Top Banner

of 20

Process Guidlines

Jun 03, 2018

Download

Documents

MKPashaPasha
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
  • 8/12/2019 Process Guidlines

    1/20

    Direction des Performances CimentiresProcess Group Leaders Network

    Process Guidelines V3 October 2005Click to access the page

    - Read me - ReadMe

    Raw milling Raw millingPreheater Preheater Kiln KilnCooler Cooler Kiln and Cooler Filter Kiln and Cooler Filter Kiln by-pass system Kiln By-pass systemGas analyser Gas analyser Coal mill Coal millCement grinding Cement Gr Weighing-dosing Weighing-dosing

    05 10 05

    Process guidelines - Contents -

  • 8/12/2019 Process Guidlines

    2/20

    Back to table of contents

    Process Guidelines V3 - October 2005

    Best practice /recommendation

    To be written

    Specifications These are the figures we give to suppliers in the tender ; this column should contain the samefigures as other documents.

    Alternatives In this column we describe alternatives, which could be accepted for cost reason, but also arenecessary for process reasons. Example would be cement mill specification is vertical mill,Alternative is ball mill and in case of a existing ball mill a roller press

    Operating target Operating target is the range where we want to have an equipment operated; this is not to begiven to suppliers, but we will check offers accordingly. Important value for process evaluation ofexisting equipment or to calculate operation cost.

    Not advisable These are choices we dont accept. Important if suppliers send alternatives on their own

    Comments

  • 8/12/2019 Process Guidlines

    3/20

    Raw milling Best Practice /Recommendation Specifications Alternatives Operating target Not advisable Comments

    Back to table of contents

    CHOICE OF MILL SYSTEM

    Vertical Mill with cyclone andfan with VFD

    Vertical Mill with cyclone andfan with VFD

    2 compartments closed circuittube mills with drying

    chambers (if moisture < 7-8%)orTube mills in combination withheated hammer crushers.High efficiency separatororRoller Press with Ball Mill

    Tube mills without dryingchamber, or without external

    drying.Autogenous Mills (only in caseof specific applications).Roll Press in circuit with V orVSK separator and/or dynamicseparator.Pregrinding circuit with two-compartments ball mill.Air Swept millCentral discharge mill

    Modification of existinggrinding shop

    Closed circuit millHigh efficiency separator

    Closed circuit millHigh efficiency separator

    Roll Press in circuit with V orVSK separator and/or dynamicseparator.Pregrinding with two-compartments ball mill circuit.Modification of 1st generationseparatorAddition of external dryingdrum

    New Equipment Ball Mill with drying chamber

    Mill Circuit Closed circuit Partial feed to the separator Open circuit

    Ball mill speed 75% critical speed 75 % critical speed 78% critical speed

    Ventilation ball mill

    Air velocity above ballcharge=1,5 to 2,2 m/sinside the trunion: 22-25 m/sinside partition:8-14 m/s0,6 - 0,8 Nm3/kg raw mixhood < 5m/sdrop out box < 2m/sVFD fan

    Air velocity above ballcharge=1,5 to 2,2 m/s

    VFD fan

    Mill L/D ratio1,5 < L/D < 3,2First compartment length = 3545% of mill total length

    Process guidelines - Raw Milling - Page 1 / 3 06/10/2005 - 10:58

  • 8/12/2019 Process Guidlines

    4/20

    Raw milling Best Practice /Recommendation Specifications Alternatives Operating target Not advisable Comments

    Back to table of contents

    Ball mill Liners

    Moderate lifting liners for firstcompartment, classifying liners

    for second compartment

    Classifying liners in secondcompartment

    Duo liftRipple liners

    Without classifying liners keepa maximum of 3 - 4 ball sizes

    Intermediate Partition wall

    Central opening adapted tothe filling degree. Slots placedconcentricly. - 8 to 12 mm slotfor central partition.- open area > 50 % by centralopening

    Diaphragms with material flowcontrol

    Slots placed radially.

    Outlet partition wall

    Central opening adapted tothe filling degree. Slots placedconcentricly. Partition wall slotsize + 2mm (max slot = 0,5min ball size)

    Slots placed radially.

    Ball charge

    Volume Loading:- for minimum kWh/t: 26-28%in C1 and 28-30% in C2- for max output: 32-34% inC1 and 34-36% in C2

    Separator Third Generation HighEfficiency

    Dust load < 1kg/m3Qf/Qa < 2.5

    1st or 2nd generationseparators

    Control

    Fresh feed control to assureconstant feed to the separator.Mill controled by LUCIE.

    Weighing rejects (beltweigher), measuring elevatorpower, mill presure loss, milloutlet temperature andelectronic ear.

    Control mill fresh feed usingonly one parameter (onlyrejects flowrate or onlyelevator power , for example)

    Fresh feed control can be doneby different ways, usingdifferent instruments or signals(rejects flowrate, elevatorpower, eletr. Ear, mill kW). It isrecommended to use them inconjunction.

    Feed

    Feed size 95%< 50 mmd80 feed < 20mm,

    Precrushing, screening,external drying

    The finer, the better

    Drying compartment Moisture inlet C1 < 1.5%Specific drying capacity

  • 8/12/2019 Process Guidlines

    5/20

    Raw milling Best Practice /Recommendation Specifications Alternatives Operating target Not advisable Comments

    Back to table of contents

    Equipment VRMVertical Roller Mill Recirculation of gas to the mill.

    Metal detector and extractor inthe feeding line (after reject'sreturn)Gas flow measurement aftercyclone or filterWater injection systemCentral mill feed.HE SeparatorMaterial External RecirculationSystem >30% Fresh Feed

    Capacity Fanwith VFDBed depth sensor

    Metal detector and extractor in

    the feeding line (after reject'sreturn)Bed depth sensorWater injection max 25 kg/tMaterial External RecirculationSystem >30% Fresh FeedCapacityFan with VFD

    Water injection facilities in the

    mill housing

    Gas speeds:

    Nozzle ring >30 m/sMill Body: 5 - 7 m/sSeparator: 3 - 5 m/sDust Load: 600 g/m3 at milloutlet

    Feed device with triple flap

    gate or rotary air lock valve,heated if wet or sticky rawmaterials.Fan max speed typical 700 rpmand >80% efficiency

    Control Constant mill exit TConstant mill gas flowMill feed a to mill deltaP

    Process guidelines - Raw Milling - Page 3 / 3 06/10/2005 - 10:58

  • 8/12/2019 Process Guidlines

    6/20

    Preheater Best practice /Recommendation Specifications Alternatives Operating target Not advisable CommentsBack to table of contents

    Equipment

    Cyclones

    5 Stage Preheater - lowmoisture < 5% raw materials

    Low pressure drop

    Bottom of cyclone> 50 height

    No horizonatal inlet ; nohorizontal surface

    4 Stage Preheater - highmoisture >5% raw materials

    For a 5 stage PH, 4.5 to 5.5kPa (including kiln)

    See priority study Preheater

    Dip Tube Length relative tocyclone inlet height

    Top (stage 1): 100%Stage 2/3: 75%minStage 4/5 : 50%min

    Top (stage 1): 100%Hurrivanes - depending on

    geometryNumber in % of inlet height

    Splash box

    Lafarge designcleaning devices. At least 55

    to 80 between meal pipe andsplash box

    2 m from flap, pipe withoutelbow

    60 for kiln feed to splash box.

    >60 o below C3 Splash plates See priority study Preheater

    Pendulum flap External knife bearing

    Precalciner Vessel + Hot core preferredResidence time > 6 secfor petcoke, Low-Nox

    Residence time > 6 sec Riser Duct plus hot core Very specific to fuel and plantconditions

    Tertiary air duct

    Downward split designfor in-line calcinerDamper control

    Duct velocity 20 to 30 m/s

    Process

    Gas duct velocity at mealentrance

    Mini 12 m/s top stagewith 17 m/s bottom

    (intermediate proportional)Can install restriction

    as alternative

    Riser velocity 16 m/s minimum

    Process guidelines - Preheater - Page 1 / 2 06/10/2005 - 10:58

  • 8/12/2019 Process Guidlines

    7/20

    Preheater Best practice /Recommendation Specifications Alternatives Operating target Not advisable CommentsBack to table of contents

    Cyclones Top cyclone efficiency > 95% Top cyclone efficiency > 95%

    Meal curtain

    Considered if high volatilecycles expected

    Most common on N-1 stageon kiln side

    LateralConsider a splitter

    Kiln inlet box

    No dead zoneSmooth design (entrance in the

    middle)No turbulances

    45- 50 slope of inlet

    Downcomer

    Cooling by water spraysMinimum evaporation: 4 sec

    (for target at 185C)No bleed air is recommended,

    except for start up

    Water design target able toprovide 185 C. Take careabout moisture in gas to coalmill take off above waterinjection

    ID fan preheaterVFD drive

    Fresh air intake beforethe fan (fan protection)

    Fan Typical Max speed 990rpm and efficiency >80%.Design margin 5% volume and1 kPa pressure

    number of fans3

    ID fan, raw mill fan &baghouse fan

    Only 2 fans

    Secondary Fuelusage

    Burner preferred for Calciner

    Process guidelines - Preheater - Page 2 / 2 06/10/2005 - 10:58

  • 8/12/2019 Process Guidlines

    8/20

    Kiln Best Practice /Recommendation Specifications Alternatives Operating target Not advisable CommentsBack to table of contents

    Equipment

    Burner type and position Lafarge BurnerMAS burner in case of regularsolid fuel and alternative fuel ;

    Position in center line of kilnand aligned on kiln axis (only

    if kiln is stable and burnerhaving sufficient impulse)

    See Lafarge Burner DesignSpreadsheet

    Fuel speedSolid Fuel: 25 - 35 m/s inburner ; >25m/s in conveyingline

    Solid Fuel: 25 - 35 m/s inburner ; >25m/s in conveyingline

    Alternative Fuel: 25 - 40 m/sin burner ; >25m/s inconveying line

    Total primary air 25 cStSwirl Design: 0,15

    Impulse Design: >2,2Final design criteria to beworked out.

    Retaining rings0,6 to 1 m from nosering assingle ring, triangulkar shape

    Double flat barMaggoteaux system

    Kiln slope 3 - 3,5 % 4%

    L/D

    >10,5 for preca (> 15 isrequired when designing foralternaitve fuels)> 15 for preheater

    Tertiary air

    From kiln hoodTake off velocity 5-6 m/sthroat and tertiary air and 25m/s in the duct

    From kiln hoodTake off velocity 5-6 m/sthroat and tertiary air and 25m/s in the duct

    Settling chamber Heat shield IKN not proven

    Shell cooling fans 12 to 18 m/s at shell SuppliedFan should be below kiln sothat air flow comes up onboth sides.

    Process guidelines - Kiln - Page 1 / 2 06/10/2005 - 10:58

  • 8/12/2019 Process Guidlines

    9/20

    Kiln Best Practice /Recommendation Specifications Alternatives Operating target Not advisable CommentsBack to table of contents

    Process

    Thermal load< 5 MW/m (kiln cross

    section)< 5 MW/m < 6.5 MW/m

    Limit for refractory.Some wet and big kilns canoverpass the limit

    Kiln hood velocity < 6 m/s

    Kiln load

  • 8/12/2019 Process Guidlines

    10/20

    Cooler Best practice /Recommendation Specifications Alternatives Operating target Not advisable CommentsBack to table of contents

    EquipmentEquipment Selection Cross Bar or Walking Floor

    DesignCross Bar or Walking FloorDesign

    Grate load < 45 t/m d < 45 t/m d

    Variable speed fans All on 1st grate Variable speed on all on 1stgrate fans. 2nd grate fans canbe with variable inlet vanesdampers

    Fan dampers (inlet radial) Flap max speed typical 1500 rpm,Efficiency > 80%. Normally 20-30% pressure reserve.

    Fix inlet rows 5 to 8 (1.5 - 2.5 m)Max 15 degree angleRefractory HorseshoeAir Cannons

    Crusher Roller crusher intermediateor at the end

    HammerCrusher

    Hammer crusher can be thefirst choice if no need for veryeffective cooling

    Grate slope 0 3 maximum

    Evacuation hoppers Simple gate and sensor level Double gate mechanicallyactivated

    ProcessAir flow design Not < 2,1 Nm3/kg > 2.1 Nm/kg ck

    > 1.7 Nm/m/s on first fans, 2Nm/m/s for KIDS

    First fans pressure > 10 kPa (100 mbar) for KIDS

    Optimal bed depth Lowest stroke permitted with20% reserve on fans(6-8 st/min for properlydesigned cooler)

    Air velocity above clinker 5 to 7 m/sClinker transport design Min. 1,5 x nominal capacitysteel conveyor

    Min. 1,5 x nominal capacitysteel conveyor

    Process guidelines - Cooler - Page 1 / 1 06/10/2005 - 10:59

  • 8/12/2019 Process Guidlines

    11/20

    Kiln filter Best practice /Recommendation Specifications Alternatives Operating target Not advisable CommentsBack to table of contents

    Equipment

    Equipment SelectionLow Pressure Pulse Jet Bag

    Filter ( 2,5 bars)

    Low Pressure Pulse Jet (LPPJ)

    Bag Filter ( 2,5 bars)

    High Pressure Pulse Jet (HPPJ)Bag Filter (6bar/100psi),Electrostatic precipitator

    Max dP< allowed by fancapacity at end of bag life.

    Limit cleaning cycles to obtaintarget bag life.

    Off line cleaning is notacceptable due to thepotential damage to the bags.

    BH sizing must maintainoperating pressure drop withinthe limits of the ID fan and thepulse jet filter ability to cleanbag on line.

    Equipment SizingGross Air to clothe ratio:1m/min average1.3 m/min max (upset cond)

    Gross Air to clothe ratio:1m/min average1.3 m/min max (upset cond)

    Bag quality

    Fabric with PTFE membraneand fiberglass structure.Known suppliers: Gore, BHA,Tetratec workingat 180C- 230C max

    Design temperature 230CPeak temperature 260C

    P84 bags of suitableconstruction.

    Adequate temperature controlto prevent teflon and SGTevaporation and bag damage.working at 180C- 230C max

    Other bag materials that arenot proven.If using P84 verify the risk ofhydrolysis.

    Bag quality and workmanshipare critical. Bag to cage fit iscritical.

    Airflow DistributionScale model to ensure goodairflow distribution and correct

    fan sizing before purchase

    Compressed Air SupplyAir coolers can be acceptablefor LPPJ.

    Use air dryers (dessicant) forHPPJ (-30deg C due point).

    Prevent moisture condensationin the bag during thecompressed air pulse.

    No oil in cleaning air.

    Exhaust Fan VFD VFDFan Typical Max speed 990rpm and efficiency >80%.Design margin 15% volume

    False AirDirect < 30% Preheater GasesCompound < 50% PreheaterGases

    Process guidelines - Kiln and Cooler Filter - Page 1 / 2 06/10/2005 - 12:08

  • 8/12/2019 Process Guidlines

    12/20

    Kiln filter Best practice /Recommendation Specifications Alternatives Operating target Not advisable CommentsBack to table of contents

    COOLER FILTER

    Equipment SelectionAir to air heat exchanger to

    get 130C at exit

    Air to air heat exchanger to

    get 130C at exit

    Common baghouse forRM/kiln and cooler

    ESP when all cooler gas usedfor raw materials drying

    Exhaust system capacity tohandle normal operation andto provide sufficient capacityfor push conditions for the fulllength of the bag life.

    Gas flow in BH hopper mustnot cause abrasion of filterbags due ro high velocities.

    Exhaust gas flow from thecooler straight entry andoriented downwards throughheat exchanger

    Gas velocity at heatexchanger's inlet in normalconditions: 80%.Design Margin 15% volume

    System SizingDesign upset conditions 450 Cexhaust gas temp. Designflow 1.7 nm3/kg clinker

    Design upset conditions 450 Cexhaust gas temp. Designflow 1.7 nm3/kg clinker

    Process guidelines - Kiln and Cooler Filter - Page 2 / 2 06/10/2005 - 12:08

  • 8/12/2019 Process Guidlines

    13/20

    Kiln By-pass system Best practice /Recommendation Specifications Alternatives Operating target Not advisable CommentsBack to table of contents

    Equipment

    Dedusting Bag filters (240C) ESPWet scrubber may be asolution when cement Cl is alimitation

    Dust transport As short as possibleMechanicalAir transport if Cl < 10%

    StorageAs small as possible,

    with mechanical extractionDirect dust addition to cooler

    filter or heat exchangerintermediate storage

    Addition to cooler only ifclinker storage does not

    promote segregation (quality -dust separation in pile)

    Process

    Location take-off

    On top of the smoke box, on

    the kiln sideDistant from C3 discharge to

    avoid dust mixing

    Level of chlorine in dustDilution with kiln feed if >

    10% ClCl control using cyclone system

    with bypass (Taiheyo)

    Quenching

    Air quenching as close aspossible to the take out, eitherdirectly to 200C or at least to

    400C

    Air to air cooler as secondcooling step to minimize the

    gas quantity

    Exhaust airTo cooler fans to avoid

    SO2/Dioxins

    Raw mill or main stack if SO2 isacceptable, dioxins still a

    threat. Detached plume also apotential issue if organics in

    raw mix

    Separate stack

    Dust managementCement (limiting factor forClas allowed by local standard)

    Clinker (limiting factor for Cl)Dust Washing with heavy

    metal recovery, for low limit ofCl in cement

    Dust wasting

    Target level of chlorine in kilnback-end mat

    1,00%Higher concentration

    acceptable if possible for build-ups

    Process guidelines - Kiln By-pass system - Page 1 / 1 06/10/2005 - 10:59

  • 8/12/2019 Process Guidlines

    14/20

    Gas analyser Best practice /Recommendation Specifications Alternatives Operating target Not advisable CommentsBack to table of contents

    Kiln inletKiln inlet

    Probe

    Probe long enough to enterthe kiln, retractable,

    motorisedDry probe requiredWater cooled jacket

    Same probe for all gasesBack flush (clean, dry air)

    Oil cooledIn-situ

    COMandatory

    Type: IRScale: 0-20000 ppm

    NOx

    MandatoryType IR

    No NO2 converter neededScale: 0-20000 ppm

    O2Mandatory

    Type: Paramagnetic0-10%

    SO2

    Required if Total SO3 input >1.2% on clinker basis or

    S/A ratio > 1.2Type UV

    Quartz cells

    0-20000ppm

    IR (on separated line)

    Gas treatment

    Heated line (>180C)2 cooler dryer 1 for SO2 and 1

    for other gasesFor other gases H2O2 injection

    Suspension preheater kiln - no PC

    Exit of preheater tower Mandatory for O2 and CO

    Exit of PrecalcinerPrecalciner

    Probe

    Probe at Bottom cyclone exitretractable,

    Dry probe requiredWater cooled jacket

    Same probe for all gasesBack flush (clean, dry air)

    Process guidelines - Gas analyser - Page 1 / 2 06/10/2005 - 11:02

  • 8/12/2019 Process Guidlines

    15/20

    Gas analyser Best practice /Recommendation Specifications Alternatives Operating target Not advisable CommentsBack to table of contents

    COMandatory

    Type: IRScale: 0-20000 ppm

    NOx

    MandatoryType IR

    No NO2 converter neededScale: 0-20000 ppm

    O2Mandatory

    Type: Paramagnetic0-10%

    Gas treatment

    Heated line (>180C)2 cooler dryer 1 for SO2 and 1

    for other gasesFor other gases H2O2 injection

    3 other in line O2 last

    CEM (stack)Location Follow local regulation

    Dust Scattered light system

    O2In-situ system (Zircon)

    0-10%

    H2OOptical in-situ system IR

    0-10%CO

    Optical in-situ system IR0-2000 mg/Nm3

    Extractive with heated probeand line (>180C) + FTIR

    NOxOptical in-situ system-UV

    0-2000 mg/Nm3Extractive with heated probe

    and line (>180C) + FTIR

    SO2Optical in-situ system-UV

    0-500 mg/Nm3Extractive with heated probe

    and line (>180C) + FTIR

    HClOptical in-situ system-IR

    0-100mg/Nm3Extractive with heated probe

    and line (>180C) + FTIR

    COVExtractive FID

    0-200mg/Nm3CO Protection with ESP

    Precalciner KilnUse precalciner exit CO withpreheater exit CO as back up

    Suspension preheater kilnUse kiln exit CO with

    preheater exit CO as back up

    Process guidelines - Gas analyser - Page 2 / 2 06/10/2005 - 11:02

  • 8/12/2019 Process Guidlines

    16/20

    Coal Mill Best practice /Recommendation Specifications Alternatives Operating target Not advisable CommentsBack to table of contents

    Equipment

    Equipment Selection Vertical mill Vertical mill

    Ball mill ,

    Ring roller millsPendulum mills

    Central discharge mills"deep bowl" mills

    Ball mills are better suited forvery hard fuels and certain

    cokes. Also need to considerturndown ratios if AF issignificant - need VFD orsomething appropriate.

    Process GasHot gas from pre heater withde dusting

    Hot gas from pre heater withde dusting

    Direct or semi direct firing

    Sensors

    CO analysers:- Raw Coal Bin- Mill Filter Exit- Each Pulverised Fuel Bin

    O2 analysers:- Preheater Exit- Before Mill- Mill Filter Exit

    Temperature sensors- Raw coal hopper/silo

    - Before mill- After mill- Hot gas duct- Filter bottom- Coal dust after filter- PF silo bottom ( In banks offour around cone)- Differential temperatureacross filter

    Differential temperature acrossseparator for ball mill

    Load Cells- Raw Coal Bin- Pulverised Coal Bins

    Pressure indication- Before mill- After mill- Mill differential pressure- Filter differential pressure

    Dust monitor- Coal bag filter main stack

    Process guidelines - Coal mill - Page 1 / 2 06/10/2005 - 11:00

  • 8/12/2019 Process Guidlines

    17/20

  • 8/12/2019 Process Guidlines

    18/20

    Cement Grinding Best practice /Recommendation Specifications Alternatives Operating target Not advisable CommentsBack to table of contents

    Equipment

    Equipment Selection Vertical Mill Vertical Mill

    Roller PressPregrinding circuit with two-

    compartment ball millcircuit.CKP with 2compartment mill,Ball mill

    Ring roller mills,central discharge mills

    Ball Mill CircuitClosed circuit mill withseparate filter for millventilation and separator

    Ball mill

    Single compartment withlifting and classifying liners*2,8 < L / D

  • 8/12/2019 Process Guidlines

    19/20

    Cement Grinding Best practice /Recommendation Specifications Alternatives Operating target Not advisable CommentsBack to table of contents

    Ventilation separatorSeparator Qf/Qa:1.8 kg/m,VFD fan for HES,

    The circulating load 200%

    Separator Qf/Qa:1.8 kg/m,VFD fan for HES,

    The circulating load 200%

    Separator Qf/Qa range: 1.8-2.5 kg/m3(200% C.L), Cementtemp 90-110 deg ,VFD for fan

    Final product load32% ball charge

    Higher filling causes higherspecific energy, problems forcooling. Ball charge withpregrinder needs to bemodified

    Process

    Control

    Pre requisites for Lucie - Freshfeed variation throughweighing of separator rejects,feed accuracy with in +/- 1%,electronic ear to detect fillingof first compartment.

    Belt weigher for rejectsElevator power

    FeedFeed size passing on100%

  • 8/12/2019 Process Guidlines

    20/20

    Weighing Dosing Best Practice /Recommendation Specifications Alternatives Operating target Not advisable Comments

    Back to table of contents

    Pulverised Coal

    Equipment Selection

    Small bins close to the burningpoint 40 m. Actual limit

    is back pressure. Long distancemeans more backpressure butcan be compensated for byproper design. Schenk Starfeeder with high pressure

    transport line notrecommended (low tolerance).

    Schenk Coriolis + BremerScrew + FK pump for long

    distance is very good.

    Velocity Minimum number of elbowsvelocity >= 25 m/sMinimum number of elbows

    velocity >= 25 m/s

    Solid concentration 4-6 kg/nm3 4-6 kg/nm3 > 7 kg/nm3

    Raw meal

    Equipment Schenk Coriolis

    PfisterWeigh Feeder

    Both still recommend level binahead of scale to minimize siloflushes. Using airlift pressure to

    calculate flow can be

    sufficiently accurate.

    Effective weighing Variation < 0,5 % (short term) Variation < 0,5 % (short term) Accuracy < 0,5 % (short term)

    Transport Elevator Elevator Air-lift

    Process guidelines - Weighing-dosing - Page 1 / 1 06/10/2005 - 11:05