PROCUREMENT ARRANGEMENT General For this project, procurement of goods, works and non-consulting services, and selection of consulting services will be carried out in accordance with the World Bank Procurement Regulations for IPF Borrowers, dated July 1, 2016. As required under the Procurement Regulations, the Trust Fund recipient will prepare a project procurement strategy for development (PPSD) to inform fit for purpose procurement arrangements in the procurement plan that will cover the 12 months’ duration of project implementation. The PPSD is under preparation and will be submitted and agreed with the Bank alongside the Procurement Plan prior to signing of the Trust Fund Agreement. The procurement section of the existing Operations Manual will be updated based on the new implementation arrangement, and to ensure compliance with the requirements of the Procurement Regulations. Capacity of the Trust Fund Recipient to do Procurement. CFSI will continue to act as the Trust Fund Recipient (TFR), which they have done for a series of TFs now under the Multi- Donor Trust Fund (MTF) Facility. They are familiar with the Bank’s Procurement policies and procedures, and have been implementing the project well. CFSI will receive training on the Procurement Regulations and on the application of STEP (Systematic Tracking of Exchanges in Procurement) on the project. In addition, CFSI need to ensure they maintain a Procurement Officer, who will act as the main person in-charge of procurement. Considering that the communities who will be implementing the sub-projects are not familiar with using structured procurement, and suppliers in the project areas are limited and may not agree to non-cash on delivery payments, all procurement activities will be centralized at the TFR level instead of each sub-project proponent doing their procurement, and suppliers will mainly deal with one entity and payment modalities can easily be agreed. This will simplify the procurement, and fast track delivery as well to the various sub-project sites. Procurement risk for the Project is “moderate”. Procurement Organization Responsibility and Organization. CFSI, as the TFR, will be responsible for all procurement activities under the project, both for the PMU needs and those under the community block grants. To handle the procurement process, CFSI will need to maintain a Procurement Officer and a Procurement Evaluation Committee (PEC) comprising of at least three (3) staff from the PMU and include representative from the BDA (Bangsamoro Development Agency) as voting member, and representatives from the beneficiary Camps as observers. Procurement Methods Procurement for the Project Management Office Procurement of Consulting Services: Implementation of the Program will require contracting by the PMU of a few specialized consulting firms and individuals to assist in project implementation. Procurement methods to be used will be in accordance with the methods allowed for in the Procurement Regulations. Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized
12

procurement arrangement - World Bank Documents

Apr 20, 2023

Download

Documents

Khang Minh
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: procurement arrangement - World Bank Documents

PROCUREMENT ARRANGEMENT

General

For this project, procurement of goods, works and non-consulting services, and selection of consulting services will be carried out in accordance with the World Bank Procurement Regulations for IPF Borrowers, dated July 1, 2016. As required under the Procurement Regulations, the Trust Fund recipient will prepare a project procurement strategy for development (PPSD) to inform fit for purpose procurement arrangements in the procurement plan that will cover the 12 months’ duration of project implementation. The PPSD is under preparation and will be submitted and agreed with the Bank alongside the Procurement Plan prior to signing of the Trust Fund Agreement. The procurement section of the existing Operations Manual will be updated based on the new implementation arrangement, and to ensure compliance with the requirements of the Procurement Regulations.

Capacity of the Trust Fund Recipient to do Procurement. CFSI will continue to act as the Trust Fund Recipient (TFR), which they have done for a series of TFs now under the Multi-Donor Trust Fund (MTF) Facility. They are familiar with the Bank’s Procurement policies and procedures, and have been implementing the project well. CFSI will receive training on the Procurement Regulations and on the application of STEP (Systematic Tracking of Exchanges in Procurement) on the project. In addition, CFSI need to ensure they maintain a Procurement Officer, who will act as the main person in-charge of procurement.

Considering that the communities who will be implementing the sub-projects are not familiar with using structured procurement, and suppliers in the project areas are limited and may not agree to non-cash on delivery payments, all procurement activities will be centralized at the TFR level instead of each sub-project proponent doing their procurement, and suppliers will mainly deal with one entity and payment modalities can easily be agreed. This will simplify the procurement, and fast track delivery as well to the various sub-project sites. Procurement risk for the Project is “moderate”.

Procurement Organization

Responsibility and Organization. CFSI, as the TFR, will be responsible for all procurement activities under the project, both for the PMU needs and those under the community block grants. To handle the procurement process, CFSI will need to maintain a Procurement Officer and a Procurement Evaluation Committee (PEC) comprising of at least three (3) staff from the PMU and include representative from the BDA (Bangsamoro Development Agency) as voting member, and representatives from the beneficiary Camps as observers.

Procurement Methods

Procurement for the Project Management Office

Procurement of Consulting Services: Implementation of the Program will require contracting by the PMU of a few specialized consulting firms and individuals to assist in project implementation. Procurement methods to be used will be in accordance with the methods allowed for in the Procurement Regulations.

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Page 2: procurement arrangement - World Bank Documents

Procurement of Goods. Goods to be procured for use by the PMU involves primarily office and communication equipment, and these can be done either through Request for Bids or Request for Quotations, as may be appropriate. Detailed procedures will be in accordance with the Procurement Regulations.

Procurement for the Community Block Grants

The term “community” is used here for the barangays, community groups and Municipalities that are potential recipients of block grant funding for approved sub-projects. The preparation of the sub-projects to be funded through the block grants will be the responsibility of the community organizations, and implementation of the sub-projects could either be through Force Account (wherein the community does the construction themselves) or through hiring of a contractor (wherein they do the construction for the community). These two modalities will be discussed in detail in the Operations Manual. Procurement will be for the ffg:

• Goods refer to construction materials delivered, tools and equipment, office supplies, etc.;

• Services refer to technical assistance, training, or trucking and hauling; and• Works refers to the construction of an entire facility under a single contract or

portions of the facility under several contracts.

As project implementation is only for one (1) year, it is critical that procurement at the Community level be successful at all times, and started immediately after sub-projects are approved. Each of the beneficiary sites or Camps may have several sub-projects which they themselves would implement, and it could be that CFSI, since they will be responsible for procurement, could group requirements from several sub-projects within a Camp, procure them, then distribute amongst the sub-projects. This will facilitate the procurement process and contract cost may turn out to be lower as procurement is done through bulk. On the other hand, for sub-projects that are complex in nature and may require technical expertise during construction, CFSI would hire local contractors to do the works for the community. Procurement methods in both cases could be: request for bids, request for quotations and direct selection.

Frequency of Procurement Supervision, and Review Requirements

Prior review supervision will be carried out from Bank office, and two per year supervision missions to visit the field to carry out post review of procurement actions will be undertaken.The Bank will carry out prior reviews of procurement activities that are of high value and/or high risk to determine whether the procurement is carried out in accordance with the requirements of the Legal Agreement. Other contracts not specified for prior review, will be post reviewed by the Bank to determine whether they comply with the requirements of the Legal Agreement. The Bank may use a third party to carry out post reviews; and any such third party shall carry out the reviews in accordance with the terms of reference provided to it by the Bank. The Procurement Plan will indicate which contracts will go through either prior or post review process.

As the PPSD is still under preparation, the proposed procurement arrangements may require an update once the final PPSD has been agreed between the TFR and the Bank.

Page 3: procurement arrangement - World Bank Documents

Page 1

PROCUREMENT

PLANPhilippines : Mindanao Trust Fund-Reconstruction and Development Project Phase II

General Information

Country: Philippines Bank’s Approval Date of the Original Procurement Plan: 2019-02-01

Revised Plan Date(s): (comma delineated, leave blank if none)2020-04-03

Project ID: P164019 GPN Date:

Project Name: Mindanao Trust Fund-Reconstruction and Development Project Phase II

Loan / Credit No: TF / A7280, TF / B0821

Executing Agency(ies):Community and Family Services International

WORKS

Activity Reference No. /

DescriptionLoan / Credit

No.Component Review Type Method

Market

Approach

Procurement

Process

Prequalification

(Y/N)

Estimated

Amount (US$)

Actual Amount

(US$)

Process

Status

Draft Pre-qualification

Documents

Prequalification

Evaluation Report

Draft Bidding

Document /

Justification

Specific Procurement

Notice / Invitation

Bidding Documents

as Issued

Proposal Submission /

Opening / Minutes

Bid Evaluation

Report and

Recommendation for

Award

Signed Contract Contract Completion

Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual

CBA-SEI-01 / Construction

of 1.45KM One Lane

Concrete Road

TF / A7280Community Development

AssistancePost Request for Bids Open - National

Single Stage - One

Envelope140,000.00 269,294.19 Completed 2018-08-18 2018-08-15 2018-08-22 2018-09-11 2018-09-12 2018-10-10 2018-09-17 2018-10-24 2018-10-04 2019-01-20 2019-08-02

COM-SEI-01 / Construction

of 1.13KM One Lane

Concrete Road

TF / A7280Community Development

AssistancePost Request for Bids Open - National

Single Stage - One

Envelope140,000.00 268,956.28 Completed 2018-08-16 2018-08-20 2018-08-22 2018-09-11 2018-09-11 2018-10-12 2018-09-14 2018-10-24 2018-10-04 2019-02-08 2019-08-22

CRA-SEI-01 / Construction

of 2 Units Solar-Powered

Water System, L2

TF / A7280Community Development

AssistancePost Request for Bids Open - National

Single Stage - One

Envelope140,000.00 122,282.38 Completed 2018-08-18 2018-08-20 2018-08-22 2018-09-11 2018-09-11 2018-10-10 2018-09-14 2018-10-24 2018-10-04 2019-01-31 2019-08-18

CBI-SEI-01 / Construction

of 1.0KM Concrete Pathway

TF / A7280Community Development

AssistancePost Request for Bids Open - National

Single Stage - One

Envelope140,000.00 123,966.04 Completed 2018-08-18 2018-08-15 2018-08-27 2018-09-11 2018-09-11 2018-10-10 2018-10-15 2018-10-24 2018-11-08 2019-01-31 2019-08-09

CAB-SEI-01 / Construction

of 1.5KM One Lane

Concrete Road

TF / A7280Community Development

AssistancePost Request for Bids Open - National

Single Stage - One

Envelope140,000.00 235,198.75 Completed 2018-08-18 2018-08-18 2018-08-22 2018-09-11 2018-09-11 2018-10-11 2018-09-14 2018-10-24 2018-11-15 2019-02-10 2019-08-09

CBA-CDD-01 / Construction

of Five(5) Solar Drier

TF / A7280Community Development

AssistancePost Request for Bids Open - National

Single Stage - One

Envelope30,000.00 54,338.23 Completed 2018-09-15 2018-09-15 2018-09-18 2018-10-08 2018-10-08 2018-10-09 2018-10-09 2018-11-19 2018-11-15 2019-02-25 2019-02-18

CBA-CDD-02 / Construction

of Water System L2

TF / A7280Community Development

AssistancePost Request for Bids Open - National

Single Stage - One

Envelope30,000.00 25,456.84 Completed 2018-09-15 2018-09-15 2018-09-18 2018-10-08 2018-10-08 2018-10-09 2018-10-12 2018-11-19 2018-11-15 2019-02-25 2019-02-03

CRA-CDD-01 / Construction

of Solar Powered Water

System L2

TF / A7280Community Development

AssistancePost Request for Bids Open - National

Single Stage - One

Envelope30,000.00 25,356.68 Completed 2018-09-15 2018-09-15 2018-09-18 2018-10-08 2018-10-08 2018-10-09 2018-10-12 2018-11-19 2018-11-15 2019-02-25 2019-07-15

CRA-CDD-02 / Construction

of Solar Powered Water

System L2

TF / A7280Community Development

AssistancePost Request for Bids Open - National

Single Stage - One

Envelope30,000.00 23,248.40 Completed 2018-09-15 2018-09-15 2018-09-18 2018-10-08 2018-10-08 2018-10-09 2018-10-12 2018-11-19 2018-11-15 2019-02-25 2019-07-15

COM-CDD-02 / Construction

of Warehouse and Solar

Dryer

TF / A7280Community Development

AssistancePost Request for Bids Open - National

Single Stage - One

Envelope30,000.00 27,619.83 Completed 2018-09-15 2018-09-15 2018-09-18 2018-10-08 2018-10-08 2018-10-09 2018-10-12 2018-11-19 2018-11-21 2019-02-25 2019-03-22

CBI-CDD-02 / Construction

of Concrete Tire Path

TF / A7280Community Development

AssistancePost Request for Bids Open - National

Single Stage - One

Envelope30,000.00 60,002.13 Completed 2018-09-15 2018-09-15 2018-09-18 2018-10-08 2018-10-09 2018-10-09 2018-10-12 2018-11-19 2018-11-12 2019-02-25 2019-04-27

CBU-CDD-02 / Construction

of Water System L2

TF / A7280Community Development

AssistancePost Request for Bids Open - National

Single Stage - One

Envelope30,000.00 27,596.31 Completed 2018-09-15 2018-09-15 2018-09-18 2018-10-08 2018-10-09 2018-10-09 2018-10-12 2018-11-19 2018-11-12 2019-02-25 2019-07-30

CAB-CDD-01 / Construction

of Water System L2

TF / A7280Community Development

AssistancePost Request for Bids Open - National

Single Stage - One

Envelope30,000.00 54,852.83 Completed 2018-09-15 2018-09-15 2018-09-18 2018-10-08 2018-10-08 2018-10-09 2018-10-12 2018-11-19 2018-10-15 2019-02-25 2019-08-13

Page 4: procurement arrangement - World Bank Documents

Page 2

CAB-CDD-02 / Construction

of Water System L2

TF / A7280Community Development

AssistancePost Request for Bids Open - National

Single Stage - One

Envelope30,000.00 53,860.67 Completed 2018-09-15 2018-09-15 2018-09-18 2018-10-08 2018-10-08 2018-10-09 2018-10-12 2018-11-19 2018-11-21 2019-02-25 2019-08-21

CBI-CDD-01 / Construction

of Warehouse with Solar

Dryer

TF / A7280Community Development

AssistancePost Request for Bids Open - National

Single Stage - One

Envelope30,000.00 28,112.72 Completed 2018-09-15 2018-09-15 2018-09-18 2018-10-08 2018-10-09 2018-10-09 2018-10-12 2018-11-18 2018-11-21 2019-02-18 2019-05-27

CBU-CDD-01 / Construction

of Water System L2

TF / A7280Community Development

AssistancePost Request for Bids Open - National

Single Stage - One

Envelope30,000.00 53,352.51 Completed 2018-09-15 2018-09-15 2018-09-18 2018-10-08 2018-10-09 2018-10-09 2018-10-12 2018-11-19 2018-11-21 2019-02-25 2019-07-30

CBI-SEI-01-L2 /

Construction of 1.0KM

Concrete Pathway ( RE BID)

TF / A7280Community Development

AssistancePost Request for Bids Open - National

Single Stage - One

Envelope140,000.00 122,480.60 Completed 2018-08-18 2018-09-15 2018-08-23 2018-10-04 2018-10-08 2018-11-03 2018-10-12 2018-12-08 2018-11-19 2019-06-06 2019-08-09

CBU- SEI-01 / Construction

of Hanging Bridge with

Concrete 200-M Pathway

TF / A7280Community Development

AssistancePost Request for Bids Open - National

Single Stage - One

Envelope140,000.00 125,167.52 Signed 2018-09-15 2018-09-15 2018-09-15 2018-10-08 2018-10-09 2018-10-09 2018-10-12 2018-11-18 2018-11-15 2019-02-28

COM-CDD-01 / Construction

of Water System L2 (RE

BID)

TF / A7280Community Development

AssistancePost Request for Bids Open - National

Single Stage - One

Envelope30,000.00 26,654.39 Completed 2018-09-15 2018-09-15 2018-09-18 2018-10-08 2018-10-08 2018-10-09 2018-10-15 2018-11-18 2018-11-15 2019-02-28 2019-02-16

CBI-CDD-01-L3 /

Construction of Warehouse

with Solar Dryer- RE BID

TF / A7280Capacity and Institution-

BuildingPost Request for Bids Open - National

Single Stage - One

Envelope30,000.00 28,499.01 Completed 2018-10-13 2018-10-18 2018-10-15 2018-11-05 2018-11-05 2018-11-07 2018-11-09 2018-11-23 2018-11-21 2019-02-26 2019-05-27

CAB-SEI-03 / Construction

of One-lane Concrete Road @

Nabalawag, Barira,

Maguindanao

TF / B0821Community Development

AssistancePost Request for Bids Open - National

Single Stage - One

Envelope105,000.00 0.00

Pending

Implementati

on

2020-04-10 2020-04-15 2020-04-24 2020-04-26 2020-05-06 2020-09-15

CBA-SEI-03 / Construction

of Concrete Road at

Sifaran, DOS, Maguindanao

TF / B0821Community Development

AssistancePost Request for Bids Open - National

Single Stage - One

Envelope105,000.00 0.00

Pending

Implementati

on

2020-04-10 2020-04-12 2020-04-24 2020-04-26 2020-05-10 2020-09-15

CBI-SEI-03 / Construction

of Farmers muti-purpose

Training Center with

Quarter @ Kura-kura,

Tamparan, Munai, LDN

TF / B0821Community Development

AssistancePost Request for Bids Open - National

Single Stage - One

Envelope105,000.00 0.00

Pending

Implementati

on

2020-04-10 2020-04-12 2020-04-24 2020-04-26 2020-05-10 2020-09-15

CRA-SEI-03 / Construction

of Solar Powered Water

System Level II @ Palao sa

Buto, Datu Paglas,

Maguindanao

TF / B0821Community Development

AssistancePost Request for Bids Open - National

Single Stage - One

Envelope52,500.00 0.00

Pending

Implementati

on

2020-03-20 2020-04-03 2020-04-03 2020-04-06 2020-06-07 2020-09-15

CRA-SEI-04 / Construction

ofSolar Powered Water

System Level 2 @

Darussalam, Inug-ug, Pikit,

North Cotabato

TF / B0821Community Development

AssistancePost Request for Bids Open - National

Single Stage - One

Envelope52,500.00 0.00

Pending

Implementati

on

2020-04-10 2020-04-12 2020-04-24 2020-04-26 2020-05-10 2020-09-15

COM-SEI-04 / Construction

of Agri- Facility building

with Solar Dryer and

provision of Corn Sheller @

Talibadok, Datu Hoffer,

Maguindanao

TF / B0821Community Development

AssistancePost Request for Bids Open - National

Single Stage - One

Envelope52,500.00 0.00

Pending

Implementati

on

2020-03-09 2020-03-13 2020-03-27 2020-03-31 2020-04-10 2020-09-15

COM-SEI-03 / Construction

of Agri- Facility building

with Solar Dryer and

provision of Corn Sheller @

Leonin, Saniag, Maguindanao

TF / B0821Community Development

AssistancePost Request for Bids Open - National

Single Stage - One

Envelope52,500.00 0.00

Pending

Implementati

on

2020-04-10 2020-04-15 2020-05-27 2020-06-26 2020-07-31 2021-01-27

Page 5: procurement arrangement - World Bank Documents

Page 3

CBU-SEI-04 / Construction

of Agri-Facility Building with

Solar Dryer & Provision of

rice Miller@ Purok 4 Brgy.

Sandab Butig, Lanao del

Sur

TF / B0821Community Development

AssistancePost Request for Bids Open - National

Single Stage - One

Envelope52,500.00 0.00

Pending

Implementati

on

2020-05-04 2020-05-05 2020-05-22 2020-05-24 2020-06-05 2020-09-11

CBU-SEI-03 / Construction

of Capacity Building Center

(2-storey) at Palestine,

Sandab, Butig, LDS

TF / B0821Community Development

AssistancePost Request for Bids Open - National

Single Stage - One

Envelope52,500.00 0.00

Pending

Implementati

on

2020-04-25 2020-04-26 2020-05-12 2020-05-13 2020-05-29 2020-09-15

GOODS

Activity Reference No. /

DescriptionLoan / Credit

No.Component Review Type Method

Market

Approach

Procurement

Process

Prequalification

(Y/N)

Estimated

Amount (US$)

Actual Amount

(US$)

Process

Status

Draft Pre-qualification

Documents

Prequalification

Evaluation Report

Draft Bidding

Document /

Justification

Specific Procurement

Notice / Invitation

Bidding Documents

as Issued

Proposal Submission /

Opening / Minutes

Bid Evaluation

Report and

Recommendation for

Award

Signed Contract Contract Completion

Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual

PMU-GO-01 / Purchase of

External Hard Drive 2T

TF / A7280Project Administration,

Monitoring & EvaluationPost

Request for

QuotationsOpen - National

Single Stage - One

Envelope372.00 359.30 Completed 2018-06-11 2018-07-31 2018-08-08 2018-08-10 2018-08-24

PMU-GO-02 / Purchase of

Wireless Mouse

TF / A7280Project Administration,

Monitoring & EvaluationPost

Request for

QuotationsOpen - National

Single Stage - One

Envelope64.00 61.81 Completed 2018-06-11 2018-07-31 2018-08-08 2018-08-10 2018-08-24

PMU-GO-04 / Purchase of

Laptop of HX

TF / A7280Project Administration,

Monitoring & EvaluationPost

Request for

QuotationsOpen - National

Single Stage - One

Envelope949.00 917.33 Completed 2018-06-06 2018-08-01 2018-06-26 2019-01-28 2018-07-16

PMU-GO-05 / Purchase of

Printers 5 units

TF / A7280Project Administration,

Monitoring & EvaluationPost

Request for

QuotationsOpen - National

Single Stage - One

Envelope1,800.00 1,498.28 Completed 2018-07-16 2018-09-26 2018-09-04 2018-10-16 2018-10-02

PMU-GO-06 / Purchase of

Laptop 6 units Capable of

Graphics & Autocadd

TF / A7280Project Administration,

Monitoring & EvaluationPost

Request for

QuotationsOpen - National

Single Stage - One

Envelope6,000.00 3,416.08 Completed 2018-07-11 2018-08-29 2018-09-04 2018-09-08 2018-10-01

BDA-GO-02 / Purchase of

Multi Function Printers

TF / A7280Project Administration,

Monitoring & EvaluationPost

Request for

QuotationsOpen - National

Single Stage - One

Envelope2,210.00 2,783.90 Completed 2018-08-12 2018-10-01 2018-08-10 2018-10-11 2018-09-03

BDA-GO-03 / Procurement

of Laptop

TF / A7280Project Administration,

Monitoring & EvaluationPost

Request for

QuotationsOpen - National

Single Stage - One

Envelope2,880.00 2,136.26 Completed 2018-08-12 2018-10-01 2018-08-10 2018-10-11 2018-08-31

BDA-GO-01 / Purchase of

Motorcycles for Camp

JTFCTs

TF / A7280Community Development

AssistancePost

Request for

QuotationsOpen - National

Single Stage - One

Envelope10,836.00 10,441.72 Completed 2018-07-12 2018-07-17 2018-07-31 2018-08-21 2018-08-31

PMU-GO-07 / Procurement

of Photo Copier

TF / A7280Project Administration,

Monitoring & EvaluationPost

Request for

QuotationsOpen - National

Single Stage - One

Envelope876.00 840.58 Completed 2018-07-06 2018-07-19 2018-08-08 2018-07-24 2018-08-10

NON CONSULTING SERVICES

Activity Reference No. /

DescriptionLoan / Credit

No.Component Review Type Method

Market

Approach

Procurement

Process

Prequalification

(Y/N)

Estimated

Amount (US$)

Actual Amount

(US$)

Process

Status

Draft Pre-qualification

Documents

Prequalification

Evaluation Report

Draft Bidding

Document /

Justification

Specific Procurement

Notice / Invitation

Bidding Documents

as Issued

Proposal Submission /

Opening / Minutes

Bid Evaluation

Report and

Recommendation for

Award

Signed Contract Contract Completion

Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual

CONSULTING FIRMSActivity Reference No. /

DescriptionLoan / Credit

No.Component Review Type Method

Market

Approach

Contract Type Estimated

Amount (US$)

Actual

Amount (US$)Process Status Terms of Reference

Expression of Interest

Notice

Short List and Draft

Request for Proposals

Request for Proposals

as Issued

Opening of Technical

Proposals / Minutes

Evaluation of

Technical Proposal

Combined Evaluation

Report and Draft

Negotiated Contract

Signed Contract Contract Completion

Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual

Page 6: procurement arrangement - World Bank Documents

Page 4

INDIVIDUAL CONSULTANTSActivity Reference No. /

DescriptionLoan / Credit

No.Component Review Type Method

Market

Approach

Contract Type Estimated

Amount (US$)

Actual

Amount (US$)Process Status Terms of Reference

Invitation to

Identified/Selected

Consultant

Draft Negotiated

ContractSigned Contract Contract Completion

Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual

MTF-CFSI-01 / Catubay Jr.,

Mario, Social Development

Officer

TF / A7280Project Administration,

Monitoring & EvaluationPost

Individual

Consultant

Selection

Open

12,671.66 17,229.03 Completed 2018-11-13 2018-05-09 2018-11-16 2018-04-30 2018-11-17 2018-04-30 2018-11-19 2018-05-09 2019-02-28 2019-08-31

MTF-CFSI-03 / Ibrahim,

Tohami, Community

Development Specialist

TF / A7280Project Administration,

Monitoring & EvaluationPost

Individual

Consultant

Selection

Open

6,384.00 10,397.04 Completed 2018-11-13 2018-07-06 2018-11-16 2018-07-06 2018-11-17 2018-06-25 2018-11-19 2018-07-06 2019-02-28 2019-08-31

MTF-CFSI-04 / Ison, Edita,

Finance Officer

TF / A7280Project Administration,

Monitoring & EvaluationPost Direct Selection Direct

12,671.68 8,326.68 Completed 2018-11-13 2018-08-08 2018-11-15 2018-04-15 2018-11-18 2018-05-01 2019-02-28 2019-08-31

MTF-CFSI-05 / Juanday,

Junhora, Finance Officer

TF / A7280Project Administration,

Monitoring & EvaluationPost Direct Selection Direct

7,795.92 670.74 Completed 2018-11-13 2018-06-25 2018-11-15 2018-06-01 2018-11-18 2018-06-26 2019-02-27 2018-09-28

MTF-CFSI-06 / Kamid

Usman, Project Engineer

TF / A7280Project Administration,

Monitoring & EvaluationPost

Individual

Consultant

Selection

Open

13,305.26 25,241.63 Completed 2018-11-13 2018-04-30 2018-11-16 2018-03-03 2018-11-17 2018-04-23 2018-11-19 2018-04-30 2019-02-28 2019-08-31

MTF-CFSI-08 / Mangcaan,

Farida, Community

Development Officer

TF / A7280Project Administration,

Monitoring & EvaluationPost Direct Selection Direct

12,655.50 4,675.12 Completed 2018-11-13 2018-05-01 2018-11-15 2018-04-15 2018-11-18 2018-05-01 2019-02-28 2018-07-28

MTF-CFSI-09 / Mariano,

Jessmin, Programme Officer

TF / A7280Project Administration,

Monitoring & EvaluationPost Direct Selection Direct

12,671.68 20,055.34 Completed 2018-11-13 2018-05-01 2018-11-15 2018-04-16 2018-11-18 2018-05-01 2019-02-28 2019-08-31

MTF-CFSI-11 / Tuya,

Abedin, Community

Development Specialist

TF / A7280Project Administration,

Monitoring & EvaluationPost

Individual

Consultant

Selection

Open

6,424.00 11,575.78 Completed 2018-11-13 2018-07-04 2018-11-16 2018-05-19 2018-11-17 2018-05-28 2018-11-19 2018-07-04 2019-02-28 2019-06-30

MTF-CFSI-12 / Pequit,

Emmaleeh, Monitoring and

Evaluation Officer

TF / A7280Project Administration,

Monitoring & EvaluationPost

Individual

Consultant

Selection

Open

11,505.00 17,687.09 Completed 2018-11-13 2018-05-05 2018-11-16 2018-11-17 2018-11-17 2018-04-23 2018-11-19 2018-05-02 2019-02-28 2019-05-10

MTF-CFSI-13 / Quesada,

Schearazmiah, Procurement

Officer

TF / A7280Project Administration,

Monitoring & EvaluationPost

Individual

Consultant

Selection

Open

12,080.26 7,695.04 Completed 2018-11-13 2018-04-23 2018-11-16 2018-03-03 2018-11-17 2018-04-16 2018-11-19 2018-04-23 2019-02-28 2019-08-31

MTF-CFSI-14 / Sali,

Abibazar, Project Engineer

TF / A7280Project Administration,

Monitoring & EvaluationPost

Individual

Consultant

Selection

Open

12,671.60 25,241.62 Completed 2018-11-13 2018-05-02 2018-11-16 2018-04-01 2018-11-17 2018-04-23 2018-11-19 2018-05-02 2019-02-28 2019-08-31

MTF-CFSI-16 / Sevillano,

Jude, Administrative Officer

TF / A7280Project Administration,

Monitoring & EvaluationPost Direct Selection Direct

9,826.66 15,089.75 Completed 2018-11-13 2018-04-01 2018-11-15 2018-03-15 2018-11-18 2018-04-01 2019-02-27 2019-08-31

MTF-CFSI-17 / Siago,

Basila, Capacity Building

Specialist

TF / A7280Project Administration,

Monitoring & EvaluationPost

Individual

Consultant

Selection

Open

11,505.00 13,282.22 Completed 2018-11-13 2018-05-02 2018-11-16 2018-03-03 2018-11-17 2018-04-23 2018-11-19 2018-05-02 2019-02-28 2019-02-28

MTF-CFSI-18 / Sinarimbo,

Nasser, Project Coordinator

TF / A7280Project Administration,

Monitoring & EvaluationPost Direct Selection Direct

34,838.20 7,217.20 Completed 2018-11-13 2018-04-23 2018-11-15 2018-04-23 2018-11-18 2018-05-01 2019-02-27 2019-08-31

MTF-BDA-02 / Abdullah,

Nor-ain, Accounting Officer

TF / A7280Capacity and Institution-

BuildingPost

Individual

Consultant

Selection

Open

9,052.78 10,393.99 Completed 2018-11-13 2018-02-22 2018-11-16 2018-04-01 2018-11-17 2018-05-02 2018-11-19 2018-05-03 2019-02-28 2019-08-31

MTF-BDA-03 / Abdulrasid,

Badrodin K., Community

Organizer

TF / A7280Capacity and Institution-

BuildingPost Direct Selection Direct

6,461.71 576.31 Completed 2018-11-13 2018-02-22 2018-11-15 2018-04-02 2018-11-18 2018-05-03 2019-02-28 2019-06-30

Page 7: procurement arrangement - World Bank Documents

Page 5

MTF-BDA-04 / Accoy,

Bassit, Rural Infrastructure

Engineer I

TF / A7280Capacity and Institution-

BuildingPost

Individual

Consultant

Selection

Open

6,977.91 8,167.25 Completed 2018-11-13 2018-02-22 2018-11-16 2018-04-01 2018-11-17 2018-03-12 2018-11-19 2018-05-02 2019-02-28 2019-06-30

MTF-BDA-08 / Alauya,

Sailanie, Community

Development Officer

TF / A7280Capacity and Institution-

BuildingPost Direct Selection Direct

8,039.49 10,058.84 Completed 2018-11-13 2018-02-22 2018-11-15 2018-04-01 2018-11-18 2018-05-03 2019-02-28 2019-08-31

MTF-BDA-10 / Alon,

Mohammad Saud A., Rural

Infrastructure Engineer II

TF / A7280Capacity and Institution-

BuildingPost Direct Selection Direct

8,039.49 10,059.61 Completed 2018-11-13 2018-02-22 2018-11-15 2018-03-25 2018-11-18 2018-04-10 2019-02-28 2019-08-31

MTF-BDA-12 / Alon,

Tonton, Rural Infrastructure

Engineer I

TF / A7280Capacity and Institution-

BuildingPost

Individual

Consultant

Selection

Open

6,977.91 8,854.18 Completed 2018-11-13 2018-02-22 2018-11-16 2018-04-01 2018-11-17 2018-05-02 2018-11-19 2018-05-03 2019-02-28 2019-06-30

MTF-BDA-13 / Ambil,

Abdulrasheed, Community

Development Officer

TF / A7280Capacity and Institution-

BuildingPost Direct Selection Direct

8,039.49 10,058.84 Completed 2018-11-13 2018-05-02 2018-11-15 2018-04-01 2018-11-18 2018-05-03 2019-02-27 2019-08-31

MTF-BDA-14 / Ambil, Arift,

Community Organizer

TF / A7280Capacity and Institution-

BuildingPost Direct Selection Direct

6,461.71 7,349.78 Completed 2018-11-13 2018-02-22 2018-11-15 2018-04-01 2018-11-18 2018-05-03 2019-02-28 2019-06-30

MTF-BDA-15 / Amerol,

Halil, Community

Development Officer

TF / A7280Capacity and Institution-

BuildingPost Direct Selection Direct

8,039.49 10,058.84 Completed 2018-11-13 2018-02-22 2018-11-15 2018-04-01 2018-11-18 2018-05-03 2019-02-28 2019-08-31

MTF-BDA-17 / Batuampar,

Cosain, Rural Infrastructure

Engineer II

TF / A7280Capacity and Institution-

BuildingPost Direct Selection Direct

8,039.49 10,058.84 Completed 2018-11-13 2018-02-22 2018-11-15 2018-04-01 2018-11-18 2018-05-03 2019-02-27 2019-08-31

MTF-BDA-18 / Cabalo,

Anuar, Community Organizer

TF / A7280Capacity and Institution-

BuildingPost Direct Selection Direct

6,461.71 7,349.78 Completed 2018-11-13 2018-02-22 2018-11-15 2018-04-01 2018-11-18 2018-05-03 2019-02-28 2019-06-30

MTF-BDA-19 / Cadon,

Julhaina, Finance Officer

TF / A7280Capacity and Institution-

BuildingPost Direct Selection Direct

10,274.88 12,086.26 Completed 2018-11-13 2018-02-22 2018-11-15 2018-03-26 2018-11-18 2018-05-03 2019-02-28 2019-08-31

MTF-BDA-21 / Danda,

Almira, Budget Officer

TF / A7280Capacity and Institution-

BuildingPost Direct Selection Direct

7,808.46 9,185.03 Completed 2018-11-13 2018-02-22 2018-11-15 2018-03-16 2018-11-18 2018-05-03 2019-02-28 2019-08-31

MTF-BDA-23 / Diahing,

Raida Mohamad, Rural

Infrastructure Engineer

TF / A7280Capacity and Institution-

BuildingPost

Individual

Consultant

Selection

Open

6,977.91 685.96 Completed 2018-11-13 2018-02-22 2018-11-16 2018-03-12 2018-11-17 2018-05-02 2018-11-19 2018-05-03 2019-02-28 2019-06-30

MTF-BDA-24 / Diangcalan,

Windel P., Deputy Executive

Director/Internal OPMC

TF / A7280Capacity and Institution-

BuildingPost Direct Selection Direct

11,497.20 13,524.07 Completed 2018-11-13 2018-02-22 2018-11-15 2018-03-25 2018-11-18 2018-05-03 2019-02-28 2019-08-31

MTF-BDA-25 / Dilabayan,

Abdulcader R. Community

Organize

TF / A7280Capacity and Institution-

BuildingPost Direct Selection Direct

6,461.71 7,453.80 Completed 2018-11-13 2018-02-22 2018-11-15 2018-04-01 2018-11-18 2018-05-03 2019-02-28 2019-06-30

MTF-BDA-26 / Dilanggalen,

Daud, Rural Infrastructure

Engineer I

TF / A7280Capacity and Institution-

BuildingPost

Individual

Consultant

Selection

Open

6,977.91 8,818.54 Completed 2018-11-13 2018-02-22 2018-11-16 2018-04-01 2018-11-17 2018-05-03 2018-11-19 2018-05-03 2019-02-28 2019-04-30

MTF-BDA-27 / Domagay,

Jamil, Rural Infrastructure

Engineer I

TF / A7280Capacity and Institution-

BuildingPost

Individual

Consultant

Selection

Open

6,977.91 8,854.18 Completed 2018-11-13 2018-02-22 2018-11-16 2018-04-01 2018-11-17 2018-05-02 2018-11-19 2018-05-03 2019-02-28 2019-04-30

MTF-BDA-28 / Dumadalog,

Bashet, Financial Database

Officer

TF / A7280Capacity and Institution-

BuildingPost

Individual

Consultant

Selection

Open

7,808.46 8,965.32 Completed 2018-11-13 2018-02-22 2018-11-16 2018-04-01 2018-11-17 2018-05-02 2018-11-19 2018-05-03 2019-02-28 2019-08-31

Page 8: procurement arrangement - World Bank Documents

Page 6

MTF-BDA-29 / Edza,

Marbawi, Monitoring and

Evaluation Officer

TF / A7280Capacity and Institution-

BuildingPost Direct Selection Direct

7,808.46 8,920.25 Completed 2018-11-13 2018-02-22 2018-11-15 2018-04-01 2018-11-18 2018-05-03 2019-02-28 2019-08-31

MTF-BDA-30 / Edza, Mar-

uf Monitoring and

Evaluation Officer

TF / A7280Capacity and Institution-

BuildingPost

Individual

Consultant

Selection

Open

7,808.46 8,965.32 Completed 2018-11-13 2018-02-22 2018-11-16 2018-04-01 2018-11-17 2018-05-02 2018-11-19 2018-05-03 2019-02-28 2019-08-31

MTF-BDA-33 / Guiamel,

Mohammadali, Internal

Control Officer

TF / A7280Capacity and Institution-

BuildingPost

Individual

Consultant

Selection

Open

7,808.46 9,007.50 Completed 2018-11-13 2018-02-22 2018-11-16 2018-04-01 2018-11-17 2018-05-02 2018-11-19 2018-05-03 2019-02-28 2019-08-31

MTF-BDA-34 / Hadjinor,

Alimodin, Community

Development Officer

TF / A7280Capacity and Institution-

BuildingPost Direct Selection Direct

8,039.49 10,017.19 Completed 2018-11-13 2018-02-22 2018-11-15 2018-04-01 2018-11-18 2018-05-03 2019-02-28 2019-08-31

MTF-BDA-35 / Hassan,

Rahima, Monitoring and

Evaluation Officer

TF / A7280Capacity and Institution-

BuildingPost Direct Selection Direct

7,808.46 8,844.85 Completed 2018-11-13 2018-02-22 2018-11-15 2018-04-01 2018-11-18 2018-05-03 2019-02-28 2019-08-31

MTF-BDA-36 / Ibrahim,

Mohammad Sajud, Rural

Infrastructure Engineer I

TF / A7280Capacity and Institution-

BuildingPost

Individual

Consultant

Selection

Open

6,977.91 8,818.54 Completed 2018-11-14 2018-02-22 2018-11-17 2018-04-01 2018-11-18 2018-05-02 2018-11-20 2018-05-03 2019-02-28 2019-06-30

MTF-BDA-38 / Kali, Amil,

Rural Infrastructure

Engineer II

TF / A7280Capacity and Institution-

BuildingPost Direct Selection Direct

8,039.49 10,017.19 Completed 2018-11-13 2018-02-22 2018-11-15 2018-04-01 2018-11-18 2018-05-03 2019-02-28 2019-07-31

MTF-BDA-39 / Kararon,

Tawab Community

Development Officer

TF / A7280Capacity and Institution-

BuildingPost Direct Selection Direct

8,039.49 10,017.19 Completed 2018-11-13 2018-02-22 2018-11-15 2018-04-01 2018-11-18 2018-05-03 2019-02-28 2019-08-31

MTF-BDA-41 / Labay,

Rahib A.Planning Officer

TF / A7280Capacity and Institution-

BuildingPost Direct Selection Direct

10,274.88 12,082.56 Completed 2018-11-13 2018-02-22 2018-11-15 2018-04-01 2018-11-18 2018-05-03 2019-02-28 2019-08-31

MTF-BDA-42 / Lakman,

Salongga, Rural

Infrastructure Engineer I

TF / A7280Capacity and Institution-

BuildingPost

Individual

Consultant

Selection

Open

6,977.91 8,854.18 Completed 2018-11-13 2018-02-22 2018-11-16 2018-04-01 2018-11-17 2018-05-02 2018-11-19 2018-05-03 2019-02-28 2019-04-30

MTF-BDA-43 / Lucman,

Abdulgaffor D. Rural

Infrastructure Engineer I

TF / A7280Capacity and Institution-

BuildingPost

Individual

Consultant

Selection

Open

6,977.91 8,854.18 Completed 2018-11-13 2018-02-22 2018-11-16 2018-04-01 2018-11-17 2018-05-02 2018-11-19 2018-05-03 2019-02-28 2019-06-30

MTF-BDA-45 /

Mamalangkas, Karnain S.

Community Organizer

TF / A7280Capacity and Institution-

BuildingPost Direct Selection Direct

6,461.71 7,317.10 Completed 2018-11-13 2018-02-22 2018-11-15 2018-04-01 2018-11-18 2018-05-03 2019-02-28 2019-06-30

MTF-BDA-46 /

Manalundong, Raquib,

Community Organizer of

Camp Bilal

TF / A7280Capacity and Institution-

BuildingPost Direct Selection Direct

6,461.71 7,319.35 Completed 2018-11-14 2018-02-22 2018-11-16 2018-04-01 2018-11-19 2018-05-03 2019-02-28 2019-06-30

MTF-BDA-48 / Manticayan,

Hashim, Learning &

Development Officer

TF / A7280Capacity and Institution-

BuildingPost Direct Selection Direct

10,274.88 8,844.85 Completed 2018-11-13 2018-02-22 2018-11-15 2018-03-16 2018-11-18 2018-05-03 2019-02-28 2019-08-31

MTF-BDA-50 / Masandag,

Nasser, Community

Organizer

TF / A7280Capacity and Institution-

BuildingPost Direct Selection Direct

6,461.71 7,317.10 Completed 2018-11-14 2018-02-22 2018-11-16 2018-04-01 2018-11-19 2018-05-03 2019-02-28 2019-08-31

MTF-BDA-52 / Mohammad,

Warda , Procurement Officer

TF / A7280Capacity and Institution-

BuildingPost

Individual

Consultant

Selection

Open

7,808.46 9,007.50 Completed 2018-11-14 2018-02-22 2018-11-17 2018-04-01 2018-11-18 2018-05-02 2018-11-20 2018-05-03 2019-02-28 2019-08-31

Page 9: procurement arrangement - World Bank Documents

Page 7

MTF-BDA-53 / Nul,

Nurhammine A. Information

& Communication Officer

TF / A7280Capacity and Institution-

BuildingPost

Individual

Consultant

Selection

Open

7,808.46 9,007.50 Completed 2018-11-13 2018-02-22 2018-11-16 2018-04-01 2018-11-17 2018-05-02 2018-11-19 2018-05-03 2019-02-28 2019-08-31

MTF-BDA-54 / Omaca-an,

Jamael, Rural Infrastructure

Engineer I

TF / A7280Capacity and Institution-

BuildingPost

Individual

Consultant

Selection

Open

6,977.91 8,835.20 Completed 2018-11-13 2018-02-22 2018-11-16 2018-04-01 2018-11-17 2018-05-02 2018-11-19 2018-05-03 2019-02-28 2019-08-31

MTF-BDA-55 / Panglima,

Sarah, Records Officer /

HRM

TF / A7280Capacity and Institution-

BuildingPost

Individual

Consultant

Selection

Open

7,808.46 9,353.94 Completed 2018-11-13 2018-02-22 2018-11-16 2018-04-01 2018-11-17 2018-05-02 2018-11-19 2018-05-03 2019-02-28 2019-08-31

MTF-BDA-56 / Pangunotan,

Maehara, Rural

Infrastructure Engineer

TF / A7280Capacity and Institution-

BuildingPost

Individual

Consultant

Selection

Open

6,977.91 8,860.40 Completed 2018-11-13 2018-02-22 2018-11-16 2018-04-01 2018-11-17 2018-05-02 2018-11-19 2018-05-03 2019-02-28 2019-06-30

MTF-BDA-59 / Salidatan,

Abdulmaguid, Adminstrative

Officer

TF / A7280Capacity and Institution-

BuildingPost Direct Selection Direct

10,274.88 12,082.56 Completed 2018-11-13 2018-02-22 2018-11-15 2018-04-01 2018-11-18 2018-05-03 2019-02-28 2019-08-31

MTF-BDA-60 / Sangcopan,

Alioden, Community

Organizer

TF / A7280Capacity and Institution-

BuildingPost Direct Selection Direct

6,461.71 7,305.06 Completed 2018-11-13 2018-02-22 2018-11-15 2018-04-01 2018-11-18 2018-05-03 2019-02-28 2019-04-30

MTF-BDA-61 / Saranggani,

Alinader, Rural

Infrastructure Engineer I

TF / A7280Capacity and Institution-

BuildingPost

Individual

Consultant

Selection

Open

6,977.91 8,768.59 Completed 2018-11-13 2018-02-22 2018-11-16 2018-04-01 2018-11-17 2018-05-02 2018-11-19 2018-05-03 2019-02-28 2019-06-30

MTF-BDA-62 / Sinulinding,

Kadafy, Community

Organizer

TF / A7280Capacity and Institution-

BuildingPost Direct Selection Direct

6,461.71 7,305.06 Completed 2018-11-14 2018-02-22 2018-11-16 2018-04-01 2018-11-19 2018-05-03 2019-02-28 2019-06-30

MTF-BDA-63 / Sundang,

Abdulgaffar, Rural

Infrastructure Engineer I

TF / A7280Capacity and Institution-

BuildingPost

Individual

Consultant

Selection

Open

6,977.91 8,860.40 Completed 2018-11-13 2018-02-22 2018-11-16 2018-04-01 2018-11-17 2018-05-02 2018-11-19 2018-05-03 2019-02-28 2019-06-30

MTF-BDA-64 / Taalim,

Rhadzni M. Project

Coordinator

TF / A7280Capacity and Institution-

BuildingPost Direct Selection Direct

10,274.88 12,062.68 Completed 2018-11-13 2018-02-22 2018-11-15 2018-04-01 2018-11-18 2018-05-03 2019-02-28 2019-08-31

MTF-BDA-65 / Taha, Elias

Community Organizer

TF / A7280Capacity and Institution-

BuildingPost Direct Selection Direct

6,461.71 7,319.35 Completed 2018-11-13 2018-02-22 2018-11-15 2018-04-01 2018-11-18 2018-05-03 2019-02-28 2019-06-30

MTF-BDA-66 / Tahir, Al-

amin, Logistics Officer

TF / A7280Capacity and Institution-

BuildingPost

Individual

Consultant

Selection

Open

7,808.46 9,007.50 Completed 2018-11-13 2018-02-22 2018-11-16 2018-04-01 2018-11-17 2018-05-02 2018-11-19 2018-05-03 2019-02-28 2019-08-31

MTF-BDA-67 / Tandalong,

Luqman, Community

Development Officer

TF / A7280Capacity and Institution-

BuildingPost Direct Selection Direct

8,039.49 10,017.19 Completed 2018-11-13 2018-02-22 2018-11-15 2018-04-01 2018-11-18 2018-05-03 2019-02-28 2019-08-31

MTF-BDA-69 / Victor,

Zainodin Safety and Security

Officer

TF / A7280Capacity and Institution-

BuildingPost

Individual

Consultant

Selection

Open

6,586.36 7,581.31 Completed 2018-11-13 2018-02-22 2018-11-16 2018-04-01 2018-11-17 2018-05-02 2018-11-19 2018-05-03 2019-02-28 2019-08-31

MTF-BDA-70 / Yacob,

Mohammad S. Executive

Director

TF / A7280Capacity and Institution-

BuildingPost Direct Selection Direct

12,719.42 14,917.72 Completed 2018-11-13 2018-02-22 2018-11-15 2018-04-01 2018-11-18 2018-05-03 2019-02-28 2019-03-31

MTF-BDA-05 / Agao,

Akmad M., Community

Organizer

TF / A7280Capacity and Institution-

BuildingPost Direct Selection Direct

6,461.71 7,350.34 Completed 2018-11-13 2018-02-22 2018-11-15 2018-11-18 2018-05-03 2019-02-28 2019-06-30

MTF-BDA-01 / Abdulhamid,

Adiamin, Community

Organizer

TF / A7280Capacity and Institution-

BuildingPost Direct Selection Direct

6,461.71 576.97 Completed 2018-11-13 2018-02-22 2018-11-15 2018-04-01 2018-11-18 2018-05-03 2019-02-28 2019-06-30

Page 10: procurement arrangement - World Bank Documents

Page 8

MTF-CON01 /

Abdullahkarim, Noraida A.

TF / A7280Project Administration,

Monitoring & EvaluationPost Direct Selection Direct

38,379.86 0.00Pending

Implementation2019-10-01 2019-10-11 2019-12-15 2020-12-31

MTF-CON02 / Akis, Carida

P.

TF / A7280Project Administration,

Monitoring & EvaluationPost Direct Selection Direct

28,244.47 0.00Pending

Implementation2019-09-01 2019-09-11 2019-11-15 2020-12-31

MTF-CON03 / Buenbrazo,

Danilo C.

TF / A7280Project Administration,

Monitoring & EvaluationPost Direct Selection Direct

25,208.34 0.00Pending

Implementation2019-09-01 2019-09-11 2019-11-15 2020-03-18

MTF-CON04 / Gatus-

Chavez, Cristina Joy Q.

TF / A7280Project Administration,

Monitoring & EvaluationPost Direct Selection Direct

20,092.36 0.00Pending

Implementation2019-10-01 2019-10-11 2019-12-15 2020-12-31

MTF-CON06 / Guinzon, Bai

Sahareah M.

TF / A7280Project Administration,

Monitoring & EvaluationPost Direct Selection Direct

17,768.16 0.00Pending

Implementation2019-09-01 2019-09-11 2019-11-15 2020-09-30

MTF-CON07 / Kamid,

Usman J.

TF / A7280Project Administration,

Monitoring & EvaluationPost Direct Selection Direct

18,444.83 0.00Pending

Implementation2019-09-01 2019-09-11 2019-11-15 2020-09-30

MTF-CON08 / Kasan,

Hafidullah N.

TF / A7280Project Administration,

Monitoring & EvaluationPost Direct Selection Direct

15,266.89 0.00Pending

Implementation2019-09-01 2019-09-11 2019-11-15 2020-12-31

MTF-CON09 / Mariano,

Jessmin V.

TF / A7280Project Administration,

Monitoring & EvaluationPost Direct Selection Direct

23,802.81 0.00Pending

Implementation2019-09-01 2019-09-11 2019-11-15 2020-12-31

MTF-CON11 / Ison, Edita

C.

TF / A7280Project Administration,

Monitoring & EvaluationPost Direct Selection Direct

23,794.81 0.00Pending

Implementation2019-09-01 2019-09-11 2019-11-15 2020-12-31

MTF-CON14 / Quesada,

Schearazmiah I.

TF / A7280Project Administration,

Monitoring & EvaluationPost Direct Selection Direct

15,828.16 0.00Pending

Implementation2019-09-01 2019-09-11 2019-11-15 2020-09-30

MTF-CON15 / Sali,

Abibazar W.

TF / A7280Project Administration,

Monitoring & EvaluationPost Direct Selection Direct

25,527.81 0.00Pending

Implementation2019-09-01 2019-09-11 2019-11-15 2020-12-31

MTF-CON16 / Sevillano,

Jude G.

TF / A7280Project Administration,

Monitoring & EvaluationPost Direct Selection Direct

17,501.17 0.00Pending

Implementation2019-09-01 2019-09-11 2019-11-15 2020-12-31

MTF-CON18 / Tan-Guialel,

Ivy Marie D.

TF / A7280Project Administration,

Monitoring & EvaluationPost Direct Selection Direct

13,823.14 0.00Pending

Implementation2019-09-01 2019-09-11 2019-11-15 2020-12-31

MTF-CON19 / Diangcalan,

Windel P.

TF / A7280Capacity and Institution-

BuildingPost Direct Selection Direct

15,028.00 0.00Pending

Implementation2019-09-01 2019-09-11 2019-11-15 2020-09-30

MTF-CON20 /

Mangansakan, Zuhaira G.

TF / A7280Capacity and Institution-

BuildingPost Direct Selection Direct

7,878.00 0.00Pending

Implementation2019-09-01 2019-09-11 2019-11-15 2020-09-30

MTF-CON21 / Kabagani,

Norhana A.

TF / A7280Capacity and Institution-

BuildingPost Direct Selection Direct

9,308.00 0.00Pending

Implementation2019-09-01 2019-09-11 2019-11-15 2020-09-30

MTF-CON22 / Edza,

Marbawi M.

TF / A7280Capacity and Institution-

BuildingPost Direct Selection Direct

9,308.00 0.00Pending

Implementation2019-09-01 2019-09-11 2019-11-15 2020-09-30

MTF-CON23 / Hassan,

Rahima A.

TF / A7280Capacity and Institution-

BuildingPost Direct Selection Direct

9,308.00 0.00Pending

Implementation2019-09-01 2019-09-11 2019-11-15 2020-09-30

MTF-CON24 / Salidatan,

Abdulmaguid K.

TF / A7280Capacity and Institution-

BuildingPost Direct Selection Direct

12,168.00 0.00Pending

Implementation2019-09-01 2019-09-11 2019-11-15 2020-09-30

MTF-CON25 / Panglima,

Sarah G.

TF / A7280Capacity and Institution-

BuildingPost Direct Selection Direct

9,308.00 0.00Pending

Implementation2019-09-01 2019-09-11 2019-11-15 2020-09-30

MTF-CON26 / Mohammad,

Warda S.

TF / A7280Capacity and Institution-

BuildingPost Direct Selection Direct

9,308.00 0.00Pending

Implementation2019-09-01 2019-09-11 2019-11-15 2020-09-30

Page 11: procurement arrangement - World Bank Documents

Page 9

MTF-CON27 / Tahir, Al-

Amen E.

TF / A7280Capacity and Institution-

BuildingPost Direct Selection Direct

4,472.00 0.00Pending

Implementation2019-10-16 2019-10-26 2019-12-30 2020-07-15

MTF-CON28 / Datumanong,

Rahima K.

TF / A7280Capacity and Institution-

BuildingPost Direct Selection Direct

8,592.00 0.00Pending

Implementation2019-10-01 2019-10-11 2019-12-15 2020-09-30

MTF-CON36 / Cadon,

JulhainaE.

TF / A7280Capacity and Institution-

BuildingPost Direct Selection Direct

12,168.00 0.00Pending

Implementation2019-09-01 2019-09-11 2019-11-15 2020-09-30

MTF-CON37 / Abdullah,

Nor-ain A.

TF / A7280Capacity and Institution-

BuildingPost Direct Selection Direct

9,912.00 0.00Pending

Implementation2019-10-01 2019-10-11 2019-12-15 2020-09-30

MTF-CON38 / Danda,

Almira A.

TF / A7280Capacity and Institution-

BuildingPost Direct Selection Direct

9,308.00 0.00Pending

Implementation2019-09-01 2019-09-11 2019-11-15 2020-09-30

MTF-CON39 / Dumadalog,

Bashet C.

TF / A7280Capacity and Institution-

BuildingPost Direct Selection Direct

9,308.00 0.00Pending

Implementation2019-09-01 2019-09-11 2019-11-15 2020-09-30

MTF-CON41 / Taalim,

Rhadzni M.

TF / A7280Capacity and Institution-

BuildingPost Direct Selection Direct

12,168.00 0.00Pending

Implementation2019-09-01 2019-09-11 2019-11-15 2020-09-30

MTF-CON42 / Labay, Rahib

A.

TF / A7280Capacity and Institution-

BuildingPost Direct Selection Direct

12,168.00 0.00Pending

Implementation2019-09-01 2019-09-11 2019-11-15 2020-09-30

MTF-CON43 / Alon,

Mohammad Saud A.

TF / A7280Capacity and Institution-

BuildingPost Direct Selection Direct

10,353.00 0.00Pending

Implementation2019-09-16 2019-09-26 2019-11-30 2020-09-30

MTF-CON44 / Batuampar,

Cosain S.

TF / A7280Capacity and Institution-

BuildingPost Direct Selection Direct

9,912.00 0.00Pending

Implementation2019-10-01 2019-10-11 2019-12-15 2020-09-30

MTF-CON45 / Mohamad,

Swaib M.

TF / A7280Capacity and Institution-

BuildingPost Direct Selection Direct

8,978.00 0.00Pending

Implementation2019-09-16 2019-09-26 2019-11-30 2020-09-30

MTF-CON46 / Alon,

Mokamad Y.

TF / A7280Capacity and Institution-

BuildingPost Direct Selection Direct

6,391.00 0.00Pending

Implementation2019-10-01 2019-10-11 2019-12-15 2020-09-30

MTF-CON47 / Ambil,

Abdulrasheed B.

TF / A7280Capacity and Institution-

BuildingPost Direct Selection Direct

10,353.00 0.00Pending

Implementation2019-09-16 2019-09-26 2019-11-30 2020-09-30

MTF-CON48 /

Mamalangkas, Karnain S.

TF / A7280Capacity and Institution-

BuildingPost Direct Selection Direct

10,353.00 0.00Pending

Implementation2019-09-16 2019-09-26 2019-11-30 2020-09-30

MTF-CON49 / Dilabayan,

Abdulcader R.

TF / A7280Capacity and Institution-

BuildingPost Direct Selection Direct

9,912.00 0.00Pending

Implementation2019-10-01 2019-10-11 2019-12-15 2020-09-30

MTF-CON50 / Amerol,

Halil L.

TF / A7280Capacity and Institution-

BuildingPost Direct Selection Direct

10,353.00 0.00Pending

Implementation2019-09-16 2019-09-26 2019-11-30 2020-09-30

MTF-CON51 / Hadjinor,

Alimuddin A.

TF / A7280Capacity and Institution-

BuildingPost Direct Selection Direct

10,353.00 0.00Pending

Implementation2019-09-16 2019-09-26 2019-11-30 2020-09-30

MTF-CON52 / Sinulinding,

Kadafy S.

TF / A7280Capacity and Institution-

BuildingPost Direct Selection Direct

10,353.00 0.00Pending

Implementation2019-10-01 2019-10-11 2019-12-15 2020-09-30

MTF-CON53 / Abo, Salman

S.

TF / A7280Capacity and Institution-

BuildingPost Direct Selection Direct

7,160.00 0.00Pending

Implementation2019-10-16 2019-10-26 2019-12-30 2020-07-15

MTF-CON54 / Diahing,

Raida B.

TF / A7280Capacity and Institution-

BuildingPost Direct Selection Direct

7,160.00 0.00Pending

Implementation2019-10-16 2019-10-26 2019-12-30 2020-07-15

MTF-CON55 / Omaca-an,

Jamael M.

TF / A7280Capacity and Institution-

BuildingPost Direct Selection Direct

7,160.00 0.00Pending

Implementation2019-10-16 2019-10-26 2019-12-30 2020-07-15

Page 12: procurement arrangement - World Bank Documents

Page 10

MTF-CON56 / Lucman

Abdulgaffar D.

TF / A7280Capacity and Institution-

BuildingPost Direct Selection Direct

7,160.00 0.00Pending

Implementation2019-10-16 2019-10-26 2019-12-30 2020-07-15

MTF-CON57 / Sundang,

Abdulgaffar Shamier L.

TF / A7280Capacity and Institution-

BuildingPost Direct Selection Direct

7,160.00 0.00Pending

Implementation2019-10-16 2019-10-26 2019-12-30 2020-07-15

MTF-CON58 / Alon, Tonton

A.

TF / A7280Capacity and Institution-

BuildingPost Direct Selection Direct

7,160.00 0.00Pending

Implementation2019-10-16 2019-10-26 2019-12-30 2020-07-15

MTF-CON59 / Ambil, Arift

P.

TF / A7280Capacity and Institution-

BuildingPost Direct Selection Direct

6,060.00 0.00Pending

Implementation2019-10-16 2019-10-26 2019-12-30 2020-07-15

MTF-CON60 / Abdulhamid,

Adianmin U.

TF / A7280Capacity and Institution-

BuildingPost Direct Selection Direct

6,060.00 0.00Pending

Implementation2019-10-16 2019-10-26 2019-12-30 2020-07-15

MTF-CON61 /

Manalundong, Raquib A.

TF / A7280Capacity and Institution-

BuildingPost Direct Selection Direct

6,060.00 0.00Pending

Implementation2019-10-16 2019-10-26 2019-12-30 2020-07-15

MTF-CON62 / Maunda,

Omar A.

TF / A7280Capacity and Institution-

BuildingPost Direct Selection Direct

6,060.00 0.00Pending

Implementation2019-10-16 2019-10-26 2019-12-30 2020-07-15

MTF-CON63 / Masandag,

Nasser K.

TF / A7280Capacity and Institution-

BuildingPost Direct Selection Direct

6,060.00 0.00Pending

Implementation2019-10-16 2019-10-26 2019-12-30 2020-07-15

MTF-CON64 / Abdulrasid,

Badrodin K.

TF / A7280Capacity and Institution-

BuildingPost Direct Selection Direct

6,060.00 0.00Pending

Implementation2019-10-16 2019-10-26 2019-12-30 2020-07-15

MTF-CON65 / Erika Mae

Lasola

TF / A7280Project Administration,

Monitoring & EvaluationPost

Individual

Consultant

Selection

20,508.63 0.00Pending

Implementation2019-10-01 2019-10-01 2019-10-01 2019-10-01 2019-10-01

MTF-CON66 / Tohami

Ibrahim

TF / A7280Project Administration,

Monitoring & EvaluationPost Direct Selection Direct

929.70 0.00Pending

Implementation2019-09-01 2019-09-11 2019-11-15 2020-05-13

MTF-CON67 / Saddam

Alipulo

TF / A7280Project Administration,

Monitoring & EvaluationPost Direct Selection Direct

2,637.17 0.00Pending

Implementation2019-09-01 2019-09-11 2019-11-15 2020-05-13

MTF-CON68 / Mario

Catubay Jr.

TF / A7280Project Administration,

Monitoring & EvaluationPost Direct Selection Direct

1,241.27 0.00Pending

Implementation2019-09-01 2019-09-11 2019-11-15 2020-05-13