Public Library Construction Grant Program Grace Kelly Construction Program Manager New York State Library/Division of Library Development
43
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: PowerPoint

Public Library Construction Grant Program

Grace KellyConstruction Program Manager

New York State Library/Division of Library Development

Page 2: PowerPoint

WHAT IS THE “NYS PUBLIC LIBRARY CONSTRUCTION GRANT PROGRAM” ? NYS Education Law 273-a

Education Department Commissioner’s Regulation 90.12

Page 3: PowerPoint

WHO CAN APPLY FOR A GRANT?

Any public library or public library system

chartered by the NYS Regents or

established by an act of the NYS Legislature

Page 4: PowerPoint

HOW DO YOU APPLY?

Application materials are on the NYSL website: http://www.nysl.nysed.gov/libdev/construc/index.html

Public Library Systems role: Ed Law 273-a(2)

Page 5: PowerPoint

HOW MUCH MONEY IS AVAILABLE? HOW MUCH CAN ONE LIBRARY OR SYSTEM APPLY FOR? Annual budget appropriation

Statewide Allocation of available funds

Max--50% of total project approved costs

Page 6: PowerPoint

APPLICATION

Applicant information Building information Project details Assurances

Page 7: PowerPoint

APPLICANT INFORMATION

Page 8: PowerPoint

BUILDING INFORMATION

Page 9: PowerPoint

BUILDING INFORMATION

Leased buildings14. Library building is:

_____ Owned by applicant

______Leased by applicant with a minimum of 10 years lease term from the date of anticipated project completion.

______Otherwise legally available (i.e., situated in a local municipal building)

(If leased or otherwise legally available, see application instructions for additional details.)

15. Library site is:

_____ Owned by applicant

_____Leased by applicant with a minimum of 10 years lease term from the date of anticipated project completion.

_____Otherwise legally available (i.e., situated in a local municipal building)

(If leased or otherwise legally available, see application instructions for additional details.)

Page 10: PowerPoint

BUILDING INFORMATION

State Historic Preservation Office

CONTACT: (518) 237-8643: press “0” to be directed to correct regional office

Page 11: PowerPoint

BUILDING INFORMATION

SED Office of Facilities Planning

Contact (518) 474-3906 to be directed to correct Project Manager

Page 12: PowerPoint

PROJECT DETAILS

Page 13: PowerPoint

PROJECT DETAILS - Cost

Estimated project costs

Page 14: PowerPoint

PROJECT DETAILS- Funding

Funding Source

Page 15: PowerPoint

PROJECT DETAILS – Dates

Project start and completion dates

3-year period starting July 1, 2009

23. a. This project is expected to start on or before _________________

b. This project was started on _______________and is not complete at the time of this application.

24. This project is expected to be completed by ___________________.

Page 16: PowerPoint

CONSTRUCTION PROJECT NARRATIVE

Page 17: PowerPoint

OTHER REQUIRED ATTACHMENTS 26. Other Required Attachments to Application (see instructions for more

details):

- Certification of Available Funds to Finance Project- Certification of 10 year minimum lease/legal agreement and project approval from building owner

- SED Office of Facilities Management Certificate of Project Approval (for school district public libraries owned by the school district)

- State Historic Preservation Office (SHPO) Approval Documentation

- Short Environmental Assessment Form

- FS-20 Forms

- Payee Information Form

- Building Photographs

Page 18: PowerPoint

Certification of Available Funds to Finance Project

Can be: Bank Statement Proof of Bond—tax exempt bonds, bond

anticipation notes, revenue anticipation notes, or similar form of obligation. (See instruction #4).

Legislative Member Item Letter on Official Letterhead signed by Board

Official Other

Page 19: PowerPoint

OTHER REQUIRED ATTACHMENTS 26. Other Required Attachments to Application (see instructions for more

details):

- Certification of Available Funds to Finance Project

- Certification of 10 year minimum lease/legal agreement and project approval from building owner

- SED Office of Facilities Management Certificate of Project Approval (for school district public libraries owned by the school district)

- State Historic Preservation Office (SHPO) Approval Documentation

- Short Environmental Assessment Form- FS-20 Forms

- Payee Information Form

- Building Photographs

Page 20: PowerPoint

Short Environmental Assessment Form For help, contact:

Sara Richards, Associate Counsel, Dormitory Authority of the State of New York at (518) 257-3120 or [email protected]

Page 21: PowerPoint

OTHER REQUIRED ATTACHMENTS 26. Other Required Attachments to Application (see instructions for more

details):

- Certification of Available Funds to Finance Project

- Certification of 10 year minimum lease/legal agreement and project approval from building owner

- SED Office of Facilities Management Certificate of Project Approval (for school district public libraries owned by the school district)

- State Historic Preservation Office (SHPO) Approval Documentation

- Short Environmental Assessment Form

- FS-20 Forms- Payee Information Form

- Building Photographs

Page 22: PowerPoint

FS-20 Form

Page 23: PowerPoint

Budget Category Forms

Page 24: PowerPoint

Budget Category Forms

Page 25: PowerPoint

OTHER REQUIRED ATTACHMENTS 26. Other Required Attachments to Application (see instructions for more

details):

- Certification of Available Funds to Finance Project

- Certification of 10 year minimum lease/legal agreement and project approval from building owner

- SED Office of Facilities Management Certificate of Project Approval (for school district public libraries owned by the school district)

- State Historic Preservation Office (SHPO) Approval Documentation

- Short Environmental Assessment Form

- FS-20 Forms

- Payee Information Form- Building Photographs

Page 26: PowerPoint

Payee Information Form

Page 27: PowerPoint

ASSURANCES

Page 28: PowerPoint

WHAT HAPPENS WHEN THE APPLICATION IS COMPLETE? Submit the application to your system

System sets deadline Systems do “System Evaluation and

Recommendation Form” Application to New York State Library by

Friday, September 11, 2009

Page 29: PowerPoint

System Evaluation and Recommendation Form

Page 30: PowerPoint

THE APPROVAL PROCESS

Applications are evaluated according to established criteria:

Completeness of application

Inclusion of all required documentation

Project eligibility

Page 31: PowerPoint

WHAT KINDS OF PROJECTS ARE ELIGIBLE? SITE ACQUISITION

Purchase of land with an existing building or with evidence of plans and available funding to construct a new building or parking lot.

NEW CONSTRUCTION New library building Addition to existing library building Demolition and Site Preparation

Page 32: PowerPoint

WHAT KINDS OF PROJECTS ARE ELIGIBLE? BUILDING RENOVATION/REHABILITATION

Installation of photovoltaic panels, geothermal wells, and other alternative energy resources

Replacement of roofs, windows, and doors Reconstruction of existing space Accessible entryways (ramps & doorways) and bathrooms Installation of elevators New electrical, plumbing, lighting, and HVAC New driveways, sidewalks, and parking lots New furniture, equipment, and shelving for new or newly

reconfigured space

Page 33: PowerPoint

WHAT KINDS OF PROJECTS ARE NOT ELIGIBLE? Routine Maintenance Architectural and Engineering firm fees Building Consultant Studies Interest or Carrying Charges on bonds

financing the project Mortgage payments Purchase of books or other library materials Landscaping

Page 34: PowerPoint

IF A LIBRARY OR LIBRARY SYSTEM RECEIVED AN AWARD IN 2008-09, CAN IT RECEIVE AN AWARD IN 2009-10?

Page 35: PowerPoint

THE PAYMENT PROCESS

50% Paid– after January 1, 2010, pending final approval of the application if not rendered prior to that date

40% Paid—after April 1, 2010 10% Paid—upon completion of project and

filing of approvable completion paperwork

Page 36: PowerPoint

WHAT DOES A LIBRARY OR LIBRARY SYSTEM HAVE TO DO ONCE A PROJECT IS COMPLETE? FS-10F Form

Completion Form

Electronic “before” and “after” Photographs

Page 37: PowerPoint

FS-10F Form

Page 38: PowerPoint

FS-10F Form

Page 39: PowerPoint

FS-10F Form

Page 40: PowerPoint

Completion Form

Page 41: PowerPoint

OTHER POSSIBLE FUNDING SOURCES: New York State Energy, Research and

Development Agency Funding for energy conservation projects www.getenergysmart.org http://www.nyserda.org/programs/

New_Construction/default.asp

Page 42: PowerPoint

WHAT HAPPENS IF OUR FUNDED PROJECT FALLS APART?

Page 43: PowerPoint

QUESTIONS?