Top Banner
39

Pressurized boiler - Remeha

Dec 05, 2021

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Pressurized boiler - Remeha
Page 2: Pressurized boiler - Remeha

• Pressurized boiler

• Heat output: 59 - 256 kW

Re

me

ha

P

2

00

Remeha P 200Technical information

Page 3: Pressurized boiler - Remeha

3

Preface 4

1 Description of the unit 41.1 General 41.2 Burners 4

2 Construction data 42.1 General 42.2 Sections 42.3 Casing 4

3 Technical data and dimensions 53.1 Dimensions 53.2 Technical data 53.3 Quotation specifications 6

4 Output data 64.1 Boiler efficiency 64.2 Combustion efficiency 6

5 Application data 75.1 L.P.H.W. version 7

5.1.1 Water temperature 75.1.2 Water pressure 75.1.3 Flow rate 75.1.4 Water treatment 7

5.2 Economisers 75.3 Flue gas discharge 75.4 Noise production 8

6 Installation requirements 86.1 Installation recommendations in the boiler house 8

7 Assembly guidelines and installation requirements 9

7.1 General 97.2 Water connections 97.3 Delivery in individual parts 9

7.3.1 General 97.3.2 Boiler assembly 9

7.4 Delivery assembled (4 to 7 sections only) 9

8 Instrument panels 118.1 Equipment contents 118.2 Instrument panel High/Low with hours run meters 118.3 Wiring diagram instrument panel High/Low with hours run meters 1 12

9 Commissioning 139.1 Pressurized boiler with gas burner 13

9.1.1 Commissioning procedure 139.1.2 Putting out of operation 13

9.2 Pressurized boiler with oil burner 139.2.1 Commissioning procedure 139.2.2 Putting out of operation 13

10 Fault finding 13

11 Maintenance recommendations 1411.1 General 1411.2 Maintenance instructions 14

TABLE OF CONTENT

Page 4: Pressurized boiler - Remeha

4

Remeha P 200

PREFACE

These technical instructions contain useful and impor-tant information for the correct operation and maintenan-ce of the Remeha boiler, model P200Read these instructions carefully before putting the boi-ler into operation, familiarise yourself with it’s control functions and operation, strictly observing the instructi-ons given. Failure to do so may invalidate warranty or prevent the boiler from operating.The installation and commissioning of the boiler must be carried out by a competent Engineer, with the relevant certification i.e.: CORGI, ACOPS, IEE regs. etc. On completion a copy of the boiler log / commissioning sheet should be returned to Broag Ltd for record purpo-ses.

If you have any questions, or if you need more informa-tion about specific subjects relating to this boiler, or it’s installation please do not hesitate to contact us.The data published in these technical instructions is based on the latest information (at date of publication) and may be subject to revisions.We reserve the right to continuous development in both design and manufacture, therefore any changes to the technology employed may not be retrospective nor may we be obliged to adjust earlier supplies accordingly.

1 DESCRIPTION OF THE UNIT

1.1 GeneralHigh efficiency pressurized boiler, suitable for use with natural gas and light oil, by means of a pressure jet burner. Also available with a condensing unit (ECO) (for natural gas only).Up to 141 kW (7 sections) the Remeha P 200 can be delivered assembled (except for casing and instrument panel).The boiler meets the requirements of the CE regulations in the following directives:- Gas appliance directive no. 90/396/EEC- Electrical low voltage directive no. 73/23/EEC- E.M.C. directive no. 89/336/EEC- Efficiency directive no. 92/42/EEC.Classification type for evacuation of the combustion pro-ducts: B23.

1.2 BurnersIn principle all CE-approved pressure jet burners are sui-table, subject to prior adjustment to the boiler capacity and boiler construction. The individual boiler satisfies inspection requirement for central heating boilers.

2 CONSTRUCTION DATA

2.1 GeneralThe boiler block consists of cast iron sections which are assembled by means of tapered nipples. The boiler is a three pass design. The boiler block is insulated with a 80 mm thick layer of glass wool.

2.2 SectionsThe sections are made of pearlitic cast iron.Weights and measures of the sections:- Front section: 59 kg H x W = 630 x 540 mm- Intermediate section: 58 kg H x W = 630 x 540 mm - Rear section: 61 kg H x W = 630 x 540 mm

2.3 CasingSteel casing, finished with a high-quality insulation. The front door is suitable for left or right opening as desired. Fig. 01 Remeha P200

IL46

Page 5: Pressurized boiler - Remeha

5

3 TECHNICAL DATA AND DIMENSIONS

3.1 Dimensions

Front view Rear viewSide view

Flow R” Return R” Flue ØD ext.

No. ofsections

Fig. 02 Dimensions00.13c.79.00002

* If the boiler is delivered with adjustable feet (standard for assembled delivery 4 to 7 sections) the boiler will be approximately 30 mm higher.

3.2 Technical data

Number of sections 4 5 6 7 8 9 10 11 12

Nominal heat output kW 34 - 59 40 - 93 46 -117 52 -141 58 -165 65 -184 71 -206 77 -229 83-256

Hi /NCV

kW 66 103 129 155 181 202 225 250 278Nominalheat input Hs /

GCVkW 73 114 143 172 201 224 250 278 309

Page 6: Pressurized boiler - Remeha

6

Remeha P 200

A mm 492 618 745 871 998 1124 1250 1377 1503

B mm 791 917 1044 1170 1297 1423 1549 1676 1802

C mm 450 575 700 825 950 1075 1200 1325 1450

ØD mm 150 150 150 150 200 200 200 200 200

Dimensions

R “ 1½" 1½" 1½" 1½" 2" 2" 2" 2" 2"

∆ t =

10°Cmbar 9 22 34 48 67 84 103 127 158

Waterresistance ∆ t =

20°Cmbar 2 5 8 12 17 21 26 32 39

Water contents litre 24 29 34 39 44 49 54 59 64

Boiler weight (dry) kg 365 425 485 545 605 665 725 775 835

Combustion chamberresistance1) mbar 0.1 0.3 0.6 1.0 1.2 1.6 1.4 1.8 2.1

Combustion gas side

contentm3 0.08 0.11 0.13 0.16 0.18 0.21 0.23 0.26 0.28

Flue gas flow rate kg/h 103 161 201 242 282 315 351 390 434

Table 01 Technical data1) Determined with 20 % excess air.

3.3 Quotation specifications- Heat exchanger manufactured from corrosion resi-

stant “pearlite” cast iron- Maximum operating pressure of 6 bar- Maximum operating temperature of 95°C- Sectional design with three passes for max efficiency

(gross 83%) and a generously sized combustion chamber for minimising NOx production

- Water cooled base and rear sections- Large insulated door (hinged left or right) allowing

easy access for service operations- Supplied in broken down form for ease of delivery and

site access

- Powder coated enamel steel casing- 80 - 100 mm thick glass wool insulation- Suitable for use with a Natural gas, and/or 35 sec oil

fired pressure jet burner (matched with most popular burner manufacturers)

- Supplied as standard with on/off switch, temperature indication, control and high limit thermostats

- Efficiency 83% (Hs - GCV)- Manufactured to ISO 9001- CE approved.

4 OUTPUT DATA

4.1 Boiler efficiencyUp to 91.7 % at Hi (82.6 % at Hs) at full load and up to 93.2 % at Hi (84.0 % at Hs) at part load.Average water temperature 70°C (80/60°C).

4.2 Combustion efficiencyUp to 93.0 % at Hi (83.8 % at Hs) at full load and up to 95.5 % at Hi (86.0 % at Hs) at part load.

Note: Hi = NCV ; Hs = GCV

Page 7: Pressurized boiler - Remeha

7

5 APPLICATION DATA

5.1 L.P.H.W. version

5.1.1 Water temperatureMaximum water temperature is 110°C.The minimum acceptable return water temperature is, for gas fired boilers 45°C and for oil fired boilers 40°C, at aflow rate corresponding to a ∆t of 20°C at nominal heat output.

5.1.2 Water pressureMaximum pressure 6 bar.The boiler is suitable for open and sealed systems up to a maximum pressure of 6 bar and a minimum pres-sure of 0.8 bar. The boiler is suitable for installation in basement or rooftop boiler houses.

5.1.3 Flow rateThe minimum flow rate through the boiler is obtained from the following formula:

nominal heat output (kW) = m3/h70

This minimum flow must be maintained for 5 minutes after the burner stops firing to avoid high temperature shut-down due to residual heat gain. Due to the design and manufacture of the boiler no specific minimum water flow requirement exists other than for over-temperature protection.

5.1.4 Water treatmentThe system should be filled with mains cold water (for the UK this will usually have a pH of between 7 and 8).Pressurised installations with a boiler/system content ratio of 1:10 or less should not require water treatment, provided that the following conditions apply:1. The system is flushed thoroughly to remove all fluxes

and debris and then filled completely once.2. Make up water is limited to 5 % per annum.3. The hardness of the water does not exceed 360 ppm

(20°D). All scale deposits will reduce the efficiency of the boiler and should be prevented. However provided the above is complied with any scale produced will not be too detrimental to the boiler efficiency and will not reduce the anticipated life expectancy of the boiler.

NOTE: Scale deposits in excess of 3 to 5 mm will reduce boiler efficiency and greatly increase the risk of premature casting failure.

As most systems contain a variety of metals which can react with each other to cause corrosion. It is con-sidered good practice to provide some form of water treatment (especially in open vented systems) in order to prevent or reduce the following:- Metallic corrosion;- Formation of scale and sludge;- Microbiological contamination;- Chemical changes in the untreated system water.

Suitable chemicals and their use should be discussed with a specialist water treatment company prior to car-rying out any work. The specification of the system and manufacturers recommendations must be taken into account, along with the age and condition of the system. New systems should be flushed thoroughly to remove all traces of flux, debris, grease and metal swarf generated during installation. Care to be taken with old systems to ensure any black metallic iron oxide sludge and other corrosive residues are removed, again by thoroughly flushing, ensuring that the system is drained completely from all low points.

NOTE: Please ensure that the new boiler plant is not in circuit when the flushing takes place, especially if cleansing chemicals are used to assist the process.

Under no circumstances is the boiler to be operated with cleaning chemicals in the system.

To summarise:- Minimise water loss;- Prevent pumping over in open vented systems;- Provide adequate air venting at all high points;- Keep pH level between 7 - 9 when using additives;- Maximum chlorine content of 200 mg/l;- Take advice on the suitability of inhibitors.

5.2 EconomisersECO’s can be delivered upon request (for natural gas only).

5.3 Flue gas dischargeFor the discharge of the flue gases, chimney draught is not required.Tests have shown that very good combustion results are obtained with zero draught at the boiler outlet.

Page 8: Pressurized boiler - Remeha

8

Remeha P 200

5.4 Noise productionThe noise level taken at a distance of 1 m around the boiler is approximately 70 to 85 dBA. The noise level at the chimney outlet will, depending on load, type of burner and chimney situation, vary from 70 to 90 dBA, measured at a distance of 1 m from the outlet. If this noise production gives rise to problems in the imme-diate vicinity, then noise reducing or absorbing measu-res should be taken.9

10

20

30

40

50

60

70

80

90

100

31,5 63 125 250 500 1000 2000 4000 8000

NR 20

NR 30

NR 40

NR 50

NR 60

NR 70

NR 80

NR 90

frequency (Hz)

dB r

e 2x

10-5

N/m

2

full load

part load

Fig. 03 Noise level readings without burner silencer

The values that have been measured are averages obtained from various measurements carried out at a distance of approximately 1 m around the boiler and at a height of approximately 1 m.

6 INSTALLATION REQUIREMENTS

6.1 Installation recommendations in the boiler houseThe necessary minimum installation space of the boiler can be seen from Fig. 04

Fig. 04 Installation recommendations in the boiler house04.15D.79.00001

Page 9: Pressurized boiler - Remeha

9

7 ASSEMBLY GUIDELINES AND INSTALLATION REQUIREMENTS

7.1 GeneralThe Remeha boilers P 200 - 4 to 7 sections can be delivered in individual parts or assembled. The Remeha boilers P 200 - 8 to 12 sections are delive-red in individual parts.

7.2 Water connectionsThe water connections are at the rear of the boiler.The flow and return connections consist of threaded male connections:- 4 - 7 sections 1 ½” BSP- 8 - 12 sections 2” BSPFlange connections in accordance with DIN 2633 can be delivered on request (Ø 70 mm ID). The return con-nection is provided with a G ¾” threaded hole in which a drain off cock is fitted.At the front of the boiler a flange is provided with 3 x G ½” threaded holes for the fitting of the thermostatpockets.

7.3 Delivery in individual parts

7.3.1 GeneralThe sizes of the boiler parts are such that they all can enter the boiler house through a normal entrance.The casing and equipment parts are delivered in pac-kaged units. If necessary, the boiler can be put into operation without casing. The casing can be added at a later stage without dismantling the water connections.On request the boiler can be delivered with adjustable boiler feet (standard for assembled delivery 4 to 7 secti-ons).

7.3.2 Boiler assemblyAssembly and installation of a boiler delivered in indivi-dual parts should only be undertaken by a recognized and approved engineer and in accordance with the assembly manual. Local regulations laid down by the relevant authorites must be adhered to.

7.4 Delivery assembled (4 to 7 sections only)The boiler is delivered completely assembled in a crate and on a pallet. Just the casings and the instrument panel are delivered seperate in package units in the crate. The boiler is delivered with adjustable boiler feet (Fig. 05). By unscrewing the boiler feet, the boiler lifts itself up from the pallet. The pallet can now be disman-tled and taken away (Fig. 06). Now the boiler level can be adjusted horizontally and in the right height (Fig. 07). After the installation of the boiler, the casings and the instrument panel can be fitted (figure 08).If necessary, the boiler can be put into operation without casing. The casing can be added at a later stage withoutdisconnecting the water connections.

Fig. 05 The boiler completely assembled in a crate and on a pallet.00.13C.79.00010, afb 1

Fig. 06 The pallet dismantled and taken away00.13C.79.00010, afb 2

Fig. 07 The boiler adjusted horizontal and at the right height 00.13C.79.00010, afb 3

Page 10: Pressurized boiler - Remeha

10

Remeha P 200

Fig. 08 Mounting casings and the instrument panel.

Page 11: Pressurized boiler - Remeha

11

8 INSTRUMENT PANELS

8.1 Equipment contentsThe panels contain all the necessary control and measu-ring instruments required to control the boiler. The con-nections have to be made on a terminal strip. The capil-laries and sensor wires, which come from the control panel, are placed in the instrument pockets that are fitted at the front of the boiler.

See par. 8.2 for an instrument panel High/Low with hours run meters. Several extra options can be built into the panels.Ask our technical departement.

8.2 Instrument panel High/Low with hours run meters

Fig. 09 Layout of the instrument panel High/Low with hours run meters00.03F.79.00004

1. Operating switch (On/Off)2. Control thermostat; setting between 35°C - 95°C3. High/Low thermostat; setting between 35°C - 95°C4. Hours run meter total running hours5. Hours run meter full load running hours6. Analoque thermometer water temperature7. High limit thermostat 110°C (lock out)8. Lock out warning lamp 9. Option for rematic® weather compensator

1 2 3 6

4 5 7 8

9

Page 12: Pressurized boiler - Remeha

12

Remeha P 200

8.3 Wiring diagram instrument panel High/Low with hours run meters 1

3

1.) E

xternal control.

rem

ove link; insert control pair (230 V)

2.) E

xternal control High/Low

.

rem

ove link; insert control pair (230 V).1

Fig. 10 Wiring diagram instrument panel High/Low with hours run meters

Page 13: Pressurized boiler - Remeha

13

9 COMMISSIONING

Note:Commissioning to only be carried out by a qualified engineer with the relevant training and certification i.e. Acops-Corgi and a commissioning data sheet completed on site for issue to owner.

9.1 Pressurized boiler with gas burner

9.1.1 Commissioning procedureIf the boiler is to be put into operation again following a period of non-use, then the following procedure must be carried out :- Open the main gas cock.- Switch the weather-compensator (if fitted) over to

manual operation (h).- Turn the thermostats to their highest setting.- Switch on the circulation pump.- Switch on the main switch.- Switch on the operation switch in the instrument

panel.- Consult burner manufacturers commissioning details.

WarningIf the instrument panel is fitted with a weather compen-sator, set the programm switch to ‘manual’ position (h). The following will now take place:- The gas burner fan will start running so that during

the purging time the combustion chamber will be ven-tilated with the air damper fully opened.

- The air damper will then go into start position. - Ignition flame lights up and is checked. - Then the control box gives the all clear signal for the

burner to switch over to full load.

9.1.2 Putting out of operationIt is sufficient to switch off the operation switch on the instrument panel. It is important that in the event of work being carried out on the burner, the boiler/burner unit must be completely electricaly isolated and the main gas cock must be shut.

9.2 Pressurized boiler with oil burner

9.2.1 Commissioning procedureIf the boiler is to be put into operation again following a period of non-use, then the following procedure must be carried out :- Open the main oil cock.- Switch the weather-compensator (if fitted) over to

manual operation ( h).- Turn the thermostat to their highest setting.- Switch on the circulation pump.- Switch on the main switch.- Switch on the operation switch in the instrument

panel.- Consult burner manufacturer commissioning details.

WarningIf the instrument panel is fitted with a weather compen-sator, set the programm switch to ‘manual’ position (h). The following will now take place:- The oil burner fan will start running so that during the

purging time the combustion chamber will be ventila-ted with the air damper fully opened.

- The air damper will then go into start position.- Ignition flame lights up and is checked.- Then the control box gives the all clear signal for the

burner to switch over to full load.

9.2.2 Putting out of operationIt is sufficient to switch off the operation switch on the instrument panel. It is important that in the event of work being carried out on the burner, the boiler/burner unit must be completely electricaly isolated and the main oil cock must be shut.

10 FAULT FINDING

High Limit thermostat lock out:- Check the water circulation (circulation pump). Reset

the High Limit thermostat (Reset button is on the instrument panel under the cover cap of the High Limit thermostat).

- Advise the installer in the event of continued lock outs.

Page 14: Pressurized boiler - Remeha

14

Remeha P 200

11 MAINTENANCE RECOMMENDATIONS

11.1 GeneralDepending on the operational conditions, the block and the burner must be checked and cleaned at least once a year for gas and at least twice a year for oil.

11.2 Maintenance instructionsCleaning of the boiler:- Put boiler out of operation.- Open the front door, if necessary after dismantling the

burner.- Remove the retarders (only for the 4 - 9 sections).- Clean the combustion chamber and flue passes using

a suitable brush.- Clean the removed retarders (4 - 9 sections).- Remove the rear panel of the boiler and remove the

cleaning cover (underneath the smoke box).- Vacuum clean the boiler and the combustion cham-

ber.- Renew the front door seals after cleaning the boiler.- Re-assemble the removed parts and close the front

door.- Re-assemble the burner (if dismantled).- Check the boiler combustion side for leakage.- Check the equipment for proper functioning and if

necessary re-adjust the control and safety equipment.- Carry out combustion analysis.- Check the water connections.

Page 15: Pressurized boiler - Remeha

16

© Copyright

All technical and technological infor-mation contained in these technical instructions,

as well as any drawings and technical descriptions furnished by us remain our property

and shall not be copied in part or whole without our prior consent in writing.

Subject to alterations52988/1000/0202/Ips.

Broag Ltd.

Head office

Remeha house

Molly Millars Lane

Wokingham,

Berkshire RG41 2QP

Tel.: 0118 978 3434

Fax: 0118 978 6977

E-mail address:

[email protected].

Branch office

Unit 3, Kestrel Close,

Quarry Hill ind. Estate,

Ilkeston

Derbyshire DE7 4RD

Tel.: 0115 944 0778

Fax: 0115 944 0588

Re

me

ha

P

20

0

Page 16: Pressurized boiler - Remeha

Remeha P 300

• Pressurized boiler

• Heat output: 278 - 709 kW

Technical Information

Re

me

ha

P

3

00

Page 17: Pressurized boiler - Remeha

Remeha P 300

2 3

CONTENTS

Preface 3

1 Description of the unit 3 1.1 General 3 1.2 Burners 3

2 Construction data 3 2.1 General 3 2.2 Sections 3 2.3 Casing 3

3 Technical data and dimensions 4 3.1 Dimensions 4 3.2 Technical data 5 3.3 Quotation specifications 5

4 Output data 5 4.1 Boiler efficiency 5 4.2 Combustion efficiency 5

5 Application data 6 5.1 Hot water version 6 5.1.1 Water temperature 6 5.1.2 Water pressure 6 5.1.3 Flow rate 6 5.1.4 Water treatment 6 5.2 Economisers 6 5.3 Flue gas discharge 6 5.4 Noise production 7

6 Installation requirements 7 6.1 Installation recommendations in the boiler house 7 6.2 Base details 7

7 Assembly guidelines and installation requirements 8 7.1 General 8 7.2 Boiler assembly 8 7.3 Water connections 8

8 Instrument panel 8 8.1 Equipment contents 8 8.2 Lay out of the instrument panel 8 8.3 Wiring diagram instrument panel 9

9 Commissioning 10 9.1 Pressurized boiler with gas burner 10 9.1.1 Commissioning procedure 10 9.1.2 Putting out of operation 10 9.2 Pressurized boiler with oil burner 10 9.2.1 Commissioning procedure 10 9.2.2 Putting out of operation 10

10 Fault finding 11 10.1 High Limit thermostat lockout 11

11 Maintenance recommendations 11 11.1 General 11 11.2 Maintenance instructions 11

Page 18: Pressurized boiler - Remeha

Remeha P 300

2 3

1 DESCRIPTION OF THE UNIT

2 CONSTRUCTION DATA

PREFACE

These technical instructions contain useful and impor-tant information for the correct operation and mainte-nance of the Remeha boiler, model P 300.Read these instructions carefully before putting the boiler into operation; familiarise yourself with its control functions and operation, strictly observing the instruc-tions given. Failure to do so may invalidate warranty or prevent the boiler from operating.A competent Engineer, with the relevant certification (i.e. CORGI, ACOPS, IEE regs. etc) must carry out the installation and commissioning of the boiler.On completion a copy of the boiler log / commissioning

sheet should be returned to Broag Ltd for record pur-poses.If you have any questions, or if you need more informa-tion about specific subjects relating to this boiler, or it's installation please do not hesitate to contact us.The data published in these technical instructions is based on the latest information (at date of publication) and may be subject to revisions.We reserve the right to continuous development in both design and manufacture, therefore any changes to the technology employed may not be retrospective nor may we be obliged to adjust earlier supplies accordingly.

1.1 GeneralHigh efficiency pressurised boiler, suitable for use with natural gas and light oil, by means of a pressure jet bur-ner. Also available with a condensing unit (ECO) (for natural gas only).The boiler meets the requirements of the CE regulations in the following directives:- Gas appliance directive no. 90/396/EEC- Electrical low voltage directive no. 73/23/EEC- E.M.C. directive no. 89/336/EEC- Efficiency directive no. 92/42/EEC.Classification type for evacuation of the combustion pro-ducts: B23.

1.2 BurnersIn principle all pressure jet burners are suitable, subject to prior adjustment to the boiler capacity and boiler con-struction.The individual boiler satisfies inspection requirement for central heating boilers.

2.1 GeneralThe boiler block consists of cast iron sections which are assembled by means of tapered nipples. The boiler is designed on the basis of the triple pass principle. The boiler block is insulated with a 100 mm thick layer of glass wool.

2.2 SectionsThe sections are made of pearlitic cast iron. Weights and measures of the sections:

Section Measures

(H x W) mm

Weights

kg

Front 1026 x 630 93

Intermediate 1026 x 640 106

Rear 1026 x 630 114

2.3 CasingSteel casing, finished with a high quality insulation. The front door is suitable for left or right opening as desired.4

Page 19: Pressurized boiler - Remeha

Remeha P 300

4 5

3 TECHNICAL DATA AND DIMENSIONS

3.1 Dimensions

Fig. 01 Dimensions of the Remeha P 30000.14C.79.00002

Rear view Front view

Sizes

A B CWeight (dry) approx.

No. of sections

mm mm mm kg

8

9

1200

1350

1520

1670

1170

1320

1040

1145

10

11

1500

1650

1820

1970

1470

1620

1250

1355

12

13

1800

1950

2120

2270

1770

1920

1460

1565

14

15

2100

2250

2410

2560

2070

2220

1670

1775

16 2400 2710 2370 1880

Flow Ø 100 (int.)

Flue gas connection Ø 300 (ext.)

Return Ø 100 (int.)

Flanges in accordance with BS4505 PN16Side view

Page 20: Pressurized boiler - Remeha

Remeha P 300

4 5

3.2 Technical data

* Determined with 20% excess air** G20 (NGA) = 34,0 MJ/m3 NCV

3.3 Quotation specifications- Heat exchanger manufactured from corrosion resi-

stant "pearlite" cast iron- Maximum operating pressure of 6 bar- Maximum operating temperature of 95°C- Sectional design with three passes for max efficiency

and a generously sized combustion chamber for mini-mising NOX production

- Water cooled base and rear sections- Large insulated door (hinged left or right) allowing

easy access for service operations- Supplied in broken down form for ease of delivery

and site access- Powder coated enamel steel casing- 80 - 100 mm thick glass wool insulation- Suitable for use with a Natural gas, and/or 35 sec oil

fired pressure jet burner (matched with most popular burner manufacturers)

- Supplied as standard with on/off switch, temperature indication, control and high limit thermostats

- Manufactured to ISO 9001- CE approved.

4 OUTPUT DATA54.1 Boiler efficiencyUp to 82.2% at Hs (91.3% at Hi) at full load and upto 87.0% at Hs (96.7% at Hi), at part load.Average water temperature 70°C (80/60°C).

4.2 Combustion efficiencyUp to 82.6% at Hs (91.8% at Hi) at full load and 88.1% at Hs (97.9% at Hi) at part load.

Note: Hi = NCV; Hs = GCV

WaterresistanceOutput Nominal heatinput

Combustionchamber

resistance*

Combustiongas sidecontents

Gasrate** T=20°C T=10°C

Watercontents

Fluegasflowrate

No. ofsections

kW kW-GCV

kW-NCV

mbar m3 m3/h mbar mbar liters kg/h

8

9

106 - 278

128 - 331

345

410

311

369

1.1

1.4

0.43

0.48

33

39

11

14

45

56

146

163

485

576

10

11

149 - 383

170 - 437

473

538

425

484

1.9

2.4

0.53

0.58

45

51

18

22

72

88

180

197

663

756

12

13

192 - 491

210 - 543

603

665

542

598

3.4

4.0

0.63

0.68

57

63

27

34

108

136

214

231

846

933

14

15

233 - 596

255 - 651

728

794

655

714

4.5

4.8

0.73

0.78

69

76

42

50

168

200

248

265

1022

1115

16 278 - 709 862 775 5.0 0.83 82 57 228 282 1210

Page 21: Pressurized boiler - Remeha

Remeha P 300

6 7

5 APPLICATION DATA

5.1 Hot water version

5.1.1 Water temperatureMaximum water temperature is 110°C.The minimum acceptable return water temperature is, both for gas and oil fired boilers 40°C, at a flow rate cor-responding to a ∆T of 20°C at nominal heat output.

5.1.2 Water pressureMaximum pressure 6 bar. The boiler is suitable for open and sealed systems up to a maximum pressure of 6 bar and a minimum pressure of 0.8 bar. Installation of the boiler on rooftop or in basement is possible.

5.1.3 Flow rateThe minimum flow rate through the boiler is obtained from the following formula:

Nominal heat output (kW) = m3/h70

This minimum flow must be maintained for 5 minutes after the burner stops firing to avoid high temperature shut-down due to residuel heat gain. Due to the design and manufacture of the boiler no specicific minimum water flow requirement exists other than for over tempe-rature protection.

5.1.4 Water treatmentThe system should be filled with mains cold water (for the UK this will usually have a pH of between 7 and 8).Pressurised installations with a boiler/system content ratio of 1:10 or less should not require water treatment, provided that the following conditions apply:1. The system is flushed thoroughly to remove all fluxes

and debris and then filled completely once.2. Make up water is limited to 5% per annum.3. The hardness of the water does not exceed 360 ppm

(20°D). All scale deposits will reduce the efficiency of the boiler and should be prevented. However provided the above is complied with any scale produced will not be too det-rimental to the boiler efficiency and will not reduce the anticipated life expectancy of the boiler.

Note: Scale deposits in excess of 3 to 5 mm will reduce boiler efficiency and greatly increase the risk of prema-ture casting failure.

As most systems contain a variety of metals which can react with each other to cause corrosion. It is consid-ered good practice to provide some form of water treat-ment (especially in open vented systems) in order to prevent or reduce the following:- Metallic corrosion;- Formation of scale and sludge;- Microbiological contamination;- Chemical changes in the untreated system water.

Suitable chemicals and their use should be discussed with a specialist water treatment company prior to car-rying out any work. The specification of the system and manufacturers recommendations must be taken into account, along with the age and condition of the system. New systems should be flushed thoroughly to remove all traces of flux, debris, grease and metal swarf generated during installation. Care to be taken with old systems to ensure any black metallic iron oxide sludge and other corrosive residues are removed, again by thoroughly flushing, ensuring that the system is drained completely from all low points.

Note: Please ensure that the new boiler plant is not in circuit when the flushing takes place, especially if clean-ing chemicals are used to assist the process.

Under no circumstances is the boiler to be operated with cleaning chemicals in the system.

To summarise:- Minimise water loss;- Prevent pumping over in open vented systems;- Provide adequate air venting at all high points;- Keep pH level between 7 - 9 when using additives;- Maximum chlorine content of 200 mg/l;- Take advice on the suitability of inhibitors.

5.2 EconomisersECO's can be delivered upon request (for natural gas only). For specifications please refer to Technical infor-mation ECO 13/14/15.

5.3 Flue gas dischargeFor the discharge of the flue gases, chimney draught is not required.Tests have shown that very good combustion results are obtained with zero draught at the boiler outlet.

Page 22: Pressurized boiler - Remeha

Remeha P 300

6 7

5.4 Noise productionThe noise level taken at a distance of 1 m around the boiler is approx. 70 to 90 dBA. The noise level at the chimney outlet will, depending on load, type of burner and chimney situation, vary from 70 to 90 dBA, taken at a distance of 1 m from the outlet. If this noise production gives rise to problems in the immediate vicinity, then noise reducing or absorbing measures should be taken.

(zonder geluiddempkap)

Remeha P300 met Monarch-brander

800025031,5

part load

125

full load

63 500 1000 40002000

50

60

70

80

90

100

NR 60

NR 70

NR 80

NR 90

dBre2X10

N/m

-52

Frequency (Hz)

Fig. 02 Noise measurement Remeha P 300 without noise silencer00.14C.79.00010

The values that have been taken for the graph in Fig. 02, are averages obtained from various measurements carried out at a distance of approx. 1 m around the boi-ler and at a height of approx.1 m.

6 INSTALLATION REQUIREMENTS

6.1 Installation recommendations in the boiler houseThe necessary minimum installation space of the boiler can be seen from Fig. 03.

6.2 Base details

Fig. 04 Base details00.14B.78.00001

Fig. 03 Installation space of the Remeha P300

* 50 mm with vibration damper

gas

train

free accessfor service to rear of boiler

fre

e a

ccess

for

serv

ice

Number of sections

A

89

12001350

1011

15001650

1213

18001950

1415

21002250

16 2400

Page 23: Pressurized boiler - Remeha

Remeha P 300

8 9

7 ASSEMBLY GUIDELINES AND INSTALLATION REQUIREMENTS

7.1 GeneralThe Remeha P 300 boiler is delivered in individual sec-tions. The sizes are such that all parts can enter the boi-ler house through a normal door entrance. The casing and equipment parts are delivered in packaged units. If necessary, the boiler can be put into operation without casing. The casing can be added at a later stage wit-hout disconnecting the water connections.

7.2 Boiler assemblyAssembly and installation of the boiler may only be car-ried out by a recognised and approved engineer and in accordance with the assembly manual. Local regulations laid down by the relevant authorities must be adhered to.

7.3 Water connectionsThe water connections are at the rear of the boiler. The flow and return connections consist of flanged connec-tions in accordance with DIN 2633. The top flange at the front of the boiler is provided with 3 x R 1⁄2” threaded holes for the fitting of the thermostat pockets. The return connection is provided with a R 3⁄4” threaded hole in which a drain off cock is fitted.

8 INSTRUMENT PANEL

8.1 Equipment contentsThe panel contains all the necessary control and measuring instruments required to control the boiler. The connections have to be made on a terminal strip. The capillaries and sensor wires, which come from the con-trol panel, are placed in the instrument pockets that are fitted at the front of the boiler. Several extra options can be built into the panels. Ask our technical department.

8.2 Lay out of the instrument panel

Fig. 05 Layout of the instrument panel High/Low with hour run meters00.03F.79.00004

1. Operating switch (On/Off).2. Control thermostat. Setting between 35°C - 90°C.3. High/Low thermostat. Setting between 35°C - 90°C.4. Hours run meter total running hours.5. Hours run meter full load running hours.6. Analogue thermometer water temperature.7. High limit thermostat 110°C (locking).8. Central warning light.9. Option for rematic® weather compensator.9

9

7 85

62 3

4

1

Page 24: Pressurized boiler - Remeha

Remeha P 300

8 9

8.3 Wiring diagram instrument panel

Fig. 06 Wiring diagram instrument panel04.13C.SC.00004

1

4B

S5

4-9

3435

TR

1CT

1-2

1-3

230V

-50H

z

L

F2 6,3A

T

F1

6,3A

T

1

BS

T

3

4-4

2 41

4-2

32

11 1210

2-1

2-2

9-1

7-4

6-2

7-3

96-

3

9-4

4-1

(CA

)36

Tm

x1

2

37L1

T1

N

1412

A1

A2

1.)

P1

21

h

26H

2.)

3-2K

1k1

11

29P2

T1 C

24 25

2-3

4-8

1.)

14 13

2019

2-4

18

16 1517

9-6

9-11

BM

TR

2

9-8

3-1

3-4

2.)

3-3

3-5

2322

9-17

9-18

9-16

B4

T2

S3

T7 bl

T6

T8

br

28274-

7

BM

9-15B5

9-2

9-13

9-10

Pow

er s

uppl

y

Con

nect

or b

urne

r lo

w

ye/g

nbk

6bk

5bk

1

Ext

erna

l sig

nal o

n-of

fE

xter

nal s

igna

l hig

h-lo

w

low

bk4

bk2

bk3

Con

nect

or b

urne

r hi

gh

bk2

high

bk1

5-4

5-5

DS

FBM

BS

CA

..Tm

xT

R

H K P

Ope

ratin

g si

gnal

s (V

olt f

ree)

Wat

er le

vel s

witc

hG

ener

al w

arni

ng s

igna

lsB

urne

r sw

itch

Will

not

be

supp

lied

(opt

iona

l)C

onne

ctor

Fus

e

Dis

turb

ance

ligh

t bur

ner

lock

edA

uxila

iry r

elay

Hou

r ru

n co

unte

rH

igh

limit

ther

mos

tat

Cor

d co

lor/

num

ber

Con

trol

ther

mos

tat

DS T 2

3

1

1-1

N

CA

3

CA

1

L1 N

Ter

min

al s

trip

04.1

3C.S

C.0

0004

.

*

h

*O

ptio

nal

CA

4-5

CA

4

1.)

Ext

ern

al C

ontr

ol O

N/O

FF

Rem

ove

link;

inse

rt c

ontr

ol p

air (

230

V)

* O

ptio

nal

2.)

Ext

ern

al c

ontr

ol H

/L

Rem

ove

link;

inse

rt c

ontr

ol p

air (

230V

)

Page 25: Pressurized boiler - Remeha

Remeha P 300

10 11

9 COMMISSIONING

Note: Commissioning to only be carried out by a quali-fied engineer with the relevant training and certification i.e. Acops - Corgi and a commissioning data sheet com-pleted on site for issue to owner

9.1 Pressurized boiler with gas burner

9.1.1 Commissioning procedureIf the boiler is to be put into operation again following a period of non-use, then the following procedure must be carried out:- Open the main gas cock.- Switch the weather-compensator (if fitted) over to

manual operation (h).- Turn the thermostats to their highest setting.- Switch on the circulation pump.- Switch on the main switch.- Switch on the operation switch in the instrument

panel.- Consult burner manufacturers commissioning details.

Warning:If the instrument panel is fitted with a weather compen-sator, set the program switch to ‘manual’ position (h). The following will now take place:- The gas burner fan will start running so that during

the purging time the combustion chamber will be ven-tilated with the air damper fully opened.

- The air damper will then go into start position. - Ignition flame lights up and is checked. - Then the control box gives the all clear signal for the

burner to switch over to full load.

9.1.2 Putting out of operationIt is sufficient to switch off the operation switch on the instrument panel. It is important that in the event of work being carried out on the burner, the boiler/burner unit must be completely electrically isolated and the main gas cock must be shut.5

9.2 Pressurized boiler with oil burner

9.2.1 Commissioning procedureIf the boiler is to be put into operation again following a period of non-use, then the following procedure must be carried out:- Open the main oil cock.- Switch the weather-compensator (if fitted) over to

manual operation (h).- Turn the thermostat to their highest setting.- Switch on the circulation pump.- Switch on the main switch.- Switch on the operation switch in the instrument

panel.- Consult burner manufacturer commissioning details.

Warning:If the instrument panel is fitted with a weather compen-sator, set the program switch to ‘manual’ position (h). The following will now take place:- The oil burner fan will start running so that during the

purging time the combustion chamber will be ventila-ted with the air damper fully opened.

- The air damper will then go into start position.- Ignition flame lights up and is checked.- Then the control box gives the all clear signal for the

burner to switch over to full load.

9.2.2 Putting out of operationIt is sufficient to switch off the operation switch on the instrument panel. It is important that in the event of work being carried out on the burner, the boiler/burner unit must be completely electrically isolated and the main oil cock must be shut.

Page 26: Pressurized boiler - Remeha

Remeha P 300

10 11

10 FAULT FINDING11Faul10.1 High Limit thermostat lockout- Check the water circulation (circulation pump). Reset

the High Limit thermostat (‘reset’ button is on the instrument panel under the cover cap of the High Limit thermostat).

- Advise the installer in the event of continued lock outs.

11 MAINTENANCE RECOMMENDATIONS

11.1 GeneralDepending on the operating conditions, the block and the burner must be checked and cleaned one or more times a year.

11.2 Maintenance instructions- Cleaning of the boiler: - Put boiler out of operation. - Open the front door, if necessary after dismantling the burner. - Remove the retarders. - Clean the combustion chamber and flue passes using a suitable brush. - Clean the removed retarders. - Remove the rear panel of the boiler and

remove the cleaning cover (underneath the smoke box).

- Vacuum clean the boiler and the combustion chamber.

- Renew the front door seals after cleaning the boiler.

- Re-assemble the removed parts and close the front door.

- Re-assemble the burner (if dismanteld).- Check the boiler combustion side for leakage.- Check the equipment for proper functioning and if

necessary re-adjust the gas control and safety equipment.

- Check combustion by means of combustion gas analyses.

- Check the water connections.

Page 27: Pressurized boiler - Remeha

12

Re

me

ha

P

3

00

© CopyrightAll technical and technological information contained in these technical instructions,as well as any drawings and technical descriptions supplied, remain ourproperty and shall not be multiplied without our prior consent in writing.

Ours is a policy of continuous development. We reserve the right to alterspecifications without prior notification.

Subject to alterations52754/1000/0402/Ip.

Broag Ltd.

Head office

Remeha house,

Molly Millars Lane,

Wokingham,

Berkshire RG41 2QP.

Tel. 0118 9783434

Fax 0118 9786977

E-mail: [email protected]

Internet: uk.remeha.com

Branch office

Unit 3, Kestrel Close,

Quarry Hill Ind. Estate,

Ilkeston

Derbyshire DE7 4RD

Tel. 0115 9440778

Fax 0115 9440588

Page 28: Pressurized boiler - Remeha

Remeha P 500

• Pressurized boiler

• Heat output: 635 - 1900 kW

Technical information

Re

me

ha

P

50

0

Page 29: Pressurized boiler - Remeha

Remeha P 500

2

Preface 3

1 Description of the unit 31.1 General 31.2 Burners 3

2 Construction data 32.1 General 32.2 Sections 32.3 Casing 3

3 Technical data and dimensions 43.1 Dimensions 43.2 Technical data 43.3 Quotation specifi cations 5

4 Output data 54.1 Boiler effi ciency 54.2 Combustion effi ciency 5

5 Application data 55.1 L.P.H.W. version 5

5.1.1 Water temperature 55.1.2 Water pressure 55.1.3 Flow rate 55.1.4 Water treatment 6

5.2 Economisers 65.3 Flue gas discharge 65.4 Noise production 6

6 Installation requirements 76.1 Installation recommendations in the boiler house 7

7 Assembly guidelines and installation requirements 7

7.1 General 77.2 Water connections 77.3 Boiler assembly 7

8 Instrument panels 88.1 Equipment contents 88.2 Instrument panel High/Low with hours run meters 88.3 Wiring diagram instrument panel High/Low with hours run meters 1 9

9 Commissioning 109.1 Pressurized boiler with gas burner 10

9.1.1 Commissioning procedure 109.1.2 Putting out of operation 10

9.2 Pressurized boiler with oil burner 109.2.1 Commissioning procedure 109.2.2 Putting out of operation 10

10 Fault Finding 11

11 Maintenance recommendations 1111.1 General 1111.2 Maintenance instructions 11

TABLE OF CONTENT

Page 30: Pressurized boiler - Remeha

3

PREFACE

These technical instructions contain useful and impor-tant information for the correct operation and maintenan-ce of the Remeha boiler, model P200Read these instructions carefully before putting the boi-ler into operation; familiarise yourself with its control functions and operation, strictly observing the instructi-ons given. Failure to do so may invalidate warranty or prevent the boiler from operating.A competent Engineer, with the relevant certifi cation (i.e. CORGI, ACOPS, IEE regs. etc) must carry out the instal-lation and commissioning of the boiler.On completion a copy of the boiler log / commissioning sheet should be returned to Broag Ltd for record purpo-ses.

If you have any questions, or if you need more informa-tion about specifi c subjects relating to this boiler, or it’s installation please do not hesitate to contact us.The data published in these technical instructions is based on the latest information (at date of publication) and may be subject to revisions.We reserve the right to continuous development in both design and manufacture, therefore any changes to the technology employed may not be retrospective nor may we be obliged to adjust earlier supplies accordingly.

1 DESCRIPTION OF THE UNIT

1.1 GeneralHigh effi ciency pressurised boiler, suitable for use with natural gas and light oil, by means of a pressure jet burner. Also available with a condensing unit (ECO) (for natural gas only).The boiler meets the requirements of the CE regulations in the following directives:- Gas appliance directive no. 90/396/EEC- Electrical low voltage directive no. 73/23/EEC- E.M.C. directive no. 89/336/EEC- Effi ciency directive no. 92/42/EEC.Classifi cation type for evacuation of the combustion pro-ducts: B23.

1.2 BurnersIn principle all CE-approved pressure jet burners are sui-table, subject to prior adjustment to the boiler capacity and boiler construction. The individual boiler satisfi es inspection requirement for central heating boilers.

2 CONSTRUCTION DATA

2.1 GeneralThe boiler block consists of cast iron sections, which are assembled by means of tapered nipples. The boiler is a three-pass design. The boiler block is insulated with a 100-mm thick layer of glass wool.

2.2 SectionsThe sections are made of pearlitic cast iron.Weights and measures of the sections:- Front section: 220 kg H x W = 1252 x 1130mm- Intermediate section: 250 kg H x W = 1238 x 1130 mm - Rear section: 250 kg H x W = 1238 x 1130 mm

2.3 CasingSteel casing, fi nished with a high-quality insulation. The front door is suitable for left or right opening as desired.

Fig. 01 Remeha P500IL50

Page 31: Pressurized boiler - Remeha

Remeha P 500

4

3 TECHNICAL DATA AND DIMENSIONS

3.1 Dimensions

Front view Side view Rear view

Flow NG 150 - DIN2633 Return NG 150 - DIN2633 Flue ØD ext. Flanges in accordance with BS 4505 PN 16

Fig. 02 Dimensions00.15D.79.00006

3.2 Technical data

Number of sections 9 10 11 12 13 14 15 16 17 18 19 20

Nominal heat output kW 635 750 865 980 1095 1210 1325 1440 1555 1670 1785 1900

Hi /NCV

kW 706 834 962 1090 1218 1341 1468 1592 1719 1846 1973 2100Nominalheat input Hs /

GCVkW 784 926 1068 1210 1352 1488 1630 1767 1908 2049 2190 2331

A mm 1350 1500 1650 1800 1950 2100 2250 2400 2550 2700 2850 3000

B mm 1660 1810 1965 2115 2265 2415 2565 2715 2870 3020 3170 3320

C mm 1270 1420 1570 1720 1870 2020 2170 2320 2470 2620 2770 2920Dimensions

ØD mm 400 400 400 400 500 500 500 500 500 500 500 500

∆ t =

10°Cmbar 149 166 180 194 189 200 213 234 262 295 337 382

Waterresistance ∆ t =

20°Cmbar 37 42 45 47 49 50 53 59 66 74 84 96

Water contents litre 495 550 605 660 715 770 825 880 935 990 1045 1100

Page 32: Pressurized boiler - Remeha

5

Boiler weight (dry) kg 2650 2910 3175 3435 3695 3955 4220 4480 4740 5005 5265 5525

Combustion chamberresistance1) mbar 1.7 2.3 3.0 3.8 3.9 4.8 5.0 5.9 5.5 6.0 6.5 7.0

Combustion gas side

contentm3 0.8 0.9 1.0 1.1 1.2 1.3 1.4 1.5 1.6 1.7 1.8 1.9

Flue gas flow rate kg/h 1102 1302 1502 1702 1901 2081 2292 2485 2683 2882 3080 3278

Table 01 Technical data1) Determined with 20 % excess air.

3.3 Quotation specifi cations- Heat exchanger manufactured from corrosion resi-

stant “pearlite” cast iron- Maximum operating pressure of 6 bar- Maximum operating temperature of 95°C- Sectional design with three passes for max effi ciency

(gross 83%) and a generously sized combustion chamber for minimising NOX production

- Water cooled base and rear sections- Large insulated door (hinged left or right) allowing

easy access for service operations- Supplied in broken down form for ease of delivery and

site access

- Powder coated enamel steel casing- 80 - 100 mm thick glass wool insulation- Suitable for use with a Natural gas, and/or 35 sec oil

fi red pressure jet burner (matched with most popular burner manufacturers)

- Supplied as standard with on/off switch, temperature indication, control and high limit thermostats

- Effi ciency 83% (Hs - GCV)- Manufactured to ISO 9001- CE approved.

4 OUTPUT DATA

4.1 Boiler effi ciencyUp to 90.2 % at Hi (81.3 % at Hs) at full load and up to 92.5 % at Hi (83.3 % at Hs) at part load.Average water temperature 70°C (80/60°C).

4.2 Combustion effi ciencyUp to 91.2 % at Hi (82.2 % at Hs) at full load and up to 95.5 % at Hi (86.0 % at Hs) at part load.

Note: Hi = NCV; Hs = GCV

5 APPLICATION DATA

5.1 L.P.H.W. version

5.1.1 Water temperatureMaximum water temperature is 110°C.The minimum acceptable return water temperature is, both for gas and oil fi red boilers 40°C, at a fl ow rate corresponding to a ∆t of 20°C at nominal heat output.

5.1.2 Water pressureMaximum pressure 6 bar.The boiler is suitable for open and sealed systems up to a maximum pressure of 6 bar and a minimum pres-sure of 0.8 bar. The boiler is suitable for installation in basement or rooftop boiler houses.

5.1.3 Flow rateThe minimum fl ow rate through the boiler is obtained from the following formula:

Nominal heat output (kW) = m3/h70

This minimum fl ow must be maintained for 5 minutes after the burner stops fi ring to avoid high temperature shutdown due to residual heat gain. Due to the design and manufacture of the boiler no specifi c minimum water fl ow requirement exists other than for over-temperature protection.

Page 33: Pressurized boiler - Remeha

Remeha P 500

6

5.1.4 Water treatmentThe system should be fi lled with mains cold water (for the UK this will usually have a pH of between 7 and 8).Pressurised installations with a boiler/system content ratio of 1:10 or less should not require water treatment, provided that the following conditions apply:1. The system is fl ushed thoroughly to remove all fl uxes

and debris and then fi lled completely once.2. Make up water is limited to 5 % per annum.3. The hardness of the water does not exceed 360 ppm

(20°D). All scale deposits will reduce the effi ciency of the boiler and should be prevented. However provided the above is complied with any scale produced will not be too detrimental to the boiler effi ciency and will not reduce the anticipated life expectancy of the boiler.

NOTE: Scale deposits in excess of 3 to 5 mm will reduce boiler effi ciency and greatly increase the risk of premature casting failure.

As most systems contain a variety of metals which can react with each other to cause corrosion. It is consid-ered good practice to provide some form of water treat-ment (especially in open vented systems) in order to prevent or reduce the following:- Metallic corrosion;- Formation of scale and sludge;- Microbiological contamination;- Chemical changes in the untreated system water.

Suitable chemicals and their use should be discussed with a specialist water treatment company prior to car-rying out any work. The specifi cation of the system and manufacturers recommendations must be taken into account, along with the age and condition of the system. New systems should be fl ushed thoroughly to remove all traces of fl ux, debris, grease and metal swarf generated during installation. Care to be taken with old systems to ensure any black metallic iron oxide sludge and other corrosive residues are removed, again by thoroughly fl ushing, ensuring that the system is drained completely from all low points.

NOTE: Please ensure that the new boiler plant is not in circuit when the fl ushing takes place, especially if cleansing chemicals are used to assist the process.

Under no circumstances is the boiler to be operated with cleaning chemicals in the system.

To summarise:- Minimise water loss;- Prevent pumping over in open vented systems;- Provide adequate air venting at all high points;- Keep pH level between 7 - 9 when using additives;- Maximum chlorine content of 200 mg/l;- Take advice on the suitability of inhibitors.

5.2 EconomisersECO’s can be delivered upon request (for natural gas only). For specifi cations please refer to Technical infor-mation ECO 13/14/15.

5.3 Flue gas dischargeFor the discharge of the fl ue gases, chimney draught is not required.Tests have shown that very good combustion results are obtained with zero draught at the boiler outlet.

5.4 Noise productionThe noise level taken at a distance of 1 m around the boiler is approximately 75 to 90 dBA. The noise level at the chimney outlet will, depending on load, type of burner and chimney situation, vary from 75 to 90 dBA, measured at a distance of 1 m from the outlet. If this noise production gives rise to problems in the imme-diate vicinity, then noise reducing or absorbing measu-res should be taken.

50

60

70

80

90

100

31,5 63 125 250 500 1000 2000 4000 8000

NR 60

NR 70

NR 80

NR 90

frequency (Hz)

dB r

e 2x

10-5

N/m

2

full load

part load9Fig. 03 Noise level readings without burner silencer

The values that have been taken are averages obtained from various measurements carried out at a distance of approximately 1 m around the boiler and at a height of approximately 1 m.

Page 34: Pressurized boiler - Remeha

7

6 INSTALLATION REQUIREMENTS

6.1 Installation recommendations in the boiler houseThe necessary minimum installation space of the boiler can be seen from Fig. 04.

Fig. 04 Installation recommendations in the boiler house04.15D.79.00001

H = 80mm without vibration damper H = 120mm with vibrationdamper

Fig. 05 Base details00.15A.78.00001

7 ASSEMBLY GUIDELINES AND INSTALLATION REQUIREMENTS

7.1 GeneralThe Remeha boiler P 500 is delivered in individual parts. The sizes of the boiler parts are such that they all can enter the boiler house through a normal entrance.The casing and equipment parts are delivered in pac-kaged units. If necessary, the boiler can be put into operation without casing. The casing can be added at a later stage without dismantling the water connections.

7.2 Water connectionsThe water connections are at the rear of the boiler.The fl ow and return connections consist of a fl anged fl ow elbow and a fl anged return connection in accor-dance with DIN 2633. The return connection is provided with a G ¾” threaded hole in which a drain off cock is fi tted.

At the front of the boiler a fl ange is provided with 2 x G ½” threaded holes for the fi tting of the thermostat pockets.

7.3 Boiler assemblyAssembly and installation of a boiler delivered in indivi-dual parts should only be undertaken by a recognised and approved engineer and in accordance with the assembly manual. Local regulations laid down by the relevant authorities must be adhered to.

Numberof

sections

A

mm

9 1350

10 1500

11 1650

12 1800

13 1950

14 2100

15 2250

16 2400

17 2550

18 2700

19 2850

20 3000

Page 35: Pressurized boiler - Remeha

Remeha P 500

8

8 INSTRUMENT PANELS

8.1 Equipment contentsThe panels contain all the necessary control and measu-ring instruments required to control the boiler. The con-nections have to be made on a terminal strip. The capil-laries and sensor wires, which come from the control panel, are placed in the instrument pockets that are fi tted at the front of the boiler.

See par. 8.2 for an instrument panel High/Low with hours run meters. Several extra options can be built into the panels.Ask our technical department.

8.2 Instrument panel High/Low with hours run meters

Fig. 06 Layout of the instrument panel High/Low with hours run meters00.03F.79.00004

1. Operating switch (On/Off)2. Control thermostat; setting between 35°C - 95°C3. High/Low thermostat; setting between 35°C - 95°C4. Hours run meter total running hours5. Hours run meter full load running hours6. Analoque thermometer water temperature7. High limit thermostat 110°C (lock out)8. Lock out warning lamp9. Option for rematic® weather compensator

1 2 3 6

4 5 7 8

9

Page 36: Pressurized boiler - Remeha

9

8.3 Wiring diagram instrument panel High/Low with hours run meters 13

Fig. 07 Wiring diagram instrument panel High/Low with hours run meters04.13C.SC.00001

1.) E

xternal control.

rem

ove link; insert control pair (230 V)

2.) E

xternal control High/Low

.

rem

ove link; insert control pair (230 V).1

Page 37: Pressurized boiler - Remeha

Remeha P 500

10

9 COMMISSIONING

Note:Commissioning to only be carried out by a qualifi ed engineer with the relevant training and certifi cation i.e. Acops-Corgi and a commissioning data sheet completed on site for issue to owner.

9.1 Pressurized boiler with gas burner

9.1.1 Commissioning procedureIf the boiler is to be put into operation again following a period of non-use, then the following procedure must be carried out :- Open the main gas cock.- Switch the weather-compensator (if fi tted) over to

manual operation (h).- Turn the thermostats to their highest setting.- Switch on the circulation pump.- Switch on the main switch.- Switch on the operation switch in the instrument

panel.- Consult burner manufacturers commissioning details.

WarningIf the instrument panel is fi tted with a weather compen-sator, set the program switch to ‘manual’ position (h). The following will now take place:- The gas burner fan will start running so that during

the purging time the combustion chamber will be ven-tilated with the air damper fully opened.

- The air damper will then go into start position. - Ignition fl ame lights up and is checked. - Then the control box gives the all clear signal for the

burner to switch over to full load.

9.1.2 Putting out of operationIt is suffi cient to switch off the operation switch on the instrument panel. It is important that in the event of work being carried out on the burner, the boiler/burner unit must be completely electrically isolated and the main gas cock must be shut.5

9.2 Pressurized boiler with oil burner

9.2.1 Commissioning procedureIf the boiler is to be put into operation again following a period of non-use, then the following procedure must be carried out :- Open the main oil cock.- Switch the weather-compensator (if fi tted) over to

manual operation (h).- Turn the thermostat to their highest setting.- Switch on the circulation pump.- Switch on the main switch.- Switch on the operation switch in the instrument

panel.- Consult burner manufacturer commissioning details.

WarningIf the instrument panel is fi tted with a weather compen-sator, set the program switch to ‘manual’ position (h). The following will now take place:- The oil burner fan will start running so that during the

purging time the combustion chamber will be ventila-ted with the air damper fully opened.

- The air damper will then go into start position.- Ignition fl ame lights up and is checked.- Then the control box gives the all clear signal for the

burner to switch over to full load.

9.2.2 Putting out of operationIt is suffi cient to switch off the operation switch on the instrument panel. It is important that in the event of work being carried out on the burner, the boiler/burner unit must be completely electrically isolated and the main oil cock must be shut.

Page 38: Pressurized boiler - Remeha

11

10 FAULT FINDING

High Limit thermostat lock out:- Check the water circulation (circulation pump). Reset

the High Limit thermostat (Reset button is on the instrument panel under the cover cap of the High Limit thermostat).

- Advise the installer in the event of continued lockouts.

11 MAINTENANCE RECOMMENDATIONS

11.1 GeneralDepending on the operational conditions, the block and the burner must be checked and cleaned at least once a year for gas and at least twice a year for oil.

11.2 Maintenance instructionsCleaning of the boiler:- Put boiler out of operation.- Open the front door, if necessary after dismantling the

burner.- Remove the retarders (only for the 9 - 16 sections).- Clean the combustion chamber and fl ue passes using

a suitable brush.- Clean the removed retarders ( 9 - 16 sections).- Remove the rear panel of the boiler and remove the

cleaning cover (underneath the smoke box).

- Vacuum clean the boiler and the combustion cham-ber.

- Renew the front door seals after cleaning the boiler.- Re-assemble the removed parts and close the front

door.- Re-assemble the burner (if dismantled).- Check the boiler combustion side for leakage.- Check the equipment for proper functioning and if

necessary re-adjust the control and safety equipment.- Carry out combustion analysis.- Check the water connections.

Page 39: Pressurized boiler - Remeha

12

© Copyright

All technical and technological information contained in these technical instructions,

as well as any drawings and technical descriptions furnished by us remain our

property and shall not be copied in part or whole without our prior consent in writing.

Subject to alterations52881/1000/0202/Ips.

Broag Ltd.

Head office

Remeha house

Molly Millars Lane

Wokingham,

Berkshire RG41 2QP

Tel.: 0118 978 3434

Fax: 0118 978 6977

E-mail address:

[email protected]

Branch office

Unit 3, Kestrel Close,

Quarry Hill ind. Estate,

Ilkeston

Derbyshire DE7 4RD

Tel.: 0115 944 0778

Fax: 0115 944 0588

Re

me

ha

P

50

0