-
VIETSOVPETRO - VIETNAM
NAM RONG DOI MOIRC-4 Wellhead Platform
PROCESS CONTROL PHILOSOPHY
A 18.11.08 ISSUED FOR CLIENT'S COMMENTS RM VJ AMA
REV. DATE DESCRIPTION PRPD. CHKD. APPD.
TECHNICS OFFSHORE ENGINEERING PTE LTD,
SINGAPORE
Saipem Triune Engineering Pvt. Ltd., New Delhi
PROCESS CONTROL
PHILOSOPHY
DOCUMENT NUMBER REV.
9512/08088-RC4-01-CP-001 A
SHEET 1 of 45
-
TABLE OF CONTENTS
1 INTRODUCTION..4
1.1 OBJECTIVE...4
2 GENERAL DESCRIPTION 4
3 ABBREVIATIONS5
4 BRIEF PROCESS DESCRIPTIONS.....6
5 DESIGN BASIS.8
5.1 DESIGN FLOW RATES...8
5.2 OPERATING & DESIGN CONDITIONS9
5.3 COMPOSITION OF CRUDE OIL FEED....10
5.4 COMPOSITION OF GASLIFT GAS...11
5.5 CHARECTERISTICS OF PSEUDO COMPONENTS12
5.6 METEROROLOGICAL DATA...13
5.7 SIMULATION CASES...14
6 PROCESS SYSTEM CONTROL PHILOSOPHY21
6.1 FACILITIES TO CONTROL ...21
6.2 TYPES OF BASIC CONTROL ...22
6.3 BRIEF DESCRIPTION OF MAIN CONTROL SYSTEMS ...23
3.1 PROCESS CONTRO & MONITORING SYSTEM (PCS)..23
3.2 SAFETY & EMERGENCY SHUTDOWN SYSTEM (SSD)..25
6.3.3 FIRE & GAS DETECTION & FIRE FIGHTING
(FGS)....26
6.3.4 REDUNDANT LOCAL AREA NETWORK (R-LAN)..27
6.3.5 SCADA.28
6.3.6 WELLHEAD CONTROL PANEL (WCP) .28 TECHNICS OFFSHORE
ENGINEERING PTE LTD, SINGAPORE
Saipem Triune Engineering Pvt. Ltd.,
New Delhi
PROCESS CONTROL PHILOSOPHY
DOCUMENT NUMBER REV.
9512/08088-RC4-01-CP-001 A
SHEET 2 OF 48
-
7 OPERATION AND CONTROL OF PROCESS SYSTEMS...29
7.1 WELL FLOW LINES CONTROL..29
7.2 INLET MANIFOLD CONTROL31
7.3 TEST METERING STATION32
7.4 RISERS CONTROL32
7.5 PRODUCTION SEPERATOR V-40033
7.5.1 SEPARATOR LEVEL CONTROL.34
7.5.2 SEPARATOR PRESSURE CONTROL..35
7.5.3 CUSTODY FLOW METERS..36
7.5.4 SEPARATOR OTHER CONTROL.36
7.6 VENT SCRUBBER V-200..37
7.6.1 VENT SCRUBBER TEMPERATURE CONTROL37
7.6.2 VENT SCRUBBER LEVEL CONTROL 37
7.7 CLOSE DRAIN & OPEN DRAIN SYSTEM (V-300 &
V-301)38
7.7.1 DRAIN TANKS TEMPERATURE CONTROL..39
7.7.2 DRAIN TANKS LEVEL CONTROL..39
7.8 GASLIFT DISTRIBUTION SYSTEM40
7.8.1 GASLIFT METERING STATION..40
7.8.2 GASLIFT GAS TO INDIVIDUAL WELL..41
7.8.3 GASLIFT FOR SLUG REMOVAL & FOR GAS DISPOSAL...42
7.9 CHEMICAL INJECTION SYSTEM..43
7.9.1 DEPRESSANT..43
7.9.2 DEMULSIFIER.44
TECHNICS OFFSHORE ENGINEERING PTE LTD,
SINGAPORE
Saipem Triune Engineering Pvt. Ltd.,
New Delhi
PROCESS CONTROL PHILOSOPHY
DOCUMENT NUMBER REV.
9512/08088-RC4-01-CP-001 A
SHEET 3 OF 48
-
1.INTRODUCTION
1.1 OBJECTIVE
The purpose of this document is to define the main control
functions for the process system. It
is intended that this document be used for the following.
Developing and/or reviewing P&IDs.
Guidance to control engineer in developing the instrument
hardware requirements
In developing Operating Procedures, Operating Manuals, etc.
2.GENERAL DESCRIPTION
Well fluids from DRAGON Oilfield located in the Continental
Shelf of South Vietnam, shell
be collected at RC4 Platform which is owned by VIETSOPETRO, a
Joint venture of Vietnam
& Soviet.
The RC-4 Platform comprises of the following process facilities
:
Collection of well fluid from various Wells: Wells number 01 to
09.
3 Injection Wells where Injection water is used.
Separation of Gas & liquid and transportation of gas &
liquid to the Processing platforms RP-1, RP-2 & RP-3.
Gas Lift disposal to cold vent through Vent Scrubber.
Gaslift Distribution System.
Risers balcony where Gas & Liquid from other platforms RC-5
& RC-DM are also joining.
Risers for Gaslift from RP-3 platform and distributing to other
platforms.
TECHNICS OFFSHORE ENGINEERING PTE LTD,
SINGAPORE
Saipem Triune Engineering Pvt. Ltd.,
New Delhi
PROCESS CONTROL PHILOSOPHY
DOCUMENT NUMBER REV.
9512/08088-RC4-01-CP-001 A
SHEET 4 OF 48
-
3.ABBREVIATIONS
API American Petroleum InstituteAPS Platform Abandonment
SignalAS Area Supervisory StationCCR Central Control RoomDCTS Data
Collection and Transfer System DCU Data Collection UnitDTU Data
Transfer UnitEDG Emergency Diesel GeneratorESD Emergency
ShutdownF&G Fire and GasHV High VoltageHVAC Heating Ventilation
and Air ConditioningLCP Local Control PanelLCS Local Control
SystemMCC Motor Control CentreMCC Motor Control CentreP&ID
Piping and Instrumentation diagramPA / GA Public Address / General
Alarm SystemPCS Process Control SystemPGCS Power Generation Control
SystemPLC Programmable Logic ControlPSD Process ShutdownPSMCS Power
Supply Monitoring and Control SystemRB Riser Block / BalconySCADA
Supervisory Control and Data AcquisitionSCSSV Surface Controlled
Subsurface Safety ValveSWP Satellite Well PlatformUPS
Un-interruptible Power SupplyUSD Unit ShutdownWCP Wellhead Control
panelWS Work Station
TECHNICS OFFSHORE ENGINEERING PTE LTD,
SINGAPORE
Saipem Triune Engineering Pvt. Ltd.,
New Delhi
PROCESS CONTROL PHILOSOPHY
DOCUMENT NUMBER REV.
9512/08088-RC4-01-CP-001 A
SHEET 5 OF 48
-
4.BRIEF PROCESS DESCRIPTION
The crude oil from all 9-production wells reaches to inlet
manifold skid of RC-4 via their own
respective flow lines. The manifold skid is assigned for
collection and distribution of well
product into individual process lines. It consists of blowdown
valves and 4 headers as below.
a) Well production Collection Header
b) Testing Header for well testing and metering
c) Vent Header
d) Drain Header
Fluid from wellhead passes through a choke valve to control the
flow towards production
header.
From production header, well fluid is routed to Inlet separator
which is a two phase separator
or it is directly routed to remote processing platform RP-3
through sub sea pipeline by
bypassing the inlet separator.
Separated liquid/gas mixture from separator after level control
valve is transported to RP-1 via
sub sea pipe line. The Pig Launcher is also provided at RC-4
platform on this line. Liquid/gas
mixture from platform RC-DM is also routed to RP-1 platform via
RC-4 through RC-4
liquid/gas mixture line. There is a Pig receiver at RC-4
platform on the RC-DM liquid/gas
mixture line.
Test header after the Test Metering Station is also routed to
separated liquid/gas mixture line
after Production Separator level control valve.
The Produced Gas from Production Separator after its pressure
control valve is transported to
RP-3 platform through a common gas transferring line. There are
two more similar facility
TECHNICS OFFSHORE ENGINEERING PTE LTD,
SINGAPORE
Saipem Triune Engineering Pvt. Ltd.,
New Delhi
PROCESS CONTROL PHILOSOPHY
DOCUMENT NUMBER REV.
9512/08088-RC4-01-CP-001 A
SHEET 6 OF 48
-
platforms RC-5 & RC-DM at the same area whose gas production
goes to RP-3 platform via
RC-4 platform through this common gas line to RP-3.
The Gaslift gas from processing platform RP-3 arrives at RC-4
platform via 16 Km long
pipeline. After reaching at RC-4 platform, it is divided into
three lines for RC-4, RC-5 & RC-
DM platform use. 8 Gaslift line towards RC-4 is reduced to 4 and
then goes to a metering
station. From metering station, gaslift gas is distributed to
all 9-production wells through
gaslift distribution manifold by flow controller.
The discharge of all PSVs, BDVs from manifold, Production
Separator & Gaslift distribution
system is routed to Vent Scrubber via vent header. The gaseous
discharge form Vent Scrubber
is sent to Vent Stack through liquid seal. The liquid discharge
from Vent Scrubber is collected
in Close drain Tank. The drip pan liquid collected from all
equipments and inlet manifold skid
is routed to Open Drain Tank. The combined discharge from Closed
& Open Drain Tank has
provision to transfer the material to liquid/gas mixture line
through a drain pump or directly to
disposal sump or to support vessel as produced water
accordingly.
Water Injection line from RP-3 arrives at RC-4 platform. After
reaching at RC-4 platform Riser
balcony, it is divided into three lines for RC-4, RC-5 &
RC-DM platform use. RC-4 water
injection line shall go to three injection wells. A tapping is
taken from this header for Killing
manifold which is required for 9 production wells & 3
Injection Wells at RC-4 platform.
Demulsifier and Depressant Chemicals storage and injection
facility are installed on the
platform.
TECHNICS OFFSHORE ENGINEERING PTE LTD,
SINGAPORE
Saipem Triune Engineering Pvt. Ltd.,
New Delhi
PROCESS CONTROL PHILOSOPHY
DOCUMENT NUMBER REV.
9512/08088-RC4-01-CP-001 A
SHEET 7 OF 48
-
5.DESIGN BASIS
5.1. DESIGN FLOW RATES
Production Wells 9
Injection Well 3
Liquid production 6000 Tonns/day
Oil 5500 Tonns/day
Water 500 Tonns/day
Maximum liquid per well 1200 Tonns/day
Maximum Gaslift gas for all wells 400,000 NM3/Day
Gaslift gas per Well 10000 - 50000 NM3/DayMaximum Injectivity of
an injection
well Upto 1000 m3/day
Notes:
1. Liquid production of 6000 Tonnes/day is the total maximum
design liquid capacity for
all 9 wells together.
2. Inlet production Separator Gas capacity shall be 400,000
NM3/day + Associated gas
with the crude oil based on Hysys calculation.
TECHNICS OFFSHORE ENGINEERING PTE LTD,
SINGAPORE
Saipem Triune Engineering Pvt. Ltd.,
New Delhi
PROCESS CONTROL PHILOSOPHY
DOCUMENT NUMBER REV.
9512/08088-RC4-01-CP-001 A
SHEET 8 OF 48
-
5.2. OPERATING AND DESIGN CONDITIONS
PRESSURE TEMPERATURE
Operating Design Operating Design
Bar g Bar g C C
Production Header 16-41 80 55 60
Test Header 16-41 80 55 60
Vent Header 2 11.5 55 -48 / 60
Drain Header ATM 11.5 55 60
Gaslift gas 105-110 125 22-30 45
Production Separator 16-41 60 55 60
Vent Scrubber 2 11.5 55 -48 / 60
Pig Launcher/Pig Receiver 16-41 80 55 60
Close Drain Tank 0.7 5.8 55 60
Open Drain Tank ATM 3.5 55 60
5.3. COMPOSITION OF CRUDE OIL FEED
TECHNICS OFFSHORE ENGINEERING PTE LTD,
SINGAPORE
Saipem Triune Engineering Pvt. Ltd.,
New Delhi
PROCESS CONTROL PHILOSOPHY
DOCUMENT NUMBER REV.
9512/08088-RC4-01-CP-001 A
SHEET 9 OF 48
-
Component Unit Quantity
N2+RARE Mole % 0.068
CO2 Mole % 0.038
H2S Mole % 0
CH4 Mole % 12.308
C2H6 Mole % 3.099
C3H8 Mole % 6.023
i-C4H10 Mole % 1.52
n-C4H10 Mole % 3.141
i-C5H12 Mole % 3.901
n-C5H12 Mole % 5.409
Pseudo C6 Mole % 6.766
Pseudo C7+ Mole % 57.727
Mol. Wt. g/mole 227.8
TECHNICS OFFSHORE ENGINEERING PTE LTD,
SINGAPORE
Saipem Triune Engineering Pvt. Ltd.,
New Delhi
PROCESS CONTROL PHILOSOPHY
DOCUMENT NUMBER REV.
9512/08088-RC4-01-CP-001 A
SHEET 10 OF 48
-
5.4. COMPOSITION OF GASLIFT GAS
TECHNICS OFFSHORE ENGINEERING PTE LTD,
SINGAPORE
Saipem Triune Engineering Pvt. Ltd.,
New Delhi
PROCESS CONTROL PHILOSOPHY
DOCUMENT NUMBER REV.
9512/08088-RC4-01-CP-001 A
SHEET 11 OF 48
Component Unit Quantity
N2+RARE Mole % 0.175
CO2 Mole % 0.068
H2S Mole % 0
CH4 Mole % 73.622
C2H6 Mole % 12.992
C3H8 Mole % 7.635
i-C4H10 Mole % 1.643
n-C4H10 Mole % 2.358
i-C5H12 Mole % 0.591
n-C5H12 Mole % 0.64
Pseudo C6 Mole % 0.406
Pseudo C7+ Mole % 0.119
Pseudo C8+ Mole % 0.02
Relative density 0.784
Mol. Weight g/mole 22.75
-
5.5. CHARACTERISTICS OF PSEUDO COMPONENTS
TECHNICS OFFSHORE ENGINEERING PTE LTD,
SINGAPORE
Saipem Triune Engineering Pvt. Ltd.,
New Delhi
PROCESS CONTROL PHILOSOPHY
DOCUMENT NUMBER REV.
9512/08088-RC4-01-CP-001 A
SHEET 12 OF 48
IN CRUDE OIL Normal Boiling Point (NBP)
Molecular Weight
Std. Ideal Liquid Density
Pseudo C6 66 C 86 663 kg/m3 at 20 C
Pseudo C7+ 358.8 861 - 903.9 kg/m3 at 20 C
Average density 875 kg/m3
IN GASLIFT Normal Boiling Point (NBP)
Molecular Weight
Std. Ideal Liquid Density
Pseudo C6 66 C 86 663 kg/m3 at 20 C
Pseudo C7+ 96 C 100.2 683 kg/m3 at 20 C
Pseudo C8+ 124 C 114.2 702 kg/m3 at 20 C
-
5.6. METEOROLOGICAL DATA
Climate : Salten Offshore Tropical
Max Wind Speed : 57.4 m/sec
Normal Wind Speed : 8.7 m/sec
Min, Wind Speed : 0.0 m/sec
Barometric Pressure : 996 1022.2 mbar
Ambient Air Quality
Maximum temperature outdoor air : 41 C
Minimum temperature outdoor air : 21 C
Normal temperature outdoor air : 35 C
Dry bulb temperature : 27 0F (-2.8 C) Minimum
Relative Humidity of outdoor air : Maximum 100% to Minimum
56%
Miscellaneous :
Solar Radiation : 335 kcal/ m2hr
Sea Water Temperature : 24.12 C 34.59 C
Sea water Salinity : 293 - 3459 mg/l
Sea water Density : 1018.4 - 1024.19 Kg/M3
Seismic Conditions
Maximum Seismicity : 6 Richter Scale .
5.7. SIMULATION CASES
TECHNICS OFFSHORE ENGINEERING PTE LTD,
SINGAPORE
Saipem Triune Engineering Pvt. Ltd.,
New Delhi
PROCESS CONTROL PHILOSOPHY
DOCUMENT NUMBER REV.
9512/08088-RC4-01-CP-001 A
SHEET 13 OF 48
-
The simulation is carried out to know the process conditions at
various possible cases based on
operating pressure & properties of crude oil system &
the gas lift system.
Case 1 : Oil 6000 Tonns/ DayWater 0 Tonns/ DayProduction
Separator Operating Pressure 16 BargGas Lift Operating Temperature
30 CGas Lift Operating Pressure 105 Barg
Case 2 :Oil 6000 Tonns/ DayWater 0 Tonns/ DayProduction
Separator Operating Pressure 41 BargGas Lift Operating Temperature
30 CGas Lift Operating Pressure 105 Barg
Case 3 :Oil 6000 Tonns/ DayWater 0 Tonns/ DayProduction
Separator Operating Pressure 16 BargGas Lift Operating Temperature
30 CGas Lift Operating Pressure 110 Barg
TECHNICS OFFSHORE ENGINEERING PTE LTD,
SINGAPORE
Saipem Triune Engineering Pvt. Ltd.,
New Delhi
PROCESS CONTROL PHILOSOPHY
DOCUMENT NUMBER REV.
9512/08088-RC4-01-CP-001 A
SHEET 14 OF 48
-
TECHNICS OFFSHORE ENGINEERING PTE LTD,
SINGAPORE
Saipem Triune Engineering Pvt. Ltd.,
New Delhi
PROCESS CONTROL PHILOSOPHY
DOCUMENT NUMBER REV.
9512/08088-RC4-01-CP-001 A
SHEET 15 OF 48
-
TECHNICS OFFSHORE ENGINEERING PTE LTD,
SINGAPORE
Saipem Triune Engineering Pvt. Ltd.,
New Delhi
PROCESS CONTROL PHILOSOPHY
DOCUMENT NUMBER REV.
9512/08088-RC4-01-CP-001 A
SHEET 16 OF 48
Case 4 :Oil 6000 Tonns/ DayWater 0 Tonns/ DayProduction
Separator Operating Pressure 41 Barg
Gas Lift Operating Temperature 30 CGas Lift Operating Pressure
110 Barg
Case 5 :Oil 6000 Tonns/ DayWater 0 Tonns/ Day
Production Separator Operating Pressure 16 BargGas Lift
Operating Temperature 22 C
Gas Lift Operating Pressure 105 Barg
Case 6 :Oil 6000 Tonns/ DayWater 0 Tonns/ DayProduction
Separator Operating Pressure 41 Barg
Gas Lift Operating Temperature 22 CGas Lift Operating Pressure
105 Barg
Case 7 :Oil 6000 Tonns/ DayWater 0 Tonns/ Day
Production Separator Operating Pressure 16 BargGas Lift
Operating Temperature 22 C
Gas Lift Operating Pressure 110 Barg
-
TECHNICS OFFSHORE ENGINEERING PTE LTD,
SINGAPORE
Saipem Triune Engineering Pvt. Ltd.,
New Delhi
PROCESS CONTROL PHILOSOPHY
DOCUMENT NUMBER REV.
9512/08088-RC4-01-CP-001 A
SHEET 17 OF 48
Case 8 :Oil 6000 Tonns/ DayWater 0 Tonns/ DayProduction
Separator Operating Pressure 41 BargGas Lift Operating Temperature
22 CGas Lift Operating Pressure 110 Barg
Case 9 :Oil 5500 Tonns/ DayWater 500 Tonns/ DayProduction
Separator Operating Pressure 16 BargGas Lift Operating Temperature
30 CGas Lift Operating Pressure 105 Barg
Case 10 :Oil 5500 Tonns/ DayWater 500 Tonns/ DayProduction
Separator Operating Pressure 41 BargGas Lift Operating Temperature
30 CGas Lift Operating Pressure 105 Barg
Case 11 :Oil 5500 Tonns/ DayWater 500 Tonns/ DayProduction
Separator Operating Pressure 16 BargGas Lift Operating Temperature
30 CGas Lift Operating Pressure 110 Barg
-
TECHNICS OFFSHORE ENGINEERING PTE LTD,
SINGAPORE
Saipem Triune Engineering Pvt. Ltd.,
New Delhi
PROCESS CONTROL PHILOSOPHY
DOCUMENT NUMBER REV.
9512/08088-RC4-01-CP-001 A
SHEET 18 OF 48
-
TECHNICS OFFSHORE ENGINEERING PTE LTD,
SINGAPORE
Saipem Triune Engineering Pvt. Ltd.,
New Delhi
PROCESS CONTROL PHILOSOPHY
DOCUMENT NUMBER REV.
9512/08088-RC4-01-CP-001 A
SHEET 19 OF 48
Case 12 :Oil 5500 Tonns/ DayWater 500 Tonns/ DayProduction
Separator Operating Pressure 41 BargGas Lift Operating Temperature
30 CGas Lift Operating Pressure 110 Barg
Case 13 :Oil 5500 Tonns/ DayWater 500 Tonns/ DayProduction
Separator Operating Pressure 16 BargGas Lift Operating Temperature
22 CGas Lift Operating Pressure 105 Barg
Case 14 :Oil 5500 Tonns/ DayWater 500 Tonns/ DayProduction
Separator Operating Pressure 41 BargGas Lift Operating Temperature
22 CGas Lift Operating Pressure 105 Barg
Case 15 :Oil 5500 Tonns/ DayWater 500 Tonns/ DayProduction
Separator Operating Pressure 16 BargGas Lift Operating Temperature
22 CGas Lift Operating Pressure 110 Barg
-
TECHNICS OFFSHORE ENGINEERING PTE LTD,
SINGAPORE
Saipem Triune Engineering Pvt. Ltd.,
New Delhi
PROCESS CONTROL PHILOSOPHY
DOCUMENT NUMBER REV.
9512/08088-RC4-01-CP-001 A
SHEET 20 OF 48
-
TECHNICS OFFSHORE ENGINEERING PTE LTD,
SINGAPORE
Saipem Triune Engineering Pvt. Ltd.,
New Delhi
PROCESS CONTROL PHILOSOPHY
DOCUMENT NUMBER REV.
9512/08088-RC4-01-CP-001 A
SHEET 21 OF 48
Case 16 :Oil 5500 Tonns/ DayWater 500 Tonns/ DayProduction
Separator Operating Pressure 41 BargGas Lift Operating Temperature
22 CGas Lift Operating Pressure 110 Barg
Case 17 :Oil 6000 Tonns/ DayWater 0 Tonns/ DayProduction
Separator Operating Pressure 30 BargGas Lift Operating Temperature
30 CGas Lift Operating Pressure 105 Barg
Case 18 :Oil 5500 Tonns/ DayWater 500 Tonns/ DayProduction
Separator Operating Pressure 30 BargGas Lift Operating Temperature
30 CGas Lift Operating Pressure 105 Barg
Case 19 :Oil 5500 Tonns/ DayWater 500 Tonns/ DayProduction
Separator Operating Pressure 30 BargGas Lift Operating Temperature
30 CGas Lift Operating Pressure 110 Barg
-
TECHNICS OFFSHORE ENGINEERING PTE LTD,
SINGAPORE
Saipem Triune Engineering Pvt. Ltd.,
New Delhi
PROCESS CONTROL PHILOSOPHY
DOCUMENT NUMBER REV.
9512/08088-RC4-01-CP-001 A
SHEET 22 OF 48
Case 20 :Oil 6000 Tonns/ DayWater 0 Tonns/ DayProduction
Separator Operating Pressure 30 BargGas Lift Operating Temperature
30 CGas Lift Operating Pressure 110 Barg
Case 21 :Oil 6000 Tonns/ DayWater 0 Tonns/ DayProduction
Separator Operating Pressure 30 BargGas Lift Operating Temperature
22 CGas Lift Operating Pressure 105 Barg
Case 22 :Oil 5500 Tonns/ DayWater 500 Tonns/ DayProduction
Separator Operating Pressure 30 BargGas Lift Operating Temperature
22 CGas Lift Operating Pressure 105 Barg
Case 23 :Oil 5500 Tonns/ DayWater 500 Tonns/ DayProduction
Separator Operating Pressure 30 BargGas Lift Operating Temperature
22 CGas Lift Operating Pressure 110 Barg
-
Case 24 :Oil 6000 Tonns/ DayWater 0 Tonns/ DayProduction
Separator Operating Pressure 30 BargGas Lift Operating Temperature
22 CGas Lift Operating Pressure 110 Barg
The above simulation cases have been utilized for preparation of
PFD,
Heat and Material Balance, data-sheets and other engineering
documents.
The equipment & pipelines are sized according to the
governing cases
out of above twenty four different cases.
TECHNICS OFFSHORE ENGINEERING PTE LTD,
SINGAPORE
Saipem Triune Engineering Pvt. Ltd.,
New Delhi
PROCESS CONTROL PHILOSOPHY
DOCUMENT NUMBER REV.
9512/08088-RC4-01-CP-001 A
SHEET 23 OF 48
-
6.PROCESS SYSTEM CONTROL PHILOSOPHY
6.1 FACILITIES TO CONTROL
The philosophy of automation, monitoring process control system,
safety instrumented system
& hazard-monitoring system is prepared for RC-4 platform
following facilities.
Production Wells control through Wellhead Control Panel
Injection Wells control
Process Equipments
Power generation control
Auxiliary Equipments
Fire Fighting Facility
Emergency handling
Accommodation platform control system
TECHNICS OFFSHORE ENGINEERING PTE LTD,
SINGAPORE
Saipem Triune Engineering Pvt. Ltd.,
New Delhi
PROCESS CONTROL PHILOSOPHY
DOCUMENT NUMBER REV.
9512/08088-RC4-01-CP-001 A
SHEET 24 OF 48
-
6.2 TYPES OF BASIC CONTROL
The basic control system of RC-4 Wellhead Satellite platform is
through PCS & PLC and it is
operated from the Control Room Workstation at RC-4 platform. The
monitoring & control
systems of RC-4 Platform are being done through following
systems:
Process Control System (PCS)
Safety & Emergency Shutdown System (SSD)
Fire & Gas System RC4 (FGS)
Redundant Local Area Network (R-LAN)
SCADA
Radio Equipment
24 VDC Uninterrupted Power Supply systems for monitoring,
control & safety facility including PA/GA & Radio
Equipment.
PA/GA System
Data Collection Interface (DCI)
Work-Station PCS/ SSD/ FGS (WS-1)
Wellhead Control Panel (WCP)
Navigation System Panel
TECHNICS OFFSHORE ENGINEERING PTE LTD,
SINGAPORE
Saipem Triune Engineering Pvt. Ltd.,
New Delhi
PROCESS CONTROL PHILOSOPHY
DOCUMENT NUMBER REV.
9512/08088-RC4-01-CP-001 A
SHEET 25 OF 48
-
6.3 BRIEF DESCRIPTION OF MAIN CONTROL SYSTEMS
The following control levels should be provided.
Level 0 : Field sensors & execution system
Level 1 : Hardware at the PLC basis (central panel : PCS, SSD,
FGS)
Level 2 : SCADA at RC4
(Software & hardware for supervisory control & data
acquisition)
6.3.1 PROCESS CONTROL AND MONITORING SYSTEM (PCS):
PCS should do the normal control and monitoring of the process
parameter. Moreover PCS at
RC4 platform is having facility to provide safety of personnel,
environment, equipment and
platform as a whole. PCS shall be in RC4 Platform Control Room
and should have following
minimum control.
Control of Oil & Gas Production, Processing &
transportation.
Control of Main & auxiliary process equipments.
Interface with Well Test Unit and Metering Unit.
Control & Monitoring Power Supply System.
TECHNICS OFFSHORE ENGINEERING PTE LTD,
SINGAPORE
Saipem Triune Engineering Pvt. Ltd.,
New Delhi
PROCESS CONTROL PHILOSOPHY
DOCUMENT NUMBER REV.
9512/08088-RC4-01-CP-001 A
SHEET 26 OF 48
-
The PCS should serve minimum following functions.
a) Provide graphical display of process information for
monitoring and interacting with
facility process equipment.
b) Displaying, managing & archiving the alarms and events
from all systems.
c) Continuous recording of process data in historical archive
files.
d) Graphical trending of both real time and historical data.
e) Generate production data reports.
f) Interfacing to third-party vendor systems.
g) Provide master communication protocol between all
subsystems.
h) PCS shall carry out functions of selfdiagnostics and internal
malfunction alarm.
i) PCS shall be tested without process shutdown in case of
change of software or loading of
new software.
j) PCS will have hardware panels for visual indication of
critical alarms, Critical Valves
status and Critical control switches.
Notes:
1. PCS shall be provided with 100% redundancy to take care of
failure condition of Central
Processor (CPU). Both the CPU should have same control
computation program in
synchronization so that changeover can be done without any
interruption.
TECHNICS OFFSHORE ENGINEERING PTE LTD,
SINGAPORE
Saipem Triune Engineering Pvt. Ltd.,
New Delhi
PROCESS CONTROL PHILOSOPHY
DOCUMENT NUMBER REV.
9512/08088-RC4-01-CP-001 A
SHEET 27 OF 48
-
6.3.2 SAFETY & EMERGENCY SHUTDOWN SYSTEM (SSD):
The main purpose of SSD should be to provide following as a
minimum.
Safety of staff, environment and process equipment of WHP RC-4
as a whole.
Automatic emergency shutdown of processes and equipment by
critical parameters and
also send indispensable signals to other systems.
Provide remote diagnostic calibration and testing.
Provide functions of self-diagnosis and signaling about internal
faults with automatic
registration and printing.
SSD shell be comprising of followings.
ESD-A (Emergency Shutdown Abandon Platform)
ESD-C (Shutdown due to emergency on other platforms)
PSD (Process Shutdown)
PSD-GL (Process Shutdown Gaslift)
ESD-GL (Emergency Shutdown Gaslift)
Receiving signal from FGS Panel for ESD-F & ESD-G.
The system SSD includes the equipment of following levels:
Level 0 : Field sensors of critical parameters and execution
units of emergency shutdown.
TECHNICS OFFSHORE ENGINEERING PTE LTD,
SINGAPORE
Saipem Triune Engineering Pvt. Ltd.,
New Delhi
PROCESS CONTROL PHILOSOPHY
DOCUMENT NUMBER REV.
9512/08088-RC4-01-CP-001 A
SHEET 28 OF 48
-
Level 1 : SSD-Panel (hardware on the PLC basis).
3.3 FIRE & GAS Detection and Fire Fighting Control System at
RC-4 (FGS) :
Fire and gas detection and fire-fighting control system (FGS) is
a separate dedicated system
and F&G Panel should be installed in RC-4 control room and
have autonomous standby power
supply unit. The main purpose of Fire & Gas control panel
should be to provide following as a
minimum.
Safety of staff, environment and process equipment of WHP RC-4
as a whole.
Automatic detection of the location of the Fire through UV/ IR
flame detectors system,
fusible loop and location of the HC gas leak at the different
location on the different decks
of the RC4 platform.
The FGS shall act upon receiving indication from detectors &
manual shutdown push
buttons to generate the Emergency Shutdown ESD-F or/and ESD-G
signals accordingly
and transfer the critical signals to the SSD and to the other
systems.
Automatic Control on RC-4 Fire Fighting System.
The system FGS includes the equipments of the following
levels:
Level 0 : F&G field detectors, actuators of RC-4
fire-fighting systems.
Level 1 : FGS-Panel (hardware at PLC base).
TECHNICS OFFSHORE ENGINEERING PTE LTD,
SINGAPORE
Saipem Triune Engineering Pvt. Ltd.,
New Delhi
PROCESS CONTROL PHILOSOPHY
DOCUMENT NUMBER REV.
9512/08088-RC4-01-CP-001 A
SHEET 29 OF 48
-
FGS shall provide the following levels of shut down according to
level of danger for personnel,
environment, process equipment, and platform as a whole.
ESD-F : Emergency shutdown and process blow-down for personnel
safety and equipment/
unit safety. Furthermore APS push buttons for activation of ESD
signals to abandon
platform shall be provided.
ESD-G: Emergency shutdown and bringing technological processes
and equipment in safe
condition but without pressure blowdown except to release high
pressure Gaslift
system.
The F & G system at RC4 shall cover only RC-4 platform.
Control system shall execute auto
and remote control of systems and devices for extinguishing of
fire at RC-4 (Fire fighting
system fire water pump, fire monitor, fire sprinkler, foam
system, CO2 etc) as well as
switching off the HVAC system.
3.4 REDUNDANT LOCAL AREA NETWORK (R-LAN):
Local Information Network should have connection with PCS &
PLC (SSD) through
necessary software and external interfaces.
Local Area network (R-LAN) shall transfer the information from
PCS to SCADA.
Information by Radio Channel should transfer through R-LAN. It
includes ESD-C
information to / from processing platform RP-3 & RP-1.
TECHNICS OFFSHORE ENGINEERING PTE LTD,
SINGAPORE
Saipem Triune Engineering Pvt. Ltd.,
New Delhi
PROCESS CONTROL PHILOSOPHY
DOCUMENT NUMBER REV.
9512/08088-RC4-01-CP-001 A
SHEET 30 OF 48
-
3.5 SCADA (Supervisory Control and Data Acquisition)
SCADA should provide receiving / transferring, processing,
registration, storage and visual
display of the information on workstations from/to systems PCS,
SSD, FGS and receiving /
transferring of the necessary information through DCI by the
radio channel. It should be
provided with ability to retrieve from archive the basic process
parameters (PT/TT - of each
separate well, PT / TT / LT - of process equipment), Well Test
Unit and Metering Unit with
indication in WS-1, demonstrating parameters variation diagrams
of each separate well and
technological process for a certain time or for all period of
data storage. SCADA should
provide warning signaling (as the controlled process parameters
over set points) and alarm
signaling (in emergencies) - light and sound signaling at
workstation (WS-1).
3.6 Wellhead Control Panel (WCP):
WCP- should provide with the following remote controls from the
system SSD:
a) Shutdown of separate wells (PSD-Closed WSSV, PSD-Closed MSSV)
- automatically from
the process control instruments or manually by the command of
operator technologist
from workstation WS-1;
a) Shutdown of all wells (ESD-Closed all WSSV / MSSV / SCSSV) -
automatically from the
control instruments/systems or manually by the ESD command of
operator technologist
from workstation WS-1
TECHNICS OFFSHORE ENGINEERING PTE LTD,
SINGAPORE
Saipem Triune Engineering Pvt. Ltd.,
New Delhi
PROCESS CONTROL PHILOSOPHY
DOCUMENT NUMBER REV.
9512/08088-RC4-01-CP-001 A
SHEET 31 OF 48
-
7 OPERATION AND CONTROL OF PROCESS SYSTEMS
Description of the operation and control of the process is
divided into different sections as
below.
Well Flow lines
Inlet Manifold
Test Metering Station
Risers
Production Separator
Vent Scrubber
Open & Close Drain system
Gaslift Distribution system
Chemicals Injection
7.1 Well Flow lines Control
There are nine separate wells with wellheads and flow lines at
the RC-4 Wellhead platform. The
wellhead of every well is consists of the following main
instrumentations.
For isolating a Well, there is underwater Sub Surface Safety
Valve (SCSSV) and One master &
One wing valve on the wellhead.
TECHNICS OFFSHORE ENGINEERING PTE LTD,
SINGAPORE
Saipem Triune Engineering Pvt. Ltd.,
New Delhi
PROCESS CONTROL PHILOSOPHY
DOCUMENT NUMBER REV.
9512/08088-RC4-01-CP-001 A
SHEET 32 OF 48
-
Master Surface Safety valves (RC4-MSSV-0011/ 0021/ 0031/ 0041/
0051/ 0061/ 0071/
0081/ 0091).
Wing Surface safety valves (RC4-WWSSV 0011/ 0021/ 0031/ 0041/
0051/ 0061/ 0071/
0081/ 0091).
Positive Flow chock Valves (RC4-FV-0011/ 0021/ 0031/ 0041/ 0051/
0061/ 0071/ 0081/
0091).
The chock valves are hydraulically actuated step by step. Choke
valve shall close only after
wing valve closes (upon LSD or manual initiation), Choke valve
closing time is adjustable.
Reopening of choke valve is only possible only when wing valve
is fully open.
The low & high pressure switches are provided on each well
flow line after the Chock valves.
The tag numbers are RC4-PSHL 0011/ 0021/ 0031/ 0041/ 0051/ 0061/
0071/ 0081/ 0091
respectively. PSHL will create electrical signal at high
pressure of 50 barg & low pressure of
10 barg, which goes to Well Head Control Panel (WHCP) to
shutdown the individual Well.
Each flow line is protected against high pressure by providing a
Shutdown valve SDV (RC4-
SDV-0011/ 0021/ 0031/ 0041/ 0051/ 0061/ 0071/ 0081/ 0091
respectively for 9 wells) followed
by three pressure transmitters, which shall be used for shutdown
purpose. On actual high
pressure in the individual flow lines, the indication from these
three pressure transmitters shall
generate Pressure High High alarm signals in PLC and based on
the 2 out of 3 voting system,
PLC shall activate the Pressure High High interlock
(RC4-PAHH-1011/ 1021/ 1031/ 1041/
1051/ 1061/ 1071/1081/ 1091 respectively for 9 production wells)
which shall shutdown the
SDV in flow line and other appropriate shutdown of the
system.
(For detail , see the Cause & Effect Matrix)
TECHNICS OFFSHORE ENGINEERING PTE LTD,
SINGAPORE
Saipem Triune Engineering Pvt. Ltd.,
New Delhi
PROCESS CONTROL PHILOSOPHY
DOCUMENT NUMBER REV.
9512/08088-RC4-01-CP-001 A
SHEET 33 OF 48
-
Each well flow line is having a check valve and a safety valve.
The operating temperature of
each flow line is 55 degC and the operating pressure range is
from 16 to 41 barg.
7.2 Inlet manifold Control
Inlet manifold is having four headers, Production Header, Test
Header, Vent Header & Drain
Header.
The production Header is designed to receive the crude oil from
all the flow lines together.
Production Header is provided with local pressure &
temperature gauges and a pressure
transmitter with Low & High pressure alarms on PCS. To
release the pressure of production
header, blowdown valve RC4-BDV-1001 is provided to depressurize
it, which operate
automatically on ESD.
A Test header is provided at the Inlet manifold which allows
testing of each well separately. To
release the pressure of test header, blowdown valve RC4-BDV-1002
is provided, which operate
automatically on ESD.
The operating pressure of these headers is 16-41 barg &
operating temperature is 55
degC.
TECHNICS OFFSHORE ENGINEERING PTE LTD,
SINGAPORE
Saipem Triune Engineering Pvt. Ltd.,
New Delhi
PROCESS CONTROL PHILOSOPHY
DOCUMENT NUMBER REV.
9512/08088-RC4-01-CP-001 A
SHEET 34 OF 48
-
7.3 Test Metering Station
As such there is no control on the test metering station.
Whenever a well is to be tested for its
components, that flow line is to be lined-up to the test header.
From test header, flow is routed
to the metering station. On metering station, a Multi Phase Flow
devise is provided which shall
indicate the flow rate of Gas, Oil & Water in the crude oil
stream.
7.4 RISERS CONTROL
All the platforms (RC-4, RC-5, RC-DM, RP-1, RP-2, RP-3) produced
gas, mixture of oil &
gas, Gaslift gas & water injection are interconnected
through risers.
Produced gas from RC-5 (Riser-06) & RC-DM (Riser-07) are
coming to RC-4 platform &
from here altogether with RC-4 Produced Gas, these are
transferred to RP-3 / RP-2 platform
through Riser-08.
Mixture of oil & gas from RC-DM (Riser-05) is coming to RC-4
platform & from here
altogether with RC-4 they are transferred via Riser 04 to RP-1
through RC-5 platform.
Gaslift gas from RP-3 (Riser-02) is coming to RC-4 platform
& from here it is getting
distributed to RC-DM (Riser-03), RC-5 (Riser-01) & RC-4
usage.
Water for injection is coming from RP-3 (Riser-09) on RC-4
platform & from here it is
getting distributed to RC-4, RC-5 (Riser-10) & RC-DM
(Riser-11).
TECHNICS OFFSHORE ENGINEERING PTE LTD,
SINGAPORE
Saipem Triune Engineering Pvt. Ltd.,
New Delhi
PROCESS CONTROL PHILOSOPHY
DOCUMENT NUMBER REV.
9512/08088-RC4-01-CP-001 A
SHEET 35 OF 48
-
Shutdown Valves SDVs are provided on the Risers where service is
Hydrocarbon fluids.
Hand Operated valves are provided in water injection line with
limit switches to know the
open & close status of these hand valves on Risers.
In case of emergency on Risers, low low pressure & high high
pressure on Produced Gas &
Liquid Risers and only low low pressure on Gaslift Risers are
provided to shutdown the
respective SDV and other related SDV accordingly.
(For detail , see the Cause & Effect Matrix)
7.5 PRODUCTION SEPARATOR V-400 :
Crude Oil from Production header enters into the Production
Separator. The operating
pressure of at 16-41 barg and 55C. Production Separator is a 2
phase Horizontal separator to
separate well fluid into gas & liquid phase. Liquid,
containing oil & water, is collected in
bottom and provided to stay in the separator for some
predetermined time based on the load
to disengage the trapped gases before going out from separator
bottom.
Produced gas from separator overhead under separator pressure
control is transferred to
processing platform RP-3 while the produced liquid from
separator bottom under level
control is transferred to processing platform RP-1 via RC-5
platform.
TECHNICS OFFSHORE ENGINEERING PTE LTD,
SINGAPORE
Saipem Triune Engineering Pvt. Ltd.,
New Delhi
PROCESS CONTROL PHILOSOPHY
DOCUMENT NUMBER REV.
9512/08088-RC4-01-CP-001 A
SHEET 36 OF 48
-
7.5.1 PRODUCTION SEPARATOR LEVEL CONTROL:
Production separator liquid level is monitored and controlled by
Interface level controller
RC4-LIC-400 on auto mode by operating level control valve
RC4-LCV-400, which is located
at separator bottom outlet liquid line. Level controller gets
the indication from local level
transmitter RC4-LT-400 that is installed on standpipe of
production separator. It keeps a
watch on interface level and hence relative liquid residence
time in the separator to ensure
effective separation.
NOTE:
1. On level transmitter failure, its indication should show bad
value with alarm and
level controller should be forced automatically to go on Manual
mode from Auto
mode, leaving Level Control valve at its last output
position.
2. Above action shall give the warning alarm to operation
personnel but considering
the normal steady rate, unnecessary shutdown can be avoided.
Another level transmitter RC4-LTS-401 is provided on separator
to keep watch on its very
low and very high level and during such condition, this
transmitter signal to PLC generate
Low-Low level alarms or High-high level alarms to take proper
action through PLC.
(For detail , see the Cause & Effect Matrix)
However, as same level control valve RC4-LCV-400 is to get trip
through PLC in case of low
low level in separator so proper instrumentation system is
required for the operation of this
valve during normal and emergency.
TECHNICS OFFSHORE ENGINEERING PTE LTD,
SINGAPORE
Saipem Triune Engineering Pvt. Ltd.,
New Delhi
PROCESS CONTROL PHILOSOPHY
DOCUMENT NUMBER REV.
9512/08088-RC4-01-CP-001 A
SHEET 37 OF 48
-
7.5.2 PRODUCTION SEPARATOR PRESSURE CONTROL:
Production separator pressure is monitored and controlled by
Interface pressure controller
RC4-PIC-400 on auto mode by operating pressure control valve
RC4-PCV-400, which is
located at separator overhead outlet gas line. Pressure
controller gets the indication from
local pressure transmitter RC4-PT-400. Depending on the
operating scenarios between the
other platform, its set point is to be decided which can vary
from 16 barg to 41 barg.
NOTE:
3. On pressure transmitter failure, its indication should show
bad value with alarm and
pressure controller should be forced automatically to go on
Manual mode from
Auto mode, leaving pressure Control valve at its last output
position.
4. Above action shall give the warning alarm to operation
personnel but considering
the normal steady rate, unnecessary shutdown can be avoided.
Another pressure transmitter RC4-PTS-402 is provided on
separator to keep watch on its
very low and very high pressure and during such condition, this
transmitter signal to PLC
generate Low-Low pressure alarms or High-high pressure alarms to
take proper action
through PLC.
(For detail , see the Cause & Effect Matrix)
However, as same pressure control valve RC4-PCV-400 is to get
trip through PLC in case of
low low pressure in separator so proper instrumentation system
is required for the operation
of this valve during normal and emergency.
TECHNICS OFFSHORE ENGINEERING PTE LTD,
SINGAPORE
Saipem Triune Engineering Pvt. Ltd.,
New Delhi
PROCESS CONTROL PHILOSOPHY
DOCUMENT NUMBER REV.
9512/08088-RC4-01-CP-001 A
SHEET 38 OF 48
-
7.5.3 CUSTODY FLOW METERS
Custody flow meter RC4-FT-401 is provided in outlet gas line
from separator. Being a custody
meter, proper pressure and temperature compensation is provided
on Gas Flow meter by
pressure transmitter RC4-PT-401 & RC4-TT-401. The
compensated flow is indicated by RC4-
FI-401 on PCS and the Cumulative flow is indicated by
RC4-FQI-401 on PCS.
Custody flow meter RC4-FT-402 is provided in outlet liquid line
from separator. RC4- FI-402
indicates the flow on PCS and the Cumulative flow is indicated
by RC4-FQI-402 on PCS.
7.5.4 OTHER MONITORING & CONTROL IN PRODUCTION SEPARATOR
a)Gas outlet demister pad differential pressure transmitter is
provided to know about the
chocking in the demister pad.
b)Temperature transmitter RC4-TT-402 is provided in liquid phase
and its indication RC4-TI-
402 is provided on PCS.
c)Blow-down facility is provided to reduce pressure in the
separator in case of fire or other
emergencies.
TECHNICS OFFSHORE ENGINEERING PTE LTD,
SINGAPORE
Saipem Triune Engineering Pvt. Ltd.,
New Delhi
PROCESS CONTROL PHILOSOPHY
DOCUMENT NUMBER REV.
9512/08088-RC4-01-CP-001 A
SHEET 39 OF 48
-
7.6 VENT SCRUBBER V-200:
The vent scrubber separates hydrocarbon liquid carried over by
the gas in the vent header. The
knocked out vapor goes to vent tip while the accumulated liquid
is transferred to closed drain
tank V-301 by gravity. There is provision to empty out the
scrubber through Drain pump.
7.6.1 VENT SCRUBBER TEMPERATURE CONTROL :
During emergency release of gas & liquid from process
system, there is potential of low
temperature discharge in the vent header & vent scrubber. An
immersion electric heater RC4-
HT-200 is provided in the Vent Scrubber in liquid phase, which
is operated to control the vent
scrubber liquid phase temperature to avoid congealing of the
oil. A temperature switch RC4-
TSH-200 is provided in the liquid phase to control the ON / OFF
power to the heater. In normal
operation while no liquid is there, this heater should remain
OFF.
The normal operating temperature in the system is 55 degC but
the set point of TSH can be
kept much below 55 degC, depending upon the characteristic of
the crude in the vent & drain
headers. There is a temperature transmitter RC4-TT-200 in liquid
phase whose indication RC4-
TI-200 comes on PCS with high and low alarms on PCS.
7.6.2 VENT SCRUBBER LEVEL CONTROL :
In normal operation, as such there is no level control on vent
scrubber. But during any
emergency discharge, during draining of a system or due to any
upset, the level can go up. So
to avoid liquid to go into the scrubber overhead vent, a high
high level protection is provided.
TECHNICS OFFSHORE ENGINEERING PTE LTD,
SINGAPORE
Saipem Triune Engineering Pvt. Ltd.,
New Delhi
PROCESS CONTROL PHILOSOPHY
DOCUMENT NUMBER REV.
9512/08088-RC4-01-CP-001 A
SHEET 40 OF 48
-
Level transmitter RC4-LT-200 on the scrubber shall provide the
level indication to PCS with
low & high alarms. Same LT indication is also going to PLC
and during very high level, RC4-
LAHH-200 shall initiate the PSD interlock to take the shutdown
of the process shutdown.
During low low level, signal RC4-LALL-200 shall come to the soft
selector switch RC4-SS-
300 which is located on PCS and if the vent scrubber is selected
for drain pump, then RC4-
LALL-200 shall activate USD via RC4-SS-300 which shall send
signal to MCC to stop motor
of drain pump RC4-H-311.
7.7 CLOSE DRAIN & OPEN DRAIN SYSTEM:
Overall Drain system consists of Open drain header, closed drain
header, Closed drain tank (V-
301), Open drain tank (V-300) and a common reciprocating drain
pump RC4-H-311.
Close drain tank is receiving the liquid from closed drain
header where equipment draining is
lined up. Vent Scrubber can also be drained into the Close drain
tank. In normal operation,
there is no such draining. The open drain tank receives flow
from all drip pans liquid collected
from all equipments & inlet manifold skid. Generally this
header is not a pressurized header
and should be self-drain towards the open drain tank.
Vapours from V-300 & V-301 are vented to atmosphere via
flame arrestor. The HC liquid is
transferred by drain pump RC4-H-311 to mixture of oil & gas
liquid line to RP-1. During
maintenance, whatever the liquid is collected in the Drain
Tanks, that can be send to disposal
system or produced water to support vessel accordingly.
TECHNICS OFFSHORE ENGINEERING PTE LTD,
SINGAPORE
Saipem Triune Engineering Pvt. Ltd.,
New Delhi
PROCESS CONTROL PHILOSOPHY
DOCUMENT NUMBER REV.
9512/08088-RC4-01-CP-001 A
SHEET 41 OF 48
-
7.7.1 OPEN DRAIN & CLOSED DRAIN TANK TEMPERATURE
CONTROL:
During emergency release of gas & liquid from process
system, there is potential of low
temperature discharge in the vent header & vent scrubber.
Vent scrubber can be drained into the
closed drain tank or liquid can come to the tank directly from
the drain header. An electric
heater RC4-HT-301 is provided in the Close Drain Tank in liquid
phase, which is operated to
control the tank liquid phase temperature. A temperature switch
RC4-TSH-301 is provided in
the liquid phase to control the ON / OFF power to the heater. In
normal operation while no
liquid is there, this heater should remain OFF.
The normal operating temperature in the system is 55 degC but
the set point of TSH can be
kept much below 55 degC, depending upon the characteristic of
the crude in the vent & drain
headers. Local temperature gauge RC4-TG-301 is provided on the
close drain tank in the
liquid phase.
7.7.2 OPEN DRAIN & CLOSED DRAIN TANK LEVEL CONTROL:
In normal operation, as such there is no level control on both
the tank. But during any
emergency discharge, during draining of a system or due to any
upset or vessels maintenance
drain, the level can go up. So to avoid liquid to go into the
overhead vent, an overflow line is
provided on both the vessels. But for low level protection,
level transmitter RC4-LT-300 &
RC4-LT-301 are provided respectively on open & close
drain.
TECHNICS OFFSHORE ENGINEERING PTE LTD,
SINGAPORE
Saipem Triune Engineering Pvt. Ltd.,
New Delhi
PROCESS CONTROL PHILOSOPHY
DOCUMENT NUMBER REV.
9512/08088-RC4-01-CP-001 A
SHEET 42 OF 48
-
During low low level, signal RC4-LALL-300 OR RC4-LALL-301 shall
come to the soft
selector switch RC4-SS-300 that is located on PCS. According to
the selection of the
equipment Level in selector switch, the interlock shall initiate
to activate USD via RC4-SS-
300. USD shall send signal to MCC to stop motor of drain pump
RC4-H-311.
7.8 GASLIFT DISTRIBUTION SYSTEM
7.8.1 GASLIFT METERING STATION
Gaslift gas line of 8, coming from processing platform RP-3
through RISER-02, is reduced to
4 followed by a Shutdown Valve RC4-SDV-800 and Gaslift metering
station. Transmitter
RC4-FT-801 monitors Gaslift gas flow towards RC4. The flow
device is Simplex change type
orifice fitting with four bored plates, one per range. As the
requirement of Gaslift in the well
can vary from minimum required to maximum so to cover the wide
range of flow rates with
accuracy, Gas metering station shall provide three flow ranges
for which three different bore
size orifice plates are to be kept ready to install in the
orifice fittings as required. Based on the
design capacity of Gaslift system and the minimum requirement of
Gaslift to one well, the
range of these orifices is to be decided during detailed
engineering.
The flow transmitter indication RC4-FI-801A shall display on
PCS. Pressure Transmitter RC4-
PT-802 & Temperature Transmitter RC4-TT-801 are provided for
pressure & temperature
compensation to the gaslift flow. The compensated flow is
indicated by RC4-FI-801 and the
cumulative flow is indicated by RC4-FQI-801 on PCS.
TECHNICS OFFSHORE ENGINEERING PTE LTD,
SINGAPORE
Saipem Triune Engineering Pvt. Ltd.,
New Delhi
PROCESS CONTROL PHILOSOPHY
DOCUMENT NUMBER REV.
9512/08088-RC4-01-CP-001 A
SHEET 43 OF 48
-
In emergency on platform or on the gaslift metering station, a
blowdown vlave RC4-BDV-801
is provided to release the pressure.
7.8.2 GASLIFT GAS TO INDIVIDUAL WELL
Gaslift from metering station shall go to the gas distribution
manifold where gas is distributed
to all wells. Gaslift flow is being controlled towards each well
through an angle valve with
diaphragm actuator (RC4-FCV-811/ 812/ 813/ 814/ 815/ 816/ 817/
818/ 819 respectively for 9
wells). Flow is being monitored by flow transmitters RC4-FT-811/
812/ 813/ 814/ 815/ 816/
817/ 818/ 819 respectively for 9 wells). The individual flow
device is Simplex change type
orifice fitting with four bored plates, one per range.
The requirement of Gaslift in the well can vary from minimum
required to maximum or even
intermittent use of gaslift, depending on the oil capacity in
the wells. To cover the wide range
of flow rates with accuracy, each line is be provided with four
flow ranges for which four
different bore size orifice plates are to be kept ready to
install in the orifice fittings as required
by mode of operation. Based on the design capacity of Gaslift
system and the minimum
requirement of Gaslift to one well, the range of these orifices
is to be decided during detailed
engineering.
A selector switch is provided on PCS for selecting Installed
Bore size which shall be the
input to the PLC base controller RC4-FY-811/ 812/ 813/ 814/ 815/
816/ 817/ 818/ 819
respectively for 9 wells. The PLC based logic shall work
according to wide range of gaslift
requirement & header pressure. Accordingly it shall provide
the remote set point to the flow
controller RC4-FIC-811/ 812/ 813/ 814/ 815/ 816/ 817/ 818/ 819
respectively for 9 wells
through PCS computer controller RC4-PY-811/812/ 813/ 814/ 815/
816/ 817/ 818/ 819
TECHNICS OFFSHORE ENGINEERING PTE LTD,
SINGAPORE
Saipem Triune Engineering Pvt. Ltd.,
New Delhi
PROCESS CONTROL PHILOSOPHY
DOCUMENT NUMBER REV.
9512/08088-RC4-01-CP-001 A
SHEET 44 OF 48
-
respectively for 9 wells which shall also take the measured
value of downstream pressure RC4-
PI-821/ 822/ 823/ 824/ 825/ 826/ 827/ 828/ 829 on PCS through
local pressure transmitters
RC4-PT-821/ 822/ 823/ 824/ 825/ 826/ 827/ 828/ 829. For detailed
modes of operation, refer
Gaslift Operation philosophy of VSP platforms.
Two chock valves are provided from main header to one bypass
header to provide controlled
gas in case of maintenance of the main flow control angle
valves.
7.8.3 GASLIFT USE FOR SLUG REMOVAL & FOR GAS DISPOSAL.
As the disposal of Gaslift is related to the underwater pipes
before RISERS which are Gaslift
main pipe from RP-3 platform to RC-4 Platform, Gaslift pipe to
RC5 & RC-DM platforms, the
take off point of this line are taken directly from three
Gaslift Risers at RC4 platform.
A shutdown valve RC4-SDV-802 is provided in the common disposal
line. A chock valve is
provided to throttle the flow. As this line is also to be used
for removal of the slug
accumulation in the Production separator gas outlet line whose
design pressure is 60 barg so
high pressure protection levels are given by providing three
pressure transmitters RC4-PT-
803A / 803B / 803C. On actual high pressure in this section of
gaslift line after chock valve
during disposal or slug removal, the indication from these three
pressure transmitters shall
generate Pressure High High alarm signals in PLC and based on
the 2 out of 3 voting system,
PLC shall activate the Pressure High High interlock RC4-PAHH-803
which shall shutdown the
RC4-SDV-802 in the gaslift disposal line.
TECHNICS OFFSHORE ENGINEERING PTE LTD,
SINGAPORE
Saipem Triune Engineering Pvt. Ltd.,
New Delhi
PROCESS CONTROL PHILOSOPHY
DOCUMENT NUMBER REV.
9512/08088-RC4-01-CP-001 A
SHEET 45 OF 48
-
As 2nd level of safety, a pressure safety valve RC4-PSV-801 is
also provided in this gaslift
section.
As the disposal is to be done from high pressure to low pressure
through chock valve, there is
potential of low temperature in this section if the disposal is
not controlled properly. So a low
temperature protection is given by providing a temperature
transmitter RC4-TT-804 which
shall generate the low temperature alarm signal in PLC and PLC
shall activate RC4-TALL-804
to shutdown the RC4-SDV-802 in gaslift disposal line.
7.9 CHEMICAL INJECTION SYSTEM
The Chemical Injection System includes dosing of the following
Chemicals:
Depressant
Demulsifier
7.9.1 DEPRESSANT
Depressant Unloading is done from container by Unloading Pumps
(H-700A5-1/ H-700A5-2).
There are four Depressant Storage Tanks E-700A2-1, E-700A2-2
with capacity of 10 M3 each
and E-700A3-1 & E-700A4-1 with capacity of 20 M3 each.
Chemical can be transferred from
Jack-up drilling Rig to storage tank.
TECHNICS OFFSHORE ENGINEERING PTE LTD,
SINGAPORE
Saipem Triune Engineering Pvt. Ltd.,
New Delhi
PROCESS CONTROL PHILOSOPHY
DOCUMENT NUMBER REV.
9512/08088-RC4-01-CP-001 A
SHEET 46 OF 48
-
Depressant Dosing pumps H-700A1-01/700A1-02/ 700A1-03/ 700A1-04/
700A1-05/ 700A1-
06/ 700A1-07/ 700A1-08/ 700A1-09/ 700A1-10/ 700A1-11 are
pneumatic operated pumps and
the pumps discharge has provision to inject the chemical to two
different points which are X-
Mas tree at down hole & at upstream of flow choke valve at
well head.
To start the dozing pump, instrument air valves (RC4-XV-711/
712/ 713/ 714/ 715/ 716/ 717/
718/ 719/ 720/ 721) are to be opened which can be done by local
hand switches RC4-HS-
711AA / 712AA/ 713AA/ 714AA / 715AA/ 716AA/ 717AA/ 718AA/ 719AA/
720AA/ 721AA
respectively and similarly to stop the pump, same instrument air
valves are to be closed which
can be done by either local hand switches RC4-HS-711AB / 712AB/
713AB/ 714AB / 715AB/
716AB/ 717AB/ 718AB/ 719AB/ 720AB/ 721AB respectively OR from
remote hand switches
RC4-HS-711B/ 712B/ 713B/ 714B/ 715B/ 716B/ 717B/ 718B/ 719B/
720B/ 721B on PCS.
There is trip of individual pump based on PSD-Well flow lines
but the two common
Deprassant Chemical injection pumps H-700A1-10/700A1-11 shall
not trip on any individual
Well PSD actuation. But if it is lined up towards any shutdown
well then it is required to stop
manually which is to be ensured through proper operating
procedure and alarms.
7.9.2 DEMULSIFIER
Demulsifier Unloading is done from container by Unloading Pumps
(H-700B5-1/ H-700B5-2).
There are two Demulsifier Storage Tanks E-700B2-1, E-700B2-2
with capacity of 2 M3 each.
Chemical can be transferred from Jack-up drilling Rig to storage
tank.
TECHNICS OFFSHORE ENGINEERING PTE LTD,
SINGAPORE
Saipem Triune Engineering Pvt. Ltd.,
New Delhi
PROCESS CONTROL PHILOSOPHY
DOCUMENT NUMBER REV.
9512/08088-RC4-01-CP-001 A
SHEET 47 OF 48
-
Demulsifier Dosing pumps H-700B1-01/700B1-02/ 700B1-03/
700B1-04/ 700B1-05/ 700B1-
06/ 700B1-07/ 700B1-08/ 700B1-09/ 700B1-10/ 700B1-11 are
pneumatic operated pumps and
the pumps discharge has provision to inject the chemical to two
different points which are X-
Mas tree at down hole & at upstream of flow choke valve at
well head.
To start the dozing pump, instrument air valves (RC4-XV-761/
762/ 763/ 764/ 765/ 766/ 767/
768/ 769/ 770/ 771) are to be opened which can be done by local
hand switches RC4-HS-
761AA / 762AA/ 763AA/ 764AA / 765AA/ 766AA/ 767AA/ 768AA/ 769AA/
770AA/ 771AA
respectively and similarly to stop the pump, same instrument air
valves are to be closed which
can be done by either local hand switches RC4-HS-761AB / 762AB/
763AB/ 764AB / 765AB/
766AB/ 767AB/ 768AB/ 769AB/ 770AB/ 771AB respectively OR from
remote hand switches
RC4-HS-761B/ 762B/ 763B/ 764B/ 765B/ 766B/ 767B/ 768B/ 769B/
770B/ 771B on PCS.
There is trip of individual pump based on PSD-Well flow lines
but the two common
Demulsifier Chemical injection pumps H-700B1-10/700B1-11 shall
not trip on any individual
Well PSD actuation. But if it is lined up towards any shutdown
well then it is required to stop
manually which is to be ensured through proper operating
procedure and alarms.
*****************************************************************************
TECHNICS OFFSHORE ENGINEERING PTE LTD,
SINGAPORE
Saipem Triune Engineering Pvt. Ltd.,
New Delhi
PROCESS CONTROL PHILOSOPHY
DOCUMENT NUMBER REV.
9512/08088-RC4-01-CP-001 A
SHEET 48 OF 48
VIETSOVPETRO - VIETNAMSHEET 1 of 45
5.1.DESIGN FLOW RATES5.2.OPERATING AND DESIGN
CONDITIONS5.3.COMPOSITION OF CRUDE OIL FEED5.4. COMPOSITION OF
GASLIFT GAS5.5. CHARACTERISTICS OF PSEUDO
COMPONENTS5.6.METEOROLOGICAL DATA Seismic Conditions5.7.SIMULATION
CASES