PRINCIPLES INCLUDED IN LIGHTNING RISK ANALYSIS Marlenique Estate, Paarl South Africa 14 August 2019 Pieter H Pretorius, PhD
PRINCIPLES INCLUDED IN LIGHTNING
RISK ANALYSIS
Marlenique Estate, Paarl
South Africa
14 August 2019
Pieter H Pretorius, PhD
1
Objective: Highlight some challenges specific to PV
installations and lightning protection.
Title: Principles Included in Lightning Risk Analysis.
Synonyms-“Principles”: philosophies
opinions
standards
norms
2
OUTLINE
© 2019
Introduction / outline.
Risk management (What is risk and what do we want to
achieve?)
Risk assessment process (IEC 62305-2 versus Classic)
Specific aspects: Engineering - Design - Construction
Concluding Remarks
3
OUTLINE
© 2019
SANS / IEC 62305 Standard – Protection Against Lightning
67 pages 84 pages 156 pages 87 pages
Comprehensive standard - 394 pages
4
OUTLINE
© 2019
Context – large utility scale PV plant
Principles apply to any PV installation.
5
OUTLINE
© 2019
Type: Flat panel PV
Units operational: 277 632
Capacity: 75 MWp; 64 MWAC
Ref: https://en.wikipedia.org/wiki/Lesedi_Solar_Park, Last Accessed 1 Aug 2019.
What is risk?
6
RISK MANAGEMENT
© 2019
• Risk (R): The value of probable average annual loss (humans and goods)
due to lightning, relative to the total value (humans and goods) of the
structure to be protected;
SANS/IEC 62305-2, Edition 2, “Protection Against Lightning, Part 2: Risk
Management”, (2011 / 2010).
Ref: SANS/IEC 62305-2, Edition 2, “Protection Against Lightning, Part 2: Risk Management”, (2011 / 2010).
P H Pretorius, Lightning Risk Considerations Related to Wire-Line Technology Applied in Large Utility Scale PV Plant, Paper Submitted forpresentation at the 9th CIGRE Southern Africa Regional Conference, Johannesburg, South Africa, 1 – 4 October 2019.
What is risk?
7
RISK MANAGEMENT
© 2019
Ref: SANS/IEC 62305-2, Edition 2, “Protection Against Lightning, Part 2: Risk Management”, (2011 / 2010).
P H Pretorius, Lightning Risk Considerations Related to Wire-Line Technology Applied in Large Utility Scale PV Plant, Paper Submitted forpresentation at the 9th CIGRE Southern Africa Regional Conference, Johannesburg, South Africa, 1 – 4 October 2019.
SANS/IEC 62305-2, Edition 2, “Protection Against Lightning, Part 2: Risk
Management”, (2011 / 2010).
General equation
RX = NX x PX x LX
where
NX is the number of dangerous events per annum;
PX is the probability of damage to a structure;
LX is the consequent loss.
Equation applies to each risk component RA, RB, RC, RM, RU, RV, RW and RZ
What is risk?
8
RISK MANAGEMENT
© 2019
For each type of loss that may occur, the relevant risk is evaluated in
accordance with SANS / IEC 62305-2. Risks to be evaluated for typical
structure:
o R1 - Risk of loss of human life (including permanent injury);
o R2 - Risk of loss of service to the public;
o R3 - Risk of loss of cultural heritage;
o R4 - Risk of loss of economic value;
With R1 and R4 more relevant in the context of large, utility scale PV plant.
SANS/IEC 62305-2, Edition 2, “Protection Against Lightning, Part 2: Risk
Management”, (2011 / 2010).
What is risk?
9
RISK MANAGEMENT
© 2019
• Risk Component (RX): The partial risk depending on the source and
the type of damage;
To evaluate the risk, R, “the relevant risk components (partial risks
depending on the source and type of damage) shall be defined and
calculated.
R, is the sum of risk components. When calculating a risk, the risk
components may be grouped according to the source of damage and the
type of damage”.
SANS/IEC 62305-2, Edition 2, “Protection Against Lightning, Part 2: Risk
Management”, (2011 / 2010).
NB: In terms of coupling modes!
Risk components a function of source and type of damage
10
RISK MANAGEMENT
© 2019
RX = NX x PX x LX
Note: RA and RB for flow chart later.
Note: RU and RV for flow chart later.
LEMP
all electromagnetic effects of lightning current via
resistive, inductive and capacitive coupling,
which create surges and electromagnetic fields
Number of dangerous events:
11
RISK MANAGEMENT
© 2019
SANS/IEC 62305-2, Edition 2, “Protection Against Lightning, Part 2: Risk
Management”, (2011 / 2010).
RX = NX x PX x LX
The number NX of dangerous events – function of:
• Lightning ground flash density;
• Physical characteristics of the structure to be protected;
• Surroundings of the structure;
• Connected lines;
• Soil resistivity.
Lightning flash density
13
RISK MANAGEMENT
© 2019
• Is the risk for lightning damage in southern parts of Namibia lower / higher
compared to Northern Cape?
R = N x P x L
Lightning collection area
15
RISK MANAGEMENT
© 2019
Source of image: Furse
• Direct strikes to / near the structure.
• Direct strikes to / near the service lines.
Probability of damage:
16
RISK MANAGEMENT
© 2019
SANS/IEC 62305-2, Edition 2, “Protection Against Lightning, Part 2: Risk
Management”, (2011 / 2010).
RX = NX x PX x LX
The probability of damage PX – function of:
• Characteristics of the structure;
• Connected lines;
• Protection measures provided;
• Technology employed.
Risk Management Process – SANS / IEC 62305-2
17
RISK MANAGEMENT
© 2019
Every risk component describes a certain threat to lightning (danger) and a
potential loss.
The loss resulting from lightning is defined as:
• L1 = Loss of human life
• L2 = Loss of service to the public
• L3 = Loss of cultural heritage
• L4 = Loss of economic value
RX = NX x PX x LX
Consequent Loss:
18
RISK MANAGEMENT
© 2019
RX = NX x PX x LX
The consequent loss LX – function of:
• Use assigned to the structure;
• Attendance of personnel or public;
• Type of service provided to public;
• Value of goods affected by damage;
• Measures provided to limit the amount of loss.
SANS/IEC 62305-2, Edition 2, “Protection Against Lightning, Part 2: Risk
Management”, (2011 / 2010).
Part of standard that provides information on:
19
RISK MANAGEMENT
© 2019
SANS/IEC 62305-2, Edition 2, “Protection Against Lightning, Part 2: Risk
Management”, (2011 / 2010).
RX = NX x PX x LX
Annex A – Annual
number of
dangerous events
Annex B –
Probability of
damage
Annex C – Amount
of Loss
Annex E – Case
study
Risk Management Process – SANS / IEC 62305-2
20
RISK MANAGEMENT
© 2019
Ref: SANS/IEC 62305-2, Edition 2, “Protection Against Lightning, Part 2: Risk Management”, (2011 / 2010).
To assess each risk component, the structure is typically divided into zones ZS with
each zone having homogeneous characteristics.
(Note: A structure may be selected to form a single zone).
Zones ZS are mainly defined by:
• The type of soil or of floor / floor covering (RA and RU);
• Fireproof compartments (RB and RV) ;
• Spatial shields (RC and RM).
RA: Electric shock to living beings due to step and touch potentials (inside and outside of the structure up to 3 m).
RB: Fire and explosion effects inside the structure due to and including sparking;
RC: Component failure due to LEMP on internal installations and incoming services.
RM: Failure of electrical and electronic systems due to LEMP on internal installations.
RU: Injuries of living beings caused by touch voltage inside the structure due to lightning current injected into a line entering the structure.
RV: Fire effects inside the structure due to mechanical and thermal effects including dangerous sparking between incoming lines and metal
parts of installations.
Risk Management Process – SANS / IEC 62305-2
21
RISK MANAGEMENT
© 2019
Ref: SANS/IEC 62305-2, Edition 2, “Protection Against Lightning, Part 2: Risk Management”, (2011 / 2010).
Further, zones may also be defined according to
• Layout of internal systems (RC and RM),
• Protection measures existing or to be installed (applies to all risk components),
• Loss LX values (applies to all risk components).
Partitioning of the structure into zones (ZS) should take into account the feasibility
of the implementation of the most suitable protection measures.
RC: Component failure due to LEMP on internal installations and incoming services.
RM: Failure of electrical and electronic systems due to LEMP on internal installations.
How much risk can be tolerated?
22
RISK MANAGEMENT
© 2019
• Tolerable risk (RT): The maximum value of the risk which can be
tolerated with the structure protected;
Ref: https://www.encyclopedia.com/computing/dictionaries-thesauruses-pictures-and-press-releases/tolerable-risk, Last Accessed 1 Aug 2019.
SANS/IEC 62305-2, Edition 2, “Protection Against Lightning, Part 2: Risk
Management”, (2011 / 2010).
NB: Introduce a LPS to mitigate the risk – not to eliminate risk!
Objective is to reduce the risk to an acceptable level.
(A level of risk deemed acceptable by society in order that some
particular benefit or functionality can be obtained, but in the knowledge
that the risk has been evaluated and is being managed).
Since zero risk is completely unachievable, most regulators defines
what is called the “Tolerable risk” (or “Acceptable risk”).
LPL Efficiency: 98% 95% 86% 79%
r = 20 m 30 m 45 m 60 m
How much risk can be tolerated?
23
RISK MANAGEMENT
© 2019
SANS / IEC 62305-1:
NB: LPS mitigate the risk – does not eliminate risk!
What do we want to achieve? Principle:
24
RISK MANAGEMENT
© 2019
ALARP - "as low as reasonably practicable”
ALARA - "as low as reasonably achievable”
are terms often used in the regulation and management of safety-critical and
safety-involved systems.
The ALARP principle requires that the residual risk shall be reduced as far as
reasonably practicable.
The residual risk is the amount of risk or danger associated with an action or
event remaining after natural or inherent risks have been reduced by risk
controls.
Ref: https://www.encyclopedia.com/computing/dictionaries-thesauruses-pictures-and-press-releases/tolerable-risk, Last Accessed 1 Aug 2019.
ALARP Principle widely applied in various industries.
25
RISK MANAGEMENT
© 2019
Ref: European Maritime Safety Agency (EMSA/OP/10/2013), Risk Acceptance Criteria and Risk Based Damage Stability, Final Report - Part 1: Risk
Acceptance Criteria, Report No 2015-0165, Rev 1, Document No.: 18KJ9LI-47, 24 Feb 2015.
Individual Risk Criteria
26
RISK MANAGEMENT
© 2019
Ref: European Maritime Safety Agency (EMSA/OP/10/2013), Risk Acceptance Criteria and Risk Based Damage Stability, Final Report - Part 1: Risk
Acceptance Criteria, Report No 2015-0165, Rev 1, Document No.: 18KJ9LI-47, 24 Feb 2015.
NB: Can apply to
individual components
at specific locations in
plant.
LSIR – Location specific individual risk
Criteria Used by US Federal Regulatory Agencies
27
RISK MANAGEMENT
© 2019
NB: Can apply to systems in plant.
Ref: Eric Marsden, Risk acceptability and tolerability, https://risk-engineering.org/risk-acceptability-tolerability/, Last Accessed 1 Aug 2019.
Risk Criteria - Approach
28
RISK MANAGEMENT
© 2019
Ref: European Maritime Safety Agency (EMSA/OP/10/2013), Risk Acceptance Criteria and Risk Based Damage Stability, Final Report - Part 1: Risk
Acceptance Criteria, Report No 2015-0165, Rev 1, Document No.: 18KJ9LI-47, 24 Feb 2015.
Tolerable risk – SANS / IEC 62305-2
29
RISK MANAGEMENT
© 2019
Ref: SANS/IEC 62305-2, Edition 2, “Protection Against Lightning, Part 2: Risk Management”, (2011 / 2010).
Loss
L1
L2
L3
L4
RT per Year
1 x 10-5
1 x 10-3
1 x 10-4
(See cost benefit analysis)
o L1 - Loss of a human life (including permanent injury);
o L2 - Loss of service to the public;
o L3 - Loss of cultural heritage;
o L4 - Loss of economic value (if not otherwise defined – see Cost Benefit Analysis);
Cost Benefit Criteria
30
RISK MANAGEMENT
© 2019
• Cost-benefit criteria - defining the acceptable cost of risk reduction measures
in a cost-benefit analysis.
• Although these do not evaluate the significance of risks directly, and hence are
not strictly risk criteria at all, they do evaluate the need for risk reduction, and
are closely connected to risk criteria.
Ref: European Maritime Safety Agency (EMSA/OP/10/2013), Risk Acceptance Criteria and Risk Based Damage Stability, Final Report - Part 1: Risk
Acceptance Criteria, Report No 2015-0165, Rev 1, Document No.: 18KJ9LI-47, 24 Feb 2015.
NB: - In view of contractual agreements.
- Economies of scale.
Cost Benefit Criteria
31
RISK MANAGEMENT
© 2019
Ref: https://www.popularmechanics.co.za/tech/karoos-kalkbult-solar-pv-plant-could-power-up-to-33-000-homes/, Last Accessed 12 Aug 2019.
NB: - Economies of scale.
Kalkbult PV Plant (Northern Cape):
• 75 MW plant - Fixed tilt;
• 312 000 solar panels;
• 105 hectares (1024,7 m x 1024,7 m);
• 1 800 km of cabling connecting all the panels,
inverters and transformers to the high-voltage
substation;
Deduce:
• Approx 42 Inverter Stations (From image);
• Scada could be in tens of 1000’s of km cable;
• Combiner boxes / (Tracker units with tilt control) /
Earth conductors / SPDs ?
Cost Benefit Criteria – SANS / IEC 62305-2
32
RISK MANAGEMENT
© 2019
Ref: SANS/IEC 62305-2, Edition 2, “Protection Against Lightning, Part 2: Risk Management”, (2011 / 2010).
Evaluation of Cost of Loss Includes Reflection on Annual Saving in Cost
Without protection measures;
With protection measures;
No Parameter Calculated From Description
1 CLZ CLZ = R4Z x ct Cost of loss in a zone
2 R4Z The risk related to loss of value in the zone, without protection measures
3 ct The total value of the structure (animals, building, content and internal systems including their activities in currency)
4 CL CL = ∑ CLZ = R4 x ct The cost of total loss in the structure
5 R4 R4 = ∑ R4Z The risk related to loss of value, without protection measures
6 CRLZ CRLZ = R'4Z x ct The cost of residual loss in a zone in spite of protection measures
7 R'4Z The risk related to loss of value in the zone, with protection measures
8 CRL CRL = ∑ CRLZ = R'4 x ct The total cost of residual loss in the structure in spite of protection measures
9 R'4 R'4 = ∑ R'4Z The risk related to loss of value in the structure, with protection measures
10 CPM CPM = CP x (i + a + m) The annual cost of protection measures
11 CP The cost of protection measures;
12 i The interest rate;
13 a The amortization rate;
14 m The maintenance rate.
15 SM SM = CL - (CPM + CRL) The annual saving in money
16 SM ≥ 0 Protection is justified if the annual saving in money is equal or more than the annual saving in money
SM = CL – (CPM + CRL)
Saving = Cost of Loss – (Cost of Protection + Cost of Residual Loss (damage))
Risk Management Process – SANS / IEC 62305-2
33
RISK MANAGEMENT
© 2019
Ref: SANS/IEC 62305-2, Edition 2, “Protection Against Lightning, Part 2:Risk Management”, (2011 / 2010).
RA: Electric shock to living beings due to step and touch
potentials (inside and outside of the structure up to 3 m);
RB: Fire and explosion effects inside the structure due to and
including sparking;
If RA + RB < RT, a complete LPS is not necessary; In this case
SPDs according to IEC 62305-3 are sufficient.
Identify structure to be
protected
Identify type of loss
relevant to structure
For each type of loss, calculate the risk components
(RA, RB, RC, RM, RV, RU, RW, RZ)
R > RT Structure protected
Introduce protection
No
Yes
LPS Installed?Yes
SPM Installed?Yes
Calculate new values of
risk components
No No
RA + RB + RU
+ RV > RT
No
Yes
Install adequate type LPS Install adequate type SPMInstall other protection
measures
RU: Injuries of living beings caused by touch voltage inside the
structure due to lightning current injected into a line entering
the structure;
RV: Fire effects inside the structure due to mechanical and
thermal effects including dangerous sparking between
incoming lines and metal parts of installations;
Risk Management Process – Classic Approach
34
RISK MANAGEMENT
© 2019
Ref: Eric Marsden, Risk acceptability and tolerability, https://risk-engineering.org/risk-acceptability-tolerability/, Last Accessed 1 Aug 2019.
Risk assessment process
35
RISK ASSESSMENT PROCESS
© 2019
Proposed - based on the risk assessment process for risk quantification and risk
management in renewable energy projects as applied by Michelez, et al, (2011).
The risk management process is based on the classical risk assessment process
that involves:
• The development of a risk register;
• Quantification of the risk level based on probability and impact using the scale
noted by Michelez, et al, (2011);
• Development of a qualitative risk evaluation matrix that reflects the original risk;
• Identification of the mitigation options;
• Development of a qualitative risk evaluation matrix that reflects the mitigated
risk;
Ref: P H Pretorius, Lightning Risk Considerations Related to Wire-Line Technology Applied in Large Utility Scale PV Plant, Paper Submitted for
presentation at the 9th CIGRE Southern Africa Regional Conference, Johannesburg, South Africa, 1 – 4 October 2019.
J Michelez, N Rossi, R Blazquez, J M Martin, E Mera, D Christensen, C Peineke, K Graf, D Lyon, G Stevens, “Risk Quantification and Risk
Management in Renewable Energy Projects”, (Report Commissioned by IEA – Renewable Energy Technology Deployment, Altran GmbH & Co, KGKonstantin Graf, 14 Jun 2011).
Risk register
36
RISK ASSESSMENT PROCESS
© 2019
The Risk Register:
• Includes a list of the lightning risk to different systems or components of the
plant.
• From this follows a risk quantification (Original Risk – without Mitigation) done
to compile the risk quantification matrix.
Ref: P H Pretorius, Lightning Risk Considerations Related to Wire-Line Technology Applied in Large Utility Scale PV Plant, Paper Submitted for
presentation at the 9th CIGRE Southern Africa Regional Conference, Johannesburg, South Africa, 1 – 4 October 2019.
J Michelez, N Rossi, R Blazquez, J M Martin, E Mera, D Christensen, C Peineke, K Graf, D Lyon, G Stevens, “Risk Quantification and Risk
Management in Renewable Energy Projects”, (Report Commissioned by IEA – Renewable Energy Technology Deployment, Altran GmbH & Co, KGKonstantin Graf, 14 Jun 2011).
Risk quantification - risk levels and scale [Michelez, et al, (2011)]
37
RISK ASSESSMENT PROCESS
© 2019
Ref: P H Pretorius, Lightning Risk Considerations Related to Wire-Line Technology Applied in Large Utility Scale PV Plant, Paper Submitted for
presentation at the 9th CIGRE Southern Africa Regional Conference, Johannesburg, South Africa, 1 – 4 October 2019.
J Michelez, N Rossi, R Blazquez, J M Martin, E Mera, D Christensen, C Peineke, K Graf, D Lyon, G Stevens, “Risk Quantification and Risk
Management in Renewable Energy Projects”, (Report Commissioned by IEA – Renewable Energy Technology Deployment, Altran GmbH & Co, KGKonstantin Graf, 14 Jun 2011).
Risk quantification matrix
38
RISK ASSESSMENT PROCESS
© 2019
Ref: P H Pretorius, Lightning Risk Considerations Related to Wire-Line Technology Applied in Large Utility Scale PV Plant, Paper Submitted for
presentation at the 9th CIGRE Southern Africa Regional Conference, Johannesburg, South Africa, 1 – 4 October 2019.
P H Pretorius, Lightning Risk Assessment Beyond the Ordinary – Application to Renewable Plant, Inaugural Earthing Africa 2017 Symposium and
Exhibition, Thaba Eco Hotel, Johannesburg, 5 – 9 Jun 2017.
Depending on impact and probability of occurrence, the risk quantification matrix to
reflect where particular risk will fall.
Example: single risk (A) (original, without mitigation) shown – Objective to lower the
risk from “Intolerable” to ideally “Acceptable”, as illustrated.
Risk quantification matrix
39
RISK ASSESSMENT PROCESS
© 2019
Ref: P H Pretorius, Lightning Risk Considerations Related to Wire-Line Technology Applied in Large Utility Scale PV Plant, Paper Submitted for
presentation at the 9th CIGRE Southern Africa Regional Conference, Johannesburg, South Africa, 1 – 4 October 2019.
P H Pretorius, Lightning Risk Assessment Beyond the Ordinary – Application to Renewable Plant, Inaugural Earthing Africa 2017 Symposium and
Exhibition, Thaba Eco Hotel, Johannesburg, 5 – 9 Jun 2017.
BEFORE MITIGATION
EXAMPLE FOR
ILLUSTRATION ONLY
(Monte Carlo or
measured data).
EXAMPLE FOR ILLUSTRATION ONLY
Risk quantification matrix
40
RISK ASSESSMENT PROCESS
© 2019
Ref: P H Pretorius, Lightning Risk Considerations Related to Wire-Line Technology Applied in Large Utility Scale PV Plant, Paper Submitted for
presentation at the 9th CIGRE Southern Africa Regional Conference, Johannesburg, South Africa, 1 – 4 October 2019.
P H Pretorius, Lightning Risk Assessment Beyond the Ordinary – Application to Renewable Plant, Inaugural Earthing Africa 2017 Symposium and
Exhibition, Thaba Eco Hotel, Johannesburg, 5 – 9 Jun 2017.
FOLLOWING MITIGATION
EXAMPLE FOR
ILLUSTRATION ONLY
(Monte Carlo or
measured data).
EXAMPLE FOR ILLUSTRATION ONLY
• Reduced 10%
(mitigation)
Engineering – Where to start ?
• User Requirement Specification (URS);
• Lightning risk assessment (vary widely – 2006 Edition still
in use!);
41
ENGINEERING - DESIGN - CONSTRUCTION
© 2019
Design – Experienced designer
42
ENGINEERING - DESIGN - CONSTRUCTION
© 2019
Specific Note from IEC 62305: The following is noted from IEC 62305-3:
“The lightning protection designer and installer should be trained in the proper
design and installation of the LPS components in accordance with the
requirements of this standard and the national rules regulating construction
work and the building of structures”.
Implies that standard is written such that the LPS designer will understand the
aspects covered / not covered and implications thereof.
Implication: Possible underestimation of risk.
Design – Limitations of standards (1)
43
ENGINEERING - DESIGN - CONSTRUCTION
© 2019
• It is specifically noted from IEC 62305-4 that:
“The scope of this part of IEC 62305 deals with the protection of equipment
within structures and not protection of interconnected structures to which
isolation transformers may provide some benefit”.
Limitation: Large earth electrode embedded in high soil resistivity soil, with
wireline technology, will behave as if it is an interconnected structure as a
result of lightning GPR.
Implication: IEC 62305 has limited application to lightning protection of wire-
line technology accompanied by large electrodes, such as that applied in
open field photovoltaic (PV) plants because of the potential equipment threat
presented by lightning GPR.
Ref: P H Pretorius, Lightning Risk Considerations Related to Wire-Line Technology Applied in Large Utility Scale PV Plant, Paper Submitted forpresentation at the 9th CIGRE Southern Africa Regional Conference, Johannesburg, South Africa, 1 – 4 October 2019.
Implication: Underestimation of risk.
Design – Lightning GPR – Electrode Behaviour
44
ENGINEERING - DESIGN - CONSTRUCTION
© 2019
Potential (V)
Distance from Strike Point (m)
Potential function of soil resistivity, electrode material & geometry / mesh density.
Design – Lightning GPR – Loss of Equipotential
45
ENGINEERING - DESIGN - CONSTRUCTION
© 2019
5 / 20 µs
100 Ω.m
100 m x 100 m
Time Domain
Design – Lightning GPR – Loss of Equipotential
46
ENGINEERING - DESIGN - CONSTRUCTION
© 2019
5 / 20 µs
100 Ω.m
100 m x 100 m
Time Domain
Design – Lightning GPR – Loss of Equipotential
47
ENGINEERING - DESIGN - CONSTRUCTION
© 2019
800 m x 500 m grid - 50 x 50 m mesh density - buried at 1 m depth -
galvanised steel (12 mm ɸ) - relative resistivity of 7,7 & relative permeability of
600 - strike point off-centre dot on electrode.
Lightning Impulse:
Peak Impulse Current 4 kA (98 % probability);
Rise Time (dI/dt) 1,8 µs
Time to Half Value 30 µs
Time Duration 150 µs allowed in the model.
Ref: P H Pretorius, Loss of Equipotential During Lightning Ground Potential Rise on Large Earthing Systems, Joint IEEE International Symposium on
Electromagnetic Compatibility & Asia‐Pacific Symposium on Electromagnetic Compatibility (2018 Joint IEEE EMC & APEMC), Suntec Convention
and Exhibition Centre, Singapore, 14 to 17 May 2018.
P.H. Pretorius, “Lightning Damage Associated with Wire Line Technology and Large Electrodes – A Hypothesis”, Inaugural Earthing Africa 2017
Symposium and Exhibition, Thaba Eco Hotel, Johannesburg, 5 – 9 Jun 2017.
Frequency Domain
R = 0,7 Ω
48
ENGINEERING - DESIGN - CONSTRUCTION
© 2019
o Higher soil resistivity presents
higher GPR, as expected;
o Higher frequencies in the
lightning current have a
localized effect on the GPR;
o The localized effect of the
GPR eradicates the
“equipotential” across the
electrode;
o Equipotential (Quasi-
equipotential) is only relevant
at lower frequencies;
Main point:
Loss of Equipotential
Ref: P H Pretorius, Loss of Equipotential During
Lightning Ground Potential Rise on Large
Earthing Systems, Joint IEEE International
Symposium on Electromagnetic Compatibility &
Asia‐Pacific Symposium on Electromagnetic
Compatibility (2018 Joint IEEE EMC & APEMC),
Suntec Convention and Exhibition Centre,
Singapore, 14 to 17 May 2018.
Frequency Domain
Design – Lightning GPR – Loss of Equipotential
49
ENGINEERING - DESIGN - CONSTRUCTION
© 2019
4,5 m
Impulse: 4 kA, 1.8 / 150 µs
Ref: P H Pretorius, Loss of Equipotential During Lightning Ground Potential Rise on Large Earthing Systems, Joint IEEE International Symposium on
Electromagnetic Compatibility & Asia‐Pacific Symposium on Electromagnetic Compatibility (2018 Joint IEEE EMC & APEMC), Suntec Convention
and Exhibition Centre, Singapore, 14 to 17 May 2018.
Part of PV plant electrode with panel support structures. Calculated GPD across part of an electrode shown
Finding: Over relatively short distances (23 m to 50 m), significant differences in
potential (up to 66.1 kV) can be presented.
Design – Lightning GPR
Unique Combinations of Conditions
* High soil resistivity (> 1000 Ω.m more prominent at higher soil resistivities)
* Lightning activity
* Wire-line technology
50
ENGINEERING - DESIGN - CONSTRUCTION
© 2019
Ref: P H Pretorius, On Ground Potential Rise Presented by Small and Large Earth Electrodes Under Lightning Conditions, IEEE AFRICON 2017,
Victoria and Alfred (V&A) Waterfront Cape Town, South Africa, 18 to 20 September 2017.
What is risk?
51© 2019
• Is the risk for lightning damage in southern parts of Namibia lower / higher
compared to Northern Cape?
Ref: P H Pretorius, Lightning Risk Considerations Related to Wire-Line Technology Applied in Large Utility Scale PV Plant, Paper Submitted forpresentation at the 9th CIGRE Southern Africa Regional Conference, Johannesburg, South Africa, 1 – 4 October 2019.
R = N x P x L
ENGINEERING - DESIGN - CONSTRUCTION
If lightning GPR ignored
Design – Lightning GPR Mitigation
❑ Single point earthing
❑ Isolating interfaces (IEC 62305)
(opto isolators / isolation transformers / optic fibre etc).
52
ENGINEERING - DESIGN - CONSTRUCTION
© 2019
Design – SANS / IEC 62305 – Isolation Devices
53
ENGINEERING - DESIGN - CONSTRUCTION
© 2019
- Isolating interface
Fibre / Radio offers best isolation.
Design – Proposal to Continue Using SANS / IEC 62305-2
54
ENGINEERING - DESIGN - CONSTRUCTION
© 2019
Ref: P H Pretorius, Lightning Risk Considerations Related to
Wire-Line Technology Applied in Large Utility Scale PV
Plant, Paper Submitted for presentation at the 9th CIGRE
Southern Africa Regional Conference, Johannesburg,South Africa, 1 – 4 October 2019.
Existing SANS / IEC 62305-2 Process Proposed Adjunct Process
Mitigate / eliminate lightning GPR –
Consider costGPR?
Identify structure to be
protected
Identify type of loss
relevant to structure
For each type of loss, calculate the risk components
(RA, RB, RC, RM, RV, RU, RW, RZ)
R > RT Structure protected
Introduce protection
No
Yes
LPS Installed?Yes
SPM Installed?Yes
Calculate new values of
risk components
No No
RA + RB + RU
+ RV > RT
No
Yes
Install adequate type LPS Install adequate type SPMInstall other protection
measures
Identify structure to be
protected
Identify type of loss
relevant to structure
For each type of loss, calculate the risk components
(RA, RB, RC, RM, RV, RU, RW, RZ)
R > RT Structure protected
Introduce protection
No
Yes
LPS Installed?Yes
SPM Installed?Yes
Calculate new values of
risk components
No No
RA + RB + RU
+ RV > RT
No
Yes
Install adequate type LPS Install adequate type SPMInstall other protection
measures
Design – Limitations of standards (2)
55
ENGINEERING - DESIGN - CONSTRUCTION
© 2019
• IEC 62305-3 notes:
“For the earth termination system: When dealing with the dispersion of the
lightning current (high frequency behaviour) into the ground, whilst minimizing
any potentially dangerous overvoltages, the shape and dimensions of the earth-
termination system are the important criteria. In general, a low earthing
resistance (if possible lower than 10 Ω when measured at low frequency) is
recommended”.
• Referencing a low frequency parameter to addresses lightning (with high
frequency content):
• Shown earlier earth electrode resistance of 0,7 Ω (1000 Ω.m soil);
• Significant GPR levels can still exist - despite << 10 Ω;
Ref: P H Pretorius, Lightning Risk Considerations Related to Wire-Line Technology Applied in Large Utility Scale PV Plant, Paper Submitted forpresentation at the 9th CIGRE Southern Africa Regional Conference, Johannesburg, South Africa, 1 – 4 October 2019.
Implication: Underestimation of risk (if 10 Ω is only compliance criterion).
Design – Limitations of standards (3)
56
ENGINEERING - DESIGN - CONSTRUCTION
© 2019
• IEC 62305-2: Indicates that the line installation factors of selected tables in
the standard are based on a soil resistivity of 400 Ω.m.
• Has a direct implication on the collection area of buried cable section: In
general, the higher the soil resistivity, the larger the collection area which is
directly proportional to the square root of the soil resistivity.
In the Northern Cape, in South Africa, where typical utility scale PV plant
are installed, it is not unusual to find soil resistivities well above 1000 Ω.m,
suggesting that the collection area is well underestimated, if not
compensated for.
Ref: P H Pretorius, Lightning Risk Considerations Related to Wire-Line Technology Applied in Large Utility Scale PV Plant, Paper Submitted forpresentation at the 9th CIGRE Southern Africa Regional Conference, Johannesburg, South Africa, 1 – 4 October 2019.
Implication: Underestimation of risk (if not compensated for).
Design – Limitations of standards (4)
57
ENGINEERING - DESIGN - CONSTRUCTION
© 2019
• Even though not directly linked to the standard and in some cases, LPS
designers do not have access to financial information of the plant (due to
project confidentiality agreements) when it is required to assess risk in
terms of R4 (Risk of loss of economic value). This in itself constrains the
risk assessment and presents the risk assessment process as
subjective.
Ref: P H Pretorius, Lightning Risk Considerations Related to Wire-Line Technology Applied in Large Utility Scale PV Plant, Paper Submitted forpresentation at the 9th CIGRE Southern Africa Regional Conference, Johannesburg, South Africa, 1 – 4 October 2019.
NB: In view of financial figures captured in contracts.
Construction – poor installation – increase risk
Poor SPD Wiring
58
ENGINEERING - DESIGN - CONSTRUCTION
© 2019
Image Source: DEHN
Construction – poor installation – increase risk
Poor Installation / Design
59
ENGINEERING - DESIGN - CONSTRUCTION
© 2019
Construction
• Installation Safety Report
• Lightning Risk Assessment
60
ENGINEERING - DESIGN - CONSTRUCTION
© 2019
Responsibility:
Designer & Installer
Liability:
Designer & Installer
Outlined and highlighted some of the principles included in
lightning risk analysis.
SANS – IEC 62305 useful and important standard.
Some limitations / gaps associated with the current version
(Edition 2) of the standard.
Awareness of these are important – design perspective.
Complete / proper design responsibility and liability remains with the design engineer as lightning protection expert.
61
CONCLUDING REMARKS
© 2019
64
CONCLUDING REMARKS - TERRATECH
© 2019
TERRATECH is the international distributor of CDEGS Software
in South Africa.
What : 1 to 2 day CPD course (includes 50 Hz safety).
When : Nov / Dec 2019
Where : Johannesburg (also considering Cape Town)
65
CONCLUDING REMARKS - TERRATECH
© 2019