PRECIOS
TOÑO ABARCA ahuatepec ABRIL MAT CRUZ
CLAVE MATERIAL U COSTO MARCA COSTO2 MARCA COSTO 3 MARCA COSTO MARCA COSTO MARCA ELECCION
MAT001 CEMENTO TON $2,100.00 CONSTRURAMA $2,060.00 $2,000.00 CRUZ A $2,040.00 $1,800.00
MAT002 MORTERO $1,480.00
MAT003 CAL TON $1,364.00 $940.00 $1,250.00 $1,363.64 $40.00 $1,364.00
MAT012 ARMEX 10X15 M $17.50 $20.00 $16.67 $16.33 $17.50
MAT013 PANEL #2 $340.00
MAT014 PANEL #3 PZA $350.00 $360.00
MAT015 MALLA PISO MT $45.00 $40.00 $45.00
MAT016 MALLA LOSA MT $80.00 $77.50 $80.00
MAT017 ESTRIBOS KG $20.00 $19.00 $17.00 $17.00 $20.00
MAT018 ALAMBRE QUEMADO KG $19.00 $17.00 $16.00 $22.00
MAT019 CLAVO KG $20.00 $20.00 $20.00
MAT020 AGUA M3 $0.30
DUELA DE 10"X 2.5MTS PZA $85.00
POLIN 10X10 PZA $100.00
ACEITE QUEMADO $5.00
MICROLASTI $75.00
FESTERFELT $160.00
MANO DE OBRACLAVECUA00 PEON $180.00CUA11 ALBAÑIL $220.00CUA001 2 PEONES $360.00CUA002 PEON , ALBAÑIL $580.00
PRECIOS
CUA003 CABO DE OFICIOS $500.00
PRECIOS
OBSERVACIONES
3 mtrs3
85 12MTS
MULTIPLICAR X 6 PRECIO PZA
PRESUPUESTO
Partida No Concepto U C PU importe
preliminares1 Limpieza M2 110.00 $5.44 $598.162 Trazo M2 110.00 $2.55 $280.113 Excavacion en terreno tipo B a mano de 0 a 2 mts de profundidad. M3 88.00 $188.31 $16571.36
SUBTOTAL $17449.64
Albañilería
4 Plantilla de cimentación con concreto de 100kg/cm2 y 2cm de espesor. M2 77.00 $76.40 $5882.875 Cimentación de mampostería. M3 55.00 $923.41 $50787.686 Relleno de cepas con material producto de excavación. M3 30.80 $108.32 $3336.267 Cadena de desplante de 15X20cm con concreto de 150kg/cm2. M2 110.00 $219.75 $24172.928 Impermeavilización de cadena de desplante de 15X20cm. M 60.50 $133.21 $8058.989 Muro de tabique. M2 275.00 $124.23 $34163.13
10 Cadena de 15X20cm con concreto de 150kg/cm2. M 110.00 $105.44 $11597.9011 Castillo de 10X10 con concreto de 150kg/cm2. M 96.00 84.64596 $8126.01
subtotal $126401.84
total $143851.47
MORTEROSLOGOTIPO
CONCEPTO Elaboración de mortero cemento arena prop. 1:5UNIDAD M3
MAT003 Calhidra TON 0.0002 $940.00 $0.19Barrote de 1 1/2" X 4 " X 8' PT 0.0027 $6.10 $0.02Duela de 3/4 " x 4 " x 8´ PT 0.018 $7.10 $0.13Hilo plastico M 0.350 $0.10 $0.03Varilla 1/2" TON 0.0002 $3690.00 $0.74
SUBTOTAL $1.11CUA002 Cuadrilla de Albail J 0.001 $748.00 $0.898
CUA 002 Albañil y peón J 0.085 $580.00 $49.30CUA003 Cabo de Oficio J 0.010 $500.00 $5.00
SUBTOTAL $54.30HERRAMIENTA Medios manuales y/o herramientas % 3.00 $54.30 $1.63
CD $101.65C.I. (10%) $10.17
SUBTOTAL $111.82FINANCIDA (1%) $1.12
SUBTOTAL $112.94
Impermeavilización de cadena de desplante de 15X20 a base de 2 capas de emulsión asfaltica y 1 capa de fieltro asfáltico
con riego de arena, incluye limpieza y acarreos a 1ra estción.
MANO DE OBRA
Muro de tabique rojo recocido 5X11.5X23cm. De 11.5cm de espesor acabado comun hasta 3.5 m. de altura, junta de 2cm aprox. de espesor, inc. material y acarreo hasta 1er estación.
CONC001 Concreto de 100kg/cm2 M3 0.01 $850.56 $8.51MAT002 Agua M3 0.05 $0.30 $0.02MAT012 Armex para castillo M 1.100 $17.50 $19.25CIMB001 Cimbra acabado común M 1.000 $16.84 $16.84
Partida No Concepto U C PU importepreliminares 1 limpieza M2 330 10.1588 3352.404
2 trazo M2 110 11.39184 1253.1024
3 Excavacion en terreno tipo M3 88 83.93 7385.84
EXPLOSIÓN DE INSUMOS
SUBTOTAL 11991.3464ALBAÑILERIA 4 PLANTILLA DE CIMENTACIOM2 110 33.19251 3651.176232
5 CIMIENTO DE MAMPOSTERM3 48.4 845.3306 40913.999666 RELLENO CON MATERIAL P M3 30.8 95.7359 2948.665727 CADENA DE DESPLANTE DE M2 110 121.7945 13397.394648 IMPERMEABILIZACION DE CM 60.5 140.6306 8508.1503329 MURO DE TABIQUE M2 275 192.5777 52958.87175
10 CADENA DE 15X 20 CONCREM 110 105.1259 11563.8486411 CASTILLO DE 10X10 CONCRM 96 76.2309 7318.166294
subtotal 122378.2583
EXPLOSIÓN DE INSUMOS
13subtotal 27277.61105
total 161647.2158
GENERADORESPROY. LOCALIZACION
NO. CONCEPTO U EJE TRAMO LARGO ANCHO ALTO No PIEZAS RESULTADO
Limpieza y deshierbe en terreno con maleza de hasta 1 metro de altura incluye apile de hierba y material en lugar.
Trazo y nivelación en terreno plano por medios maniales, para desplante de estructura, estableciendo ejes auxiliares pasos y referencias. incluye material y mano de obra.
Excavación a mano n terreno tipo "B" seco en cepas de hasta 2m. D e altura; incluye afloje, extracción, amacice, limpieza de plantilla y taludes, medida en banco.
Plantilla de cimentación de 100kg/cm2 con agregado de 3/4 y un espesor de 2cm, incluye material y mano de obra.
Cimentación de piedra brasa asentada con mortero cemento cal.arena prop. 1:1:6, incluye acarreo a 1ra estación.
Relleno de cepas con material producto de excavación compactado con pizón a mano en capas de 10cm. I ncluye volteo con pala.
Cadena de desplante de 15x 20 con concreto de 150 kg/ cm2 con agregado de 3/4 y refuerzo con 4 varillas del #3 y estribos del no.2 a cada 20cm.
Impermeavilización de cadena de desplante de 15X20 a base de 2 capas de emulsión asfaltica y 1 capa de fieltro asfáltico con riego de arena, incluye limpieza y acarreos a 1ra estción.
Muro de tabique rojo recocido 5X11.5X23cm. De 11.5cm de espesor acabado comun hasta 3.5 m. de altura, junta de 2cm aprox. de espesor, inc. material y acarreo hasta 1er estación.
Castillo 10X10 con concreto de 100kg/cm2 y refuerzo de acero de armex colocado a cada 3m. Aprox.
Cadena de cerramiento de 15x20cm con concreto de 150 kg/cm2 con agregado de 3/4 y refuerzo de armex de 10X15cm.
Programa de Obra
Fin Duración Fza. Tbjo. Periódo 1 Periódo 2 Periódo 3 Periódo 4 Periódo 5 Periódo 6 Periódo 7L MM J V S L MM J V S L MM J V S L MM J V S L MM J V S L MM J V S L MM
Limpieza, deshierve y desenraice del terreno con maleza de 1m de altura, incluyematerial y apile de hierba en el lugar
Trazo y nivelación en terreno plano por medios manuales, para desplante de estructura, estableciendo ejes auxiliares, pasos y referencias, incluye material y mano de obra.
Excabación a mano en terreno tipo B seco en cepas de hasta 2 m de profundidad, incluye afloje, estracción, amacice,limpieza de plantilla y taludes, medida en banco.
Excabación a mano en terreno tipo B seco en cepas de hasta 2 m de profundidad, incluye afloje, estracción, amacice,limpieza de plantilla y taludes, medida en banco.