Page 1: Presented by: Dr. Husam Arman Quality management: SPC II 1.

Presented by:

Dr. Husam Arman

Quality management: SPC II

1

Page 2: Presented by: Dr. Husam Arman Quality management: SPC II 1.

Histograms do not take into account changes over time.

Control charts can tell us when a process changes

2

Page 3: Presented by: Dr. Husam Arman Quality management: SPC II 1.

Control Chart Applications

Establish state of statistical control

Monitor a process and signal when it goes out of control

Determine process capability

3

Page 4: Presented by: Dr. Husam Arman Quality management: SPC II 1.

Commonly Used Control Charts

Variables data x-bar and R-charts x-bar and s-charts Charts for individuals (x-charts)

Attribute data For “defectives” (p-chart, np-chart) For “defects” (c-chart, u-chart)

4

Page 5: Presented by: Dr. Husam Arman Quality management: SPC II 1.

Control chart functions

Control charts are decision-making tools - they provide an economic basis for deciding whether to alter a process or leave it alone

Control charts are problem-solving tools - they provide a basis on which to formulate improvement actions

SPC exposes problems; it does not solve them!

5

Page 6: Presented by: Dr. Husam Arman Quality management: SPC II 1.

Control charts

Control charts are powerful aids to understanding the performance of a process over time.

PROCESS

Input Output

What’s causing variability?6

Page 7: Presented by: Dr. Husam Arman Quality management: SPC II 1.

Control charts identify variation

Chance causes - “common cause” inherent to the process or random and not

controllable if only common cause present, the process is

considered stable or “in control” Assignable causes - “special cause”

variation due to outside influences if present, the process is “out of control”

7

Page 8: Presented by: Dr. Husam Arman Quality management: SPC II 1.

Common Causes

Special Causes

8

Page 9: Presented by: Dr. Husam Arman Quality management: SPC II 1.

Control charts help us learn more about processes Separate common and special causes of

variation Determine whether a process is in a state of

statistical control or out-of-control Estimate the process parameters (mean,

variation) and assess the performance of a process or its capability

9

Page 10: Presented by: Dr. Husam Arman Quality management: SPC II 1.

Control charts to monitor processes To monitor output, we use a control chart

we check things like the mean, range, standard deviation

To monitor a process, we typically use two control charts mean (or some other central tendency

measure) variation (typically using range or standard

deviation)

10

Page 11: Presented by: Dr. Husam Arman Quality management: SPC II 1.

Control chart components

Centerline shows where the process average is centered

or the central tendency of the data Upper control limit (UCL) and Lower control

limit (LCL) describes the process spread

11

Page 12: Presented by: Dr. Husam Arman Quality management: SPC II 1.

Control charts are practical tools to monitor the evolution of production processes.

In any production process a certain amount of natural variability will always exist (this is the cumulative effect of small and unavoidable causes)

A process that is operating in the presence of chance causes of variation only is said to be in statistical control.

Control chart

12

Page 13: Presented by: Dr. Husam Arman Quality management: SPC II 1.

A process that is operating in the presence of assignable causes (sources of variability that are not part of the chance causes) is said to be out of control.

Three main sources of assignable causes:

1) improperly adjusted or controlled machines (or failures);

2) operator errors;

3) defective raw materials.

Control chart

13

Page 14: Presented by: Dr. Husam Arman Quality management: SPC II 1.

A control chart contains A center line (CL) An upper control limit

(UCL) A lower control limit (LCL)

(LCL)

(UCL)

(CL)

Control limits are different from specification limits

Control chart

14

Page 15: Presented by: Dr. Husam Arman Quality management: SPC II 1.

A point that plots within the control limits indicates that the process is in control → no action is necessary

A point that plots outside the control limits is evidence that the process is out of control

→ Investigation and corrective action are required to find and eliminate assignable cause(s)

There is a close connection between control charts and hypothesis testing (to test if the process is in a state of statistical control: we can fail to reject or reject this hypothesis)

(LCL)

(UCL)

(CL)Basic criterion

15

Page 16: Presented by: Dr. Husam Arman Quality management: SPC II 1.

… in general we use L=3 → ±3·sw control limits16

Page 17: Presented by: Dr. Husam Arman Quality management: SPC II 1.

Three standard deviations

99.73%

3 3

17

Page 18: Presented by: Dr. Husam Arman Quality management: SPC II 1.

One of the two main types of control charts is chart for VARIABLES (quality characteristics measured on a numerical scale; e.g. geometrical dimensions, weights, tensile strengths…)

- (mean) control charts

- R (range) control charts

- s2 (sample variance) control charts

- s (sample standard deviation) control charts

- xi (control charts for individual measurements)

x

Control chart

18

Page 19: Presented by: Dr. Husam Arman Quality management: SPC II 1.

Control chart for variables (Ch 5)

Variables are the measurable characteristics of a product or service.

Measurement data is taken and arrayed on charts.

19

Page 20: Presented by: Dr. Husam Arman Quality management: SPC II 1.

X-bar and R charts

The X-bar chart - used to detect changes in the mean between subgroups tests central tendency or location effects

The R chart - used to detect changes in variation within subgroups tests dispersion effects

20

Page 21: Presented by: Dr. Husam Arman Quality management: SPC II 1.

Step 1 Define the problem

Use other quality tools to help determine the general problem that’s occurring and the process that’s suspected of causing it. brainstorm using cause and effect diagram,

why-why, Pareto charts, etc.

21

Page 22: Presented by: Dr. Husam Arman Quality management: SPC II 1.

Step 2 Select a quality characteristic to be measured Identify a characteristic to study - for

example, part length or any other variable affecting performance typically choose characteristics which are

creating quality problems possible characteristics include: length, height,

viscosity, temperature, velocity, weight, volume, density, etc.

22

Page 23: Presented by: Dr. Husam Arman Quality management: SPC II 1.

Step 3 Choose a subgroup size to be sampled Choose homogeneous subgroups

Homogeneous subgroups are produced under the same conditions, by the same machine, the same operator, the same mold, at approximately the same time.

Try to maximize chance to detect differences between subgroups, while minimizing chance for difference with a group.

23

Page 24: Presented by: Dr. Husam Arman Quality management: SPC II 1.

Other guidelines

The larger the subgroup size, the more sensitive the chart becomes to small variations in the process average.

This increases data collection costs. Destructive testing may make large

subgroup sizes infeasible. Subgroup sizes smaller than 4 aren’t

representative of the distribution averages. Subgroups over 10 should use S chart.

24

Page 25: Presented by: Dr. Husam Arman Quality management: SPC II 1.

Step 4 Collect the data

Run the process untouched to gather initial data for control limits.

Generally, collect 20-25 subgroups (100 total samples) before calculating the control limits.

Each time a subgroup of sample size n is taken, an average is calculated for the subgroup and plotted on the control chart.

25

Page 26: Presented by: Dr. Husam Arman Quality management: SPC II 1.

Step 5 Determine trial centerline for the Xbar chart

The centerline should be the population mean, Since it is unknown, we use X double bar, or the

grand average of the subgroup averages.

m

m

i

i 1

XX

26

Page 27: Presented by: Dr. Husam Arman Quality management: SPC II 1.

1 2 3 m

1 2 3 m

x x x ... xgrand average x

mR R R ... R

mean range Rm

1) x11, x12, … , x1n R1

2) x21, x22, … , x2n R2

......

...

m) xm1, xm2, … , xmn

Rm

1x

2x

mx

27

Page 28: Presented by: Dr. Husam Arman Quality management: SPC II 1.

Step 6 Determine trial control limits - Xbar chart The normal curve displays the distribution of

the sample averages. A control chart is a time-dependent pictorial

representation of a normal curve. Processes that are considered under control

will have 99.73% of their graphed averages fall within six standard deviations.

28

Page 29: Presented by: Dr. Husam Arman Quality management: SPC II 1.

UCL & LCL calculation

deviation standard

3XLCL

3XUCL

29

Page 30: Presented by: Dr. Husam Arman Quality management: SPC II 1.

Determining an alternative value for the standard deviation (Xbar chart)

XCL RAXUCL 2X

RAXLCL 2X

30

Page 31: Presented by: Dr. Husam Arman Quality management: SPC II 1.

Step 7 Determine trial control limits - R chart The range chart shows the spread or

dispersion of the individual samples within the subgroup. If the product shows a wide spread, then the

individuals within the subgroup are not similar to each other.

Equal averages can be deceiving. Calculated similar to x-bar charts;

Use D3 & D4

31

Page 32: Presented by: Dr. Husam Arman Quality management: SPC II 1.

R-chart

m

m

ii

1

RR

RR 3UCLR RR 3LCLR

32

Page 33: Presented by: Dr. Husam Arman Quality management: SPC II 1.

Determining an alternative value for the standard deviation (R chart)

m

m

ii

1

RR

RDUCL 4R RDLCL 3R

33

Page 34: Presented by: Dr. Husam Arman Quality management: SPC II 1.

Example

34

Page 35: Presented by: Dr. Husam Arman Quality management: SPC II 1.

R-bar chart exceptions

Because range values cannot be negative, a value of 0 is given for the lower control limit of sample sizes of six or less (see D3 value in the previous table).

35

Page 36: Presented by: Dr. Husam Arman Quality management: SPC II 1.

Step 8 Examine the process - Interpret the charts

A process is considered to be stable and in a state of control, or under control, when the performance of the process falls within the statistically calculated control limits and exhibits only chance, or common causes.

36

Page 37: Presented by: Dr. Husam Arman Quality management: SPC II 1.

Consequences of misinterpreting the process Blaming people for problems that they

can’t control Spending time and money looking for

problems that do not exist Spending time and money on unnecessary

process adjustments Taking action where no action is warranted Asking for worker-related improvements

when process improvements are needed first 37

Page 38: Presented by: Dr. Husam Arman Quality management: SPC II 1.

Process variation

When a system is subject to only chance causes of variation, 99.73% of the measurements will fall within 3 standard deviations If 1000 subgroups are measured, 997 will fall

within the six sigma limits.

38

Page 39: Presented by: Dr. Husam Arman Quality management: SPC II 1.

Chart zones

Based on our knowledge of the normal curve, a control chart exhibits a state of control when:

1. Two thirds of all points are near the center value.

2. A few of the points are on or near the center value

3. The points appear to float back and forth across the centerline.

4. The points are balanced on both sides of the centerline.

5. No points beyond the control limits.

6. No patterns or trends.39

Page 40: Presented by: Dr. Husam Arman Quality management: SPC II 1.

Identifying patterns

Sudden shift in the process average Cycles Trends

40

Page 41: Presented by: Dr. Husam Arman Quality management: SPC II 1.

Shift in Process Average

41

Page 42: Presented by: Dr. Husam Arman Quality management: SPC II 1.

Identifying Potential Shifts

42

Page 43: Presented by: Dr. Husam Arman Quality management: SPC II 1.

Cycles

43

Page 44: Presented by: Dr. Husam Arman Quality management: SPC II 1.

Trend

44

Page 45: Presented by: Dr. Husam Arman Quality management: SPC II 1.

Step 9 Revise the charts

In certain cases, control limits are revised because: out-of-control points were included in the

calculation of the control limits. The process is in-control but the within

subgroup variation significantly improves.

45

Page 46: Presented by: Dr. Husam Arman Quality management: SPC II 1.

Revising the charts

Interpret the original charts Isolate the causes Take corrective action Revise the chart

Only remove points for which you can determine an assignable cause

46

Page 47: Presented by: Dr. Husam Arman Quality management: SPC II 1.

Step 10 Achieve the purpose

Our goal is to decrease the variation inherent in a process over time.

As we improve the process, the spread of the data will continue to decrease.

Quality improves!!

47

Page 48: Presented by: Dr. Husam Arman Quality management: SPC II 1.

Charts for Attributes

Fraction nonconforming (p-chart) Fixed sample size Variable sample size

np-chart for number nonconforming

Charts for defects c-chart u-chart

48

Page 49: Presented by: Dr. Husam Arman Quality management: SPC II 1.

Control Chart Selection

Quality Characteristic

variable attribute

n>1?

n>=10 ?

x and MRno

yes

x and s

x and Rno

yes

defective defect

constant sample size?

p-chart withvariable samplesize

no

p ornp

yes constantsampling unit?

c u

yes no

49

Page 50: Presented by: Dr. Husam Arman Quality management: SPC II 1.

Control Chart Design Issues

Basis for samplingSample sizeFrequency of samplingLocation of control limits

50

Page 51: Presented by: Dr. Husam Arman Quality management: SPC II 1.

SPC Implementation Requirements

Top management commitmentProject championInitial workable projectEmployee education and trainingAccurate measurement system

51