Top Banner
VIETSOVPETRO - VIETNAM NAM RONG – DOI MOI RC-4 Wellhead Platform PROCESS CONTROL PHILOSOPHY A 18.11.08 ISSUED FOR CLIENT'S COMMENTS RM VJ AMA REV. DATE DESCRIPTION PRPD. CHKD. APPD. TECHNICS OFFSHORE ENGINEERING PTE LTD, SINGAPORE Saipem Triune Engineering Pvt. Ltd., New Delhi PROCESS CONTROL PHILOSOPHY DOCUMENT NUMBER REV. 9512/08088-RC4-01-CP-001 A SHEET 1 of 45
48
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
  • VIETSOVPETRO - VIETNAM

    NAM RONG DOI MOIRC-4 Wellhead Platform

    PROCESS CONTROL PHILOSOPHY

    A 18.11.08 ISSUED FOR CLIENT'S COMMENTS RM VJ AMA

    REV. DATE DESCRIPTION PRPD. CHKD. APPD.

    TECHNICS OFFSHORE ENGINEERING PTE LTD,

    SINGAPORE

    Saipem Triune Engineering Pvt. Ltd., New Delhi

    PROCESS CONTROL

    PHILOSOPHY

    DOCUMENT NUMBER REV.

    9512/08088-RC4-01-CP-001 A

    SHEET 1 of 45

  • TABLE OF CONTENTS

    1 INTRODUCTION..4

    1.1 OBJECTIVE...4

    2 GENERAL DESCRIPTION 4

    3 ABBREVIATIONS5

    4 BRIEF PROCESS DESCRIPTIONS.....6

    5 DESIGN BASIS.8

    5.1 DESIGN FLOW RATES...8

    5.2 OPERATING & DESIGN CONDITIONS9

    5.3 COMPOSITION OF CRUDE OIL FEED....10

    5.4 COMPOSITION OF GASLIFT GAS...11

    5.5 CHARECTERISTICS OF PSEUDO COMPONENTS12

    5.6 METEROROLOGICAL DATA...13

    5.7 SIMULATION CASES...14

    6 PROCESS SYSTEM CONTROL PHILOSOPHY21

    6.1 FACILITIES TO CONTROL ...21

    6.2 TYPES OF BASIC CONTROL ...22

    6.3 BRIEF DESCRIPTION OF MAIN CONTROL SYSTEMS ...23

    3.1 PROCESS CONTRO & MONITORING SYSTEM (PCS)..23

    3.2 SAFETY & EMERGENCY SHUTDOWN SYSTEM (SSD)..25

    6.3.3 FIRE & GAS DETECTION & FIRE FIGHTING (FGS)....26

    6.3.4 REDUNDANT LOCAL AREA NETWORK (R-LAN)..27

    6.3.5 SCADA.28

    6.3.6 WELLHEAD CONTROL PANEL (WCP) .28 TECHNICS OFFSHORE

    ENGINEERING PTE LTD, SINGAPORE

    Saipem Triune Engineering Pvt. Ltd.,

    New Delhi

    PROCESS CONTROL PHILOSOPHY

    DOCUMENT NUMBER REV.

    9512/08088-RC4-01-CP-001 A

    SHEET 2 OF 48

  • 7 OPERATION AND CONTROL OF PROCESS SYSTEMS...29

    7.1 WELL FLOW LINES CONTROL..29

    7.2 INLET MANIFOLD CONTROL31

    7.3 TEST METERING STATION32

    7.4 RISERS CONTROL32

    7.5 PRODUCTION SEPERATOR V-40033

    7.5.1 SEPARATOR LEVEL CONTROL.34

    7.5.2 SEPARATOR PRESSURE CONTROL..35

    7.5.3 CUSTODY FLOW METERS..36

    7.5.4 SEPARATOR OTHER CONTROL.36

    7.6 VENT SCRUBBER V-200..37

    7.6.1 VENT SCRUBBER TEMPERATURE CONTROL37

    7.6.2 VENT SCRUBBER LEVEL CONTROL 37

    7.7 CLOSE DRAIN & OPEN DRAIN SYSTEM (V-300 & V-301)38

    7.7.1 DRAIN TANKS TEMPERATURE CONTROL..39

    7.7.2 DRAIN TANKS LEVEL CONTROL..39

    7.8 GASLIFT DISTRIBUTION SYSTEM40

    7.8.1 GASLIFT METERING STATION..40

    7.8.2 GASLIFT GAS TO INDIVIDUAL WELL..41

    7.8.3 GASLIFT FOR SLUG REMOVAL & FOR GAS DISPOSAL...42

    7.9 CHEMICAL INJECTION SYSTEM..43

    7.9.1 DEPRESSANT..43

    7.9.2 DEMULSIFIER.44

    TECHNICS OFFSHORE ENGINEERING PTE LTD,

    SINGAPORE

    Saipem Triune Engineering Pvt. Ltd.,

    New Delhi

    PROCESS CONTROL PHILOSOPHY

    DOCUMENT NUMBER REV.

    9512/08088-RC4-01-CP-001 A

    SHEET 3 OF 48

  • 1.INTRODUCTION

    1.1 OBJECTIVE

    The purpose of this document is to define the main control functions for the process system. It

    is intended that this document be used for the following.

    Developing and/or reviewing P&IDs.

    Guidance to control engineer in developing the instrument hardware requirements

    In developing Operating Procedures, Operating Manuals, etc.

    2.GENERAL DESCRIPTION

    Well fluids from DRAGON Oilfield located in the Continental Shelf of South Vietnam, shell

    be collected at RC4 Platform which is owned by VIETSOPETRO, a Joint venture of Vietnam

    & Soviet.

    The RC-4 Platform comprises of the following process facilities :

    Collection of well fluid from various Wells: Wells number 01 to 09.

    3 Injection Wells where Injection water is used.

    Separation of Gas & liquid and transportation of gas & liquid to the Processing platforms RP-1, RP-2 & RP-3.

    Gas Lift disposal to cold vent through Vent Scrubber.

    Gaslift Distribution System.

    Risers balcony where Gas & Liquid from other platforms RC-5 & RC-DM are also joining.

    Risers for Gaslift from RP-3 platform and distributing to other platforms.

    TECHNICS OFFSHORE ENGINEERING PTE LTD,

    SINGAPORE

    Saipem Triune Engineering Pvt. Ltd.,

    New Delhi

    PROCESS CONTROL PHILOSOPHY

    DOCUMENT NUMBER REV.

    9512/08088-RC4-01-CP-001 A

    SHEET 4 OF 48

  • 3.ABBREVIATIONS

    API American Petroleum InstituteAPS Platform Abandonment SignalAS Area Supervisory StationCCR Central Control RoomDCTS Data Collection and Transfer System DCU Data Collection UnitDTU Data Transfer UnitEDG Emergency Diesel GeneratorESD Emergency ShutdownF&G Fire and GasHV High VoltageHVAC Heating Ventilation and Air ConditioningLCP Local Control PanelLCS Local Control SystemMCC Motor Control CentreMCC Motor Control CentreP&ID Piping and Instrumentation diagramPA / GA Public Address / General Alarm SystemPCS Process Control SystemPGCS Power Generation Control SystemPLC Programmable Logic ControlPSD Process ShutdownPSMCS Power Supply Monitoring and Control SystemRB Riser Block / BalconySCADA Supervisory Control and Data AcquisitionSCSSV Surface Controlled Subsurface Safety ValveSWP Satellite Well PlatformUPS Un-interruptible Power SupplyUSD Unit ShutdownWCP Wellhead Control panelWS Work Station

    TECHNICS OFFSHORE ENGINEERING PTE LTD,

    SINGAPORE

    Saipem Triune Engineering Pvt. Ltd.,

    New Delhi

    PROCESS CONTROL PHILOSOPHY

    DOCUMENT NUMBER REV.

    9512/08088-RC4-01-CP-001 A

    SHEET 5 OF 48

  • 4.BRIEF PROCESS DESCRIPTION

    The crude oil from all 9-production wells reaches to inlet manifold skid of RC-4 via their own

    respective flow lines. The manifold skid is assigned for collection and distribution of well

    product into individual process lines. It consists of blowdown valves and 4 headers as below.

    a) Well production Collection Header

    b) Testing Header for well testing and metering

    c) Vent Header

    d) Drain Header

    Fluid from wellhead passes through a choke valve to control the flow towards production

    header.

    From production header, well fluid is routed to Inlet separator which is a two phase separator

    or it is directly routed to remote processing platform RP-3 through sub sea pipeline by

    bypassing the inlet separator.

    Separated liquid/gas mixture from separator after level control valve is transported to RP-1 via

    sub sea pipe line. The Pig Launcher is also provided at RC-4 platform on this line. Liquid/gas

    mixture from platform RC-DM is also routed to RP-1 platform via RC-4 through RC-4

    liquid/gas mixture line. There is a Pig receiver at RC-4 platform on the RC-DM liquid/gas

    mixture line.

    Test header after the Test Metering Station is also routed to separated liquid/gas mixture line

    after Production Separator level control valve.

    The Produced Gas from Production Separator after its pressure control valve is transported to

    RP-3 platform through a common gas transferring line. There are two more similar facility

    TECHNICS OFFSHORE ENGINEERING PTE LTD,

    SINGAPORE

    Saipem Triune Engineering Pvt. Ltd.,

    New Delhi

    PROCESS CONTROL PHILOSOPHY

    DOCUMENT NUMBER REV.

    9512/08088-RC4-01-CP-001 A

    SHEET 6 OF 48

  • platforms RC-5 & RC-DM at the same area whose gas production goes to RP-3 platform via

    RC-4 platform through this common gas line to RP-3.

    The Gaslift gas from processing platform RP-3 arrives at RC-4 platform via 16 Km long

    pipeline. After reaching at RC-4 platform, it is divided into three lines for RC-4, RC-5 & RC-

    DM platform use. 8 Gaslift line towards RC-4 is reduced to 4 and then goes to a metering

    station. From metering station, gaslift gas is distributed to all 9-production wells through

    gaslift distribution manifold by flow controller.

    The discharge of all PSVs, BDVs from manifold, Production Separator & Gaslift distribution

    system is routed to Vent Scrubber via vent header. The gaseous discharge form Vent Scrubber

    is sent to Vent Stack through liquid seal. The liquid discharge from Vent Scrubber is collected

    in Close drain Tank. The drip pan liquid collected from all equipments and inlet manifold skid

    is routed to Open Drain Tank. The combined discharge from Closed & Open Drain Tank has

    provision to transfer the material to liquid/gas mixture line through a drain pump or directly to

    disposal sump or to support vessel as produced water accordingly.

    Water Injection line from RP-3 arrives at RC-4 platform. After reaching at RC-4 platform Riser

    balcony, it is divided into three lines for RC-4, RC-5 & RC-DM platform use. RC-4 water

    injection line shall go to three injection wells. A tapping is taken from this header for Killing

    manifold which is required for 9 production wells & 3 Injection Wells at RC-4 platform.

    Demulsifier and Depressant Chemicals storage and injection facility are installed on the

    platform.

    TECHNICS OFFSHORE ENGINEERING PTE LTD,

    SINGAPORE

    Saipem Triune Engineering Pvt. Ltd.,

    New Delhi

    PROCESS CONTROL PHILOSOPHY

    DOCUMENT NUMBER REV.

    9512/08088-RC4-01-CP-001 A

    SHEET 7 OF 48

  • 5.DESIGN BASIS

    5.1. DESIGN FLOW RATES

    Production Wells 9

    Injection Well 3

    Liquid production 6000 Tonns/day

    Oil 5500 Tonns/day

    Water 500 Tonns/day

    Maximum liquid per well 1200 Tonns/day

    Maximum Gaslift gas for all wells 400,000 NM3/Day

    Gaslift gas per Well 10000 - 50000 NM3/DayMaximum Injectivity of an injection

    well Upto 1000 m3/day

    Notes:

    1. Liquid production of 6000 Tonnes/day is the total maximum design liquid capacity for

    all 9 wells together.

    2. Inlet production Separator Gas capacity shall be 400,000 NM3/day + Associated gas

    with the crude oil based on Hysys calculation.

    TECHNICS OFFSHORE ENGINEERING PTE LTD,

    SINGAPORE

    Saipem Triune Engineering Pvt. Ltd.,

    New Delhi

    PROCESS CONTROL PHILOSOPHY

    DOCUMENT NUMBER REV.

    9512/08088-RC4-01-CP-001 A

    SHEET 8 OF 48

  • 5.2. OPERATING AND DESIGN CONDITIONS

    PRESSURE TEMPERATURE

    Operating Design Operating Design

    Bar g Bar g C C

    Production Header 16-41 80 55 60

    Test Header 16-41 80 55 60

    Vent Header 2 11.5 55 -48 / 60

    Drain Header ATM 11.5 55 60

    Gaslift gas 105-110 125 22-30 45

    Production Separator 16-41 60 55 60

    Vent Scrubber 2 11.5 55 -48 / 60

    Pig Launcher/Pig Receiver 16-41 80 55 60

    Close Drain Tank 0.7 5.8 55 60

    Open Drain Tank ATM 3.5 55 60

    5.3. COMPOSITION OF CRUDE OIL FEED

    TECHNICS OFFSHORE ENGINEERING PTE LTD,

    SINGAPORE

    Saipem Triune Engineering Pvt. Ltd.,

    New Delhi

    PROCESS CONTROL PHILOSOPHY

    DOCUMENT NUMBER REV.

    9512/08088-RC4-01-CP-001 A

    SHEET 9 OF 48

  • Component Unit Quantity

    N2+RARE Mole % 0.068

    CO2 Mole % 0.038

    H2S Mole % 0

    CH4 Mole % 12.308

    C2H6 Mole % 3.099

    C3H8 Mole % 6.023

    i-C4H10 Mole % 1.52

    n-C4H10 Mole % 3.141

    i-C5H12 Mole % 3.901

    n-C5H12 Mole % 5.409

    Pseudo C6 Mole % 6.766

    Pseudo C7+ Mole % 57.727

    Mol. Wt. g/mole 227.8

    TECHNICS OFFSHORE ENGINEERING PTE LTD,

    SINGAPORE

    Saipem Triune Engineering Pvt. Ltd.,

    New Delhi

    PROCESS CONTROL PHILOSOPHY

    DOCUMENT NUMBER REV.

    9512/08088-RC4-01-CP-001 A

    SHEET 10 OF 48

  • 5.4. COMPOSITION OF GASLIFT GAS

    TECHNICS OFFSHORE ENGINEERING PTE LTD,

    SINGAPORE

    Saipem Triune Engineering Pvt. Ltd.,

    New Delhi

    PROCESS CONTROL PHILOSOPHY

    DOCUMENT NUMBER REV.

    9512/08088-RC4-01-CP-001 A

    SHEET 11 OF 48

    Component Unit Quantity

    N2+RARE Mole % 0.175

    CO2 Mole % 0.068

    H2S Mole % 0

    CH4 Mole % 73.622

    C2H6 Mole % 12.992

    C3H8 Mole % 7.635

    i-C4H10 Mole % 1.643

    n-C4H10 Mole % 2.358

    i-C5H12 Mole % 0.591

    n-C5H12 Mole % 0.64

    Pseudo C6 Mole % 0.406

    Pseudo C7+ Mole % 0.119

    Pseudo C8+ Mole % 0.02

    Relative density 0.784

    Mol. Weight g/mole 22.75

  • 5.5. CHARACTERISTICS OF PSEUDO COMPONENTS

    TECHNICS OFFSHORE ENGINEERING PTE LTD,

    SINGAPORE

    Saipem Triune Engineering Pvt. Ltd.,

    New Delhi

    PROCESS CONTROL PHILOSOPHY

    DOCUMENT NUMBER REV.

    9512/08088-RC4-01-CP-001 A

    SHEET 12 OF 48

    IN CRUDE OIL Normal Boiling Point (NBP)

    Molecular Weight

    Std. Ideal Liquid Density

    Pseudo C6 66 C 86 663 kg/m3 at 20 C

    Pseudo C7+ 358.8 861 - 903.9 kg/m3 at 20 C

    Average density 875 kg/m3

    IN GASLIFT Normal Boiling Point (NBP)

    Molecular Weight

    Std. Ideal Liquid Density

    Pseudo C6 66 C 86 663 kg/m3 at 20 C

    Pseudo C7+ 96 C 100.2 683 kg/m3 at 20 C

    Pseudo C8+ 124 C 114.2 702 kg/m3 at 20 C

  • 5.6. METEOROLOGICAL DATA

    Climate : Salten Offshore Tropical

    Max Wind Speed : 57.4 m/sec

    Normal Wind Speed : 8.7 m/sec

    Min, Wind Speed : 0.0 m/sec

    Barometric Pressure : 996 1022.2 mbar

    Ambient Air Quality

    Maximum temperature outdoor air : 41 C

    Minimum temperature outdoor air : 21 C

    Normal temperature outdoor air : 35 C

    Dry bulb temperature : 27 0F (-2.8 C) Minimum

    Relative Humidity of outdoor air : Maximum 100% to Minimum 56%

    Miscellaneous :

    Solar Radiation : 335 kcal/ m2hr

    Sea Water Temperature : 24.12 C 34.59 C

    Sea water Salinity : 293 - 3459 mg/l

    Sea water Density : 1018.4 - 1024.19 Kg/M3

    Seismic Conditions

    Maximum Seismicity : 6 Richter Scale .

    5.7. SIMULATION CASES

    TECHNICS OFFSHORE ENGINEERING PTE LTD,

    SINGAPORE

    Saipem Triune Engineering Pvt. Ltd.,

    New Delhi

    PROCESS CONTROL PHILOSOPHY

    DOCUMENT NUMBER REV.

    9512/08088-RC4-01-CP-001 A

    SHEET 13 OF 48

  • The simulation is carried out to know the process conditions at various possible cases based on

    operating pressure & properties of crude oil system & the gas lift system.

    Case 1 : Oil 6000 Tonns/ DayWater 0 Tonns/ DayProduction Separator Operating Pressure 16 BargGas Lift Operating Temperature 30 CGas Lift Operating Pressure 105 Barg

    Case 2 :Oil 6000 Tonns/ DayWater 0 Tonns/ DayProduction Separator Operating Pressure 41 BargGas Lift Operating Temperature 30 CGas Lift Operating Pressure 105 Barg

    Case 3 :Oil 6000 Tonns/ DayWater 0 Tonns/ DayProduction Separator Operating Pressure 16 BargGas Lift Operating Temperature 30 CGas Lift Operating Pressure 110 Barg

    TECHNICS OFFSHORE ENGINEERING PTE LTD,

    SINGAPORE

    Saipem Triune Engineering Pvt. Ltd.,

    New Delhi

    PROCESS CONTROL PHILOSOPHY

    DOCUMENT NUMBER REV.

    9512/08088-RC4-01-CP-001 A

    SHEET 14 OF 48

  • TECHNICS OFFSHORE ENGINEERING PTE LTD,

    SINGAPORE

    Saipem Triune Engineering Pvt. Ltd.,

    New Delhi

    PROCESS CONTROL PHILOSOPHY

    DOCUMENT NUMBER REV.

    9512/08088-RC4-01-CP-001 A

    SHEET 15 OF 48

  • TECHNICS OFFSHORE ENGINEERING PTE LTD,

    SINGAPORE

    Saipem Triune Engineering Pvt. Ltd.,

    New Delhi

    PROCESS CONTROL PHILOSOPHY

    DOCUMENT NUMBER REV.

    9512/08088-RC4-01-CP-001 A

    SHEET 16 OF 48

    Case 4 :Oil 6000 Tonns/ DayWater 0 Tonns/ DayProduction Separator Operating Pressure 41 Barg

    Gas Lift Operating Temperature 30 CGas Lift Operating Pressure 110 Barg

    Case 5 :Oil 6000 Tonns/ DayWater 0 Tonns/ Day

    Production Separator Operating Pressure 16 BargGas Lift Operating Temperature 22 C

    Gas Lift Operating Pressure 105 Barg

    Case 6 :Oil 6000 Tonns/ DayWater 0 Tonns/ DayProduction Separator Operating Pressure 41 Barg

    Gas Lift Operating Temperature 22 CGas Lift Operating Pressure 105 Barg

    Case 7 :Oil 6000 Tonns/ DayWater 0 Tonns/ Day

    Production Separator Operating Pressure 16 BargGas Lift Operating Temperature 22 C

    Gas Lift Operating Pressure 110 Barg

  • TECHNICS OFFSHORE ENGINEERING PTE LTD,

    SINGAPORE

    Saipem Triune Engineering Pvt. Ltd.,

    New Delhi

    PROCESS CONTROL PHILOSOPHY

    DOCUMENT NUMBER REV.

    9512/08088-RC4-01-CP-001 A

    SHEET 17 OF 48

    Case 8 :Oil 6000 Tonns/ DayWater 0 Tonns/ DayProduction Separator Operating Pressure 41 BargGas Lift Operating Temperature 22 CGas Lift Operating Pressure 110 Barg

    Case 9 :Oil 5500 Tonns/ DayWater 500 Tonns/ DayProduction Separator Operating Pressure 16 BargGas Lift Operating Temperature 30 CGas Lift Operating Pressure 105 Barg

    Case 10 :Oil 5500 Tonns/ DayWater 500 Tonns/ DayProduction Separator Operating Pressure 41 BargGas Lift Operating Temperature 30 CGas Lift Operating Pressure 105 Barg

    Case 11 :Oil 5500 Tonns/ DayWater 500 Tonns/ DayProduction Separator Operating Pressure 16 BargGas Lift Operating Temperature 30 CGas Lift Operating Pressure 110 Barg

  • TECHNICS OFFSHORE ENGINEERING PTE LTD,

    SINGAPORE

    Saipem Triune Engineering Pvt. Ltd.,

    New Delhi

    PROCESS CONTROL PHILOSOPHY

    DOCUMENT NUMBER REV.

    9512/08088-RC4-01-CP-001 A

    SHEET 18 OF 48

  • TECHNICS OFFSHORE ENGINEERING PTE LTD,

    SINGAPORE

    Saipem Triune Engineering Pvt. Ltd.,

    New Delhi

    PROCESS CONTROL PHILOSOPHY

    DOCUMENT NUMBER REV.

    9512/08088-RC4-01-CP-001 A

    SHEET 19 OF 48

    Case 12 :Oil 5500 Tonns/ DayWater 500 Tonns/ DayProduction Separator Operating Pressure 41 BargGas Lift Operating Temperature 30 CGas Lift Operating Pressure 110 Barg

    Case 13 :Oil 5500 Tonns/ DayWater 500 Tonns/ DayProduction Separator Operating Pressure 16 BargGas Lift Operating Temperature 22 CGas Lift Operating Pressure 105 Barg

    Case 14 :Oil 5500 Tonns/ DayWater 500 Tonns/ DayProduction Separator Operating Pressure 41 BargGas Lift Operating Temperature 22 CGas Lift Operating Pressure 105 Barg

    Case 15 :Oil 5500 Tonns/ DayWater 500 Tonns/ DayProduction Separator Operating Pressure 16 BargGas Lift Operating Temperature 22 CGas Lift Operating Pressure 110 Barg

  • TECHNICS OFFSHORE ENGINEERING PTE LTD,

    SINGAPORE

    Saipem Triune Engineering Pvt. Ltd.,

    New Delhi

    PROCESS CONTROL PHILOSOPHY

    DOCUMENT NUMBER REV.

    9512/08088-RC4-01-CP-001 A

    SHEET 20 OF 48

  • TECHNICS OFFSHORE ENGINEERING PTE LTD,

    SINGAPORE

    Saipem Triune Engineering Pvt. Ltd.,

    New Delhi

    PROCESS CONTROL PHILOSOPHY

    DOCUMENT NUMBER REV.

    9512/08088-RC4-01-CP-001 A

    SHEET 21 OF 48

    Case 16 :Oil 5500 Tonns/ DayWater 500 Tonns/ DayProduction Separator Operating Pressure 41 BargGas Lift Operating Temperature 22 CGas Lift Operating Pressure 110 Barg

    Case 17 :Oil 6000 Tonns/ DayWater 0 Tonns/ DayProduction Separator Operating Pressure 30 BargGas Lift Operating Temperature 30 CGas Lift Operating Pressure 105 Barg

    Case 18 :Oil 5500 Tonns/ DayWater 500 Tonns/ DayProduction Separator Operating Pressure 30 BargGas Lift Operating Temperature 30 CGas Lift Operating Pressure 105 Barg

    Case 19 :Oil 5500 Tonns/ DayWater 500 Tonns/ DayProduction Separator Operating Pressure 30 BargGas Lift Operating Temperature 30 CGas Lift Operating Pressure 110 Barg

  • TECHNICS OFFSHORE ENGINEERING PTE LTD,

    SINGAPORE

    Saipem Triune Engineering Pvt. Ltd.,

    New Delhi

    PROCESS CONTROL PHILOSOPHY

    DOCUMENT NUMBER REV.

    9512/08088-RC4-01-CP-001 A

    SHEET 22 OF 48

    Case 20 :Oil 6000 Tonns/ DayWater 0 Tonns/ DayProduction Separator Operating Pressure 30 BargGas Lift Operating Temperature 30 CGas Lift Operating Pressure 110 Barg

    Case 21 :Oil 6000 Tonns/ DayWater 0 Tonns/ DayProduction Separator Operating Pressure 30 BargGas Lift Operating Temperature 22 CGas Lift Operating Pressure 105 Barg

    Case 22 :Oil 5500 Tonns/ DayWater 500 Tonns/ DayProduction Separator Operating Pressure 30 BargGas Lift Operating Temperature 22 CGas Lift Operating Pressure 105 Barg

    Case 23 :Oil 5500 Tonns/ DayWater 500 Tonns/ DayProduction Separator Operating Pressure 30 BargGas Lift Operating Temperature 22 CGas Lift Operating Pressure 110 Barg

  • Case 24 :Oil 6000 Tonns/ DayWater 0 Tonns/ DayProduction Separator Operating Pressure 30 BargGas Lift Operating Temperature 22 CGas Lift Operating Pressure 110 Barg

    The above simulation cases have been utilized for preparation of PFD,

    Heat and Material Balance, data-sheets and other engineering documents.

    The equipment & pipelines are sized according to the governing cases

    out of above twenty four different cases.

    TECHNICS OFFSHORE ENGINEERING PTE LTD,

    SINGAPORE

    Saipem Triune Engineering Pvt. Ltd.,

    New Delhi

    PROCESS CONTROL PHILOSOPHY

    DOCUMENT NUMBER REV.

    9512/08088-RC4-01-CP-001 A

    SHEET 23 OF 48

  • 6.PROCESS SYSTEM CONTROL PHILOSOPHY

    6.1 FACILITIES TO CONTROL

    The philosophy of automation, monitoring process control system, safety instrumented system

    & hazard-monitoring system is prepared for RC-4 platform following facilities.

    Production Wells control through Wellhead Control Panel

    Injection Wells control

    Process Equipments

    Power generation control

    Auxiliary Equipments

    Fire Fighting Facility

    Emergency handling

    Accommodation platform control system

    TECHNICS OFFSHORE ENGINEERING PTE LTD,

    SINGAPORE

    Saipem Triune Engineering Pvt. Ltd.,

    New Delhi

    PROCESS CONTROL PHILOSOPHY

    DOCUMENT NUMBER REV.

    9512/08088-RC4-01-CP-001 A

    SHEET 24 OF 48

  • 6.2 TYPES OF BASIC CONTROL

    The basic control system of RC-4 Wellhead Satellite platform is through PCS & PLC and it is

    operated from the Control Room Workstation at RC-4 platform. The monitoring & control

    systems of RC-4 Platform are being done through following systems:

    Process Control System (PCS)

    Safety & Emergency Shutdown System (SSD)

    Fire & Gas System RC4 (FGS)

    Redundant Local Area Network (R-LAN)

    SCADA

    Radio Equipment

    24 VDC Uninterrupted Power Supply systems for monitoring, control & safety facility including PA/GA & Radio Equipment.

    PA/GA System

    Data Collection Interface (DCI)

    Work-Station PCS/ SSD/ FGS (WS-1)

    Wellhead Control Panel (WCP)

    Navigation System Panel

    TECHNICS OFFSHORE ENGINEERING PTE LTD,

    SINGAPORE

    Saipem Triune Engineering Pvt. Ltd.,

    New Delhi

    PROCESS CONTROL PHILOSOPHY

    DOCUMENT NUMBER REV.

    9512/08088-RC4-01-CP-001 A

    SHEET 25 OF 48

  • 6.3 BRIEF DESCRIPTION OF MAIN CONTROL SYSTEMS

    The following control levels should be provided.

    Level 0 : Field sensors & execution system

    Level 1 : Hardware at the PLC basis (central panel : PCS, SSD, FGS)

    Level 2 : SCADA at RC4

    (Software & hardware for supervisory control & data acquisition)

    6.3.1 PROCESS CONTROL AND MONITORING SYSTEM (PCS):

    PCS should do the normal control and monitoring of the process parameter. Moreover PCS at

    RC4 platform is having facility to provide safety of personnel, environment, equipment and

    platform as a whole. PCS shall be in RC4 Platform Control Room and should have following

    minimum control.

    Control of Oil & Gas Production, Processing & transportation.

    Control of Main & auxiliary process equipments.

    Interface with Well Test Unit and Metering Unit.

    Control & Monitoring Power Supply System.

    TECHNICS OFFSHORE ENGINEERING PTE LTD,

    SINGAPORE

    Saipem Triune Engineering Pvt. Ltd.,

    New Delhi

    PROCESS CONTROL PHILOSOPHY

    DOCUMENT NUMBER REV.

    9512/08088-RC4-01-CP-001 A

    SHEET 26 OF 48

  • The PCS should serve minimum following functions.

    a) Provide graphical display of process information for monitoring and interacting with

    facility process equipment.

    b) Displaying, managing & archiving the alarms and events from all systems.

    c) Continuous recording of process data in historical archive files.

    d) Graphical trending of both real time and historical data.

    e) Generate production data reports.

    f) Interfacing to third-party vendor systems.

    g) Provide master communication protocol between all subsystems.

    h) PCS shall carry out functions of selfdiagnostics and internal malfunction alarm.

    i) PCS shall be tested without process shutdown in case of change of software or loading of

    new software.

    j) PCS will have hardware panels for visual indication of critical alarms, Critical Valves

    status and Critical control switches.

    Notes:

    1. PCS shall be provided with 100% redundancy to take care of failure condition of Central

    Processor (CPU). Both the CPU should have same control computation program in

    synchronization so that changeover can be done without any interruption.

    TECHNICS OFFSHORE ENGINEERING PTE LTD,

    SINGAPORE

    Saipem Triune Engineering Pvt. Ltd.,

    New Delhi

    PROCESS CONTROL PHILOSOPHY

    DOCUMENT NUMBER REV.

    9512/08088-RC4-01-CP-001 A

    SHEET 27 OF 48

  • 6.3.2 SAFETY & EMERGENCY SHUTDOWN SYSTEM (SSD):

    The main purpose of SSD should be to provide following as a minimum.

    Safety of staff, environment and process equipment of WHP RC-4 as a whole.

    Automatic emergency shutdown of processes and equipment by critical parameters and

    also send indispensable signals to other systems.

    Provide remote diagnostic calibration and testing.

    Provide functions of self-diagnosis and signaling about internal faults with automatic

    registration and printing.

    SSD shell be comprising of followings.

    ESD-A (Emergency Shutdown Abandon Platform)

    ESD-C (Shutdown due to emergency on other platforms)

    PSD (Process Shutdown)

    PSD-GL (Process Shutdown Gaslift)

    ESD-GL (Emergency Shutdown Gaslift)

    Receiving signal from FGS Panel for ESD-F & ESD-G.

    The system SSD includes the equipment of following levels:

    Level 0 : Field sensors of critical parameters and execution units of emergency shutdown.

    TECHNICS OFFSHORE ENGINEERING PTE LTD,

    SINGAPORE

    Saipem Triune Engineering Pvt. Ltd.,

    New Delhi

    PROCESS CONTROL PHILOSOPHY

    DOCUMENT NUMBER REV.

    9512/08088-RC4-01-CP-001 A

    SHEET 28 OF 48

  • Level 1 : SSD-Panel (hardware on the PLC basis).

    3.3 FIRE & GAS Detection and Fire Fighting Control System at RC-4 (FGS) :

    Fire and gas detection and fire-fighting control system (FGS) is a separate dedicated system

    and F&G Panel should be installed in RC-4 control room and have autonomous standby power

    supply unit. The main purpose of Fire & Gas control panel should be to provide following as a

    minimum.

    Safety of staff, environment and process equipment of WHP RC-4 as a whole.

    Automatic detection of the location of the Fire through UV/ IR flame detectors system,

    fusible loop and location of the HC gas leak at the different location on the different decks

    of the RC4 platform.

    The FGS shall act upon receiving indication from detectors & manual shutdown push

    buttons to generate the Emergency Shutdown ESD-F or/and ESD-G signals accordingly

    and transfer the critical signals to the SSD and to the other systems.

    Automatic Control on RC-4 Fire Fighting System.

    The system FGS includes the equipments of the following levels:

    Level 0 : F&G field detectors, actuators of RC-4 fire-fighting systems.

    Level 1 : FGS-Panel (hardware at PLC base).

    TECHNICS OFFSHORE ENGINEERING PTE LTD,

    SINGAPORE

    Saipem Triune Engineering Pvt. Ltd.,

    New Delhi

    PROCESS CONTROL PHILOSOPHY

    DOCUMENT NUMBER REV.

    9512/08088-RC4-01-CP-001 A

    SHEET 29 OF 48

  • FGS shall provide the following levels of shut down according to level of danger for personnel,

    environment, process equipment, and platform as a whole.

    ESD-F : Emergency shutdown and process blow-down for personnel safety and equipment/

    unit safety. Furthermore APS push buttons for activation of ESD signals to abandon

    platform shall be provided.

    ESD-G: Emergency shutdown and bringing technological processes and equipment in safe

    condition but without pressure blowdown except to release high pressure Gaslift

    system.

    The F & G system at RC4 shall cover only RC-4 platform. Control system shall execute auto

    and remote control of systems and devices for extinguishing of fire at RC-4 (Fire fighting

    system fire water pump, fire monitor, fire sprinkler, foam system, CO2 etc) as well as

    switching off the HVAC system.

    3.4 REDUNDANT LOCAL AREA NETWORK (R-LAN):

    Local Information Network should have connection with PCS & PLC (SSD) through

    necessary software and external interfaces.

    Local Area network (R-LAN) shall transfer the information from PCS to SCADA.

    Information by Radio Channel should transfer through R-LAN. It includes ESD-C

    information to / from processing platform RP-3 & RP-1.

    TECHNICS OFFSHORE ENGINEERING PTE LTD,

    SINGAPORE

    Saipem Triune Engineering Pvt. Ltd.,

    New Delhi

    PROCESS CONTROL PHILOSOPHY

    DOCUMENT NUMBER REV.

    9512/08088-RC4-01-CP-001 A

    SHEET 30 OF 48

  • 3.5 SCADA (Supervisory Control and Data Acquisition)

    SCADA should provide receiving / transferring, processing, registration, storage and visual

    display of the information on workstations from/to systems PCS, SSD, FGS and receiving /

    transferring of the necessary information through DCI by the radio channel. It should be

    provided with ability to retrieve from archive the basic process parameters (PT/TT - of each

    separate well, PT / TT / LT - of process equipment), Well Test Unit and Metering Unit with

    indication in WS-1, demonstrating parameters variation diagrams of each separate well and

    technological process for a certain time or for all period of data storage. SCADA should

    provide warning signaling (as the controlled process parameters over set points) and alarm

    signaling (in emergencies) - light and sound signaling at workstation (WS-1).

    3.6 Wellhead Control Panel (WCP):

    WCP- should provide with the following remote controls from the system SSD:

    a) Shutdown of separate wells (PSD-Closed WSSV, PSD-Closed MSSV) - automatically from

    the process control instruments or manually by the command of operator technologist

    from workstation WS-1;

    a) Shutdown of all wells (ESD-Closed all WSSV / MSSV / SCSSV) - automatically from the

    control instruments/systems or manually by the ESD command of operator technologist

    from workstation WS-1

    TECHNICS OFFSHORE ENGINEERING PTE LTD,

    SINGAPORE

    Saipem Triune Engineering Pvt. Ltd.,

    New Delhi

    PROCESS CONTROL PHILOSOPHY

    DOCUMENT NUMBER REV.

    9512/08088-RC4-01-CP-001 A

    SHEET 31 OF 48

  • 7 OPERATION AND CONTROL OF PROCESS SYSTEMS

    Description of the operation and control of the process is divided into different sections as

    below.

    Well Flow lines

    Inlet Manifold

    Test Metering Station

    Risers

    Production Separator

    Vent Scrubber

    Open & Close Drain system

    Gaslift Distribution system

    Chemicals Injection

    7.1 Well Flow lines Control

    There are nine separate wells with wellheads and flow lines at the RC-4 Wellhead platform. The

    wellhead of every well is consists of the following main instrumentations.

    For isolating a Well, there is underwater Sub Surface Safety Valve (SCSSV) and One master &

    One wing valve on the wellhead.

    TECHNICS OFFSHORE ENGINEERING PTE LTD,

    SINGAPORE

    Saipem Triune Engineering Pvt. Ltd.,

    New Delhi

    PROCESS CONTROL PHILOSOPHY

    DOCUMENT NUMBER REV.

    9512/08088-RC4-01-CP-001 A

    SHEET 32 OF 48

  • Master Surface Safety valves (RC4-MSSV-0011/ 0021/ 0031/ 0041/ 0051/ 0061/ 0071/

    0081/ 0091).

    Wing Surface safety valves (RC4-WWSSV 0011/ 0021/ 0031/ 0041/ 0051/ 0061/ 0071/

    0081/ 0091).

    Positive Flow chock Valves (RC4-FV-0011/ 0021/ 0031/ 0041/ 0051/ 0061/ 0071/ 0081/

    0091).

    The chock valves are hydraulically actuated step by step. Choke valve shall close only after

    wing valve closes (upon LSD or manual initiation), Choke valve closing time is adjustable.

    Reopening of choke valve is only possible only when wing valve is fully open.

    The low & high pressure switches are provided on each well flow line after the Chock valves.

    The tag numbers are RC4-PSHL 0011/ 0021/ 0031/ 0041/ 0051/ 0061/ 0071/ 0081/ 0091

    respectively. PSHL will create electrical signal at high pressure of 50 barg & low pressure of

    10 barg, which goes to Well Head Control Panel (WHCP) to shutdown the individual Well.

    Each flow line is protected against high pressure by providing a Shutdown valve SDV (RC4-

    SDV-0011/ 0021/ 0031/ 0041/ 0051/ 0061/ 0071/ 0081/ 0091 respectively for 9 wells) followed

    by three pressure transmitters, which shall be used for shutdown purpose. On actual high

    pressure in the individual flow lines, the indication from these three pressure transmitters shall

    generate Pressure High High alarm signals in PLC and based on the 2 out of 3 voting system,

    PLC shall activate the Pressure High High interlock (RC4-PAHH-1011/ 1021/ 1031/ 1041/

    1051/ 1061/ 1071/1081/ 1091 respectively for 9 production wells) which shall shutdown the

    SDV in flow line and other appropriate shutdown of the system.

    (For detail , see the Cause & Effect Matrix)

    TECHNICS OFFSHORE ENGINEERING PTE LTD,

    SINGAPORE

    Saipem Triune Engineering Pvt. Ltd.,

    New Delhi

    PROCESS CONTROL PHILOSOPHY

    DOCUMENT NUMBER REV.

    9512/08088-RC4-01-CP-001 A

    SHEET 33 OF 48

  • Each well flow line is having a check valve and a safety valve. The operating temperature of

    each flow line is 55 degC and the operating pressure range is from 16 to 41 barg.

    7.2 Inlet manifold Control

    Inlet manifold is having four headers, Production Header, Test Header, Vent Header & Drain

    Header.

    The production Header is designed to receive the crude oil from all the flow lines together.

    Production Header is provided with local pressure & temperature gauges and a pressure

    transmitter with Low & High pressure alarms on PCS. To release the pressure of production

    header, blowdown valve RC4-BDV-1001 is provided to depressurize it, which operate

    automatically on ESD.

    A Test header is provided at the Inlet manifold which allows testing of each well separately. To

    release the pressure of test header, blowdown valve RC4-BDV-1002 is provided, which operate

    automatically on ESD.

    The operating pressure of these headers is 16-41 barg & operating temperature is 55

    degC.

    TECHNICS OFFSHORE ENGINEERING PTE LTD,

    SINGAPORE

    Saipem Triune Engineering Pvt. Ltd.,

    New Delhi

    PROCESS CONTROL PHILOSOPHY

    DOCUMENT NUMBER REV.

    9512/08088-RC4-01-CP-001 A

    SHEET 34 OF 48

  • 7.3 Test Metering Station

    As such there is no control on the test metering station. Whenever a well is to be tested for its

    components, that flow line is to be lined-up to the test header. From test header, flow is routed

    to the metering station. On metering station, a Multi Phase Flow devise is provided which shall

    indicate the flow rate of Gas, Oil & Water in the crude oil stream.

    7.4 RISERS CONTROL

    All the platforms (RC-4, RC-5, RC-DM, RP-1, RP-2, RP-3) produced gas, mixture of oil &

    gas, Gaslift gas & water injection are interconnected through risers.

    Produced gas from RC-5 (Riser-06) & RC-DM (Riser-07) are coming to RC-4 platform &

    from here altogether with RC-4 Produced Gas, these are transferred to RP-3 / RP-2 platform

    through Riser-08.

    Mixture of oil & gas from RC-DM (Riser-05) is coming to RC-4 platform & from here

    altogether with RC-4 they are transferred via Riser 04 to RP-1 through RC-5 platform.

    Gaslift gas from RP-3 (Riser-02) is coming to RC-4 platform & from here it is getting

    distributed to RC-DM (Riser-03), RC-5 (Riser-01) & RC-4 usage.

    Water for injection is coming from RP-3 (Riser-09) on RC-4 platform & from here it is

    getting distributed to RC-4, RC-5 (Riser-10) & RC-DM (Riser-11).

    TECHNICS OFFSHORE ENGINEERING PTE LTD,

    SINGAPORE

    Saipem Triune Engineering Pvt. Ltd.,

    New Delhi

    PROCESS CONTROL PHILOSOPHY

    DOCUMENT NUMBER REV.

    9512/08088-RC4-01-CP-001 A

    SHEET 35 OF 48

  • Shutdown Valves SDVs are provided on the Risers where service is Hydrocarbon fluids.

    Hand Operated valves are provided in water injection line with limit switches to know the

    open & close status of these hand valves on Risers.

    In case of emergency on Risers, low low pressure & high high pressure on Produced Gas &

    Liquid Risers and only low low pressure on Gaslift Risers are provided to shutdown the

    respective SDV and other related SDV accordingly.

    (For detail , see the Cause & Effect Matrix)

    7.5 PRODUCTION SEPARATOR V-400 :

    Crude Oil from Production header enters into the Production Separator. The operating

    pressure of at 16-41 barg and 55C. Production Separator is a 2 phase Horizontal separator to

    separate well fluid into gas & liquid phase. Liquid, containing oil & water, is collected in

    bottom and provided to stay in the separator for some predetermined time based on the load

    to disengage the trapped gases before going out from separator bottom.

    Produced gas from separator overhead under separator pressure control is transferred to

    processing platform RP-3 while the produced liquid from separator bottom under level

    control is transferred to processing platform RP-1 via RC-5 platform.

    TECHNICS OFFSHORE ENGINEERING PTE LTD,

    SINGAPORE

    Saipem Triune Engineering Pvt. Ltd.,

    New Delhi

    PROCESS CONTROL PHILOSOPHY

    DOCUMENT NUMBER REV.

    9512/08088-RC4-01-CP-001 A

    SHEET 36 OF 48

  • 7.5.1 PRODUCTION SEPARATOR LEVEL CONTROL:

    Production separator liquid level is monitored and controlled by Interface level controller

    RC4-LIC-400 on auto mode by operating level control valve RC4-LCV-400, which is located

    at separator bottom outlet liquid line. Level controller gets the indication from local level

    transmitter RC4-LT-400 that is installed on standpipe of production separator. It keeps a

    watch on interface level and hence relative liquid residence time in the separator to ensure

    effective separation.

    NOTE:

    1. On level transmitter failure, its indication should show bad value with alarm and

    level controller should be forced automatically to go on Manual mode from Auto

    mode, leaving Level Control valve at its last output position.

    2. Above action shall give the warning alarm to operation personnel but considering

    the normal steady rate, unnecessary shutdown can be avoided.

    Another level transmitter RC4-LTS-401 is provided on separator to keep watch on its very

    low and very high level and during such condition, this transmitter signal to PLC generate

    Low-Low level alarms or High-high level alarms to take proper action through PLC.

    (For detail , see the Cause & Effect Matrix)

    However, as same level control valve RC4-LCV-400 is to get trip through PLC in case of low

    low level in separator so proper instrumentation system is required for the operation of this

    valve during normal and emergency.

    TECHNICS OFFSHORE ENGINEERING PTE LTD,

    SINGAPORE

    Saipem Triune Engineering Pvt. Ltd.,

    New Delhi

    PROCESS CONTROL PHILOSOPHY

    DOCUMENT NUMBER REV.

    9512/08088-RC4-01-CP-001 A

    SHEET 37 OF 48

  • 7.5.2 PRODUCTION SEPARATOR PRESSURE CONTROL:

    Production separator pressure is monitored and controlled by Interface pressure controller

    RC4-PIC-400 on auto mode by operating pressure control valve RC4-PCV-400, which is

    located at separator overhead outlet gas line. Pressure controller gets the indication from

    local pressure transmitter RC4-PT-400. Depending on the operating scenarios between the

    other platform, its set point is to be decided which can vary from 16 barg to 41 barg.

    NOTE:

    3. On pressure transmitter failure, its indication should show bad value with alarm and

    pressure controller should be forced automatically to go on Manual mode from

    Auto mode, leaving pressure Control valve at its last output position.

    4. Above action shall give the warning alarm to operation personnel but considering

    the normal steady rate, unnecessary shutdown can be avoided.

    Another pressure transmitter RC4-PTS-402 is provided on separator to keep watch on its

    very low and very high pressure and during such condition, this transmitter signal to PLC

    generate Low-Low pressure alarms or High-high pressure alarms to take proper action

    through PLC.

    (For detail , see the Cause & Effect Matrix)

    However, as same pressure control valve RC4-PCV-400 is to get trip through PLC in case of

    low low pressure in separator so proper instrumentation system is required for the operation

    of this valve during normal and emergency.

    TECHNICS OFFSHORE ENGINEERING PTE LTD,

    SINGAPORE

    Saipem Triune Engineering Pvt. Ltd.,

    New Delhi

    PROCESS CONTROL PHILOSOPHY

    DOCUMENT NUMBER REV.

    9512/08088-RC4-01-CP-001 A

    SHEET 38 OF 48

  • 7.5.3 CUSTODY FLOW METERS

    Custody flow meter RC4-FT-401 is provided in outlet gas line from separator. Being a custody

    meter, proper pressure and temperature compensation is provided on Gas Flow meter by

    pressure transmitter RC4-PT-401 & RC4-TT-401. The compensated flow is indicated by RC4-

    FI-401 on PCS and the Cumulative flow is indicated by RC4-FQI-401 on PCS.

    Custody flow meter RC4-FT-402 is provided in outlet liquid line from separator. RC4- FI-402

    indicates the flow on PCS and the Cumulative flow is indicated by RC4-FQI-402 on PCS.

    7.5.4 OTHER MONITORING & CONTROL IN PRODUCTION SEPARATOR

    a)Gas outlet demister pad differential pressure transmitter is provided to know about the

    chocking in the demister pad.

    b)Temperature transmitter RC4-TT-402 is provided in liquid phase and its indication RC4-TI-

    402 is provided on PCS.

    c)Blow-down facility is provided to reduce pressure in the separator in case of fire or other

    emergencies.

    TECHNICS OFFSHORE ENGINEERING PTE LTD,

    SINGAPORE

    Saipem Triune Engineering Pvt. Ltd.,

    New Delhi

    PROCESS CONTROL PHILOSOPHY

    DOCUMENT NUMBER REV.

    9512/08088-RC4-01-CP-001 A

    SHEET 39 OF 48

  • 7.6 VENT SCRUBBER V-200:

    The vent scrubber separates hydrocarbon liquid carried over by the gas in the vent header. The

    knocked out vapor goes to vent tip while the accumulated liquid is transferred to closed drain

    tank V-301 by gravity. There is provision to empty out the scrubber through Drain pump.

    7.6.1 VENT SCRUBBER TEMPERATURE CONTROL :

    During emergency release of gas & liquid from process system, there is potential of low

    temperature discharge in the vent header & vent scrubber. An immersion electric heater RC4-

    HT-200 is provided in the Vent Scrubber in liquid phase, which is operated to control the vent

    scrubber liquid phase temperature to avoid congealing of the oil. A temperature switch RC4-

    TSH-200 is provided in the liquid phase to control the ON / OFF power to the heater. In normal

    operation while no liquid is there, this heater should remain OFF.

    The normal operating temperature in the system is 55 degC but the set point of TSH can be

    kept much below 55 degC, depending upon the characteristic of the crude in the vent & drain

    headers. There is a temperature transmitter RC4-TT-200 in liquid phase whose indication RC4-

    TI-200 comes on PCS with high and low alarms on PCS.

    7.6.2 VENT SCRUBBER LEVEL CONTROL :

    In normal operation, as such there is no level control on vent scrubber. But during any

    emergency discharge, during draining of a system or due to any upset, the level can go up. So

    to avoid liquid to go into the scrubber overhead vent, a high high level protection is provided.

    TECHNICS OFFSHORE ENGINEERING PTE LTD,

    SINGAPORE

    Saipem Triune Engineering Pvt. Ltd.,

    New Delhi

    PROCESS CONTROL PHILOSOPHY

    DOCUMENT NUMBER REV.

    9512/08088-RC4-01-CP-001 A

    SHEET 40 OF 48

  • Level transmitter RC4-LT-200 on the scrubber shall provide the level indication to PCS with

    low & high alarms. Same LT indication is also going to PLC and during very high level, RC4-

    LAHH-200 shall initiate the PSD interlock to take the shutdown of the process shutdown.

    During low low level, signal RC4-LALL-200 shall come to the soft selector switch RC4-SS-

    300 which is located on PCS and if the vent scrubber is selected for drain pump, then RC4-

    LALL-200 shall activate USD via RC4-SS-300 which shall send signal to MCC to stop motor

    of drain pump RC4-H-311.

    7.7 CLOSE DRAIN & OPEN DRAIN SYSTEM:

    Overall Drain system consists of Open drain header, closed drain header, Closed drain tank (V-

    301), Open drain tank (V-300) and a common reciprocating drain pump RC4-H-311.

    Close drain tank is receiving the liquid from closed drain header where equipment draining is

    lined up. Vent Scrubber can also be drained into the Close drain tank. In normal operation,

    there is no such draining. The open drain tank receives flow from all drip pans liquid collected

    from all equipments & inlet manifold skid. Generally this header is not a pressurized header

    and should be self-drain towards the open drain tank.

    Vapours from V-300 & V-301 are vented to atmosphere via flame arrestor. The HC liquid is

    transferred by drain pump RC4-H-311 to mixture of oil & gas liquid line to RP-1. During

    maintenance, whatever the liquid is collected in the Drain Tanks, that can be send to disposal

    system or produced water to support vessel accordingly.

    TECHNICS OFFSHORE ENGINEERING PTE LTD,

    SINGAPORE

    Saipem Triune Engineering Pvt. Ltd.,

    New Delhi

    PROCESS CONTROL PHILOSOPHY

    DOCUMENT NUMBER REV.

    9512/08088-RC4-01-CP-001 A

    SHEET 41 OF 48

  • 7.7.1 OPEN DRAIN & CLOSED DRAIN TANK TEMPERATURE CONTROL:

    During emergency release of gas & liquid from process system, there is potential of low

    temperature discharge in the vent header & vent scrubber. Vent scrubber can be drained into the

    closed drain tank or liquid can come to the tank directly from the drain header. An electric

    heater RC4-HT-301 is provided in the Close Drain Tank in liquid phase, which is operated to

    control the tank liquid phase temperature. A temperature switch RC4-TSH-301 is provided in

    the liquid phase to control the ON / OFF power to the heater. In normal operation while no

    liquid is there, this heater should remain OFF.

    The normal operating temperature in the system is 55 degC but the set point of TSH can be

    kept much below 55 degC, depending upon the characteristic of the crude in the vent & drain

    headers. Local temperature gauge RC4-TG-301 is provided on the close drain tank in the

    liquid phase.

    7.7.2 OPEN DRAIN & CLOSED DRAIN TANK LEVEL CONTROL:

    In normal operation, as such there is no level control on both the tank. But during any

    emergency discharge, during draining of a system or due to any upset or vessels maintenance

    drain, the level can go up. So to avoid liquid to go into the overhead vent, an overflow line is

    provided on both the vessels. But for low level protection, level transmitter RC4-LT-300 &

    RC4-LT-301 are provided respectively on open & close drain.

    TECHNICS OFFSHORE ENGINEERING PTE LTD,

    SINGAPORE

    Saipem Triune Engineering Pvt. Ltd.,

    New Delhi

    PROCESS CONTROL PHILOSOPHY

    DOCUMENT NUMBER REV.

    9512/08088-RC4-01-CP-001 A

    SHEET 42 OF 48

  • During low low level, signal RC4-LALL-300 OR RC4-LALL-301 shall come to the soft

    selector switch RC4-SS-300 that is located on PCS. According to the selection of the

    equipment Level in selector switch, the interlock shall initiate to activate USD via RC4-SS-

    300. USD shall send signal to MCC to stop motor of drain pump RC4-H-311.

    7.8 GASLIFT DISTRIBUTION SYSTEM

    7.8.1 GASLIFT METERING STATION

    Gaslift gas line of 8, coming from processing platform RP-3 through RISER-02, is reduced to

    4 followed by a Shutdown Valve RC4-SDV-800 and Gaslift metering station. Transmitter

    RC4-FT-801 monitors Gaslift gas flow towards RC4. The flow device is Simplex change type

    orifice fitting with four bored plates, one per range. As the requirement of Gaslift in the well

    can vary from minimum required to maximum so to cover the wide range of flow rates with

    accuracy, Gas metering station shall provide three flow ranges for which three different bore

    size orifice plates are to be kept ready to install in the orifice fittings as required. Based on the

    design capacity of Gaslift system and the minimum requirement of Gaslift to one well, the

    range of these orifices is to be decided during detailed engineering.

    The flow transmitter indication RC4-FI-801A shall display on PCS. Pressure Transmitter RC4-

    PT-802 & Temperature Transmitter RC4-TT-801 are provided for pressure & temperature

    compensation to the gaslift flow. The compensated flow is indicated by RC4-FI-801 and the

    cumulative flow is indicated by RC4-FQI-801 on PCS.

    TECHNICS OFFSHORE ENGINEERING PTE LTD,

    SINGAPORE

    Saipem Triune Engineering Pvt. Ltd.,

    New Delhi

    PROCESS CONTROL PHILOSOPHY

    DOCUMENT NUMBER REV.

    9512/08088-RC4-01-CP-001 A

    SHEET 43 OF 48

  • In emergency on platform or on the gaslift metering station, a blowdown vlave RC4-BDV-801

    is provided to release the pressure.

    7.8.2 GASLIFT GAS TO INDIVIDUAL WELL

    Gaslift from metering station shall go to the gas distribution manifold where gas is distributed

    to all wells. Gaslift flow is being controlled towards each well through an angle valve with

    diaphragm actuator (RC4-FCV-811/ 812/ 813/ 814/ 815/ 816/ 817/ 818/ 819 respectively for 9

    wells). Flow is being monitored by flow transmitters RC4-FT-811/ 812/ 813/ 814/ 815/ 816/

    817/ 818/ 819 respectively for 9 wells). The individual flow device is Simplex change type

    orifice fitting with four bored plates, one per range.

    The requirement of Gaslift in the well can vary from minimum required to maximum or even

    intermittent use of gaslift, depending on the oil capacity in the wells. To cover the wide range

    of flow rates with accuracy, each line is be provided with four flow ranges for which four

    different bore size orifice plates are to be kept ready to install in the orifice fittings as required

    by mode of operation. Based on the design capacity of Gaslift system and the minimum

    requirement of Gaslift to one well, the range of these orifices is to be decided during detailed

    engineering.

    A selector switch is provided on PCS for selecting Installed Bore size which shall be the

    input to the PLC base controller RC4-FY-811/ 812/ 813/ 814/ 815/ 816/ 817/ 818/ 819

    respectively for 9 wells. The PLC based logic shall work according to wide range of gaslift

    requirement & header pressure. Accordingly it shall provide the remote set point to the flow

    controller RC4-FIC-811/ 812/ 813/ 814/ 815/ 816/ 817/ 818/ 819 respectively for 9 wells

    through PCS computer controller RC4-PY-811/812/ 813/ 814/ 815/ 816/ 817/ 818/ 819

    TECHNICS OFFSHORE ENGINEERING PTE LTD,

    SINGAPORE

    Saipem Triune Engineering Pvt. Ltd.,

    New Delhi

    PROCESS CONTROL PHILOSOPHY

    DOCUMENT NUMBER REV.

    9512/08088-RC4-01-CP-001 A

    SHEET 44 OF 48

  • respectively for 9 wells which shall also take the measured value of downstream pressure RC4-

    PI-821/ 822/ 823/ 824/ 825/ 826/ 827/ 828/ 829 on PCS through local pressure transmitters

    RC4-PT-821/ 822/ 823/ 824/ 825/ 826/ 827/ 828/ 829. For detailed modes of operation, refer

    Gaslift Operation philosophy of VSP platforms.

    Two chock valves are provided from main header to one bypass header to provide controlled

    gas in case of maintenance of the main flow control angle valves.

    7.8.3 GASLIFT USE FOR SLUG REMOVAL & FOR GAS DISPOSAL.

    As the disposal of Gaslift is related to the underwater pipes before RISERS which are Gaslift

    main pipe from RP-3 platform to RC-4 Platform, Gaslift pipe to RC5 & RC-DM platforms, the

    take off point of this line are taken directly from three Gaslift Risers at RC4 platform.

    A shutdown valve RC4-SDV-802 is provided in the common disposal line. A chock valve is

    provided to throttle the flow. As this line is also to be used for removal of the slug

    accumulation in the Production separator gas outlet line whose design pressure is 60 barg so

    high pressure protection levels are given by providing three pressure transmitters RC4-PT-

    803A / 803B / 803C. On actual high pressure in this section of gaslift line after chock valve

    during disposal or slug removal, the indication from these three pressure transmitters shall

    generate Pressure High High alarm signals in PLC and based on the 2 out of 3 voting system,

    PLC shall activate the Pressure High High interlock RC4-PAHH-803 which shall shutdown the

    RC4-SDV-802 in the gaslift disposal line.

    TECHNICS OFFSHORE ENGINEERING PTE LTD,

    SINGAPORE

    Saipem Triune Engineering Pvt. Ltd.,

    New Delhi

    PROCESS CONTROL PHILOSOPHY

    DOCUMENT NUMBER REV.

    9512/08088-RC4-01-CP-001 A

    SHEET 45 OF 48

  • As 2nd level of safety, a pressure safety valve RC4-PSV-801 is also provided in this gaslift

    section.

    As the disposal is to be done from high pressure to low pressure through chock valve, there is

    potential of low temperature in this section if the disposal is not controlled properly. So a low

    temperature protection is given by providing a temperature transmitter RC4-TT-804 which

    shall generate the low temperature alarm signal in PLC and PLC shall activate RC4-TALL-804

    to shutdown the RC4-SDV-802 in gaslift disposal line.

    7.9 CHEMICAL INJECTION SYSTEM

    The Chemical Injection System includes dosing of the following Chemicals:

    Depressant

    Demulsifier

    7.9.1 DEPRESSANT

    Depressant Unloading is done from container by Unloading Pumps (H-700A5-1/ H-700A5-2).

    There are four Depressant Storage Tanks E-700A2-1, E-700A2-2 with capacity of 10 M3 each

    and E-700A3-1 & E-700A4-1 with capacity of 20 M3 each. Chemical can be transferred from

    Jack-up drilling Rig to storage tank.

    TECHNICS OFFSHORE ENGINEERING PTE LTD,

    SINGAPORE

    Saipem Triune Engineering Pvt. Ltd.,

    New Delhi

    PROCESS CONTROL PHILOSOPHY

    DOCUMENT NUMBER REV.

    9512/08088-RC4-01-CP-001 A

    SHEET 46 OF 48

  • Depressant Dosing pumps H-700A1-01/700A1-02/ 700A1-03/ 700A1-04/ 700A1-05/ 700A1-

    06/ 700A1-07/ 700A1-08/ 700A1-09/ 700A1-10/ 700A1-11 are pneumatic operated pumps and

    the pumps discharge has provision to inject the chemical to two different points which are X-

    Mas tree at down hole & at upstream of flow choke valve at well head.

    To start the dozing pump, instrument air valves (RC4-XV-711/ 712/ 713/ 714/ 715/ 716/ 717/

    718/ 719/ 720/ 721) are to be opened which can be done by local hand switches RC4-HS-

    711AA / 712AA/ 713AA/ 714AA / 715AA/ 716AA/ 717AA/ 718AA/ 719AA/ 720AA/ 721AA

    respectively and similarly to stop the pump, same instrument air valves are to be closed which

    can be done by either local hand switches RC4-HS-711AB / 712AB/ 713AB/ 714AB / 715AB/

    716AB/ 717AB/ 718AB/ 719AB/ 720AB/ 721AB respectively OR from remote hand switches

    RC4-HS-711B/ 712B/ 713B/ 714B/ 715B/ 716B/ 717B/ 718B/ 719B/ 720B/ 721B on PCS.

    There is trip of individual pump based on PSD-Well flow lines but the two common

    Deprassant Chemical injection pumps H-700A1-10/700A1-11 shall not trip on any individual

    Well PSD actuation. But if it is lined up towards any shutdown well then it is required to stop

    manually which is to be ensured through proper operating procedure and alarms.

    7.9.2 DEMULSIFIER

    Demulsifier Unloading is done from container by Unloading Pumps (H-700B5-1/ H-700B5-2).

    There are two Demulsifier Storage Tanks E-700B2-1, E-700B2-2 with capacity of 2 M3 each.

    Chemical can be transferred from Jack-up drilling Rig to storage tank.

    TECHNICS OFFSHORE ENGINEERING PTE LTD,

    SINGAPORE

    Saipem Triune Engineering Pvt. Ltd.,

    New Delhi

    PROCESS CONTROL PHILOSOPHY

    DOCUMENT NUMBER REV.

    9512/08088-RC4-01-CP-001 A

    SHEET 47 OF 48

  • Demulsifier Dosing pumps H-700B1-01/700B1-02/ 700B1-03/ 700B1-04/ 700B1-05/ 700B1-

    06/ 700B1-07/ 700B1-08/ 700B1-09/ 700B1-10/ 700B1-11 are pneumatic operated pumps and

    the pumps discharge has provision to inject the chemical to two different points which are X-

    Mas tree at down hole & at upstream of flow choke valve at well head.

    To start the dozing pump, instrument air valves (RC4-XV-761/ 762/ 763/ 764/ 765/ 766/ 767/

    768/ 769/ 770/ 771) are to be opened which can be done by local hand switches RC4-HS-

    761AA / 762AA/ 763AA/ 764AA / 765AA/ 766AA/ 767AA/ 768AA/ 769AA/ 770AA/ 771AA

    respectively and similarly to stop the pump, same instrument air valves are to be closed which

    can be done by either local hand switches RC4-HS-761AB / 762AB/ 763AB/ 764AB / 765AB/

    766AB/ 767AB/ 768AB/ 769AB/ 770AB/ 771AB respectively OR from remote hand switches

    RC4-HS-761B/ 762B/ 763B/ 764B/ 765B/ 766B/ 767B/ 768B/ 769B/ 770B/ 771B on PCS.

    There is trip of individual pump based on PSD-Well flow lines but the two common

    Demulsifier Chemical injection pumps H-700B1-10/700B1-11 shall not trip on any individual

    Well PSD actuation. But if it is lined up towards any shutdown well then it is required to stop

    manually which is to be ensured through proper operating procedure and alarms.

    *****************************************************************************

    TECHNICS OFFSHORE ENGINEERING PTE LTD,

    SINGAPORE

    Saipem Triune Engineering Pvt. Ltd.,

    New Delhi

    PROCESS CONTROL PHILOSOPHY

    DOCUMENT NUMBER REV.

    9512/08088-RC4-01-CP-001 A

    SHEET 48 OF 48

    VIETSOVPETRO - VIETNAMSHEET 1 of 45

    5.1.DESIGN FLOW RATES5.2.OPERATING AND DESIGN CONDITIONS5.3.COMPOSITION OF CRUDE OIL FEED5.4. COMPOSITION OF GASLIFT GAS5.5. CHARACTERISTICS OF PSEUDO COMPONENTS5.6.METEOROLOGICAL DATA Seismic Conditions5.7.SIMULATION CASES