Top Banner
Pre-proposal Meeting Agenda Thursday May 14, 2009 US-95, Garwood to Sagle, District 1 GARVEE Transportation Program US-95, Garwood to Sagle, Athol Stage - Key No. 09791 US-95, Garwood to Sagle, Granite South Stage - Key No. 11894
10

Pre-proposal Meeting Agenda Thursday May 14, 2009 US-95, Garwood to Sagle, District 1 GARVEE Transportation Program US-95, Garwood to Sagle, Athol Stage.

Dec 27, 2015

Download

Documents

Charlene Powers
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Pre-proposal Meeting Agenda Thursday May 14, 2009 US-95, Garwood to Sagle, District 1 GARVEE Transportation Program US-95, Garwood to Sagle, Athol Stage.

Pre-proposal Meeting AgendaThursday May 14, 2009

US-95, Garwood to Sagle, District 1

GARVEE Transportation Program

US-95, Garwood to Sagle, Athol Stage - Key No. 09791US-95, Garwood to Sagle, Granite South Stage - Key No. 11894

Page 2: Pre-proposal Meeting Agenda Thursday May 14, 2009 US-95, Garwood to Sagle, District 1 GARVEE Transportation Program US-95, Garwood to Sagle, Athol Stage.

GARVEE Transportation Program

Agenda

1. Welcome & Introductions (Andrea Aliev)

2. GARVEE Program Current Status (Ed Randol)

3. General Project Information - Both projects (Amy Schroeder and Steve Alters)

4. KN 09791 US-95, Garwood to Sagle, Athol Stage (Steve Alters)

5. KN 11894 US-95, Garwood to Sagle, Granite South Stage (Steve Alters)

6. Questions – KN 09791 and KN 11894 (Steve Alters, Kimball Ohsiek, and Joe Samer)

7. Key Dates and Selection Criteria (Andrea Aliev)

Page 3: Pre-proposal Meeting Agenda Thursday May 14, 2009 US-95, Garwood to Sagle, District 1 GARVEE Transportation Program US-95, Garwood to Sagle, Athol Stage.

Garwood to Sagle corridor

• key map garwood_sagle.pdf

Page 4: Pre-proposal Meeting Agenda Thursday May 14, 2009 US-95, Garwood to Sagle, District 1 GARVEE Transportation Program US-95, Garwood to Sagle, Athol Stage.

Specific Information - Both Projects

• Ultimate Section – Four lanes with grade separated intersections

• Ultimate Typical Section – Four Lanes & 22-foot paved median– Garwood to Sagle environmental document (ROD December

2009)

• Initial Typical Section – Four Lanes & 4 to 14-foot paved median– US-95 Cooridor review (August 2008)

Page 5: Pre-proposal Meeting Agenda Thursday May 14, 2009 US-95, Garwood to Sagle, District 1 GARVEE Transportation Program US-95, Garwood to Sagle, Athol Stage.

Specific Information - Both Projects

• Schedule (Estimated)

– Selection of Design Consultant Team: June 2009

– Begin Intermediate Design, Consultant NTP: July 2009

– Intermediate Design Review: November 2009

– Complete Roadway Final Design: October 2010

– PS&E Approval: December 2010

Page 6: Pre-proposal Meeting Agenda Thursday May 14, 2009 US-95, Garwood to Sagle, District 1 GARVEE Transportation Program US-95, Garwood to Sagle, Athol Stage.

Athol Stage – KN 09791

Athol Stage.pdf

Page 7: Pre-proposal Meeting Agenda Thursday May 14, 2009 US-95, Garwood to Sagle, District 1 GARVEE Transportation Program US-95, Garwood to Sagle, Athol Stage.

Athol Stage – KN 09791

• ITD performing Preliminary design – Estimated completion June 2009

• ITD Bridge designing Athol Structure

• Known Utilities• Verizon• Kootenai Electric Cooperative, Inc.• Time Warner Cable• Avista Utilities – Gas• Linwood Estates – Water• Northern Lights Electric, Inc.• City of Athol

Page 8: Pre-proposal Meeting Agenda Thursday May 14, 2009 US-95, Garwood to Sagle, District 1 GARVEE Transportation Program US-95, Garwood to Sagle, Athol Stage.

Granite South Stage – KN 11894

Granite South Stage.pdf

Page 9: Pre-proposal Meeting Agenda Thursday May 14, 2009 US-95, Garwood to Sagle, District 1 GARVEE Transportation Program US-95, Garwood to Sagle, Athol Stage.

Granite South Stage – KN 11894

• ITD performing Preliminary design – Estimated completion June 2009

• Known Utilities• Verizon

• Sprint Cell Tower

• Linwood Estates – Water

• Northern Lights Electric, Inc.

• Trans Canada Gas Transmission Northwest