8/12/2019 Process Guidlines
1/20
Direction des Performances CimentiresProcess Group Leaders Network
Process Guidelines V3 October 2005Click to access the page
- Read me - ReadMe
Raw milling Raw millingPreheater Preheater Kiln KilnCooler Cooler Kiln and Cooler Filter Kiln and Cooler Filter Kiln by-pass system Kiln By-pass systemGas analyser Gas analyser Coal mill Coal millCement grinding Cement Gr Weighing-dosing Weighing-dosing
05 10 05
Process guidelines - Contents -
8/12/2019 Process Guidlines
2/20
Back to table of contents
Process Guidelines V3 - October 2005
Best practice /recommendation
To be written
Specifications These are the figures we give to suppliers in the tender ; this column should contain the samefigures as other documents.
Alternatives In this column we describe alternatives, which could be accepted for cost reason, but also arenecessary for process reasons. Example would be cement mill specification is vertical mill,Alternative is ball mill and in case of a existing ball mill a roller press
Operating target Operating target is the range where we want to have an equipment operated; this is not to begiven to suppliers, but we will check offers accordingly. Important value for process evaluation ofexisting equipment or to calculate operation cost.
Not advisable These are choices we dont accept. Important if suppliers send alternatives on their own
Comments
8/12/2019 Process Guidlines
3/20
Raw milling Best Practice /Recommendation Specifications Alternatives Operating target Not advisable Comments
Back to table of contents
CHOICE OF MILL SYSTEM
Vertical Mill with cyclone andfan with VFD
Vertical Mill with cyclone andfan with VFD
2 compartments closed circuittube mills with drying
chambers (if moisture < 7-8%)orTube mills in combination withheated hammer crushers.High efficiency separatororRoller Press with Ball Mill
Tube mills without dryingchamber, or without external
drying.Autogenous Mills (only in caseof specific applications).Roll Press in circuit with V orVSK separator and/or dynamicseparator.Pregrinding circuit with two-compartments ball mill.Air Swept millCentral discharge mill
Modification of existinggrinding shop
Closed circuit millHigh efficiency separator
Closed circuit millHigh efficiency separator
Roll Press in circuit with V orVSK separator and/or dynamicseparator.Pregrinding with two-compartments ball mill circuit.Modification of 1st generationseparatorAddition of external dryingdrum
New Equipment Ball Mill with drying chamber
Mill Circuit Closed circuit Partial feed to the separator Open circuit
Ball mill speed 75% critical speed 75 % critical speed 78% critical speed
Ventilation ball mill
Air velocity above ballcharge=1,5 to 2,2 m/sinside the trunion: 22-25 m/sinside partition:8-14 m/s0,6 - 0,8 Nm3/kg raw mixhood < 5m/sdrop out box < 2m/sVFD fan
Air velocity above ballcharge=1,5 to 2,2 m/s
VFD fan
Mill L/D ratio1,5 < L/D < 3,2First compartment length = 3545% of mill total length
Process guidelines - Raw Milling - Page 1 / 3 06/10/2005 - 10:58
8/12/2019 Process Guidlines
4/20
Raw milling Best Practice /Recommendation Specifications Alternatives Operating target Not advisable Comments
Back to table of contents
Ball mill Liners
Moderate lifting liners for firstcompartment, classifying liners
for second compartment
Classifying liners in secondcompartment
Duo liftRipple liners
Without classifying liners keepa maximum of 3 - 4 ball sizes
Intermediate Partition wall
Central opening adapted tothe filling degree. Slots placedconcentricly. - 8 to 12 mm slotfor central partition.- open area > 50 % by centralopening
Diaphragms with material flowcontrol
Slots placed radially.
Outlet partition wall
Central opening adapted tothe filling degree. Slots placedconcentricly. Partition wall slotsize + 2mm (max slot = 0,5min ball size)
Slots placed radially.
Ball charge
Volume Loading:- for minimum kWh/t: 26-28%in C1 and 28-30% in C2- for max output: 32-34% inC1 and 34-36% in C2
Separator Third Generation HighEfficiency
Dust load < 1kg/m3Qf/Qa < 2.5
1st or 2nd generationseparators
Control
Fresh feed control to assureconstant feed to the separator.Mill controled by LUCIE.
Weighing rejects (beltweigher), measuring elevatorpower, mill presure loss, milloutlet temperature andelectronic ear.
Control mill fresh feed usingonly one parameter (onlyrejects flowrate or onlyelevator power , for example)
Fresh feed control can be doneby different ways, usingdifferent instruments or signals(rejects flowrate, elevatorpower, eletr. Ear, mill kW). It isrecommended to use them inconjunction.
Feed
Feed size 95%< 50 mmd80 feed < 20mm,
Precrushing, screening,external drying
The finer, the better
Drying compartment Moisture inlet C1 < 1.5%Specific drying capacity
8/12/2019 Process Guidlines
5/20
Raw milling Best Practice /Recommendation Specifications Alternatives Operating target Not advisable Comments
Back to table of contents
Equipment VRMVertical Roller Mill Recirculation of gas to the mill.
Metal detector and extractor inthe feeding line (after reject'sreturn)Gas flow measurement aftercyclone or filterWater injection systemCentral mill feed.HE SeparatorMaterial External RecirculationSystem >30% Fresh Feed
Capacity Fanwith VFDBed depth sensor
Metal detector and extractor in
the feeding line (after reject'sreturn)Bed depth sensorWater injection max 25 kg/tMaterial External RecirculationSystem >30% Fresh FeedCapacityFan with VFD
Water injection facilities in the
mill housing
Gas speeds:
Nozzle ring >30 m/sMill Body: 5 - 7 m/sSeparator: 3 - 5 m/sDust Load: 600 g/m3 at milloutlet
Feed device with triple flap
gate or rotary air lock valve,heated if wet or sticky rawmaterials.Fan max speed typical 700 rpmand >80% efficiency
Control Constant mill exit TConstant mill gas flowMill feed a to mill deltaP
Process guidelines - Raw Milling - Page 3 / 3 06/10/2005 - 10:58
8/12/2019 Process Guidlines
6/20
Preheater Best practice /Recommendation Specifications Alternatives Operating target Not advisable CommentsBack to table of contents
Equipment
Cyclones
5 Stage Preheater - lowmoisture < 5% raw materials
Low pressure drop
Bottom of cyclone> 50 height
No horizonatal inlet ; nohorizontal surface
4 Stage Preheater - highmoisture >5% raw materials
For a 5 stage PH, 4.5 to 5.5kPa (including kiln)
See priority study Preheater
Dip Tube Length relative tocyclone inlet height
Top (stage 1): 100%Stage 2/3: 75%minStage 4/5 : 50%min
Top (stage 1): 100%Hurrivanes - depending on
geometryNumber in % of inlet height
Splash box
Lafarge designcleaning devices. At least 55
to 80 between meal pipe andsplash box
2 m from flap, pipe withoutelbow
60 for kiln feed to splash box.
>60 o below C3 Splash plates See priority study Preheater
Pendulum flap External knife bearing
Precalciner Vessel + Hot core preferredResidence time > 6 secfor petcoke, Low-Nox
Residence time > 6 sec Riser Duct plus hot core Very specific to fuel and plantconditions
Tertiary air duct
Downward split designfor in-line calcinerDamper control
Duct velocity 20 to 30 m/s
Process
Gas duct velocity at mealentrance
Mini 12 m/s top stagewith 17 m/s bottom
(intermediate proportional)Can install restriction
as alternative
Riser velocity 16 m/s minimum
Process guidelines - Preheater - Page 1 / 2 06/10/2005 - 10:58
8/12/2019 Process Guidlines
7/20
Preheater Best practice /Recommendation Specifications Alternatives Operating target Not advisable CommentsBack to table of contents
Cyclones Top cyclone efficiency > 95% Top cyclone efficiency > 95%
Meal curtain
Considered if high volatilecycles expected
Most common on N-1 stageon kiln side
LateralConsider a splitter
Kiln inlet box
No dead zoneSmooth design (entrance in the
middle)No turbulances
45- 50 slope of inlet
Downcomer
Cooling by water spraysMinimum evaporation: 4 sec
(for target at 185C)No bleed air is recommended,
except for start up
Water design target able toprovide 185 C. Take careabout moisture in gas to coalmill take off above waterinjection
ID fan preheaterVFD drive
Fresh air intake beforethe fan (fan protection)
Fan Typical Max speed 990rpm and efficiency >80%.Design margin 5% volume and1 kPa pressure
number of fans3
ID fan, raw mill fan &baghouse fan
Only 2 fans
Secondary Fuelusage
Burner preferred for Calciner
Process guidelines - Preheater - Page 2 / 2 06/10/2005 - 10:58
8/12/2019 Process Guidlines
8/20
Kiln Best Practice /Recommendation Specifications Alternatives Operating target Not advisable CommentsBack to table of contents
Equipment
Burner type and position Lafarge BurnerMAS burner in case of regularsolid fuel and alternative fuel ;
Position in center line of kilnand aligned on kiln axis (only
if kiln is stable and burnerhaving sufficient impulse)
See Lafarge Burner DesignSpreadsheet
Fuel speedSolid Fuel: 25 - 35 m/s inburner ; >25m/s in conveyingline
Solid Fuel: 25 - 35 m/s inburner ; >25m/s in conveyingline
Alternative Fuel: 25 - 40 m/sin burner ; >25m/s inconveying line
Total primary air 25 cStSwirl Design: 0,15
Impulse Design: >2,2Final design criteria to beworked out.
Retaining rings0,6 to 1 m from nosering assingle ring, triangulkar shape
Double flat barMaggoteaux system
Kiln slope 3 - 3,5 % 4%
L/D
>10,5 for preca (> 15 isrequired when designing foralternaitve fuels)> 15 for preheater
Tertiary air
From kiln hoodTake off velocity 5-6 m/sthroat and tertiary air and 25m/s in the duct
From kiln hoodTake off velocity 5-6 m/sthroat and tertiary air and 25m/s in the duct
Settling chamber Heat shield IKN not proven
Shell cooling fans 12 to 18 m/s at shell SuppliedFan should be below kiln sothat air flow comes up onboth sides.
Process guidelines - Kiln - Page 1 / 2 06/10/2005 - 10:58
8/12/2019 Process Guidlines
9/20
Kiln Best Practice /Recommendation Specifications Alternatives Operating target Not advisable CommentsBack to table of contents
Process
Thermal load< 5 MW/m (kiln cross
section)< 5 MW/m < 6.5 MW/m
Limit for refractory.Some wet and big kilns canoverpass the limit
Kiln hood velocity < 6 m/s
Kiln load
8/12/2019 Process Guidlines
10/20
Cooler Best practice /Recommendation Specifications Alternatives Operating target Not advisable CommentsBack to table of contents
EquipmentEquipment Selection Cross Bar or Walking Floor
DesignCross Bar or Walking FloorDesign
Grate load < 45 t/m d < 45 t/m d
Variable speed fans All on 1st grate Variable speed on all on 1stgrate fans. 2nd grate fans canbe with variable inlet vanesdampers
Fan dampers (inlet radial) Flap max speed typical 1500 rpm,Efficiency > 80%. Normally 20-30% pressure reserve.
Fix inlet rows 5 to 8 (1.5 - 2.5 m)Max 15 degree angleRefractory HorseshoeAir Cannons
Crusher Roller crusher intermediateor at the end
HammerCrusher
Hammer crusher can be thefirst choice if no need for veryeffective cooling
Grate slope 0 3 maximum
Evacuation hoppers Simple gate and sensor level Double gate mechanicallyactivated
ProcessAir flow design Not < 2,1 Nm3/kg > 2.1 Nm/kg ck
> 1.7 Nm/m/s on first fans, 2Nm/m/s for KIDS
First fans pressure > 10 kPa (100 mbar) for KIDS
Optimal bed depth Lowest stroke permitted with20% reserve on fans(6-8 st/min for properlydesigned cooler)
Air velocity above clinker 5 to 7 m/sClinker transport design Min. 1,5 x nominal capacitysteel conveyor
Min. 1,5 x nominal capacitysteel conveyor
Process guidelines - Cooler - Page 1 / 1 06/10/2005 - 10:59
8/12/2019 Process Guidlines
11/20
Kiln filter Best practice /Recommendation Specifications Alternatives Operating target Not advisable CommentsBack to table of contents
Equipment
Equipment SelectionLow Pressure Pulse Jet Bag
Filter ( 2,5 bars)
Low Pressure Pulse Jet (LPPJ)
Bag Filter ( 2,5 bars)
High Pressure Pulse Jet (HPPJ)Bag Filter (6bar/100psi),Electrostatic precipitator
Max dP< allowed by fancapacity at end of bag life.
Limit cleaning cycles to obtaintarget bag life.
Off line cleaning is notacceptable due to thepotential damage to the bags.
BH sizing must maintainoperating pressure drop withinthe limits of the ID fan and thepulse jet filter ability to cleanbag on line.
Equipment SizingGross Air to clothe ratio:1m/min average1.3 m/min max (upset cond)
Gross Air to clothe ratio:1m/min average1.3 m/min max (upset cond)
Bag quality
Fabric with PTFE membraneand fiberglass structure.Known suppliers: Gore, BHA,Tetratec workingat 180C- 230C max
Design temperature 230CPeak temperature 260C
P84 bags of suitableconstruction.
Adequate temperature controlto prevent teflon and SGTevaporation and bag damage.working at 180C- 230C max
Other bag materials that arenot proven.If using P84 verify the risk ofhydrolysis.
Bag quality and workmanshipare critical. Bag to cage fit iscritical.
Airflow DistributionScale model to ensure goodairflow distribution and correct
fan sizing before purchase
Compressed Air SupplyAir coolers can be acceptablefor LPPJ.
Use air dryers (dessicant) forHPPJ (-30deg C due point).
Prevent moisture condensationin the bag during thecompressed air pulse.
No oil in cleaning air.
Exhaust Fan VFD VFDFan Typical Max speed 990rpm and efficiency >80%.Design margin 15% volume
False AirDirect < 30% Preheater GasesCompound < 50% PreheaterGases
Process guidelines - Kiln and Cooler Filter - Page 1 / 2 06/10/2005 - 12:08
8/12/2019 Process Guidlines
12/20
Kiln filter Best practice /Recommendation Specifications Alternatives Operating target Not advisable CommentsBack to table of contents
COOLER FILTER
Equipment SelectionAir to air heat exchanger to
get 130C at exit
Air to air heat exchanger to
get 130C at exit
Common baghouse forRM/kiln and cooler
ESP when all cooler gas usedfor raw materials drying
Exhaust system capacity tohandle normal operation andto provide sufficient capacityfor push conditions for the fulllength of the bag life.
Gas flow in BH hopper mustnot cause abrasion of filterbags due ro high velocities.
Exhaust gas flow from thecooler straight entry andoriented downwards throughheat exchanger
Gas velocity at heatexchanger's inlet in normalconditions: 80%.Design Margin 15% volume
System SizingDesign upset conditions 450 Cexhaust gas temp. Designflow 1.7 nm3/kg clinker
Design upset conditions 450 Cexhaust gas temp. Designflow 1.7 nm3/kg clinker
Process guidelines - Kiln and Cooler Filter - Page 2 / 2 06/10/2005 - 12:08
8/12/2019 Process Guidlines
13/20
Kiln By-pass system Best practice /Recommendation Specifications Alternatives Operating target Not advisable CommentsBack to table of contents
Equipment
Dedusting Bag filters (240C) ESPWet scrubber may be asolution when cement Cl is alimitation
Dust transport As short as possibleMechanicalAir transport if Cl < 10%
StorageAs small as possible,
with mechanical extractionDirect dust addition to cooler
filter or heat exchangerintermediate storage
Addition to cooler only ifclinker storage does not
promote segregation (quality -dust separation in pile)
Process
Location take-off
On top of the smoke box, on
the kiln sideDistant from C3 discharge to
avoid dust mixing
Level of chlorine in dustDilution with kiln feed if >
10% ClCl control using cyclone system
with bypass (Taiheyo)
Quenching
Air quenching as close aspossible to the take out, eitherdirectly to 200C or at least to
400C
Air to air cooler as secondcooling step to minimize the
gas quantity
Exhaust airTo cooler fans to avoid
SO2/Dioxins
Raw mill or main stack if SO2 isacceptable, dioxins still a
threat. Detached plume also apotential issue if organics in
raw mix
Separate stack
Dust managementCement (limiting factor forClas allowed by local standard)
Clinker (limiting factor for Cl)Dust Washing with heavy
metal recovery, for low limit ofCl in cement
Dust wasting
Target level of chlorine in kilnback-end mat
1,00%Higher concentration
acceptable if possible for build-ups
Process guidelines - Kiln By-pass system - Page 1 / 1 06/10/2005 - 10:59
8/12/2019 Process Guidlines
14/20
Gas analyser Best practice /Recommendation Specifications Alternatives Operating target Not advisable CommentsBack to table of contents
Kiln inletKiln inlet
Probe
Probe long enough to enterthe kiln, retractable,
motorisedDry probe requiredWater cooled jacket
Same probe for all gasesBack flush (clean, dry air)
Oil cooledIn-situ
COMandatory
Type: IRScale: 0-20000 ppm
NOx
MandatoryType IR
No NO2 converter neededScale: 0-20000 ppm
O2Mandatory
Type: Paramagnetic0-10%
SO2
Required if Total SO3 input >1.2% on clinker basis or
S/A ratio > 1.2Type UV
Quartz cells
0-20000ppm
IR (on separated line)
Gas treatment
Heated line (>180C)2 cooler dryer 1 for SO2 and 1
for other gasesFor other gases H2O2 injection
Suspension preheater kiln - no PC
Exit of preheater tower Mandatory for O2 and CO
Exit of PrecalcinerPrecalciner
Probe
Probe at Bottom cyclone exitretractable,
Dry probe requiredWater cooled jacket
Same probe for all gasesBack flush (clean, dry air)
Process guidelines - Gas analyser - Page 1 / 2 06/10/2005 - 11:02
8/12/2019 Process Guidlines
15/20
Gas analyser Best practice /Recommendation Specifications Alternatives Operating target Not advisable CommentsBack to table of contents
COMandatory
Type: IRScale: 0-20000 ppm
NOx
MandatoryType IR
No NO2 converter neededScale: 0-20000 ppm
O2Mandatory
Type: Paramagnetic0-10%
Gas treatment
Heated line (>180C)2 cooler dryer 1 for SO2 and 1
for other gasesFor other gases H2O2 injection
3 other in line O2 last
CEM (stack)Location Follow local regulation
Dust Scattered light system
O2In-situ system (Zircon)
0-10%
H2OOptical in-situ system IR
0-10%CO
Optical in-situ system IR0-2000 mg/Nm3
Extractive with heated probeand line (>180C) + FTIR
NOxOptical in-situ system-UV
0-2000 mg/Nm3Extractive with heated probe
and line (>180C) + FTIR
SO2Optical in-situ system-UV
0-500 mg/Nm3Extractive with heated probe
and line (>180C) + FTIR
HClOptical in-situ system-IR
0-100mg/Nm3Extractive with heated probe
and line (>180C) + FTIR
COVExtractive FID
0-200mg/Nm3CO Protection with ESP
Precalciner KilnUse precalciner exit CO withpreheater exit CO as back up
Suspension preheater kilnUse kiln exit CO with
preheater exit CO as back up
Process guidelines - Gas analyser - Page 2 / 2 06/10/2005 - 11:02
8/12/2019 Process Guidlines
16/20
Coal Mill Best practice /Recommendation Specifications Alternatives Operating target Not advisable CommentsBack to table of contents
Equipment
Equipment Selection Vertical mill Vertical mill
Ball mill ,
Ring roller millsPendulum mills
Central discharge mills"deep bowl" mills
Ball mills are better suited forvery hard fuels and certain
cokes. Also need to considerturndown ratios if AF issignificant - need VFD orsomething appropriate.
Process GasHot gas from pre heater withde dusting
Hot gas from pre heater withde dusting
Direct or semi direct firing
Sensors
CO analysers:- Raw Coal Bin- Mill Filter Exit- Each Pulverised Fuel Bin
O2 analysers:- Preheater Exit- Before Mill- Mill Filter Exit
Temperature sensors- Raw coal hopper/silo
- Before mill- After mill- Hot gas duct- Filter bottom- Coal dust after filter- PF silo bottom ( In banks offour around cone)- Differential temperatureacross filter
Differential temperature acrossseparator for ball mill
Load Cells- Raw Coal Bin- Pulverised Coal Bins
Pressure indication- Before mill- After mill- Mill differential pressure- Filter differential pressure
Dust monitor- Coal bag filter main stack
Process guidelines - Coal mill - Page 1 / 2 06/10/2005 - 11:00
8/12/2019 Process Guidlines
17/20
8/12/2019 Process Guidlines
18/20
Cement Grinding Best practice /Recommendation Specifications Alternatives Operating target Not advisable CommentsBack to table of contents
Equipment
Equipment Selection Vertical Mill Vertical Mill
Roller PressPregrinding circuit with two-
compartment ball millcircuit.CKP with 2compartment mill,Ball mill
Ring roller mills,central discharge mills
Ball Mill CircuitClosed circuit mill withseparate filter for millventilation and separator
Ball mill
Single compartment withlifting and classifying liners*2,8 < L / D
8/12/2019 Process Guidlines
19/20
Cement Grinding Best practice /Recommendation Specifications Alternatives Operating target Not advisable CommentsBack to table of contents
Ventilation separatorSeparator Qf/Qa:1.8 kg/m,VFD fan for HES,
The circulating load 200%
Separator Qf/Qa:1.8 kg/m,VFD fan for HES,
The circulating load 200%
Separator Qf/Qa range: 1.8-2.5 kg/m3(200% C.L), Cementtemp 90-110 deg ,VFD for fan
Final product load32% ball charge
Higher filling causes higherspecific energy, problems forcooling. Ball charge withpregrinder needs to bemodified
Process
Control
Pre requisites for Lucie - Freshfeed variation throughweighing of separator rejects,feed accuracy with in +/- 1%,electronic ear to detect fillingof first compartment.
Belt weigher for rejectsElevator power
FeedFeed size passing on100%
8/12/2019 Process Guidlines
20/20
Weighing Dosing Best Practice /Recommendation Specifications Alternatives Operating target Not advisable Comments
Back to table of contents
Pulverised Coal
Equipment Selection
Small bins close to the burningpoint 40 m. Actual limit
is back pressure. Long distancemeans more backpressure butcan be compensated for byproper design. Schenk Starfeeder with high pressure
transport line notrecommended (low tolerance).
Schenk Coriolis + BremerScrew + FK pump for long
distance is very good.
Velocity Minimum number of elbowsvelocity >= 25 m/sMinimum number of elbows
velocity >= 25 m/s
Solid concentration 4-6 kg/nm3 4-6 kg/nm3 > 7 kg/nm3
Raw meal
Equipment Schenk Coriolis
PfisterWeigh Feeder
Both still recommend level binahead of scale to minimize siloflushes. Using airlift pressure to
calculate flow can be
sufficiently accurate.
Effective weighing Variation < 0,5 % (short term) Variation < 0,5 % (short term) Accuracy < 0,5 % (short term)
Transport Elevator Elevator Air-lift
Process guidelines - Weighing-dosing - Page 1 / 1 06/10/2005 - 11:05