ORAHS 2010 Prediction of the Time to Complete a Series of Surgical Cases to Avoid Cardiac Operating Room Overutilization* Rene Alvarez, MEng Centre for Research in Healthcare Engineering, Department of Mechanical and Industrial Engineering at the University of Toronto St. Michael’s Hospital, Toronto, ON, Canada Richard Bowry, MB BS FRCA St. Michael’s Hospital, Toronto, ON, Canada Faculty of Medicine, University of Toronto Michael Carter, PhD Centre for Research in Healthcare Engineering, Department of Mechanical and Industrial Engineering at the University of Toronto * Accepted for publication in the Canadian Journal of Anesthesia Editor: Donald R. Miller, M.D. Reviewer: Franklin Dexter, M.D., PhD
29
Embed
Prediction of the time to complete a series of surgical cases to avoid OR overutilization
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
ORAHS 2010
Prediction of the Time to Complete a Series of Surgical Cases to Avoid Cardiac Operating Room Overutilization*
Rene Alvarez, MEng Centre for Research in Healthcare Engineering, Department of Mechanical and Industrial Engineering at the University of Toronto St. Michael’s Hospital, Toronto, ON, Canada Richard Bowry, MB BS FRCA St. Michael’s Hospital, Toronto, ON, Canada Faculty of Medicine, University of Toronto Michael Carter, PhD Centre for Research in Healthcare Engineering, Department of Mechanical and Industrial Engineering at the University of Toronto
* Accepted for publication in the Canadian Journal of Anesthesia
Editor: Donald R. Miller, M.D.
Reviewer: Franklin Dexter, M.D., PhD
ORAHS 2010
Agenda
1. Objectives
2. Introduction
3. Methods
4. Results
5. Discussion
6. Conclusions
ORAHS 2010
1. Objectives
ORAHS 2010
Objective
We present a methodology to accurately estimate the time to complete a series of surgical cases in a single cardiac OR to avoid overutilization when:
the first case starts on time
there are no add-on cases
block time was calculated to match the typical OR workload
ORAHS 2010
2. Introduction
ORAHS 2010
OR Efficiency
Efficient OR utilization must account for the cost of both underutilized and overutilized OR hours
From the accounting perspective, the staffing expense during scheduled hours is a sunk cost so the savings for finishing cases early is effectively zero
A “zero tolerance for overtime” policy may be too rigid
Therefore, OR efficiency has two competing priorities: using all available time to perform cases
control overutilization
ORAHS 2010
Overutilization
If for a single OR we assume that:
1. the first case starts on time
2. there are no add-on cases
3. block time was calculated to match the typical OR workload
Then, overutilization in that OR can be minimized by accurately estimating the time required to complete the each case
ORAHS 2010
How to estimate surgery duration?
a. Surgeons’ estimation
b. Average time using historical data
c. Historical data combined with the surgeon’s own estimate
d. A linear prediction model that combined objective factors with the surgeons’ estimate of operative time
ORAHS 2010
Lognormal approximation
Most authors agree that the lognormal distribution is adequate to represent surgical times
ORAHS 2010
How to sum these random times?
Alvarez et al. (ORAHS 2008) suggested a methodology based on the Fenton-Wilkinson Approximation
The Fenton-Wilkinson approach: gives an accurate estimate particularly in the tail of
the cumulative distribution function
offers a closed-form solution for approximating the underlying parameters to the lognormal distribution
ORAHS 2010
3. Methods
ORAHS 2010
Data: surgeries
We studied 6,090 cases performed by 9 different cardiovascular surgeons between January 1st, 2004 and January 30th, 2009 at St. Michael’s Hospital, located in Toronto, Ontario, Canada
Cases were grouped clinically into 13 different categories
Coronary artery bypass graft surgery (CABG) accounted for 63.33% of the cases
1. Aortic plus mitral valve replacement/repair
2. Aortic valve replacement/repair 3. Aortic valve replacement/repair plus
cardiopulmonary bypass) 11. Minor procedure 12. Mitral valve replacement/repair 13. Mitral valve replacement/repair plus
CABG
ORAHS 2010
Data: turnover times
We collected data during a five month period (January 2009-May 2009)
The average turnover time was 0.50 hours, with a standard deviation of 0.23 hours
ORAHS 2010
Lognormal distribution fit
We fitted three parameter lognormal distributions to surgical times and turnover times
To study the lognormal goodness of fit we:
conducted Kolmogorov-Smirnov tests, and
performed two graphical analyses:
1. comparison of time histograms against the fitted lognormal distributions
2. probability plots to compare both the real data quantiles against the lognormal ones
ORAHS 2010
Validation
We selected a schedule composed of 2 CABGs performed by the same surgeon (256 historical records)
We obtained the probability distribution of this schedule using our methodology
We then simulated 1 million schedule durations
Finally we compared the simulated ones with the real durations
Percventile FW Real Min %
PC_5 6.46 6.75 -17.47 -4.31
PC_10 6.79 7.00 -12.45 -2.96
PC_15 7.02 7.17 -8.55 -1.99
PC_20 7.21 7.33 -7.33 -1.67
PC_25 7.38 7.42 -2.47 -0.55
PC_30 7.53 7.50 1.56 0.35
PC_35 7.67 7.75 -5.03 -1.08
PC_40 7.80 7.83 -1.91 -0.41
PC_45 7.93 8.00 -3.91 -0.81
PC_50 8.07 8.08 -0.97 -0.20
PC_55 8.20 8.25 -2.93 -0.59
PC_60 8.34 8.42 -4.70 -0.93
PC_65 8.48 8.50 -1.04 -0.20
PC_66_66 8.53 8.50 1.96 0.39
PC_70 8.64 8.67 -1.78 -0.34
PC_75 8.81 8.75 3.36 0.64
PC_80 9.00 9.08 -5.17 -0.95
PC_85 9.23 9.50 -16.46 -2.89
PC_90 9.52 9.83 -18.96 -3.21
PC_95 9.96 10.25 -17.15 -2.79
Differences
ORAHS 2010
Estimators for schedule duration
1. The “estimated average duration of the schedule” calculated as the sum of the average surgical times and turnover times in the schedule
this “empirical average” is equivalent to the mean value of the lognormal probability distribution of the schedule duration.
2. The second tertile cut-off point of the lognormal distribution obtained using Alvarez et al. (ORAHS 2008) methodology
the time taken for 2/3 of cases to be completed
ORAHS 2010
Lognormal distribution of the schedule
ORAHS 2010
4. Results
ORAHS 2010
Simultaneous schedule tracking
June-August 2009
138 scheduled blocks
43 blocks were excluded due to last minute changes to the schedule resulting in unpredicted delays or case cancellations
95 schedules were analyzed
42 (44.2%) comprised two sequential coronary artery bypass graft (1 to 3 bypasses) surgeries
ORAHS 2010
Prediction of the total duration
0.19 hrs 0.59 hrs
Average 2nd tertile cut-off point
ORAHS 2010
Overtime
37 (39.95%) schedules with overtime
average overtime was 65.81 minutes
standard deviation 50.33 minutes
range from 5 minutes to 170 minutes
The estimated average
predicted 44 overrun schedules
32 overran
The second tertile cut-off point
predicted 61 overrun schedules
35 overran
26 false predictions in total:
the real duration of the schedule was on average located at the 26.67% percentile point (standard deviation 17.53%).
ORAHS 2010
5. Discussion
ORAHS 2010
Lognormal fit
Graphical analyses and computer simulation validate the lognormal distribution even in those cases where the p-value of the traditional goodness of fit test rejects it
ORAHS 2010
Average
We validated the use of the average duration of a series of surgical cases and turnover times to estimate total schedule duration
We found the average value to be located between the 51% and 53% percentile points for 74.74% of the cases
ORAHS 2010
Overtime prediction capacity
Our results suggest that neither the estimated average nor the second tertile cut-off points alone are able to predict the need for overtime without considerable false positive results
As suggested by Alvarez et al. (ORAHS 2008) the combined use of the estimated average schedule duration and the second tertile cut-off point may help limit overtime expense
ORAHS 2010
Cancellations
An analysis of the cancellation data, where the second case was cancelled due to insufficient time, showed that most of the first cases exceeded the second tertile cut-off point
This is an expected effect of lognormal distributed operating times and cannot be prevented using this methodology
ORAHS 2010
6. Conclusions
ORAHS 2010
Decision rule
Approve an schedule only when the second tertile cut-off point is less or equal the block time length plus an “acceptable overtime” (e.g. 30 minutes for an 8 hours block time)
ORAHS 2010
Prediction of the Time to Complete a Series of Surgical Cases to Avoid Cardiac Operating Room Overutilization*
Rene Alvarez, MEng Centre for Research in Healthcare Engineering, Department of Mechanical and Industrial Engineering at the University of Toronto St. Michael’s Hospital, Toronto, ON, Canada Richard Bowry, MB BS FRCA St. Michael’s Hospital, Toronto, ON, Canada Faculty of Medicine, University of Toronto Michael Carter, PhD Centre for Research in Healthcare Engineering, Department of Mechanical and Industrial Engineering at the University of Toronto
* Accepted for publication in the Canadian Journal of Anesthesia