© Copyright 2014 OSIsoft, LLC. Presented by Power Transformer Simulation Laboratory for Proactive Maintenance II Nicolas Di Gaetano & Luc Vouligny
39

Power Transformer Simulation Laboratory for Proactive ...

Dec 18, 2021

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Power Transformer Simulation Laboratory for Proactive ...

© Copyr i gh t 2014 O SIs o f t , LLC .

Presented by

Power Transformer

Simulation

Laboratory for

Proactive

Maintenance II

Nicolas Di Gaetano

& Luc Vouligny

Page 2: Power Transformer Simulation Laboratory for Proactive ...

© Copyr i gh t 2014 O SIs o f t , LLC .

Agenda

• An overview of Hydro-Québec

• Context of the project

• Objectives of the project

• Transformer monitoring

• Conclusion & Future Work

Page 3: Power Transformer Simulation Laboratory for Proactive ...

© Copyr i gh t 2014 O SIs o f t , LLC .

Snapshot

• Hydro-Québec is among the largest power

generator in North America

– 98% renewable energy

• Hydro-Québec is among the largest power

transmission companies in North America

• Hydro-Québec is the largest electric utility in

Canada

3

Page 4: Power Transformer Simulation Laboratory for Proactive ...

© Copyr i gh t 2014 O SIs o f t , LLC .

About Hydro-Québec

4

Page 5: Power Transformer Simulation Laboratory for Proactive ...

© Copyr i gh t 2014 O SIs o f t , LLC .

About Hydro-Québec’s Research Institute

(IREQ)

> Largest electric utility research centre in North America

• 500 employees of which half are researchers

• $100M invested each year on 100 projets

• 1000 patents

5

Page 6: Power Transformer Simulation Laboratory for Proactive ...

© Copyr i gh t 2014 O SIs o f t , LLC .

Hydro-Québec TransÉnergie

• Transmission assets: $17.6 B

• 33,630 km of power transmission

lines

– Including 11,422 km of 735 kV lines

• 514 transmission substations

• Annual investment: $1,3 B

6

Page 7: Power Transformer Simulation Laboratory for Proactive ...

© Copyr i gh t 2014 O SIs o f t , LLC .

17 interconnections with

neighboring markets

(> 6,000 MW)

7

Page 8: Power Transformer Simulation Laboratory for Proactive ...

© Copyr i gh t 2014 O SIs o f t , LLC .

Context of the project

• Network: reliable and available

• Data: high-quality, value-added and just-in-time

• Decisions: appropriate, timely

• Power transformers are critical assets of the network

– Average age: 33 years old

– Their life expectancy: 40-50 years

• Transition from systematic to proactive maintenance

8

Page 9: Power Transformer Simulation Laboratory for Proactive ...

© Copyr i gh t 2014 O SIs o f t , LLC .

Objectives of the project

• Maximize asset life

• Reduce the Risk & Cost of unexpected failure

• Drive maintenance and inspection by asset

condition

• Awareness of its condition and performance

• To maximize system availability

9

Page 10: Power Transformer Simulation Laboratory for Proactive ...

© Copyr i gh t 2014 O SIs o f t , LLC .

Transformer monitoring

Real-time monitoring

10

2 3 41 5 6MEET Project

Sensors,

IEDs,

Transducers

Communication

Infrastructure

Data Server

(PI System)Computational Intelligence

Diagnostics & PrognosticsWeb Interface

Sustainability

& Maintenance

Action

Page 11: Power Transformer Simulation Laboratory for Proactive ...

© Copyr i gh t 2014 O SIs o f t , LLC .

Transformer monitoring: From past to future

• Use remote monitoring for all growth and asset sustainment projects– More than 500 substations over a 15-year timeframe (2009–2025)

• Objective: 30 to 40 substations a year

– Monitoring of 240 strategic transformers by 2015

• Gas and moisture

• Temperature

• Bushing and tap changer monitors (future deployment) – OSIsoft PI System

• Automatic addition of points (PI APS, PI GenericCSV_APS connector)• Maximizes use of PI AF templates

• PI AF SDK

200820072006 2009

IT infrastructure

2010 2011 2025

Business

case

11

Page 12: Power Transformer Simulation Laboratory for Proactive ...

© Copyr i gh t 2014 O SIs o f t , LLC .

PI Webparts: Displays

12

Page 13: Power Transformer Simulation Laboratory for Proactive ...

© Copyr i gh t 2014 O SIs o f t , LLC .

PI Webparts: Displays (continued)

13

Page 14: Power Transformer Simulation Laboratory for Proactive ...

© Copyr i gh t 2014 O SIs o f t , LLC .

PI Webparts: Displays (continued)

14

Page 15: Power Transformer Simulation Laboratory for Proactive ...

© Copyr i gh t 2014 O SIs o f t , LLC .

PI Notifications: Alerts

Remote Maintenance Centres

Technical Support

Managers15

Page 16: Power Transformer Simulation Laboratory for Proactive ...

© Copyr i gh t 2014 O SIs o f t , LLC .

Transformer monitoring

Bushing

Dissolved

Gas

Thermal

Performance

Tap Changer

Moisture

and Aging

Mechanical state

16

2 3 41 5 6MEET Project

Sensors,

IEDs,

Transducers

Communication

Infrastructure

Data Server

PI SystemComputational Intelligence

Diagnostics & PrognosticsWeb Interface

Sustainability

& Maintenance

Action

Page 17: Power Transformer Simulation Laboratory for Proactive ...

© Copyr i gh t 2014 O SIs o f t , LLC .

Acquisition, Estimation & Detection

17

Microsoft StreamInsight

PI Server

Queries

TCP/SI Adapte

r

PI Input

Adapter

PI OutputAdapter

Simulated

data

PI

Points

Real

data

PI to PI

Microsoft StreamInsight

PI Server

Queries

TCP/SI Adapte

r

PI Input

Adapter

PI OutputAdapter

Microsoft StreamInsight

PI Server

Queries

TCP/SI Adapte

r

PI Input

Adapter

PI OutputAdapter

Estimation

data

Asset

maintenance

model

Detection

logic

JMS/SI

Input Conn.

Page 18: Power Transformer Simulation Laboratory for Proactive ...

© Copyr i gh t 2014 O SIs o f t , LLC .

Thermal prediction with physical models

• IEC 60076-7 International Standard

– Loading guide for oil-immersed power transformer

• IEEE Clause 7 Non-Linear

• IEEE Clause 7 Linear

• Swift

• Susa

18

Page 19: Power Transformer Simulation Laboratory for Proactive ...

© Copyr i gh t 2014 O SIs o f t , LLC .

IEC 60076-7 / Exponential Equations

19

– Load varies as a step function

– Used in the determination of heat

transfer parameters

– Increasing load (κ)

– Decreasing load (κ)

19

Page 20: Power Transformer Simulation Laboratory for Proactive ...

© Copyr i gh t 2014 O SIs o f t , LLC .

IEC 60076-7 / Difference EquationsTemporal variables

> κ : Load factor

> θo: Top-Oil temperature

> θa : Ambient temperature

> Dt: Time interval

• 1 minute

Constants:

> k11 : Model constant

• 0,8

> τO : Avg. oil time constant

• 150

> Δ θor : Top oil rise constant

• 50

> R: Load loss ratio

• 8,4

> x: Exponential power of current vs top oil rise

• 0,8

20

- Both the load and the ambient

temperature are time-varying

- Adapted for monitoring purposes

Page 21: Power Transformer Simulation Laboratory for Proactive ...

© Copyr i gh t 2014 O SIs o f t , LLC .

Acquisition, Estimation & Detection

21

Microsoft StreamInsight

PI Server

Queries

TCP/SI Adapte

r

PI Input

Adapter

PI OutputAdapter

Simulated

data

PI

Points

Real

data

PI to PI

Microsoft StreamInsight

PI Server

Queries

TCP/SI Adapte

r

PI Input

Adapter

PI OutputAdapter

Microsoft StreamInsight

PI Server

Queries

TCP/SI Adapte

r

PI Input

Adapter

PI OutputAdapter

Estimation

data

Asset

maintenance

model

Detection

logic

Exponential

Equation

Difference

Equation

Page 22: Power Transformer Simulation Laboratory for Proactive ...

© Copyr i gh t 2014 O SIs o f t , LLC .

Difference equation performance

Simulation

Estimation

22

Page 23: Power Transformer Simulation Laboratory for Proactive ...

© Copyr i gh t 2014 O SIs o f t , LLC .

Real data

• 3 years of data

23

Load from 0 to 1.35 pu

Ambient Temp. from -31°C to 33°C

Page 24: Power Transformer Simulation Laboratory for Proactive ...

© Copyr i gh t 2014 O SIs o f t , LLC .

Performance with real data

24

Top-Oil

Ambient

Estimated

Difference

Page 25: Power Transformer Simulation Laboratory for Proactive ...

© Copyr i gh t 2014 O SIs o f t , LLC .

Performance over a year

25

Page 26: Power Transformer Simulation Laboratory for Proactive ...

© Copyr i gh t 2014 O SIs o f t , LLC .

Results with physical models – 2009

26

Page 27: Power Transformer Simulation Laboratory for Proactive ...

© Copyr i gh t 2014 O SIs o f t , LLC .

Results with physical models – 2011

27

Page 28: Power Transformer Simulation Laboratory for Proactive ...

© Copyr i gh t 2014 O SIs o f t , LLC .

Results with clustering

28

Page 29: Power Transformer Simulation Laboratory for Proactive ...

© Copyr i gh t 2014 O SIs o f t , LLC .

Neural networks

• Neural networks are nonlinear black-box

structures with “interesting” properties

– general architecture

– universal approximator

– non-sensitive to over-parametrization

– have learning algorithm to acquire knowledge from

their environment, using examples

– have recall algorithm to use the learned knowledge

29

Page 30: Power Transformer Simulation Laboratory for Proactive ...

© Copyr i gh t 2014 O SIs o f t , LLC .

Basic Regressor Neural Networks

Current Inputs

(Static Networks)

Current Inputs

and Past Outputs

(Dynamic Networks)

30

Page 31: Power Transformer Simulation Laboratory for Proactive ...

© Copyr i gh t 2014 O SIs o f t , LLC .

Matlab results for Neural Network

top-oil temperature prediction

31

2011 data test (6 months)– Mean Absolute Error: 0.25%

– Mean Error : 0.1 °C

– Max Error : 1 °C

Page 32: Power Transformer Simulation Laboratory for Proactive ...

© Copyr i gh t 2014 O SIs o f t , LLC .

Abnormal behaviour (data cleaning)

AmbT load Actual ANN

9.68 36 19.52 19.49

9.68 36 10.85 10.89

9.68 11739 146.90 15.81

9.68 12339 13.86 16.88

9.56 3 24.86 28.95

9.58 36 10.79 27.59

9.37 3 24.75 15.70

9.38 3 10.70 10.71

9.37 3 10.72 10.69

9.38 3 10.72 10.69

9.37 3 10.67 10.66

Page 33: Power Transformer Simulation Laboratory for Proactive ...

© Copyr i gh t 2014 O SIs o f t , LLC .

Neural Network Estimator

33

Microsoft StreamInsight

PI Server

Queries

TCP/SI Adapte

r

PI Input

Adapter

PI OutputAdapter

Simulation

data

PI

Points

Real

data

PI to PI

Microsoft StreamInsight

PI Server

Queries

TCP/SI Adapte

r

PI Input

Adapter

PI OutputAdapter Microsoft StreamInsight

PI Server

Queries

TCP/SI Adapte

r

PI Input

Adapter

PI OutputAdapter

Estimation

data

Detection

logic

.dll

Page 34: Power Transformer Simulation Laboratory for Proactive ...

© Copyr i gh t 2014 O SIs o f t , LLC .

Neural Network prediction results with real data

34

Page 35: Power Transformer Simulation Laboratory for Proactive ...

© Copyr i gh t 2014 O SIs o f t , LLC .

Future work

• Gradual implementation of models (2014-2018)– Thermal performance

– Dissolved gas

– Moisture and aging

– Tap changer and bushing

– Mechanical state

• Each model are developed with the following steps

35

Specification Development Coding Testing Documentation Implementation

Page 36: Power Transformer Simulation Laboratory for Proactive ...

© Copyr i gh t 2014 O SIs o f t , LLC .

Proactive maintenance Advantages

• Transformers– Avoiding major failures

– Avoiding unavailability and captive power

• Equipment– Awareness about equipment condition as it

ages

• Sensors – Detection of malfunctioning equipment

– Improvements on many equipment settings

36

Page 37: Power Transformer Simulation Laboratory for Proactive ...

© Copyr i gh t 2014 O SIs o f t , LLC .

- Transformers

– Avoiding major failures

- Equipment

– Awareness about equipment

condition as it ages

Solution Results and Benefits

Power Transformer Simulation Laboratory for

Proactive Maintenance

- Maximization of asset life

- Risk & Cost Reduction of

unexpected failure

- Maintenance and Inspection

driven by asset condition

37

- Set up the infrastructure &

organization needed to ensure

real-time monitoring of

transformer condition

- Real-time data analysis with

predictive model

« Now that we have on-line monitoring possibilities

for maintenance purposes on power transformers,

our simulation laboratory will allow us to elaborate

and test many possibilities of proactive

maintenance models & technics before

implementing them in the field. »

Business Challenge

Page 38: Power Transformer Simulation Laboratory for Proactive ...

© Copyr i gh t 2014 O SIs o f t , LLC .

Nicolas Di Gaetano• [email protected]

• Fiability Engineer

• TransEnergie, Hydro-Québec

38

Arnaud Zinflou• [email protected]

• Researcher

• IREQ, Hydro-Québec

Patrick Picher• [email protected]

• Researcher & project manager

• IREQ, Hydro-Québec

Luc Vouligny• [email protected]

• Researcher

• IREQ, Hydro-Québec

Page 39: Power Transformer Simulation Laboratory for Proactive ...

© Copyr i gh t 2014 O SIs o f t , LLC .

Brought to you by