MINUTES OF THE 122 nd MEETING OF THE SEAC KERALA HELD DURING 15 th , 16 th , 17 th &18 th JUNE 2021 AT THE CONFERENCE HALL, STATE ENVIRONMENT IMPACT ASSESSMENT AUTHORITY, THIRUVANANTHAPURAM The 122 nd meeting of the SEAC KERALA was held online during 15 th ,16 th ,17 th &18 th June, 2021 observing all the Covid-19 protocols stipulated by the Government. The meeting started at 10.00 AM on 15 th June, 2021 with Dr.C. Bhaskaran, Chairman, SEAC KERALA chairing. The Chairman welcomed the members to the meeting. The Committee then moved on to the deliberations on the agenda items. PHYSICAL FILES Minutes of the 121 st SEAC meeting held on 22nd, 23rd & 24th April 2021 Decision: Noted Presentation Environmental Clearance for Masonary stone mine quarry in Survey No.59/1- 1,86/4 in Block number 79 in Koottikkal village, Kanjirapally Taluk, Kottayam District (2438/EC1/2019/SEIAA Decision: The proponent and the RQP were present. The RQP made the presentation. The Committee entrusted Shri.G. Sankar & Dr.S. Sreekumar with the Field Inspection. Judgment in WP (C) 3317/2021 filed by Sri.Siril Jose- regarding the validity of EC. (File No.615/EC4/2021/SEIAA) Decision: The proponent and the RQP were present. The RQP made the presentation. The Committee entrusted Dr.R.Ajayakumar Varma and Dr. N. Anilkumar with the Field Inspection. Judgment in WP (C) 3337/2021 filed by Sri.Jilson Joseph- regarding the validity of EC. (File No.617/EC4/2021/SEIAA) Decision: The proponent and the RQP were present. The RQP made the presentation. The Committee entrusted Dr. R. Ajayakumar Varma and Dr. N. Anilkumar with the Field Inspection. Item No.122.01 Item No. 122.02 Item No.122.03 Item No.122.04
55

Presentation - SEIAA-KERALA

Jan 23, 2023

Download

Documents

Khang Minh
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Presentation - SEIAA-KERALA

MINUTES OF THE 122nd

MEETING OF THE SEAC KERALA HELD DURING 15th

, 16th

,

17th

&18th

JUNE 2021 AT THE CONFERENCE HALL, STATE ENVIRONMENT IMPACT

ASSESSMENT AUTHORITY, THIRUVANANTHAPURAM

The 122nd

meeting of the SEAC KERALA was held online during 15th,16

th,17

th &18

th June,

2021 observing all the Covid-19 protocols stipulated by the Government. The meeting started at 10.00

AM on 15th

June, 2021 with Dr.C. Bhaskaran, Chairman, SEAC KERALA chairing. The Chairman

welcomed the members to the meeting. The Committee then moved on to the deliberations on the

agenda items.

PHYSICAL FILES

Minutes of the 121st SEAC meeting held on 22nd, 23rd & 24th April 2021

Decision: Noted

Presentation

Environmental Clearance for Masonary stone mine quarry in Survey

No.59/1- 1,86/4 in Block number 79 in Koottikkal village, Kanjirapally

Taluk, Kottayam District (2438/EC1/2019/SEIAA

Decision: The proponent and the RQP were present. The RQP made the presentation. The

Committee entrusted Shri.G. Sankar & Dr.S. Sreekumar with the Field Inspection.

Judgment in WP (C) 3317/2021 filed by Sri.Siril Jose- regarding

the validity of EC. (File No.615/EC4/2021/SEIAA)

Decision: The proponent and the RQP were present. The RQP made the presentation. The

Committee entrusted Dr.R.Ajayakumar Varma and Dr. N. Anilkumar with the Field Inspection.

Judgment in WP (C) 3337/2021 filed by Sri.Jilson Joseph-

regarding the validity of EC. (File No.617/EC4/2021/SEIAA)

Decision: The proponent and the RQP were present. The RQP made the presentation. The

Committee entrusted Dr. R. Ajayakumar Varma and Dr. N. Anilkumar with the Field Inspection.

Item No.122.01

Item No. 122.02

Item No.122.03

Item No.122.04

Page 2: Presentation - SEIAA-KERALA

Judgment in WP (C) No.3510/2021 filed by Sri.P.M.Aboobacker,

Palakkal Granites - regarding the validity of EC. (File

No.1054/EC4/2021/SEIAA)

Decision: The proponent and the RQP were present. The RQP made the presentation. The

Committee entrusted Shri.K. Krishna Panicker & Dr. P.S.Easa with the Field Inspection.

Hearing

Judgement in WP(C) No. 12073/2020 (H) dated 19.06.2020 filed by

M. M. Joseph, Menacheril House, Boothathankettu (P.O.),

Pindimana, Kothamangalam, Ernakulam (File No:

1032/EC3/2020/SEIAA)

Decision: The proponent and the RQP were present. The Committee heard them and decided

to await the response of the proponent on the matter of fresh appraisal of the proposal as

requested by him at the time of hearing.

Application for Environment Clearance application for mining

lease in respect of “Granite Building Stone Quarry of M/s.

Kizhakethalacakal Rocks, over an extent of 12.4408 Ha.

Survey.Nos. 184/1A (Government Land), Elappara Village,

Peermade Taluk, Idukki District, Kerala State. (Proposal No.

SIA/KL/MIN/145075/2020) File No. 1195/EC2/2018/SEIAA

Decision: The proponent and the RQP were present. The Committee decided to invite the

proponent for presentation of the alternate proposal after the study of slope stabilisation measures

by a reputed agency as agreed to by the proponent.

Application for Environmental Clearance for mining of Granite

Building Stone Quarry project in Survey No 292/1 A of Vellad

Village, Thaliparamba Taluk, Kannur District, Kerala by Mr.

Mathew, M/s Alacode Granites (File No.

1277(A)/EC2/2019/SEIAA)

Decision: The proponent and the RQP were present. The Committee heard the proponent and

decided to invite the proponent for presentation of the additional details. The Committee also

decided to provide the relevant portions of the FIR to the proponent. The Committee also

entrusted Dr. R. Ajayakumar Varma, Dr. N. Anilkumar, Sri.K. Krishna Panicker and Sri. G.

Sankar to study the additional details prior to its presentation before the Committee.

Additional Documents Received

Item No.122.05

Item No. 122.06

Item No.122.07

Item No.122.08

Page 3: Presentation - SEIAA-KERALA

Application for Environmental Clearance for Building Stone

Quarry in Survey No 34/3-2,34/10,34/9,35/1-2,31/1-2,31/1-3,31/1-

4,45/2,45/7,45/8-2,46/1-2,34/8,34/12,44/2-3,46/3,45/5,45/6,34/3,44/4

and 44/5,34/2 in Mancode Village, Kottarakara Taluk, Kollam

District (File.No.2543/EC2/2019/SEIAA (Online File No.

1462/EC2/2019/SEIAA)

Decision: Deferred for scrutiny of the additional documents submitted by the proponent as a

physical file.

Environmental clearance for the proposed Building stone quarry

project in, Survey No.1619/1,1621/1 in Kanthaladu Village,

Thamarassery Taluk, Kozhikode District, Kerala, by

Mr.Haridasan T.H, (FileNo.1264/EC1/2019/ SEIAA)

Decision: Deferred for scrutiny of the additional documents submitted by the proponent as a

physical file.

Judgment in WP (C) 5361/2021 filed by Sri. Linej T.P- regarding

the validity of EC. (File No.912/EC4/2021/SEIAA)

Decision: The Committee decided to invite the proponent for presentation.

Judgment in WP (C) 3721/2021 filed by Sri.C.P.Muhammed-

regarding the validity of EC. (File No.748/EC4/2021/SEIAA)

Decision: The Committee decided to invite the proponent for presentation.

Judgment in WP (C) 7697/2021 (J) filed by Smt. Bindhu P.A.,

Thevarmadom Granites - regarding the Revalidation of EC (File

No. 997/EC3/4906/2015)- (Revalidation –Additional documents

received)

Decision: The Committee decided to invite the proponent for presentation.

Environmental Clearance for the quarry project in Sy. No. 1/1(pt),

2/2(pt), 3/3(pt) and 32/2(pt) at Mankada Village, Mankada

Panchayath, Perinthalmanna Taluk, Malappuram District by

Sri.M.P.Shoukathali, Managing Director, M/s.Ernad Granites Pvt.

Ltd. – Judgment dated 30.03.2021 in WP(C) No.8301 of 2021 -

Revalidation of EC (File No.609/SEIAA/EC1/4638/2015) – reg :-

(Revalidation –Additional documents received)

Item No.122.09

Item No.122.10

Item No.122.11

Item No.122.12

Item No.122.13

Item No.122.14

Page 4: Presentation - SEIAA-KERALA

Decision: The Committee decided to invite the proponent for presentation.

Environmental Clearance for the quarry project in Sy.Nos. 110/1,

111/3 at Karakunnu Village, Thrikkalan Panchayath,

Malappuram – Judgment dated 22.02.2021 in WP(C) No.4396 of

2021 - Revalidation of EC (File No.848/SEIAA/EC1/2861/2015) –

reg :- (Revalidation –Additional documents received)

Decision: The Committee decided to invite the proponent for presentation.

Environmental Clearance for the Building Stone quarry project in Sy.No.

36/3 (pt), 37/1(pt), 37/2(pt), 37/3(pt) at Morayoor Village, Kondotty

Taluk, Malappuram District, Kerala by Sri.E.A.Abdul Karim, M/s

Malabar Aggregates – Judgment dated 23.02.2021 in WP(C) No.4687 of

2021 - Revalidation of EC (File No.853/SEIAA/EC1/2977/2015)

Decision: The Committee decided to invite the proponent for presentation.

Environmental Clearance for the quarry project in Sy.Nos. 51pt, 47/1pt

& 49/2pt in Kizhuparamba Village, Ernad Taluk, Malappuram District,

Kerala by Sri.K. Kunjumoyin, Managing Partner, M/s Friends Crushers

– Judgment dated 29.03.2021 in WP(C) No.8118 of 2021 - Revalidation of

EC (File No.861/SEIAA/EC1/2990/2015)

Decision: The Committee decided to invite the proponent for presentation.

Environmental Clearance issued by DEIAA, Malappuram for the

quarry project in Re.Sy.No.234 in Pathaikkara Village,

Perinthalmanna Taluk, Malappuram District, Kerala by

Shri.Saidalavi.K – Judgment dated 29.03.2021 in WP(C) No.8190 of

2021 - Revalidation of EC (File No.1052/EC6/2021/SEIAA) – reg :

Decision: The Committee decided to invite the proponent for presentation.

Environmental clearance for the proposed quarry project in Survey

No. 163 (Block No.22),2/2-2,2/4-3,2/4-2,3/1-2,2/3,2/2-3,2/4-4,2/4-5

(BlocK No.27) in Urangattiri Village, Ernad Taluk, Malappuram

District, Kerala by Mr. K.V. Moideenkoya, M/s Kallarattikkal

Granites (File No. 1230/EC2/2019/SEIAA)

Decision: The Committee decided to invite the proponent for presentation.

Item No.122.15

Item No.122.16

Item No.122.17

Item No.122.18

Item No.122.19

Page 5: Presentation - SEIAA-KERALA

Environmental Clearance for mining of Granite Building Stone

Quarry in Survey Nos 178/1, 179/pt, Block No: 56 in Morayur

Village, Kondotty Taluk, Malappuram District, Kerala for an area

of 2.1404 ha by Sri. Muhammed Faisal K. P(File No-

1300/EC/2019/SEIAA)

Decision: The Committee decided to invite the proponent for presentation.

Forwarded from SEIAA

Environmental Clearance for the proposed building stone quarry in

Re- Survey No. 498/2, 498/3, 499/3, 499/4 in Chalavara Village,

Ottapalam Taluk, Palakkad District, Kerala by Mr. Paul.K.T.,

Managing Director, M/s K.T.Crusher‟s & Aggregates Pvt. Ltd. (File

No. 1260/EC2/2019/SEIAA)

Decision: Deferred for scrutiny of the additional documents submitted by the proponent as a

physical file.

Environmental Clearance issued for the proposed Commercial

Complex (Hotel, Convention Centre & Shopping Mall) project, M/s

LULU International Shopping Mall Pvt. Ltd., Thiruvanathapuram

District - Clarification sought regarding CER/CSR commitments

(File No.1047/EC1/899/SEIAA/2016)

Decision: The Committee entrusted Er. M. Dileepkumar with the detailed study of the

proposals.

Environmental Clearance for the Granite Building Stone Quarry

project in Survey No 326/2-9 in Eramalloor Village,

Kothamangalam Taluk, Ernakulam District, Kerala for an extent

of 0.5522 Ha of land by Sri. P.M. Moitheen –Review petition

(Proposal No: SIA/KL/MIN/145890/2020) (File No:

1430/EC3/2019/SEIAA)

Decision: Deferred for scrutiny of the physical file.

Environmental Clearance for the Commercial project “Ozone

Mall” in Sy. Nos. 4/2B, 146/1 and 146/7 at Pathaikkara Village,

Perinthalmanna Municipality, Perinthalmanna Taluk,

Malappuram District, Kerala by Sri. A.K. Abdul Aziz, M/s INOA

Properties & Developers L.L.P. – Request to remove the Ordinary

earth – reg :- (File No. 864/SEIAA/ EC1/3073/2015)

Decision: The Committee decided to invite the proponent for hearing.

Item No.122.20

Item No.122.21

Item No.122.22

Item No.122.23

Item No.122.24

Page 6: Presentation - SEIAA-KERALA

Environmental Clearance for the quarry project in Sy. Nos. 2066/1,

2067/2, 2063, 2057, 2056/2, 3 and 2067/1 at Kuttichira Village ,

Kodassery Panchayath, Chalakkudy Taluk, Thrissur District by

Sri. Shibu Pynadath John, Managing Director, M/s Pynadath

Granite Pvt.Ltd. – Judgment dated 18.11.2020 in WP(C) No.24278

of 2020 - Revalidation of EC- reg :- (File

No.606/SEIAA/EC1/4633/2014)

Decision: The Committee discussed the recommendation of SEIAA as well as the orders of the

Hon’ble High Court in this regard. The Committee decided to await further orders of the Hon’ble

HC on the petition filed by the proponent on 21-04-2021 against the cancellation of the EC. Since

there are separate directions from the Hon‟ble HC in this regard, the same are to be

brought to the notice SEIAA for further action.

Request for Reconsideration

Environmental Clearance for removal of Ordinary Earth in

Sy.No.604/5-A,604/5-B,604/2-A,604/2-Bat Onakkoor Village,

Muvattupuzha Taluk, Ernakulam District by Sri.Saji.P.K. [File

No.2797/EC4/2019/SEIAA]

Decision: The Committee decided to inform the SEIAA that final decision on the

proposal could not be taken in the light of the minimum distance norms of 200mfor

mining involving blasting and 100mfor mining not involving blasting are stipulated by

the Hon‟ble NGT wherein final orders are awaited.

General

SEAC meeting – Member Secretary, SEAC neither participated

in the SEAC meeting nor signed the minutes – Reg. (File No.

1501/A2/2021/SEIAA)

Decision:The Committee decided to inform the SEIAA that as the Secretary of SEAC has

stated he had not attended the 119th, 120th& 121st meetings of SEAC and the Minutes of these

meetings were approved by the Chairman. Therefore, necessary corrections have to be

incorporated in the connected records.

Additional Agenda

Environmental Clearance issued by DEIAA, Malappuram for the

quarry project in Re.Sy.No.231 of Elankur Village, Eranad Taluk,

Malappuram District, Kerala by Shri.Hasim Malik, JSS Granites

– Judgment dated 09.02.2021 in WP(C) No.3280 of 2021 -

Revalidation of EC (File No.394/EC6/2021/SEIAA) – reg : -

Item No.122.25

Item No.122.26

Item No.122.27

Item No.122.28

Page 7: Presentation - SEIAA-KERALA

Decision: The proponent and the RQP were present. The RQP made the presentation. The

Committee entrusted Dr. P.S. Easa and Dr. S. Sreekumar with the Field Inspection.

Environmental Clearance issued by DEIAA, Malappuram for the quarry

project in Re.Sy. Nos. Q02-1065/pt in Melmuri Village, Eranad Taluk,

Malappuram District, Kerala by Sri.Muhammed Ibrahim – Judgment

dated 09.02.2021 in WP(C) No.3314 of 2021 - Revalidation of EC (File

No.395/EC6/2021/SEIAA) – reg : -

Decision: The proponent and the RQP were present. The RQP made the presentation. The

Committee entrusted Dr. P.S. Easa and Dr. S. Sreekumar with the Field Inspection.

Environmental Clearance for the quarry project in Sy. Nos. 182/1,

184/1, 185/2 and 186/5 at Nediyirippu Village & Panchayat,

Kondotty Taluk, Malappuram District, Kerala by Shri.K.M.

Koyamu, Managing Partner, M/s.Chirayil Granite Industries –

Judgment dated 03.02.2021 in WP(C) No.2793 of 2021 -

Revalidation of EC (File No.814/SEIAA/EC1/2485/2015) – reg : -

Decision: The proponent and the RQP were present. The RQP made the presentation. The

Committee entrusted Dr. P.S. Easa and Dr. S. Sreekumar with the Field Inspection.

Environmental Clearance issued to M/s. Darkstone Land Developers

Pvt.Ltd in Sy. No. 1/1 (pt) of Ottappalam Village, Ottappalam

Taluk, Palakkad District, Kerala by Sri. Shamsudheen. M.P –

Crl.M.C. No. 1232 of 2021- Interim Report furnished-reg (File No.

705/SEIAA/KL/5657/2014)

Decision: The Committee discussed the issue. The Committee endorsed the Interim

Report prepared by Dr. R.Ajayakumar Varma and Dr.A.V.Raghu

in this regard and ratified the action of the Chairman, SEAC in

sending the Interim Report to the SEIAA due to legal emergency.

AGENDA 1

1. SIA/KL/MIN/129838/2019,1771/EC6/2020/SEIAA

Environmental Clearance for the Granite Building Stone Quarryproject in

Survey Nos. 8/2, 8/2-18 in Vettilappara Village, Eranad Taluk,Malappuram

District, Kerala for an area of 1.2914 Ha by Sri.P.P.Veeran M/SCherupara

Granites.

Item No.122.29

Item No.122.30

Item No.122.31

Page 8: Presentation - SEIAA-KERALA

Decision: The proponent and the RQP were present. The RQP made the presentation. The

Committee entrusted Dr. P.S. Easa & Dr. S. Sreekumar with the Field Inspection and also

directed the proponent to submit the following additional documents /details:

a. Detailed Project report on the Revised EMP incorporating the specific CER activities in

physical terms to be undertaken by the proponent in consultation with the stakeholders as

stipulated in the OM No.22- 65/2017-IA.III dated 30/09/2020 and OM No. 22-65/2017-

IA.III dated 20/10/2020 of the MoEF&CC, GOI instead of allocation of funds under

CER. The CER activities incorporated in the EMP should be undertaken during the first

two years of validity period of the EC so as to ensure that the maintenance of the

interventions undertaken can be done by the proponent during the remaining validity

period of the EC.

b. Revised biodiversity assessment with quantification separately for the core and buffer

areas.

c. Biodiversity summary in tabular form

d. A Recent survey map showing distance to residential/public buildings, inhabited sites,

canals, roads, electric lines, mobile towers, religious places etc., within 200 m. radius of

the lease boundary certified by the Village Officer.

e. Detailed water level measurement data of nearby open wells with geo coordinates.

f. Revised tree cutting details

g. Recent cluster certificate

h. Details of project cost.

i. Recent test results on air, water and other parameters.

j. Details of ESA.

2. SIA/KL/MIN/132766/2019,1718/EC6/2020/SEIAA

Environmental Clearance for the Granite Building Stone Quarry project in Re-

survey no. 337/1 in Morayur village, Kondotty

Taluk,MalappuramDistrict,Keralaforanareaof0.6301HabyM.KunhiMuhammed

.

Decision: The proponent and the RQP were present. The RQP made the presentation. The

Committee directed the proponent to submit the following additional documents /details:

a. Modification of OB dumping site

b. Modified Project Cost by including the quarry road

c. A Recent survey map showing distance to residential/public buildings, inhabited sites,

canals, roads, electric lines, mobile towers, religious places etc., within 200 m. radius of

the lease boundary certified by the Village Officer.

d. Garland drainage to be done

e. Geo-Coordinates of observation wells

f. Contour map of the project area

g. 500m. Land use/ Land cover map with details such as building, drains, wells etc.

h. Detailed Project Report on the Revised EMP incorporating the specific CER activities in

Page 9: Presentation - SEIAA-KERALA

physical terms to be undertaken by the proponent in consultation with the stakeholders

as stipulated in the OM No.22- 65/2017-IA.III dated 30/09/2020 and OM No. 22-

65/2017-IA.III dated 20/10/2020 of the MoEF&CC, GOI instead of allocation of funds

under CER. The CER activities incorporated in the EMP should be undertaken during

the first two years of validity period of the EC so as to ensure that the maintenance of the

interventions undertaken can be done by the proponent during the remaining validity

period of the EC.

i. Revised biodiversity assessment with quantification separately for the core and buffer

areas.

j. Biodiversity summary in tabular form

k. Detailed water level measurement data of nearby open wells with geo coordinates.

l. Form 1M

m. Recent cluster Certificate

n. Details of ESA

3. SIA/KL/MIN/134153/2019,1797/EC6/2020/SEIAA

Application for Environmental Clearance for the Granite Building Stone

Quarry project in Sy No-276/1 in Oorakam village, Thirurangadi Taluk,

MalappuramDistrict,Keralaforanareaof0.7874HabyShri.K.P.Muhammed

Basheer

Decision: The proponent and the RQP were present. The RQP made the presentation. The

Committee directed the proponent to submit the following additional documents /details:

a. Compensatory Afforestation Plan

b. Detailed Project Report on the Revised EMP incorporating the specific CER activities in

physical terms to be undertaken by the proponent in consultation with the stakeholders as

stipulated in the OM No.22- 65/2017-IA.III dated 30/09/2020 and OM No. 22-65/2017-

IA.III dated 20/10/2020 of the MoEF&CC, GOI instead of allocation of funds under

CER. The CER activities incorporated in the EMP should be undertaken during the first

two years of validity period of the EC so as to ensure that the maintenance of the

interventions undertaken can be done by the proponent during the remaining validity

period of the EC.

c. Revised biodiversity assessment with quantification separately for the core and buffer

areas.

d. Biodiversity summary in tabular form

e. A Recent survey map showing distance to residential/public buildings, inhabited sites,

canals, roads, electric lines, mobile towers, religious places etc., within 200 m. radius of

the lease boundary certified by the Village Officer.

f. Detailed water level measurement data of nearby open wells with geo coordinates

4. SIA/KL/MIN/141476/2020,1660/EC6/2020/SEIAA

EnvironmentalClearanceforthebuildingstonequarryprojectinSurveyNo.

Page 10: Presentation - SEIAA-KERALA

104/1ofKuruvavillage,PerinthalmannaTaluk,MalappuramDistrict,Keralaforanar

ea of0.2958HabyShri.SiddiqueAparambil

Decision: The proponent and the RQP were present. The RQP made the presentation. The

Committee entrusted Dr. P.S. Easa & Dr. S. Sreekumar with the Field Inspection and also

directed the proponent to submit the following additional documents /details:

a. Detailed Project Report on the Revised EMP incorporating the specific CER activities in

physical terms to be undertaken by the proponent in consultation with the stakeholders as

stipulated in the OM No.22- 65/2017-IA.III dated 30/09/2020 and OM No. 22-65/2017-

IA.III dated 20/10/2020 of the MoEF&CC, GOI instead of allocation of funds under

CER. The CER activities incorporated in the EMP should be undertaken during the first

two years of validity period of the EC so as to ensure that the maintenance of the

interventions undertaken can be done by the proponent during the remaining validity

period of the EC.

b. Revised biodiversity assessment with quantification separately for the core and buffer

areas.

c. A Recent survey map showing distance to residential/public buildings, inhabited sites,

canals, roads, electric lines, mobile towers, religious places etc., within 200 m. radius of

the lease boundary certified by the Village Officer.

d. Biodiversity summary in tabular form

e. Water level data of nearby open wells with geo coordinates

f. Revised project cost

g. 500m Land use and Land cover map

5. SIA/KL/MIN/142599/2020,1773/EC6/2020/SEIAA

Environmental Clearance for the Building stone quarry project in Survey No.

161/2, 161/3, 161/4, 145/1 in Urangattiri Village, Ernad Taluk, Malappuram

District, Kerala for an extent of 0.8949Ha. by Shri. Mithun.K

Decision: The proponent and the RQP were present. The RQP made the presentation. The

Committee entrusted Dr. P.S. Easa & Dr. S. Sreekumar with the Field Inspectionand also directed

the proponent to submit the following additional documents /details:

a. Detailed Project Report on the Revised EMP incorporating the specific CER activities in

physical terms to be undertaken by the proponent in consultation with the stakeholders as

stipulated in the OM No.22- 65/2017-IA.III dated 30/09/2020 and OM No. 22-65/2017-

IA.III dated 20/10/2020 of the MoEF&CC, GOI instead of allocation of funds under

CER. The CER activities incorporated in the EMP should be undertaken during the first

two years of validity period of the EC so as to ensure that the maintenance of the

interventions undertaken can be done by the proponent during the remaining validity

period of the EC.

b. Revised biodiversity assessment with quantification separately for the core and buffer

areas.

Page 11: Presentation - SEIAA-KERALA

c. A Recent survey map showing distance to residential/public buildings, inhabited sites,

canals, roads, electric lines, mobile towers, religious places etc., within 200 m. radius of

the lease boundary certified by the Village Officer.

d. Biodiversity summary in tabular form

e. Detailed water level measurement data of nearby open wells with geo coordinates.

f. Tree cutting and planting details

g. Greenbelt development plan

h. Recent cluster certificate

i. Area demarcation required

j. Lab test details with NABL Accreditation details

k. District Survey Report

l. Details of ESA

m. Approved mining plan and drainage plan

n. Recent hazard zonation map

6. SIA/KL/MIN/145476/2020,1705/EC6/2020/SEIAA

Environmental Clearance for the Laterite (Building stone) Quarry project in

Re-Survey No. BL 11 244/3-3, 244/3-4, 244/3-5 of Pallikkal Village, Ernad

Taluk, Malappuram District, Kerala for an area of 0.1862 Ha by Vijosh P M

Decision: The proponent and the RQP were present. The RQP made the presentation. The

Committee directed the proponent to submit the following additional documents /details:

a. A Recent survey map showing distance to residential/public buildings, inhabited sites,

canals, roads, electric lines, mobile towers, religious places etc., within 200 m. radius of

the lease boundary certified by the Village Officer.

b. Lithological section with depth details indicating the profile of the Laterite.

c. Detailed Project Report on the Revised EMP incorporating the specific CER activities in

physical terms to be undertaken by the proponent in consultation with the stakeholders

as stipulated in the OM No.22- 65/2017-IA.III dated 30/09/2020 and OM No. 22-

65/2017-IA.III dated 20/10/2020 of the MoEF&CC, GOI instead of allocation of funds

under CER. The CER activities incorporated in the EMP should be undertaken during

the first two years of validity period of the EC so as to ensure that the maintenance of the

interventions undertaken can be done by the proponent during the remaining validity

period of the EC.

d. Biodiversity summary in tabular form

e. Detailed water level measurement data of nearby open wells with geo coordinates.

7. SIA/KL/MIN/148469/2020,1710/EC6/2020/SEIAA

Environmental Clearance for the Laterite (Building stone) Quarry project in

Re-

SurveyNo.185/1ofKattipparuthyVillage,TirurTaluk,MalappuramDistrict,Keralaforane

Page 12: Presentation - SEIAA-KERALA

xtentof0.0971HabyShri. Ali,N

Decision: The proponent and the RQP were present. The RQP made the presentation. The

Committee entrusted Dr. P.S. Easa & Dr. S. Sreekumar with the Field Inspection and also

directed the proponent to submit the following additional documents /details:

a. Lithological section indicating the profile of the Laterite.

b. Detailed Project Report on the Revised EMP incorporating the specific CER activities in

physical terms to be undertaken by the proponent in consultation with the stakeholders as

stipulated in the OM No.22- 65/2017-IA.III dated 30/09/2020 and OM No. 22-65/2017-

IA.III dated 20/10/2020 of the MoEF&CC, GOI instead of allocation of funds under

CER. The CER activities incorporated in the EMP should be undertaken during the first

two years of validity period of the EC so as to ensure that the maintenance of the

interventions undertaken can be done by the proponent during the remaining validity

period of the EC.

c. A Recent survey map showing distance to residential/public buildings, inhabited sites,

canals, roads, electric lines, mobile towers, religious places etc., within 200 m. radius of

the lease boundary certified by the Village Officer.

d. Biodiversity summary in tabular form

e. Detailed water level measurement data of nearby open wells with geo coordinates.

8. SIA/KL/MIN/148500/2020,1711/EC6/2020/SEIAA

Environmental Clearance for the Laterite (Building stone) Quarry project in

Re-S u r v e y N o. 27 of Athavanad V il l a g e , Tirur Taluk,

MalappuramDistrict,Keralaforanextentof0.1940HabyAhammed Nasar M

Decision: The proponent and the RQP were present. The RQP made the presentation. The

Committee directed the proponent to submit the following additional documents /details:

a. A Recent survey map showing distance to residential/public buildings, inhabited sites,

canals, roads, electric lines, mobile towers, religious places etc., within 200 m. radius of

the lease boundary certified by the Village Officer.

b. Lithological section indicating the profile of the Laterite.

c. Detailed Project Report on the Revised EMP incorporating the specific CER activities in

physical terms to be undertaken by the proponent in consultation with the stakeholders

as stipulated in the OM No.22- 65/2017-IA.III dated 30/09/2020 and OM No. 22-

65/2017-IA.III dated 20/10/2020 of the MoEF&CC, GOI instead of allocation of funds

under CER. The CER activities incorporated in the EMP should be undertaken during

the first two years of validity period of the EC so as to ensure that the maintenance of the

interventions undertaken can be done by the proponent during the remaining validity

period of the EC.

d. Revised biodiversity assessment with quantification separately for the core and buffer

areas.

e. A Recent survey map showing distance to residential/public buildings, inhabited sites,

canals, roads, electric lines, mobile towers, religious places etc., within 200 m. radius of

Page 13: Presentation - SEIAA-KERALA

the lease boundary certified by the Village Officer.

f. Biodiversity summary in tabular form

g. Detailed water level measurement data of nearby open wells with geo coordinates.

9. SIA/KL/MIN/149363/2020,1769/EC6/2020/SEIAA

Environmental Clearance for the Building stone quarry project of Sri.

SajanManioveranextentof0.9709Ha.inSy.No.2398ofPeechiVillage,ThrissurTaluk,Thriss

urDistrict,Kerala

Decision: The proponent and the RQP were present. The RQP made the presentation. The

Committee entrusted Dr. P.S. Easa & Dr. S. Sreekumar with the Field Inspection and also

directed the proponent to submit the following additional documents /details:

a. Detailed Project Report on the Revised EMP incorporating the specific CER activities in

physical terms to be undertaken by the proponent in consultation with the stakeholders as

stipulated in the OM No.22- 65/2017-IA.III dated 30/09/2020 and OM No. 22-65/2017-

IA.III dated 20/10/2020 of the MoEF&CC, GOI instead of allocation of funds under

CER. The CER activities incorporated in the EMP should be undertaken during the first

two years of validity period of the EC so as to ensure that the maintenance of the

interventions undertaken can be done by the proponent during the remaining validity

period of the EC.

b. Revised biodiversity assessment with quantification separately for the core and buffer

areas.

c. A Recent survey map showing distance to residential/public buildings, inhabited sites,

canals, roads, electric lines, mobile towers, religious places etc., within 200 m. radius of

the lease boundary certified by the Village Officer.

d. Biodiversity summary in tabular form

e. Detailed water level measurement data of nearby open wells with geo coordinates

f. Site- specific Garland & Drainage plan

10. SIA/KL/MIN/151675/2020,1709/EC6/2020/SEIAA

Environmental Clearance for the Building stone quarry project in Re- Sy. Nos.

26/9, 26/13, 26/10 & 26/11 of Wadakkanchery Village, Thalappilly Taluk,

Thrissur District, Kerala for an extent of 1.937 Ha.byM/s. Peacock Rock

Products.

Decision: The proponent and the RQP were present. The RQP made the presentation. The

Committee directed the proponent to submit the following additional documents /details:

a. Drainage Plan

b. Compensatory afforestation plan with native Sp. Existed in the quarry site.

c. Proof of the application submitted for the permission from the National Board for

Wildlife.

d. Detailed Project Report on the Revised EMP incorporating the specific CER activities in

physical terms to be undertaken by the proponent in consultation with the stakeholders as

stipulated in the OM No.22- 65/2017-IA.III dated 30/09/2020 and OM No. 22-65/2017-

IA.III dated 20/10/2020 of the MoEF&CC, GOI instead of allocation of funds under

Page 14: Presentation - SEIAA-KERALA

CER. The CER activities incorporated in the EMP should be undertaken during the first

two years of validity period of the EC so as to ensure that the maintenance of the

interventions undertaken can be done by the proponent during the remaining validity

period of the EC.

e. Revised biodiversity assessment with quantification separately for the core and buffer

areas.

f. A Recent survey map showing distance to residential/public buildings, inhabited sites,

canals, roads, electric lines, mobile towers, religious places etc., within 200 m. radius of

the lease boundary certified by the Village Officer.

g. Monitoring well details

h. Compensatory afforestation plan

i. Biodiversity summary in tabular form

j. Detailed water level measurement data of nearby open wells with geo coordinates

11. SIA/KL/MIN/152637/2020,1706/EC6/2020/SEIAA

Environmental Clearance for the Laterite Quarry project in Re-Survey Nos.

57/12, 57/13 & 57/1 of Valambur

Village,PerinthalmannaTaluk,MalappuramDistrict,Keralafor

anextentof0.969675HabyMohammedFaisalP

Decision: The proponent and the RQP were present. The RQP made the presentation. The

Committee entrusted Dr. S. Sreekumar & Shri. G. Sankar with the Field Inspection and also

directed the proponent to submit the following additional documents /details:

a. Lithological section indicating the profile of the Laterite.

b. Detailed Project Report on the Revised EMP incorporating the specific CER activities in

physical terms to be undertaken by the proponent in consultation with the stakeholders as

stipulated in the OM No.22- 65/2017-IA.III dated 30/09/2020 and OM No. 22-65/2017-

IA.III dated 20/10/2020 of the MoEF&CC, GOI instead of allocation of funds under

CER. The CER activities incorporated in the EMP should be undertaken during the first

two years of validity period of the EC so as to ensure that the maintenance of the

interventions undertaken can be done by the proponent during the remaining validity

period of the EC.

c. Revised biodiversity assessment with quantification separately for the core and buffer

areas.

d. A Recent survey map showing distance to residential/public buildings, inhabited sites,

canals, roads, electric lines, mobile towers, religious places etc., within 200 m. radius of

the lease boundary certified by the Village Officer.

e. Biodiversity summary in tabular form

f. Detailed water level measurement data of nearby open wells with geo coordinates.

12. SIA/KL/MIN/152770/2020,1708/EC6/2020/SEIAA

Environmental Clearance for the Laterite (Building stone) Quarry project in Re

Sy No 228/3-1, 228/3-4, 228/3-5 of Pookkottur Village, Ernad Taluk,

Malappuram District, Kerala over an extent of 0.3886 Ha in by Shri.Abdul

Page 15: Presentation - SEIAA-KERALA

Kareem

Decision: The proponent and the RQP were present. The RQP made the presentation. The

Committee entrusted Dr. S. Sreekumar & Shri. G. Sankar with the Field Inspection and also

directed the proponent to submit the following additional documents /details:

a. Lithological section indicating the profile of the Laterite.

b. Revised project cost.

c. Detailed Project Report on the Revised EMP incorporating the specific CER activities in

physical terms to be undertaken by the proponent in consultation with the stakeholders as

stipulated in the OM No.22- 65/2017-IA.III dated 30/09/2020 and OM No. 22-65/2017-

IA.III dated 20/10/2020 of the MoEF&CC, GOI instead of allocation of funds under

CER. The CER activities incorporated in the EMP should be undertaken during the first

two years of validity period of the EC so as to ensure that the maintenance of the

interventions undertaken can be done by the proponent during the remaining validity

period of the EC.

d. Revised biodiversity assessment with quantification separately for the core and buffer

areas.

e. A Recent survey map showing distance to residential/public buildings, inhabited sites,

canals, roads, electric lines, mobile towers, religious places etc., within 200 m. radius of

the lease boundary certified by the Village Officer.

f. Biodiversity summary in tabular form

g. Detailed water level measurement data of nearby open wells with geo coordinates.

13. SIA/KL/MIN/152789/2020,1707/EC6/2020/SEIAA

Environmental Clearance for Laterite building stone quarry project in Re Sy

No-284/1, Block No.28 of Kavanur Village, Ernad Taluk, Malappuram District,

Kerala over an extent of 0.5533 Ha by of Moideen

Decision: The proponent and RQP were present. The RQP made the presentation. The

Committee entrusted Dr. S. Sreekumar & Shri. G. Sankar with the Field Inspection and also

directed the proponent to submit the following additional documents /details:

a. Lithological section indicating the profile of the Laterite.

b. Detailed Project Report on the Revised EMP incorporating the specific CER activities in

physical terms to be undertaken by the proponent in consultation with the stakeholders as

stipulated in the OM No.22- 65/2017-IA.III dated 30/09/2020 and OM No. 22-65/2017-

IA.III dated 20/10/2020 of the MoEF&CC, GOI instead of allocation of funds under

CER. The CER activities incorporated in the EMP should be undertaken during the first

two years of validity period of the EC so as to ensure that the maintenance of the

interventions undertaken can be done by the proponent during the remaining validity

period of the EC.

c. Revised biodiversity assessment with quantification separately for the core and buffer

areas.

d. A Recent survey map showing distance to residential/public buildings, inhabited sites,

Page 16: Presentation - SEIAA-KERALA

canals, roads, electric lines, mobile towers, religious places etc., within 200 m. radius of

the lease boundary certified by the Village Officer.

e. Biodiversity summary in tabular form

f. Detailed water level measurement data of nearby open wells with geo coordinates.

14. SIA/KL/MIN/156633/2020,1772/EC6/2020/SEIAA

Environmental Clearance for Laterite building stone quarry project in Sy No-

477/1-2 Vazhakkad Village, Kondotty Taluk, Malappuram District, Kerala for

an area of 0.7325Ha by Mr. Ismail. K.P

Decision: The proponent and the RQP were present. The RQP made the presentation. The

Committee entrusted Dr. S. Sreekumar & Shri. G. Sankar with the field inspection and also

directed the proponent to submit the following additional documents /details:

a. Clarification regarding the production plan

b. Detailed Project Report on the Revised EMP incorporating the specific CER activities in

physical terms to be undertaken by the proponent in consultation with the stakeholders as

stipulated in the OM No.22- 65/2017-IA.III dated 30/09/2020 and OM No. 22-65/2017-

IA.III dated 20/10/2020 of the MoEF&CC, GOI instead of allocation of funds under

CER. The CER activities incorporated in the EMP should be undertaken during the first

two years of validity period of the EC so as to ensure that the maintenance of the

interventions undertaken can be done by the proponent during the remaining validity

period of the EC.

c. Revised biodiversity assessment with quantification separately for the core and buffer

areas. c. A Recent survey map showing distance to residential/public buildings, inhabited

sites, canals, roads, electric lines, mobile towers, religious places etc., within 200 m.

radius of the lease boundary certified by the Village Officer.

d. Biodiversity summary in tabular form

e. Detailed water level measurement data of nearby open wells with geo coordinates

f. Lithological section indicating the profile of the Laterite.

15. SIA/KL/MIN/161364/2020,1765/EC6/2020/SEIAA

Environmental Clearance for Laterite building stone quarry project in Re

Survey No. 2/3-105, 2/3-102, 2/3-108, 2/3- 106& 2/3-103 of Irimbiliyam Village, Tirur

Taluk, Malappuram District, Kerala State for an extent of 0.7752Ha by Shri.Anil

Kumar

Decision: The proponent and the RQP were present. The RQP made the presentation. The

Committee entrusted Dr. S. Sreekumar & Shri. G. Sankar with the Field Inspection and also

directed the proponent to submit the following additional documents /details:

a. Detailed Project Report on the Revised EMP incorporating the specific CER activities in

physical terms to be undertaken by the proponent in consultation with the stakeholders as

stipulated in the OM No.22- 65/2017-IA.III dated 30/09/2020 and OM No. 22-65/2017-

IA.III dated 20/10/2020 of the MoEF&CC, GOI instead of allocation of funds under

Page 17: Presentation - SEIAA-KERALA

CER. The CER activities incorporated in the EMP should be undertaken during the first

two years of validity period of the EC so as to ensure that the maintenance of the

interventions undertaken can be done by the proponent during the remaining validity

period of the EC.

b. Revised biodiversity assessment with quantification separately for the core and buffer

areas.

c. A Recent survey map showing distance to residential/public buildings, inhabited sites,

canals, roads, electric lines, mobile towers, religious places etc., within 200 m. radius of

the lease boundary certified by the Village Officer.

d. Biodiversity summary in tabular form

e. Detailed water level measurement data of nearby open wells with geo coordinates

f. Details of top soil and its storage

g. Tree cutting and Greenbelt details

h. District Survey Report

i. Lithological section indicating the profile of the Laterite.

16. SIA/KL/MIN/161510/2020,1770/EC6/2020/SEIAA

Environmental Clearance for Laterite building stone quarry project in Re

Survey No. 2/3-16 & 2/1-45 of Irimbiliyam Village, Tirur taluk, Malappuram district,

Kerala State for an extent of 0.2958

Decision: The proponent and the RQP were present. The RQP made the presentation. The

Committee entrusted Dr. S. Sreekumar & Shri. G. Sankar with the Field Inspection and also

directed the proponent to submit the following additional documents /details:

a. Detailed Project Report on the Revised EMP incorporating the specific CER activities in

physical terms to be undertaken by the proponent in consultation with the stakeholders as

stipulated in the OM No.22- 65/2017-IA.III dated 30/09/2020 and OM No. 22-65/2017-

IA.III dated 20/10/2020 of the MoEF&CC, GOI instead of allocation of funds under

CER. The CER activities incorporated in the EMP should be undertaken during the first

two years of validity period of the EC so as to ensure that the maintenance of the

interventions undertaken can be done by the proponent during the remaining validity

period of the EC.

b. Revised biodiversity assessment with quantification separately for the core and buffer

areas.

c. A Recent survey map showing distance to residential/public buildings, inhabited sites,

canals, roads, electric lines, mobile towers, religious places etc., within 200 m. radius of

the lease boundary certified by the Village Officer.

d. Biodiversity summary in tabular form

e. Detailed water level measurement data of nearby open wells with geo coordinates

f. Details of top soil and its storage

g. Tree cutting and Greenbelt details

h. District Survey Report

Page 18: Presentation - SEIAA-KERALA

i. Lithological section indicating the profile of the Laterite.

17. SIA/KL/MIN/161725/2020,1717/EC6/2020/SEIAA

Environmental Clearance for Laterite building stone quarry project in Re-

Survey Nos. 382/4-15, 382/5-14 of Moorkkanad Village, Perintalmanna Taluk,

Malappuram District, Kerala for an extent of 0.4858 Ha by Sri.Aneesh

Ambalakath

Decision:The proponent and the RQP were present. The RQP made the presentation. The

Committee entrusted Dr. S. Sreekumar & Dr .A. V. Raghu with the Field Inspection and also

directed the proponent to submit the following additional documents /details:

a. Detailed Project Report on the Revised EMP incorporating the specific CER activities in

physical terms to be undertaken by the proponent in consultation with the stakeholders as

stipulated in the OM No.22- 65/2017-IA.III dated 30/09/2020 and OM No. 22-65/2017-

IA.III dated 20/10/2020 of the MoEF&CC, GOI instead of allocation of funds under

CER. The CER activities incorporated in the EMP should be undertaken during the first

two years of validity period of the EC so as to ensure that the maintenance of the

interventions undertaken can be done by the proponent during the remaining validity

period of the EC.

b. Revised biodiversity assessment with quantification separately for the core and buffer

areas.

c. A Recent survey map showing distance to residential/public buildings, inhabited sites,

canals, roads, electric lines, mobile towers, religious places etc., within 200 m. radius of

the lease boundary certified by the Village Officer.

d. Biodiversity summary in tabular form

e. Detailed water level measurement data of nearby open wells with geo coordinates.

f. Lithological section indicating the profile of the Laterite.

g. Depth of water table during pre-monsoon and post - monsoon periods

18. SIA/KL/MIN/163206/2020,1733/EC6/2020/SEIAA

Environmental Clearance for Laterite building stone quarry project in Re Sy.

No-240/A-320inMoorkkanadvillage,

PerinthalmannaTaluk,MalappuramDistrict,Keralaforanareaof0.9928HabyMr.S

ameeh

Decision: The proponent and the RQP were present. The RQP made the presentation. The

Committee entrusted Dr.S.Sreekumar & Dr.A.V.Raghu with the Field Inspection and also

directed the proponent to submit the following additional documents /details:

a. Mine Closure Plan

b. Detailed Project Report on the Revised EMP incorporating the specific CER activities in

physical terms to be undertaken by the proponent in consultation with the stakeholders as

stipulated in the OM No.22- 65/2017-IA.III dated 30/09/2020 and OM No. 22-65/2017-

IA.III dated 20/10/2020 of the MoEF&CC, GOI instead of allocation of funds under

CER. The CER activities incorporated in the EMP should be undertaken during the first

Page 19: Presentation - SEIAA-KERALA

two years of validity period of the EC so as to ensure that the maintenance of the

interventions undertaken can be done by the proponent during the remaining validity

period of the EC.

c. Revised biodiversity assessment with quantification separately for the core and buffer

areas.

d. A Recent survey map showing distance to residential/public buildings, inhabited sites,

canals, roads, electric lines, mobile towers, religious places etc., within 200 m. radius of

the lease boundary certified by the Village Officer.

e. Biodiversity summary in tabular form

f. Detailed water level measurement data of nearby open wells with geo coordinates

g. Lithological section indicating the profile of the Laterite.

19. SIA/KL/MIN/50013/2019,1318/EC2/2019/SEIAA

Environmental Clearance for the Granite Building stone quarry project in

Survey No:488 of Vettathur village, Perinthalmanna Taluk,Malappuram

District, Kerala for an extent of 7.7085 Ha by Shri. Haridasan (Complaint

received from Sri. Unniyambath Muhammed)

Decision:The proponent and the RQP were present. The RQP made the presentation. The

Committee entrusted Shri.K. Krishna Panicker & Dr. P.S. Easa with the Field Inspection and

also directed the proponent to submit the following additional documents /details:

a. Detailed Project Report on the Revised EMP incorporating the specific CER activities in

physical terms to be undertaken by the proponent in consultation with the stakeholders as

stipulated in the OM No.22- 65/2017-IA.III dated 30/09/2020 and OM No. 22-65/2017-

IA.III dated 20/10/2020 of the MoEF&CC, GOI instead of allocation of funds under

CER. The CER activities incorporated in the EMP should be undertaken during the first

two years of validity period of the EC so as to ensure that the maintenance of the

interventions undertaken can be done by the proponent during the remaining validity

period of the EC.

b. Revised biodiversity assessment with quantification separately for the core and buffer

areas.

c. A Recent survey map showing distance to residential/public buildings, inhabited sites,

canals, roads, electric lines, mobile towers, religious places etc., within 200 m. radius of

the lease boundary certified by the Village Officer.

d. Biodiversity summary in tabular form

e. Detailed water level measurement data of nearby open wells with geo coordinates.

20. SIA/KL/MIN/50538/2019,1378/EC2/2019/SEIAA

Expansion of Existing Building Stone Mine (Quarry, Minor Mineral Mining)

project of M/s Kilinakod Rock Products Pvt. Ltd. at Re-Survey Nos. 24/3

pt.,25/2, 27/1, 28/2, 28/3 of Oorakam Village, Thirurangadi Taluk, Malappuram

district. (Complaint received from Ooragam Mala Samrakshana Janakeeya

Page 20: Presentation - SEIAA-KERALA

Action Samithy & Sri.Apputti)

Decision: The proponent and the RQP were present. The RQP made the presentation. The

Committee directed the proponent to submit the following additional documents /details:

a. Compensatory afforestation plan with native Species.

b. Slope stability study details

c. Report from MoEF&CC

d. Clarification on the complaints received.

e. Detailed Project Report on the Revised EMP incorporating the specific CER activities in

physical terms to be undertaken by the proponent in consultation with the stakeholders as

stipulated in the OM No.22- 65/2017-IA.III dated 30/09/2020 and OM No. 22-65/2017-

IA.III dated 20/10/2020 of the MoEF&CC, GOI instead of allocation of funds under

CER. The CER activities incorporated in the EMP should be undertaken during the first

two years of validity period of the EC so as to ensure that the maintenance of the

interventions undertaken can be done by the proponent during the remaining validity

period of the EC.

f. Revised biodiversity assessment with quantification separately for the core and buffer

areas.

g. A Recent survey map showing distance to residential/public buildings, inhabited sites,

canals, roads, electric lines, mobile towers, religious places etc., within 200 m. radius of

the lease boundary certified by the Village Officer.

h. Biodiversity summary in tabular form

i. Afforestation plan

j. Detailed water level measurement data of nearby open wells with geo coordinates

AGENDA 2

1. SIA/KL/MIN/126475/2019,1724/EC3/2020/SEIAA

Environmental Clearance for the building stone quarry at Re-Survey No. 104/8-

1pt, 110/7pt, Block No.12 of Vengoor Village, Kunnathunad Taluk, Ernakulam

District, Kerala for an Area of0.6046Ha byMr. Tijo Lalu

Decision: The proponent and the RQP were present. The RQP made the presentation. The

Committee directed the proponent to submit the following additional documents /details:

a. Revised Drainage plan

b. Compensatory afforestation plan

c. OB dumping site

d. Detailed Project Report on the Revised EMP incorporating the specific CER activities in

physical terms to be undertaken by the proponent in consultation with the stakeholders as

stipulated in the OM No.22- 65/2017-IA.III dated 30/09/2020 and OM No. 22-65/2017-

IA.III dated 20/10/2020 of the MoEF&CC, GOI instead of allocation of funds under

CER. The CER activities incorporated in the EMP should be undertaken during the first

two years of validity period of the EC so as to ensure that the maintenance of the

interventions undertaken can be done by the proponent during the remaining validity

period of the EC.

Page 21: Presentation - SEIAA-KERALA

e. Drainage plan to be site specific with silt traps

f. Map showing OB dumping site

g. Site-specific compensatory afforestation plan

h. Details of ESA

i. Revised biodiversity assessment with quantification separately for the core and buffer

areas.

j. A Recent survey map showing distance to residential/public buildings, inhabited sites,

canals, roads, electric lines, mobile towers, religious places etc., within 200 m. radius of

the lease boundary certified by the Village Officer.

k. Biodiversity summary in tabular form

l. Detailed water level measurement data of nearby open wells with geo coordinates.

2. SIA/KL/MIN/131666/2019,1783/EC3/2020/SEIAA

Building Stone Quarry of Mr. P. V. Santhosh for an area of 0.9998 Ha 288/1-

1,288/1-2,287/2,288/3atMazhuvannoorVillage,Kunnathunadutaluk,Ernakulam

Decision: The proponent and the RQP were present. The RQP made the presentation. The

Committee entrusted Shri. K. Krishna Panicker & Dr. N. Ajithkumar with the Field Inspection

and also directed the proponent to submit the following additional documents /details:

a. Detailed Project Report on the Revised EMP incorporating the specific CER activities in

physical terms to be undertaken by the proponent in consultation with the stakeholders as

stipulated in the OM No.22- 65/2017-IA.III dated 30/09/2020 and OM No. 22-65/2017-

IA.III dated 20/10/2020 of the MoEF&CC, GOI instead of allocation of funds under

CER. The CER activities incorporated in the EMP should be undertaken during the first

two years of validity period of the EC so as to ensure that the maintenance of the

interventions undertaken can be done by the proponent during the remaining validity

period of the EC.

b. Revised biodiversity assessment with quantification separately for the core and buffer

areas.

c. A Recent survey map showing distance to residential/public buildings, inhabited sites,

canals, roads, electric lines, mobile towers, religious places etc., within 200 m. radius of

the lease boundary certified by the Village Officer.

d. Biodiversity summary in tabular form

e. Detailed water level measurement data of nearby open wells with geo coordinates

f. Recent cluster certificate

3. SIA/KL/MIN/133526/2019,1734/EC3/2020/SEIAA

Environment Clearance in respect of the Proposed Granite Building Stone

Quarry over an extent of 1.6939 Hectares in Re-Survey Nos. 223/2pt and 227/1pt

ofAlakodeVillage,ThodupuzhaTaluk,IdukkiDistrict,KeralabyMr.BinoyJose

Decision: The proponent and the RQP were present. The RQP made the presentation. The

Committee entrusted Shri. G. Sankar & Dr. N. Ajithkumar with the Field Inspection.

Page 22: Presentation - SEIAA-KERALA

4. SIA/KL/MIN/136876/2020,1687/EC3/2020/SEIAA

Granite Building Stone Quarry of Shri. Shine Mathew over an extent of 1.0336

Ha. (2.5540Acres)in BlockNo.13,Re-Sy. No. 541/2, Purappuzha Village,

Thodupuzha Taluk, Idukki District, Kerala State, India.

Decision: The proponent and RQP were present. The RQP made the presentation. The

Committee entrusted Shri. G. Sankar and Dr.N.Ajithkumar with the Field Inspection and also

directed the proponent to submit the following additional documents /details:

a. Detailed Project Report on the Revised EMP incorporating the specific CER activities in

physical terms to be undertaken by the proponent in consultation with the stakeholders as

stipulated in the OM No.22- 65/2017-IA.III dated 30/09/2020 and OM No. 22-65/2017-

IA.III dated 20/10/2020 of the MoEF&CC, GOI instead of allocation of funds under

CER. The CER activities incorporated in the EMP should be undertaken during the first

two years of validity period of the EC so as to ensure that the maintenance of the

interventions undertaken can be done by the proponent during the remaining validity

period of the EC.

b. Revised biodiversity assessment with quantification separately for the core and buffer

areas.

c. A Recent survey map showing distance to residential/public buildings, inhabited sites,

canals, roads, electric lines, mobile towers, religious places etc., within 200 m. radius of

the lease boundary certified by the Village Officer.

d. Biodiversity summary in tabular form

e. Water level data of nearby open wells with geo coordinates

f. Tree cutting & Green belt details with species specification

g. 500m Land use and Land cover map

h. Pre- feasibility Report

i. ESA details

5. SIA/KL/MIN/137503/2020,1720/EC3/2020/SEIAA

Granite Building stone quarry of “Mr.Saji Sebastian, Sy.No:

128/3Bpt,128/4pt,129/1-4pt,129/2-1pt, in Arakkuzha Village, Muvattupuzha

Taluk, Ernakulam District, Kerala

Decision: The proponent and the RQP were present. The RQP made the presentation. The

Committee directed the proponent to submit the following additional documents /details:

a. Compensatory afforestation plan

b. Tree cutting Quantitative information in Core & Buffer zone.

c. Modified CER

d. Site specific drainage map with silt traps

e. Recent cluster Certificate

f. Area demarcated for compensatory afforestation and plan

g. Detailed Project Report on the Revised EMP incorporating the specific CER activities in

physical terms to be undertaken by the proponent in consultation with the stakeholders as

stipulated in the OM No.22- 65/2017-IA.III dated 30/09/2020 and OM No. 22-65/2017-

IA.III dated 20/10/2020 of the MoEF&CC, GOI instead of allocation of funds under

Page 23: Presentation - SEIAA-KERALA

CER. The CER activities incorporated in the EMP should be undertaken during the first

two years of validity period of the EC so as to ensure that the maintenance of the

interventions undertaken can be done by the proponent during the remaining validity

period of the EC.

h. Revised biodiversity assessment with quantification separately for the core and buffer

areas.

i. A Recent survey map showing distance to residential/public buildings, inhabited sites,

canals, roads, electric lines, mobile towers, religious places etc., within 200 m. radius of

the lease boundary certified by the Village Officer.

j. Biodiversity summary in tabular form

k. Detailed water level measurement data of nearby open wells with geo coordinates.

6. SIA/KL/MIN/139395/2020,1703/EC3/2020/SEIAA

Granite Building Stone Quarry of M/s. St. Augustine‟s Granites” over an extent

of 3.6352 Ha. (8.9825 Acres) Re-Sy. Block No. 28, Re-Sy. Nos. 101/3, 102/4-2,

102/5, 102/5-1, 102/6, 102/7, 102/8, 179/1, 179/1-1, 179/3-1, 179/3-2, 179/3-3,

Ramapuram Village, Meenachil Taluk, Kottayam District, Kerala

Decision: The proponent and the RQP were present. The RQP made the presentation. The

Committee directed the proponent to submit the following additional documents /details:

a. Recent Cluster Certificate

b. Tree cutting Quantitative information in Core & Buffer zone.

c. Bore well details

d. Detailed Project Report on the Revised EMP incorporating the specific CER activities in

physical terms to be undertaken by the proponent in consultation with the stakeholders as

stipulated in the OM No.22- 65/2017-IA.III dated 30/09/2020 and OM No. 22-65/2017-

IA.III dated 20/10/2020 of the MoEF&CC, GOI instead of allocation of funds under

CER. The CER activities incorporated in the EMP should be undertaken during the first

two years of validity period of the EC so as to ensure that the maintenance of the

interventions undertaken can be done by the proponent during the remaining validity

period of the EC.

e. Revised biodiversity assessment with quantification separately for the core and buffer

areas.

f. A Recent survey map showing distance to residential/public buildings, inhabited sites,

canals, roads, electric lines, mobile towers, religious places etc., within 200 m. radius of

the lease boundary certified by the Village Officer.

g. Biodiversity summary in tabular form

h. Detailed water level measurement data of nearby open wells with geo coordinates

i. Proof of the application submitted for the permission from the National Board for

Wildlife

j. Recent cluster certificate

7. SIA/KL/MIN/143147/2020,1755/EC3/2020/SEIAA

Granite Building Stone Quarry at Survey No. 73/1B, 73/2B of Muvattupuzha

Village, Muvattupuzha Taluk, Ernakulam, Kerala over an extent of 0.7091 Ha

of Mr. Jiji P Ulahannan

Page 24: Presentation - SEIAA-KERALA

Decision: The proponent and the RQP were present. The RQP made the presentation. The

Committee directed the proponent to submit the following additional documents /details:

a. Latest cluster certificate

b. Detailed Project Report on the Revised EMP incorporating the specific CER activities in

physical terms to be undertaken by the proponent in consultation with the stakeholders as

stipulated in the OM No.22- 65/2017-IA.III dated 30/09/2020 and OM No. 22-65/2017-

IA.III dated 20/10/2020 of the MoEF&CC, GOI instead of allocation of funds under

CER. The CER activities incorporated in the EMP should be undertaken during the first

two years of validity period of the EC so as to ensure that the maintenance of the

interventions undertaken can be done by the proponent during the remaining validity

period of the EC.

c. Revised biodiversity assessment with quantification separately for the core and buffer

areas.

d. A Recent survey map showing distance to residential/public buildings, inhabited sites,

canals, roads, electric lines, mobile towers, religious places etc., within 200 m. radius of

the lease boundary certified by the Village Officer.

e. Biodiversity summary in tabular form

f. Detailed water level measurement data of nearby open wells with geo coordinates.

g. Tree cutting and planting details

h. Recent cluster certificate

8. SIA/KL/MIN/144310/2020,1725/EC2/2020/SEIAA

Environmental Clearance for Building Stone quarry project in Sy. No- 428/pt of

Thayannur Village, Vellarikund Taluk, Kasaragod District of Kerala for an

extent of 0.5267 Ha by Mr .Rajan V.V

Decision: The proponent and the RQP were present. The RQP made the presentation. The

Committee directed the proponent to submit the following additional documents /details:

a. Compensatory afforestation

b. Revision of EMP cost

c. Drainage map should be redrawn separating buffer and garland canal

d. Hazard zonation map

e. Recent Cluster Certificate.

f. Detailed Project report on the Revised EMP incorporating the specific CER activities in

physical terms to be undertaken by the proponent in consultation with the stakeholders as

stipulated in the OM No.22- 65/2017-IA.III dated 30/09/2020 and OM No. 22-65/2017-

IA.III dated 20/10/2020 of the MoEF&CC, GOI instead of allocation of funds under

CER. The CER activities incorporated in the EMP should be undertaken during the first

two years of validity period of the EC so as to ensure that the maintenance of the

interventions undertaken can be done by the proponent during the remaining validity

period of the EC.

g. Revised biodiversity assessment with quantification separately for the core and buffer

areas.

h. A Recent survey map showing distance to residential/public buildings, inhabited sites,

canals, roads, electric lines, mobile towers, religious places etc., within 200 m. radius of

the lease boundary certified by the Village Officer.

i. Afforestation plan

Page 25: Presentation - SEIAA-KERALA

j. Biodiversity summary in tabular form

k. Detailed water level measurement data of nearby open wells with geo coordinates.

9. SIA/KL/MIN/146311/2020,1712/EC3/2020/SEIAA

Environmental Clearance for the building stone quarry at Survey

No.66/1,66/2A,66/2A,66/2B,128/2A,128/2B3,128/2B2,128/3A,128/3B2,of

ArakkuzhaVillage, Muvattupuzha Taluk, Ernakulam District, Kerala for an

Area of 1.7634 Ha by Saji Sebastian.

Decision: The proponent and the RQP were present. The RQP made the presentation. The

Committee directed the proponent to submit the following additional documents /details:

a. Biodiversity summary in tabular form

b. Tree cutting details

c. Recent cluster Certificate

d. Detailed Project Report on the Revised EMP incorporating the specific CER activities in

physical terms to be undertaken by the proponent in consultation with the stakeholders as

stipulated in the OM No.22- 65/2017-IA.III dated 30/09/2020 and OM No. 22-65/2017-

IA.III dated 20/10/2020 of the MoEF&CC, GOI instead of allocation of funds under

CER. The CER activities incorporated in the EMP should be undertaken during the first

two years of validity period of the EC so as to ensure that the maintenance of the

interventions undertaken can be done by the proponent during the remaining validity

period of the EC.

e. Revised biodiversity assessment with quantification separately for the core and buffer

areas.

f. A Recent survey map showing distance to residential/public buildings, inhabited sites,

canals, roads, electric lines, mobile towers, religious places etc., within 200 m. radius of

the lease boundary certified by the Village Officer.

g. Detailed water level measurement data of nearby open wells with geo coordinates.

10. SIA/KL/MIN/151402/2020,1732/EC3/2020/SEIAA

Environment Clearance for Granite Building Stone Quarry over an extent of

1.5608 Hectares in situated at Sy.No: 219/1,219/2,219/3 in Manimala Village,

Kanjirappally Taluk, Kottayam District, Kerala State by Mr. Suraj Thomas,

Managing Partner, M/S. Seven Stars Granites

Decision: The proponent and the RQP were present. The RQP made the presentation. The

Committee directed the proponent to submit the following additional documents /details:

a. Tree cutting details

b. Detailed Project Report on the Revised EMP incorporating the specific CER activities in

physical terms to be undertaken by the proponent in consultation with the stakeholders as

stipulated in the OM No.22- 65/2017-IA.III dated 30/09/2020 and OM No. 22-65/2017-

IA.III dated 20/10/2020 of the MoEF&CC, GOI instead of allocation of funds under

CER. The CER activities incorporated in the EMP should be undertaken during the first

two years of validity period of the EC so as to ensure that the maintenance of the

interventions undertaken can be done by the proponent during the remaining validity

period of the EC.

c. Revised biodiversity assessment with quantification separately for the core and buffer

areas.

Page 26: Presentation - SEIAA-KERALA

d. A Recent survey map showing distance to residential/public buildings, inhabited sites,

canals, roads, electric lines, mobile towers, religious places etc., within 200 m. radius of

the lease boundary certified by the Village Officer.

e. Biodiversity summary in tabular form

f. Detailed water level measurement data of nearby open wells with geo coordinates.

g. ESA Details

h. Overflow channel of garland drainage is to be connected to natural drain.

i. OB site is to be shifted to an appropriate place

11. SIA/KL/MIN/160178/2020,1798/EC6/2020/SEIAA

Environment Clearance for Granite Building Stone Quarry in Re Survey Nos.

365/1-7, 365/1-4, 365/1- 5,365/1-3,365/3,365/1-2 & 365/2 in Kavanur Village,

Ernad Taluk, Malappuram District, Keralaover an extent of 1.7830 Ha

Decision: The proponent and the RQP were present. The RQP made the presentation. The

Committee directed the proponent to submit the following additional documents /details:

a. Detailed Project Report on the Revised EMP incorporating the specific CER activities in

physical terms to be undertaken by the proponent in consultation with the stakeholders as

stipulated in the OM No.22- 65/2017-IA.III dated 30/09/2020 and OM No. 22-65/2017-

IA.III dated 20/10/2020 of the MoEF&CC, GOI instead of allocation of funds under

CER. The CER activities incorporated in the EMP should be undertaken during the first

two years of validity period of the EC so as to ensure that the maintenance of the

interventions undertaken can be done by the proponent during the remaining validity

period of the EC.

b. Revised biodiversity assessment with quantification separately for the core and buffer

areas.

c. A Recent survey map showing distance to residential/public buildings, inhabited sites,

canals, roads, electric lines, mobile towers, religious places etc., within 200 m. radius of

the lease boundary certified by the Village Officer.

d. Biodiversity summary in tabular form e. Water level data of nearby open wells with geo

coordinates

e. Greenbelt plan

f. 500m Land use & Land cover map

12. SIA/KL/MIN/163594/2020,1756/EC3/2020/SEIAA

Granite Building Stone Quarry of Mr. Dineesh Vijayan at Re. Sy. No. 140/2,

140/2-1, 140/2-1-1 of Vallichira Village, Meenachil Taluk, Kottayam District of

Kerala for an extent of 0.7137 Ha

Decision: The proponent and the RQP were present. The RQP made the presentation. The

Committee directed the proponent to submit the following additional documents /details:

a. Compensatory afforestation with native Sp.

b. Tree cutting details

c. Detailed Project Report on the Revised EMP incorporating the specific CER activities in

physical terms to be undertaken by the proponent in consultation with the stakeholders as

stipulated in the OM No.22- 65/2017-IA.III dated 30/09/2020 and OM No. 22-65/2017-

Page 27: Presentation - SEIAA-KERALA

IA.III dated 20/10/2020 of the MoEF&CC, GOI instead of allocation of funds under

CER. The CER activities incorporated in the EMP should be undertaken during the first

two years of validity period of the EC so as to ensure that the maintenance of the

interventions undertaken can be done by the proponent during the remaining validity

period of the EC.

d. Revised biodiversity assessment with quantification separately for the core and buffer

areas.

e. A Recent survey map showing distance to residential/public buildings, inhabited sites,

canals, roads, electric lines, mobile towers, religious places etc., within 200 m. radius of

the lease boundary certified by the Village Officer.

f. Biodiversity summary in tabular form

g. Detailed water level measurement data of nearby open wells with geo coordinates

13. SIA/KL/MIN/164009/2020,1372/EC2/2019/SEIAA

Environmental Clearance Building Stone Mine Quarry Project of Mr.Rajan

Thomas at Re Survey Nos. 205/3, 205/5, 199/3, 199/8, 199/7, 199/7-1, 199/9,

199/6-1, 198/1, 198/2, 197/1, 198/5, 198/5-6, 198/4, 207/1, 198/3, 206/2, 206, 206/4,

206/1, 206/3 of Kanjirappally Village & Panchayat, Kanjirappally Taluk,

Kottayam District, Kerala for an area of 4.9231 Ha

Decision: The proponent and the RQP were present. The RQP made the presentation. The

Committee entrusted Shri. K. Krishna panicker & Dr. N. Ajithkumar with the Field Inspection

and also directed the proponent to submit the following additional documents /details:

a. Revised buffer area plan

b. Site- specific drainage plan

c. Specific plan for reuse of water

d. Water quality assessment and maintenance

e. Sediments test report & Source of minerals

f. Solution for biological pollution of water

g. Production revision

h. Compensatory afforestation plan

i. Production plan of endemic plants.

j. Detailed Project Report on the Revised EMP incorporating the specific CER activities in

physical terms to be undertaken by the proponent in consultation with the stakeholders as

stipulated in the OM No.22- 65/2017-IA.III dated 30/09/2020 and OM No. 22-65/2017-

IA.III dated 20/10/2020 of the MoEF&CC, GOI instead of allocation of funds under

CER. The CER activities incorporated in the EMP should be undertaken during the first

two years of validity period of the EC so as to ensure that the maintenance of the

interventions undertaken can be done by the proponent during the remaining validity

period of the EC.

14. SIA/KL/MIN/164222/2020,1757/EC3/2020/SEIAA

Environmental Clearance for the building stone quarry at Re Survey

No.171/8,of Airapuram Village, Kunnathunad Taluk, Ernakulam District,

Kerala for an Area of 0.9995 Ha. By N S Ganesh, Managing Partner, M/S

ESSGEE Trading and infrastructure

Decision: The proponent and the RQP were present. The RQP made the presentation. The

Page 28: Presentation - SEIAA-KERALA

Committee directed the proponent to submit the following additional documents /details:

a. Recent cluster Certificate

b. Tree cutting details

c. Detailed Project Report on the Revised EMP incorporating the specific CER activities in

physical terms to be undertaken by the proponent in consultation with the stakeholders as

stipulated in the OM No.22- 65/2017-IA.III dated 30/09/2020 and OM No. 22-65/2017-

IA.III dated 20/10/2020 of the MoEF&CC, GOI instead of allocation of funds under

CER. The CER activities incorporated in the EMP should be undertaken during the first

two years of validity period of the EC so as to ensure that the maintenance of the

interventions undertaken can be done by the proponent during the remaining validity

period of the EC.

d. Details of monitored wells

e. Revised biodiversity assessment with quantification separately for the core and buffer

areas.

f. A Recent survey map showing distance to residential/public buildings, inhabited sites,

canals, roads, electric lines, mobile towers, religious places etc., within 200 m. radius of

the lease boundary certified by the Village Officer.

g. Biodiversity summary in tabular form

h. Detailed water level measurement data of nearby open wells with geo coordinates

15. SIA/KL/MIN/166510/2020,1811/EC3/2020/SEIAA

Building Stone Mine (Quarry, Minor Mineral Mining) project of M/s

Chattupara Granites Private Limited at Survey Nos.734/1B-32, 734/1B-34-3,

734/1B-34-4 of Kalloorkkad Village, Muvattupuzha Taluk, Ernakulam District,

Kerala in an area of 0.9700 hectares.

Decision: The proponent and the RQP were present. The RQP made the presentation. The

Committee entrusted Shri. K. Krishna Panicker and Dr. N. Ajithkumar for Field Inspection

and also directed the proponent to submit the following documents/details:

a. Proposal for biodiversity restoration for butterfly attraction should be site specific.

b. Workout maximum creditable flood accident potential.

c. Modified Form1M considering the changes in the nearest houses

d. Detailed Project Report on the Revised EMP incorporating the specific CER activities in

physical terms to be undertaken by the proponent in consultation with the stakeholders as

stipulated in the OM No.22- 65/2017-IA.III dated 30/09/2020 and OM No. 22-65/2017-

IA.III dated 20/10/2020 of the MoEF&CC, GOI instead of allocation of funds under

CER. The CER activities incorporated in the EMP should be undertaken during the first

two years of validity period of the EC so as to ensure that the maintenance of the

interventions undertaken can be done by the proponent during the remaining validity

period of the EC.

16. SIA/KL/MIN/169050/2020,1785/EC3/2020/SEIAA

Environmental Clearance for Ordinary Earth Mining Project of Mrs.Anu J

Kadavan, over an extent of 0.5685 Ha in Re Sy No-406/2-3-2 of Vazhakulam

Village, Kunnathunad Taluk, Ernakulam District, Kerala

Page 29: Presentation - SEIAA-KERALA

Decision: The proponent and the RQP were present. The RQP made the presentation. The

Committee entrusted Shri. K. Krishna Panicker and Dr. N. Ajithkumar with the Field

Inspectionand also directed the proponent to submit the following documents/details:

a. Quantity should be specified in demand letter

b. Recent demand letter from the end user.

17. SIA/KL/MIN/174851/2020,1800/EC6/2020/SEIAA

Application for Environmental Clearance for the Laterite building stone quarry

project in ReSurvey No. 477/1-2 of Vazhakkad village, Kondotty taluk,

Malappuram district, Kerala for an area of 0.7649 Ha by Mr. Abu Thahir P

Decision: The proponent and RQP were present. The RQP made the presentation. The

Committee entrusted Dr. S. Sreekumar & Shri. G. Sankar with the Field Inspectionand also

directed the proponent to submit the following documents/details:

a. Detailed Project Report on the Revised EMP incorporating the specific CER activities in

physical terms to be undertaken by the proponent in consultation with the stakeholders as

stipulated in the OM No.22- 65/2017-IA.III dated 30/09/2020 and OM No. 22-65/2017-

IA.III dated 20/10/2020 of the MoEF&CC, GOI instead of allocation of funds under

CER. The CER activities incorporated in the EMP should be undertaken during the first

two years of validity period of the EC so as to ensure that the maintenance of the

interventions undertaken can be done by the proponent during the remaining validity

period of the EC.

b. Revised biodiversity assessment with quantification separately for the core and buffer

areas.

c. A Recent survey map showing distance to residential/public buildings, inhabited sites,

canals, roads, electric lines, mobile towers, religious places etc., within 200 m. radius of

the lease boundary certified by the Village Officer.

d. Biodiversity summary in tabular form

e. Water level data of nearby open wells with geo coordinates

f. Lithological section indicating the Laterite profile.

18. SIA/KL/MIN/179449/2020,1814/EC3/2020/SEIAA

Environmental Clearance for Ordinary Earth Mining Project of Mr.Mathachan

P.J, over an extent of 0.9692 Ha in Re Sy No-440/1-2, 440/12-2, 440/2-2-2-2,

440/2-2-2 of Aikaranadu North Village, Kunnathunad Taluk, Ernakulam

District, Kerala

Decision: The proponent and the RQP were present. The RQP made the presentation. The

Committee entrusted Shri. K. Krishna Panicker and Dr. N. Ajithkumar with the Field

Inspection.

19. SIA/KL/MIN/34543/2019,1589/EC1/2020/SEIAA

Granite Building Stone Quarry of Mr. Jose Varghese at Sy. No. 5/1 of Alakode

Village, Thodupuzha Taluk, Idukki District, Kerala

Page 30: Presentation - SEIAA-KERALA

Decision: The proponent and the RQP were present. The RQP made the presentation. The

Committee directed the proponent to submit the following additional documents /details:

a. Revised project cost

b. Detailed Project Report on the Revised EMP incorporating the specific CER activities in

physical terms to be undertaken by the proponent in consultation with the stakeholders as

stipulated in the OM No.22- 65/2017-IA.III dated 30/09/2020 and OM No. 22-65/2017-

IA.III dated 20/10/2020 of the MoEF&CC, GOI instead of allocation of funds under

CER. The CER activities incorporated in the EMP should be undertaken during the first

two years of validity period of the EC so as to ensure that the maintenance of the

interventions undertaken can be done by the proponent during the remaining validity

period of the EC.

c. Recent cluster Certificate

d. Details of monitored wells

20. SIA/KL/MIS/142842/2020,1741/EC3/2020/SEIAA

Environmental Clearance of the proposed Residential Building Project „Jains

Marine Bay‟ at Ponjikara, Ernakulam at Re survey No. Re. Survey No. 281/7-2,

280/5-2, 280/4, 281/8-2, 281/5- 2, 281/73, 280/83, 281/13, 280/32, 280/2, 281/3,

281/4, 281/22, 281/114, 281/93,281/152,281/162,280/7, 281/1, 281/18, 281/12,

281/19, 281/6-2, 280/6 at Mulavukad Village, Kanayannur Taluk, Ernakulam

District

Decision: The proponent and the RQP were present. The RQP made the presentation. The

Committee entrusted Dr. N. Ajithkumar & Er. M. Dileepkumar with the Field Inspection and also

directed the proponent to submit the following additional documents /details:

a. Detailed Project Report on the Revised EMP incorporating the specific CER activities in

physical terms to be undertaken by the proponent in consultation with the stakeholders as

stipulated in the OM No.22- 65/2017-IA.III dated 30/09/2020 and OM No. 22-65/2017-

IA.III dated 20/10/2020 of the MoEF&CC, GOI instead of allocation of funds under

CER. The CER activities incorporated in the EMP should be undertaken during the first

two years of validity period of the EC so as to ensure that the maintenance of the

interventions undertaken can be done by the proponent during the remaining validity

period of the EC

b. Include Mangrove associate species in the planting proposed

AGENDA 3

1. SIA/KL/MIN/132702/2019,1726/EC2/2020/SEIAA

Environment Clearance for mining lease of Granite Building Stone Quarry

ofShri.Byju T.V over an extent of 1.5913 Ha.(3.9321 Acres) at SyNo. 506/2Pt,

Kanjirangad Village, Mananthavady Taluk, Wayanad District, Kerala

Decision: The proponent and the RQP were present. The RQP made the presentation. The

Committee directed the proponent to submit the following additional documents /details:

a. Recent cluster certificate

Page 31: Presentation - SEIAA-KERALA

b. Biodiversity Revision

c. Compensatory Afforestation

d. Detailed Project Report on the Revised EMP incorporating the specific CER activities in

physical terms to be undertaken by the proponent in consultation with the stakeholders as

stipulated in the OM No.22- 65/2017-IA.III dated 30/09/2020 and OM No. 22-65/2017-

IA.III dated 20/10/2020 of the MoEF&CC, GOI instead of allocation of funds under

CER. The CER activities incorporated in the EMP should be undertaken during the first

two years of validity period of the EC so as to ensure that the maintenance of the

interventions undertaken can be done by the proponent during the remaining validity

period of the EC.

e. Revised biodiversity assessment with quantification separately for the core and buffer

areas.

f. A Recent survey map showing distance to residential/public buildings, inhabited sites,

canals, roads, electric lines, mobile towers, religious places etc., within 200 m. radius of

the lease boundary certified by the Village Officer.

g. Biodiversity summary in tabular form

h. Detailed water level measurement data of nearby open wells with geo coordinates. f.

Details of tree cutting

i. Recent Air, Water and other parameters test results.

j. 500m Landuse and Land cover map

k. ESA details

2. SIA/KL/MIN/133893/2019,1788/E2/2020/SEIAA

Environment Clearance for mining of „Granite Building Stone Quarry of M/s.

Pulpally Stone Crushers‟ over an extent of 0.7905 Ha.(1.9533 Acres) at Re-

Sy.Nos. 399/1, 399/15 & 399/18, Padichira Village, Sulthan Bathery Taluk,

Wayanad District, Kerala by Shri. Binoj K Baby

Decision: The proponent and the RQP were present. The RQP made the presentation. The

Committee directed the proponent to submit the following additional documents /details:

a. Detailed Project Report on the Revised EMP incorporating the specific CER activities

in physical terms to be undertaken by the proponent in consultation with the

stakeholders as stipulated in the OM No.22- 65/2017-IA.III dated 30/09/2020 and OM

No. 22-65/2017-IA.III dated 20/10/2020 of the MoEF&CC, GOI instead of allocation of

funds under CER. The CER activities incorporated in the EMP should be undertaken

during the first two years of validity period of the EC so as to ensure that the

maintenance of the interventions undertaken can be done by the proponent during the

remaining validity period of the EC.

b. Revised biodiversity assessment with quantification separately for the core and buffer

areas.

c. A recent survey map showing distance to residential/public buildings, inhabited sites,

canals, roads, electric lines, mobile towers, religious places etc., within 200 m. radius of

the lease boundary certified by the Village Officer.

d. Biodiversity summary in tabular form e. Water level data of nearby open wells with geo

coordinates

e. DSR

f. Tree cutting details & Green belt plan with species specification.

g. 500m Land use and Land cover map

Page 32: Presentation - SEIAA-KERALA

h. ESA details

3. SIA/KL/MIN/134824/2020,1729/EC2/2020/SEIAA

Environment Clearance for mining of Granite Building Stone Quarry of Mr.

Safarulla, K. at Re-Sy.No-320/1,321/2 of Vorkady Village, Manjeshwaram

Taluk, Kasaragod District of Kerala for an extent of 0.1920 Ha

Decision: The proponent and the RQP were present. The RQP made the presentation. The

Committee directed the proponent to submit the following additional documents /details:

a. Detailed Project Report on the Revised EMP incorporating the specific CER activities

in physical terms to be undertaken by the proponent in consultation with the

stakeholders as stipulated in the OM No.22- 65/2017-IA.III dated 30/09/2020 and OM

No. 22-65/2017-IA.III dated 20/10/2020 of the MoEF&CC, GOI instead of allocation of

funds under CER. The CER activities incorporated in the EMP should be undertaken

during the first two years of validity period of the EC so as to ensure that the

maintenance of the interventions undertaken can be done by the proponent during the

remaining validity period of the EC.

b. Revised biodiversity assessment with quantification separately for the core and buffer

areas.

c. A Recent survey map showing distance to residential/public buildings, inhabited sites,

canals, roads, electric lines, mobile towers, religious places etc., within 200 m. radius of

the lease boundary certified by the Village Officer.

d. Biodiversity summary in tabular form

e. Detailed water level measurement data of nearby open wells with geo coordinates.

f. Details of tree cutting /planting required

g. Detailed afforestation plan

4. SIA/KL/MIN/140590/2020,1791/EC2/2020/SEIAA

Environment Clearance for Granite buildingstone quarrying located in Re-Sy.

Nos.382/1, &382/5,PadichiraVillage, Sulthan Bathery Taluk, Wayanad

District, Kerala Stateoveranextentof0.7300HabySri.JobyJohn

Decision: The proponent and the RQP were present. The RQP made the presentation. The

Committee directed the proponent to submit the following additional documents /details:

a. Detailed Project Report on the Revised EMP incorporating the specific CER activities in

physical terms to be undertaken by the proponent in consultation with the stakeholders

as stipulated in the OM No.22- 65/2017-IA.III dated 30/09/2020 and OM No. 22-

65/2017-IA.III dated 20/10/2020 of the MoEF&CC, GOI instead of allocation of funds

under CER. The CER activities incorporated in the EMP should be undertaken during

the first two years of validity period of the EC so as to ensure that the maintenance of

the interventions undertaken can be done by the proponent during the remaining

validity period of the EC.

b. Revised biodiversity assessment with quantification separately for the core and buffer

areas.

c. A Recent survey map showing distance to residential/public buildings, inhabited sites,

canals, roads, electric lines, mobile towers, religious places etc., within 200 m. radius of

the lease boundary certified by the Village Officer.

Page 33: Presentation - SEIAA-KERALA

d. Biodiversity summary in tabular form

e. Detailed water level measurement data of nearby open wells with geo coordinates

f. Proof of the application submitted for the permission from the National Board for

Wildlife

g. Revised drainage plan

h. Report on slope stability

i. Green belt plan with mixed crop

5. SIA/KL/MIN/142152/2020,1737/EC4/2020/SEIAA

EnvironmentalClearanceforLateritebuildingstonequarryofMr.Suresh.T,over

an extent of 0.4047 Ha, Resy no-113/21(113/2) in Mavoor Village,Kozhikode

Taluk, Kozhikode District,Kerala

Decision: The proponent and RQP were present. The RQP made the presentation. The

Committee entrusted Shri. K. Krishna Panicker and Dr. P.S Easa for Field Inspection and also

directed the proponent to submit the following additional documents /details:

a. Detailed Project Report on the Revised EMP incorporating the specific CER activities in

physical terms to be undertaken by the proponent in consultation with the stakeholders as

stipulated in the OM No.22- 65/2017-IA.III dated 30/09/2020 and OM No. 22-65/2017-

IA.III dated 20/10/2020 of the MoEF&CC, GOI instead of allocation of funds under

CER. The CER activities incorporated in the EMP should be undertaken during the first

two years of validity period of the EC so as to ensure that the maintenance of the

interventions undertaken can be done by the proponent during the remaining validity

period of the EC.

b. A Recent survey map showing distance to residential/public buildings, inhabited sites,

canals, roads, electric lines, mobile towers, religious places etc., within 200 m. radius of

the lease boundary certified by the Village Officer.

c. Biodiversity summary in tabular form

d. Detailed water level measurement data of nearby open wells with geo coordinates.

e. Lithological cross section with depth details

6. SIA/KL/MIN/149660/2020,1682/EC1/2020/SEIAA

Environment Clearance for Granite building stone quarry in Sy.No: 137/4-11,

137/4-11-1, 137/422, 137/4-21 in Thachanattukara-1 Village, Mannarkkad

Taluk, Palakkad District, Kerala by Sri.Mujeeb P.K

Decision: The proponent was not present online and intimated the inconvenience to

attend the meetingdue to regional lockdown, over phone. The RQP was present and he

made the presentation. The Committee directed the proponent to submit the following

additional documents /details:

a. Revised mining plan, the depth of the benches should be limited without affecting

the water table.

b. Revised CER focusing on the green infrastructure development

Page 34: Presentation - SEIAA-KERALA

c. Detailed Project Report on the Revised EMP incorporating the specific CER

activities in physical terms to be undertaken by the proponent in consultation with

the stakeholders as stipulated in the OM No.22- 65/2017-IA.III dated 30/09/2020 and

OM No. 22-65/2017-IA.III dated 20/10/2020 of the MoEF&CC, GOI instead of

allocation of funds under CER. The CER activities incorporated in the EMP should

be undertaken during the first two years of validity period of the EC so as to ensure

that the maintenance of the interventions undertaken can be done by the proponent

during the remaining validity period of the EC.

c. Project cost should be revised realistically

d. Revised drainage plan

e. Biodiversity assessment for core and buffer

f. Detailed greenbelt plan

7. SIA/KL/MIN/150672/2020,1680/EC1/2020/SEIAA

Environment Clearance for Granite building stone quarry in Sy.No: 142/1 , in

Thachanattukara-1 Village, Mannarkkad Taluk, Palakkad District, Kerala by

Sri. Muhammed Mammunni

Decision: The proponent’s representative and the RQP were present. The RQP

made the presentation. The Committee directed the proponent to submit the revised

presentation with the documents sought in 120th

SEAC meeting besides the following additional documents /details:

a. Detailed Project Report on the Revised EMP incorporating the specific CER

activities in physical terms to be undertaken by the proponent in consultation with

the stakeholders as stipulated in the OM No.22- 65/2017-IA.III dated 30/09/2020 and

OM No. 22-65/2017-IA.III dated 20/10/2020 of the MoEF&CC, GOI instead of

allocation of funds under CER. The CER activities incorporated in the EMP should

be undertaken during the first two years of validity period of the EC so as to ensure

that the maintenance of the interventions undertaken can be done by the proponent

during the remaining validity period of the EC.

b. Revised biodiversity assessment with quantification separately for the core and

buffer areas.

c. A Recent survey map showing distance to residential/public buildings, inhabited

sites, canals, roads, electric lines, mobile towers, religious places etc., within 200 m.

radius of the lease boundary certified by the Village Officer.

d. Biodiversity summary in tabular form

e. Detailed water level measurement data of nearby open wells with geo coordinates

f. Site specific drainage plan

g. Revised project cost

h. Tree cutting details

i. Hazard Zonation Map

j. Detailed greenbelt plan

8. SIA/KL/MIN/152787/2020,1716/EC1/2020/SEIAA

Environment Clearance for Granite Building stone quarry At Re Survey No:

24/1, 25/4, Block No: 50 in Mangalam Dam Village, Alathur Taluk, Palakkad

Page 35: Presentation - SEIAA-KERALA

District, Kerala State by Shri. M V Antoo

Decision: The proponent and the RQP were present. The RQP made the presentation. The

Committee directed the proponent to revise the proposal in toto on account of the facts that

details relating to biodiversity, including faunal biodiversity is lacking, CER detailing is

sketchy and there is no comprehensive plan for CER as part of EMP. Drainage including the

natural drains need to be reworked, and how the depth of 40 meter of mining is going to

impinge the ground water level of the proposed site, whether the proposed area is under ESA.

The Committee also decided to direct the proponent to submit the following additional

documents/details:

a. Tree cutting plan

b. Recent cluster certificate

c. Detailed Project Report on the Revised EMP incorporating the specific CER activities

in physical terms to be undertaken by the proponent in consultation with the

stakeholders as stipulated in the OM No.22- 65/2017-IA.III dated 30/09/2020 and OM

No. 22-65/2017-IA.III dated 20/10/2020 of the MoEF&CC, GOI instead of allocation

of funds under CER. The CER activities incorporated in the EMP should be undertaken

during the first two years of validity period of the EC so as to ensure that the

maintenance of the interventions undertaken can be done by the proponent during the

remaining validity period of the EC.

d. Revised biodiversity assessment with quantification separately for the core and buffer

areas.

e. A Recent survey map showing distance to residential/public buildings, inhabited sites,

canals, roads, electric lines, mobile towers, religious places etc., within 200 m. radius of

the lease boundary certified by the Village Officer.

f. Biodiversity summary in tabular form

g. Detailed water level measurement data of nearby open wells with geo coordinates.

h. Greenbelt plan

9. SIA/KL/MIN/153085/2020,1777/EC1/2020/SEIAA

EnvironmentalClearancefortheProposedGranite(BuildingStone)QuarryinBlock

no.83, Re Survey No: 66 of Ambalappara -II and Block No.80, ReSy.No:287/17

of Ambalappara-I village in Ottappalam Taluk, Palakkad

District,KeralabyShri.P.K.Abdul KhaderofM/S FathimaGranites

Decision: The proponent and the RQP were present. The RQP made the presentation. The

Committee entrusted Dr. S Sreekumar and Dr. A.V Raghu for the Field Inspection and also

directed the proponent to submit the following additional documents /details:

a. Detailed Project Report on the Revised EMP incorporating the specific CER activities in

physical terms to be undertaken by the proponent in consultation with the stakeholders as

stipulated in the OM No.22- 65/2017-IA.III dated 30/09/2020 and OM No. 22-65/2017-

IA.III dated 20/10/2020 of the MoEF&CC, GOI instead of allocation of funds under

CER. The CER activities incorporated in the EMP should be undertaken during the first

two years of validity period of the EC so as to ensure that the maintenance of the

interventions undertaken can be done by the proponent during the remaining validity

period of the EC.

b. Revised biodiversity assessment with quantification separately for the core and buffer

Page 36: Presentation - SEIAA-KERALA

areas.

c. Legible Recent survey map showing distance to residential/public buildings, inhabited

sites, canals, roads, electric lines, mobile towers, religious places etc., within 200 m.

radius of the lease boundary certified by the Village Officer.

d. Biodiversity summary in tabular form

e. Detailed water level measurement data of nearby open wells with geo coordinates

f. Recent cluster certificate

g. Revised project cost

h. Compensatory afforestation plan

10. SIA/KL/MIN/154284/2020,1736/EC4/2020/SEIAA

Building Stone Mine (Quarry, Minor Mineral Mining) project of M/s Star

Granites situated at Re-Sy. No.2/1B, Re-Sy.BlockNo.5,ofKedavoorVillage,

Thamarassery Taluk, Kozhikode District, Kerala

Decision: The proponent and the RQP were present. The RQP made the presentation. The

Committee directed the proponent to submit the following additional documents /details:

a. Recent cluster certificate

b. Air quality report

c. Buffer & Drainage to be site - specific

d. Detailed Project Report on the Revised EMP incorporating the specific CER activities in

physical terms to be undertaken by the proponent in consultation with the stakeholders as

stipulated in the OM No.22- 65/2017-IA.III dated 30/09/2020 and OM No. 22-65/2017-

IA.III dated 20/10/2020 of the MoEF&CC, GOI instead of allocation of funds under

CER. The CER activities incorporated in the EMP should be undertaken during the first

two years of validity period of the EC so as to ensure that the maintenance of the

interventions undertaken can be done by the proponent during the remaining validity

period of the EC.

e. Revised biodiversity assessment with quantification separately for the core and buffer

areas.

f. A Recent survey map showing distance to residential/public buildings, inhabited sites,

canals, roads, electric lines, mobile towers, religious places etc., within 200 m. radius of

the lease boundary certified by the Village Officer.

g. Biodiversity summary in tabular form

h. Detailed water level measurement data of nearby open wells with geo coordinates.

i. Location sketch

11. SIA/KL/MIN/156925/2020,1743/EC4/2020/SEIAA

EnvironmentalClearanceforLateriteBuildingStoneQuarryofMr.SaneeshKat Sy.

No 46/726, 727, 728, 729, 730, 731, 732, 733 of Kalliad Village, Iritty

Taluk,KannurDistrictofKeralaforanextentof0.9711Ha

Decision: The proponent and the RQP were present. The RQP made the presentation. The

Page 37: Presentation - SEIAA-KERALA

Committee entrusted Dr. R. Ajayakumar Varma and Dr. N. Anil Kumar with the field inspection

directed the proponent to submit the documents /details:

a. Detailed Project Report on the Revised EMP incorporating the specific CER activities in

physical terms to be undertaken by the proponent in consultation with the stakeholders as

stipulated in the OM No.22- 65/2017-IA.III dated 30/09/2020 and OM No. 22-65/2017-

IA.III dated 20/10/2020 of the MoEF&CC, GOI instead of allocation of funds under

CER. The CER activities incorporated in the EMP should be undertaken during the first

two years of validity period of the EC so as to ensure that the maintenance of the

interventions undertaken can be done by the proponent during the remaining validity

period of the EC.

b. Revised biodiversity assessment with quantification separately for the core and buffer

areas.

c. A Recent survey map showing distance to residential/public buildings, inhabited sites,

canals, roads, electric lines, mobile towers, religious places etc., within 200 m. radius of

the lease boundary certified by the Village Officer.

d. Biodiversity summary in tabular form

e. Detailed water level measurement data of nearby open wells with geo coordinates.

f. List of trees to be planted in green belt

g. Vertical lithological section

h. Drainage plan showing water flow to the natural drain.

12. SIA/KL/MIN/158875/2020,1751/EC1/2020/SEIAA

Environmental Clearance for the proposed granite building stone quarry in

ReSy. No35/1ofVallappuzhaVillage,PattambiTaluk, Palakkad District for an

area of 0.7099 Ha. by President, Ottappalam Taluk Karinkal Quarry Operators

Industrial Co-Operative Society Ltd.

Decision:The proponent and the RQP were present. The RQP made the presentation. The

Committee directed the proponent to submit the following additional documents /details:

a. Detailed Project Report on the Revised EMP incorporating the specific CER activities in

physical terms to be undertaken by the proponent in consultation with the stakeholders as

stipulated in the OM No.22- 65/2017-IA.III dated 30/09/2020 and OM No. 22-65/2017-

IA.III dated 20/10/2020 of the MoEF&CC, GOI instead of allocation of funds under

CER. The CER activities incorporated in the EMP should be undertaken during the first

two years of validity period of the EC so as to ensure that the maintenance of the

interventions undertaken can be done by the proponent during the remaining validity

period of the EC.

b. Revised biodiversity assessment with quantification separately for the core and buffer

areas.

c. Detailed greenbelt/afforestation plan

d. A Recent survey map showing distance to residential/public buildings, inhabited sites,

canals, roads, electric lines, mobile towers, religious places etc., within 200 m. radius of

the lease boundary certified by the Village Officer. d. Biodiversity summary in tabular

form

e. Detailed water level measurement data of nearby open wells with geo coordinates.

Page 38: Presentation - SEIAA-KERALA

f. Recent cluster certificate.

13. SIA/KL/MIN/159168/2020,1752/EC1/2020/SEIAA

Environmental Clearance for the proposed granite buildingstone quarryin Re-

Sy. No.492/3, Block No.19 of Thiruvegappura Village, Pattambi Taluk,

Palakkad District for an area of 0.4177 Ha. by President, Ottappalam Taluk

Karinkal Quarry Operators Industrial Co- Operative Society Limited

Decision: The proponent and the RQP were present. The RQP made the presentation. The

Committee directed the proponent to submit the following additional documents /details:

a. Revised project cost

b. Revised drainage plan

c. Afforestation plan (consider rejuvenation of Sacred Groves)

d. Recent cluster certificate

e. Detailed Project Report on the Revised EMP incorporating the specific CER

activities in physical terms to be undertaken by the proponent in consultation with

the stakeholders as stipulated in the OM No.22- 65/2017-IA.III dated 30/09/2020 and

OM No. 22-65/2017-IA.III dated 20/10/2020 of the MoEF&CC, GOI instead of

allocation of funds under CER. The CER activities incorporated in the EMP should

be undertaken during the first two years of validity period of the EC so as to ensure

that the maintenance of the interventions undertaken can be done by the proponent

during the remaining validity period of the EC.

f. Revised biodiversity assessment with quantification separately for the core and

buffer areas.

g. A Recent survey map showing distance to residential/public buildings, inhabited

sites, canals, roads, electric lines, mobile towers, religious places etc., within 200 m.

radius of the lease boundary certified by the Village Officer.

h. Biodiversity summary in tabular form

i. Detailed water level measurement data of nearby open wells with geo coordinates.

14. SIA/KL/MIN/160638/2020,1721/EC2/2020/SEIAA

Environmental Clearance for Building Stone Quarry of Mr.S.Sundarasan over

an extent of 0.7678 Ha. Re Survey no.114/2-1,115/6-4-2,113/6,113/4- 2,113/13, of

PuthoorVillage,KottarakkaraTaluk,KollamDistrict

Decision: The proponent and the RQP were present. The RQP made the presentation.The

Committee directed the proponent to submit the following additional documents /details:

a. Clarification regarding the OB dumping site

b. Modified garland plan

c. Detailed Project Report on the Revised EMP incorporating the specific CER

activities in physical terms to be undertaken by the proponent in consultation with

the stakeholders as stipulated in the OM No.22- 65/2017-IA.III dated 30/09/2020 and

OM No. 22-65/2017-IA.III dated 20/10/2020 of the MoEF&CC, GOI instead of

allocation of funds under CER. The CER activities incorporated in the EMP should

be undertaken during the first two years of validity period of the EC so as to ensure

that the maintenance of the interventions undertaken can be done by the proponent

Page 39: Presentation - SEIAA-KERALA

during the remaining validity period of the EC.

d. Revised biodiversity assessment with quantification separately for the core and

buffer areas.

e. A Recent survey map showing distance to residential/public buildings, inhabited

sites, canals, roads, electric lines, mobile towers, religious places etc., within 200 m.

radius of the lease boundary certified by the Village Officer.

f. Biodiversity summary in tabular form

g. Detailed afforestation plan

h. Detailed water level measurement data of nearby open wells with geo coordinates.

15. SIA/KL/MIN/161938/2020,1727/EC2/2020/SEIAA

Environment Clearance for Granite Building Stone Quarry of Mr. Sudheesh A

T at Re Survey No: 129/20,129/19,134/6,134/7 of Padichira Village, Sulthan

Bathery Taluk, Wayanad District, Kerala for an area of1.8407 hectares

Decision: The proponent and the RQP were present. The RQP made the presentation. The

Committee directed the proponent to submit the following additional documents /details:

a. Revised biodiversity assessment with quantification separately for the core and buffer

areas.

b. Tree cutting details and restoration plan

c. Details regarding the application for wildlife clearances from nearby ESZs.

d. Detailed Project Report on the Revised EMP incorporating the specific CER

activities in physical terms to be undertaken by the proponent in consultation with

the stakeholders as stipulated in the OM No.22- 65/2017-IA.III dated 30/09/2020 and

OM No. 22-65/2017-IA.III dated 20/10/2020 of the MoEF&CC, GOI instead of

allocation of funds under CER. The CER activities incorporated in the EMP should

be undertaken during the first two years of validity period of the EC so as to ensure

that the maintenance of the interventions undertaken can be done by the proponent

during the remaining validity period of the EC.

e. Revised biodiversity assessment with quantification separately for the core and

buffer areas.

f. A Recent survey map showing distance to residential/public buildings, inhabited

sites, canals, roads, electric lines, mobile towers, religious places etc., within 200 m.

radius of the lease boundary certified by the Village Officer.

g. Biodiversity summary in tabular form

h. Eco-restoration plan

i. Detailed water level measurement data of nearby open wells with geo coordinates.

j. Provide more silt traps in garland drainage plan and link to the natural drainage.

16. SIA/KL/MIN/161967/2020,1747/EC1/2020/SEIAA

Environmental Clearance for the Proposed Granite (Building Stone) Quarry in

Re-SurveyNos.98/2-1,98/1,98/1-1inNellanadVillage,NedumangadTaluk,

Thiruvananthapuram District, Kerala by Sri.Abdul Nazar A

Decision: The proponent and the RQP were present. The RQP made the presentation. The

Page 40: Presentation - SEIAA-KERALA

Committee directed the proponent to submit the following additional documents /details:

a. Revised Project Cost

b. Detailed Project Report on the Revised EMP incorporating the specific CER

activities in physical terms to be undertaken by the proponent in consultation with

the stakeholders as stipulated in the OM No.22- 65/2017-IA.III dated 30/09/2020 and

OM No. 22-65/2017-IA.III dated 20/10/2020 of the MoEF&CC, GOI instead of

allocation of funds under CER. The CER activities incorporated in the EMP should

be undertaken during the first two years of validity period of the EC so as to ensure

that the maintenance of the interventions undertaken can be done by the proponent

during the remaining validity period of the EC.

c. Revised biodiversity assessment with quantification separately for the core and

buffer areas.

d. A Recent survey map showing distance to residential/public buildings, inhabited

sites, canals, roads, electric lines, mobile towers, religious places etc., within 200 m.

radius of the lease boundary certified by the Village Officer.

e. Biodiversity summary in tabular form

f. Detailed water level measurement data of nearby open wells with geo coordinates

g. Clarification on the complaints received on 14.06.2021 from Kadal Kaani Paara

Action Council.

17. SIA/KL/MIN/163854/2020,1773/EC1/2020/SEIAA

Environmental Clearance for the Granite Building Stone Quarry of M/s. Delta

Aggregates &Sand Pvt.Ltdoveranextentof3.7691Ha.atSurvey.Nos. 889/1-15-

1&889/1-15,PerunadVillage,RanniTaluk,Pathanamthitta District, Kerala

Decision: The proponent and the RQP were present. The RQP made the presentation. The

Committee entrusted Shri. G. Sankar and Smt.Beena Govindan with the Field Inspection and also

directed the proponent to submit the following additional documents /details:

a. Afforestation details

b. Detailed Project Report on the Revised EMP incorporating the specific CER

activities in physical terms to be undertaken by the proponent in consultation with

the stakeholders as stipulated in the OM No.22- 65/2017-IA.III dated 30/09/2020 and

OM No. 22-65/2017-IA.III dated 20/10/2020 of the MoEF&CC, GOI instead of

allocation of funds under CER. The CER activities incorporated in the EMP should

be undertaken during the first two years of validity period of the EC so as to ensure

that the maintenance of the interventions undertaken can be done by the proponent

during the remaining validity period of the EC.

c. Revised biodiversity assessment with quantification separately for the core and

buffer areas.

d. A Recent survey map showing distance to residential/public buildings, inhabited

sites, canals, roads, electric lines, mobile towers, religious places etc., within 200 m.

radius of the lease boundary certified by the Village Officer.

e. Biodiversity summary in tabular form

Page 41: Presentation - SEIAA-KERALA

f. Detailed greenbelt/afforestation plan

g. Detailed water level measurement data of nearby open wells with geo coordinates

18. SIA/KL/MIN/170197/2020,1776/EC1/2020/SEIAA

Environmental Clearance for the Proposed Granite Building Stone Quarry of

Mr. Anish S atRe.Sy.No.136/pt,137/ptof Kozhipathy Village, Chittur Taluk,

Palakkad District, Kerala

Decision: The proponent and the RQP were present. The RQP made the presentation. The

Committee directed the proponent to submit the following additional documents /details:

a. Tree cutting details

b. Google map showing distance to the nearest wild life Sanctuary

c. Detailed Project Report on the Revised EMP incorporating the specific CER

activities in physical terms to be undertaken by the proponent in consultation with

the stakeholders as stipulated in the OM No.22- 65/2017-IA.III dated 30/09/2020 and

OM No. 22-65/2017-IA.III dated 20/10/2020 of the MoEF&CC, GOI instead of

allocation of funds under CER. The CER activities incorporated in the EMP should

be undertaken during the first two years of validity period of the EC so as to ensure

that the maintenance of the interventions undertaken can be done by the proponent

during the remaining validity period of the EC.

d. Revised biodiversity assessment with quantification separately for the core and

buffer areas.

e. Site-specific drainage plan

f. A Recent survey map showing distance to residential/public buildings, inhabited

sites, canals, roads, electric lines, mobile towers, religious places etc., within 200 m.

radius of the lease boundary certified by the Village Officer.

g. Biodiversity summary in tabular form

h. Detailed afforestation plan

i. Detailed water level measurement data of nearby open wells with geo coordinates

j. ESA details

k. Valid RQP certificate

19. SIA/KL/MIN/170229/2020,1795/EC1/2020/SEIAA

Environmental Clearance for the Proposed Granite (BuildingStone)Quarryin

BlockNo:33,Re-SurveyNos: 369/1/2,368/4/1,368/3 in Ongallur II Village,

Pattambi Taluk, Palakkad District, Kerala by Sri. Abdul Gafoor

Decision: The proponent and the RQP were present. The RQP made the presentation. The

Committee directed the proponent to submit the following additional documents /details:

a. Revised site specific Drainage map

b. Detailed Project Report on the Revised EMP incorporating the specific CER

activities in physical terms to be undertaken by the proponent in consultation with

the stakeholders as stipulated in the OM No.22- 65/2017-IA.III dated 30/09/2020 and

OM No. 22-65/2017-IA.III dated 20/10/2020 of the MoEF&CC, GOI instead of

allocation of funds under CER. The CER activities incorporated in the EMP should

be undertaken during the first two years of validity period of the EC so as to ensure

Page 42: Presentation - SEIAA-KERALA

that the maintenance of the interventions undertaken can be done by the proponent

during the remaining validity period of the EC.

c. Revised biodiversity assessment with quantification separately for the core and

buffer areas.

d. A Recent survey map showing distance to residential/public buildings, inhabited

sites, canals, roads, electric lines, mobile towers, religious places etc., within 200 m.

radius of the lease boundary certified by the Village Officer.

e. Biodiversity summary in tabular form e. Water level data of nearby open wells with

geo coordinates

f. Form1M

g. OB dumping site

h. Drainage map

i. Proof of the application submitted for the permission from the National Board for

Wildlife.

20. SIA/KL/MIN/41970/2019,1715/EC1/2020/SEIAA

EnvironmentclearancefortheProposedGraniteBuildingStoneQuarryoveran

extent of 1.2120 Hectares in Re-Survey No. 222part (Govt. Land.) at

Pazhayakunnummel Village, Block No.-33, Chirayinkeezhu Taluk,

Thiruvananthapuram District of Kerala State by Mr. SAKKEER,A.

Decision: The proponent and the RQP were present. The RQP made the presentation. The

Committee directed the proponent to submit the following additional documents /details:

a. Rock fall and slope stabilization

b. Detailed Project Report on the Revised EMP incorporating the specific CER activities in

physical terms to be undertaken by the proponent in consultation with the stakeholders as

stipulated in the OM No.22- 65/2017-IA.III dated 30/09/2020 and OM No. 22-65/2017-

IA.III dated 20/10/2020 of the MoEF&CC, GOI instead of allocation of funds under

CER. The CER activities incorporated in the EMP should be undertaken during the first

two years of validity period of the EC so as to ensure that the maintenance of the

interventions undertaken can be done by the proponent during the remaining validity

period of the EC.

c. Revised biodiversity assessment with quantification separately for the core and buffer

areas.

d. A Recent survey map showing distance to residential/public buildings, inhabited sites,

canals, roads, electric lines, mobile towers, religious places etc., within 200 m. radius of

the lease boundary certified by the Village Officer.

e. Biodiversity summary in tabular form

f. Detailed water level measurement data of nearby open wells with geo coordinates.

g. Recent cluster certificate

h. Google map with boundary pillars

AGENDA 4

Page 43: Presentation - SEIAA-KERALA

1. SIA/KL/MIN/134486/2020,1790/EC4/2020/SEIAA

Environmental Clearance for the building stone quarry of Sri. Shamseer VK,

projectis situated atRe Survey No. 2/18, 2/20, 2/46, 2/76, 2/77, 2/78 in Raroth

Village, Thamarassery Taluk, Kozhikode District, and Kerala for an

areaof0.9926hectares

Decision: The proponent and the RQP were present. The RQP made the presentation. The

Committee decided to direct the proponent to submit the following additional documents

/details:

a. OB dumping site clarification

b. Recent cluster certificate

c. Details of water resources

d. Detailed Project Report on the Revised EMP incorporating the specific CER

activities in physical terms to be undertaken by the proponent in consultation with

the stakeholders as stipulated in the OM No.22- 65/2017-IA.III dated 30/09/2020 and

OM No. 22-65/2017-IA.III dated 20/10/2020 of the MoEF&CC, GOI instead of

allocation of funds under CER. The CER activities incorporated in the EMP should

be undertaken during the first two years of validity period of the EC so as to ensure

that the maintenance of the interventions undertaken can be done by the proponent

during the remaining validity period of the EC.

e. Revised biodiversity assessment with quantification separately for the core and

buffer areas.

f. A Recent survey map showing distance to residential/public buildings, inhabited

sites, canals, roads, electric lines, mobile towers, religious places etc., within 200 m.

radius of the lease boundary certified by the Village Officer.

g. Biodiversity summary in tabular form

h. Detailed water level measurement data of nearby open wells with geo coordinates

i. Hazard Zonation Map

j. Approved mining plan

k. Greenbelt development plan

2. SIA/KL/MIN/136866/2020,1719/EC3/2020/SEIAA

Environment Clearance for mining permit of “Granite Building Stone Quarry

of M/s. Kadanadu Granites” over an extent of 0.7452 Ha. (1.8413 Acres) in

BlockNo.30,Re-Sy.Nos.327,1-1&327/1-1-1,KadanaduVillage, Meenachil Taluk,

Kottayam District, Kerala State,India.

Decision: The proponent and the RQP were present. The RQP made the presentation. The

Committee decided to direct the proponent to submit the following additional documents

/details:

a. OB & Garland canal to be redrawn

b. Detailed Project Report on the Revised EMP incorporating the specific CER activities in

physical terms to be undertaken by the proponent in consultation with the stakeholders as

stipulated in the OM No.22- 65/2017-IA.III dated 30/09/2020 and OM No. 22-65/2017-

IA.III dated 20/10/2020 of the MoEF&CC, GOI instead of allocation of funds under

CER. The CER activities incorporated in the EMP should be undertaken during the first

Page 44: Presentation - SEIAA-KERALA

two years of validity period of the EC so as to ensure that the maintenance of the

interventions undertaken can be done by the proponent during the remaining validity

period of the EC.

c. Revised biodiversity assessment with quantification separately for the core and buffer

areas.

d. Recent cluster certificate

e. A Recent survey map showing distance to residential/public buildings, inhabited sites,

canals, roads, electric lines, mobile towers, religious places etc., within 200 m. radius of

the lease boundary certified by the Village Officer.

f. Biodiversity summary in tabular form

g. Detailed water level measurement data of nearby open wells with geo coordinates.

3. SIA/KL/MIN/138256/2020,1702/EC4/2020/SEIAA

Building Stone Quarry of Mr. K.K. Mohammed ,overanextentof0.9199 Haat

Re.Sy.No188/2 in Kodiyathur Village, KozhikodeTaluk, Kozhikode District,

Kerala.

Decision: The proponent and the RQP were present. The RQP made the presentation. The

Committee entrusted Sri. K. Krishna Panicker and Dr. P.S Easa with the Field Inspection and

also directed the proponent to submit the following additional documents /details:

a. Detailed Project Report on the Revised EMP incorporating the specific CER activities in

physical terms to be undertaken by the proponent in consultation with the stakeholders as

stipulated in the OM No.22- 65/2017-IA.III dated 30/09/2020 and OM No. 22-65/2017-

IA.III dated 20/10/2020 of the MoEF&CC, GOI instead of allocation of funds under

CER. The CER activities incorporated in the EMP should be undertaken during the first

two years of validity period of the EC so as to ensure that the maintenance of the

interventions undertaken can be done by the proponent during the remaining validity

period of the EC.

b. Revised biodiversity assessment with quantification separately for the core and buffer

areas.

c. A Recent survey map showing distance to residential/public buildings, inhabited sites,

canals, roads, electric lines, mobile towers, religious places etc., within 200 m. radius of

the lease boundary certified by the Village Officer.

d. Biodiversity summary in tabular form

e. Water level data of nearby open wells with geo coordinates

f. Revised project cost

g. Tree cutting details and Greenbelt plan with species details

h. DSR

4. SIA/KL/MIN/148123/2020,1658/EC6/2020/SEIAA

Environmental clearance for Granite building stone quarry of Mr. Kunhalan .K,

for an extent of 0.8165 Ha Re. Sy. Nos. 211/1, 211/3-2 (Block No. 59) of Pulpatta

Village, Eranad Taluk, Malappuram District, Kerala

Decision:The proponent and the RQP were present. The RQP made the presentation.The

Page 45: Presentation - SEIAA-KERALA

Committee decided to direct the proponent to submit the following additional documents

/details:

1. Detailed Project Report on the Revised EMP incorporating the specific CER activities

in physical terms to be undertaken by the proponent in consultation with the

stakeholders as stipulated in the OM No.22- 65/2017-IA.III dated 30/09/2020 and

OM No. 22-65/2017-IA.III dated 20/10/2020 of the MoEF&CC, GOI instead of

allocation of funds under CER. The CER activities incorporated in the EMP should

be undertaken during the first two years of validity period of the EC so as to ensure

that the maintenance of the interventions undertaken can be done by the proponent

during the remaining validity period of the EC.

2. DSR

5. SIA/KL/MIN/148582/2020,1690/EC4/2020/SEIAA

Environmental Clearance for Laterite Building Stone Quarry of Mr .Gopi at Re-

Sy. No- 33/1 of Naduvannur Village, Koyilandy Taluk, Kozhikode

DistrictofKeralaforanextentof0.2429HaunderB2category

Decision: The proponent and the RQP were present. The RQP made the presentation. The

Committee decided to direct the proponent to submit the following additional documents

/details:

a. Details regarding post-mining activity

b. Detailed Project Report on the Revised EMP incorporating the specific CER activities

in physical terms to be undertaken by the proponent in consultation with the

stakeholders as stipulated in the OM No.22- 65/2017-IA.III dated 30/09/2020 and

OM No. 22-65/2017-IA.III dated 20/10/2020 of the MoEF&CC, GOI instead of

allocation of funds under CER. The CER activities incorporated in the EMP should

be undertaken during the first two years of validity period of the EC so as to ensure

that the maintenance of the interventions undertaken can be done by the proponent

during the remaining validity period of the EC.

c. Revised biodiversity assessment with quantification separately for the core and buffer

areas.

d. A Recent survey map showing distance to residential/public buildings, inhabited sites,

canals, roads, electric lines, mobile towers, religious places etc., within 200 m. radius

of the lease boundary certified by the Village Officer.

e. Biodiversity summary in tabular form

f. Water level data of nearby open wells with geo coordinates

g. 500m Land use and Landover map

h. Lithological section indicating the Laterite profile

6. SIA/KL/MIN/156447/2020,1731/EC3/2020/SEIAA

Environmental Clearance for the building stone quarry at Survey

No.338/1A/20/D&D2 of Keerampara Village, KothamangalamTaluk, Ernakulam

District,KeralaforanAreaof0.9133Ha. By ShymonAnto

Decision: The proponent and the RQP were present. The RQP made the presentation. The

Committee decided to direct the proponent to submit the following additional documents

Page 46: Presentation - SEIAA-KERALA

/details:

a. Detailed Project Report on the Revised EMP incorporating the specific CER activities in

physical terms to be undertaken by the proponent in consultation with the stakeholders as

stipulated in the OM No.22- 65/2017-IA.III dated 30/09/2020 and OM No. 22-65/2017-

IA.III dated 20/10/2020 of the MoEF&CC, GOI instead of allocation of funds under

CER. The CER activities incorporated in the EMP should be undertaken during the first

two years of validity period of the EC so as to ensure that the maintenance of the

interventions undertaken can be done by the proponent during the remaining validity

period of the EC.

b. Revised biodiversity assessment with quantification separately for the core and buffer

areas.

c. A Recent survey map showing distance to residential/public buildings, inhabited sites,

canals, roads, electric lines, mobile towers, religious places etc., within 200 m. radius of

the lease boundary certified by the Village Officer.

d. Biodiversity summary in tabular form

e. Detailed water level measurement data of nearby open wells with geo coordinates.

f. Recent cluster certificate

7. SIA/KL/MIN/156655/2020,1754/EC3/2020/SEIAA

Granite Building stone quarry of Mr. Deepak Cheerothy at 171/2-2, 171/4 of

Karukutty Village, Aluva Taluk & Ernakulam District for an extend of 0.9600ha

Decision: The proponent and the RQP were present. The RQP made the presentation. The

Committee decided to directthe proponent to submit the following additional documents /details:

a. Recent cluster certificate

b. OB dumping details

c. Recent survey map

d. Detailed Project Report on the Revised EMP incorporating the specific CER activities in

physical terms to be undertaken by the proponent in consultation with the stakeholders as

stipulated in the OM No.22- 65/2017-IA.III dated 30/09/2020 and OM No. 22-65/2017-

IA.III dated 20/10/2020 of the MoEF&CC, GOI instead of allocation of funds under

CER. The CER activities incorporated in the EMP should be undertaken during the first

two years of validity period of the EC so as to ensure that the maintenance of the

interventions undertaken can be done by the proponent during the remaining validity

period of the EC.

e. Revised biodiversity assessment with quantification separately for the core and buffer

areas.

f. A Recent survey map showing distance to residential/public buildings, inhabited sites,

canals, roads, electric lines, mobile towers, religious places etc., within 200 m. radius of

the lease boundary certified by the Village Officer.

g. Biodiversity summary in tabular form

h. Detailed water level measurement data of nearby open wells with geo coordinates.

i. Revise drainage plan with sufficient silt traps

Page 47: Presentation - SEIAA-KERALA

j. OB dumping location must be shown in the map

8. SIA/KL/MIN/162481/2020,1742/EC4/2020/SEIAA

Environmental Clearance for Laterite Building Stone Quarry of Sri Deepa N.K.

at Sy. No23/798, 23/912ofKalliadVillage,IrittyTaluk, Kannur District

ofKeralaforanextentof0.5567HaunderB2category

Decision: The proponent’s representative and the RQP were present. The RQP made the

presentation. The Committee directed the proponent to submit the following additional

documents /details:

a. Detailed Project Report on the Revised EMP incorporating the specific CER activities in

physical terms to be undertaken by the proponent in consultation with the stakeholders as

stipulated in the OM No.22- 65/2017-IA.III dated 30/09/2020 and OM No. 22-65/2017-

IA.III dated 20/10/2020 of the MoEF&CC, GOI instead of allocation of funds under

CER. The CER activities incorporated in the EMP should be undertaken during the first

two years of validity period of the EC so as to ensure that the maintenance of the

interventions undertaken can be done by the proponent during the remaining validity

period of the EC.

b. Revised biodiversity assessment with quantification separately for the core and buffer

areas.

c. A Recent survey map showing distance to residential/public buildings, inhabited sites,

canals, roads, electric lines, mobile towers, religious places etc., within 200 m. radius of

the lease boundary certified by the Village Officer.

d. Biodiversity summary in tabular form

e. Detailed water level measurement data of nearby open wells with geo coordinates

f. Lithological section indicating the profile of the Laterite.

9. SIA/KL/MIN/167079/2020,1787/EC4/2020/SEIAA

Environmental Clearance for Laterite building stone quarry of Mr. George

Joseph,overanextentof0.1942 Ha.ResyNo-143/1 in Perumanna Village,

Kozhikode Taluk, Kozhikode District, Kerala. Decision: The proponent and the RQP were present. The RQP made the presentation. The

Committee decided to recommend the issuance of EC subject to the following specific condition

in addition to the general conditions:

a. Submission of sworn affidavit regarding post-mining activity

10. SIA/KL/MIS/171583/2020, 1789/EC4/2020/SEIAA

Environmental Clearance for the Proposed Commercial cum Special Residential

Building in Ward No. 16, Re.SyNo.128/1,2A, 2BatPanoor

Municipality,PanoorVillage,ThalasseryTaluk,KannurDistrict,Kerala

Page 48: Presentation - SEIAA-KERALA

Decision: The consultant and the proponent were present. The consultant made the presentation

The Committee decided to direct the proponent to submit the following documents/details:

a. Details of STP, including details of Tertiary Treatment Unit (Ultra Filtration Unit), with

pre-treatment facilities of PSF and PCF (in continuation to the primary and secondary

type of treatment of sewage with MBBR type ASP), for establishing 150 KLD STP, in

order to ensure quality of treated water, fit for re-use /recycle for Flushing / Gardening/

Fire Fighting/ / HVAC make up water / Recharge of local ground water.

b. Re-examine the cost estimation given for STP, as Rs 52 lakh, considering the secondary

and tertiary treatment, as proposed above.

c. Undertaking that action will be taken for ensuring to use water efficient plumbing

features and twin line plumbing system, for ensuring recycle/reuse of treated waste

water.

d. Earmark a convenient location in the site plan, with sufficient covered storage space, for

non-degradable solid waste (dry waste), for ensuring hygienic storage and periodical

handing over of the same to Recyclers/ Local body.

e. Earmark a convenient location in the basement Floor / at site, for ensuring hygienic

storage space for biodegradable waste (wet waste) and biogas plant, for ensuring usage

of biogas, within the compound.

f. Plan for developing a Compensatory Afforestation Plan, at suitable location inside/

outside the project area, following the norms of minimum of 1 plant per 80 sqm plinth

area, specified in the KMBR.

g. Give details of pumping test conducted, in the two available wells at the proposed site,

for knowing yield, zone of influence of well and aquifer response, while pumping from

a single well as well as from both.

h. Details of storm water drainage plan in the proposed site, considering recharge potential

of proposed water abstraction points in the boundaries and proposed rain water

harvesting.

i. Details of proposed delay pond, and settling facility proposed, for imparting primary

settling of storm water.

j. Plan / Undertaking that, action will be taken for planning and implementing proper

facilities for tapping Solar Energy in the Roof Top of proposed building, (even though

there is a mention of 60 kWp capacity solar water heating system in the EMP), for

harnessing solar power for meeting partial energy requirement and for exploring

possibility for linking it with KSEB power line.

k. Revised CER following the latest MoEF&CC guidelines.

l. Undertaking that action will be taken for ensuring to plan and implement a realistic and

suitable green area development, with suitable species of trees and plants, specifically

suitable for the area .Also committing that vegetation will be adopted appropriately on

the ground as well as over built structure such as roofs, basements, podiums etc.

m. Undertaking that action will be taken for ensuring to plan a climate responsive design as

per Green Building Guidelines and also committing that exposed roof area and covered

parking will be covered with material having high solar reflective index.

n. Undertaking that action will be taken for ensuring that the building design will cater to

the differently-abled citizens.

o. Undertaking that action will be taken for ensuring that the design of the building will

be done in compliance to Energy Building Code as applicable.

Page 49: Presentation - SEIAA-KERALA

AGENDA 5

1. SIA/KL/MIN/127534/2019 ,1554/EC1/2019/SEIAA

Environment Clearance for Granite Building Stone Quarry in Sy.No. 340/1-

26/3,340/1-28/2,340/1-30/1,340/1/26-2,340/1/26-1,Enadimangalam Village, Adoor

Taluk, Pathanamthitta District byMr. Mathew Daniel

Decision: Deferred for further scrutiny

2. SIA/KL/MIN/131090/2019 ,1571/EC2/2019/SEIAA

Granite Building Stone Quarry of Mr. Sudheesh A T at Re Survey No: 151/1,

151/7ofKaniyambattaVillage,VythiriTaluk,WayanadDistrict,Kerala foran

areaof1.5875 hectares

Decision: Deferred for further scrutiny

3. SIA/KL/MIN/132322/2019 ,1635/EC1/2020/SEIAA

Granite Building Stone Quarry of Shri. Nino K Thomas‟ over an extent of

2.7213 Ha. (6.7243 Acres) at Re-Survey Block No. 31, Re-survey. Nos. 457/1,

457/2,457/3, 457/4, 457/4-1, 457/5, 457/6 & 457/7, Vadasserikkara Village, Ranni

Taluk, Pathanamthitta District, Kerala

Decision: Deferred for further scrutiny

4. SIA/KL/MIN/133062/2019 ,1576/EC2/2019/SEIAA

Proposed Granite Building Stone Quarry of M/s Valad Granites at SurveyNo.

253/62,253/356,253/349ofValadVillage,ManathavadiTaluk,Wayanad District,

and Kerala for anareaof2.9249hectares

Decision: Deferred for further scrutiny

5. SIA/KL/MIN/134803/2020,1656/EC3/2020/SEIAA

Application for Environmental Clearance for the Granite Building Stone Quarry

project in Re-Survey Nos. 304part (Govt. Land) Parathodu Village, Block No.-

49 of Udumbanchola Taluk, Idukki District, Kerala for an extent of 3.0000

Hectares bySri. Binu George

Decision: Deferred for further scrutiny

6. SIA/KL/MIN/134893/2020 ,1585/EC1/2020/SEIAA

Environmental Clearance for the proposed Granite Building Stone quarry

projectin SurveyNo. 208/1,Alanallur –3 Village, Mannarkkadu Taluk, Palakkad

District, district, M/s PLANETS ANDS&AGGREGATES

Decision: Deferred for further scrutiny

7. SIA/KL/MIN/144086/2020 ,1597/EC4/2020/SEIAA

Environmental Clearance for Laterit Building Stone Quarry of Mr.

Ramachandran, P. at Re-Sy. No- 19/245 of Koodathai Village, Thamarassery

Taluk,KozhikodeDistrictofKeralaforanextentof0.8094HaunderB2 category

Page 50: Presentation - SEIAA-KERALA

Decision: Deferred for further scrutiny

8. SIA/KL/MIN/145130/2020 ,1664/EC1/2020/SEIAA

Building Stone Mine( Quarry, Minor Mineral Mining) project ofM/s Capital

Granites at Survey Nos. 2/3&3/2at Shoranur IIVillage, Ottappalam Taluk,

Palakkad District ,Kerala for area of 2.4946 hec

Decision: Deferred for further scrutiny

9. SIA/KL/MIN/148361/2020 ,1641/EC3/2020/SEIAA

Building Stone Quarry of M/s Seas Rock Products at Survey No

426/3,426/4,426/5inNeyyasseryVillage,ThodupuzhaTaluk,IdukkiDistrict, Kerala

State foranextentof1.5163Ha

Decision: Deferred for further scrutiny

10. SIA/KL/MIN/150010/2020,1627/EC4/2020/SEIAA

Environmental Clearance for Laterite building stone quarry project of

Moyimonul Rasheed over an extent of 0.9919 Ha in Re Sy No- 44/1, 41/1 of

Thalakulathur Village, Kozhikode Taluk, Kozhikode District, Kerala.

Decision:

The Committee directed the proponent to upload a detailed drainage plan including the

width, depth and carrying capacity of the channel along with a map depicting the

drainage line up to an existing natural stream in the area. The design of the drainage

channel should be such that there will not be any stagnation of water within mining

area and project site. The map and details submitted earlier is not satisfactory as it does

not contain adequate details. Therefore, the proponent is directed to submit the details

as sought earlier. It is also decided to bring this to the notice of SEIAA.

11. SIA/KL/MIN/158734/2020 ,1768/EC6/2020/SEIAA

Application for Environmental Clearance for the Granite building stone quarry

project in Sy No-157/4 Kuruva Village,Perinthalmanna Taluk, Malappuram

District, Kerala for an area of 0.9789HabyShri. RasheedaliKottakkaran

Decision: Deferred for further scrutiny

12. SIA/KL/MIN/163150/2020 ,1749/EC1/2020/SEIAA

Environmental Clearance for the Proposed Granite (BuildingStone)Quarryin

Re-SurveyNo:129/1,Block No:30inOngallur1Village,PattambiTaluk, Palakkad

District, Kerala by Sri. Musthafa, A

Decision: Deferred for further scrutiny

13. SIA/KL/MIN/171976/2020 ,1851/EC2/2020/SEIAA

(Conversion TOR to EC) Proposed Granite Building Stone Quarry of Mr. P

Abdullaat Re SurveyNo 274/45 ofVillage-Panathady Village, Vellarikund Taluk,

Kasargode District, Kerala for an extent of0.2104 Ha

Decision: Deferred for further scrutiny

Page 51: Presentation - SEIAA-KERALA

14. SIA/KL/MIN/32061/2019 ,1622/EC2/2020/SEIAA

Environment Clearance for the Granite Building Stone Quarry of M/s

Nellimunda Granates and Sands Pvt Ltd‟ over an extent of 1.1341Ha (2.8026

Acres) at Re Sy No. 374/752 & 374/738, Valad Village, Mananthavady

Taluk,Wayanad District,KeralaState, for a production capacity of 45,231.25

tonnes per annum.

Decision: Deferred for further scrutiny

15. SIA/KL/MIN/44488/2019 ,1474/EC1/2019/SEIAA

Granite Building Stone Quarry of Sri. Nino K Thomas at Re-Survey Block No.

31,Re-survey.Nos.394/2,461/1&461/4,VadasserikkaraVillage,RanniTaluk,

Pathanamthitta District, Kerala

Decision: Deferred for further scrutiny

16. SIA/KL/MIS/148576/2020 ,1645/EC1/2020/SEIAA

Artech Grand Tower Residential Building Project at Sasthamangalam,

Thiruvananthapuram

Decision: Deferred for further scrutiny

17. SIA/KL/MIS/153603/2020 ,1673/EC2/2020/SEIAA

Environment Clearance for proposed Hospital buildings within the existing Holy

Cross Hospital complex to be developed by M/s Holy Cross Hospital, Kottiyam

Decision: Deferred for further scrutiny

18. SIA/KL/MIS/42326/2018 ,1458/EC3/2019/SEIAA

Capacity Enhancement of Secured Landfill Facility at Existing Common

Hazardous Waste Treatment, Storage and Disposal Facility (TSDF) site

proposedbyKEILatBlockNo.37,SurveyNo.205ofPuthenkurissuVillage,

KunnathunadTaluk, Ernakulam District.

Decision: Deferred for further scrutiny

AGENDA 6

1. SIA/KL/MIN/133902/2019,1678/EC6/2020/SEIAA

Proposed Laterite (Building Stone) Quarry in Re-Survey No. BL 11 239/2 of

Pallikkal Village, Kondotty Taluk, Malappuram District, Kerala for an

extent of 0.1943 Ha under B2 category. (Judgment dt.07.04.2021 in

Page 52: Presentation - SEIAA-KERALA

WP(C) No.2667 of 2021)(Copyattached)

Decision: The Committee decided to inform the SEIAA that final decision on the

proposal could not be taken in the light of the minimum distance norms of 200m. for

mining involving blasting and 100m.for mining not involving blasting are stipulated by

the Hon’ble NGT wherein final orders are awaited.

2. SIA/KL/MIN/142917/2020,1659/EC6/2020/SEIAA

Application for Environmental Clearance for the Building Stone Quarry

project in Sy. No‟s 453/1 of Arakkuparamba Village, PerinthalmannaTaluk,

Malappuram District, Kerala for an area of0.6340Ha bySri.Unnikrishnan

Decision: The Committee discussed the Field Inspection Report and decided to direct the

proponent to submit the following documents/details:

a. Recent cluster certificate

b. Details of open well –Depth of water table during post monsoon and its geoco- ordinates

O.B site must be shifted to an appropriate place.

c. Approach road has to be widened from 3m to 7m.

d. Quantitative assessment of biodiversity has to be done separately for core and buffer and

summarised in a tabular form.

e. Considering the lack of space for greening the buffer along BP3 and BP4, a compensatory

afforestation needs to be done and a plan to be prepared and submitted.

3. SIA/KL/MIN/147339/2020,1669/EC6/2020/SEIAA

The building stone quarry project of M/s Granites India is situated at Survey

Nos.98/2pt,98/24 pt(Block No.1)&SurveyNo.428/66 pt (Block No.2)of Edayur

Village of Tirur Taluk, MalappuramDist

Decision: The CER submitted is not yet part of the EMP. EMP incorporating the CER has to

be submitted. The CER also needs to be detailed with physical details of the proposal like

toilet building, solar lights, ambulance and well recharge.

4. SIA/KL/MIN/205474/2021,1444/EC2/2019/SEIAA

Granite Building Stone Quarry of Mr.K.I Joseph (Conversion ToR to EC),

Venganellur Village, ThalappillyTaluk,ThrissurDistrict,SurveyNo.53,Area-

0.9910Ha.

Decision: Deferred for further scrutiny.

5. SIA/KL/MIN/93154/2019,1235/EC2/2019/SEIAA

ApplicationforEnvironmentalClearancefortheGraniteBuildingStoneQuarry

projectinReSy.No92/ptofPulpattaVillage,ErnadTaluk,Malappuram

District,Keralaforanareaof1.7396Ha by Shri.MohammedKunhiHaji

Decision: The Committee discussed the Field Inspection Report and decided to direct the

proponent to submit the following documents/details:

a. The boundary pillars must be fixed to the ground using concrete. The Geo co- ordinates

must be marked on the pillars.

Page 53: Presentation - SEIAA-KERALA

b. Details of open well – depth of water table during post monsoon and its Geoco- ordinates

must be provided.

6. SIA/KL/MIS/209935/2021 ,1896/EC1/2021/SEIAA

EnvironmentalClearancefortheproposedbuildingconstructionprojectaspart of

development of IT/ITES campus (Phase-1) to be developed by M/s Tata

Consultancy Services Ltd. (Green Building Certificate)

Decision: The Committee scrutinized the proposal submitted by the proponent. The Committee

decided to invite the proponent for presentation.

CONSIDERATION OF TOR PROPOSAL

1. SIA/KL/MIN/41118/2019,1444/EC2/2019/SEIAA

Submission of Terms of Reference (TOR) for EIA of the mining permit in

respect of “Building StoneQuarryofMr.K.IJoseph”,overanextentof0.9910 Ha.

Survey No. 53/2 in Venganellur Village, Thalappilly Taluk, Thrissur District,

Kerala

Decision: Further decision in this proposal will be taken in the EC Proposal No.

SIA/KL/MIN/205474/2021

2. SIA/KL/NCP/57270/2020,1890/EC3/2021/SEIAA

Residential Building Project – Kent Mahal of M/s. Kent Constructions Pvt. Ltd.,

at Sy. Nos. 141/3, 141/4, 141/5 & 141/8 of Puthencruz Village, Vadavucode

Puthencruz Grama Panchayat, Kunnathunadu Taluk, Ernakulam District,

Kerala State.

Decision: The Committee discussed the proposals. The application of the proponent is

dated 23-10-2020 which is outside the window period for remediation of violation cases

prescribed by MoEF&CC and hence cannot be appraised by SEIAA. These facts have

to be brought to the notice of SEIAA for consideration.

3. SIA/KL/MIN/60375/2021,1884/EC4/2021/SEIAA

TOR (Terms of Reference)for the Proposed Granite Building Stone Quarry over

an area of 5.2794 Ha located At Un Survey (Field No. 2159, 2160, 2162 NotFinal)

in Koodaranji Village, Thamarassery Taluk, Kozhikode District, Kerala.

Category„B‟

Decision: The Committee scrutinized the proposal submitted by the proponent. The Committee

decided to invite the proponent for presentation of ToR.

General Decisions:

It is decided to expedite the field inspection in respect of the proposals for revalidation of

Page 54: Presentation - SEIAA-KERALA

EC as there is a time limit stipulated by the Hon‟ble High Court of Kerala.

It is also decided to direct the proponents of the proposals for revalidation of EC to follow

the original mine plan for calculating the life of the mine.

It is decided to convene the next meeting of SEAC during 27th -30th, July, 2021.

The meeting ended at 5pm on 18th June, 2021 with a vote of thanks.

Sd/-

Dr. C. Bhaskaran

Chairman, SEAC

List of members attending the SEAC meeting on 15.06.2021

1 Shri.M.Dileep Kumar 7 Dr.N.Anilkumar

2 Dr.R.Ajayakumar Varma 8 Shri.K.Krishna Panicker

3 Smt.Beena Govindan 9 Shri.V.N.Jithendran

4 Dr.P.S.Easa 10 Dr.A.V.Raghu

5 Shri.G.Sankar 11 Dr.N.Ajithkumar

6 Dr.S.Sreekumar

List of members attending the SEAC meeting on 16.06.2021

1 Shri.M.Dileep Kumar 7 Dr.N.Anilkumar

2 Dr.R.Ajayakumar Varma 8 Shri.K.Krishna Panicker

3 Smt.Beena Govindan 9 Shri.V.N.Jithendran

4 Dr.P.S.Easa 10 Dr.A.V.Raghu

5 Shri.G.Sankar 11 Dr.N.Ajithkumar

6 Dr.S.Sreekumar

Page 55: Presentation - SEIAA-KERALA

List of members attending the SEAC meeting on 17.06.2021

1 Shri.M.Dileep Kumar 7 Dr.N.Anilkumar

2 Dr.R.Ajayakumar Varma 8 Shri.K.Krishna Panicker

3 Smt.Beena Govindan 9 Shri.V.N.Jithendran

4 Dr.P.S.Easa 10 Dr.A.V.Raghu

5 Shri.G.Sankar 11 Dr.N.Ajithkumar

6 Dr.S.Sreekumar

List of members attending the SEAC meeting on 18.06.2021

1 Shri.M.Dileep Kumar 7 Dr.N.Anilkumar

2 Dr.R.Ajayakumar Varma 8 Shri.K.Krishna Panicker

3 Smt.Beena Govindan 9 Dr.A.V.Raghu

4 Dr.P.S.Easa 10 Dr.N.Ajithkumar

5 Shri.G.Sankar

6 Dr.S.Sreekumar