELECTRONICS AND COMMUNICATION WORKS
CLOSED CIRCUIT TELEVISION SYSTEM
Complete Closed Circuit Television System Assembly
and Accessories
DOME TYPE CCTV CEILING MOUNT IP CAMERA
BULLET TYPE CCTV CEILING MOUNTED IP
CAMERA
Cat 6 UTP Cable
µPVC Pipe, 20mmØ (½"Ø), Thick wall
µPVC Junction Box with cover, 4" orange octagonal
Fittings & Consumables
COMMUNICATION AND DATA SYSTEMS
Manage Switch
D-Link 24 port smart switch
CTC
Wireless Access point; 802.11 a/b/g/n/ac; 100/100/1000
Ethernet ports; Passive PoE; WE, WPA-PSK, WPA-Enterprise
(WPA/WPA2, TKIP/AES)
RJ45 Connector
Cat 6 UTP Cable
Telephone/Internet outlets(1-gang) with plate and cover
µPVC Pipe, 20mmØ (½"Ø), Thick wall
µPVC Utility Box, 2"x4" orange
Fittings & Consumables
Page 113
112
24
REHABILITATION
OF OVERHEAD
FEEDER LINE
1.00 LOT
Supply and installation of 150mm2 THHN-THWN cable, as
indicated in the plans & specifications. Pulling of 3-sets 3x150mm2
of wire from new steel pole-1 to pole-2 via ductbank and cable
ladder. Connect/ splice new and old wires end to end using suitable
size split bolt inside the splicing box . Perform megger test, submit
test reports and ensure that test is acceptable or passed per standard
before energization.
Supply and Installation of steel pole and hardware assembly
complete with double Cross-Arm and Braces, Truss Guy, Secondary
Racks, Supports, grounding, Accessories, Splicing Box Outdoor
Type Nema 4R Stainless Steel (1000x300x200mm) and split bolt
connectors.
Supply and installation of cable ladder in the steel pole as detailed in
drawings and specifications.
Removal of existing wooden pole, cut/ remove existing overhead
feeder line in obstruction above the Gate-4 Façade.
Supply and installation of steel pole grounding system.
Demolition of existing concrete pedestal and wooden pole for
STEAM Library service entrance. Re-route/ transfer existing 2-sets
feeder wire of STEAM Library Building from Old wooden pole to
new steel pole. Pull excess wire up to power house.
The contractor must visit and conduct survey the site perform visual
and site actual measurements and satisfy himself as to the local
conditions and facilities that may affect his work. He will deem to
have done this before preparing & submission of his proposal.
Excluded in the scope;
- Removal of data/ fiber optic cables
- Pulling of data and fiber optic cables
M A T E R I A L S
WIRES/CABLES
Copper Wire, 150 mm2 THHN/THWN-2
ELECTRICAL POLE
30 Feet steel pole and hardware assembly complete with
double Cross-Arm and Braces, Truss Guy, Secondary Racks,
Supports, Grounding, Accessories, Splicing Box Outdoor Type
Nema 4R Stainless Steel (1000x300x200mm) and split bolt
connectors.
Cable Ladder 300x100mmx2400mm with cover
Page 114
113
Cable Ladder 100x100mmx2400mm with cover
Cable Ladder Supports and Accessories
REMOVAL OF EXISTING POLE
Removal of existing wooden pole, cut/ remove existing overhead
feeder line in obstruction above the Gate-4 Façade.
STEAM LIBRARY FEEDER WIRE
Demolition of existing concrete pedestal and wooden pole for
STEAM Library service entrance. Re-route/ transfer existing 2-sets
feeder wire of STEAM Library Building from Old wooden pole to
new steel pole. Pull excess wire up to power house.
25 PLUMBING
WORKS 1.00 LOT
All plumbing works included herein shall be executed according to
the provisions of the National Plumbing Code, National Building
Code and the Rules and Regulations of Batangas City;
The drawings are not intended to show every pipes, fittings, valves
and appliances. All such item whether specifically mentioned or not,
or indicated on the drawings shall be finished and installed if
necessary to complete the system in accordance with the best
practice of the Plumbing Trade and to the satisfaction of the
Owner/Representative;
All materials to be used shall be new and shall conform to the
Reference Code and Standards. Use of materials shall further be
governed by other requirements, imposed on other section of these
specifications. Materials shall be subject to test necessary for their
fitness if so required;
The Contractor shall furnish all materials, labor and equipment
necessary for the installation of all water lines, fixtures and
accessories;
All works must communicate to the Owner/Representative before
commencement;
SYSTEM DESCRIPTION: Provide new plumbing systems,
complete and ready for operation. Plumbing systems including
manufacturer’s products shall be in accordance with the required and
advisory of the IAPMO Uniform Plumbing Code and Philippine
National Plumbing Code. Plumbing systems include piping less than
1.50meters outside of the building;
Horizontal sanitary sewer piping shall be run in practical alignment
at a minimum slope of 1% for pipes 4" & larger & 2% for 3"∅&
smaller.
Page 115
114
Horizontal drainage/waste piping shall be run in practical alignment
at a minimum slope of 1% for pipes 4" & larger & 2% for 3"∅&
smaller.
All fixtures shall be provided with p-trap seal of not to less than
50mm but not more than 100mm in depth.
The contractor shall verify all existing utilities at site, that is, the
actual pipe sizes, locations, and depths, top and invert elevations of
all existing pipes and related structures. The contractors shall
provide the necessary excavations, backfilling and surface
restoration of the affected areas in the laying of sewer, storm
drainage and water supply lines.
M A T E R I A L S
PVC Sanitary/Drainage Pipes
(150mm) 6" dia. PVC Pipe x 3m
(100mm) 4" dia. PVC Pipe x 3m
(75mm) 3" dia. PVC Pipe x 3m
(50mm) 2" dia. PVC Pipe x 3m
PVC Sanitary/Drainage/Vent Fittings
6" dia. Coupling
4" dia Coupling
3" dia. Coupling
2" dia. Coupling
4"x2" Wye Reducer
4" dia. Wye
4" Elbow 90 deg.
4" Elbow 45 deg.
3" Elbow 90 deg.
3" Elbow 45 deg.
2" dia Tee
2" Elbow 90 deg.
2" Elbow 45 deg.
2" Wye
Page 116
115
2" dia. U-trap with plug and seal ring
4" dia. Clean-out
2" dia. Clean-out
PVC Solvent
PPR & GI Waterline Pipes
(25mm dia.) 1" GI Pipe x 6m
(20mm dia.) 3/4" GI Pipe x 6m
(20mm dia.) 3/4" PPR Pipe x 4m PN20
PPR & GI Waterline Fittings & Accessories
(25mm dia.) 1" GI Coupling
(25mm dia.) 1" GI Union
(25mm dia.) 1" GI 90 deg. Elbow
(25mm dia.) 1" GI Tee
(25mm dia.) 1" Brass Gate Valve
(20mm dia.) 3/4" GI Coupling
(20mm dia.) 3/4" GI Union
(20mm dia.) 3/4" GI 90 deg. Elbow
(20mm dia.) 3/4" GI Tee
(20mm dia.) 3/4" Brass Gate Valve
(20mm dia.) 3/4" PPR Union
(20mm dia.) 3/4" PPR Coupling
(20mm dia.) 3/4" PPR 90 deg. Elbow
(20mm dia.) 3/4" PPR 90 deg. Threaded Elbow
(20mm dia.) 3/4" PPR Tee
(20mm dia) 3/4" End cap
(20mm dia.) 1" PPR Gate Valve
Page 117
116
26
PLUMBING
FIXTURES AND
ACCESSORIES
1.00 LOT
Contractor shall furnish all materials, labor and equipment necessary
for the installation of all water lines, fixtures and accessories.
Supply and installation of all plumbing fixtures and accessories such
as water closet, lavatories, floor drains, bidet, kitchen sink, faucets,
soap dispenser/holder, tissue holder and grease trap;
All materials and equipment to be installed shall be of approved
quality and should be presented to the Owner for approval prior to
installation;
M A T E R I A L S
Pantry and Restroom Finishing
Water Closet with fittings
Stainless Steel Bidet faucet
Lavatory Wall Hung Type Half Pedestal
Lavatory Faucet
Stainless Steel Wall Mount Tap Faucet
Stainless steel Liquid Soap Dispenser
Stainless steel tissue holder
4" x 4" Stainless Floor Drain
Stainless Steel Gooseneck Faucet
Stainless Steel Single Bowl Pantry Sink
100mm Bronze Floor Cleanout
50mm Bronze Floor Cleanout
Class "A" Mirror for restrooms
3/4" thk. Natural Granite Slab (counter top and splash
board)
Portable Grease Trap 4GPM
50mm Dome-Type Roof Drain
Other Materials
40 kg. Cement
Tile Adhesive (25kg/bag)
Page 118
117
River Sand
Cutting Disk
27 CATCH BASINS 1.00 LOT
Catch basins shall be constructed as shown in the plan.
M A T E R I A L S
Catch Basins
4" CHB
Cement
Sand
10mm rebars
#16 GI Tie Wire
32mm x 4mm x 6m Galvanized Flat Bar for Grating
Welding Rod (25kg per box)
Cutting Disk
28
HAULING OF
WASTES AND
DEMOLISHED
MATERIALS
1.00 lot Hauling of waste and demolished materials and cleaning of all the
excess and unnecessary materials;
G E N E R A L
A All applicable provisions of the different divisions of the Specifications for each work shall apply for all items
cited in this schedule.
B Discrepancy arising from this section of the Contract Documents must be brought to the attention of the
Owner or representative Architect/Engineer whose decision shall be final.
C
Materials deemed necessary to complete the works but not specifically mentioned in the Specification,
Working Drawing, or in the Contract Document shall be supplied and installed by the Contractor. Such materials shall
be of the highest quality and kind, and installed or applied in a workmanlike manner at prescribed or appropriate
locations following the Standard Practice of Civil Engineering, National Building Code of the Philippines and
Construction Procedures.
D All items with specified approved brand, manufacturer, supplier, fabricator, trademark and the like shall be
strictly followed.
E The Contractor shall coordinate the work with the Project Management Office to expedite the implementation
of the project.
Page 119
118
F The Contractor shall supply all finishing accessories and furnishing fixtures as may be approved by the owner
or representative and shall be installed by the Contractor whenever required by the Owner or Representative.
G In case of items not included in this Matrix for Scope of Works but necessary for the completion of the
project, the bidder shall provide the additional items subject for evaluation by the TWG.
H Items such as accessories, fittings, consumables and other similar items/materials shall be detailed and
quantified by the bidder.
C O N F L I C T I N R E F E R E N C E D O C U M E N T S
In the case of any conflict between the technical requirement and specifications of this contract and the reference
documents, or among the reference documents, the order of precedence is:
1) Scope of Work/Matrix for Scope of Works
2) Basic Engineering Drawings
3) Technical Specifications
The Contractor shall notify any discrepancy found in the documentation to BatStateU in writing for clarification.
BatStateU will respond to such request in writing.
Section VII. Drawings
The actual drawings, including site plans should be given
separately.
Page 121
120
Section VIII. Bill of Quantities
Notes on the Bill of Quantities
Objectives
The objectives of the Bill of Quantities are:
a. to provide sufficient information on the quantities of Works to be performed to
enable Bids to be prepared efficiently and accurately; and
b. when a Contract has been entered into, to provide a priced Bill of Quantities for use
in the periodic valuation of Works executed.
In order to attain these objectives, Works should be itemized in the Bill of Quantities in
sufficient detail to distinguish between the different classes of Works, or between Works of
the same nature carried out in different locations or in other circumstances which may give
rise to different considerations of cost. Consistent with these requirements, the layout and
content of the Bill of Quantities should be as simple and brief as possible.
Daywork Schedule
A Daywork Schedule should be included only if the probability of unforeseen work, outside
the items included in the Bill of Quantities, is high. To facilitate checking by the Entity of
the realism of rates quoted by the Bidders, the Daywork Schedule should normally comprise
the following:
a. A list of the various classes of labor, materials, and Constructional Plant for which
basic daywork rates or prices are to be inserted by the Bidder, together with a
statement of the conditions under which the Contractor will be paid for work
executed on a daywork basis.
b. Nominal quantities for each item of Daywork, to be priced by each Bidder at
Daywork rates as Bid. The rate to be entered by the Bidder against each basic
Daywork item should include the Contractor’s profit, overheads, supervision, and
other charges.
Provisional Sums
A general provision for physical contingencies (quantity overruns) may be made by
including a provisional sum in the Summary Bill of Quantities. Similarly, a contingency
allowance for possible price increases should be provided as a provisional sum in the
Summary Bill of Quantities. The inclusion of such provisional sums often facilitates
budgetary approval by avoiding the need to request periodic supplementary approvals as the
future need arises. Where such provisional sums or contingency allowances are used, the
SCC should state the manner in which they will be used, and under whose authority (usually
the Procuring Entity’s Representative’s).
Page 122
121
The estimated cost of specialized work to be carried out, or of special goods to be supplied,
by other contractors should be indicated in the relevant part of the Bill of Quantities as a
particular provisional sum with an appropriate brief description. A separate procurement
procedure is normally carried out by the Procuring Entity to select such specialized
contractors. To provide an element of competition among the Bidders in respect of any
facilities, amenities, attendance, etc., to be provided by the successful Bidder as prime
Contractor for the use and convenience of the specialist contractors, each related provisional
sum should be followed by an item in the Bill of Quantities inviting the Bidder to quote a
sum for such amenities, facilities, attendance, etc.
Signature Box
A signature box shall be added at the bottom of each page of the Bill of Quantities where the
authorized representative of the Bidder shall affix his signature. Failure of the authorized
representative to sign each and every page of the Bill of Quantities shall be a cause for
rejection of his bid.
These Notes for Preparing a Bill of Quantities are intended only as information for the
Procuring Entity or the person drafting the Bidding Documents. They should not be included
in the final documents.
CONTENT
Item
No. Description
% of
Total Unit Quantity
1 MOBILIZATION/DEMOBILIZATION 0.342 LOT 1.00
2 CONSTRUCTION SAFETY & HEALTH
PROGRAM 0.925 LOT 1.00
3 OTHER GENERAL REQUIREMENTS
(Project Photographs and Project Billboards) 0.121 LOT 1.00
4 TEMPORARY FACILITIES/FIELD OFFICE 0.659 LOT 1.00
5 SITEWORKS 14.364 LOT 1.00
6 FORMWORKS 0.643 LOT 1.00
7 REINFORCED CONCRETE WORKS 82.815 cu.m. 682.00
8 HAULING OF WASTES AND
DEMOLISHED MATERIALS 0.132 LOT 1.00
CONSTRUCTION 100.0
Page 123
122
Section IX. Checklist of Technical and Financial
Documents
Notes on the Checklist of Technical and Financial Documents
The prescribed documents in the checklist are mandatory to be submitted in the Bid, but
shall be subject to the following:
a. GPPB Resolution No. 09-2020 on the efficient procurement measures during a State
of Calamity or other similar issuances that shall allow the use of alternate documents
in lieu of the mandated requirements; or
b. any subsequent GPPB issuances adjusting the documentary requirements after the
effectivity of the adoption of the PBDs.
The BAC shall be checking the submitted documents of each Bidder against this checklist
to ascertain if they are all present, using a non-discretionary “pass/fail” criterion pursuant to
Section 30 of the 2016 revised IRR of RA No. 9184.
Page 124
123
Checklist of Technical and Financial Documents
I. TECHNICAL COMPONENT ENVELOPE
Class “A” Documents
Legal Documents
⬜ (a) Valid PhilGEPS Registration Certificate (Platinum Membership) (all pages);
Or
⬜ (b) Registration certificate from Securities and Exchange Commission (SEC),
Department of Trade and Industry (DTI) for sole proprietorship, or
Cooperative Development Authority (CDA) for cooperatives or its equivalent
document;
And
⬜ (c) Mayor’s or Business permit issued by the city or municipality where the
principal place of business of the prospective bidder is located, or the
equivalent document for Exclusive Economic Zones or Areas;
And
⬜ (e) Tax clearance per E.O. No. 398, s. 2005, as finally reviewed and approved by
the Bureau of Internal Revenue (BIR).
Technical Documents
⬜ (f) Statement of the prospective bidder of all its ongoing government and private
contracts, including contracts awarded but not yet started, if any, whether
similar or not similar in nature and complexity to the contract to be bid; and
⬜ (g) Statement of the bidder’s Single Largest Completed Contract (SLCC) similar
to the contract to be bid, except under conditions provided under the rules;
and
⬜ (h) Philippine Contractors Accreditation Board (PCAB) License;
or
Special PCAB License in case of Joint Ventures;
and registration for the type and cost of the contract to be bid; and
⬜ (i) Original copy of Bid Security. If in the form of a Surety Bond, submit also a
certification issued by the Insurance Commission;
or
Original copy of Notarized Bid Securing Declaration; and
(j) Project Requirements, which shall include the following:
⬜ a. Organizational chart for the contract to be bid;
⬜ b. List of contractor’s key personnel (e.g., Project Manager, Project
Engineers, Materials Engineers, and Foremen), to be assigned to the
contract to be bid, with their complete qualification and experience
data;
⬜ c. List of contractor’s major equipment units, which are owned, leased,
and/or under purchase agreements, supported by proof of ownership or
certification of availability of equipment from the equipment
lessor/vendor for the duration of the project, as the case may be; and
Page 125
124
⬜ (k) Original duly signed Omnibus Sworn Statement (OSS);
and if applicable, Original Notarized Secretary’s Certificate in case of a
corporation, partnership, or cooperative; or Original Special Power of
Attorney of all members of the joint venture giving full power and authority
to its officer to sign the OSS and do acts to represent the Bidder.
Financial Documents
⬜ (l) The prospective bidder’s audited financial statements, showing, among others,
the prospective bidder’s total and current assets and liabilities, stamped
“received” by the BIR or its duly accredited and authorized institutions, for
the preceding calendar year which should not be earlier than two (2) years
from the date of bid submission; and
⬜ (m) The prospective bidder’s computation of Net Financial Contracting Capacity
(NFCC).
Class “B” Documents
⬜ (n) If applicable, duly signed joint venture agreement (JVA) in accordance with
RA No. 4566 and its IRR in case the joint venture is already in existence;
or
duly notarized statements from all the potential joint venture partners stating
that they will enter into and abide by the provisions of the JVA in the instance
that the bid is successful.
II. FINANCIAL COMPONENT ENVELOPE
⬜ (o) Original of duly signed and accomplished Financial Bid Form; and
Other documentary requirements under RA No. 9184
⬜ (p) Original of duly signed Bid Prices in the Bill of Quantities; and
⬜ (q) Duly accomplished Detailed Estimates Form, including a summary sheet
indicating the unit prices of construction materials, labor rates, and equipment
rentals used in coming up with the Bid; and
⬜ (r) Cash Flow by Quarter.
Page 127
Bid Form for the Procurement of Infrastructure Projects [shall be submitted with the Bid]
BID FORM
Date :
Project Identification No. :
To: [name and address of Procuring Entity]
Having examined the Philippine Bidding Documents (PBDs) including the Supplemental or Bid Bulletin Numbers [insert numbers], the receipt of which is hereby duly acknowledged, we, the undersigned, declare that:
a. We have no reservation to the PBDs, including the Supplemental or Bid Bulletins, for the Procurement Project: [insert name of contract];
b. We offer to execute the Works for this Contract in accordance with the PBDs;
c. The total price of our Bid in words and figures, excluding any discounts offered
below is: [insert information];
d. The discounts offered and the methodology for their application are: [insert information];
e. The total bid price includes the cost of all taxes, such as, but not limited to: [specify the applicable taxes, e.g. (i) value added tax (VAT), (ii) income tax, (iii) local taxes, and (iv) other fiscal levies and duties], which are itemized herein and reflected in the detailed estimates,
f. Our Bid shall be valid within the a period stated in the PBDs, and it shall remain
binding upon us at any time before the expiration of that period;
g. If our Bid is accepted, we commit to obtain a Performance Security in the amount of [insert percentage amount] percent of the Contract Price for the due performance of the Contract, or a Performance Securing Declaration in lieu of the the allowable forms of Performance Security, subject to the terms and conditions of issued GPPB guidelines1 for this purpose;
h. We are not participating, as Bidders, in more than one Bid in this bidding process,
other than alternative offers in accordance with the Bidding Documents;
i. We understand that this Bid, together with your written acceptance thereof included in your notification of award, shall constitute a binding contract between us, until a formal Contract is prepared and executed; and
j. We understand that you are not bound to accept the Lowest Calculated Bid or any
other Bid that you may receive.
k. We likewise certify/confirm that the undersigned, is the duly authorized
1 currently based on GPPB Resolution No. 09-2020
Page 128
representative of the bidder, and granted full power and authority to do, execute and perform any and all acts necessary to participate, submit the bid, and to sign and execute the ensuing contract for the [Name of Project] of the [Name of the Procuring Entity].
l. We acknowledge that failure to sign each and every page of this Bid Form,
including the Bill of Quantities, shall be a ground for the rejection of our bid.
Name:
Legal Capacity:
Signature:
Duly authorized to sign the Bid for and behalf of:
Date:
Page 129
Bid Securing Declaration Form [shall be submitted with the Bid if bidder opts to provide this form of bid security]
REPUBLIC OF THE PHILIPPINES) CITY OF ) S.S.
BID SECURING DECLARATION Project Identification No.: [Insert number]
To: [Insert name and address of the Procuring Entity]
I/We, the undersigned, declare that:
1. I/We understand that, according to your conditions, bids must be supported by a Bid Security, which may be in the form of a Bid Securing Declaration.
2. I/We accept that: (a) I/we will be automatically disqualified from bidding for any procurement contract with any procuring entity for a period of two (2) years upon receipt of your Blacklisting Order; and, (b) I/we will pay the applicable fine provided under Section 6 of the Guidelines on the Use of Bid Securing Declaration, within fifteen (15) days from receipt of the written demand by the procuring entity for the commission of acts resulting to the enforcement of the bid securing declaration under Sections 23.1(b), 34.2, 40.1 and 69.1, except 69.1(f),of the IRR of RA No. 9184; without prejudice to other legal action the government may undertake.
3. I/We understand that this Bid Securing Declaration shall cease to be valid on the following circumstances:
a. Upon expiration of the bid validity period, or any extension thereof pursuant to your request;
b. I am/we are declared ineligible or post-disqualified upon receipt of your notice to such effect, and (i) I/we failed to timely file a request for reconsideration or (ii) I/we filed a waiver to avail of said right; and
c. I am/we are declared the bidder with the Lowest Calculated Responsive Bid, and I/we have furnished the performance security and signed the Contract.
IN WITNESS WHEREOF, I/We have hereunto set my/our hand/s this day of [month] [year] at [place of execution].
[Insert NAME OF BIDDER OR ITS AUTHORIZED REPRESENTATIVE]
[Insert signatory’s legal capacity] Affiant
[Jurat] [Format shall be based on the latest Rules on Notarial Practice]
Page 130
Contract Agreement Form for the Procurement of Infrastructure Projects (Revised)
[not required to be submitted with the Bid, but it shall be submitted within ten (10) days after receiving the Notice of Award]
CONTRACT AGREEMENT
THIS AGREEMENT, made this [insert date] day of [insert month], [insert year] between [name and address of PROCURING ENTITY] (hereinafter called the “Entity”) and [name and address of Contractor] (hereinafter called the “Contractor”).
WHEREAS, the Entity is desirous that the Contractor execute [name and identification number of contract] (hereinafter called “the Works”) and the Entity has accepted the Bid for [contract price in words and figures in specified currency] by the Contractor for the execution and completion of such Works and the remedying of any defects therein.
NOW THIS AGREEMENT WITNESSETH AS FOLLOWS:
1. In this Agreement, words and expressions shall have the same meanings as are respectively assigned to them in the Conditions of Contract hereinafter referred to.
2. The following documents as required by the 2016 revised Implementing Rules and
Regulations of Republic Act No. 9184 shall be deemed to form and be read and construed as part of this Agreement, viz.:
a. Philippine Bidding Documents (PBDs); i. Drawings/Plans; ii. Specifications; iii. Bill of Quantities; iv. General and Special Conditions of Contract; v. Supplemental or Bid Bulletins, if any;
b. Winning bidder’s bid, including the Eligibility requirements, Technical and Financial Proposals, and all other documents or statements submitted;
Bid form, including all the documents/statements contained in the Bidder’s bidding envelopes, as annexes, and all other documents submitted (e.g., Bidder’s response to request for clarifications on the bid), including corrections to the bid, if any, resulting from the Procuring Entity’s bid evaluation;
c. Performance Security;
d. Notice of Award of Contract and the Bidder’s conforme thereto; and
e. Other contract documents that may be required by existing laws and/or the Procuring Entity concerned in the PBDs. Winning bidder agrees that additional contract documents or information prescribed by the GPPB that are subsequently required for submission after the contract execution, such as the Notice to Proceed, Variation Orders, and Warranty Security, shall likewise form part of the Contract.
Page 131
3. In consideration for the sum of [total contract price in words and figures] or such other sums as may be ascertained, [Named of the bidder] agrees to [state the object of the contract] in accordance with his/her/its Bid.
4. The [Name of the procuring entity] agrees to pay the above-mentioned sum in accordance with the terms of the Bidding.
IN WITNESS whereof the parties thereto have caused this Agreement to be executed the day and year first before written.
[Insert Name and Signature]
[Insert Signatory’s Legal Capacity]
for:
[Insert Procuring Entity]
[Insert Name and Signature]
[Insert Signatory’s Legal Capacity]
for:
[Insert Name of Supplier]
Acknowledgment
[Format shall be based on the latest Rules on Notarial Practice]
Page 132
Omnibus Sworn Statement (Revised) [shall be submitted with the Bid]
REPUBLIC OF THE PHILIPPINES) CITY/MUNICIPALITY OF ) S.S.
AFFIDAVIT
I, [Name of Affiant], of legal age, [Civil Status], [Nationality], and residing at [Address of Affiant], after having been duly sworn in accordance with law, do hereby depose and state that:
1. [Select one, delete the other:]
[If a sole proprietorship:] I am the sole proprietor or authorized representative of [Name of Bidder] with office address at [address of Bidder];
[If a partnership, corporation, cooperative, or joint venture:] I am the duly authorized and designated representative of [Name of Bidder] with office address at [address of Bidder];
2. [Select one, delete the other:]
[If a sole proprietorship:] As the owner and sole proprietor, or authorized representative of [Name of Bidder], I have full power and authority to do, execute and perform any and all acts necessary to participate, submit the bid, and to sign and execute the ensuing contract for [Name of the Project] of the [Name of the Procuring Entity], as shown in the attached duly notarized Special Power of Attorney;
[If a partnership, corporation, cooperative, or joint venture:] I am granted full power and authority to do, execute and perform any and all acts necessary to participate, submit the bid, and to sign and execute the ensuing contract for [Name of the Project] of the [Name of the Procuring Entity], as shown in the attached [state title of attached document showing proof of authorization (e.g., duly notarized Secretary’s Certificate, Board/Partnership Resolution, or Special Power of Attorney, whichever is applicable;)];
3. [Name of Bidder] is not “blacklisted” or barred from bidding by the Government of the
Philippines or any of its agencies, offices, corporations, or Local Government Units, foreign government/foreign or international financing institution whose blacklisting rules have been recognized by the Government Procurement Policy Board, by itself or by relation, membership, association, affiliation, or controlling interest with another blacklisted person or entity as defined and provided for in the Uniform Guidelines on Blacklisting;
4. Each of the documents submitted in satisfaction of the bidding requirements is an authentic copy of the original, complete, and all statements and information provided therein are true and correct;
5. [Name of Bidder] is authorizing the Head of the Procuring Entity or its duly authorized
representative(s) to verify all the documents submitted;
6. [Select one, delete the rest:]
[If a sole proprietorship:] The owner or sole proprietor is not related to the Head of the Procuring Entity, members of the Bids and Awards Committee (BAC), the Technical
Page 133
Working Group, and the BAC Secretariat, the head of the Project Management Office or the end-user unit, and the project consultants by consanguinity or affinity up to the third civil degree;
[If a partnership or cooperative:] None of the officers and members of [Name of Bidder] is related to the Head of the Procuring Entity, members of the Bids and Awards Committee (BAC), the Technical Working Group, and the BAC Secretariat, the head of the Project Management Office or the end-user unit, and the project consultants by consanguinity or affinity up to the third civil degree;
[If a corporation or joint venture:] None of the officers, directors, and controlling stockholders of [Name of Bidder] is related to the Head of the Procuring Entity, members of the Bids and Awards Committee (BAC), the Technical Working Group, and the BAC Secretariat, the head of the Project Management Office or the end-user unit, and the project consultants by consanguinity or affinity up to the third civil degree;
7. [Name of Bidder] complies with existing labor laws and standards; and
8. [Name of Bidder] is aware of and has undertaken the responsibilities as a Bidder in
compliance with the Philippine Bidding Documents, which includes:
a. Carefully examining all of the Bidding Documents; b. Acknowledging all conditions, local or otherwise, affecting the implementation of the
Contract; c. Making an estimate of the facilities available and needed for the contract to be bid, if
any; and d. Inquiring or securing Supplemental/Bid Bulletin(s) issued for the [Name of the
Project].
9. [Name of Bidder] did not give or pay directly or indirectly, any commission, amount, fee, or any form of consideration, pecuniary or otherwise, to any person or official, personnel or representative of the government in relation to any procurement project or activity.
10. In case advance payment was made or given, failure to perform or deliver any of the obligations and undertakings in the contract shall be sufficient grounds to constitute criminal liability for Swindling (Estafa) or the commission of fraud with unfaithfulness or abuse of confidence through misappropriating or converting any payment received by a person or entity under an obligation involving the duty to deliver certain goods or services, to the prejudice of the public and the government of the Philippines pursuant to Article 315 of Act No. 3815 s. 1930, as amended, or the Revised Penal Code.
IN WITNESS WHEREOF, I have hereunto set my hand this day of , 20 at , Philippines.
[Insert NAME OF BIDDER OR ITS AUTHORIZED REPRESENTATIVE]
[Insert signatory’s legal capacity] Affiant
[Jurat] [Format shall be based on the latest Rules on Notarial Practice]
Page 134
Performance Securing Declaration (Revised) [if used as an alternative performance security but it is not required to be submitted with the
Bid, as it shall be submitted within ten (10) days after receiving the Notice of Award]
REPUBLIC OF THE PHILIPPINES) CITY OF ) S.S.
PERFORMANCE SECURING DECLARATION Invitation to Bid: [Insert Reference Number indicated in the Bidding Documents] To: [Insert name and address of the Procuring Entity]
I/We, the undersigned, declare that:
1. I/We understand that, according to your conditions, to guarantee the faithful performance by the supplier/distributor/manufacturer/contractor/consultant of its obligations under the Contract, I/we shall submit a Performance Securing Declaration within a maximum period of ten (10) calendar days from the receipt of the Notice of Award prior to the signing of the Contract.
2. I/We accept that: I/we will be automatically disqualified from bidding for any procurement contract with any procuring entity for a period of one (1) year for the first offense, or two (2) years for the second offense, upon receipt of your Blacklisting Order if I/We have violated my/our obligations under the Contract;
3. I/We understand that this Performance Securing Declaration shall cease to be valid
upon:
a. issuance by the Procuring Entity of the Certificate of Final Acceptance, subject to the following conditions:
i. Procuring Entity has no claims filed against the contract awardee; ii. It has no claims for labor and materials filed against the contractor; and iii. Other terms of the contract; or
b. replacement by the winning bidder of the submitted PSD with a performance
security in any of the prescribed forms under Section 39.2 of the 2016 revised IRR of RA No. 9184 as required by the end-user.
IN WITNESS WHEREOF, I/We have hereunto set my/our hand/s this day of [month]
[year] at [place of execution].
[Insert NAME OF BIDDER OR ITS AUTHORIZED REPRESENTATIVE] [Insert signatory’s legal capacity]
Affiant
[Jurat] [Format shall be based on the latest Rules on Notarial Practice]
Page 135
Batangas State University BatStateU Infra Form No.1
Bidding Documents for Infrastructure Projects (Based on Revised IRR of RA 9184, 2016)
List of all Ongoing Government & Private Construction Contracts including contracts awarded but not yet started
Business Name :
Business Address :
Name of
Contract/Location
Project Cost
a. Owner Name b. Address
c. Telephone Nos.
Nature of Work
Contractor’s Role a. Date Awarded
b. Date Started
c. Date of
Completion
% of Accomplishment
Value of
Outstanding
Works Description % Planned Actual
Government
Private
Total Cost
NOTE: This statement shall be supported with: 1 Notice of Award and/or Contract 2. Notice to Proceed issued by the owner 3 Certificate of Accomplishments signed by the owner or Project Engineer
Submitted by :
(Printed Name & Signature
Designation :
Date :
One of the technical documents required to be in the Eligibility Envelope of a prospective bidder is a list of all its on-going, completed, and awarded but not yet started contracts.
Page 136
Batangas State University BatStateU Infra Form No. 2
Bidding Documents for Infrastructure Projects (Based on Revised IRR of RA 9184, 2016)
Statement of Single Largest Government or Private Contracts completed which is similar in nature
Business Name :
Business Address :
Name of
Contract/Location
Project Cost
a. Owner Name b. Address
c. Telephone Nos.
Nature of Work
Contractor’s Role a. Date Awarded
b. Date Started
c. Date of
Completion
% of Accomplishment
Value of
Outstanding
Works Description % Planned Actual
Total Cost
NOTE: This statement shall be supported with: 1 Contract 2. CPES rating sheets and/or Certificate of Completion
3 Certificate of Acceptance
Submitted by :
(Printed Name & Signature
Designation :
Date :
One of the technical documents required to be in the Eligibility Envelope of a prospective bidder is a list of all contracts which are similar in nature and complexity to the contract to be bid. This statement will show that the value of the prospective bidder’s largest single completed contract, adjusted to current prices using the National Statistics Office (NSO) consumer price indices available at the G-EPS website, and similar to
the contract to be bid, must be at least fifty percent (50%) of the approved budget for the contract to be bid.
Page 137
Batangas State University BatStateU Infra Form No.3
Bidding Documents for Infrastructure Projects (Based on Revised IRR of RA 9184, 2016)
NET FINANCIAL CONTRACTING CAPACITY
A. Summary of the Applicant Firm’s/Contractor’s assets and liabilities on the basis of the attached
income tax return and audited financial statement, stamped “RECEIVED” by the Bureau of Internal
Revenue or BIR authorized collecting agent, for the immediately preceding year and a certified
copy of Schedule of Fixed Assets particularly the list of construction equipment.
Year 20
1. Total Assets
2. Current Assets
3. Total Liabilities
4. Current Liabilities
5. Total Net Worth (1-3)
6. Current Net Worth or Net Working Capital (2-4)
B. The Net Financial Contracting Capacity (NFCC) based on the above data is computed as follows:
NFCC = [(Current assets minus current liabilities) (15)] minus the value of all outstanding or
uncompleted portions of the projects under ongoing contracts, including awarded contracts yet to
be started, coinciding with the contract to be bid.
NFCC = P
The value of bidder’s current assets and current liabilities shall be based on the latest Audited
Financial Statements submitted to the BIR.
Herewith attached are certified true copies of the income tax return and audited financial statement:
stamped “RECEIVED” by the BIR or BIR authorized collecting agent for the immediately preceding
year.
Submitted by:
Name of Firm / Contractor
Signature of Authorized Representative Date :
NOTE: 1. If Partnership or Joint Venture, each Partner or Member Firm of Joint Venture shall submit the
above requirements.
The above information are among the financial documents required for Eligibility Check. Together with the legal and technical documents
required, the financial documents shall be placed inside the Eligibility Envelope and submitted to the BAC on or before the deadline for the submission and receipt of Eligibility Envelopes.
Page 138
Batangas State University BatStateU Infra Form No. 4a
Bidding Documents for Infrastructure Projects (Based on Revised IRR of RA 9184, 2016)
FORM OF BID SECURITY (BANK GUARANTEE)
WHEREAS, (Name of Bidder) (hereinafter called “the Bidder”) has submitted his bid dated
(Date) for the (Name of Contract) (hereinafter called “the Bid”).
KNOW ALL MEN by these presents that We (Name of Bank) of (Name of Country) having our
registered office at (hereinafter called “the Bank” are bound unto
(Name of Procuring Entity) (hereinafter called “the Entity”) in the sum of (insert amount)_ for
which payment well and truly to be made to the said Entity the Bank binds himself, his successors and
assigns by these presents.
SEALED with the Common Seal of the said Bank this day of 20 .
THE CONDITIONS of this obligation are that:
1) if the Bidder withdraws his Bid during the period of bid validity specified in the Form of
Bid; or
2) if the Bidder does not accept the correction of arithmetical errors of his bid price in
accordance with the Instructions to Bidder; or
3) if the Bidder having been notified of the acceptance of his bid and award of contract to
him by the Entity during the period of bid validity:
a) fails or refuses to execute the Form of Contract in accordance with the Instructions
to Bidders, if required; or
b) fails or refuses to furnish the Performance Security in accordance with the
Instructions to Bidders;
we undertake to pay to the Entity up to the above amount upon receipt of his first written demand,
without the Entity having to substantiate its demand, provided that in his demand the Entity will note
that the amount claimed by it is due to the occurrence of any one or combination of the three (3)
conditions stated above.
The Guarantee will remain in force up to and including the date days after the
deadline for submission of Bids as such deadline is stated in the Instructions to Bidders or as it may be
extended by the Entity, notice of which extension(s) to the Bank is hereby waived. Any demand in
respect of this Guarantee should reach the Bank not later than the above date.
DATE : _ SIGNATURE OF THE BANK
WITNESS : SEAL
(Signature, Name and Address)
The bidder should insert the amount of the guarantee in words and figures, denominated in the currency of the Entity’s country or an
equivalent amount in a freely convertible currency. This figure should be the same as shown of the Instructions to Bidders.
Usually 28 days after the end of the validity period of the Bid. Date should be inserted by the Entity before the bidding documents are issued.
Page 139
Batangas State University BatStateU Infra Form No.5
Bidding Documents for Infrastructure Projects (Based on Revised IRR of RA 9184, 2016)
Contractor’s Organizational Chart for the Contract
Submit Copy of the Organizational Chart that the Contractor intends to use to execute the Contract
if awarded to him. Indicate in the chart the names of the Project Manager, Project Engineer, Bridge
Engineer, Structural Engineer, Materials and Quality Control Engineer, Foreman and other Key
Engineering Personnel.
1. This organization chart should represent the “Contractor’s Organization” required for the Project, and not the organizational chart of the
entire firm.
2. The Bidders shall comply with and submit sample form BatStateU Infra Form No. 9 for each of such key personnel. 3. Each such nominated engineer/key personnel shall comply with and submit sample forms BatStateU Infra Form No. 11 and BatStateU Infra
Form No. 12.
4. All these are required to be in the Technical Envelope of the Bidder.
Attach the required Proposed Organizational Chart for the Contract as stated above
Page 140
Batangas State University BatStateU Infra Form No.6
Bidding Documents for Infrastructure Projects (Based on Revised IRR of RA 9184, 2016)
Contractor’s Letter-Certificate to Procuring Entity
Date:
Name of the Head of the Procuring Entity
Position of the Head of the Procuring Entity
Name of the Procuring Entity
Address of the Procuring Entity
Dear Sir / Madame:
Supplementing our Organizational Chart for the Contract, we have the honor to submit
herewith, and to certify as true and correct, the following pertinent information:
1. That I/we have engaged the services of (Name of Employee) , to be the
(Designation) of the (Name of Contract) , who is a (Profession) with
Professional License Certificate No. _ issued on
and who has performed the duties in the construction of the Contracts enumerated in the
duly filled Form .
2. The said Engineer shall be designated by us as our (Designation) to personally perform
the duties of the said position in the above-mentioned Project, if and when the same is
awarded in our favor.
3. That said Engineer shall employ the best care, skill and ability in performing his duties
in accordance with the Contract Agreement, Conditions of Contract, Plans,
Specifications, Special Provisions, and other provisions embodied in the proposed
contract.
4. That said Engineer shall be personally present at the jobsite to supervise the phase of
the construction work pertaining to this assignment as (Designation), all the time.
5. That, in order to guarantee that said Engineer shall perform his duties properly and be
personally present in the Job Site, he is hereby required to secure a certificate of
appearance for the Procuring Entity Engineer at the end of every month.
That, in the event that I/we elect or choose to replace said (Designation) with another
Engineer, the Procuring Entity will be accordingly notified by us in writing at least
twenty one (21) days before making the replacement. We will submit to the Procuring
Entity, for prior approval, the name of the proposed new (Designation), his
qualifications, experience, list of projects undertaken and other relevant information.
6. That any willful violation on my/our part of the herein conditions may prejudice my/our
standing as a reliable contractor in future bidding of the Procuring Entity.
Page 141
Batangas State University BatStateU Infra Form No.6
Bidding Documents for Infrastructure Projects (Based on Revised IRR of RA 9184, 2016)
Very truly yours,
(Authorized Representative of Bidder)
CONCURRED IN:
(Name of Engineer)
(Address)
Page 142
Batangas State University BatStateU Infra Form No.7
Bidding Documents for Infrastructure Projects (Based on Revised IRR of RA 9184, 2016)
Statement of Availability of Key Personnel
(Date of Issuance)
Name of the Head of the Procuring Entity
Name of the Procuring Entity
Address of the Procuring Entity
Attention : Prof. ENRICO M. DALANGIN
Chairman
Bids and Awards Committee
Dear Sir / Madame:
In compliance with the requirements of the Batangas State University-Bids and Awards
Committee for the bidding of the (Name of the Contract) , we certify that
(Name of the Bidder)__ has in its employ key personnel, such as project managers,
project engineers and foremen, who may be engaged for the construction of the said
contract.
Very truly yours,
(Name of Representative)
(Position)
(Name of Bidder)
Page 143
Batangas State University BatStateU Infra Form No.8
Bidding Documents for Infrastructure Projects (Based on Revised IRR of RA 9184, 2016)
KEY PERSONNEL
Give the detailed information of the following personnel who are scheduled to be assigned as full-time
field staff for the project. Fill up a form for each person.
- Authorized Managing Officer / Representative
- Sustained Technical Employee
PERSONAL DATA
Name :
Date of Birth :
Nationality :
Education and Degrees :
Specialty :
Registration :
Length of Service with the Firm : Years of Experience (from / to) :
If length of service in the firm is less than ten (10) years, give name and length of service with previous
employers for a ten (10)-year period (attached additional sheet/s), if necessary:
Name and Address of Employer Length of Service
year(s) from / to
Experience:
This should cover the past ten (10) years of experience. (Attached as many pages as necessary to show
involvement of personnel in projects using the format below).
Experience Data
Name of Project :
Name and Address of Owner :
Name and Address of the Owner’s Engineer (Consultant)
:
Indicate the Features of Project :
(Particulars of the project components and any other
particular interest connected with the project)
Contract Amount Expressed in Philippine Currency
:
Position :
Structures for which the employee was
responsible
:
Assignment Period (from / to) :
Name and Signature of Employee
It is hereby certified that the above personnel can be assigned to this project, if the contract is awarded to
our company.
(Place and Date) (The Authorized Representative)
One of the requirements from the bidder to be included in its Technical Envelope is a list of contractor’s key personnel (viz., Project Manager,
Project Engineers, Materials Engineers, and Foremen), to be assigned to the contract to be bid, with their complete qualification and
experience data (including the key personnel’s signed written commitment to work for the project once awarded the contract).
Page 144
Batangas State University BatStateU Infra Form No.9
Bidding Documents for Infrastructure Projects (Based on Revised IRR of RA 9184, 2016)
Key Personnel’s Certificate of Employment
Issuance Date
Name of the Head of the Procuring Entity
Position of the Head of the Procuring Entity
Name of the Procuring Entity
Address of the Procuring Entity
Dear Sir / Madame:
I am (Name of Nominee) a Licensed Engineer with Professional License No.
issued on (date of issuance) at (place of issuance) .
I hereby certify that (Name of Bidder) has engaged my services as (Designation) for
(Name of the Contract), if awarded to it.
As (Designation) , I supervised the following completed projects similar to the contract under
bidding):
NAME OF PROJECT OWNER COST DATE
COMPLETED
At present, I am supervising the following projects:
NAME OF PROJECT OWNER COST DATE
COMPLETED
In case of my separation for any reason whatsoever from the above-mentioned Contractor, I
shall notify the (Name of the Procuring Entity) at least twenty one (21) days before the effective date
of my separation.
As (Designation) , I know I will have to stay in the job site all the time to supervise and manage
the Contract works to the best of my ability, and aware that I am authorized to handle only one (1)
contract at a time.
I do not allow the use of my name for the purpose of enabling the above-mentioned Contractor
to qualify for the Contract without any firm commitment on my part to assume the post of
(Designation) therefor, if the contract is awarded to him since I understand that to do so will be a
sufficient ground for my disqualification as (Designation) in any future (Name of the
Procuring Entity) bidding or employment with any Contractor doing business with the (Name of
the Procuring Entity) .
(Signature of Engineer)
DRY SEAL
One of the requirements from the bidder to be included in its Technical Envelope is a list of contractor’s key personnel (viz., Project Manager,
Project Engineers, Materials Engineers, and Foremen), to be assigned to the contract to be bid, with their complete qualification and
experience data (including the key personnel’s signed written commitment to work for the project once awarded the contract).
Page 145
Batangas State University BatStateU Infra Form No.9
Bidding Documents for Infrastructure Projects (Based on Revised IRR of RA 9184, 2016)
Republic of the Philippines )
) S.S.
SUBSCRIBED AND SWORN TO before me this day of 20 affiant
exhibiting to me his Residence Certificate No.
.
issued on at
Notary Public
Until December 31, 20
Doc. No. ;
Page No. ;
Book No. ;
Series of ;
One of the requirements from the bidder to be included in its Technical Envelope is a list of contractor’s key personnel (viz., Project Manager,
Project Engineers, Materials Engineers, and Foremen), to be assigned to the contract to be bid, with their complete qualification and
experience data (including the key personnel’s signed written commitment to work for the project once awarded the contract).
Page 146
Batangas State University BatStateU Infra Form No.10
Bidding Documents for Infrastructure Projects (Based on Revised IRR of RA 9184, 2016)
Qualification of Key Personnel Proposed to be Assigned to the Contract
Business Name : Business Address :
Project Manager /
Engineer
Materials Engineer Foreman Construction
Safety and Health Personnel
Other positions deemed
required by the Applicant for this project
1 Name
2 Address
3 Date of Birth
4 Employed Since
5 Experience
6 Previous Employment
7 Education
8 PRC License
Minimum : Project Manager /
Materials Engineer
Foreman
Foreman
NOTE : Attached Individual Resume and PRC License of the (professional) personnel.
Submitted by :
(Printed Name & Signature)
Designation :
Date :
One of the requirements from the bidder to be included in its Technical Envelope is a list of contractor’s key personnel (viz., Project Manager, Project Engineers, Materials Engineers, and Foremen), to be assigned to
the contract to be bid, with their complete qualification and experience data (including the key personnel’s signed written commitment to work for the project once awarded the contract).
Page 147
Batangas State University BatStateU Infra Form No. 11
Bidding Documents for Infrastructure Projects (Based on the Revised IRR of RA 9184,2016)
MANPOWER UTILIZATION SCHEDULE
Category Month
Contractor’s Name: Name of the Procuring Entity: Contract Name:
Submitted by:
Name of the Representative of the Bidder: Date:
Position:
Name of the Bidder:
The manpower schedule (weekly or monthly scheduling of skilled and unskilled workers, including Project Manager, Project Engineers, Materials Engineers, or Foremen) is required to be in the Technical Envelope of
the Bidder.
Page 148
Batangas State University BatStateU Infra Form No. 12
Bidding Documents for Infrastructure Projects (Based on Revised IRR of RA 9184, 2016)
List of Equipment, Owned or Leased and/or under Purchase Agreements, Pledged to the Proposed Contract
Business Name :
Business Address :
Description Model /
Year
Capacity /
Performance / Size
Plate No. Motor No. /
Body No.
Location Condition Proof of Ownership / Lessor or
Vendor
A. Owned
i.
ii.
iii.
iv.
v.
B. Leased
i.
ii.
iii.
iv.
v.
C. Under Purchase Agreements
i.
ii.
iii.
iv.
v.
List of minimum equipment required for the project:
Submitted by :
(Printed Name & Signature)
Designation :
Date :
One of the requirements from the bidder to be included in its Technical Envelope is the list of its equipment units pledged for the contract to be bid, which are owned (supported by proof/s of ownership), leased, and/or under purchase agreements (with corresponding engine numbers, chassis numbers and/or serial numbers), supported by certification of availability of equipment from the equipment lessor/vendor for the duration of the
project
Page 149
Batangas State University BatStateU Infra Form No.13
Bidding Documents for Infrastructure Projects (Based on Revised IRR of RA 9184, 2016)
Statement of Availability of Equipment
(Date of Issuance)
Name of the Head of the Procuring Entity
Name of the Procuring Entity
Address of the Procuring Entity
Attention : Prof. ENRICO M. DALANGIN
Chairman
Bids and Awards Committee
Dear Sir / Madame:
In compliance with the requirements of the Batangas State University-Bids and
Awards Committee for the bidding of the (Name of the Contract) , we certify that
(Name of the Bidder) owns, has under lease, and/or has under purchase
agreements the following equipment that may be used for the duration of the contract.
Attached is the list and proof of acquisition of the equipment needed in the execution
of the above-mentioned contract.
Very truly yours,
(Name of Representative)
(Position)
(Name of Bidder)
Page 150
Batangas State University BatStateU Infra Form No.14
Bidding Documents for Infrastructure Projects (Based on Revised IRR of RA 9184, 2016)
EQUIPMENT UTILIZATION SCHEDULE
Category / Equipment Month
Contractor’s Name: Name of the Procuring Entity: Contract Name:
Submitted by:
Name of the Representative of the Bidder Date:
Position
Name of the Bidder
One of the requirements from the bidder to be included in its Technical Envelope is its equipment utilization schedule, referring to the weekly or monthly scheduling of the minimum equipment required for the project.
Page 151
Batangas State University BatStateU Infra Form No.16
Bidding Documents for Infrastructure Projects (Based on Revised IRR of RA 9184, 2016)
Affidavit of Compliance to
Scope of Works & Specifications of Finishes and Materials
(Date of Issuance)
Prof. ENRICO M. DALANGIN
Chairperson
Bids and Awards Committee Batangas
State University
Dear Sir / Madame:
In compliance with the requirements of Batangas State University-Bids and Awards Committee
for the bidding of the (Name of the Contract) , we at (Name of Bidder), commit to comply
with the Scope of Works and Specifications of Finishes and Materials necessary in the
completion of the said contract.
Very truly yours,
(Name of Representative)
(Position)
(Name of Bidder)
SUBSCRIBED AND SWORN to before me this day of at
, Philippines. Affiant /s is / are personally known to me and was
/ were identified by me through competent evidence of identity as defined in the 2004 Rules on
Notarial Practice (A.M.) No. 02-8-13-SC). Affiant/s exhibited to me his / her [insert type of
government identification card used, with his / her photograph and signature appearing thereon,
with no. and his / her Community Tax Certificate No.
issued on at .
Witness my hand and seal this day of .
NAME OF NOTARIAL PUBLIC
Serial No. of Commission
Notary Public for until
Roll of Attorney’s No.
PTR No. , [date issued], [place issued]
IBP No. , [date issued], [place issued]
Doc. No.
Page No.
Book No.
Series of
Page 152
Batangas State University BatStateU Infra Form No.17
Bidding Documents for Infrastructure Projects (Based on Revised IRR of R.A. 9184, 2016)
REQUEST FOR CLARIFICATION
Date of Letter
Prof. ENRICO M. DALANGIN
BAC Chairperson
Batangas State University
Rizal Avenue, Batangas City
Tel. No.: (043) 980-0385 local 1549
Dear Sir:
In relation to the Section of Page of the Bidding Documents for (Name of the
Project), to wit:
“ (quote unclear provision) “
We appreciate it if you could provide further explanation or clarification on the above.
Thank you very much.
Very truly yours,
Name of the Representative of the Bidder
Name of the Bidder