Pre-launch RF Optimisation Main Activities
42

Pre-Post Launch Optimization techniques

Jul 17, 2016

Download

Documents

Sadiq Mohammed

Stages of RF network optimization, before and after launch operations
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Pre-Post Launch Optimization techniques

Pre-launch RF Optimisation

Main Activities

Page 2: Pre-Post Launch Optimization techniques

Pre-launch Optimisation

▪ We are building a “Network” so get one layer done at a time▪ Set up Default RAN Parameters▪ Except for those we know already i.e Noise Rise Limit.▪ Get the Air interface Uu done first.▪ Do drive testing and look for good indicators to benchmark our

progress

Page 3: Pre-Post Launch Optimization techniques

Drive Testing purpose

▪ Drive testing can be done to:

▫ Evaluate initial Cell Plan (Pre-Launch)▫ Network Maintenance (Post-Launch)▫ Network Optimisation (Post-Launch)

▪ The main objectives are:

1- To collect the required KPI’s with enough accuracy2- To take the right number of samples under the right conditions3- To measure over representative areas (route planning)

Drive Testing and Post - Processing

Page 4: Pre-Post Launch Optimization techniques

Key Performance Indicators (KPI’s)

▪ Basic KPI’s for CPICH and SCH channels▫ RSCP▫ Ec/No▫ SIR▫ UL Tx Power

▪ Other important aspects to look at:▫ Peak, Aggregate values for the above KPI’s▫ Layer 3 messaging for Procedures▫ Mean Active Set

▪ To provide the required accuracy, good equipment is key…

Drive Testing and Post - Processing

Page 5: Pre-Post Launch Optimization techniques

When to use Scanners

▪ Use Scanners to:▫ Analyse signal quality and Interference▫ Provide fast and accurate measurements▫ Analyse Pilot Pollution issues▫ Measure all channels in the band▫ Provide L1 and L2 measurements

▪ Limitations of Scanners▫ Can’t make calls: no chance to analyse Accessibility▫ Can’t look at dropped calls: no chance to look at Retainability▫ Can’t analyse handovers

Drive Testing and Post - Processing

Page 6: Pre-Post Launch Optimization techniques

When to use Testmobiles

▪ Use Testmobiles to:▫ Get the customer’s perception of the network▫ Measure the Best Server▫ Check Neighbours and Handovers▫ To decode L2 and L3 messages

▪ Limitations of Test-mobiles▫ They see only what the NodeB tells them to look at▫ Can’t analyse Pilot Pollution▫ Can’t measure other servers▫ Limited Neighbour list

Drive Testing and Post - Processing

Page 7: Pre-Post Launch Optimization techniques

▪ Look at data summaries to get an overview of the drive results (software dependant)

▪ Look at coverage and other plots to find root causes

▪ Correlate predicted vs measured data

▪ Correlate Scanner and UE data

▪ Replay the data if necessary to obtain more information

Scanner File AnalysisDrive Testing and Post - Processing

Page 8: Pre-Post Launch Optimization techniques

▪ Look at data summaries to get an overview of the drive results (software dependant)

▪ Look at Layer 3 messaging to find root causes

▪ Analyse signalling flows

▪ Correlate Scanner and UE data

▪ Replay the data if necessary to obtain more information

UE File AnalysisDrive Testing and Post - Processing

Page 9: Pre-Post Launch Optimization techniques

Drive Test Team

▪ Drive representative routes gathering:▫ Scanner data (rooftop mounted calibrated antenna)▫ Mobile (UE) data (test mobile on rear seat connected to

laptop)▫ Scanner provides accurate measurements of pilot strength

etc.▫ UE data provides evidence of call success and uplink Tx

power.

▪ Drive test data is passed to the SAT team.

Drive Testing and Post - Processing

Page 10: Pre-Post Launch Optimization techniques

Team Work - Example

▪ Drive test reveals calls dropped in an area where best pilot is very low.

▪ SAT team checks with configuration engineer regarding cell status

▪ Check made with planning tool to see whether problem is “predictable”

▪ If no obvious reason, SAT directs drive test team to investigate.

Drive Testing and Post - Processing

Page 11: Pre-Post Launch Optimization techniques

Team Work – Example (continued)

▪ Drive test team report that an obstacle/terrain feature exists that is not on map data.

▪ SAT team recommend solution (antenna height/orientation)

▪ Effect checked on planning tool

▪ Configuration Engineer actions change and reports when implemented.

▪ SAT instructs drive test team to re-examine

Drive Testing and Post - Processing

Page 12: Pre-Post Launch Optimization techniques

Pre-launch (coverage)

▪ Optimising Coverage and Ec/Io▪ Control of cell antenna radiation is crucial to achieving designed

capacity. In particular “high sites” can dramatically reduce the capacity of a network.

▪ It becomes more difficult to achieve high Frequency Re-use Efficiency as cells are packed closer together.

▪ Problems only become apparent as system becomes heavily loaded.

Page 13: Pre-Post Launch Optimization techniques

Pre-launch (coverage)

▪ If a mobile experiences comparable path loss to a number of cells, problems can arise through no single cell dominating.

▪ Problems include: low Ec/Io; low capacity on downlink; frequent updates to membership of the active set

▪ Pilot Pollution

Page 14: Pre-Post Launch Optimization techniques

Neighbours Objectives

▪ Maintain a reasonable level of Soft and Softer Handover overhead: 30%-40%

▪ Minimise unnecessary handovers

▪ Minimise inter-technology handovers UMTS-GSM-UMTS

▪ KPI’s▫ Mean number of terminals in Soft and Softer Handover▫ Mean number of inter-technology handovers

Optimisation Overview

Page 15: Pre-Post Launch Optimization techniques

Interference Objectives

▪ Avoid Scrambling Code interference

▪ Minimise inter-system interference (UMTS-GSM)

▪ Minimise inter-operator interference (UMTS-UMTS)

▪ KPI’s▫ Pilot Coverage overlaps▫ Adjacent channel interference power ratio (ACIR)

Optimisation Overview

Page 16: Pre-Post Launch Optimization techniques

Pilot Ec / N0 of cell 1

Pilot Ec / N0 of cell 2

Pilot Ec / N0 of cell 3

Reporting_range- Hysteresis_event1A Hysteresis_event1C

Reporting_range+ Hysteresis_event1B

TTT TTTTTT

Connected to cell 1

Event 1A=add cell2

Event 1C=replace cell 1 with cell 3

Event 1B=remove cell 3

WCDMA IF Soft Handover Algorithm

Note: Maximum number of SC in AS is 2

Connected to cell 1 and 2

UTRAN Parameters

Page 17: Pre-Post Launch Optimization techniques

Pre-launch (hard handover)

▪ Customers transferring to 3g should:▫ gain access to video telephony services▫ benefit from higher data rates for GPRS and HSCSD▫ experience a service “at least as good as GSM” for voice services

▪ Satisfying this last requirement will necessitate successful inter-technology radio access test handovers occurring.

Page 18: Pre-Post Launch Optimization techniques

Pre-launch (hard handover)

▪ Active UE will hand over to GSM when Ec/No thresholds are met.

▪ Ec/No should be logged.

Ec/No

time

Enter compressed mode

Perform Hand Over

2d

3a

Page 19: Pre-Post Launch Optimization techniques

Pre-launch (hard handover)▪ Active UE will not hand back to UMTS network.

▪ Idle UE can undergo reselection in both directions.

▪ Compressed Mode (“slotted mode”) is needed when making measurements from another frequency without a full dual frequency terminal.

▪ Secondary issues: compressed mode requires higher power (or reduced throughput)

▪ Fast power control loop is interrupted.

▪ At cell edge, compressed mode overhead estimated to be between 2 and 4 dB.

Page 20: Pre-Post Launch Optimization techniques

Pre-launch (handover)

▪ In active mode: drive will be uni-directional▪ In idle mode: drive should be bi-directional▪ Active mode: make a continuous call

▫ monitor for IRAT hand over (or call drop)▫ monitor rapid GSM hand overs after IRAT (10 seconds)▫ check GSM network sustains connection (30 seconds)

Page 21: Pre-Post Launch Optimization techniques

Different strategies for HHO  Event RSCP (dBm) TTT (msec) Ec/Io (dB) TTT (msec) Hysteresis

Operator1

           

e1e -105 640 -12 640 0

e1f -108 100 -15 100 0

           

Operator 2

e1e -107 1280 -9 1280 0

e1f -110 640 -13 320 0

           

  Tx Power Thres (dBm) TTT (msec) Hysteresis    

           

e6a 18 0 0    

e6b 18 320 0    

UTRAN Parameters

Page 22: Pre-Post Launch Optimization techniques

  Event CPICH Ec/Io (dB) TTT (msec) Hysteresis  

Operator 3

         

e2d -10 1280 0  

e2f -9 320 0  

  UMTS CPICH Ec/Io (dB) GSM RSSI (dBm) TTT (msec) Hysteresis

e3a -12 -95 100 0

Different Strategies fo HHO (2)

UTRAN Parameters

Page 23: Pre-Post Launch Optimization techniques

Pre launch (scrambling codes)

▪ Scrambling code planning▪ 64 Groups of 8 codes▪ If the number of groups and codes can be limited, advantages

will result.

▪ If fewer codes per group are used, then the mobile will find its best server more rapidly.

▪ Also, the fewer the codes per group, the less processing that has to be done by the mobile in general. This increases the battery life.

▪ Handover, is made faster and more reliable by limiting the number of groups.

▪ The challenge is to avoid interference whilst limiting the number of codes and the number of groups.

Page 24: Pre-Post Launch Optimization techniques

Pre-launch (neighbours)

▪ Likely strategy:▪ Make co-sited GSM cell a neighbour▪ Make neighbours of this cell a neighbour▪ Manually adjust “as appropriate”.▪ Again, drive test data will be used to tune the list.▪ Big message “If we missed a neighbour it becomes a

interference, hence capacity is decreased”

Page 25: Pre-Post Launch Optimization techniques

Incorrect Neighbours

Neighbours and Scrambling Codes

▪ Similar case to “Too many Neighbours”, though here it’s not the quantity but the quality of the Neighbours that’s a problem

▪ Some Neighbours may not be strong candidates, and some strong pilots may be left out.

▪ There may be a SC from a distant boomer site that need to be removed

▪ Detected through drive testing and Post-Processing

Page 26: Pre-Post Launch Optimization techniques

Pre-launch (test-mobile measurements)

▪ Test-mobile measurements, depending on the availability of engineering mobiles, should allow measurement of:

▫ CPICH and P-CCPCH availability▫ DCH - Dedicated channel DL performance ▫ Cell dominance▫ Active set size▫ Required UL Tx Power

Page 27: Pre-Post Launch Optimization techniques

Pre-launch (test-mobile)

▪ Potential for inconsistency:▫ Different (uncalibrated) antenna/feeder▫ Different drive test route▫ Different UE speed over the route (hold ups at traffic

lights etc.)▫ Different analyser being used.▫ Different level of network loading (affects Ec/Io).

Page 28: Pre-Post Launch Optimization techniques

Pre-launch (cluster optimisation)

▫ Procedure▪ Identify size and location of clusters

▪ Define Cluster characteristics▫ Coverage, Interference, Handover region size and location▫ Neighbour list assessment▫ Access, handover and call failures

▪ Take Measurements▫ Drive tests▫ Ec/Io, pilot power, UE TX Power, Neighbours, call success drops and

Handover stats.▫ Service allocation, FER/BLER, Throughput, Max and Av. BER, Delay

▪ An engineer will have responsibility for a particular cluster.

Page 29: Pre-Post Launch Optimization techniques

Pre-launch (Benchmark)

▪ Typical Criteria Unloaded:▫ 95% of area delivers pilot strength of >-85 dBm (dense

urban) or -91 dBm (urban).▫ 95% of area covered should register Ec/No better than -10

dB.

Page 30: Pre-Post Launch Optimization techniques

Pre-launch (Benchmark)

Ec/Io >-12 dB 99.91%Ec/Io >-11 dB 99.44%Ec/Io >-10 dB 98.14%Ec/Io >-9 dB 94.97%Ec/Io >-8 dB 89.44%Ec/Io >-7 dB 81.22%Ec/Io >-6 dB 68.83%Ec/Io >-5 dB 53.66%Ec/Io >-4 dB 34.94%Ec/Io >-3 dB 13.46%

•Typical drive test result from optimised cluster.

Page 31: Pre-Post Launch Optimization techniques

Pre-launch (interference)

▪ Identify areas of low Ec/Io

▪ Examine pilot levels (there will probably be more than three).

▪ Identify any unwanted pilots (from cells that are not intended to provide coverage in that area).

▪ Reduce level of these pilots (usually by down-tilting) be aware of the effect on coverage in service area of cell: use planning tool

Page 32: Pre-Post Launch Optimization techniques

Pre-launch (Functional testing)

▪ When carrying out cyclic testing with AMR or VT the Call Completion Success Rate (CCSR) is the most significant parameter.

▪ When testing packet traffic, the Context Activation Success Rate (CASR) and the throughput/time to download are of great interest.

▪ Agreement must be made on suitable timeouts: e.g. how long should the UE attempt to establish a call (20 seconds?) before a failure is registered. Likewise for context activation.

▪ Driving till drop checks for continuous coverage requirements, neighbour planning and hand over procedures.

Page 33: Pre-Post Launch Optimization techniques

Pre-launch (handset testing)

▪ On some occasions failure may be specific to a handset.▪ Perhaps the handset does not respond to a paging command or other

message.▪ Perhaps the handset drops a call in an environment where other

handsets do not drop calls.▪ UMTS technology is still improving.

Page 34: Pre-Post Launch Optimization techniques

Conclusion -What is different in UMTS

▪ Single Frequency▫ Cannot frequency plan around problems caused by “rogue” sites.▫ Need to optimise clusters of sites rather than single cells.

▪ Level of loading affects performance▫ Cell activity affects coverage and throughput.▫ Interpretation of measurements required.

▪ Flexible structure sensitive to small changes in performance

▫ Air interface performance directly affects capacity and coverage.

▪ Mixed Services

Page 35: Pre-Post Launch Optimization techniques

Pre-launch KPIs

▪ Coverage RSCP▪ Ec/Io▪ RRC success rate▪ SHO %▪ HHO failed %▪ Average RACH, FACH, PCH, UL/DL DCH throughput [kbps]▪ PDP Context Activation set up time▪ 10% retransmissions for PS▪ Latency for PS

Page 36: Pre-Post Launch Optimization techniques

Post-launch Optimisation

Main Activities

Page 37: Pre-Post Launch Optimization techniques

Post-launch Optimisation

“Proper optimisation”

▪ Increasing network capacity

▪ Serving hotspots

▪ Increasing coverage for higher data rate services

▪ maximising return on investment

Page 38: Pre-Post Launch Optimization techniques

Post-launch Optimisation

This will involve

▪ Adding more sites

▪ Further sectorisation of existing sites

▪ Optimising RAN parameters

▪ Reducing interference

▪ Utilising more than one carrier

▪ Implementing a hierarchical cell structure

▪ Providing indoor solutions

Page 39: Pre-Post Launch Optimization techniques

Post-launch

▪ Assuming the network has been launched and:▫ Coverage is “OK”.

▫ Higher services coverage is “patchy”.

▫ Coverage prioritised over capacity

▪ Aim is that we,

▫ Increase Network Capacity

▫ Increase Coverage for high resource services

▫ Improve quality of service offered to users.

Page 40: Pre-Post Launch Optimization techniques

Post-launch (hard capacity)

▪ There is no value in increasing the “soft” capacity of the air

interface above the network’s “hard” capacity.

▪ Often the network will be launched with a low level of “hard”

capacity.

Page 41: Pre-Post Launch Optimization techniques

Post-launch (remarks)

▪ Optimisation is a cycle▪ UMTS is being optimised with a much statistic analysis

approach.▪ Other things to consider – protocols and applications this is

something new for RF Engineers.

Page 42: Pre-Post Launch Optimization techniques