One Team: Relevant, Ready, Responsive, Reliable 1 Improve Hurricane Improve Hurricane Protection to the Protection to the IHNC Partnering IHNC Partnering Update Brief Update Brief August 21, 2007
15
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: PowerPoint

One Team: Relevant, Ready, Responsive, Reliable

1

Improve Hurricane Improve Hurricane Protection to the IHNC Protection to the IHNC Partnering Update BriefPartnering Update Brief

August 21, 2007

Page 2: PowerPoint

One Team: Relevant, Ready, Responsive, Reliable2

Interim Project Update

Permanent Solution Project Update

Draft Request for Proposal (RFP) Process

Project Cooperation Agreement (PCA)

Agenda

Page 3: PowerPoint

One Team: Relevant, Ready, Responsive, Reliable3

No option achievable before Hurricane season 2009 Raising the walls

Constructability challenges Limited Right of Way and room for construction

8.5 miles total of floodwalls and gates 4.2 miles South of I-10 overpass on IHNC

Impacts on commercial industry Temporary Barge Gate

Constructability challenges Akin to permanent structure

Potential for NEPA impacts Impacts on navigation

Constrictions Potential for NEPA impacts Impacts on navigation Real Estate

Interim Protection Challenges

Page 4: PowerPoint

One Team: Relevant, Ready, Responsive, Reliable4

Barge Gate Reviewing designs based on updated 100yr elevation design criteria

Differential head, Impact loads Required Real Estate owned by NASA, Port of New Orleans

Allows for expedited real estate acquisition process ERDC optimizing channel opening for velocity and navigation

Goal is to eliminate center pier and one bulkhead Eases navigation and environmental impact concerns

MVN/HPO Environmental determining best method to achieve NEPA compliance – ERDC analysis is crucial

HPO Contracting determining best expedited means for contract mechanisms MVN H&H modeling inundation maps for 4 scenarios (Current conditions, With

Barge Gate, Walls S of I-10 at el. 15’, All walls on IHNC at el. 15’) Working in conjunction with A-E to refine cost, all aspects of design and

construction schedules, and ways to expedite delivery Final Schedule and Cost analysis to be complete once refined designs are

complete – joint HPO/A-E effort Goal remains all efforts complete NLT 31 AUG 07

Interim Protection Path Ahead

Page 5: PowerPoint

One Team: Relevant, Ready, Responsive, Reliable5

100-yr IHNC Project

Provide a 100-year Level of Protection to the IHNC from

Hurricane-Induced Storm Surges by the 2011 Season

Page 6: PowerPoint

One Team: Relevant, Ready, Responsive, Reliable6

Project Status

Advertised Phase One July 2nd

Short-listed to the four most qualified firms: Tetra Tech, EC, Inc Kiewit Federal Group, Inc Shaw Environmental & Infrastructure, Inc Washington Group International, Inc/Interbeton, Inc JV

Next step – Phase Two Draft RFP

Page 7: PowerPoint

One Team: Relevant, Ready, Responsive, Reliable7

Timeline (est.)

Issue Notice to Proceed for Construction 1 Sept 08

Phase 1 – Request for Proposals

NEPA / IER complete June 08

PCA Amended (if needed) per 30% Design

Amended PCA Executed

Real Estate Acquisition complete by Dec 08

Phase 2 – Request for Proposals (Issue Sept 07)

Award Design-Build Construction Contract Mar 08

Contractor Prepares 30% Design by June 08

Complete by 1 Jun 2011

Construction

Final Funding Notification

Project Cooperation Agreement (PCA) Negotiation

PCA Executed Feb 08

Contractor Completes Design

Phase II RFP Issued Sept 24, 2007

Page 8: PowerPoint

One Team: Relevant, Ready, Responsive, Reliable8

Draft RFP Process Issue draft RFP to local sponsor and short-

listed firms this week

Meet individually with firms 4-6 Sept

Meet with local sponsor Sept 11th to review Draft RFP comments

Final RFP pre-release meeting with local sponsor Sept 18th

Page 9: PowerPoint

One Team: Relevant, Ready, Responsive, Reliable9

Phase II Proposals

Open to all alternatives

No navigation requirement on the MRGO Will modify if Congress doesn’t act Concept design complete for deep-draft nav

No assumptions for Seabrook

Bayou Bienvenue must remain open

Page 10: PowerPoint

One Team: Relevant, Ready, Responsive, Reliable10

Alternative A

IHNC Alternative Concepts

Alternative B

Alternative C Alternative D

Alternative A

Page 11: PowerPoint

One Team: Relevant, Ready, Responsive, Reliable11

NEPA Alternatives

Page 12: PowerPoint

One Team: Relevant, Ready, Responsive, Reliable12

Evaluation Criteria

Most Probable Schedule

Technical Solution

Management Approach

Most Probable Lifecycle Cost

Socioeconomic Plan

Page 13: PowerPoint

One Team: Relevant, Ready, Responsive, Reliable13

Technical Performance Specs

100-year design elevations

Navigable structures

Barriers (walls, levees, etc.)

Minimize OMRR&R

Training Requirements

Environmental Requirements

Construction Management & Safety

Page 14: PowerPoint

One Team: Relevant, Ready, Responsive, Reliable14

Project Cooperation Agreement (PCA)

Project is fully funded by U.S. Government

USACE shall afford the Non-federal sponsor (DOTD/ SLFPAE) the opportunity to review and comment on all aspects of the project

Non-federal sponsor responsibilities: Provide all non-federal government lands Secure commandeering order(s) (if available) to all private lands Operate, maintain, repair, rehabilitate, replace project

Hold and save the Government free from damages

Page 15: PowerPoint

One Team: Relevant, Ready, Responsive, Reliable15

Questions/Comments