1 public Practical Guidance for Large Scale Migrations
1 publicPractical Guidance for Large Scale Migrations
Practical Guidance for Large Scale Migrations
SharePoint vNext: The true Story of a bulk migration
Andries den Haan
November 2014
A brief personal introduction
• Working in IT since 1999
• Passionate about portals, collaboration and social
media
• Certified expert on Microsoft SharePoint products and
technologies
• Focus on business processes optimization,
platform infrastructure, migrations and governance
• Contact details:
• www.twitter.com/awdhaan
• www.linkedin.com/in/andriesdenhaan
• www.slideshare.net/awdhaan.
3 publicPractical Guidance for Large Scale Migrations
…and working at KPN Consulting
• Veterans when it comes to the web, enterprise
search, corporate portals, content management
and information worker solutions
• The current Web, Apps and Data team is the
typical “Gallic village” within the greater KPN
• Part of Application Services
(ERP/Applications/Testing)
• Not only SharePoint, but also:
• Mobile Apps (TEDx Amsterdam, Bijenradar)
• Application frameworks (Amber Alert)
• Content management (Tridion, Orchard).
4 Practical Guidance for Large Scale Migrations public
What you can expect from this session
• A true story on how we approach(ed) large scale
legacy SharePoint migration projects
• How to deal with common pitfalls
• Working with 3rd party tools and extending them to fit
our needs
• Lessons learned on choices we’ve made and issues
we solved along the way.
5 publicPractical Guidance for Large Scale Migrations
Agenda
• Setting the scene
• Our approach
• Tooling choices
• Challenges along the way
• Lessons learned
6 publicPractical Guidance for Large Scale Migrations
Our mission: “Migrate 4 TB in 2.5 Months!”
7 publicPractical Guidance for Large Scale Migrations
Our mission: Migrate 4 TB in 2.5 Months!
• Andries den Haan (project leader, lead consultant)
• Mathijs Vlasveld (SharePoint developer)
• Terence Bahlen (SharePoint developer)
• Neal de Jel (SharePoint developer).
Prior to the project, a site survey was performed
to gain insight on the state of things
• Microsoft SharePoint Portal Server 2003
• Some metrics:
• 3-tier topology (2 WFE’s, 1 APP)
• Total data volume: 4.5 TB
• Approx. 12.000 site collections
• Data gathered via:
• Microsoft tooling (stsadm)
• Database queries (and being naughty by doing so)
• Typical tooling (e.g. Windiff, SPSitemanager)
• Server, web.config scan (manual )
• Site owner interviews (e.g. for special sites).
8 publicPractical Guidance for Large Scale Migrations
The site survey showed some interesting
challenges to be expected during the migration
• Support effort focused on availability
• No governance model:
• Unlimited site growth
• 2 GB file uploads possible
• No blocked file types
• Multiple site collections above 300 GB
• Large sites within the same database
• A fair amount of orphaned items
• Custom site definitions and web parts
(used in over 6.000 site collections).
9 publicPractical Guidance for Large Scale Migrations
Main project drivers
10 publicPractical Guidance for Large Scale Migrations
Main project drivers:
• Clean-up and restructure required
• The existing SharePoint version was not able
to keep up with evolving user requirements
• Software and hardware end-of-life (duh!)
• Improve on governance and support.
Customer expectations were straight forward!
11 publicPractical Guidance for Large Scale Migrations
Customer expectations
were straight forward!
The migration was to be finished before the end
of the year!
12 publicPractical Guidance for Large Scale Migrations
The migration was to be finished
before the end of the year!
The urgency to migrate was also driven by the
state
13 publicPractical Guidance for Large Scale Migrations
The urgency to migrate was also driven by the state of the data:
a warehouse in need of a clean-up and restructure!
Our customer’s expectations were clear and
simple, avoid disrupting daily business!
14 publicPractical Guidance for Large Scale Migrations
Business continuity was key:
Avoid disrupting daily business!
Risks
15 publicPractical Guidance for Large Scale Migrations
This mission was not without impediments:
• No changes to the source system allowed!
• Limited support on the current environment
• Custom coded site definitions and web parts
• Migration performance (and how to plan on this)
• How to handle obsolete data or sites without ownership.
Our approach was based on an extensive
preparation phase and Agile SCRUM principles
16 publicPractical Guidance for Large Scale Migrations
Preparation
(site survey)
Go Live
Start
locks
and
migrations
Daily
stand-up
Prepare
batch jobs
Pre and post
migration issue
related
tasks
Monitoring
and sleep
Migration
Result
checks
Daily cycle
Post-migration
(decommissioning)Ongoing migrations
Why did we choose 3rd party tooling to support
the migration?
• No direct upgrade path from SharePoint Portal Server 2003 to SharePoint Server
2010
• Required clean-up and restructure
• Pressure to deliver within a short timeframe
• Migration requirements:
• Preservation of (system)metadata and permissions
• Speed: optimize the throughput to meet our deadline
• Mapping of old and new sites or definitions, content types, lists or web parts
• Granularity (sometimes only a sub site/list/specific item may require migration)
• Filtering (e.g. on date or other properties)
• Support for full and incremental (bulk) migrations.
17 publicPractical Guidance for Large Scale Migrations
The AvePoint DocAve platform provided us with
the tools needed to get the job done
• Track record
(including large scale Microsoft IT migration)
• Rich set of migration (and content mgt.) capabilities
• Acceptable software costs
• Warm response to vendor inquiry
• Handling of support requests prior and during the
project.
Extensions required to optimize the bulk migration process!
18 publicPractical Guidance for Large Scale Migrations
We built a custom batch builder tool to support
planning and reporting of ongoing migrations
We extended the DocAve tooling to optimize bulk migration planning and reporting:
• Import unscheduled sites from the migration to-do list matching the amount of data
that could be processed within a service window
• Choose target database (allowing for redistribution of site collections)
• Create DocAve batch migration configuration job files for the selected sites
• Check on potential issues prior to migration
• Generate mapping files for automated redirects and various scripts
• Read back migration job reports from DocAve and update the To-do list.
19 publicPractical Guidance for Large Scale Migrations
A public to-do list allowed the migration team to
plan bulk migrations and report on progress
• Just a SharePoint list with relevant columns to describe the state of the sites in the
context of the migration
• Sites may have an (un)scheduled, migrated or ignored state
• Site owners able to check planning and migration result of sites through search
• Open communication to all stakeholders.
20 publicPractical Guidance for Large Scale Migrations
The same list was also used to report progress
to the project owner
• The project owner had a transparent
view on migration progress and
possible issues on a daily basis
• The list was also used to comply with
the acceptance criteria for project
closure (our definition of done).
21 publicPractical Guidance for Large Scale Migrations
Our Batch builder tool supports the selection of
sites from the to-do list for bulk job creation
22 publicPractical Guidance for Large Scale Migrations
The Batch builder tool also provides the creation
of other batch files or data checks
• Setting sites to read-only or (un)lock scripts
• mappings.csv for URL redirection or sites.txt to activate a notification bar feature
• Check if sites exists or other pre-checks (e.g. too long URL’s or large files/lists) and
export reports to share with site owners or the migration team.
23 publicPractical Guidance for Large Scale Migrations
After the migration, the Batch builder tool
provides a means of bulk reporting
• Import DocAve migration job reports to update the to-do list for successful, failed or
migrations with exceptions and overall progress reporting
• Additionally add comments about e.g. exceptions, delayed go live or reschedule.
24 publicPractical Guidance for Large Scale Migrations
Our migration setup was built for both
performance and flexibility
25 publicPractical Guidance for Large Scale Migrations
SharePoint 2003
Collaboration farm
DOCAVE
AGENT
DOCAVE
AGENT
Batch builder
tool
SharePoint 2010
Collaboration farm
DOCAVE
AGENT
DOCAVE
AGENT
WFE1
WFE2
WFE1
WFE2
3.75 GB per hour per agent set
To-do listSharePoint 2010
Legal content farm
DOCAVE
AGENT
DOCAVE
AGENT
WFE1
WFE2
DocAve
management
server
A custom C# script in the global.asax on each
source WFE selectively redirects user requests
• Custom code was added to the
global.asax of each web application in
the source environment
• Using a mappings.csv file with a source
and target URL value pair on each line
• All requests for a specific URL (and
below) were redirected to the new site
• Appended with each new migration
• Low server resource usage
(tested with 10.000+ entries)
• Not applicable to web folder mappings.
26 publicPractical Guidance for Large Scale Migrations
Migrated sites temporarily show a custom
notification bar linking to the migration info site
• Site collection feature displaying a custom message in the notification bar area
• Only visible for migrated sites (not for new ones)
• Bulk feature activation using the Batch builder tool
• Removed after the migration project finished.
27 publicPractical Guidance for Large Scale Migrations
Migrations performed via a standard operating
procedure
• Prior to the migration, each site collection is set to read-only
• To finalize a successful migration, no-access locks and redirects are set for the old
sites and notification bars enabled for the new sites
• In case of a roll-back, the redirect and notification bar functions are not enabled and
the source site is set back to read/write.
28 publicPractical Guidance for Large Scale Migrations
Content
freeze
Execute
migration job
Enabled redirect
and notification
bar
Go live!
Validate
migration-
result
Prepare
migrations
The daily cycle for the team during the 2.5 month
migration period
• Daily migrations (standard sites) from Monday to Friday (18:00-7:00)
• Weekends (special cases or large sites)
• Last 2 weeks: Legal case sites (24/7).
29 publicPractical Guidance for Large Scale Migrations
7:00 8:00 16:009:00-15:00
Migration result checks
Daily check-in (stand-up)
Pre and post migration issue related tasks
Prepare batch jobs
18:00
Start locks and migrations
Our challenges and solutions
30 publicPractical Guidance for Large Scale Migrations
Common challenges along the way:
• Extra large file uploads not possible in the new farm
• Blocked file types (so MP3’s, .EXE files, VB scripts, …)
• Supersized site collections (over 200 GB)
• Large lists (slow migration).
But we also had some unexpected challenges
For reasons still unknown the migration of a large site
collection (100+ webs) had an unexpected result:
• Each library URL in the site collection was named after the
first folder or item within that library
• Resolved by using a database query (being naughty again )
in the source system to get the original library URL’s and
PowerShell to “system”update the library URL’s in bulk ($list.RootFolder.MoveTo($listUrl))
• Apart from this the migration was successful .
31 publicPractical Guidance for Large Scale Migrations
We saved the biggest challenge for last:
migrating 5.000+ customized legal case sites
• 24/7 migration jobs during 15 days for only 100 GB (# of objects overrules size)
• Some jobs spanning multiple days
• Site definition/content type/field type mapping and obsolete web part removal.
32 publicPractical Guidance for Large Scale Migrations
Highlights of a successful project
• 2.220 sites (4.1 TB) migrated in 2.5 months
• 5.681 customized sites migrated within the last 2 weeks
• Creative solutions for (un)expected challenges
• Project delivery within time and budget
• Effective collaboration with the other teams:
• Adaptation
• Infrastructure
• Offshore support
• AvePoint support.
33 publicPractical Guidance for Large Scale Migrations
The secret of our success is based on a small
dedicated team with a clear mission and process
• Customer oriented SCRUM-like approach
(business continuity)
• Sufficient and open communication to site owners and
stakeholders
• A very robust, but flexible migration process
• Ensuring the right tools for the job (consider homemade)
• Frequent team stand-up meetings regarding progress,
impediments and solutions
• Leveraging our knowledge, creativity and Windows
PowerShell to solve the encountered issues
• Reusable for an upcoming SharePoint 2007-2013
migration.