Customer Preparation Guide to BSC6900 Installation
Scope GlobalDocumen
t code.
ObjectCustomer/Huawei Engineer/Partner
Product Version
V900R011/R012/R013/R014
Realeasing Dept.
TSD Wireless Product Service Dept.
Document Version
1.4
Product BSC6900
Customer Preparation Guide to BSC6900 Installation
Draft: Date:
Review: Date:
Review: Date:
Approve: Date:
Huawei Technologies Co., Ltd.
Customer Preparation Guide to BSC6900 Installation
Revise Record
DateRevision Version
Description Author
2009-9-21 1.0 Initial Version Gao Peng
2010-2-10 1.1Add preparation for OSS Network and
preparation for software networkGao Peng
2010-7-19 1.2Add the electrical specifications of
BSC6900V900R012 Gao Peng
2010-12-18 1.3Add the electrical specifications of
BSC6900V900R013Gao Peng
2011-12-29 1.4Add the electrical specifications of
BSC6900V900R014Ni Huijun
Huawei Technologies Co., Ltd. No dissemination without permission Page ii Total 22
Customer Preparation Guide to BSC6900 Installation
4. 1 Preparation of DC Power and Storage Batteries..............................................................10
4. 2 Preparation of AC Power.................................................................................................10
4. 3 Preparation of Transmission Equipment..........................................................................10
4. 4 Preparation of DDF..........................................................................................................10
4. 5 Preparation of Cabling Racks..........................................................................................11
Huawei Technologies Co., Ltd. No dissemination without permission Page iii Total 22
Customer Preparation Guide to BSC6900 Installation
4. 6 Preparation of Cabling Racks..........................................................................................11
4.7 Preparation for pedestal by customer................................................................................11
Appendix A Self-check List...................................................................................................................12
A.1 Acceptance of the Equipment Room Environment..................................................................12
A.2 Acceptance of the Power Supply.............................................................................................13
A.3 Acceptance of the Grounding Cables.......................................................................................13
Appendix B Physical Parameters of BSC6900.......................................................................................14
Appendix C Calculation of Air Conditioner Capacity............................................................................15
Huawei Technologies Co., Ltd. No dissemination without permission Page iv Total 22
Preparation Guide to BSC6900 Installation Internal
Chapter 1 Preface
Dear customers, thank you for choosing the BSC6900 products of Huawei. For better
cooperation between us and for smooth engineering, we hereby provide you with this guide
for you to prepare for the project installation of the product. We hope that you can make all
the preparations according to the requirements stated in this guide before Huawei engineers
arrive at the site so that during the project implementation, the equipment can be installed
smoothly and rapidly and put into operation to create better social and economic benefits at a
date as earliest as possible. You need to get the following ideas before making the preparing
for project installation:
After making all the preparations, please contact Huawei’s local representative office
in due time so that Huawei can arrange the corresponding engineer(s) for the project
installation.
If due to some causes, the specific installation of the project is implemented while the
preparations for project installation are not completely finished, you shall take the
responsibility of arranging the corresponding personnel to complete the unfinished
part during the project installation to facilitate the smooth progress of the project.
If due to some causes, the specific installation of the project is implemented while the
preparations for project installation are not completely finished, and the project
cannot go on during the project installation due to your insufficient preparations,
Huawei is entitled to proposing the suspension of installation according to the
specific conditions. After you have made full preparations, we may negotiate again to
resume the work.
While making the preparations, if you have any question, you may consult Huawei’s
representative office in the local province or city at any time.
Address of Huawei’s local representative office:
Tel/Fax of Huawei’s local representative office:
Project supervisor of Huawei’s local representative office & Tel:
2023-04-07 HUAWEI Confidential Page1
Preparation Guide to BSC6900 Installation Internal
Chapter 2 Installation Flow of Huawei
To strengthen cooperation and understanding, the installation flow of Huawei is briefly
introduced here. The equipment installation flow of Huawei is implemented as soon as the
contract takes effect and until the final acceptances passed to enter the maintenance flow.
The process is as follows:
It can be seen that the smooth completion of a project needs the close cooperation between
the customer and Huawei. Here we hope that this project can be completed smoothly. If any
question , please contact the local representative office in time. We will provide help and
2023-04-07 HUAWEI Confidential Page2
Preparation Guide to BSC6900 Installation Internal
service to you sincerely.
Chapter 3 Installation Requirements
3.1 Introduction to the BSC6900
The BSC6900 is an important network element of the Huawei Single RAN solution. It adopts the industry-leading multiple radio access technologies, IP transmission mode, and modular design. In addition, it is integrated with the functions of the UMTS BSC6900 and GSM BSC, thus efficiently maintaining the trend of multi-RAT convergence in the mobile network.
The BSC6900 can be flexibly configured as a BSC6900 GSM, BSC6900 UMTS, or BSC6900 GU as required in different networks. The BSC6900 in independent mode refers to the BSC6900 GSM or the BSC6900 UMTS whereas the BSC6900 in integrated mode refers to the BSC6900 GU.
The BSC6900 GSM, in compliance with the 3GPP R6, operates as an independent NE to access the GSM network and performs the functions of the GSM BSC. With the support of EDGE+, the BSC6900 GSM can be upgraded to the BSC6900 GU through addition of UMTS boards and software upgrade.
The BSC6900 GU operates as an independent NE to access the GSM&UMTS network and integrates the functions of the GSM BSC and the UMTS BSC6900. When the BSC6900 GU accesses the GSM network, the 3GPP R6 applies; when the BSC6900 GU accesses the UMTS network, the 3GPP R7 applies.
The BSC6900 UMTS, in compliance with the 3GPP R7, operates as an independent NE to access the UMTS network and performs the functions of the UMTS BSC6900.
The following figure shows the BSC6900
2023-04-07 HUAWEI Confidential Page3
Preparation Guide to BSC6900 Installation Internal
Figure 3-1 BSC6900
Figure 3-2 Position of BSC6900 in the network
The interfaces between the BSC6900 and each NE in the UMTS network are as follows:
Iub: the interface between the BSC6900 and the NodeB Iur: the interface between the BSC6900 and the BSC6900 Iu-CS: the interface between the BSC6900 and the Mobile Switching Center (MSC)
or Media Gateway (MGW) Iu-PS: the interface between the BSC6900 and the Serving GPRS Support Node
(SGSN) Iu-BC: the interface between the BSC6900 and the Cell Broadcast Center (CBC)
These interfaces are standard interfaces, through which equipment from different vendors can be interconnected.
The interfaces between the BSC6900 and each NE in the GSM network are as follows:
2023-04-07 HUAWEI Confidential Page4
Preparation Guide to BSC6900 Installation Internal
Abis: the interface between the BSC6900 and the BTS A: the interface between the BSC6900 and the Mobile Switching Center (MSC) or
Media Gateway (MGW) Gb: the interface between the BSC6900 and the Serving GPRS Support Node
(SGSN)
The A and Gb interfaces are standard interfaces, through which the equipment from different vendors can be interconnected.
The BSC6900 performs functions such as radio resource management, base station management, power control, and handover control.
3.2 Equipment Room Building Requirements
3.2.1 Equipment Room Building
The equipment rooms for BSC6900 consist of the switch room, the control room (usually with
an area no less than 20m2), and the auxiliary room. Sometimes the switch room and the
control room can be integrated. The equipment room should not be on the first floor lest the
equipment room be waterlogged or humid. Addition it cannot be on the top floor, because the
sunshine directly overheats the equipment room, and lightning strike becomes more likely.
1) The civil engineering work of the sectors like the equipment room and corridors has been
fully completed, with the indoor wall being fully dry.
2) Floor load of the equipment room: less than 450 kg per square meter;
3) The net height (from the surface of the antistatic floor to the lower edge of the beam) of
the BSC6900 equipment room should not be less than 3.5m for the upward cabling mode
and should not be less than 3m for the downward cabling mode. The size of the main
doors of the equipment room shall not hinder moving of the equipment. The locks and
keys of the doors shall be complete;
4) Ventilation equipment shall be provided;
5) The ceiling, walls, doors, windows and floor of the equipment room shall not break off,
cause dust or accumulate dust easily, and shall be able to prevent the incursion of dust
and sand. It is strictly required that the ceiling be waterproof and dust-proof. The
decoration material shall be non-inflammable or fire-retardant;
6) Various troughs shall have moisture-proof measures with smooth corners. The floor and
cover plates shall be tightly sealed. The lighting and power wires should adopt hidden
layout as much as possible;
7) Color of the equipment room
i. Normally, patterned materials shall not be adopted for the floor, and the walls
and roof should be in bright and quietly elegant colors.
8) Area requirement and floor plan of the equipment room
i. The area of the equipment room where the equipment is to be installed should
be determined according to the final capacity of the office. For the specific
requirements, you may negotiate with the surveyors of Huawei during the
equipment room layout planning;
2023-04-07 HUAWEI Confidential Page5
Preparation Guide to BSC6900 Installation Internal
3.2.2 Layout requirements for the BSC6900 switch room:
The distance between the faces of two rows of cabinets shall not be less than 1.8m. The
distance between the cabinet side and the wall should be no less than 0.8 meters, and the
distance between the debugging side and the wall should be no less than 1.0 meter, as
shown in Figure 3-2 (the dimensions are for reference only). There shall be a walkway over
1.0m wide in the equipment room.
Figure 3- 2 Layout requirements for the equipment room
3.2.3 BSC6900 equipment room:
If the antistatic raised floor is installed in the equipment room, it is suggested that the height of
the floor be between 300mm and 450mm. The resistance value of the raised floor shall
comply with Technical Requirements for the Raised Floor Used in Computer Equipment
Rooms. The floorboards should be tightly fit and robust, with the horizontal error no greater
than 2mm per square meter. The equipment should be well grounded. Antistatic floor or floor
leather with semi-conductive materials should be paved. In the latter case, copper foil should
be used to ground it at several points (Copper foil should press tightly between the cement
floor and the semi-conductive floor, and should be connected to the grounding wire).
If raised floor is not available, the antistatic floor should be applied (volume resistively 1.0×
107 ~ 1.0 × 1010Ω). Electrostatic conductive floor or raised floor must be grounded. It can
connect to grounding device through current limiting resistor and connecting wire. Resistance
of the current limiting resistor shall be 1MΩ.
3.3 Requirement for Equipment Operation Environment
The environment shall be clean, dustless and free from the incursion of any corrosive gas,
exhaust gas and chemical exhaust gas. No water pipes shall pass the equipment room. The
equipment room shall be prevented from contact with water in any case. If the central heating
is installed in the equipment room, no valve shall be left or no connector shall be exposed.
The air conditioning equipment shall satisfy the requirements of maintaining the indoor
temperature and humidity. The environment shall also prevent the equipment from damage
2023-04-07 HUAWEI Confidential Page6
Preparation Guide to BSC6900 Installation Internal
caused by static electricity or interference from the electromagnetic field.
3.3.1 Antistatic and EMI Requirements
1) The equipment room should adopt the antistatic floor or antistatic ground that is well
grounded.
2) The equipment room should be equipped with antistatic clothes and antistatic wrist straps.
3) The equipment room should keep away from EMI. The intensity of the electric field shall
not exceed 300mV/m, and that of the magnetic field shall not exceed 11GS.
3.3.2 Dust-proof Requirements
1) The concentration of the dust granules with the diameter more than 5 microns is less than
3×104 granule/m3.
2) The dust granules shall be non-conductive, non-magnetic conductive and anti-corrosive.
Recommended dustproof measures for the equipment room:
a. Tightly seal the doors and the windows. The outer window shall use double-layer glass for
sealing. The door shall be added with dustproof sealing strips.
b. Maintain the cleanliness of working clothes and slippers, and clean/change them
frequently.
c. Isolate the control room from the BSC6900 equipment room with aluminum alloy glass.
Do not enter the BSC6900 equipment room unless necessary, because dust or other
interference factors may be caused by staff that frequently walks about the room;
d. The relative humidity of the equipment room shall be a little higher within the permitted
range to reduce the static dust absorption.
3.3.3 Temperature and Humidity Requirements
Temperature (°C) Relative humidity (%)
Normal working
conditions (see Note 1)
Short-term working
conditions (see Note 2)
Normal working
conditions
Short-term working
conditions
15°C ~ 30°C 0°C ~ 45°C 40%~65% 20%~90%
Note 1: Under the normal working conditions of the switch, the measurement of temperature
and humidity refers to the value measured 2.0 meters above the floor and 0.4 meters in front
of the equipment (measured when there is no protection board in the front or at the back of
the rack).
Note 2: The short-term working condition means that the continuous operation period is no
more than 48 hours and the accumulated yearly operation periods are no more than 15 days.
2023-04-07 HUAWEI Confidential Page7
Preparation Guide to BSC6900 Installation Internal
The equipment room shall be equipped with air conditioners as follows:
a. Air-condition humidity: 30%-75%; 50%-60% recommended.
b. Air-condition temperature: 18ºC ~ 28ºC; 20ºC ~ 25ºC recommended.
3.3.4 Noise
Indoor noise ≤70 decibels (the machine can work in a harsher environment however ,amore
harsh environment is detrimental to human health).
3.3.5 Lighting
1) Avoid direct sunlight to prevent aging and distortion of the components such as circuit
boards caused by long-term irradiation.
2) The average illumination is 150~200LX. There should be no glare. Normally, the
fluorescence lamps embedded in the ceiling are adopted. The average illumination for
NodeB can be more than 50LX.
3) Emergency lamps shall be installed in the equipment room.