7/27/2019 Primavera 10.0...Contract Manager
1/506
Primavera
Contract Manager Users Guide
7/27/2019 Primavera 10.0...Contract Manager
2/506
Copyright 1996, 2009, Oracle and/or its affiliates. All rights reserved. .
The Programs (which include both the software and documentation) contain proprietary information; they are
provided under a license agreement containing restrictions on use and disclosure and are also protected by
copyright, patent, and other intellectual and industrial property laws. Reverse engineering, disassembly, or
decompilation of the Programs, except to the extent required to obtain interoperability with other independentlycreated software or as specified by law, is prohibited.
The information contained in this document is subject to change without notice. If you find any problems in the
documentation, please report them to us in writing. This document is not warranted to be error-free. Except as
may be expressly permitted in your license agreement for these Programs, no part of these Programs may be
reproduced or transmitted in any form or by any means, electronic or mechanical, for any purpose.
If the Programs are delivered to the United States Government or anyone licensing or using the Programs on
behalf of the United States Government, the following notice is applicable:
U.S. GOVERNMENT RIGHTS Programs, software, databases, and related documentation and technical data
delivered to U.S. Government customers are "commercial computer software" or "commercial technical data"
pursuant to the applicable Federal Acquisition Regulation and agency-specific supplemental regulations. Assuch, use, duplication, disclosure, modification, and adaptation of the Programs, including documentation and
technical data, shall be subject to the licensing restrictions set forth in the applicable Oracle license agreement,
and, to the extent applicable, the additional rights set forth in FAR 52.227-19, Commercial Computer Software--
Restricted Rights (June 1987). Oracle USA, Inc., 500 Oracle Parkway, Redwood City, CA 94065.
The Programs are not intended for use in any nuclear, aviation, mass transit, medical, or other inherently
dangerous applications. It shall be the licensee's responsibility to take all appropriate fail-safe, backup, redun-
dancy and other measures to ensure the safe use of such applications if the Programs are used for such purposes,
and we disclaim liability for any damages caused by such use of the Programs.
Oracle, JD Edwards, PeopleSoft, and Siebel are registered trademarks of Oracle Corporation and/or its affiliates.
Other names may be trademarks of their respective owners.
The Programs may provide links to Web sites and access to content, products, and services from third parties.
Oracle is not responsible for the availability of, or any content provided on, third-party Web sites. You bear all
risks associated with the use of such content. If you choose to purchase any products or services from a third
party, the relationship is directly between you and the third party. Oracle is not responsible for: (a) the quality of
third-party products or services; or (b) fulfilling any of the terms of the agreement with the third party, including
delivery of products or services and warranty obligations related to purchased products or services. Oracle is not
responsible for any loss or damage of any sort that you may incur from dealing with any third party.
Certain products included in the software require the following disclosures:
* * * * *
Portions copyright (c) Macromedia, Inc. All rights reserved.
* * * * *
Portions (c) Microsoft Corporation. All rights reserved.
7/27/2019 Primavera 10.0...Contract Manager
3/506
* * * * *
Copyright 2002 Sybase, Inc. All Rights Reserved.
* * * * *
Apache Software License Version 1.1 Components
Commons-codec, Jakarta-poi, POI are licensed under the Apache Software License Version 1.1, which requires
the following disclosures:
Copyright (c) 2000 The Apache Software Foundation. All rights reserved.
Redistribution and use in source and binary forms, with or without modification, are permitted provided that the
following conditions are met:
1. Redistributions of source code must retain the above copyright notice, this list of conditions and the following
disclaimer.
2. Redistributions in binary form must reproduce the above copyright notice, this list of conditions and the
following disclaimer in the documentation and/or other materials provided with the distribution.
3. The end-user documentation included with the redistribution, if any, must include the following acknowl-
edgment:
"This product includes software developed by the Apache Software Foundation (http://www.apache.org/)."
Alternately, this acknowledgment may appear in the software itself, if and wherever such third-party acknowl-
edgments normally appear.
4. The names "Apache" and "Apache Software Foundation" must not be used to endorse or promote products
derived from this software without prior written permission. For written permission, please contact
5. Products derived from this software may not be called "Apache", nor may "Apache" appear in their name,
without prior written permission of the Apache Software Foundation.
THIS SOFTWARE IS PROVIDED ``AS IS'' AND ANY EXPRESSED OR IMPLIED WARRANTIES,
INCLUDING, BUT NOT LIMITED TO, THE IMPLIED WARRANTIES OF MERCHANTABILITY AND
FITNESS FOR A PARTICULAR PURPOSE ARE DISCLAIMED. IN NO EVENT SHALL THE APACHE
SOFTWARE FOUNDATION OR ITS CONTRIBUTORS BE LIABLE FOR ANY DIRECT, INDIRECT,
INCIDENTAL, SPECIAL, EXEMPLARY, OR CONSEQUENTIAL DAMAGES (INCLUDING, BUT NOT
LIMITED TO, PROCUREMENT OF SUBSTITUTE GOODS OR SERVICES; LOSS OF USE, DATA, OR
PROFITS; OR BUSINESS INTERRUPTION) HOWEVER CAUSED AND ON ANY THEORY OF
LIABILITY, WHETHER IN CONTRACT, STRICT LIABILITY, OR TORT (INCLUDING NEGLIGENCE OR
OTHERWISE) ARISING IN ANY WAY OUT OF THE USE OF THIS SOFTWARE, EVEN IF ADVISED OFTHE POSSIBILITY OF SUCH DAMAGE.
* * * * *
Apache License, Version 2.0 Components
7/27/2019 Primavera 10.0...Contract Manager
4/506
Apache Commons CSV, Commons-digester, Struts, Xerces are licensed under the Apache License, Version 2.0
(the "License"); you may not use these components except in compliance with the License. You may obtain a
copy of the License at http://www.apache.org/licenses/LICENSE-2.0.
Unless required by applicable law or agreed to in writing, software distributed under the License is distributed on
an "AS IS" BASIS, WITHOUT WARRANTIES OR CONDITIONS OF ANY KIND, either express or implied.
* * * * *
Jacob requires the following disclosures:
Copyright (c) 1999-2001 Dan Adler, 315 E72 St. NY, NY, 10021, USA.
mailto:[email protected]. All rights reserved.
Redistribution and use in source and binary forms, with or without modification, are permitted provided that the
following conditions are met:
1. Redistributions of source code must retain the above copyright notice, this list of conditions and the followingdisclaimer.
2. Redistributions in binary form must reproduce the above copyright notice, this list of conditions and the
following disclaimer in the documentation and/or other materials provided with the distribution.
3. Redistributions in any form must be accompanied by information on how to obtain complete source code for
the JACOB software.
Redistribution of the JACOB software is not permitted as part of any commercial product that is targeted
primarily at Java developers. Such products include, but are not limited to: Java virtual machines, integrated
development environments, code libraries, and application server products. Licensing terms for such distribution
may be obtained from the copyright holder.
THIS SOFTWARE IS PROVIDED ``AS IS'' AND ANY EXPRESS OR IMPLIED WARRANTIES,
INCLUDING, BUT NOT LIMITED TO, THE IMPLIED WARRANTIES OF MERCHANTABILITY AND
FITNESS FOR A PARTICULAR PURPOSE ARE DISCLAIMED. IN NO EVENT SHALL THE
COPYRIGHT HOLDER BE LIABLE FOR ANY DIRECT, INDIRECT, INCIDENTAL, SPECIAL,
EXEMPLARY, OR CONSEQUENTIAL DAMAGES (INCLUDING, BUT NOT LIMITED TO,
PROCUREMENT OF SUBSTITUTE GOODS OR SERVICES; LOSS OF USE, DATA, OR PROFITS; OR
BUSINESS INTERRUPTION) HOWEVER CAUSED AND ON ANY THEORY OF LIABILITY, WHETHER
IN CONTRACT, STRICT LIABILITY, OR TORT (INCLUDING NEGLIGENCE OR OTHERWISE) ARISING
IN ANY WAY OUT OF THE USE OF THIS SOFTWARE, EVEN IF ADVISED OF THE POSSIBILITY OF
SUCH DAMAGE.
* * * * *
Jaxen-core, Jaxen-jdom, and Saxpath (now part of the Jaxen project) require the following disclosures:
Copyright 2003-2006 The Werken Company. All Rights Reserved. Redistribution and use in source and binary
forms, with or without modification, are permitted provided that the following conditions are met:
7/27/2019 Primavera 10.0...Contract Manager
5/506
* Redistributions of source code must retain the above copyright notice, this list of conditions and the following
disclaimer.
* Redistributions in binary form must reproduce the above copyright notice, this list of conditions and the
following disclaimer in the documentation and/or other materials provided with the distribution.
* Neither the name of the Jaxen Project nor the names of its contributors may be used to endorse or promote
products derived from this software without specific prior written permission.
THIS SOFTWARE IS PROVIDED BY THE COPYRIGHT HOLDERS AND CONTRIBUTORS "AS IS" AND
ANY EXPRESS OR IMPLIED WARRANTIES, INCLUDING, BUT NOT LIMITED TO, THE IMPLIED
WARRANTIES OF MERCHANTABILITY AND FITNESS FOR A PARTICULAR PURPOSE ARE
DISCLAIMED. IN NO EVENT SHALL THE COPYRIGHT OWNER OR CONTRIBUTORS BE LIABLE
FOR ANY DIRECT, INDIRECT, INCIDENTAL, SPECIAL, EXEMPLARY, OR CONSEQUENTIAL
DAMAGES (INCLUDING, BUT NOT LIMITED TO, PROCUREMENT OF SUBSTITUTE GOODS OR
SERVICES; LOSS OF USE, DATA, OR PROFITS; OR BUSINESS INTERRUPTION) HOWEVER CAUSED
AND ON ANY THEORY OF LIABILITY, WHETHER IN CONTRACT, STRICT LIABILITY, OR TORT
(INCLUDING NEGLIGENCE OR OTHERWISE) ARISING IN ANY WAY OUT OF THE USE OF THIS
SOFTWARE, EVEN IF ADVISED OF THE POSSIBILITY OF SUCH DAMAGE.
* * * * *
Jdom requires the following disclosures:
Copyright (C) 2000-2004 Jason Hunter & Brett McLaughlin. All rights reserved.
Redistribution and use in source and binary forms, with or without modification, are permitted provided that the
following conditions are met:
1. Redistributions of source code must retain the above copyright notice, this list of conditions, and the following
disclaimer.
2. Redistributions in binary form must reproduce the above copyright notice, this list of conditions, and the
disclaimer that follows these conditions in the documentation and/or other materials provided with the distri-
bution.
3. The name "JDOM" must not be used to endorse or promote products derived from this software without prior
written permission. For written permission, please contact .
4. Products derived from this software may not be called "JDOM", nor may "JDOM" appear in their name,
without prior written permission from the JDOM Project Management . In
addition, we request (but do not require) that you include in the end-user documentation provided with the
redistribution and/or in the software itself an acknowledgement equivalent to the following:
"This product includes software developed by the JDOM Project (http://www.jdom.org/)." Alternatively, theacknowledgment may be graphical using the logos available at http://www.jdom.org/images/logos."
7/27/2019 Primavera 10.0...Contract Manager
6/506
THIS SOFTWARE IS PROVIDED ``AS IS'' AND ANY EXPRESSED OR IMPLIED WARRANTIES,
INCLUDING, BUT NOT LIMITED TO, THE IMPLIED WARRANTIES OF MERCHANTABILITY AND
FITNESS FOR A PARTICULAR PURPOSE ARE DISCLAIMED. IN NO EVENT SHALL THE JDOM
AUTHORS OR THE PROJECT CONTRIBUTORS BE LIABLE FOR ANY DIRECT, INDIRECT,
INCIDENTAL, SPECIAL, EXEMPLARY, OR CONSEQUENTIAL DAMAGES (INCLUDING, BUT NOT
LIMITED TO, PROCUREMENT OF SUBSTITUTE GOODS OR SERVICES; LOSS OF USE, DATA, ORPROFITS; OR BUSINESS INTERRUPTION) HOWEVER CAUSED AND ON ANY THEORY OF
LIABILITY, WHETHER IN CONTRACT, STRICT LIABILITY, OR TORT (INCLUDING NEGLIGENCE OR
OTHERWISE) ARISING IN ANY WAY OUT OF THE USE OF THIS SOFTWARE, EVEN IF ADVISED OF
THE POSSIBILITY OF SUCH DAMAGE.
* * * * *
Jericho HTML Parser requires the following disclosures:
The source code for this program is available from the link provided on Primavera Systems, Inc.'s open source
licensing website. The source code is also available from Sourceforge.net.
Primavera Systems, Inc. provides no provisions in connection with this software component which differ from
those provided under the Eclipse Public License version 1.0.
THIS SOFTWARE IS PROVIDED BY THE COPYRIGHT HOLDERS AND CONTRIBUTORS "AS IS" AND
ANY EXPRESS OR IMPLIED WARRANTIES, INCLUDING, BUT NOT LIMITED TO, THE IMPLIED
WARRANTIES OF MERCHANTABILITY AND FITNESS FOR A PARTICULAR PURPOSE ARE
DISCLAIMED. IN NO EVENT SHALL THE CONTRIBUTORS BE LIABLE FOR ANY DIRECT,
INDIRECT, INCIDENTAL, SPECIAL, EXEMPLARY, OR CONSEQUENTIAL DAMAGES (INCLUDING,
BUT NOT LIMITED TO, PROCUREMENT OF SUBSTITUTE GOODS OR SERVICES; LOSS OF USE,
DATA, OR PROFITS; OR BUSINESS INTERRUPTION) HOWEVER CAUSED AND ON ANY THEORY OF
LIABILITY, WHETHER IN CONTRACT, STRICT LIABILITY, OR TORT (INCLUDING NEGLIGENCE OR
OTHERWISE) ARISING IN ANY WAY OUT OF THE USE OF THIS SOFTWARE, EVEN IF ADVISED OFTHE POSSIBILITY OF SUCH DAMAGE.
* * * * *
Pdfbox requires the following disclosures
Copyright (c) 2002-2007, www.pdfbox.org. All rights reserved.
Redistribution and use in source and binary forms, with or without modification, are permitted provided that the
following conditions are met:
1. Redistributions of source code must retain the above copyright notice, this list of conditions and the following
disclaimer.
2. Redistributions in binary form must reproduce the above copyright notice, this list of conditions and the
following disclaimer in the documentation and/or other materials provided with the distribution.
7/27/2019 Primavera 10.0...Contract Manager
7/506
3. Neither the name of pdfbox; nor the names of its contributors may be used to endorse or promote products
derived from this software without specific prior written permission.
THIS SOFTWARE IS PROVIDED BY THE COPYRIGHT HOLDERS AND CONTRIBUTORS "AS IS" AND
ANY EXPRESS OR IMPLIED WARRANTIES, INCLUDING, BUT NOT LIMITED TO, THE IMPLIED
WARRANTIES OF MERCHANTABILITY AND FITNESS FOR A PARTICULAR PURPOSE AREDISCLAIMED. IN NO EVENT SHALL THE REGENTS OR CONTRIBUTORS BE LIABLE FOR ANY
DIRECT, INDIRECT, INCIDENTAL, SPECIAL, EXEMPLARY, OR CONSEQUENTIAL DAMAGES
(INCLUDING, BUT NOT LIMITED TO, PROCUREMENT OF SUBSTITUTE GOODS OR SERVICES;
LOSS OF USE, DATA, OR PROFITS; OR BUSINESS INTERRUPTION) HOWEVER CAUSED AND ON
ANY THEORY OF LIABILITY, WHETHER IN CONTRACT, STRICT LIABILITY, OR TORT (INCLUDING
NEGLIGENCE OR OTHERWISE) ARISING IN ANY WAY OUT OF THE USE OF THIS SOFTWARE,
EVEN IF ADVISED OF THE POSSIBILITY OF SUCH DAMAGE.
* * * * *
Scriptaculous requires the following disclosures:
Copyright (c) 2005-2007 Thomas Fuchs (http://script.aculo.us, http://mir.aculo.us)
Permission is hereby granted, free of charge, to any person obtaining a copy of this software and associated
documentation files (the "Software"), to deal in the Software without restriction, including without limitation the
rights to use, copy, modify, merge, publish, distribute, sublicense, and/or sell copies of the Software, and to
permit persons to whom the Software is furnished to do so, subject to the following conditions:
The above copyright notice and this permission notice shall be included in all copies or substantial portions of
the Software.
THE SOFTWARE IS PROVIDED "AS IS", WITHOUT WARRANTY OF ANY KIND, EXPRESS OR
IMPLIED, INCLUDING BUT NOT LIMITED TO THE WARRANTIES OF MERCHANTABILITY, FITNESS
FOR A PARTICULAR PURPOSE AND NONINFRINGEMENT. IN NO EVENT SHALL THE AUTHORS OR
COPYRIGHT HOLDERS BE LIABLE FOR ANY CLAIM, DAMAGES OR OTHER LIABILITY, WHETHERIN AN ACTION OF CONTRACT, TORT OR OTHERWISE, ARISING FROM, OUT OF OR IN
CONNECTION WITH THE SOFTWARE OR THE USE OR OTHER DEALINGS IN THE SOFTWARE
7/27/2019 Primavera 10.0...Contract Manager
8/506
7/27/2019 Primavera 10.0...Contract Manager
9/506
ix
Table of Contents
Preface.................................................................................................xvContract Manager Module Documentation ....................................................... xvi
About this Manual ............................................................................................ xviiCustomer Support ............................................................................................ xviii
Getting Started
Overview...............................................................................................3Starting Contract Manager.................................................................................... 4
The Contract Manager Workspace ....................................................................... 5
Key Concepts....................................................................................................... 9
Sample Projects .................................................................................................. 12
Roles ................................................................................................................... 14
Planning and Adding a Contract Manager Project........................17First Steps ........................................................................................................... 18
Adding a Project and Entering General Information.......................................... 19
Creating a Project Template................................................................................ 22
Setting Access Rights (Project Access).............................................................. 24
Setting Up the Company Directory .................................................................... 28
Customizing the Control Center ......................................................................... 35
Setting Up Distribution Lists .............................................................................. 37
Assigning Default Contacts ................................................................................ 40
Using the Approval Process................................................................................ 41
Entering Initial Contract Information ................................................................. 54Creating Submittal Packages and Submittals ..................................................... 56
Linking with a Project Management Module Schedule ..................................... 57
7/27/2019 Primavera 10.0...Contract Manager
10/506
x Table of Contents
Primavera - Contract Manager
Working with a Project
Working with Log and Document Windows ...................................61Using Log and Document Windows ................................................................... 62
Adding, Editing, and Deleting Documents ......................................................... 63Using the Spelling Checker.................................................................................64
Creating, Editing, and Assigning Layouts .......................................................... 66
Selecting Layouts................................................................................................ 69
Filtering Data in Layouts ....................................................................................70
Sorting Data in Layouts ......................................................................................76
Grouping Data in Layouts...................................................................................79
Attaching Files and URLs to Documents ........................................................... 82
Customizing Log and Document Windows .....................................85Customizing the Project View.............................................................................86
Customizing Text in Contract Manager .............................................................. 87Choosing Acronyms and Descriptions................................................................89
Creating User-Defined Document Types ............................................................ 90
Creating and Using Custom Fields ..................................................................... 91
Setting Up Dictionaries and Preferences .........................................95Defining Dictionaries..........................................................................................96
Defining Project Dictionaries............................................................................105
Specifying Project Settings ............................................................................... 107
Specifying User Settings...................................................................................121
Setting Layout Options .....................................................................................122
Maintaining a Contract Manager Database..................................123Adding Contract Manager Databases ...............................................................124
Backing Up a Sybase Server Database ............................................................. 126
Printing Logs, Forms, and Reports................................................129Printing Overview............................................................................................. 130
Printing a Log.................................................................................................... 131
Printing Forms................................................................................................... 132
Printing Reports ................................................................................................134
Printing Multi-Project Reports..........................................................................135
Printing Dunning Letters...................................................................................137
Using Print Preview ..........................................................................................139
Communicating Project Information
Sending Contract Manager Documents to Other Users...............143Inbox Overview.................................................................................................144
Setting Up the Inbox ......................................................................................... 146
Entering E-Mail Addresses for Contacts .......................................................... 147
7/27/2019 Primavera 10.0...Contract Manager
11/506
Table of Contents xi
Primavera - Contract Manager
Preparing Transmittals....................................................................149Preparing a New Transmittal ............................................................................ 150
Using Distribution Lists in Transmittals........................................................... 153
Copying a Transmittal ...................................................................................... 154
Generating Transmittals from Other Documents.............................................. 155Delivering Transmittals .................................................................................... 156
Recording and Tracking Communications....................................159Sending Documents to a Correspondence Log................................................. 160
Adding Correspondence Documents Manually................................................ 163
Recording Letters.............................................................................................. 165
Using Requests for Information........................................................................ 171
Sending Notices................................................................................................ 174
Sending Noncompliance Notices...................................................................... 175
Generating a New Document from an Existing One ........................................ 176
Writing Notes with Notepads ........................................................................... 178Documenting Telephone Calls.......................................................................... 180
E-mailing Forms ............................................................................................... 181
Importing E-mail into the Correspondence Received Log ............................... 183
Tracking E-mail Sent Through Contract Manager ........................................... 186
Managing Safety Notices and Reports ............................................................. 188
Recording Meeting Minutes............................................................193Adding a Meeting ............................................................................................. 194
Producing an Agenda from the Minutes of the Last Meeting .......................... 197
Using the Advanced Print Function.................................................................. 198
Working with Contracts, Project Costs, and Changes
Setting Up and Using the Cost Worksheet.....................................201How Costs are Tracked..................................................................................... 202
Items the Cost Worksheet Tracks ..................................................................... 203
Adding Cost Codes........................................................................................... 205
Adding Cost Code Definitions.......................................................................... 208
Copying Cost Codes and Titles ........................................................................ 210
Distributing Costs to the Cost Worksheet......................................................... 211
Distributing Costs Using Change Management ............................................... 214
Getting the Information You Need from the Cost Worksheet .......................... 216Using the Custom Cost Worksheet Section ...................................................... 218
Managing Contracts and Purchase Orders...................................221Adding a Contract or Purchase Order............................................................... 222
Creating Submittals from a Contract or Purchase Order .................................. 226
Generating Materials Delivery Records from a Contract or Purchase Order ... 227
Generating Requisitions from a Contract or Purchase Order ........................... 229
Distributing Budgeted and Committed Costs to the Cost Worksheet............... 231
Reviewing Contract Status................................................................................ 233
Using Trends.....................................................................................235
7/27/2019 Primavera 10.0...Contract Manager
12/506
xii Table of Contents
Primavera - Contract Manager
Why Use Trends?..............................................................................................236
Adding a Trend .................................................................................................237
Generating a Trend............................................................................................238
Distributing Costs to the Cost Worksheet ......................................................... 239
Preparing Requisitions for Payment ..............................................243Process Overview..............................................................................................244
Setting Up Requisitions .................................................................................... 246
Adding a Requisition ........................................................................................254
Recording Progress ...........................................................................................255
Certifying a Requisition....................................................................................262
Distributing Actual Costs to the Cost Worksheet..............................................266
Sending a Requisition .......................................................................................268
Recording Invoices...........................................................................271Adding Invoices to a Contract/PO .................................................................... 272
Distributing Actual Costs to the Cost Worksheet.............................................. 277
Using Change Management ............................................................281The Change Management Process .................................................................... 282
Specifying Change Management Project Settings ............................................ 284
Defining Reason Codes.....................................................................................286
Initiating Change Management from Other Documents...................................287
Adding Change Documents .............................................................................. 288
Proposals and Change Orders ........................................................................... 293
Applying Markup..............................................................................................298
Collecting into Change Orders..........................................................................301
Approving Change Orders ................................................................................ 303Generating Change Documents from Change Management.............................304
Costing Generated Documents..........................................................................307
Adding Multiple Commitment Documents to the Estimated Phase ................. 308
Entering Change Orders and Proposals without Using Change Management
311Prerequisite: Turn on the Functionality.............................................................312
Adding a Change Order to the Change Order Log File .................................... 313
Adding a Proposal to the Proposals Log File....................................................319
Using Procurement ..........................................................................325The Procurement Process..................................................................................326Initiating Procurement.......................................................................................327
Award Procurement Items to a Bidder .............................................................. 340
Creating and Tracking Issues .........................................................349Linking Contract Manager Module Documents Using Issues .......................... 350
Searching for Documents to Build Issues ......................................................... 353
Logging and Tracking Information
Tracking Drawings...........................................................................359
7/27/2019 Primavera 10.0...Contract Manager
13/506
Table of Contents xiii
Primavera - Contract Manager
Drawings Overview.......................................................................................... 360
Setting Up Drawing Data.................................................................................. 363
Adding Drawing Documents ............................................................................ 365
Creating Drawing Sets...................................................................................... 368
Managing Submittals.......................................................................373The Submittal Process ...................................................................................... 374
Adding a Submittal Package............................................................................. 375
Adding a Submittal........................................................................................... 377
Copying a Submittal ......................................................................................... 379
Tracking and Updating a Submittal Using Review Cycles............................... 380
Tracking Multiple Reviewers............................................................................ 383
Updating Submittals from a Package ............................................................... 385
Using Schedule Activities for Reference and to Update Submittals ................ 387
Compiling a Submittal Distribution List .......................................................... 393
Producing Transmittals from Submittals .......................................................... 395Tracking Materials Delivery ...........................................................399
Adding Materials Delivery Records ................................................................. 400
Adding a Materials Delivery Ticket and Posting to Multiple Materials at Once405
Including Materials Deliveries on Requisitions................................................ 407
Using Daily Reports .........................................................................413Preparing a Daily Report .................................................................................. 414
Reporting Resource Use ................................................................................... 415
Listing Visitors.................................................................................................. 416
Recording Materials Deliveries ........................................................................ 417
Including Schedule Activities........................................................................... 419Recording Weather Conditions......................................................................... 421
Adding Attachments......................................................................................... 422
Generating Daily Reports ................................................................................. 423
Tracking Insurance Certificates .....................................................425Adding an Insurance Certificate ....................................................................... 426
Producing Punch Lists.....................................................................429Creating Punch Lists......................................................................................... 430
Adding Items to a Punch List ........................................................................... 431
Exchanging Contract Manager Module Data
Exchanging Contract Manager Module Data with a Project Management
Module Schedule ..............................................................................437Setting Up Project Management Module Schedules for Use with Contract Manager438
Linking to a Project Management Module Schedule ....................................... 440
Importing Contract Manager Module Data into Project Management Module Projects to C
or Status Activities............................................................................................ 443
Assigning Activity IDs to Contract Manager Module Documents .................. 445
7/27/2019 Primavera 10.0...Contract Manager
14/506
xiv Table of Contents
Primavera - Contract Manager
Importing Field Mappings from Contract Manager into the Project Management Module447
Retrieving Field Mappings from the Project Management Module into Contract Manager449
Exchanging Contract Manager Module Data with Other Applications455Exporting Contract Manager Module Data to Other Applications ................... 456
Importing Data from Other Applications..........................................................460Import Specifications ........................................................................................ 463
Index..................................................................................................481
7/27/2019 Primavera 10.0...Contract Manager
15/506
xv
Primaveras Contract Manager module is
contract-control software designed to help
you manage your projects more easily. From
submittals to change orders, all the facts
about your project are at your fingertips.
This manual shows you ways to plan and
create a project in Contract Manager, and
how to manage that project by logging and
tracking project information, using meeting
minutes, transmittals, contracts, purchase
orders, requisitions, change orders, and soon. You will learn how to exchange data
between the module and other programs, and
identify the best methodology for tailoring
the control process to your workflow.
In this chapter
Contract Manager Module
Documentation
About this Manual
Customer Support
Preface
7/27/2019 Primavera 10.0...Contract Manager
16/506
xvi Preface
Primavera - Contract Manager
Contract Manager Module Documentation
Contract Manager Installation Guide explains how to install the
module for Microsoft SQL, Oracle, and Sybase, and explains how to
convert data from previous versions for use in 10.0.The network ordatabase administrator responsible for the initial installation of the
module, ongoing maintenance of the system and database, and
general troubleshooting should read this manual.
Contract Manager Users Guide (this manual) shows how to manage
and monitor documents from initial contracts through the last change
order. All individuals who use the module should read this guide, even
if they are already familiar with previous versions of the software.
See Help for the latestContract Manager
information. Use it as yourprimary source ofinformation.
Contract Manager Help is an integrated comprehensive help system
that supplements the printed documentation. Help is available while
you are working in the module for quick access to information aboutdialog boxes and fields. Help also includes step-by-step procedures
for performing the module functions and answers to common
questions. The Table of Contents provides a starting point for many
major topics. You can also use Helps powerful Search and Index
features to find topics related to any text you enter. Click How To for a
list of all procedures contained in Help.
Online Documentation can be accessed by inserting the Contract
Manager CD-ROM in your computers CD-ROM drive, then clicking
View Documentation from the setup program menu. In addition to the
Contract Manager Users Guide andInstallation Guide, the followingdocumentation is available online:
Project Management Module Integration Field Mappings contains
the field mappings from Contract Manager to the Project
Management module.
A Getting Startedmanual tohelp you use InfoMaker, the report
writer included with the module software.
For a summary of some ofthese questions and their
answers, see F r e q u e n t l y A s k e d Q u e s t i o n s in Help.
Technical Bulletins on the Primavera Web site provide detailed,
technical documents generated by Primavera Customer Support to
answer questions asked by users.
Several areas of Contract Manager are customizable, such asthe Project View, document names, log column headings, anddocument field labels. The examples throughout this manualand in the online help use the default settings shipped with thesoftware.
7/27/2019 Primavera 10.0...Contract Manager
17/506
Preface xvii
Primavera - Contract Manager
About this Manual
Anyone who will be using Contract Manager to track projects should
use this manual. This includes owners, construction managers, general
contractors, subcontractors, architects, designers, engineers,administrators responsible for setting up the module, and persons who
will enter data in. Whether you are an experienced user or are new to the
program, the Users Guide contains the information you need to use the
module to organize all your projects successfully.
Part Contents
Getting Started Provides an introduction to Contract Manager, including workflow, the
module workspace, sample projects, and the initial steps required to plan
and add a project. Instructions are included for setting access rights,
entering contacts, creating distribution lists, entering initial contract
information, creating submittals, and linking with a Project Managemen
module schedule.
Working with a Contract Manager Project Explains how to work with, and customize, the module log and documen
windows, set up dictionaries and preferences, and print logs, forms, and
reports.
Communicating Project Information Describes how to send Contract Manager module documents to other
users, prepare transmittals, track different types of communications,
record meeting minutes, and manage safety-related documents.
Working with Contracts, Project Costs,and Changes
Describes how to set up the Cost Worksheet, manage contracts andpurchase orders, use trends, prepare requisitions for payment, record
invoices, use the Change Management module to customize the workflow
for your companys needs, use procurement to track bidding, and create
and track issues.
Logging and Tracking Information Illustrates how the module logs and tracks important project information
such as drawings, submittals, materials, daily reports, insurance
certificates, and punch lists.
Exchanging Contract Manager Data Describes how to link schedule data to the module, exchange module
data with a Project Management module schedule, and export/import
data to and from other applications.
7/27/2019 Primavera 10.0...Contract Manager
18/506
xviii Preface
Primavera - Contract Manager
Customer Support
If you have a question about using Contract Manager that you or your
network administrator cannot answer using the documentation or Help,
contact Customer Support at the times and locations listed below.
Please have your Contract Manager module serial number ready when you
call. This number is printed on your serial number diskette. It can also be
displayed when using the module by right-clicking on the Help icon in the
header. Each interaction is logged to help Primavera resolve your
questions quickly.
In the United States, Primavera periodically and randomlymonitors Customer Support calls to ensure that you arereceiving the highest quality support.
Contract Manager databases contain calculations calledstored procedures. Although a Contract Manager databaseadministrator has the ability to modify these procedures,Primavera does not recommend changing them. Modifyingthese procedures voids your Primavera Customer Supportagreement.
OfficeTimeZone Hours Telephone FAX E-mail Address*
Bala Cynwyd,PA,
US
ET 8:00-8:00(Mon.-Fri.)
1-610-668-3030 1-610-667-0652 [email protected]
London,
England,
UK
GMT 8:30-6:30
(Mon.-Fri.)
44-20-8563-5555 44-20-8563-5533 [email protected]
*Primaveras Web site at http:www.primavera.com/customer/index.asp provides support and product information
such as knowledgebases, file downloads, user group and news group information, and a product enhancement
request form.
7/27/2019 Primavera 10.0...Contract Manager
19/506
7/27/2019 Primavera 10.0...Contract Manager
20/506
This part describes key concepts for using Contract Managercontract-control software. Contract Manager was formerly
known as Expedition or Expedition Professional.
Overview explains how to start Contract Manager and how to use
the sample projects provided with this release. It also discusses
Contract Manager module terms and defines the different project
roles that users perform.
Planning and Adding a Contract Manager Module Project
describes how to set up your Contract Manager module database,
including the company directory and distribution list, and how to
assign access rights.
7/27/2019 Primavera 10.0...Contract Manager
21/506
7/27/2019 Primavera 10.0...Contract Manager
22/506
4 Part 1: Getting Started
Primavera - Contract Manager
Starting Contract Manager
Users open Contract Manager from a client Browser - there is no client
software to install. The Contract Manager administrator provides a Web
address to users for accessing Contract Manager. To connect, openMicrosoft Internet Explorer, and type the Web address of the Contract
Manager Web server provided to you.
The Contract Manager administrator usually provides user IDs and
passwords. Type your user ID and password, then click Log In.
For information aboutchanging these defaults ona network, see C o n t r a c t M a n a g e r A dm i n is t r a t io n
A p p l i c a t i o n in Help.
The default Contract Manager user ID and passwordshipped with Contract Manager is EXP (for both fields).
The minimum supported monitor resolution is 1024x768.
7/27/2019 Primavera 10.0...Contract Manager
23/506
Overview 5
Primavera - Contract Manager
The Contract Manager Workspace
When you open the Contract Manager, the Workspace appears; this is
where all Contract Manager tasks begin.
The Workspace is divided into two main areas: the Project View on the
left and the Control Center (Workspace) on the right.
Project View The Project View shows your project hierarchy, whichincludes the top-level folder called All Projects, followed by the folder
for each project, the folders in each project, and the modules (logs and
documents) inside these folders. It also contains a Templates folder
which consists of any project templates you may have created, including
the default templates, DESIGN and SCHOOL. The Project Viewfunctions the same way as Microsoft Windows Explorer. When a folder
is collapsed, click its icon to display the names of the items in that
folder. To collapse the folder, click the folder icon again.
Templates
Modules (logs
and
documents)
Projects
Project view
7/27/2019 Primavera 10.0...Contract Manager
24/506
7/27/2019 Primavera 10.0...Contract Manager
25/506
Overview 7
Primavera - Contract Manager
You can quickly accessdocuments in your court that
require you to take an action,then print a report corresponding
to these action items for theproject. An example of an action
is shown on the next page.
Click to display theselected report.
Click a section of the chart todisplay a list of Requests for
Information documents.
7/27/2019 Primavera 10.0...Contract Manager
26/506
8 Part 1: Getting Started
Primavera - Contract Manager
To display available forms andreports, from the document window,
click Select an Action, Advanced
Print, then click Go. Select the type odocument, select the type ofdocument, and then click Print or
Preview.
The example at the left shows thePreview function. To print the
document, click the printer icon nextto Save a copy on the tool bar at the
top of the document.
7/27/2019 Primavera 10.0...Contract Manager
27/506
7/27/2019 Primavera 10.0...Contract Manager
28/506
10 Part 1: Getting Started
Primavera - Contract Manager
Change Managementenables you to manage project modifications due
to changes. You specify which change documents are created, when
they are created, and where they are calculated on the Cost Worksheet.
By recording all necessary contract, contractor, and cost data early in
the change process, you can evaluate the effect of the change on allcontracts involved and see the current status of the change at a glance.
Markup provides a way to manage overhead and profit by adding
markup values to change documents. The module can calculate
overhead and profit automatically, and add additional costs to change
orders and proposals. You can set default values for overhead, profit,
and any other markup categories you create. Typically you will collect
all proposals from committed parties, and then roll the costs and codes
of each document to create a quote to the customer or owner of a
project. With markup, you can add your overhead and profit prior to
submitting the quote.
Daily Reportsprovide a record of daily activities and conditions. Usethese reports to record conditions observed in the field, such as soil,
rock, or underground utilities that were not moved correctly, as well as
to track and communicatethe potential effect of these recordedconditions in a timely manner. You can also include underway activities
from Contract Manager module schedules that are linked to the project
to see where the work is taking place on that report day.
Telephone Records, Meeting Minutes, Correspondence, Requests forInformation (RFIs), and Noticesenable you to record information thatmay affect both the submittal and change processes. For example, a
change in condition may result in meetings, phone calls, notes, letters,
and correspondence that lead to a formal contract change.
Change Orders result from changes in the scope of work, site
conditions, or schedule delays. You can post costs associated with
changes to the Cost Worksheet so you have a total financial picture of
past events and projected future costs. With this view, you can measure
the impact of each change order on any contract or purchase order.
Track submittals Submittals include contract drawings, samplematerials, and permits that need approval. Submittals help you ensure
contract compliance by tracking who received what and when they
received it.
7/27/2019 Primavera 10.0...Contract Manager
29/506
Overview 11
Primavera - Contract Manager
Daily Reports, Telephone Records, Meeting Minutes, Correspondence,
RFIs, andNoticesalso support the submittal process. For example,during a submittal cycle a reviewer may reject a submittal; as a result,
the project team may have meetings and exchange phone calls, letters,
and correspondence to clarify the requirements for resubmittal.
Drawings andDrawing Sets maintain a list of project drawings,
facilitate the dissemination of these drawings to other parties, and
provide information about the status of revisions. When you add
distributions to drawing sets or create revisions, an entry is made in the
Transmittal Creation Queue for each contact on the distribution list.
Transmittals accompany documents, such as submittals and drawings to
create a permanent record of the actions taken. Submittal items and
drawing revisions are automatically placed in the Transmittal Creation
Queue; you can add any transmittals in this queue to the database and
print them for recipients on your distribution list. The module can
quickly generate transmittals, or you can customize your own.
Dunning Letters remind participants of overdue items such as submittals
and drawings. Contract Manager can quickly generate dunning letters,
or you can customize your own.
Reports and Forms provide quick and accurate project information in
various formats. The flexible reporting feature produces reports that
summarize when items such as submittals are due, who received whatand when, what has been approved and what is pending, and how many
days items are overdue.
Use the cross-document tools The Issues feature cross-references and links documents from any Contract Manager module log
to issues you define. You can link documents to issues directly as you
add records to the documents, or you can link documents to issues
automatically based on keywords such as underground, electrical, or
some other item that may be related to a problem or other situation. The
module then assembles the documents for review in a fully organized,
indexed list so you can easily trace the sequence of actions taken, saving
hours of work.
The Inboxstores items sent to you electronically by other participants.
You can also use this feature to communicate quickly with other project
team members by sending documents related to submittals and changes.
7/27/2019 Primavera 10.0...Contract Manager
30/506
7/27/2019 Primavera 10.0...Contract Manager
31/506
Overview 13
Primavera - Contract Manager
ENGR (Office Building) contains drawings and drawing sets for theDesign Review phase of the drawing process. This project is used in the
examples in the Tracking Drawings chapter to show how designers (or
architects or engineers) track drawings.
7/27/2019 Primavera 10.0...Contract Manager
32/506
14 Part 1: Getting Started
Primavera - Contract Manager
Roles
The roles of the construction manager, general contractor, owner, and
the engineer/architect/designer are described in this section to help you
understand how Contract Manager is implemented by various teammembers in a business workflow.
Construction manager As the construction manager, you will usethe module to manage changes and project costs, monitor progress, and
communicate with other team members.
Because you represent the owners interests throughout the design,
construction, and post-construction phases of the project, you
continually answer questions about costs, quality, and progress. How
much funding is required to complete the project? What is the budget,
given the changes to date? What are the pending changes and problemareas? Is the project progressing according to the schedule? Who is
responsible for the overdue submittals? What are the areas of
noncompliance?
The following list includes tasks that are usually the responsibility of the
construction manager in the contract process. Included with each task is
the corresponding chapter/part in this manual where you can find more
information about those tasks.
Managing submittals Managing Submittals chapter
Maintaining updated estimates of cost overruns or underruns Setting Up and Using the Cost Worksheetchapter
Tracking changes for each project issue and their effect on the cost
at completion Part 4: Working with Contracts, Project Costs, and
Changes
Quickly finding all the documents you need to resolve open issues
Creating and Tracking Issues chapter
Monitoring progress through written and verbal communications
Part 3: Communicating Project Information
Customizing Contract Manager to match your companys standards
Customizing Log and Document Windows and Setting Up
Dictionaries and Preferences chapters
Generating supporting reports Printing Logs, Forms, and Reports
chapter
7/27/2019 Primavera 10.0...Contract Manager
33/506
Overview 15
Primavera - Contract Manager
General contractor As the general contractor, you will use themodule to manage shop drawings and submittal items, track project
issues, document the change process, and record daily progress. When
you want to compare progress to the schedule, you can retrieve your
schedule.
The following list includes tasks that are usually the responsibility of the
general contractor in the contract process. Included with each task is the
corresponding chapter/part in this manual where you can find more
information about those tasks.
Using the Drawing and Submittals logs to track shop drawings and
submittal items Tracking Drawings andManaging Submittals
chapters
Coordinating submittal activities with the project schedule
Managing Submittals andExchanging Contract Manager Datawith a Project Management Module Schedule chapters
Identifying issues that require resolution and creating change
documents Creating and Tracking Issues chapter and Part 4:
Working with Contracts, Project Costs, and Changes
Identifying areas with significant cost variance and analyzing the
effects of pending changes on profit Setting Up and Using the
Cost Worksheetchapter, and Part 4: Working with Contracts,
Project Costs, and Changes
Tracking items that must be completed before final payment ismade Part 4: Working with Contracts, Project Costs, and
Changes
Reporting daily progress Using Daily Reports chapter
Generating supporting reports Printing Logs, Forms, and Reports
chapter
Owner As the project owner, you will use the module to organizeproject data so you can stay on top of progress, coordinate activities
with your operations people, and make sure that all of the project detailsare handled by the appropriate people. You will find the comprehensive
records of documents, correspondence, and changes invaluable for
claims avoidance.
The following list includes tasks that are usually the responsibility of the
owner in the contract process. Included with each task is the
corresponding chapter/part in this manual where you can find more
information about those tasks.
7/27/2019 Primavera 10.0...Contract Manager
34/506
16 Part 1: Getting Started
Primavera - Contract Manager
Analyzing the projected cost and identifying areas with significant
cost variances Setting Up and Using the Cost Worksheetchapter
Approving requisitions Preparing Requisitions for Payment
chapter
Identifying unfinished tasks for which final payment should be
withheld Part 4: Working with Contracts, Project Costs, and
Changes
Identifying issues that require resolution and issuing change orders
Creating and Tracking Issues chapter and Part 4: Working with
Contracts, Project Costs, and Changes
Managing submittals Managing Submittals chapter
Comparing daily progress to the schedule Using Daily Reports
chapter
Generating supporting reports Printing Logs, Forms, and Reports
chapter
Engineer/Architect/Designer As the project designer, you will usethe module to track specifications and drawings, control the submittal
review process, monitor progress by the design team, communicate with
other team members, and coordinate the activities of outside
consultants.
The following list includes tasks that are usually the responsibility of thedesigner in the contract process. Included with each task is the
corresponding chapter/part in this manual where you can find more
information about those tasks.
Managing design and contract drawings Tracking Drawings
chapter
Recording the design budget and expenses Setting Up and Using
the Cost Worksheetchapter
Tracking changes in scope and their effect on the cost at completion
Part 4: Working with Contracts, Project Costs, and Changes
Quickly finding all the documents you need to resolve open issues
Creating and Tracking Issues chapter
Monitoring progress through written and verbal communications
Part 3: Communicating Project Information
Generating supporting reports Printing Logs, Forms, and Reports
chapter
7/27/2019 Primavera 10.0...Contract Manager
35/506
17
This chapter presents a general approach for
structuring and entering project information
in the Contract Manager. Use these
guidelines to set up Contract Manager
functionality in the most effective way for
your business.
In this chapter
First Steps
Adding a Project and EnteringGeneral Information
Creating a Project Template
Setting Access Rights (ProjectAccess)
Setting Up the Company Directory
Customizing the Control Center
Setting Up Distribution Lists
Assigning Default Contacts
Using the Approval Process
Setting Up Cost Codes andModifying Cost WorksheetHeadings
Creating Submittal Packages and
Submittals
Linking with a Project
Management Module Schedule
Planning and Adding a ContractManager Project
7/27/2019 Primavera 10.0...Contract Manager
36/506
18 Part 1: Getting Started
Primavera - Contract Manager
First Steps
Contract Manager offers a wide range of features and functions.
Depending on how you currently manage contractsor how you want
to manage themyou can use all the features or select only the ones youneed to support your work process.
The following figure is a general plan for setting up and implementing
Primavera. Step 1 is described in theInstallationGuide. The remainder
of this chapter describes steps 2 through 5.
Contract Manager flexibility enables you to realize its benefits even if
you do not have all the details about your project at the beginning. As
the project progresses, you can add and/or modify the information
entered during the initial setup, such as new negotiated contracts, new or
changed companies, and more clearly defined submittals and submittal
packages.
For details on tailoring
Contract Managerfunctions to your
companys requirements,see the Cu s t om i z in g L o g a n d D o cu m e n t W i n d o w s
chapter.
These are the basic steps to get started in Contract Manager; adapt them
to your own work processes.
2.Add the project and
enter generalinformation.
1.Set up and start
ContractManager.
3.Set up the
initial CompanyDirectory.
4.Enter initial contractinformation (and
define cost codes).
5.Create initial
submittalpackages.
3a.Optionally link to &
use the scheduleactivities.
7/27/2019 Primavera 10.0...Contract Manager
37/506
Planning and Adding a Contract Manager Project 19
Primavera - Contract Manager
Adding a Project and Entering General InformationFor detailed information onadding a new project, inHelp click How To, then
click A d d a N e w P r o j e ct .From there, you can chooselinks torelated topics.
Add a new project You can add a new project in Contract Managerat any time. Right-click on the top-level folder. You can choose from
two ways to create a project. Choose New Project to use the Add Project Wizard, which guides
you from start to finish. This method is best when you have most of
the information prepared for the project or are unfamiliar with
creating a new project.
Choose Publish Project to create a project name and assign it to an
administrator, who will then enter the project information. Contract
Manager notifies the administrator that a project has been added
that requires information.
The New Project option is not available if you do not haverights to create a new project.
See Help for detailed information on using either of these options to
create a new project.
The following shows the dialog box that displays when you choose New
Project to add a project using the Add Project Wizard.
Type a uniqueabbreviation and title for
the project. You mustenter data in these fields
to add a project.
Click Next to continuecreating the project.
Select any of thesetopics to move directly to
that phase in the wizard.
7/27/2019 Primavera 10.0...Contract Manager
38/506
20 Part 1: Getting Started
Primavera - Contract Manager
The preceding figure shows the dialog box that displays when you
choose Publish Project to add a project.
For more informationabout setting access rights,
see S e t t i n g A c c e s s R ig h t s ( P r o j e c t A c c e ss ) later in
this chapter.
When you add a new project, you become the projectadministrator. Project administrators have access to alldocuments in their projects. (Contract Manageradministrators have access to all documents in all projects.)By default, all other users have no access rights to newprojects. Assign users access to a project in the ProjectAccess window (right-click on a project and choose ProjectAccess).
Delete a project To delete an entire project, right-click on the project
in the Project View, then choose Delete Project.
When you delete a project, you permanently remove thatproject and all its associated documents.
Select the administrator;Contract Manager notifies
that person that a requesthas been made to create a
new project.
7/27/2019 Primavera 10.0...Contract Manager
39/506
7/27/2019 Primavera 10.0...Contract Manager
40/506
22 Part 1: Getting Started
Primavera - Contract Manager
Creating a Project Template
If you will be adding projects that use the same key parties, currency, and
schedule information, you can create a project template that contains this
information. Use this template as the basis for each new project youcreate.
Add a new project template You can make an existing project atemplate. Right-click on the project and select Save As Template.
Use the template as a basis for a new project When you want to
create a new project that uses the information in the template, do the
following:
1 right-click on the top level folder and choose New Project.
2 Enter a project name and title, then click Template on the left.
3 Choose the first option, Use Template, and select the template from
the drop-down list.
Click Template to choose atemplate.
Select the template you wantto use for this project.
7/27/2019 Primavera 10.0...Contract Manager
41/506
Planning and Adding a Contract Manager Project 23
Primavera - Contract Manager
When you select a template, Contract Manager creates the new project
based on the information contained in the template. You can edit this
information in the new project.
7/27/2019 Primavera 10.0...Contract Manager
42/506
7/27/2019 Primavera 10.0...Contract Manager
43/506
7/27/2019 Primavera 10.0...Contract Manager
44/506
26 Part 1: Getting Started
Primavera - Contract Manager
To restrict a users access to documents that have a certain To or From
Contact, and to submittals in which that same contact is listed as a
Received, Sent, Returned, or Forwarded reviewer, click Select next to
the Access by Company field (at the bottom of the dialog box). Click
Select next to the company you want to assign.
You cannot change Access rights for administrators. Theyalways have full access to all projects.
Click to set the users
access rights to allmodules at once.
7/27/2019 Primavera 10.0...Contract Manager
45/506
Planning and Adding a Contract Manager Project 27
Primavera - Contract Manager
Set access rights for a group of users across projects Tosave time, the project administrator can copy the access rights for users
in one project to another project. Right-click on the project to which you
want to copy access rights, then choose Copy User Access.
Click Select to choose theproject from which to copy
users access rights.
Use these buttons to addand remove user access
rights to your project.
Select the users.
7/27/2019 Primavera 10.0...Contract Manager
46/506
28 Part 1: Getting Started
Primavera - Contract Manager
Setting Up the Company Directory
The Company Directory enables you to store information about everyone
involved in your project. You can include names, phone numbers, and
addresses of subcontractors, managers, suppliers, your own staff, and anyother companies or individuals involved in the project.
Nearly all Contract Manager documents use the information included in
the Company Directory. Entering this information at the beginning of the
project ensures that your unique abbreviations are consistent, avoiding
confusion and mistakes. Even if you have only part of the companys
information, enter at least the company abbreviation, name, office address,
and a key contact; you can add missing details later.
For more information on
adding companies andcontacts, see A d dCom p a n i e s a n d C o n t a c t s in
Help.
Add a company and contact Click Companies in the Project
Information folder, then click Add Company.
Click Add to create acontact for the
company. The firstcontact you add
becomes the keycontact.
Type important details
about the company inthe Remarks section.
In the Details section,mark to indicate if the
company is aDisadvantaged-
(DBE), Minority-
(MBE), or Woman-owned (WBE)
business enterprise.
7/27/2019 Primavera 10.0...Contract Manager
47/506
Planning and Adding a Contract Manager Project 29
Primavera - Contract Manager
Contract Manage requiresthat you enter the keycontacts initials.
In the Company section, enter an abbreviation for the company and the
company name. The key contact is the person to whom most documents
will be addressed. This field is filled once the first contact is entered in
the Contacts section.
Select a specification section code. Specification section codes are a part
of a standard coding system developed by the Construction
Specification Institute (CSI). You can select these codes from any
Specification Section data field, or you can create your own codes
(right-click on the top-level folder, then choose Dictionaries,
Specification Sections).
For information on creatingyour own roles andspecification section codes,
s e e S et t i n g U p D i c t i o n a r i e s a n d P r e f e r e n c e s , or C r e a t e Con t a c t R o l e s in Help.
Select the companys role. You can select an existing role, or you can
create a new role and add it to the list (right-click on the top-level folder,
then choose Dictionaries, Company Roles).
Add contacts for the company To add contacts for the company,click the edit icon beside the company, expand the Contacts section in
the Company document window, and click Add. You can add as many
contacts as needed for each company.
Link a User Account with a contact In order to use a contact inthe document approval and document owner processes of Contract
Manager, you must link a valid user account with the contact. One user
account can have multiple contacts linked to it. Contacts without valid
user accounts linked with them will not be available for selection duringdocument approval and document owner processes.
To associate a user account with a contact, click the Select link next to
the User Account field. On the Select User dialog box, choose the
correct user account, and click the Select button.
Add remarks to a contact Expand the Remarks section in theCompany document window and type any important details, such as
directions or office hours.
To define standard papersizes, right-click on the top-level folder and chooseDictionaries, Drawings,Paper Sizes.
Add an address, paper size, and number of copies fordrawing distribution to a contact Expand the Contacts section inthe Company document window and click the document icon next to the
contact you want to update. Enter information for all applicable
addresses, such as office, shipping, or billing; phone numbers; and e-
mail information. Select the paper size, and type the number of copies
you will be using to send drawings for design review or distribution for
this contact. This information is used in the Drawings and Drawing Sets
logs. Click Save & Close when finished.
7/27/2019 Primavera 10.0...Contract Manager
48/506
30 Part 1: Getting Started
Primavera - Contract Manager
Contract Manager does not apply changes you make in thiswindow to any documents where the original addressalready appears (such as contracts). This practice protectsthe validity of the original document information.
Copy the Company Directory To set up a new project more
quickly, you can copy the Company Directory from a similar project in
the same database or from the group Company Directory. Right-click on
the project and choose Copy Companies.
Define custom paper sizes that will
appear here by right-clicking on the top-level folder and choosing Dictionaries,
Drawings, Paper Sizes.
Click Selectnext to User
Account tochoose theaccount to
associate with
the contact.
Scroll down toenter more contact
information.
7/27/2019 Primavera 10.0...Contract Manager
49/506
Planning and Adding a Contract Manager Project 31
Primavera - Contract Manager
You can also copy companies and contacts from a project to the group
level. Right-click on the top-level folder and choose Copy Companies.
Click Select to choose the
project (or group) fromwhich to copy companies.
Select the companies
to copy to the project,then click Add.
Click Select to choose the project from
which to copy companies and contacts.
Select the companiesto copy to the group,
then click Add.
7/27/2019 Primavera 10.0...Contract Manager
50/506
7/27/2019 Primavera 10.0...Contract Manager
51/506
Planning and Adding a Contract Manager Project 33
Primavera - Contract Manager
Saving Companies and Contacts in theProject/Group List
Each project contains its own directory of project companies. ContractManager also maintains a directory of database companies that all
projects in the same database can share.
For more information onhow to set contact
preferences, see S e t t i n g P r o j e c t P r e f e r e n c e s in theS e t t i n g U p D i c t i o n a r i e s a n d
P r e f e r e n c e s chapter.
When you add a new project, Contract Manager uses the Project
Company Directory by default. To use the same companies for all of
your projects, switch to the Group (database) Company Directory.
Right-click on a project and choose Project Settings. In the Companies
section, click Switch. Project will change to Group to indicate that
the Group directory is in use.
You can save new companies in the Group Company Directory while
using the Project Company Directory. In Project Settings, mark the AddCompany to Group After Adding to Project checkbox.
If you change an existing company in a project, Contract Manager also
updates the Group Company Directory, even if the active directory is
Project, as long as you marked the Update Group When Project
Company Edited checkbox in the Project Settings dialog box.
7/27/2019 Primavera 10.0...Contract Manager
52/506
34 Part 1: Getting Started
Primavera - Contract Manager
Adding Companies and Contacts fromOther Documents
When you add a document, you may need to enter information for acompany that is not in the Company Directory. Rather than interrupt
your current task, you can add companies and contacts from most
documents without going back to the Companies dialog box.
For more information, seeS e le c t C o n t a c t d i a l o g b o x in Help.
When you click Select for a company or contact field, the Select
Company or Select Contact dialog box opens. To add a new company or
contact, choose whether to organize by company or contact, then click
Add Contact or Add Company, depending on which you want to add.
Type the company name and abbreviation (if adding a new company),the contacts full name and initials, and other information, if available,
then click Save. Primavera adds the company and contact information to
the Company Directory. You can edit the information later if necessary.
7/27/2019 Primavera 10.0...Contract Manager
53/506
7/27/2019 Primavera 10.0...Contract Manager
54/506
36 Part 1: Getting Started
Primavera - Contract Manager
Customize the Control Center Click Customize this Page to selectwhich items appear in the Control Center and where they are placed.
For detailed information oncustomizing your desktop,see Cu s t om i z e W o r k s p a c e d i a l o g b o x in Help.
Items can be included more than once in the Control Center. For
example, if you want issues to appear as a graph, a bar chart, and a pie
chart, move three Issue items to the Layout area, then edit each items
appearance by clicking the Edit link above it in the Control Center.
Select the items to includein the Control Center, then
click Add to move theitems to the Layout area.
7/27/2019 Primavera 10.0...Contract Manager
55/506
7/27/2019 Primavera 10.0...Contract Manager
56/506
38 Part 1: Getting Started
Primavera - Contract Manager
Any changes you make toyour company directoryare also reflected for thecorresponding company in
distribution lists.
Click Select in the Contacts section to open the Select Contacts dialog
box. To easily find the contacts you need, you can organize by contact,
company, or distribution list. All companies in the current project appear
if the Project Setting is set to Project; all group companies appear if the
Project Setting is set to Group. Companies assigned to the Group level
apply to all projects in that group. Click Select next to each contact you
want to add, then click Save.
To remove items from a distribution list, click Unselect next to the name
of the contact you want to remove. Click Save and Return to Menu
when you finish defining the list. To delete the distribution list, click
Delete next to the list you want to remove.
Tomodify alist, click
its icon.
Establish a distribution list by
selecting companies.
7/27/2019 Primavera 10.0...Contract Manager
57/506
Planning and Adding a Contract Manager Project 39
Primavera - Contract Manager
Edit a distribution list You can also edit an existing distribution listname and/or title. In the Company Directory log window, click Define
Distribution Lists, then click the document icon next to the list you want
to modify. Make the changes. Click Save and Return to Menu when you
finish modifying the current list. Primavera reflects any changes infuture uses of the list; the original version of the list (before editing)
remains unchanged where it is already used in Primavera. Click Close
from the Distribution Lists dialog box when you finish defining
distribution lists.
Copy a distribution list to a new list To save time, you can createa new distribution list based on an existing one. In the Company
Directory log window, click Define Distribution Lists, then click the
Save Distribution List As icon next to the list you want to copy. A new
distribution list is created containing the names from the copied list.
Type an
abbreviation andtitle for the new
distribution list.
Click Select toadd additional
names to the
distribution list.
7/27/2019 Primavera 10.0...Contract Manager
58/506
40 Part 1: Getting Started
Primavera - Contract Manager
Assigning Default Contacts
To specify which contacts will automatically display in the To and From
fields of a particular document, right-click on the project and choose
Default Field Values.
The Set Default Field Values window displays the default contact
assignments for the currently open project.
Customize contact assignments To customize this information,click Select next to the field to which you want to assign a default
contact. In the Select Company dialog box, click Select next to the
company you want to assign as the default, then click OK.
You can edit or delete default contacts at any time.Changing the default contact affects new documents only.Contact names for existing documents remain unchanged.
7/27/2019 Primavera 10.0...Contract Manager
59/506
Planning and Adding a Contract Manager Project 41
Primavera - Contract Manager
Using the Approval Process
Overview of the approval process Prior to Contract Manager12.0, there were several document fields related to approval, but no
formal approval process. In Contract Manager version 12.0 and later,there is an approval process for the following types of documents:
Contracts
Change Order documents
Purchase Orders
Request for Information (RFI) documents
Payment Requisitions
The approval process is the same for each of these documents. For eachof these types of documents, a document owner must be specified. This
can be done at the project level by right-clicking the project name and
selecting project settings to display the Project Settings dialog box that
you can use to set the document owners for the entire project.
When set at the project level, each time one of these types of documents
is created, the name of the document owner will automatically be
entered in the Document Owner field. the document owner can also be
selected when the document is created. Once the document owner is
selected, only the Contract Manager administrator, the project owner, or
the document owner can select a different document owner.
Contract Manager documents can be added by anyone who has both the
security privilege to add documents, and who has access to the project.
Documents can be approved by the Contract Manager administrator, the
project owner, or the document owner who is acting for any contact on
the document review list.
Prerequisites The following prerequisites must be met before you
can use the approval process:
1 The companies for the project must be created.
2 The contacts for the companies must be created, and each contact
must be linked to a user account.
3 The contacts must have view, add, and edit rights for the project.
This is done in the Contract Manager Administration application
when the user account is created.
7/27/2019 Primavera 10.0...Contract Manager
60/506
42 Part 1: Getting Started
Primavera - Contract Manager
Log onto the Administration application, and click the User
Accounts link in the left pane to display the User Account
dialog box. Use this to add a User Account.
After the user account is created, you can change access rights
when running Contract Manager by right-clicking on the project
name and selecting Project Access to display the Project
Access dialog box.
Once on the Project Access dialog box, click the icon to the left
of the to the user name to display the User Project Access
dialog box, and set the user project access rights.
If the user is not listed for this project, click the Add Users to
this Project button on the Project Access dialog box. This
displays the Select User dialog box. Use this dialog box to
select the users to add to the project.
7/27/2019 Primavera 10.0...Contract Manager
61/506
Planning and Adding a Contract Manager Project 43
Primavera - Contract Manager
4 The contacts must have approval rights for the project.
This is done in the Contract Manager Administration
application when a user access template is created. Log onto the
Administration application, and click the Access Templates link
to display the Access Templates window. After that, the
template is assigned to the user account when the user account
is created on the User Account dialog box. Once the template has been assigned to a user account, you can
change the approval rights when running Contract Manager by
right-clicking on the project name and selecting Project Access
to display the Project Access dialog box.
Once on the Project Access dialog box, click the icon next to the
user name to display the User Project Access dialog box, and
set the approval rights.
If the user is not listed for this project, click the Add Users to
this Project button on the Project Access dialog box. Thisdisplays the Select User dialog box. Use this dialog box to
select the users to add to the project.
5 Contacts must have an approval limit that is greater than or equal to
the amount of the document being created. If you select a contact
for the reviewer list, and that contact does not have a limit greater
than or equal to the amount of the document, an error message
displays when you initiate the approval process. In that case, you
must remove that contact name, and reinitiate the approval process.
7/27/2019 Primavera 10.0...Contract Manager
62/506
7/27/2019 Primavera 10.0...Contract Manager
63/506
7/27/2019 Primavera 10.0...Contract Manager
64/506
7/27/2019 Primavera 10.0...Contract Manager