Top Banner
Power System for the Better Water Maker P14418 System Design Review
45

Power System for the Better Water Maker P14418. ● Background ○ Problem Statement and Project Plan ○ Customer Needs and Engineering Requirements ○ Constraints.

Dec 25, 2015

Download

Documents

Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Power System for the Better Water Maker P14418. ● Background ○ Problem Statement and Project Plan ○ Customer Needs and Engineering Requirements ○ Constraints.

Power System for the

Better Water Maker

P14418

System Design Review

Page 2: Power System for the Better Water Maker P14418. ● Background ○ Problem Statement and Project Plan ○ Customer Needs and Engineering Requirements ○ Constraints.

Agenda● Background

○ Problem Statement and Project Plan

○ Customer Needs and Engineering Requirements

○ Constraints and Design Drivers

○ Project Risk Assessment

● System Analysis

○ House of Quality Results

○ Functional Decomposition

○ Pugh Analysis

● Individual Concepts and Architectural Developments

○ Concept and Schematic

○ Risk Assessment

○ Initial Cost Estimate

○ Test Plan

● Feedback

Page 3: Power System for the Better Water Maker P14418. ● Background ○ Problem Statement and Project Plan ○ Customer Needs and Engineering Requirements ○ Constraints.

Problem Statement

The Better Water Maker was developed to disinfect water in nations with high mortality rates due to poor water and sanitation systems. The goal of our team is to provide a low cost, efficient power generation system for the Better Water Maker that does not tire the user, while it is fun and easy to use.

Page 4: Power System for the Better Water Maker P14418. ● Background ○ Problem Statement and Project Plan ○ Customer Needs and Engineering Requirements ○ Constraints.

Project Plan

Page 5: Power System for the Better Water Maker P14418. ● Background ○ Problem Statement and Project Plan ○ Customer Needs and Engineering Requirements ○ Constraints.

Customer Needs (Critical)

Primary needs

● Generate adequate power

● Is not tiring

● Reduced cost

● Maintain durability

Page 6: Power System for the Better Water Maker P14418. ● Background ○ Problem Statement and Project Plan ○ Customer Needs and Engineering Requirements ○ Constraints.

Engineering Requirements

● Generate 25 Watts

● Can be used for at least 5 minutes

● Costs less than $150

● Lasts for at least 180,000 gallons of water

Page 7: Power System for the Better Water Maker P14418. ● Background ○ Problem Statement and Project Plan ○ Customer Needs and Engineering Requirements ○ Constraints.

Constraints & Design Drivers

Key Design Drivers

• Functionality, Reliability, Cost, Usability, Manufacturability

• Durability, Efficiency

Constraints

• Cost, Size, Weight, Strength of User

Page 8: Power System for the Better Water Maker P14418. ● Background ○ Problem Statement and Project Plan ○ Customer Needs and Engineering Requirements ○ Constraints.

System Analysis: HOQ Results

Four highest weighted needs:

● Ease of Repair

● Cost

● Unit Life

● Effort Required

Page 9: Power System for the Better Water Maker P14418. ● Background ○ Problem Statement and Project Plan ○ Customer Needs and Engineering Requirements ○ Constraints.

Functional Decomposition

Page 10: Power System for the Better Water Maker P14418. ● Background ○ Problem Statement and Project Plan ○ Customer Needs and Engineering Requirements ○ Constraints.

Timing Diagram

Page 11: Power System for the Better Water Maker P14418. ● Background ○ Problem Statement and Project Plan ○ Customer Needs and Engineering Requirements ○ Constraints.

General Process Flow Chart

Page 12: Power System for the Better Water Maker P14418. ● Background ○ Problem Statement and Project Plan ○ Customer Needs and Engineering Requirements ○ Constraints.

Pugh Analysis

Page 13: Power System for the Better Water Maker P14418. ● Background ○ Problem Statement and Project Plan ○ Customer Needs and Engineering Requirements ○ Constraints.

Pugh Analysis

Page 14: Power System for the Better Water Maker P14418. ● Background ○ Problem Statement and Project Plan ○ Customer Needs and Engineering Requirements ○ Constraints.

Pugh Analysis

Page 15: Power System for the Better Water Maker P14418. ● Background ○ Problem Statement and Project Plan ○ Customer Needs and Engineering Requirements ○ Constraints.

Solar Concept: Schematic

Acquire Water

Hook up

Battery

Communicates Readiness to User

Plug in

BWM

Dispense Water

Page 16: Power System for the Better Water Maker P14418. ● Background ○ Problem Statement and Project Plan ○ Customer Needs and Engineering Requirements ○ Constraints.

Engineering Analysis

Assumptions:

● 30W Solar Panel

● Surface Area: 0.262 m^2

● Efficiency: 18%

● 2-axis rotation

● Clear-sky analysis

● BWM requires 20.4-25.5W

Page 17: Power System for the Better Water Maker P14418. ● Background ○ Problem Statement and Project Plan ○ Customer Needs and Engineering Requirements ○ Constraints.
Page 18: Power System for the Better Water Maker P14418. ● Background ○ Problem Statement and Project Plan ○ Customer Needs and Engineering Requirements ○ Constraints.
Page 19: Power System for the Better Water Maker P14418. ● Background ○ Problem Statement and Project Plan ○ Customer Needs and Engineering Requirements ○ Constraints.

Solar Insolation by Region

Page 20: Power System for the Better Water Maker P14418. ● Background ○ Problem Statement and Project Plan ○ Customer Needs and Engineering Requirements ○ Constraints.

Port-au-Prince, Haiti Sun Chart: Hot Climate

Page 21: Power System for the Better Water Maker P14418. ● Background ○ Problem Statement and Project Plan ○ Customer Needs and Engineering Requirements ○ Constraints.

Nepal Sun Chart: Cooler Climate

Page 22: Power System for the Better Water Maker P14418. ● Background ○ Problem Statement and Project Plan ○ Customer Needs and Engineering Requirements ○ Constraints.

Calculations for 20° Latitude: Haiti

● 8AM to 4PM availability

● Shade drastically reduces power

Page 23: Power System for the Better Water Maker P14418. ● Background ○ Problem Statement and Project Plan ○ Customer Needs and Engineering Requirements ○ Constraints.

Solar Concept: Risk Assessment By Importance

● Reliability○ Weather

○ Time

○ Shading

● Theft

● Battery○ Shipping

○ Cost

○ Safety

○ Life

● Additional Controls

● Cost○ Component

Page 24: Power System for the Better Water Maker P14418. ● Background ○ Problem Statement and Project Plan ○ Customer Needs and Engineering Requirements ○ Constraints.

Solar Concept: Cost Analysis

● 30W Monocrystalline Solar Panel 18V- $71.06● 2-Axis Stand- $20-$30● AC Converter- $20● Wire extension- $10● 12V lead acid battery - $30

Total Cost:

~$150

● May end up outside budget, but the system will provide power for any device.

Page 25: Power System for the Better Water Maker P14418. ● Background ○ Problem Statement and Project Plan ○ Customer Needs and Engineering Requirements ○ Constraints.

Solar Concept: Test Plan

● Use multimeter to verify the power.

● Measure the power if a cell is shaded.

● Collect data on battery charging capability.

● Test ability of a child to use from start to finish.

● Obtain a survey from users on its ease of use.

Page 26: Power System for the Better Water Maker P14418. ● Background ○ Problem Statement and Project Plan ○ Customer Needs and Engineering Requirements ○ Constraints.

Leg-powered Concept

● Recumbent Bicycle

● Direct- or Chain-Drive

Pros Cons

● More power in legs than arms● Less tiring than current design● Higher efficiency than current● Possibility to reduce amounts

of motors

● Might add cost● High forces on seating

structure● More complicated setup than

current design● Less portable than current

Page 27: Power System for the Better Water Maker P14418. ● Background ○ Problem Statement and Project Plan ○ Customer Needs and Engineering Requirements ○ Constraints.

Pedals Mounted on Crankshaft

Pedals Mounted on Separate Sprockets

Seat

Seat

Backrest

Bucket

2x4

Current Generator

Current Generator

Leg-powered Concept: Schematic

Page 28: Power System for the Better Water Maker P14418. ● Background ○ Problem Statement and Project Plan ○ Customer Needs and Engineering Requirements ○ Constraints.

Risk Assessment

● Large forces in system

● More complicated setup

● Reduced component life

● Complex seating requirements

Page 29: Power System for the Better Water Maker P14418. ● Background ○ Problem Statement and Project Plan ○ Customer Needs and Engineering Requirements ○ Constraints.

Design Architecture

Feature

Seat

Crank and Motors

LEDs

Wires, Chain, and Sprocket

Function Accomplished

Place User

Generate Power

Communicate to User

Transfer Power

Page 30: Power System for the Better Water Maker P14418. ● Background ○ Problem Statement and Project Plan ○ Customer Needs and Engineering Requirements ○ Constraints.

Leg-powered Concept: Cost Analysis

● Crankset - $10-20*

● Pedals - $4*

● Chain - $10

● Keyed Shaft - $10 -17*

● Sprocket - $5 - 10

Chain Drive - $39 - 61

*Direct Drive - $24 - 41

Page 31: Power System for the Better Water Maker P14418. ● Background ○ Problem Statement and Project Plan ○ Customer Needs and Engineering Requirements ○ Constraints.

Leg-powered Concept: Test Plan

● Have volunteers test for comfort

● Measures forces on seat and pedals

● Can run for 5 minutes or more

● Run generator while attached to a voltmeter○ Ensure voltage is limited correctly

Page 32: Power System for the Better Water Maker P14418. ● Background ○ Problem Statement and Project Plan ○ Customer Needs and Engineering Requirements ○ Constraints.

Spring Concept: Schematic

SwingSingle Jump Platform

Double Jump Platform

Page 33: Power System for the Better Water Maker P14418. ● Background ○ Problem Statement and Project Plan ○ Customer Needs and Engineering Requirements ○ Constraints.

Risk Assessment

●Solenoids create heato Proper heat sink

●Springs could breako Properly constrained

●Solenoid plunger must be correctly alignedo Prevent improper movement

●Oscillations may be erratico Use bridge rectifier

Page 34: Power System for the Better Water Maker P14418. ● Background ○ Problem Statement and Project Plan ○ Customer Needs and Engineering Requirements ○ Constraints.

Spring Concept: Design Architecture

Feature

Casing/Spring Enclosure

Solenoid

Springs

Rectifier

Function Accomplished

Place User

Generate Power

Facilitate Power Generation

Regulate Power

Page 35: Power System for the Better Water Maker P14418. ● Background ○ Problem Statement and Project Plan ○ Customer Needs and Engineering Requirements ○ Constraints.

Spring Concept: Cost Analysis

● Springs - $3-10 each

● Solenoid - $15-30 each

● Rectifier - $0.50-3

● Plywood casing - $5-10 per setup

● Rope/chain - $0.70/ft

Swing - $30-68

Single Jump Platform - $26-63

Double Jump Platform - $52-123

Page 36: Power System for the Better Water Maker P14418. ● Background ○ Problem Statement and Project Plan ○ Customer Needs and Engineering Requirements ○ Constraints.

Spring Concept: Test Plan

● Test the components for each output individuallyo Verify with expectations

● Test the ergonomics of the setup to determine whether it requires less effort than the original design

● Bring children in to set up and use the apparatus

● Use DOE tools to validate the testing results

Page 37: Power System for the Better Water Maker P14418. ● Background ○ Problem Statement and Project Plan ○ Customer Needs and Engineering Requirements ○ Constraints.

Recommendations:

●Solar Concept:o Has great potential, even beyond BWM, but has high risk

in reliability and cost.

●Leg-Powered Deviceo High reliability in combination with low cost and OTS

components make this a desirable concept.

●Spring Concepto Unknown reliability of power; this will need more anaysis

before moving forward, but it has great potential to be fun and easy to use, as well as low in cost.

Page 38: Power System for the Better Water Maker P14418. ● Background ○ Problem Statement and Project Plan ○ Customer Needs and Engineering Requirements ○ Constraints.

Questions and Comments?

Page 39: Power System for the Better Water Maker P14418. ● Background ○ Problem Statement and Project Plan ○ Customer Needs and Engineering Requirements ○ Constraints.

Springs (Century Spring Corp.)P/N: 7052 $3.84

OD: 1in

Length: 3in Max. displacement: 1.2in

k: 51lb/in Max. load: 60lb

P/N: 12556 $5.31

OD: 1in

Length: 4.45in

Max. displacement: 1.2in

k: 53lb/in Max. load: 64lb

P/N: 7056 $8.96

OD: 1.219in

Length: 4in Max. displacement: 1.2in

k: 99lb/in Max. load: 118lb

P/N: 11860 $8.66

OD: 2.125in

Length: 5.38in

Max. displacement: 4in

k: 5.5lb/in Max. load: 22lb

P/N: S-3159

$13.20

OD: 2.875in

Length: 3in Max. displacement: 1.4in

k: 15lb/in Max. load: 20lb

P/N: D-1306

$5.73

OD: .375in

Length: 3in Max. displacement: 0.9in

k: 42lb/in Max. load: 38lb

Page 40: Power System for the Better Water Maker P14418. ● Background ○ Problem Statement and Project Plan ○ Customer Needs and Engineering Requirements ○ Constraints.

Solenoids (ElectroMechanics Online)P/N: S-16-50 $27.73

Pull-type 18W

Long Pulse 25% Duty Cycle

Max. on-time: 50s

Actuation Length: <1.6in

P/N: S-10-50 $22.40

Pull-type 16W

Long Pulse 25% Duty Cycle

Max. on-time: 20s

Actuation Length: <1in

P/N: S-10-50 $22.40

Pull-type 8W

Intermittent 50% Duty Cycle

Max. on-time: 75s

Actuation Length: <1in

Page 41: Power System for the Better Water Maker P14418. ● Background ○ Problem Statement and Project Plan ○ Customer Needs and Engineering Requirements ○ Constraints.

Rectifiers (Mouser Electronics)

P/N: 625-2KBP02M-E4 $0.58

Current: 2A Max. current surge: 60A

Peak reverse voltage: 200V

Single Phase Bridge-style

P/N: 625-PB4006-E3 $3.02

Current: 4.4A Max. current surge: 400A

Peak reverse voltage: 600V

Single Phase Bridge-style

P/N: 512-GBPC3510 $3.05

Current: 35A Max. current surge: 400A

Peak reverse voltage: 1000V

Single Phase Bridge-style

Page 42: Power System for the Better Water Maker P14418. ● Background ○ Problem Statement and Project Plan ○ Customer Needs and Engineering Requirements ○ Constraints.

Gravity Feed (not power generation)

Pros Cons

● Possible elimination of pump (5+W)

● Less effort required

● Can be OTS

● Needs more structural support due to higher center of mass

● Need to use pump to regulate flow or use gate valve and throttle valve

● Users need to lift water into funnel

Page 43: Power System for the Better Water Maker P14418. ● Background ○ Problem Statement and Project Plan ○ Customer Needs and Engineering Requirements ○ Constraints.

Solar Power Supplement to Current BWM Design

Pros:

- Solar panel will reduce load on user

- Redesign of current system may be minimal

- Reduced learning curve for current users

Page 44: Power System for the Better Water Maker P14418. ● Background ○ Problem Statement and Project Plan ○ Customer Needs and Engineering Requirements ○ Constraints.

Solar Power Supplement to Current BWM Design

Cons:

- Cloud cover and night- time eliminate the improvement

- Solar panels are susceptible to theft

Page 45: Power System for the Better Water Maker P14418. ● Background ○ Problem Statement and Project Plan ○ Customer Needs and Engineering Requirements ○ Constraints.

House of Quality