Project XXXX Service Tech Production Planning Module __________________________________________________________________________________________ ________ Caritor Protected Page 1 of 22
Sep 04, 2015
1
EBP2.0 Release 2 ------ Heading
Project XXXX Service Tech
Production Planning Module
TABLE OF CONTENTS
I. Define MRP controllers.
II. Shop Floor Control.
III. Define Order Type.
IV. Define Order Type dependent parameters.
V. Define Checking Control.
VI. Define Scheduling Parameters for Production Orders.
VII. Define Confirmation Parameters for Order types.
VIII. Define Number ranges for Order Types.
IX. Define Task list assignment for Material Types.
Master Data
Define MRP controllers
The person responsible for a group of materials in MRP in a plant or company.
Material that takes part in material requirements planning must be assigned to an MRP controller.
MRP controller has to be defined for Materials for which MRP run is required. It can be a person or group of persons.
1. Title: Define MRP Controllers
2. Short Description: Plant 3001, Plant 3010, Plant 3020, Plant 3050, Plant 3060, Plant 3070,Plant 3080
3. IMG Path: Implementation Guide for R/3 Customizing(Production( Production planning( Master production scheduling (Master Data ( Define MRP controllers
4. Transaction Code: SPRO
MRP controllers Assigned to Various Plants
Shop Floor ControlDefine Order TypeA tool that categorizes orders according to purpose.
The order type contains information that is necessary for managing orders.
Example
Production orders
Maintenance orders
Capital investment orders
An order type has the controlling parameters of an order.
With a particular order type we can define,
Controlling partner update
Settlement profile
Status Management
1. Title: Define Order Type
2. Short Description: Order Types were created for 7 plants of XXXX Service Tech Company.
3. IMG Path: Implementation Guide for R/3 Customizing(Production( Shop Floor Control( Master data( Order( Define Order Types
4. Transaction Code: OPJH
Production Order Types
Rework Order Types
Define Order Type dependent parameters
Here we are defining the parameters that are valid for each order type and plant.
1. Title: Define Order Type dependent parameters
2. Short Description: Order Type dependent parameters were defined for order types
3. IMG Path: Implementation Guide for R/3 Customizing(Production( Shop floor control( Master data( Order ( Define order type dependent parameters
4. Transaction Code: OPL8
Define Checking Control
For a plant-order type combination we can define a checking control.
We can specify the following actions,
Whether an availability check is to be carried out (During creation or release an order)
Whether an availability check is to be carried out when we save an order that has been created or released
Which checking rule is to be used
What effect a material shortfall is to have on the creation or release of an order (error or warning message)
1. Title: Define Checking Control
2. Short Description: Checking controls have been defined for order creation, order release.
3. IMG Path: Implementation Guide for R/3 Customizing(Production( Shop Floor Control( Opearation ( opearations ( Availability check ( Define Checking control
4. Transaction Code :OPJK
Checking Control assigned to Plant 3001
Checking Control assigned to Plant 3010
Checking Control assigned to Plant 3020
Checking Control assigned to Plant 3060
Checking Control assigned to Plant 3080
Checking Control
Scheduling Parameters for Production orders
Scheduling Parameter for Plant 3001
Scheduling Parameter for Plant 3010
Scheduling Parameter for Plant 3020
Scheduling Parameter for Plant 3050
Scheduling Parameter for Plant 3060
Scheduling Parameter for Plant 3070
Scheduling Parameter for Plant 3080
Define Parameters for Order Confirmation
Confirmation Parameters for Plant 3001
Confirmation Parameters for Plant 3010
Confirmation Parameters for Plant 3020
Confirmation Parameters for Plant 3050
Confirmation Parameters for Plant 3060
Confirmation Parameters for Plant 3070
Confirmation Parameters for Plant 3080
Routing Data for material Types
The task list type N has to be assigned to the new material types created
HAL1
FERT1
Number Range assignment for Production Order Types
Business Function: 1
Rework Order types
Business Function: 2
DateRELIANT Confidential & Privileged Draft 00Page 1
__________________________________________________________________________________________________
Caritor ProtectedPage 2 of 18