Page 1: Previous WorksLink systems

WorksLinkAutomated Client Reporting for Construction Projects

WorksLink.com.au

[email protected]

Page 2: Previous WorksLink systems

WorksLink integrates information across construction and engineering projects to simplify management and reporting tasks.

WorksLink has been driven by the needs of Project Managers and contractors for over a decade.

WorksLink systems are designed to be delivered quickly and efficiently to support projects of limited duration.

What WorksLink does

Page 3: Previous WorksLink systems

WorksLink has been deployed for over 10 years on 15 major sites for a large number of major industry players.

WorksLink has brought order and efficiency to the administration of a wide range of engineering and construction projects.

WorksLink has often been brought in mid-project to help get projects back on track.

WorksLink creates the admin links that deliver project performance.

WorksLink Background

Page 4: Previous WorksLink systems

WorksLink Core Modules

S-Curve

Invoices and

Payments

Work Breakdow

n Structure

Tools

HR

Labour

Hours

Skills

Equipment Hours

Consumables

Equipment

Equipment Hiring

Client Reporting

Quantities

Dayworks

Variations

Travel

Accomodation

Safety

Client Work

Breakdown

Structure

Alerts

Page 5: Previous WorksLink systems

Argyle Diamonds Underground Expansion (WA)

BHP Billiton RGP5 Rail Duplication (WA)

Fortescue Metals Railway Construction (WA)

Dalrymple Bay Coal Terminal Expansion (QLD)

BHP Billiton RGP3 Wharf Construction (WA)

Cowal Gold Mine Construction (NSW)

Other Projects

Projects Covered

Page 6: Previous WorksLink systems

Argyle Diamonds Underground Expansion

WorksLink

Page 7: Previous WorksLink systems

Project already underway when WorksLink introduced

One WorksLink software developer on-site for 9 months

Automatic population of 3-password protected client Excel spreadsheet for weekly Quantity Manhour Report (QMR). Report contained over 3000 line items with key data field regularly changing. Contractor was paid according to data submitted here. Very significant headache reduction by automating this.

Argyle Diamonds Underground Expansion

Page 8: Previous WorksLink systems

Internal QMR report generated for Project Manager, Commercial, Engineers and Supervisor to meet and verify weekly progress.

S-Curve generated automatically from Quantity and Manhour data

Hour Transfers between Costcodes by Engineers automatically managed

Monthly Accruals generated for upload into corporate accounting system

Two Construction companies in consortium, separate Timesheets for each generated from WorksLink

Argyle Diamonds Underground Expansion

Page 9: Previous WorksLink systems

Argyle - Labour Hours

Page 10: Previous WorksLink systems

Argyle - Costcodes

Page 11: Previous WorksLink systems

Argyle - Quantities

Page 12: Previous WorksLink systems

Argyle - QMR Hour Transfer

•Transfer of hours from one Costcode to another•Usually caused by Supervisors not being aware of the full list•Usually carried out by Engineers towards the end of each week

Page 13: Previous WorksLink systems

Argyle - Internal QMR

Excel report generated for a weekly meeting to review quantities and hours to be submitted to client.

Page 14: Previous WorksLink systems

Argyle - Variation Register

Page 15: Previous WorksLink systems

Argyle - Dayworks

Page 16: Previous WorksLink systems

Argyle - COINS Integration

Page 17: Previous WorksLink systems

BHP Billiton RGP5Rail Duplication

WorksLink

Page 18: Previous WorksLink systems

200km Iron Ore Rail Duplication Project in Pilbara

One software developer in Perth office for 6 weeks Same base product as for Argyle project Same Client QMR (Qty ManHour Report) as Argyle Two WorksLink systems configured between three Companies in

Consortium (Two in JV) Reporting integrated across all three companies Different internal coding structure used by one Camp Room management modules developed and used by 3rd party

camp provider Excel-like interface for uploading hours and quantities (low bandwidth

site) Automated generation of data to feed into client systems on a daily basis Alerts automatically generated to warn of inconsistent data as well as

reports or data transfers that are due. Alerts automatically disappear when resolved.

BHP Billiton RGP5

Page 19: Previous WorksLink systems

Fortescue Metals Railway Construction

WorksLink

Page 20: Previous WorksLink systems

Project already underway when WorksLink introduced

First project utilising web-based version of WorksLink

Relatively basic functionality employed over a 5 month period

WorksLink developer on site for 4 days only

Fortescue Metals Railway Construction

Page 21: Previous WorksLink systems

Dalrymple Bay Coal Terminal Expansion

WorksLink

Page 22: Previous WorksLink systems

Jetty construction component of DBCT 7X Project

One WorksLink developer on-site for 35 days 4 page (1xA3 folded) Daily Site Sheet for each Supervisor

containing (completed sheet saved as PDF in corporate doc management system):

Employee List (and Costcodes) Contractors in their area Safety actions taken and Safety department instructions Weather and Tide information from BOM Equipment allocated to that crew (minimising overrun of hire

periods) Progress reporting Issues/Concerns raised

Automatic generation of Project Controls spreadsheet

Dalrymple Bay Coal Terminal Expansion

Page 23: Previous WorksLink systems

BHP Billiton RGP3Wharf Construction

WorksLink

Page 24: Previous WorksLink systems

Project underway when WorksLink brought in

One WorksLink software developer spent 4 days on site configuring WorksLink system

Included generation of weekly and monthly report in exact Excel format as specified by the client containing a detailed breakdown of various status information about employees. Saved HR manager 8 hours every week.

Otherwise similar functionality to that employed for the Cowal Gold Mine Construction project.

BHP Billiton RGP3 Wharf Construction

Page 25: Previous WorksLink systems

Cowal Gold Mine Construction

WorksLink

Page 26: Previous WorksLink systems

Project already underway when WorksLink introduced

One software developer onsite for 9 months configuring and managing WorksLink

Daily Site Report integrating: Supervisor and their Workgroup of Employees Record of previous day’s Costcode, Flight in or Flight out, RDO, R&R

pending for each employee Notes from Superintendent/Construction Manager Current day’s activities and hours recorded on this sheet

Reconciliation with corporate Payroll data (some employees significantly overpaid – embarrassing!)

% Allocation for tasks against WBS for installation of Steel, Mechanical and Piping to feed into Project Controls

Cowal Gold Mine Construction

Page 27: Previous WorksLink systems

Other Projects

WorksLink

Page 28: Previous WorksLink systems

160 man workforce

Mobile device to internet synchronisation of Tools and Consumable data currently being rolled out

Client Invoicing and Claiming to be rolled out in March 2010

Concepts based on system initially developed 12 years ago for managing engineering workshops

Significant overlap with Construction Site edition of WorksLink

Hunter Valley Workshop

Page 29: Previous WorksLink systems

WorksLink was to be used for this project

Client pulled the project before it could happen (was done internally several years later)

Would have been the perfect project to see massive functionality developed within WorksLink

Port Kembla Blast Furnace No 5 Reline

Page 30: Previous WorksLink systems

WorksLink provides the glue between Contractor and Client

WorksLink On Your ProjectYour

Business• Existing Systems

Your Partners• Existing Systems

WorksLink

Client Reporting

• As per client spec

Internal Reporting

• Timely, flexible, informative