Power Sector Reforms in India: A Critical Appraisal of Orissa’s Reforms Experience A Thesis Submitted to the Utkal University in Partial Fulfilment of the Requirement for the Degree of DOCTOR OF PHILOSOPHY IN COMMERCE By MR. SARBESH MISHRA Under The Supervision of PROF. AMBIKA PRASAD DASH DR. MALAY KUMAR MOHANTY UTKAL UNIVERSITY Bhubaneswar 2008
Power Sector Reforms in India: A Critical Appraisal of Orissa's Reforms Experience - highlights the significance of Power sector reforms initiatives across India and Orissa being the pioneer state.
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Power Sector Reforms in India: A Critical Appraisal of Orissa’s Reforms
Experience
A Thesis Submitted to the Utkal University in Partial Fulfilment of the Requirement for the Degree of
DOCTOR OF PHILOSOPHY
IN COMMERCE
By MR. SARBESH MISHRA
Under The Supervision of
PROF. AMBIKA PRASAD DASH
DR. MALAY KUMAR MOHANTY
UTKAL UNIVERSITY
Bhubaneswar 2008
2
Department of Commerce
Utkal University,
Bhubaneswar.
DECLARATION
I hereby declare that this thesis entitled “Power Sector Reforms in India: A
Critical Appraisal of Orissa’s Reforms Experience” submitted to the Utkal
University in fulfillment of the requirements for the award of the Degree of
Doctor of Philosophy in Commerce is a bonafide record of original research
work done by me under the supervision and guidance of Professor Ambika
Prasad Dash and Dr. Malay Kumar Mohanty and the thesis has not been
submitted to any other University or Institution for the award of any degree or
diploma.
(Signature of the Candidate)
SARBESH MISHRA
Enrolment No: 6-commerce-2003-2004
Date of Registration: 27.5.2004.
3
Prof. Ambika Prasad Dash Dr. Malay Kumar Mohanty
Power Management Institute Ravenshaw University
NOIDA – 201306 (U.P) Department of Commerce
Cuttack – 753003, Orissa.
CERTIFICATE
This is to certify that the thesis titled “Power Sector Reforms in India: A critical
Appraisal of Orissa’s Reforms Experience” submitted to the Utkal University,
Bhubaneswar in fulfillment of the requirements for the award of the Degree of
Doctor of Philosophy in Commerce is a bonafide record of original research work
done by Mr. Sarbesh Mishra, under our supervision and guidance and this thesis has
not been submitted to any other University or Institution for the award of any
degree.
(Ambika Prasad Dash) (Malay Kumar Mohanty)
4
Prof. Ambika Prasad Dash Dr. Malay Kumar Mohanty
Power Management Institute Ravenshaw University
NOIDA – 201306 (U.P) Department of Commerce
Cuttack – 753003, Orissa.
AREA CERTIFICATE
The work done by the candidate is original and within the area of registration for
which the candidate has already been for the registration.
(Ambika Prasad Dash) (Malay Kumar Mohanty)
5
ACKNOWLEDGEMENT
I express my profound gratitude to my supervisors, Professor A.P Dash and
Dr. M K Mohanty, whose benign guidance has enlightened my path through the
course of this work. Besides their dedication to academic life, their disciplined and
austere habits have been a source of constant inspiration to me. They are humane
with willingness to help others, care for everyone, and always being concerned
about the progress. With these rare qualities I have found in them not merely
supervisor but a noble soul, a “Guru”.
I express my gratitude to Prof. Arabinda Mishra, TERI University, New
Delhi, Prof. Tanmay Panda, BITS, PILANI (DUBAI) Campus for their continuous
concern about my progress in research. My special thanks to Mr. Sovan Kanungo,
IAS, Prof. Rajat Bakshi, MDI, Gurgaon, Mr. P Chanda, AGM, NTPC Ltd. Dr. G N
Patel, Registrar, BIMTECH, Prof. Mukesh Chaturvedi, MDI, Gurgaon, Maj. Gen. N.
K Dhir, Prof. P K Mishra, HoD, Environmental Science, Jyotivihar, Mr. Dillip Raj
Behera, DGM, Public Relations, OPTCL and Mr. S.N Sabat, IPS, DIG of Police,
Uttar Pradesh for their guidance during different stages of this research.
I am thankful to other teachers of the department Prof. S Moharana, HoD,
Department of Commerce, Prof. Ranjan Kumar Bal, Dr. J K Parida, Dr. P K Hota,
Dr. K B Das, Dr. M Sahu, Mr. A K Sahu for their encouragement and interest in my
academic pursuit.
I acknowledge my sincere gratitude to University of Delhi for allowing me to
pursue PhD work being a faculty member. I also acknowledge the help and facilities
availed from Army Institute of Management & Technology, Greater NOIDA and I
extend my profound regards to late Director of the institute Prof. (Brigadier) M. M.
Trivedi, VSM for his timely help and encouragement.
6
I cannot express my gratitude in words to my late father Shri Indramadhab
Mishra, whose blessings have always been with me throughout this work along with
the best wishes from my family members, mother Ms. Puspalata Mishra, my elder
brother Mr. Abesh Mishra, my brother-in-law Mr. B P Dwivedi, my sister Ms.
Ajanta Dwivedi and my sister-in-law Ms. Saswati Mishra . It’s needless to mention
about my wife Sushree’s contribution, in each and every step of this research work
she has willingly extended her cooperation
My special thanks must go to my guide’s family for their timely help and
constant inspiration. My sincere regards and thanks to Prof. Suman Mahapatra,
Dean, School of Languages, Ravenshaw University for his painstaking effort of
correcting my thesis meticulously and also to Mr. K. Anand, Acquisition Editor,
Vikas Publishing House for undertaking to publish my thesis after its
acknowledgement.
It is my pleasure to acknowledge Mr. Vineet Sahu, Mr. Satya Sundar Panda,
Mr. Saurav Rath and Mr. Amarendra Mohanty for their moral support and timely
inspiration.
(Sarbesh Mishra)
7
LIST OF TABLE
Page No. 1. Table 1: Power Sector Performance: Gaps between Targets and Realities on Key Indicators in a sampling 17
of regions and Countries. 2. Table 2: Generation of Power – Sector wise 22
and Compositions 3. Table 3: Hydel Potential – Global Scenario 23 4. Table 4: States with substantial undeveloped 23
Hydro potential 5. Table 5: Inter-regional Links under Operation 24 6. Table 6: Plan Outlay On power Sector (1961-90) 27 7. Table 7: Installed Power Capacity 1950 to 2000 27 8. Table 8: Installed Capacity (MW) At a Glance 27 9. Table 9: Physical Performance (At the All India Level) 28 10. Table 10: Public Sector Investment In power 1992-2002 32 11. Table 11: Capacity Addition 1992-2002 32 12. Table 12: Tenth Plan Power Sector Outlay (2002-07) 36 13. Table 13: Financing Pattern of Central Sector outlay in 36
Tenth Plan (Rs. Crore at 2001-02 prices) 14. Table 14: Electricity Consumption in Brazil 55
Twh (1994 – 2002) 15. Table 15: Comparative statement of sops extended by 108
different countries 16. Table 16: Estimated Break-up of T& D losses in M.P 149 17. Table 17: Achievement of OSEB during 35 years 163 18. Table 18: Accounting P\L 173
8
19. Table 19: Cash P\L 173 20. Table 20: Details of Revaluation 178 21. Table 21: Debt Equity Comparison 180 22. Table 22: Profit / (Loss) Comparison Over The Years 181 23. Table 23: Details Of Loans 182 24. Table 24: Statement Of Power Purchase, Sale, T& D Loss 183
Billing Collection, etc 25. Table 25: Sources & Application of Funds 184 26. Table 26: Expenditure Incurred On Consultancy Services 185 27. Table 27: Revaluation of Assets 204 28. Table 28: Financial Result Analysis of Andhra Pradesh 211 29. Table 29: Financial Result Analysis of Orissa 211 30. Table 5.1: Indicators of Access to Electricity by 219
Sample Households 31. Table 5.2: Metering of Households in Rural and 222
Urban areas 32. Table 5.3: Uses of Electricity by Households in Rural 223
and Urban Areas 33. Table 5.4: Economy in use of electricity by members of 224
the household 34. Table 5.5: Reasons for Economy in Use by Households 225
in reform period 35. Table 5.6: Perceived changes in electricity tariff in reform 226
period 36. Table 5.7: Billing frequency as reported by the households 228 37. Table 5.8: Irregularity in Billing 228 38. Table 5.9: Billing efficiency in rural and urban areas 230
9
39. Table 5.10: Consumer perceptions on power supply 231
in the reform period 40. Table 5.11: Duration of Power Failure in pre-reform 232
and reform periods 41. Table 5.12: Duration of power cut during pre reform 234
And reform periods 42. Table 5.13: Alternative sources of lighting used by 235
consumers during power cut/failure 43. Table 5.14: Consumer perceptions on voltage 236
quality in reform period 44. Table 5.15: Difficulties reported due to voltage 237
problem in the reform period 45. Table 5.16: Protective measures by households in 237
case of voltage problem 46. Table-5.17: Consumer perceptions about reform’s 240
impact on education of children 47. Table-5.18: Consumer perceptions about reform’s 242
impact on health services and health care in households 48. Table-5.19: Consumer perceptions about reform’s 243
impact on women 49. Table 5.20: Employment in cottage, tiny and small 244
scale industries 50. Table 5.21 Summary statement of the perceptions 246
of HHs on impact indicators 51. Table 5.22: Consumer’s Willingness to Pay for 247
Electricity at a Hiked Rate of Tariff by Levels of Education
52. Table 5.23: District wise status of Metering 248 of sample units belonging to commercial and industrial category
53. Table 5.24: District wise status of Supply of 249 Electricity to commercial and industrial users
54. Table 5.24: Alternative Sources of Power / Stand 250
by Facilities and the associated cost for commercial and industrial users of different capacity size (KW terms)
10
List of Charts Page No.
1. Chart 1: Power generation mix during several 21 plan period
2. Chart 2: Reasons for poor financial health 25
3. Chart 3: Plant load factor (PLF) 41
4. Chart 4: Load duration curve 41
5. Chart 5: T&D loss determination between four states 140
6. Chart 6: Relationship between different party 161
7. Chart 7: GRIDCO structure 169
8. Chart 8: Reasons for economy in use of electricity 218
11
CONTENTS
Page No.
Declaration ii
Certificate iii
Area Certificate iv
Acknowledgements v
List of Table vii
List of Charts x
CHAPTERS
1. INTRODUCTION
I. Backdrop of Power Sector Reforms 1
II. Review of Literature 2
III. Significance of Study 10
IV. Objective of the Study 11
V. Hypotheses of the Study 12
VI. Scope and Limitations of the Study 12
VII. Methodology of the Study 13
VIII. Organisation of the Study 14
2. POWER SECTOR REFORMS: A CONCEPTUAL
FRAMEWORK
i. Introduction 15
ii. What is Reforms 17
iii. Role of Power Sector in Indian Perspective 19
iv. Power Sector in Pre-reform Period (1961 – 90) 26
v. Indian Economy: Growth of Power Sector 26
vi. Power Sector during Reforms period (1992 – 2002) 29
vii. Original Electricity Bill 2001 35
viii. Private Sector Participation in Generation 37
12
III. GROWTH OF POWER SECTOR
i. International Scenario of Power Sector 39
United Kingdom (UK) 39
United State of America (USA) 44
Brazil 52
Argentina 56
iii. Indian State’s Experiences 60
Andhra Pradesh Reforms 62
Delhi Reforms 79
IV. POWER SECTOR REFORMS
i. Electricity Act. 2003 97
ii. Single Buyer Vs. Multi buyer Model in Distribution 105
iii. World Bank Models on Unbundling of PSUs 109
iv. Reforms in Electricity Tariffs 110
v. Availability Based Tariff 122
vi. Methods of Calculation of Cross Subsidy 132
vii. High Transmission Energy Audit 138
V. RESTRUCTURING INITIATIVES IN ORISSA’S POWER SECTOR
i. Introduction 158
ii. First Phase of Reforms 159
iii. Second Phase of Reforms 164
iv. Restructuring of GRIDCO 166
v. Sequence of events of reforms 170
vi. Benefits of Reforms 172
vii. Analysis of Fault lines – 186
Kanungo Committee’s Findings
viii. Turnaround of GRIDCO – A Case Study 202
ix. Comparison of Financial Performance: 211
Orissa Vis-à-vis Andhra Pradesh
13
VI. SOCIO ECONOMIC IMPACT ASSESSMENT OF POWER
SECTOR REFORMS
i. Introduction 213
ii. Micro level data source: Sampling framework 214
iii. Analysis of household data 216
iv. Uses of Electricity 223
v. Electricity Tariff 226
vi. Problems in supply of Power 230
vii. Socio economic impact of reform on education 238
viii. Socio-economic impact of reforms on Health 241
ix. Socio economic impact of reforms on women 242
x. Impact of power sector reform on livelihood 244
xi. Consumer’s willingness to pay at hiked rate 247
VII. CONCLUSION
• Summary 252
• Findings 256
• Suggestions 266
• Scope for further research 268
VIII. SCHEDULE OF ENACTMENTS 269
IX. LIST OF ABBREVIATIONS 270
X. BIBLIOGRAPHY AND REFERENCES 273
14
Backdrop of Power Sector Reforms
The Indian constitution has included power in concurrent list, which means
both the centre and state share the responsibility for this sector. Article 246 of
the constitution vests the parliament as well as the state legislature with the
power to frame laws. The Electricity Supplies Act. 1948 was amended in
1991 to permit private sector participation in generation. Many Independent
Power Producers (IPPs) came with their proposals but very few could get the
financial closure and commissioning of power plants in 10 years. The most
important factor was that most of the state electricity boards were fast moving
towards bankruptcy. The reforms carried out in 1991 in the area of power
generation made us realize that reform has to begin from distribution end for
sustainable development of power. The process of distribution reform started
with the enactment of regulatory Act. In 1998 to minimize the political
interference in power sector and rationalize the tariff. In pursuance to reforms,
states started unbundling the vertically integrated structure of state electricity
boards (SEBs) into three separate corporate identities of Generation,
Transmission and Distribution as a precursor to the participation of private
sector in distribution.
Learning from the Orissa experience, the main metric for choosing companies
was not based on valuation, but on performance improvement goals. In order
to promote competition in the electric power sector, the Electricity Act 2003
(E. Act) mandates open access to the transmission and distribution network
for any supplier of electricity. Successful implementation of structural reform
requires both the hardware of technological advances in the power system and
the software of workable contractual relationships. Utilities need to make
efforts to identify such links / areas of high losses; there is still significant
uncertainty and differences over the real level of total as well as Transmission
and HT losses. Even two to three years after the establishment of the SERCs
15
and the reforms process, there is still ambiguity over the real level of T&D
losses.
Review of Literature:-
Industry and Energy Department, World Bank (1996) in its research paper
“Power Sector Reforms in Developing Countries and Role of World bank”
discusses the experience of the Bank with the sector and the main drivers for
sector reform, the expected benefits of reform, the formulation of the Bank's
policy in this area, the principles and elements of reform, and the
methodologies of bringing about reform. The key message with regard to the
last point is that selection and design of the reform process and final sector
structure must be adapted to each country. Hence, the country's authorities
must make judicious choices among the many power sector restructuring
models and concomitant regulatory frameworks. The paper also discusses
issues of implementation lessons of experience, and the role of the Bank in
the reform process.
The precise dimensions of the governmental and sectoral reform may vary,
but in each case the reform effort needs to be governed by a set of clear
objectives. These are to (a) increase efficiency in generation through
competition, whenever possible, or through regulation based on efficient
enterprises and energy and other measures; (b) maintain service reliability by
setting strict rules to supply and variations from the technical standards (e.g.,
in voltage and frequency levels); (c) increase the security of supply in terms
of numbers of suppliers and types of energy resources; (d) improve
environmental protection by establishing clear rules in the construction and
operation of energy facilities, coupled with enforcement mechanisms and the
requisite penalties or incentives; (e) attract capital, domestic or foreign, by
establishing clear and stable" rules of the game" that relieve the government's
burden of funding the sector; and develop competition in the electricity
16
services to customers, where viable, as a means of increasing the economic
efficiency of the sector.
The policy advisory group of Infrastructure Development Finance
Company Limited (IDFC), 1998 in its research paper “Power Sector Reform
in Orissa: Should and can it be replicated?” This research reviews this process
in Orissa, to examine its replicability for other states. It concludes that it
should be possible to transfer the reform process well beyond Orissa, subject
to a few safeguards. The objective of the privatisation process must be to
transfer the companies to the private sector, followed by obtaining a fair price
for government assets. At the same time it is imperative to insulate the
outcome against the possibility of renegotiations and default.
To reiterate, the replicability of the Orissa experience lies in ensuring that the
private sector is able to run the privatised entities, i.e., they are fundamentally
commercially viable. Doing this will require structuring distribution zones
properly and ensuring adequate financial support for the reforming entity, i.e.
the DISCOMs, during the transition process, so that it does not end up with an
unhealthy balance sheet, even when it is operationally efficient. It is also
essential to remember that people are as important as structure. To that end,
the selection and continuance of persons in charge of the process is of utmost
importance, as is the composition of the regulatory body. Subject to these
safeguards, which appear relatively easy to implement, it should be very
much possible to transfer the electricity reform process well beyond Orissa.
Asian Development Bank (ADB), 2001-02 in its research paper which acted
as Blue Print for “Power Sector Development” has identified the fault lines
and has found out the probable reasons which have emanated from:
• inadequate power generation capacity;
• lack of optimum utilisation of the existing generation
• capacity;
17
• inadequate inter-regional transmission links;
• inadequate and ageing sub-transmission & distribution
network leading to power cuts and local failures/faults;
• large scale theft and skewed tariff structure;
• slow pace of rural electrification;
• inefficient use of electricity by the end consumer;
• lack of grid discipline
In view of the fact that addition of new capacity takes relatively longer time,
strategies have also been formulated to augment power supply in
short/medium run. These are:
• Increased generation through Renovation and Modernization (R&M)
of old stations.
• Utilisation of the surplus capacity of the captive power plants into the
grid
• Demand Side Management (DSM) to flatten the demand curves
(introducing time of day tariffs and metering).
• Introduction of a new system of matching time and load profiles for
different zones in the country.
• Energy Conservation (The Ministry is piloting the Energy
Conservation Bill, which, when enacted, will provide necessary legal
framework for promoting conservation and efficiency).
• Evacuation of power from the power surplus eastern region.
Sankar, T.L (2002), Advisor-energy, Administrative Staff College of India,
Hyderabad, in his work on “Power Reforms in India – the search for an
indigenous model for promoting competition” has identified the major
problems namely, the slow rate of addition to power generating capacity; the
lack of noticeable improvement in the governance, management and level of
service to consumers; the failure of efforts to induct the private sector into
18
distribution; the inability to find a solution to the problem of subsidised
supply of power to agriculturists; the chaotic condition of governance of LT
distribution with, inter alia, the level of T&D losses remaining undetermined
and the annual loss reduction in the system being very slow; the
rationalisation or rebalancing of tariffs becoming a losing game because the
average cost of supply increases faster than the possible rates of increase of
tariffs; and the deficits accumulated over the years imposing an unbearable
interest burden limiting the capacity to raise funds in the commercial market.
He has also attempted to find out the followings:
• Should farmers, like other customers, pay the cost-of-service or the
average cost of supply?
• If farmers cannot pay the tariff and have to be provided power at
subsidised rates, what should be the level of subsidy?
• Who should pay the subsidy -- other users of power or all taxpayers
through the state government?
• Should the Government of India pay part or the entire subsidy as it
does in the case of fertilizer?
• If the tariff for agriculture is very low, is it worthwhile installing
meters for these consumers?
He has suggested of Revised Reform Programme (RRP). The RRP should be
taken as a comprehensive integral programme consisting of the following
elements, which should be implemented together.
Declaration that all new generating capacity would serve the consumers or
DISCOMs directly, abandoning the single-buyer model.
19
Agricultural pumpsets and small households, which on socio-political
considerations have to be provided electricity at below the average cost,
should be supplied by an earmarked allocation from the generating plants
with the lowest generating costs. The quantity supplied thus as an
‘‘entitlement’’ should be specified by the government.
DISCOMs should be much smaller than currently contemplated and have
a maximum turnover of Rs. 6-8 billion.
All management of the distribution system below 11 kV should be
gradually shifted to the consumers themselves, with the requisite technical
and investment support coming from the DISCOMs.
Regulators should settle within one year the issues of relevance for long-
term multi-year tariff fixation, with explicit targets for T&D loss reduction
and for various other parameters.
Accumulated deficits and securitization and APDRP should be linked as
proposed above.
Abraham, P (2003), ex-power secretary, Government of India in his work on
Power Sector Reforms; Focus on Distribution has emphatically identified as
the one of the prime movers of the economic development. In his work he has
stated the non-availability of sufficient power and of good quality which is
going to be the single most critical constraint for the overall development of
the country.
Power distribution throughout India is plagued by:-
• Inadequate and deteriorating physical infrastructure
• Skewed tariffs, high T&D losses, theft of energy
20
• Poor collection of revenue
• Dissatisfactory management practices and extreme consumer
dissatisfaction and more particularly the situation is acute in rural
areas.
The budgetary provisions of the state governments were reducing and the gap
between demand and supply was ever increasing and the gap between cost of
supply and tariff was widening. He stressed on the need for a comprehensive
accelerated reforms basing on the global experiences particularly from South
American Nations and USA, UK, Canada, etc.
He has impressed on the need of choosing right kind of reforms model among
the laid down models. The pre-requisites for carrying out such reforms and
privatization and the road map ahead for bringing the reforms to their logical
conclusion, so that a healthy and viable power sector can be created to
contribute substantially to the alround growth of our economy.
He has elaborated on the need of Government’s support for reforms, including
support during the transition period, organisational and financial restructuring,
and all other such issues which are germane for reforms.
Tongia, Rahul (2003), in his Stanford – CMU Indian Power Sector Reforms
Studies has analysed the following things: -
• Will reforms lead to economic viability of the system? Will this come
through tariff increase or cost control (or both)?
• What is the best role for the regulator, and are they equipped to be fair,
transparent, and independent regulators?
21
• If we open the sector up to privatization (distinct from retail
competition), who will come in? Are there enough players? What
returns do they want or expect?
• Should rapid privatization of viable (urban) areas be done quickly, or
will such cherry-picking harm the overall system? To what extent
should there be pooling of costs (both at the generation level, and at the
retail level)? How fair and effective are such systems?
The analysis indicates several important ingredients for successful reform. For
starters, initial assumptions must be realistic and accurate, as must targets for
the participants. This was one of the major failures in Orissa, where the losses
were significantly higher than thought, and the growth of paying customers
did not materialize.
In addition, there needs to be sustained government support for reforms,
ranging from things varying from anti-theft legislation, to managing SEB
unions, to overcoming public opposition in general. In addition, if the newly
corporatised (or privatized) entities are to behave like companies, any gap
between average tariff and average cost of supply must be met through
explicit government subsidies (which, ideally, should be target driven and
time-bound).
At the end of the day, India’s reforms have thus far gone a fair ways towards
the ingredients necessary to reaching the goals of increased access, efficiency,
and viability, but they have not yet directly done so. These reforms, necessary
but perhaps not sufficient, will be the focus of enormous effort and
expenditure by the government, funding agencies, and companies in the
coming decade.
22
Ranganathan, V and D, Rao Narasimha (2004), IIMB in their research
paper on “Power Sector Reforms in India” have analysed the progress of the
reforms in India which formally started along-with economic liberalization in
1991-92, though the impetus for private sector participation in the power
sector predates this. Despite aggressive reform policies in the 90s, private
sector participation was moderate at best, and the financial losses and cash
flows of State Electricity Boards (SEBs) reached crisis proportions.
They have outlined the stages of power sector reform, placing the
development of markets in context. They warn that in a situation of supply
scarcity, competitive markets – namely spot markets – can lead to price
increases and volatility, which will be slow to change due to short-term
supply inelasticity. More important is the need for bilateral trade under open
access to better exploit cheap, remote hydro and coal fuel resources in
northern India. They envision an environment of managed competition in a
bilateral market with regulated (capped) contract prices.
Shahi, R V (2005), currently the power secretary of India, in his work on
“Indian Power Sector; Challenge and Response” has highlighted the
infirmities in the power sector namely:-
• Power supply to Industry and Agriculture
• Poor quality of supply of power
• Lack of concern for consumers
• Highly skewed tariff structure
He has recognised the importance of manufacturing sector as it contributes
significantly to the growth of economy and helps in generating employment.
For them enabled to be competitive issues such as price of power, supply of
power without interruptions and quality of power are all equally important
and relevant. Risk perception of developers and lenders has been so high that
23
in spite of best of private power policy formulated and notified in early
nineties, active responses were negligible. Having failed to get right and
adequate response from private sector, in order that vital infrastructure sector
does not get starved of funds for required expansion, during the 10th. Five
year plan public sector outlay was substantially enhanced. Continued inflow
of Government resources without commensurate commercial revival of this
sector would not only be an unsustainable arrangement, but as a matter of
fact, this may not even yield desired results.
Lesson learnt from Orissa’s privatization is that in India private sector today
is not equipped to handle adequately rural electricity distribution. It needs to
be recognised that consumers need not and should not wait for improved
services only when privatization happens. Competition is needed even within
the public sector on basis of performance benchmarks. He has maintained that
significant amount of improvement can be brought about even without any
substantial investment, just by way of toning up the operational maintenance
practices, better inventory management, training and development of people
and sharpening of work culture.
Significance of the Study: -
The present work aims to highlight the extent of reforms in power sector
commenced since Sept. 1991 to till date. It shows the comparative study of
rate of growth in generation, distribution and per capita consumption of power
along with several developed nations.
It also systematically studies the experience of ORISSA, which adopted
reforms process in late 1996 and its problems over these years. The findings
of the study will highlight the various aspects in this regard, which require
attention of the Govt.
24
Objective: -
Orissa is the first state in India to initiate reforms in the Power Sector. It has
left a benchmark for the whole of country and for a good experimentation.
Again in this backdrop, the objective of the project would be to study the
impact of reforms in the development of Generation, Transmission and
above all in the Distribution end. A concerted effort would be made to
have comparative analysis among different states that adopted reforms.
In an effort to achieve these objectives, the following steps would be
undertaken
- To ascertain the provision of quality power on demand to all
consumers.
- To study the different elements which determines the tariff structure?
To see whether there’s availability of alternatives to consumers.
- To verify the creditworthiness of power sector and if it is capable of
funding future investment needs.
- To check the extent of progress made in rural electrification.
- To measure the degree of transmission and distribution loss, if it’s in
the permissible limit.
- To systematically analyze the reasons for Orissa’s failure to become a
financially viable corporation.
- To make the interstate comparison of efficiency i.e. Orissa with Delhi
(Which adopted reforms in 2002) and to bring out the weakness of the
previous at the distribution end.
- To suggest alternatives to increase the cash flow without tariff hike.
- To examine the existing laws prevailing in different states to curb the
menace of power theft (Inter state comparison on state Electricity Act.)
25
Hypotheses: -
- To study if the power sector reforms have brought in commercial
viability in Power Supply Industry.
- To study if the power sector reforms resulted in the Supply of power at
Reasonable and Affordable Rate.
- To study if the power sector reforms have brought in Fiscal Discipline.
- To check if the introduction of OERC (Orissa Electricity Regulatory
Commission) has led to rationalization of Tariff structure and protected
the consumer’s interest.
Scope: -
The scope of present study has been with an eye on the process of power
sector reforms in India that was initiated in early 90’s. The present study is
restricted to few aspects i.e. a conceptual background on legislative aspect of
Indian Electricity Act. 1910 and Electricity Supplies Act.1948 and its reforms
that was initiated by amending them in 1991 and subsequent in Electricity Bill
2003.
It also empirically studies the various functional reforms carried out by
different state governments. It covers time series and cross section analysis on
trend scenario.
Limitation of the Study: -
The compilation and execution of the present study have to pass through
several constraints due to unavailability of adequate primary data. The
available data is very unsystematic which discouraged the systematic
26
treatment of data. Hence the study would have been more systematic if
detailed data would have been available.
Methodology: -
The present study is carried out by using some primary data and rest on
secondary statistical data. The data has primarily been obtained from Power
Management Institute, NTPC Ltd. POWERGRID, University Library -
University of Delhi, Corporate Office-GRIDCO/OPTCL and from several sub
divisional offices across India. Apart from this, several published journal viz.
TERI, Energy Watch, powerline, ADB Review and by interviewing some
senior personnel of different areas related to power industry. The method of
study includes the following:
-A survey of available literature on topic.
-Collection of data (Both time series and cross section)
-Analysis of published & Non-published Journals.
-Analysis of Primary & Secondary Data.
-Analysis of circulated Questionnaire.
-Classification and tabulation of data.
-Preparation of charts, graphs and schedules for proper presentation
-Suggestion and remedial measures for overcoming the problems faced by the
organization officials and scope for further study.
27
Organisation of the study
I. INTRODUCTION
II. POWER SECTOR REFORMS: A CONCEPTUAL FRAMEWORK
III. GROWTH OF POWER SECTOR
IV. POWER SECTOR REFORMS
V. RESTRUCTURING INITIATIVES IN ORISSA’S POWER SECTOR
VI. SOCIO ECONOMIC IMPACT ASSESSMENT OF POWER SECTOR
REFORMS
VII. CONCLUSION
• Summary
• Findings
• Suggestions
• Scope for further research
VIII. SCHEDULE OF ENACTMENTS
28
POWER SECTOR REFORMS: A CONCEPTUAL FRAMEWORK
Introduction
Electricity was entirely under the provision of the states as per the
Government of India Act 1936 but it was because of Dr. Ambedkar, who
was a member of the executive council for Power during 1942-46, Power was
included in the Concurrent List, Schedule VII of the constitution.
Recognizing the potential for the growth of power at that time, Dr. Ambedkar
felt the development of electricity in the whole country which cannot be left
to the provinces alone. According to Article 246 of the constitution,
parliament as well as the state legislatures has the concurrent powers to make
laws with respect to electricity. Whenever there is any conflict in the laws, the
central law shall prevail over the state laws. Dr. Ambedkar’s philosophy for
jurisdiction of central govt. over the electricity had withstood the test of time.
“The most challenging unbundling of all would be that of the
bureaucracy”
– Editors’ comment, India Infrastructure Report 2002.
Need For Reforms
Developing countries needs energy particularly electric power for social and
economic development. Many developing countries are unable meet their
energy demands of their economies because of the poor performance of their
existing plants and the shortage of adequate investment for new facilities to
meet the growth in demand.
Although the World Bank experience has been mixed, the performance of its
client countries electric power utilities has generally been poor to dismal. The
sub standard performance is usually reflected in low plant availability and
productivity, poor service to customers (Characterized mainly by energy
shortages leading to frequent blackouts and substandard system frequency)
29
and poor financial returns. The proximate causes of these problems are, on the
physical plant level, lack of readily available spare parts, scarcity or poor
quality of operating materials viz. lubricants, chemicals etc, poor maintenance
practices, inadequate training of operation and maintenance personnel and
lack of investment in necessary upgrading.
On financial front, government policies that have kept electricity tariffs well
below the cost of supply, combined with weak collection efforts by utilities,
have drained government budget resources instead of contributing positively.
It has thus been common for World Bank borrowers to request financing of
new plant at the same time as they maintain existing plant availabilities of less
than 50 percent.
A final problem for the power sector is on the institutional side, where
governments have controlled their power utilities as if they were departments
of the state and have used this control to pursue populist politics and social
policies that are incompatible with the commercial objectives. Governments’
inability to continue large subsidies to these utilities for operating purposes
and to mobilize funding for large investments needed for new plant to satisfy
the growing demand, with the private sector’s reluctance to invest in such
poor risk ventures, are leading to further deterioration in the performance of
electric utilities.
30
Table 1: Power Sector Performance: Gaps between Targets and Realities on Key Indicators in a sampling of regions and Countries
Note: SSA – Sub- Saharan Africa What is Reform?
Power sector reform consists of process of changes along four different but
inter-dependent axes: management, ownership, structure and regulation. The
structural change begins with the realization that a monolithic structure, often
established as part of a centrally planned or command economy is too
inflexible to respond to market forces and to provide appropriate incentives
for such responses. The government functions need to be broken into
a. That the government cannot relinquish such as the roles of setting
general policy & strategy, and sector regulation and supervision.
INDICATOR TARGET
REALITY
REGION / COUNTRY
Percentage of Population Served Utility management
• Customers per employee • Blackouts (hrs. / Yr.) • Load Factor • System Losses
Commercial Performance • Accounts receivable
(days) Financial Performance
• Return on assets • Self-financing ration
90%
150-250 7
70% 10-12%
30-45
8-12% >25%
5%
42 750 46% 35%
462
-19.8% 0%
SSA
Bangladesh Philippines
Nepal Bangladesh
Nigeria
India Jordan
31
b. Those that are subsidiary to the role of government and that can be
transferred, wholly or partially, to the private sector, such as
ownership, operation and management of energy facilities.
c. Those are not the core functions of the sector & that can be transferred
to other sectors such as research & development and construction and
manufacturing services.
The government’s function can be assumed by a ministry of energy, or state
energy commission or state supervisory agency. The ownership function can
be retained by the state, or it can be transferred to municipal or regional
companies or private sector. In any case the day to day, the day to day
management of the enterprises, even if fully state owned, should be exercised
by commercially operating entity. Finally the third category of functions
should be left to universities, research and development institutes, and
independent private sector companies.
Thus, the process of reform moves along two intertwined paths, one relating
to the other government actions and one relating to sector & enterprise
restructuring. The first path involves legal and institutional framework;
second involves commercialization and corporatisation of enterprises. It is
clear that the type of the regulatory framework and sector structure are closely
interconnected. The precise dimension of governmental and sectoral reform
may vary, but in each case the reform effort needs to be governed by a set of
clear objectives. These are to
a. increase efficiency in generation through competition. Or through
regulation based on efficient enterprises and energy use, conservation
and other measures.
b. maintain service reliability by setting strict rules to limit unreasonable
interruptions of supply and variations from technical standards ( e.g.
voltage and frequency levels)
32
c. increase the security of supply in terms of numbers of suppliers and
types of energy resources
d. improve environmental protection by establishing clear rules in the
construction & operation of energy facilities, coupled with
enforcement mechanisms and the requisite penalties or incentives
e. attract capital, domestic or foreign, by establishing clear and stable
“Rules of the Game” that relieves government’s burden of funding the
sector
f. develop competition in the supply of electricity services to customers,
where viable, a means for increasing the economic efficiency of the sector.
Role of Power Sector in Indian Perspective
The growth of economy calls for a matching growth for infrastructural
facilities where power is a major tool. Invariably power is an indispensable
unit of infrastructure, whose growth can never be compromised with. The
growth rate for the demand of power in developing economy like India is
generally higher than the growth of GDP (Gross Domestic Product). In order
to achieve a healthy growth rate of GDP around 8 per cent per annum, the
growth rate for power is prescribed to be more than 10 per cent per annum. So
far power sector has been greatly dependent on budgetary support and
external borrowings.
This thrust on generation, and even expensive IPP power, is best
characterized by Homi Bhabha’s oft-quoted statement,
“No power is as costly as no power”
The power generation grew from one MW in 1900 to 1363 MW during the
independence. After independence, the need for wide spread availability of
power was felt. Thus Electricity (Supply) Act, 1948 was enacted with an
intention to rationalize generation, transmission and distribution of electricity
in the country. The state electricity boards (SEBs) were allowed to start their
33
own generating stations except the nuclear power stations. To meet the
growing demand of power centrally sponsored Public Sector Enterprises like
National Thermal Power Corporation (NTPC) & National Hydro Power
Corporation (NHPC) were formed in 1975. Earlier being entrusted with
generation of power from coal and gas whereas later was asked to look after
the hydro based power generation. Power Grid Corporation of India Ltd.
(POWERGRID) was formed in 1989, to look after transmission of power and
to develop the interconnected grid system across the country.
NTPC was set up in 1975 with a view to promote and develop thermal power
in India. The corporation has grown geometrically in terms of both production
and quality power supply, within the country. The corporation has 13 coal
based thermal power projects and 7 gas / liquid fuels based combined cycle
projects. NTPC has adopted multi pronged growth strategy to become 40,000
MW plus company by the end of 2012. It has also acquired 314 MW of
captive power plant of SAIL through formation of joint venture with SAIL.
National Hydroelectric Power Corporation (NHPC) was set up in 1975 and
soon got the title of “Largest Producer” of hydro Power in India. NHPC has
commissioned several big hydro based electric generation projects across the
country including some in the difficult terrains. It also lends technical advice
to different state govts. in their projects.
Of course, hydro projects are attractive since, once constructed, they have
very low marginal costs (no fuel costs), and they offer reasonably high levels
of load control and quick start capabilities (subject to water availability).
However, Indian dispatch mechanisms do not fully account for marginal
cost pricing. While the ash content is high, the sulphur content is quite low,
reducing the need for clean-up technologies. No Indian coal plant today
incorporates Flue Gas Desulphurization (FGD) technology.
34
Nuclear power generation in India is in its infancy. It hardly meets 2.5% of
total generation. So Thorium, like Uranium 238 is the primary raw material
whose isotopes are available. (The primary form, or isotope, of natural
uranium, is fertile.
It can not undergo a fission reaction until converted into another element
through a nuclear reaction, such as in a Fast Breeder Reactor). Breeding is the
process of producing more fissile material from fertile than consumed to
sustain the reaction. India has the largest thorium reserves in the world, which
if converted to fissile material, could provide hundreds of thousands of
megawatts of power, for many, many centuries.
(Chidambaram, R. and C. Ganguly (1996). "Plutonium and Thorium in the Indian
Nuclear Programme)
Chart 1: Power generation mix during several plan
period
35
Table 2: Generation of Power – Sector wise & Compositions
ALL FIGURES IN MW X PLAN XI PLAN TOTAL
CENTRAL SECTOR
• Ministry of Power • Ministry of Coal • Department of Atomic
Energy • Ministry of Non-
conventional Energy Sources
23,000 210
1,220 4,055
23,500. 1,500 5,160 6,625
46,500 1,710 6,380 10,680
Total Central Sector
28,485
36,785
65,270
Total State Sector
8,300
10,600
18,900
Total Private Sector
9,400
13,500
22,900
Overall Capacity Addition (approx.)
46,000
61,000
1,07,000
36
Table 3: Hydel Potential – Global Scenario
Table 4: States with substantial undeveloped Hydro potential
and high proportion of Unmetered supply, large scale theft of power in
collusion of SEB staffs, poor billing and collection mechanism, perennial
problems like theft of cable, wires etc., non payment of government dues and
even resistance to disconnection of supply for non-payment of dues, poor
customer grievance redressal mechanism by SEBs.
Due to ailing state finances, state governments did not show any willingness
to stand guarantee for payment for power purchased by the SEBs. In 1992, the
government of India offered counter guarantee to few fast track projects but
none of these could reach financial closure. Investors had to face formidable
procedural hurdles; negotiations had to be carried out with numerous agencies
both at centre and state level. Since the raw material for thermal power being
44
coal, so IPPs wanted to ensure the smooth and timely supply of coal. But both
coal companies and railways, which transport the coal, expressed their
unwillingness to enter in to any legally enforceable fuel supply agreements.
The public perception was that power supply from IPP is costlier than from a
similar publicly owned generating station which led to the reopening of the
Power Purchase Agreements (PPAs). Added to this was the bureaucratic
delay. Single window mechanisms proved to be ineffective. This was not
conducive in attracting the private investment in the power sector. The
questions were raised about the Government commitment to power sector
reform especially for the private players.
Private players did not show any interest in power transmission. The scope
available for the owner of a transmission line to cut costs or maximize
revenue is remote because the owner has no control over the flow of power in
his line. In developed countries also investors did not show much interest in
erecting transmission line.
The private sector has to play an important role in power distribution. The
sizeable backlog of investment required to reduce technical and commercial
loss and keep pace with load growth. More importantly improvement in
operational efficiency and quality of service, proper billing and collection
mechanism, greater responsiveness to consumer needs will be the principal
gains from private ownership and management of distribution network. A
successful distribution reform holds the key to success in restructuring of
power sector.
45
Table 10: Public Sector Investment In power 1992-2002 Centre States and UTS Total Investment
(Rs. Cr.) % of Plan outlay
Investment (Rs. Cr.)
% of plan outlay
Investment (Rs. Cr.)
% of Plan outlay
Eighth Plan
30,426 11.0 46,251 24.0 76,577 15.8
Ninth Plan
53,299 10.8 70,926 18.9 1,24,526 14.5
Note: In the ‘investment” column, expenditure is shown for eighth plan and outlay for ninth plan. Source: Planning Commission, Annual Report (2001-02) on the working of State Electricity Boards and Electricity Departments. Annexure 2.3 & 2.4 Table 11: Capacity Addition 1992-2002 Central
Source: Planning Commission, Ninth Plan, Vol II, Chapter 6, Table 14 and Draft Tenth Plan, Vol 2, Table 8.2.2
46
From the above two figures namely Public Sector Investment in Power and
capacity addition during the ten year period led us to this conclusions-
1. The central government started spending more money on power in
comparison to previous years and a substantial hike in central outlay in
ninth plan can be seen.
2. Actual capacity addition fell seriously short of target in both Eighth
and Ninth Plan.
3. Private sector participation in capacity addition was worse among these
three. In eighth plan actual capacity addition almost 50% of the target
set but in ninth plan it was even less than 30% of the target set.
4. Capacity addition of hydro power in state sector was steadily
increasing & phenomenal rise can be observed in ninth plan.
5. Actual capacity addition fell seriously short of target both in Eighth
and Ninth Plan periods.
In short, the post reform performance shows that far from any improvement in power situation, this sector suffered severe setback.
Table 6: Electricity – GDP Elasticity in India Elasticity
First Plan 1951-1956 3.14 Second Plan 1956-1961 3.38 Third Plan 1961-1966 5.04 Fourth Plan 1969-1974 1.85 Fifth Plan 1974-1979 1.88 Sixth Plan 1980-1985 1.39 Seventh Plan 1985-1990 1.50 Eighth Plan 1992-1997 0.97 Ninth Plan 1997-2002 0.75
Calculated and compiled from data from the Planning Commission and Ministry of Finance (Economic
Surveys) While many Plan documents claim growth targets of 40-60,000 MW for the
coming 5 Year Plans, and even segment these into state, central, and private,
it is unclear how such growth will be financed or sustained in the current
47
operating environment. Assuming a target of 100,000 MW expansion, which
would less than double the per capita consumption given the increase in
population over 10 years, the estimated investment would be 150 billion US$,
using the rule of thumb (coal-centric) that 1 MW of capacity addition requires
1 billion dollars investment for generation, and half that more for T&D. 15
billion dollars per annum is almost 4% of the GDP, a number too high for
domestic savings rates and budgets alone. This was one of the prime reasons
that the government wanted foreign investment in the power sector, making
this a central feature of the 1991 reforms.
(India’s development is largely based on Soviet-style 5 year plans, and a few
Annual Plans in between. Critics state that too much effort is placed on Plan
(largely capital) expenditure, and not enough focus is there on operating
expenditures, like maintenance, monitoring, enforcement, analysis, etc. In
most states, if a consumer needs a new connection, they have to pay non-
trivial connection fees if the lines need to be extended. The charges vary by
state. Part of this may be due to poor metering. Older electromechanical
meters have a threshold below which they fail to register consumption. Newer
electronic meters only became available in the 1990s.)
(The Indian (British-based) system was supposed to have a near permanent bureaucracy, giving
stability as the elected politicians shifted over time. This is in contrast to the American system, where
the new executive office brings in a new (but fixed term) operating staff for the various departments.)
48
Electricity Bill 2001(Power for all by 2012)
There is a major revamping of India’s power sector planned via the Electricity
Bill 2001, which is in Parliament but has not yet been passed. This legislation
was originally planned for 2000, and was renamed for 2001, but the act was
ratified by the parliament only 2003, referred as Electricity Act. 2003.
Main Features of Bill include
1. Formulation of a National Electricity Policy by the Govt. of India
2. Strengthening anti-theft laws
3. Generation free from licensing except for hydro units
4. Requirement of techno-economic approval done away with
5. Captive generation free from controls
6. Open access to transmission lines
7. Setting up of State Electricity Regulatory Commission (SERC)
mandatory
8. Open access in distribution to be allowed by SERC in phases
9. Retail tariff to be determined by regulatory commission
10. Trading a distinct activity permitted with licensing
11. Establishment of Appellate Tribunal
This would be a major bill, revamping the 1910 and 1948 Laws, and
extending reforms further. Fundamentally, it moves the country towards
power markets, but it provides very little detail on the operations of such a
system, e.g., the role of any Independent System Operator (ISO). It states that
Regional Load Dispatch Centres will be responsible for grid operations, and
failing their abilities or powers, the Central Transmission Unit (i.e., Power
Grid) will take over this role. The Electricity Grid Code referred to in the bill,
as formulated today (Power Grid 2002), states that these entities will not trade
power, but only facilitate power transactions. The Power Trading
Corporation, though designed to trade power, is not set up as an ISO. Both the
Bill and the Code indicate Regional as well as State Load Dispatch Centres.
49
This appears to be a poor design, as the synchronous grid should not operate
with such granularity.
The Electricity Bill 2001 has a strong focus on bulk (High Tension)
consumers, who can get open access to generators (captive or IPPs).
However, it doesn’t indicate how much surcharge the utilities can pose, for
the losses they incur (loss of paying customer) (Mahalingam 2002). This
tension, over paying customers that sustain the cross-subsidies of today, is
one of the major issues facing the Indian power system.
Table 12: Tenth Plan Power Sector Outlay (2002-07) Ministry/Department Outlay Centre Power 1,43,399 Coal 8,008 Atomic Energy 25,577 States & UTs 82,224 All-India 2,59,208 Note: The outlays of Ministry of Coal and Department of Atomic energy are for ‘Power programmes’ Source: Derived from Planning Commission, draft tenth plan, Vol 2, Annexure 3-A to 3-C Table 13: Financing Pattern of Central Sector outlay in Tenth Plan (Rs. Crore at 2001-02 prices)
Note: 1.The outlay under Atomic Energy covers both power and R&D programmes. In the Tenth plan Rs. 25577 are for power 2. The budgetary support for coal includes Rs. 1257.4 cr. And Rs. 8007.6 cr. Under ‘Ninth Plan Realisation’ and ‘Tenth Plan Projections’ respectively for power. (Neyveli Lignite Corporation). Source: Planning Commission, Draft Tenth Plan, Vol 1, Annexure 3-B.
Budgetary Support Total Outlay Internal and Extra-budgetary resources
on a year to year basis as income or expense in the period in which it
arises and Foreign Exchange Rate Variation shall be adjusted on a year
to year basis.
Recovery of Income-tax and Foreign Exchange Rate Variation
• Recovery of Income-tax and Foreign Exchange Rate Variation shall be
done directly by the generating company or the transmission licensee,
as the case may be, from the beneficiaries without making any
application before the Commission.
Provided that in case of any objections by the beneficiaries to the amounts
claimed on account of income-tax or Foreign Exchange Rate Variation, the
generating company or the transmission licensee, as the case may be, may
make an appropriate application before the Commission for its decision.
Deviation from norms
Tariff for sale of electricity by a generating company may also be determined
in deviation of the norms specified in these regulations subject to the
conditions that:
130
• The overall per unit tariff of electricity over the entire life of the asset,
calculated on the basis of the norms in deviation does not exceed the
per unit tariff calculated on the basis of the norms specified in these
regulations; and
• Any such deviation shall come into effect only after approval by the
Commission.
In case of the existing generating stations, TPS-I and TPS-II (Stage I & II) of
Neyveli Lignite Corporation Ltd, whose tariff was initially determined by
following Net Fixed Assets approach based on mutual agreement between
Neyveli Lignite Corporation Ltd and the beneficiaries, tariff shall continue to
be determined by adopting Net Fixed Assets approach.
Power to Remove Difficulties
If any difficulty arises in giving effect to these regulations, the Commission
may, of its own motion or otherwise, by an order and after giving a reasonable
opportunity to those likely to be affected by such order, make such provisions,
not inconsistent with these regulations, as may appear to be necessary for
removing the difficulty.
Power to Relax
The Commission, for reasons to be recorded in writing, may vary any of the
provisions of these regulations on its own motion or on an application made
before it by an interested person.
131
Determination of Tariff (under Electricity Act. 2003)
62. (i) The Appropriate Commission shall determine the tariff in accordance
with provisions of this Act for –
(a) Supply of electricity by a generating company to a distribution
licensee:
Provided that the Appropriate Commission may, in case of shortage of supply
of electricity, fix the minimum and maximum ceiling of tariff for sale or
purchase of electricity in pursuance of an agreement, entered into between a
generating company and a licensee or between licensees, for a period not
exceeding one year to ensure reasonable prices of electricity;
(b) Transmission of electricity;
(c) Wheeling of electricity;
(d) Retail sale of electricity.
Provided that in case of distribution of electricity in the same area by two or
more distribution licensees, the Appropriate Commission may, for promoting
competition among distribution licensees, fix only maximum ceiling of tariff
for retail sale of electricity.
ii. The Appropriate Commission may require a licensee or a generating
company to furnish separate details, as may be specified in respect of
generation, transmission and distribution for determination of tariff.
iii. The Appropriate Commission shall not, while determining the tariff
under this Act, show undue preference to any consumer of electricity but
may differentiate according to the consumer's load factor, power factor,
voltage, total consumption of electricity during any specified period or
the time at which the supply is required or the geographical position of
132
any area, the nature of supply and the purpose for which the supply is
required.
iv. No tariff or part of any tariff may ordinarily be amended more frequently
than once in any financial year, except in respect of any changes
expressly permitted under the terms of any fuel surcharge formula as
may be specified.
v. The Commission may require a licensee or a generating company to
comply with such procedures as may be specified for calculating the
expected revenues from the tariff and charges which he or it is permitted
to recover.
vi. If any licensee or a generating company recovers a price or charge
exceeding the tariff determined under this section, the excess amount
shall be recoverable by the person who has paid such price or charge
along with interest equivalent to the bank rate without prejudice to any
other liability incurred by the licensee.
Determination of Tariff by Bidding Process
63. Notwithstanding anything contained in section 62, the Appropriate
Commission shall adopt the tariff if such tariff has been determined through
transparent process of bidding in accordance with the guidelines issued by the
Central Government.
Procedure for Tariff Order
64. (1) An application for determination of tariff under section 62 shall be
made by a generating company or licensee in such manner and accompanied
by such fee, as may be determined by regulations.
133
(2) Every applicant shall publish the application, in such abridged form and
manner, as may be specified by the Appropriate Commission.
(3) The Appropriate Commission shall, within one hundred and twenty days
from receipt of an application under sub-section (1) and after considering all
suggestions and objections received from the public,-
Issue a tariff order accepting the application with such
modifications or such conditions as may be specified in
that order;
Reject the application for reasons to be recorded in
writing if such application is not in accordance with the
provisions of this Act and the rules and regulations made
there under or the provisions of any other law for the
time being in force:
Provided that an applicant shall be given a reasonable opportunity of being
heard before rejecting his application.
(4) The Appropriate Commission shall, within seven days of making the
order, send a copy of the order to the Appropriate Government, the Authority,
and the concerned licensees and to the person concerned.
(5) Notwithstanding anything contained in Part X, the tariff for any inter-State
supply, transmission or wheeling of electricity, as the case may be, involving
the territories of two States may, upon application made to it by the parties
intending to undertake such supply, transmission or wheeling, be determined
under this section by the State Commission having jurisdiction in respect of
the licensee who intends to distribute electricity and make payment therefore:
134
(6) A tariff order shall, unless amended or revoked, shall continue to be in
force for such period as may be specified in the tariff order.
Provision of Subsidy by State Government
65. If the State Government requires the grant of any subsidy to any consumer
or class of consumers in the tariff determined by the State Commission under
section 62, the State Government shall, notwithstanding any direction which
may be given under section 108, pay, within in advance in the manner as may
be specified, by the State Commission the amount to compensate the person
affected by the grant of subsidy in the manner the State Commission may
direct, as a condition for the license or any other person concerned to
implement the subsidy provided for by the State Government:
Provided that no such direction of the State Government shall be operative if
the payment is not made in accordance with the provisions contained in this
section and the tariff fixed by State Commission shall be applicable from the
date of issue of orders by the Commission in this regard.
Development of Market
66. The Appropriate Commission shall endeavor to promote the development
of a market (including trading) in power in such manner as may be specified
and shall be guided by the National Electricity Policy referred to in section 3
in this regard.
135
AVAILABILITY BASED TARIFF (ABT)
ABT has been under discussion since 1994 when M/s ECC, an ADB
consultant, first supported it. GOI constituted a National Task Force in
February 1995. It had ten meetings till end 1998 where all the related issues
were discussed. A draft notification was prepared for issue by government.
With effect from May 15, 1999 the jurisdiction was vested in the CERC.
Papers were sent to the Commission in June 1999 by the MoP. The
proceedings were held in the Commission from July 26 to 28, 1999. The ABT
order dated January 4, 2000 of the Commission departs significantly from the
draft notification as also from the prevailing tariff design.
Why ABT?
1. India plans to have an integrated National Grid. This will assist in meeting
demand with the least cost supply. Five Regional grids already exist. Some
linkages between Regions are also in place.
1. The five Regional grids work at vastly varying operational parameters
today. Frequency level is one such operational parameter. The target
frequency prescribed by the Indian Electricity Rules is 50 Hz
2. Integrated grid operations require the normalisation of frequency
across all five Regions. The alternative is to insulate each Regional
Grid by Back to Back HVDC links. This is an expensive option.
Normalisation of frequency requires proactive load management by
beneficiaries and despatch discipline by generators.
3. There is currently no formal system of financial incentives to promote
grid discipline.
4. The ABT provides this mechanism.
2. Chronic surpluses in the East and shortages in the South, have resulted in
sustained functioning of these grids at frequencies which are far beyond even
136
the normal band, liberally defined by the IEGC as frequency variation within
49.5 to 50.3 Hz
1. Continued functioning at non-standard frequency results in long-term
damages to both generation and end use equipment. This is a “hidden
cost” which is borne by the customer in the long term.
2. The ABT will induce corrections in the prevailing frequency to bring it
within the permissible band.
3. Frequent fluctuations in frequency caused by short-term variations in the
demand supply gap due to the tripping of load or outage of a generator or a
transmission line impose substantial costs on generators and consumers.
1. The ABT will address this problem by inducing grid discipline.
4. Economic efficiency dictates that least cost power should be despatched in
preference to more costly power (merit order despatch). This becomes
difficult without a two part tariff for all stations. States tend to compare the
total cost of central generators with the variable cost of their own stations,
since for them the fixed costs of state level stations are sunk costs. These
results in making central generation appear artificially more expensive than
state level stations even though on variable cost basis the former may be
cheaper.
1. The two-part tariff of the ABT by making the payment of fixed cost a
fixed liability of the states converts it into a sunk cost thereby levelling
the playing field between central generators and state level plants.
5. Currently beneficiaries are not liable for payment of the fixed cost
associated with the share of capacity allocated to them. If a beneficiary
decides not to draw any energy he can escape payment of the fixed charge,
which then gets paid by the person drawing energy. This is unfair since it
137
increases the cost of energy even for those beneficiaries who may be drawing
energy within their entitlements.
1. The two-part tariff of the ABT assures that each beneficiary will be
liable for payment of the fixed cost associated with its share of
allocated generation capacity.
6. Currently generators have a perverse financial incentive to go on generating
even when there may be no demand. This results in high frequency in the grid
as is endemic in the East
1. The ABT will discourage such behaviour by pricing generation outside
the schedule in relation to the prevailing frequency.
What Is ABT?
• It is a performance-based tariff for the supply of electricity by
generators owned and controlled by the central government.
• It is also a new system of scheduling and despatch, which requires
both generators and beneficiaries to commit to day-ahead schedules.
• It is a system of rewards and penalties seeking to enforce day ahead
pre-committed schedules, though variations are permitted if notified
One and one half hours in advance.
• The order emphasises prompt payment of dues. Non-payment of
prescribed charges will be liable for appropriate action under
sections 44 and 45 of the ERC Act.
It has three parts:
- A fixed charge (FC) payable every month by each beneficiary to the
generator for making capacity available for use. The FC is not the same for
each beneficiary. It varies with the share of a beneficiary in a generators
capacity. The FC, payable by each beneficiary, will also vary with the level of
availability achieved by a generator.
138
- In the case of thermal stations like those of NLC, where the fixed charge has
not already been defined separately by GOI notification, it will comprise
interest on loan, depreciation, O&M expenses, ROE, Income Tax and Interest
on working capital.
- In the case of hydro stations it will be the residual cost after deducting the
variable cost calculated as being 90% of the lowest variable cost of thermal
stations in a region.
- An energy charge (defined as per the prevailing operational cost norms) per
Kwh of energy supplied as per a pre-committed schedule of supply drawn
upon a daily basis.
- A charge for Unscheduled Interchange (UI charge) for the supply and
consumption of energy in variation from the pre-committed daily schedule.
This charge varies inversely with the system frequency prevailing at the time
of supply/consumption. Hence it reflects the marginal value of energy at the
time of supply.
How is ABT different from normal proceedings to determine generation
tariff?
1. The ABT proceeding has not attempted to consider most of the cost drivers
like ROE, Operational Costs, depreciation rate, composition of the Rate Base,
capital structure etc. Proceedings to redefine these norms are being held
separately. Hence the ABT proceedings have been concerned more with tariff
design rather than definition of tariff norms or determination of tariff levels.
2. Its incidence is a function not only of the behaviour of a generator but also
of the behaviour of a beneficiary. Disciplined beneficiaries and generators
stand to gain. Undisciplined beneficiaries and generators stand to lose.
139
Broad features of ABT design
1. It implements the long held view that electricity tariffs should be two-
part comprising a fixed charge and a separate energy charge.
2. It increases the target availability level at which generators will be able
to recover their fixed costs and ROE from 62.79% deemed PLF at
present to 80% (85% after one year) for all thermal stations, 85% for
Hydro in the first year and 77% (82% after one year) for NLC.
3. Misdeclaration of availability entails severe penalties.
4. It rationalises the relationship between availability level and recovery
of fixed cost.
The draft notification provided for recovery of (annual fixed costs
minus ROE) at 30% availability and recovery of ROE on pro-rata basis
between 30% and 70% availability. This order provides for payment of
capacity charges between 0% and target availability (as indicated in
item 2 above) on pro-rata basis.
5. The draft notification had provided for payment of capacity charges for
prolonged outages. This order disallows such payments.
6. It delinks the earning of incentive from availability and links it instead
to the actual achievement of generation. Hence incentives will be
earned by generators only where there is a genuine demand for
additional energy generation unlike the prevailing situation, or the
proposed draft received from the GOI, under which it is earned purely
because the generator is available.
7. Draft notification linked incentives to equity. This order preserves the
status quo of one paise per Kwh per each 1% increase in PLF above
target availability.
140
8. It increases the minimum performance criterion for the earning of an
incentive from 68.5% deemed PLF at present to 80% (85% after one
year) for all thermal stations, 85% for Hydro and 77% (82% after one
year) for NLC.
9. It introduces severe financial penalties for grid indiscipline along with
significant rewards for behaviour, which enforces grid discipline for
both generators as well as beneficiaries.
10. The order permits market pricing for the trading of surplus energy by
beneficiaries and generators.
11. The order urges the GOI to allocate the unallocated capacity a month
in advance so that beneficiaries know their exact share in capacity in
advance and can take steps to trade surplus power.
12. It will be implemented in stages from April 1, 2000 starting from the
South. The new norm for incentive will however be applicable from
this date for all central stations. In the case of NPC, GOI to decide
applicability of the order.
141
COMPARISON OF EXISTING TARIFF SYSTEM AND AVAILABILITY BASED TARIFF
Sl. No.
Description of Item
Existing System
Draft ABT Proposal
ABT Order
1. Capacity / Fixed Charge
Annual Fixed Charge (AFC) include : a) Interest on loan b)Depreciation c)O&M d)Return on Equity e) Income-Taxf) Interest on Working Capital
Fixed charges excluding ROE i.e. all other five items of the existing system. ROE treated separately
Capacity charge as per existing system
2. Basis of recovery
Recovered at 62.79% deemed PLF. 50% AFC at 0% PLF and full recovery at 68.49% deemed PLF.
FC excluding ROE recovered at 30% availability on pro-rata basis between 0% and 30% availability. ROE recovered on pro-rata availability between 30% and 70%
Pro-rata recovery of capacity charge for i) NTPC stations: Between 0 to 80% availability in the first year and 0 to 85% availability in the second year ii) NLC Stations Between 0 to 77% availability in the first year and 0 to 82% availability in the second year iii) NHPC Stations Between 0 to 85% availability in the first year and availability in the second year to be announced by the commission separately.
3. Incentives Above 68.49% deemed PLF, incentives at 1 paise/KWh for each 1% increase in
Incentive beyond target availability of 70% is as follows:
1 paise/KWh/each percentage increase in PLF of 80%/ 85% in the first/ second year for NLC and 85% in the first year for
142
PLF. 70% to 85% - 0.4% of equity for each 1% increase in availability beyond 85%.
NHPC.
4. Sharing of fixed cost
Based on actual energy drawls
Based on allocated capacity
Based on allocated capacity
5. Recovery of variable cost
Based on actual energy drawls
Based on Scheduled Energy
Based on Scheduled Energy
6. Deviations from schedule – UI charges
No penalties for such deviation
Varying between 0 to 360 paise/Kwh for the frequency range of 50.5 Hz to 49 Hz
Varying between 0 to 420 paise/Kwh for the frequency range of 50.5 Hz to 49 Hz
7. Norms for tariff determination
GOI Tariff notification
GOI Tariff notification
GOI Tariff notification till such time Commission finalises its views
8. Procedure for payment of capacity charge if ABT is introduced in the middle of a financial year
Not applicable Not specified
Specified
9. Prolonged Outages
Included in item (2) above
Provided for payment of adjusted capacity charges
Does not provide for payment of capacity charges
10. Marketing of surplus energy
Not applicable Not specified
Encouraged and will not require commission’s approval
143
11. Splitting up of capacity and energy charge for hydro stations.
Capacity charge covered depreciation and interest on loan. Energy covered ROE, income tax, O&M and interest on working capital.
Capacity charge covered depreciation and interest on loan. Energy covered ROE, income tax, O&M and interest on working capital.
Till such commission notifies peak and off-peak energy rates for hydro-stations, primary energy charge would be taken as 90% of the lowest variable charge of the thermal power station in the concerned region. The balance of total charges would be recovered as capacity charges.
12. Payment of dues to generators
As per agreements
As per agreements
As per orders of the commission
13. Applicability All central generating stations
All central generating stations staggered region wise
i) ABT implementation is staggered region wise ii) Fixed charge recovery and basis for incentive payments revised from 1st April, 2000. iii) GOI to decide about ABT for automatic power stations.
14. PLF for incentives during interim period
Not applicable Not specified
Till the introduction of ABT in other regions and after 1.4.2000, the actual PLF for incentive purposes for NTPC shall be 80% instead of deemed PLF of 68.49%. The PLF in the first year for incentive purposes for NHPC shall be 85%.
144
Open Access: Methods for Calculation of Cross-Subsidy Surcharge and
Assessment of the Financial Impacts on Utilities
Introduction
In order to promote competition in the electric power sector, the Electricity
Act 2003 (E. Act) mandates open access to the transmission and distribution
network for any supplier of electricity. With open access, upon approval by
the Electricity Regulatory Commission (ERC), competing suppliers will be
able to provide electricity to certain categories of consumers and thus bring
competition into generation and supply of electricity. A major complication in
the transition to competition is the loss of cross-subsidy revenues that were
being provided by the exiting consumer to fund the subsidized (below cost
provision of) supply to the majority of LT consumers.
The EAct has attempted to compensate the utilities by allowing State
Commissions to impose surcharges on those consumers leaving the licensee
and receiving power from competing suppliers. However, the wording of the
Act on these issues is not clear regarding the level of the surcharges and the
method of their calculation. For this reason, the EAct is subject to multiple
interpretations and there have been several suggestions for how these
surcharges are to be calculated.
Here we describe the recommendations made by various parties regarding the
method of calculation and level of the surcharges. Then we discuss our
concerns about these recommendations. Next, we assess the likely revenue
loss for licensees due to open access and the extent to which the various
recommended methods would compensate the utilities for the revenue loss.
145
We’ve discussed the conflicting requirements for making open access
economically attractive and protecting the financial health of utilities. We
conclude with suggestions on other factors that need to be considered to make
the transition to competition a little smoother.
Recommendations by Various Parties on Mechanisms to Calculate the
Cross- Subsidy Surcharge
Electricity Act 2003
The EAct allows open access before cross-subsidies are eliminated through
the payment of a surcharge but requires that the subsidies be progressively
reduced in a manner determined by the State Commission. Clarifying the
purpose of the surcharge, the Act states that the surcharge is to “meet the
requirements of current level of cross subsidy within the area of supply of the
distribution licensee.” While the Act is silent on the method to be used to
calculate the cross-subsidy surcharge, it clearly states that the State
Commission will determine the cross-subsidy surcharge and the manner in
which it will be progressively reduced. However, the EAct requires that the
State Commissions be guided by the National Electricity Policy, National
Electricity Plan, and Tariff Policy which are to be notified by the Ministry of
Power (MoP). Thus these policies will also have an influence on the
calculation of the cross-subsidy surcharge to be decided by the State
Commissions.
First Draft of Tariff policy paper by MoP
MoP prepared a Preliminary Discussion Paper on Tariff Policy with the
assistance of CRISIL, which mentions that, the “Commission would decide
the surcharge such that the loss of cross-subsidy is shared between the
consumer and the incumbent distribution licensee.” This statement is an
146
interpretation/ extension of the EAct, because the EAct does not mention any
sharing of the cross-subsidy but simply states “…such surcharge shall be
utilised to meet the requirements of current level of cross subsidy…”
Draft National Electricity Tariff Policy as recommended by the Task Force
The Report of the Task Force on Power Sector Investments and Reforms
dated February 2004 included a draft tariff policy in which it recommended
that the cross-subsidy surcharge for open access be computed based on the
Long Run Incremental Costs (LRIC).
In its recommendations, the Task Force said that the cross subsidy surcharge
should represent the difference between the actual tariffs and LRIC. The
Report went on to say that the appropriate Commission should conduct the
necessary studies to determine LRIC or have the studies carried out by the
licensees. It suggested that in the interim the costs of the most expensive
generating unit (based on both fixed and variable costs) be used as a proxy for
LRIC. In October 2004, the Ministry of Power (MoP) recommended to the
Planning Commission that it take note of these recommendations of the Task
Force while formulating policy on the cross-subsidy surcharge.
Other Recommendations
Sankar (2004) discusses two alternatives for determining the surcharge. He
looks at the cross-subsidy as either: (1) the HT tariff minus the average cost of
supply; or (2) the HT tariff minus the cost to serve the HT consumer class.
Using the example of AP, he estimates the cross-subsidy surcharge to be Rs
1.65 per kWh and Rs. 2.05 per kWh based on the two methods respectively.
He argues that simply using either of these approaches will result in a high
cross subsidy surcharge that would make open access meaningless and stall
reforms of the power sector. Mr. Sankar recommends that the National
147
Electricity Policy or the Tariff Policy should define the cross subsidy paid by
a consumer class as the difference between the tariff for that consumer class
and the average cost of supply. He further recommends that the surcharge be
only a fraction, say 50 percent, of the present level of cross-subsidy. He
considers it reasonable to fix the surcharge at a fraction of the cross-subsidy
because according to him the consumer opting for open access is taking a
greater risk than one that stays with the utility. Furthermore, he says that to
make open access meaningful, the cost of supply from open access including
the surcharge should be less than the grid tariff. As an alternative, Mr. Sankar
suggests that the marginal cost of power purchase be used as the cost to serve
in calculating the surcharge.
A Consultation Paper prepared by NCAER for CERC titled Introducing
Competition in Generation of Electricity, recommends that the surcharge be
subject to a ceiling determined by the following equation:
Max. Surcharge = Tariff for departing consumer – Marginal cost of supply
for the discom
“As an alternative formulation” the paper recommends that the surcharge not
be greater than 20 percent of the average price of power procured by the
DISTCOs in the preceding financial year. In most cases, the alternate
formulation would result in a much lower surcharge.
Concerns with Recommended Methods for Calculating the Cross-
Subsidy Surcharge
Issues with the Use of LRIC*
The Task Force Report does not give a reason for recommending that the
difference between the actual tariffs and LRIC (Long Run Incremental Cost)
148
be used for calculating the cross-subsidy surcharge. Clearly, the LRIC do not
represent the current cost to serve the existing customer, but could be seen as
a proxy for the costs that will be avoided by the utility.
Cross-subsidy revenues are equal to the difference between the revenue
generated by a customer and the cost to serve that customer. Cost to serve is
based on an allocation of total costs to different customer categories. In
contrast, LRIC are akin to marginal costs. By using LRIC as a proxy for cost
to serve, one is allocating the costs of new additions to a single consumer
category (HT consumers). But actually while calculating the cost to serve, the
cost of new additions is merged with existing costs so that the cost of capacity
additions are spread across all categories of consumers. Therefore, by using
LRIC as a proxy for cost to serve, one is overstating the cost to serve if LRIC
is greater than the average of the existing costs, and one is understating the
cost to serve if LRIC is less than the average existing costs. Usually LRIC is
higher than the existing costs so the cost to serve would be overstated
resulting in a smaller surcharge.
Furthermore, if HT load leaves the system much faster than the expected load
growth, then capacity additions will not be required for some time but instead
the utility may have to pay for existing fixed costs that cannot be avoided. In
that case, the avoided costs will be zero, and instead, there will be stranded
costs. Thus we see that for cases of rapid departure of HT load, the use of
LRIC (based on capacity additions) will significantly overstate the avoided
costs and understate the surcharge required*.
*- Long Run Incremental Cost
*- Another issue with the use of LRIC is that estimating LRIC can be difficult
because these are forward looking costs which are based on forecasts. There
can be great variations in the forecasts made by different parties and the
regulatory agency must decide whose forecast is the most reliable. This is
often not easy.
149
Issues with the Use of Marginal Unit Cost (MUC)
We have several concerns with the use of MUC to calculate the surcharge.
First, MUC do not represent avoidable costs. Generally, the fixed costs of the
marginal unit are not avoidable. If the licensee’s load is reduced because of
the departure of some customers, at best the licensee will avoid the highest
variable cost of either its own plants or the plants from which it purchases
power. In those cases where the marginal unit for a utility may be an
unplanned purchase from a surplus area or the unallocated portion of a
Central Generating Station (CGS), the utility may be able to avoid both the
fixed and variable costs of the contract.
The second reason why it is inappropriate to use MUC to calculate the
surcharge is that this assumes that for any utility, there is a single generating
unit that is on the margin at all times, and that is not so. The generating unit
on the margin changes with the time of day and season. During peak periods,
peaking units with very high variable costs are on the margin while during
off-peak periods, baseload units with very low variable costs may be on the
margin, etc.. Thus generally the most expensive unit would be the one that
operates only at the times of the system peak (and hence would have a low
PLF) and applying that cost to all the 8760 hours3 of the year would lead to a
gross overstatement of the avoidable costs.
The third problem with the use of MUC to calculate the surcharge is that the
highest cost unit is not applicable to the entire decrement of load. The use of a
single unit (the highest cost unit) to represent avoidable costs for all the load
that would go out due to open access is likely to be incorrect. As an example,
consider that 1000MW of industrial load is expected to leave the licensee and
get electricity from alternative suppliers. If the capacity of the highest cost
generating resource is only 200 MW, then clearly it would be incorrect to
150
assume that the costs per kWh of the 200 MW units would be applicable to
the entire 1000 MW load block. The avoidable costs for the remaining 800
MW would be lower. Therefore, the size of the decrement of load for
calculating the avoidable costs must match the expected decrement in load
due to open access. The avoidable cost would then be the weighted average of
the costs of the generating units that would no longer be required.
These concerns with the use of MUC to calculate the surcharge are best
illustrated by calculating the surcharge for different states by strictly
following the recommendations for the use of MUC. For AP and
Maharashtra, the total costs (fixed plus variable) of the marginal generating
unit per kWh are higher than the tariff for HT industrial consumers.
Therefore, if the recommendations for the use of MUC are strictly followed,
we get a negative cross-subsidy surcharge. The main reason for this
anomalous result is that the marginal unit operates for a very short time in the
year and it is incorrect to apply its costs to a load decrement that covers most
of the hours of the year.
Issues with the Use of the Average Cost of Supply
If the average cost of supply is used to calculate the surcharge, then the
resulting revenues will not completely compensate the licensee for the loss of
cross-subsidizing revenues. This can be seen from the following calculation:
Cross-subsidizing revenues provided by HT consumers = HT tariff - Cost to
Serve HT consumers
If the average cost of supply is used to calculate the surcharge, then
Surcharge using average cost of supply = HT tariff – Average Cost of Supply
151
Therefore, the revenue deficit due to the use of average cost of supply is given
by the following equation:
Cross-subsidizing revenue deficit = Average cost of supply – Costs to Serve
HT Consumers
How large would be this deficit due to the use of average cost of supply
instead of cost to serve? We consider the case of AP, where the HT tariff is
4.11 Rs/kWh; the average cost of supply is 2.82Rs/kWh, and the cost to serve
HT consumers is 2.61 Rs/kWh. Using the equations given above, we see that
the revenue deficit would be Rs 0.21 per kWh. The total HT sales for
Category I and II consumers for the year are projected to be 7297 MU, so if
half the HT load opts for open access, then the revenue deficit will be Rs. 77
crores per year. If, for calculating the surcharge, the average cost of supply is
reduced by 50% as suggested, then the loss will be Rs. 312 crores per year.
HT Energy Audit: The Crucial Starting Point for Curbing Revenue Loss
Introduction
For the last two decades, the financial crisis besetting the Indian power sector
has been an issue of great concern for the planners and experts. In 1990s, the
discussion on this crisis was focused on the large subsidies for agricultural
consumers and the rapid growth in agricultural power consumption. It is
worth noting that this preoccupation with agricultural tariff and subsidy
persisted in spite of efforts on the part of some researchers to point out
another crucial causative factor. These researchers had been pointing out that
excessive transmission and distribution (T&D) losses, hidden under the garb
of agricultural consumption, had been a major cause for the poor financial
health of utilities (Roy 1996, Reddy and Sumithra 1997, Dixit and Sant 1997).
However, most experts and leaders of the sector continued with their
152
preoccupation with the agricultural subsidy without serious investigation into
this crucial factor.
In the last few years, especially after establishment of the independent state
electricity regulatory commissions (SERCs), many state utilities are revising
their T&D loss estimates from the earlier lower figures of around 18-20% to
anything in the range of 35% to 50%. With this, it is now being widely
accepted that reduction in T&D losses to a reasonable level is essential for
restoring financial viability of the utilities*.
* A calculation for Maharashtra state utility indicates that financial loss due to
excessive T&D loss (defined as that above 25%) is about Rs 2,500 crores p.a.
And, this is more than the agricultural subsidy that is claimed to be\ Rs. 2,100
crores p.a.
However, the belated acceptance of excessive T&D losses has resulted in
considerable delay in action to reduce these losses, which is proving
extremely costly. Nonetheless, it is a welcome sign that the issue of T&D
losses is coming into limelight now and different approaches are being
suggested as prescriptions to address the issue.
This section highlights the large swings that have been occurring in the
estimation of T&D losses in various states as well as the prevailing
uncertainty in estimation of even transmission losses and HT-level losses.
Based on experiences from the states such as Haryana, Maharashtra and
Andhra Pradesh, the third section highlights unwillingness on the part of
utilities to carry out effective metering even at the HT level. The fourth
section points out that commercial loss even at the HT-level might be
significant in terms of revenue lost per customer as well as of the total
revenue loss. The fifth section discusses various advantages of focusing on
HT-level energy audit for increase in utilities revenue. The sixth section
argues that the approaches of “100% Metering” and “Total Energy Audit”
153
(including LT energy audit) though essential, would, at best, yield
significant benefits only in the long term. The last section presents the
conclusions of this analysis.
1. Swings in the Estimates of T& D Losses
The first step in the efforts for reducing excessive T&D losses is to properly
estimate T&D losses. The next and probably more important step in these
efforts is to identify various links or geographical areas in the network that
have excessive losses. It is possible that losses in some of these areas or links
could be easier to curb as compared to losses in other links/areas.
Identification of such links / areas makes it possible to focus initial efforts for
reduction in T & D losses on these areas or links. The next two sub-sections
demonstrate that, though SERCs and
Chart 5: T& D Loss determination between four states
Figure highlights changes in the estimated T&D losses in various states. The state utilities have attempted a more realistic estimation of T&D losses during the regulatory process. In states such as Maharashtra and Haryana, the upward revision of loss estimates has been much higher than the RC targeted loss reduction. The bar sequence for Karnataka has been changed as Karnataka utility did two substantial revisions in the loss estimate before the KERC—s first tariff order.
154
Utilities are making efforts to identify such links / areas of high losses; there
is still significant uncertainty and differences over the real level of total as
well as Transmission and HT losses.
2. T&D Loss Estimation
Analysis of regulatory orders by SERCs from different states indicate that,
even two to three years after establishment of the SERCs and the reforms
process, there is still ambiguity over the real level of T&D losses. Figure 1
shows changes in the estimate of T&D losses in the four states.
State after state has revised the figures for T&D losses upward in the last few
years. This has happened in some typical steps. First, as a prelude to the
setting up of the SERCs, the state utilities typically increased the loss
estimates from the historical low values to a more realistic level.
Subsequently, SERCs ordered reduction in T&D losses, usually by around by
5-7 percentages point. As against this target of lowering T&D losses the
utilities have come back to SERCs with further revised estimates of losses,
which are typically 5 to 10 percentage points more than their earlier estimates.
This resulted in SERCs (as in the case of Maharashtra & Haryana) approving
higher loss levels in subsequent orders. The Maharashtra ERC revised
approved loss levels from 27% to 36%, whereas the Haryana ERC revised
approved loss levels from 25% to 41%*.
*Though the MERC order does not explicitly state the approved loss level, it
is back calculated based on the loss level projected by MSEB and additional
revenue from commercial loss reduction as directed by MERC.
For explaining these upward changes in the T&D loss estimates, the utilities
cite some typical reasons such as (a) increased (and hence ’better—) sample
of agricultural consumers used for estimation of their average hours of
consumption and (b) changes in assumed usage level (i.e. load factor) of the
155
un-metered domestic or commercial consumers. Additionally, the utilities
have argued that it is impossible to reduce T&D losses to the levels envisaged
and desired by the SERCs in a period of four to five years. The state utility in
Delhi (viz., Delhi Vidyut Board) has produced evidence of international
experience in support of this argument. Some utilities have also argued that,
in order to achieve the significant reduction in T&D losses, they will have to
police the entire state to curb the rampart power theft. Unfortunately, none of
the utilities in the country, whether private or public, has been able to reduce
the T&D losses to the level mandated by the SERCs.
3. Estimation of Transmission and HT Losses
Measurement or even estimation of T&D loss in the LT (low voltage /
tension) system is a difficult task, as the LT network connects millions of
small consumers spread across the country and even into remote and
inaccessible areas. However, unlike the LT system, the transmission or high-
tension (HT, i.e., 11 kV and above) network connects only to a few thousand
large consumers. Hence, it is much easier to monitor the HT network. Due to
the large volume of electricity flows in the HT network, monitoring and
protection systems are already in place in the HT network. For example, at
least by design, HT sub-stations are provided with proper metering system to
measure feeder-wise incoming and outgoing energy flows.
As a result, one would expect that making correct measurement (or at least
estimation) of losses in the HT system would be easier and less prone to large
swings.
Unfortunately, most Indian utilities fall short even on this count. Let us
review the situation in this regard in the three- considered to be relatively
better managed- states of Maharashtra, Karnataka and Andhra Pradesh.
156
Maharashtra
In its tariff proposal presented before the SERC in March 2000, Maharashtra
State Electricity Board (or MSEB) claimed that losses in its Extra HT (EHT)
network for the three previous years had been in the range of 3.8 % to 4.2%
(MSEB 2000). These estimates were based on the ’load-flow studies—
carried out by MSEB. As against this, MSEB, in its tariff proposal submitted
in August 2001, claimed that average EHT losses for the preceding six
months were 6.7% (starting with 8.4% and coming down to 4.8% in the last
month). This implied an upward revision by 2.7 %! (MSEB 2001). This
recent estimate seems to be based on the meter readings, but MSEB has not
provided estimate of technical losses (i.e., results of load-flow study) for this
period.
Karnataka
Karnataka Power Transmission Corporation Limited (KPTCL), the Karnataka
utility, had estimated transmission losses for the three consecutive years
(1999 to 2001) as 15.6%, 16.47% and 15.17%. Against this, the Karnataka
Electricity Regulatory Commission (KERC) pointed out that the studies
conducted by two consultants (viz. PRDC, Bangalore and MECON),
indicated transmission losses (up to 33 kV) to be around 10% (KERC 2000).
The estimates by the consultants were based on load-flow studies and on
meter readings, wherever available. Thus, here again, there is a large
difference of over 5 percent points in the estimation of just the transmission
losses.
Andhra Pradesh
The case of Andhra Pradesh (AP) is more revealing. In the first tariff proposal
before the Andhra Pradesh Electricity Regulatory Commission (APERC), the
state utility had claimed the transmission losses to be 4.6%. But, in the second
157
tariff proposal, the utility claimed transmission (up to 132 kV level) loss level
to be 8.7%! The utility explained this upward revision in transmission losses
by saying that the earlier estimates had been based on load-flow studies,
whereas the revised losses were based on actual meter readings. As per the
utility—s claim, metered data in the period of the four months showed actual
transmission losses at the level of 9.6%, and after making certain adjustments
for ”metering accuracy and meter reading cycle time‘ etc. the utility estimated
the annual loss level to be at 8.7%. During the process of the review of the
‘Revenue Requirement’ APERC asked the utility to carry out a load-flow
study. Surprisingly, the utility was prompt in carrying out the load-flow study
and came out with an estimate of technical transmission losses to be 8.7%!
(APERC 2001). It is not a surprise, however, that there are serious lacunae in
the calculations in the load-flow study submitted by the utility.
To summarize, the above discussion indicates that even after a few years of
regulatory process, accurate estimation of ETH or HT losses is proving to be a
difficult task. To overcome this shortcoming, several SERCs have initiated
detailed technical studies with the help of external consultants to clearly
establish the technical losses at transmission / HT level. As discussed later,
estimation of technical losses at the HT level (through load-flow studies)
coupled with calculation of actual losses on the basis of energy audit would
lead to identification of commercial losses.
3. Unwillingness of Utilities for Effective HT Metering
Realizing the importance of proper energy audit for accurate estimation of
T&D losses and reduction in the same, several SERCs have directed the
utilities to undertake ”Total Energy Audit‘ and “100% Metering”. But, the
emerging evidence clearly demonstrate that the utilities are unable, rather
unwilling, to undertake “Energy Audit‘or”100% Metering’ even at the HT
level.
158
Maharashtra
Maharashtra Electricity Regulatory Commission (or MERC), in its first tariff
order dated 5th May 2000, directed MSEB to install the ’Time-of-Day— (or
TOD) meters for all industrial HT consumers by September 2000 and for all
the remaining HT consumers by December 2000. It also directed MSEB to
furnish quarterly reports giving the number of these meters and data obtained
from the same. But, even six months after the target date, MSEB was able to
provide TOD meters only to half of the approximately 10,000 HT consumers.
MSEB—s performance has been equally awful in dealing with the task of
energy audit of its express feeders. Since 1994-95, MSEB has been claiming
that it is carrying out regular energy audit of selected urban areas as well as of
the Express Feeders (GoM, 1996). MSEB reiterated this claim in its tariff
proposal submitted in March 2000. It repeated this claim again in the proposal
submitted in August 2001.
However, this time, MSEB could actually make available the data compiled
from energy meters installed on about 220 ‘Express Feeders’ for the period of
six months. Out of the total 1320 data points (i.e., 6 months multiplied by 220
feeders), nearly 45% of these data points indicate loss figures that are either
less than -0.5% or greater than +5%! (Prayas 2001). This is striking because,
usually, the technical losses on such type of feeders should lie in the range of
1% to 2%. This implies that about half of the data points are indicating either
ineffective metering, commercial losses, or excessive technical losses. This is
a clear indication of MSEB—s failure to carry out effective metering even for
these 220 ’Express Feeders—. It is worthwhile to note that the energy
supplied through these 220 ‘Express Feeders’ account for nearly 20% of
MSEB’s yearly revenue (considering average HT industrial tariff of Rs
4.2/unit).
159
Andhra Pradesh
The case of AP is more serious. In its tariff order dated 27 May 2000, APERC
directed the utility to install high-accuracy (i.e., the 0.2% accuracy class)
meters at all interface points (where the ownership of power changes from
one utility to other, i.e., from either generation to TRANSCO or from
TRANSCO to DISCO) and file a compliance report within one month, i.e., by
June 2000. Ten months later, in the subsequent tariff order dated 24th March
2001, APERC mentioned that the utility could implement this directive only
for 3% of the total interface points. Moreover, this order also reported that the
utility is demanding another full year to implement the directive! There is no
other way to term this delay as ridiculous, when one realizes that, in order to
comply with this directive, the utility had to install, in all, only 460 meters.
Haryana
The status of HT-level metering seems even more serious in the case of
Haryana. Haryana Electricity Regulatory Commission (HERC), in its tariff
order dated 26th November 1999, categorically mentioned that all interface
metering (where the ownership of power changes) should be completed latest
by 31st March 2000, i.e., within the period of four months. It went to the
extent of mentioning that “All metering would be completed by 31 March
2000 for all purposes including transmission and bulk supply tariff
application by the licensee. The Commission would not like to be presented
again with the plea of nonmetering for any purposes whatsoever after 31
March 2000” (emphasis original).
The utility failed to comply with this directive but went ahead and filed
another tariff revision application. In its subsequent tariff order in December
2000, HERC said, The Commission reiterates that this work should be given
high priority and no slippages beyond the targeted completion date of July
2001 will be allowed“(emphasis original) (p. 56, para 5.1.2.2). One would
expect that the utility would have followed this simple directive at least by the
160
extended target date. But the scene repeated after few months. The subsequent
tariff order by HERC dated 6th August 2001 (Annex 3) also mentioned that,
till the date, the utility had failed to introduce interface meters as directed and
has, in fact, requested waiver of this directive! In the case of Haryana, the
total number of meters to be installed under this directive was about 300. This
failure of utility forced the SERC to estimate transmission losses on the basis
of data from other agencies such as regional electricity board and power grid.
To summarize, it is serious that utilities are taking SERCs for granted by not
implementing even such simple but crucial directives. Moreover, it goes
without saying, that the suggested prescription of T&D loss reduction through
‘100% Metering’ approach would be a non-starter if the utilities are unwilling
and / or unable to carry out metering and data-gathering tasks even at the
small number of locations, despite the full-knowledge of the high-stakes
involved in the energy flowing through these points.
4. Indication of Significant Commercial Losses at HT Level
The inability, rather unwillingness, of the utilities to install proper metering
even at the HT-level raises strong suspicion that all may not be well at the HT
level. Further analyses indicate possibilities of substantial commercial losses
even at the HT level.
Andhra Pradesh
As mentioned earlier, the transmission losses in AP as per the metered data
(for a period of four months) were 9.6% (APERC 2001). The utility applied
some corrections and arrived at the estimate of the annual losses of 8.7%
based on the meter data. The utility justified this loss-level as the technical
losses using a load-flow study. This study found the peak power losses to be
9.66%. The utility then used an assumed figure of 90% for the ’Load Factor—
and multiplied the peak power losses with the assumed Load Factor to arrive
161
at the estimate of technical losses as 8.7%. This calculation for technical
losses is flawed because the ’Load Factor— (i.e., average load divided by
peak load) for the utility was about 70% and not 90%. Using correct load
factor indicates technical losses of 6.7% i.e. around 2% less than losses
indicated by metered data. The APERC has recently engaged the CPRI
(Central Power Research Institute) for estimation of technical transmission
losses.
Maharashtra
In case of MSEB, indication of the possibility of substantial commercial loss
at the HT level emerges from the analysis of the energy audit data of the
Express Feeders supplied by MSEB, which is mentioned earlier. Out of the
220 Express Feeders, nearly 40% of the feeders show consistently
problematic readings. These include either no reading or the reading showing
losses outside the range of (- 0.5%) to (+5 %) for four or more months out of
the six-month period! (Prayas 2001). Such a large number of
consistently problematic readings on a very small number of high-stake
feeders also points to the possibility of substantial leakage at the HT level.
Madhya Pradesh
The tariff proposal put up by Madhya Pradesh Electricity Board (for FY
2001-02) before the SERC clearly mentions that, as per the study carried out
by M/s Descon Consultants, commercial losses attributed to the HT industries
is estimated at 5.4% (of energy available for sale at the bus-bar).
Unfortunately, no details about the methodology or sampling used in this
study were available. Table 1 below is reproduced from the MPEB tariff
application.
162
Table 16: Estimated Break-up of T& D losses in M.P
Energy Input (MU) 27,000
T&D Losses (as the percentage of Generation) 43.2%
Technical Losses 15.3%
Total Commercial Losses 27.9%
HT Industry 5.4%
LT Industry 6.5%
Household 13.0%
LT Commercial
3.0%
Total Commercial Losses
27.9%
Source: Consultants study as quoted in MPEB Tariff Application (2001 – 02)(MPEB – 2001)
To summarize, the recent data coming out in the regulatory process
demonstrate that it would not be improper to conclude that in most utilities,
revenue loss due to commercial losses at the HT level would be significant.
5. HT Energy Audit: Key Staring Requirement
The above two sections clearly demonstrate that: (i) the state utilities are
unwilling to establish proper metering even at the HT level, and (ii) there is a
strong evidence to indicate that all losses at HT-level may not be technical
and may include substantial commercial losses. This needs to be viewed in
combination with the facts that in most states, (i) HT consumption is in the
range of 20% - 30% of total sales, and (ii) HT sales account for nearly 50% -
60% of the total revenue. If we take into consideration all these facts it is clear
that even a small commercial loss in the HT-section has significant impact on
163
revenue of the utilities. With the HT tariff being twice that of the LT tariff and
the number of HT consumers being less than 0.1% of the LT consumers; it is
obvious that the first point of attack has to be the HT sector. As such, the first
priority in the efforts towards T&D loss reduction should be to establish an
effective metering and audit regime at the HT level to curb revenue loss at
this level.
Efforts of reducing commercial losses at the HT level can take different
forms; starting from proper vigilance and inspection by utility staff (and /or
outside agency) to instituting a rigorous energy audit to identify losses in
various feeders. But, depending simply on administrative measures such as
vigilance squads has proved to be ineffective in the current utility setup. More
direct measures, which could hold utility and its staff accountable, need to be
adopted. Rigorous energy audit is one such measure. Such an audit should
aim at establishing the energy balance right from the points of generation /
power purchase to points where energy is transformed to LT level. In
addition, the audit system should be capable of
(i) detecting malpractices on a routine and consistent basis;
(ii) being implemented in a time bound manner; and
(iii) evolving concrete and indisputable performance indicators
for the utility staff
The energy balance can be depicted in the equation form as follows:
Energy Loss (HT level) =Energy generated (net) (A) + Energy Purchased (B)
- Energy Consumed by HT consumers (C) - Energy transformed to LT (i.e.
440 V) (D)
In the above equation, A and B are metered points and these data are readily
available with all utilities. Part D, i.e., energy transformed to LT side is
difficult to measure and may involve sizable investment as well as number of
metering points. For example, in the case of Maharashtra, accurate
164
measurement of Part D would imply metering of 180,000 distribution
transformers (DT) on LT side. This implies an investment of around Rs 150
crore (about 1.5% of utility revenue) for metering. In addition to HT energy
audit, this approach will allow us to zoom onto the DT level losses and,
hence, would be far effective in localizing high theft points. But its
implementation - in terms of installation of meters, proper maintenance,
reading, and data analysis in a routine and consistent manner - could take
substantial time. Hence, as an intermediate option, some approximations
could be considered. These are discussed below.
The first such approximation could be to restrict the audit only up to 33 kV
level (i.e., instead of measuring energy transformed to 440 V, energy
transformed to 11 kV or 22 kV should be considered). Since energy fed into
all the 11 / 22 kV feeders is now measured or expected to be measured soon
(as per the MoP’s August 2001 report), calculating such an energy balance up
to 33 kV is simple. It only involves maintenance and reading of all meters on
the 11 / 22 kV feeders (in the substations). In state such as Maharashtra, this
reduces the meter reading points to around 5,500 outgoing feeders and
existing meters of HT consumer. But this would cover over 20% of the total
energy fed into the system and 25-30% of revenue. The 11/22 kV express
feeders, i.e., feeders supplying to only HT consumers, could be readily
brought into this audit, expanding the coverage a little more. In the
subsequent phase, efforts could be made to include all 11 kV or 22 kV feeders
supplying to at least one HT consumer. Tackling these mixed feeders, i.e.,
feeders supplying to HT consumers as well as having DTs (i.e. 11/22 kV to
440 V) could be somewhat tricky. Depending on the configuration of each
such feeder, different options will have to be adopted. Some possible options
would include supplying HT consumers through a separate feeder (as was
being attempted in some states as part of the system improvement program) or
installing check meters for a group of HT consumers. Installing meters on LT
side of DTs could be considered, where the number of DTs on the feeder is
165
less. As a last resort, one could install a check meter for each HT consumer on
such mixed feeders. Investment required for such additional metering need
not be a deterrent for its implementation. For example, Maharashtra has
around 10,000 HT consumers, which give revenue of around Rs. 6,000 crores
p.a. Assuming additional metering at all of these 10,000 points (check meters
for each consumer) at a cost of Rs. 50,000 per metering point, the one time
investment would be Rs. 50 crores. This ONE TIME investment would be
less than 0.5% of the utility’s yearly revenue (or 1% of HT revenue). Such
check meters can help identify the problematic consumers / areas, where
difference in check meter and consumer meter readings falls outside the range
+/- 1% or either of the meter reading is unavailable. This can also become a
concrete performance indicator for the staff.
Depending on the state of the HT metering and capabilities of the utility, the
manner and the speed of the action-plan may vary. However, there is no
barrier to achieving the minimum target of ‘Energy Audit’ up to the 33 kV in
a short time of say, one year. This audit should give an energy balance right
from the generation (or power purchase) points up to the HT consumers.
Difference in such audited loss figures and the estimated technical losses
(based on the load-flow study) could be a concrete indicator of commercial
losses.
Such an approach involving tight and complete energy audit at the HT level is
desirable for several reasons discussed below.
Relative Ease of Implementation
As discussed above, effective energy audit at the HT-level requires
installation and reading of only a few thousand meters, unlike the audit of LT
system.
166
Low Investment and High Returns
Since HT tariff is significantly higher than LT tariff, reduction in HT
commercial losses would be much more valuable. Such high returns coupled
with the relatively low-levels of investment and managerial inputs required to
institute HT-level energy audit (compared to the LT energy audit or 100%
metering approach), imply quicker and higher benefits. This is essential
considering the current precarious financial situation of utilities. A ’back-of-
the-envelope— calculation for MSEB indicates that HT energy audit can pay
back the investment (of around Rs. 50 Cr.) in just half a year, if theft of only
238 MU (= 0.5% of bus bar energy or about 2% of the HT consumption) is
curbed.
“A No-Regrets” Strategy
Effective metering at the HT level is also essential for implementing ‘Total
Energy Audit’ and theft (identification and) reduction through “100%
Metering approach”. This is because at times meters indicating input energy
to a division / zone are malfunctioning or readings are misreported, resulting
in higher transmission /HT losses and lower losses at division / zone level. To
address this issue it is essential to have equal emphasis on correct
measurement of transmission and HT losses and reduction in the same. Such
HT energy audit is also essential for reforms involving unbundling of utilities
or even for implementing concepts such as profit centers in existing SEBs.
Further, if utility is unable to effectively carry out even the HT energy audit –
which requires much less managerial and administrative efforts (compared to
‘Total Energy Audit’ and ‘100% Metering’ approaches) - then the very
expectation of T&D loss reduction to a reasonable level will need serious
rethinking.
167
6. The “100% Metering” Approach: A Long- term Solution
The approaches of “100% Metering” and “Total Energy Audit” are essential
for achieving several objectives such as:
a. tariff regime based on the principle of “pay as per-use”
b. better targeting of subsidy,
c. identification of some of the 11/ 22 kV mixed feeders that have
excessive technical or commercial loss, and, finally
d. establishing accountability up to the level of linesmen of the
utility.
Hence, it is inescapable to carry out the “Total Energy Audit” as well as
‘100% Metering’.
But, it needs to be considered that this requires not only large investments but
also immense efforts involved in installation and regular reading of millions
of meters (in each state) as well as in billing equally large number of
consumers. In the case of millions of “single bulb houses” innovative
approaches such as load limiters and efficient bulbs would be far more
prudent than blanket metering in the medium term.
The second consideration in making effective use of “100% Metering” relates
to the billing systems of SEBs. Many utilities are yet to install the system of
computerized billing and systematic numbering of each consumer (linking the
consumer to a pole / DT or a feeder). Further, well-designed software to
capture and analyse these data will have to be put in place and used by a large
number of sub division level staff!
Another aspect relates to integrity of the audit. Unless the billed energy is
traced back to the supplied energy up to the point at which energy is fed into
the system, the utility of the whole exercise could be greatly reduced. The
168
whole exercise can be rendered ineffective by tampering (or making
dysfunctional or not reading) just a few key meters.
These will certainly act as major hurdles in implementing and effective use of
“100% Metering” towards the goal of complete LT level energy audit.
Before we commit to ‘100% Metering’ as the sole answer, it is worth doing a
reality check. Metering and billing performance of utilities is not very
encouraging even in the case of categories of customers that already fall in the
‘100% metered’ bracket (e.g., domestic, commercial, and industrial). In
Orissa, most of the LT consumption is not metered. In UP, consumption of
44% of metered consumers (that include domestic, commercial, and even
small industrial consumers) is “assessed” and not measured. During the first
tariff hearing of MSEB, it was revealed that about half of the bills issued to
residential and commercial consumers were not based of metered
consumption despite these consumers had been metered since the time of
connection.
Considering these factors, despite large investment and immense efforts,
approaches of ‘100% Metering’ and “Total Energy Audit” are unlikely to
yield significant results in most states within a time frame of three to five
years. Hence, we cannot ignore the HT audit and it has to be treated as the
starting point for proper identification of high loss area, for curbing theft and
more importantly the revenue loss.
Conclusion
The emphasis by SERCs and the Ministry of Power on reduction of excessive
T&D losses is a welcome development. Considering that many power utilities
are almost bankrupt, it is essential to give higher priority to measures that can
lead to increased revenue within a short time with limited investments, and
169
with limited managerial efforts. This understanding coupled with the recent
evidence of poor HT-level metering and possibilities of significant
commercial losses at the HT level, necessitates that the approach of stringent
HT-level energy audit be made the foremost priority. This crucial as well as
urgent measure should not be put on the backburner in our zeal to ensure
“100% Metering” and “Total Energy Audit” at the LT level.
Many SERCs have directed utilities to undertake HT energy audit in
successive tariff orders. Considering the importance and relative ease of HT-
level energy audit, the SERCs need to be far stricter in dealing with the
failures of utilities in complying with their directives in this regard. This is
essential for maintaining the sanctity of the directives by SERCs. For
example, the SERCs should direct utilities to institute effective HT-level
energy audit within a reasonable period and should reject any tariff proposal
after that period, if it is not accompanied by proper results of the HT-level
energy audit. Unless the SERCs adopt such unyielding stand on
implementation of such crucial, urgent, and relatively ‘easy-to-implement’
measures, the entire regulatory process would soon be rendered ineffective.
On the other hand, such unyielding stand on the part of SERCs would also
create pressure on the utility’s top brass to make those responsible for HT
energy audit more accountable. SERCs should also direct utilities to publish
results of such energy audit (along with names of concerned officers) through
newspapers as well as on the Internet so as to facilitate public scrutiny of
utility’s performance.
In order to facilitate HT energy audit and to overcome the financial
difficulties associated with procurement of meters, the SERCs may choose to
charge a special component in tariff, which should be devoted exclusively to
meeting expenses relating to the HT-level energy audit. Consumers should be
willing to share this small additional burden (of the order of 1 or 2 paise per
unit) to ensure that utility is made accountable. Such an approach would also
170
help in ensuring more stringent public scrutiny of performance of utilities on
this account.
Simply carrying out stringent HT level energy audit and curbing HT theft
would, by no means, be sufficient to make utilities financially viable.
Reduction of high technical losses, LT level theft, and other efficiency
improvement measures are also essential. But curbing HT theft with iron hand
would, on one hand, give the utilities much needed cash and, on the other
hand, would give a clear signal to corrupt utility staff and consumers that the
party is over. Such a signal is also critical for the success of measures such as
“Total Energy Audit” and “100% metering”.
171
Reforms and Restructuring Initiatives in Orissa’s Power Sector In 1994, the government of Orissa initiated power sector reforms and its
restructuring. The reform programme resulted in the vertical unbundling of
the state owned integrated utility, corporatisation of resultant entities and
constitution of an autonomous regulatory commission for power sector
regulation in the state. One of the key features of the reform programme
was the privatization of distribution activity. To make the process successful
and obtain more revenues, there was need for the distribution entities to
change the existing culture and approach to management. The state
government undertook a process of organizational strengthening to develop
appropriate organizational structure, systems and business process suitable
to the new environment.
Encouraged by the Government of India, assisted by the World Bank, and
supported with grants from the Government of U.K (DFID), Orissa took the
initiatives and earned the reputation of being the first state to reform its
electricity industry. The Orissa Electricity Reform Act, setting out the basic
framework of the reform, enacted in 1995 came in to force from 1 April 1996.
The principal objectives of the reform, as set out in the preamble to the Act
and the policy papers of the Government of Orissa, were the following:
a. Restructuring of the electricity industry for rationalization of
generation, transmission, distribution and supply of electricity.
b. Development of the industry in an efficient, economic and competitive
manner.
c. To provide for avenues for participation in the industry of private
entrepreneurs, attract private investment and reduce the need for
government funding of the electricity sector.
172
d. To improve the quality of the service to the consumer.
e. To enhance operational efficiency and reduce losses.
f. To provide for a transport mechanism for development and regulation
of the industry, including tariff fixation and dispute settlement, through
an independent statutory body, the Orissa Electricity Regulatory
Commission (OERC).
g. To contribute to the economic growth of the state by ensuring superior
electricity supply, and
h. To create opportunities for increasingly rewarding employment for
technical personnel and provide a stable environment for career
development in the electricity sector.
Conceptualization of the reform and road map for its implementation had
been drawn up after elaborate exercise in association with the World Bank
and with active involvement of a large number of consultants including
several foreign consulting firms of high international repute.
FIRST PHASE OF REFORM:
All the major steps in the restructuring process have since been taken as
envisaged under the reform scheme:
• OSEB was restructured and corporatised in to Grid Corporation of
Orissa (GRIDCO) and Orissa Hydro Power Corporation (OHPC) in
April 1996.
• The Orissa Electricity Regulatory Commission (OERC) was
established in August 1996.
173
• Orissa Power Generation Corporation (OPGC) was privatized with
divestment of 49% stake and transfer of management control to a
private operator, AES in January 1999.
• Four distribution companies (DISTCOs), incorporated as wholly
owned subsidiaries of GRIDCO, were privatized with transfer of 51%
stake to private operators: three of these, namely, NESCO, WESCO
and SOUTHCO were acquired by BSES in April 1999 and the fourth,
viz. CESCO by AES in September 1999.
In brief we can summarize that power sector reform comprised of
Restructuring OSEB, Privatization, Competition, Regulation and above all
reforms in tariff structure.
Since the existing legal provisions were not adequate to provide necessary
managerial and financial autonomy to the power sector, it was necessary to
draft the Orissa Electricity Reform Bill, 1995 with provision to establish an
independent and transparent regulatory commission and thereby attract
private investment in to the state power sector. The assets and personnel were
also transferred to the newly created entities such as the GRIDCO and OHPC
with effect from the first of April 1996 on provisional basis. The transfer
became absolute with effect from 1st April 1997.
GRIDCO disinvested 51% of its equity holding to private investors with
strong financial standing and technical capabilities. 10% of the equity has
been reserved for the employees of GRIDCO- which would entitle them to
direct monetary and welfare benefits. GRIDCO retains 39% of the holdings in
the DISTCOs.
174
Chart 6: Relationship between different party
Background of OSEB Established in 1961, OSEB was the main body responsible for power sector
development in the state. OSEB was vested with the responsibility of public
power supply in the entire state as well as for related state level regulation.
OSEB obtained the required power for distribution either from its own
generating stations or by purchasing from other generating utilities. By using
its transmission and distribution network, it applied power to the end
consumers.
OSEB was owned by the Government of Orissa and was governed by the
provisions of The Electricity (Supply) Act. 1948. The 1948 Act explicitly
required the SEBs to operate and adjust their tariffs to achieve a minimum
return after interest of 3 percent on net fixed assets in operation. According to
the provisions of Electricity (Supply) Act, 1948, state governments were
required to provide subsidies to help the SEBs meet their minimum return
requirements by compensating for the low tariffs charged for residential and
agricultural consumers.
175
Performance of OSEB
The performance of OSEB in terms of Plant Load Factor (PLF) and
Transmission & Distribution losses had been quite poor vis a vis other SEBs
during the period 1991-94. During this period, Orissa also had a considerable
power deficit which was estimated to be in excess of 10 percent, higher than
the all-India average of 8 percent.
The Transmission and Distribution losses though stated to be around 24
percent by OSEB were reported to be much higher. A clear indication of large
transmission and distribution losses was made in the Annual Administration
Report of the GRIDCO which listed such losses as high as 49.47%.
In 1993-94, the ratio of customers served to the employees of OSEB was 29,
whereas the all India average was around 80 (Comparison of performance of
Electricity Boards and Electricity payments, Planning Commission,
Government of India, 1994). The billing and collection of OSEB had been
poor because a large portion of the billing was not done on the basis metre
reading but on average consumption or on load factors, which resulted in
lower collection revenues. Figures available for 1996-97 indicated that only
12.19% of the total bills were based on metre reading.
Lack of appropriate controls and poor accounting of sales revenues had
affected the revenue collection. Figures available for 1998 indicated that in
some of the revenue divisions, the percentage of billings collected was as low
as 17%. Unmetered supply to a large number of consumers and theft of power
resulted in non-technical losses being as high as 20-25 per cent. (There are two types of power losses during transmission and distribution: technical and non-
technical losses. Technical loss is the energy lost in the wires and equipment in a distribution
system for technical reasons like resistance. Non-technical loss or commercial loss occurs due to
theft, non-metering or defective / tampered metering of consumers, and inefficient billing and
revenue collection systems)
176
In spite of an annual average growth of about 19% in sales revenue, OSEB
had not been able to earn the statutory rate of return of 3 percent on net fixed
assets without subsidy from the Government of Orissa because of its very low
level of tariffs. In spite of the sales revenue not being able to meet the
operating costs, there was no tariff increase from 1990 to 1992.
Table 17: Achievement of OSEB during 35 years Sl. No.
Area of Achievement
1961-62
1974-75 1984-85
1994-95 1995-96 1999-2000
1. Installed Capacity(MW)
9.897 547.675 1134 1731.93 1731.93 2498.88
2. Transmission & Distribution Lines(KM)
2839.67
33945.21
83414 116715 118286 120625
3. Total Energy Input(MU)
641.43 2335.07 4348 7851 9244.93 11130
4. Energy Sold (MU)
556.44 1995.12 3566 6471.14 4560.36 6286.49
5. % Loss of Energy Sold
13.2 14.5 17.9 17.6 50.4 43.52
6. Energy Billed(MU)
- - - 4536.33 4560.36 6286.49
7. % Loss to Energy Billed
- - - 42.22 50.4 43.52
8. Revenue Earned (Cr.)
2.23 23.31 116.09 725.11 912.14 1547
9. Consumers Served (no.s)
31013 234977 716706
1230354
1273844
1600551
10. Villages Electrified(No.s)
118 11525 23762 33131 32088 35190
11. Assets in Use(Cr.)
4.91 133 498.3 1073.14 1022.85 -
12. Employees (No.s)
4737 18224 33000 34450 34732 28309
13. Per capita Consumption (Kwh/Yr.)
31.8 73.3 137 248 292.5 352
177
Orissa Achievement in Distribution Sector Second Phase of Reform Privatization of Distribution Functions:
In pursuant to the Orissa Electricity Reform (Transfer of Assets, liabilities,
proceedings & personnel of GRIDCO to distribution companies) Rules, 1998,
the government of Orissa transferred the distribution assets and properties
along with personnel of GRIDCO to 4 distribution companies namely
CESCO, NESCO, WESCO, and SOUTHCO continued to function as
affiliates of GRIDCO up to 31.03.1999 and thereafter functioned under the
distribution and retail supply license obtained from OERC.
Objectives of Privatization of Distribution Function:
A. Operational Improvements :
(i) Improve quality of service to consumers
(ii) Improve operational efficiencies and reduce losses.
B. Financial Benefits :
(i) Attract private investment to the distribution business
(ii) Reduce the need for government funding of the electricity
sector
(iii) Contribute to increased economic growth in Orissa.
C. Employee Considerations :
(i) Create opportunities for secure and increasingly rewarding
employment for the qualified personnel
(ii) Provide a stable environment for employees
D. Sale of all 4 Zones to promote competition
178
In keeping with the objectives of power sector reform and the commitments
given to the World Bank by the state government, the distribution function
was required to be privatized. After considerations of various options
available for privatization, the corporation decided to adopt the best mode of
Joint sector/ Joint venture route. The sequence agreed was that the four
distribution zones which were functioning under the corporation will be
converted into four distribution companies as its wholly owned subsidiary.
The privatization process was accomplished in three stages e.g. Qualification
of companies/consortia, RFP and Lodgement of bids and negotiation and
completion. 51 companies/consortia initially participated in the ICB but 13 of
them furnishing SOQs. 11 companies were pre-qualified by GRIDCO board,
out of which 4 companies did not participate in the bidding process because
of reasons e.g. Asian Economic Crisis, Pokhran-II blast and unviable and
small businesses and regulatory risks. 4 more companies did not participate in
the bidding process. Out of the remaining bidders, the following 03 bidders
were found to be technically qualified like BSES, Singaporepower-Grasim
and TEC-Viridian. BSES was selected for WESCO, NESCO and SOUTHCO
and the management was handed over with effect from 01.04.99. As TEC-
Viridian failed to honour their offer, the earnest money guarantee of Rupees 5
crores was invoked. Dispute raised by TEC-Viridian is pending in arbitration.
AES-Jyoti structure, the pre-qualified bidder was selected for CESCO through
a process of negotiation and the management was handed over with effect
from 01.09.99. Thus through a process of international competitive bidding,
GRIDCO offered 51% stake to private sector investors keeping a share
holding of 39% with it and 10% share for Employees Welfare Trust.
It may be mentioned here that no asset sale has taken place. Assets have been
assigned to respective companies. Only the business has been sold with a
179
premium although all the 4(Four) companies are loss making and bore a part
of the loans and liabilities.
The new structure of the electricity sector in Orissa is as follows:
1. There are independent generation sources like NTPC, OHPC, OPGC,
IPPs and CPPs.
2. GRIDCO purchases power under PPAs from the independent
generators and provides bulk supplies to privatized distribution
companies at a bulk supply price. This means GRIDCO acts as a
Transmission Company between the generators and the distribution
companies.
3. Privatized Distribution Companies have come into existence viz.
WESCO, NESCO, SOUTHCO and CESCO. These privatized
distribution companies cater to the needs of customers.
RESTRUCTURING OF GRIDCO
GRIDCO presently undertakes –
1. The Transmission and Bulk supply activities in the state of Orissa.
2. Sale of energy outside the state of Orissa.
3. The SLD (State Load Despatch) Functions.
Under the provisions of the Electricity Act, 2003, trading in electricity has
been recognised as a distinct activity which can only be undertaken with a
license to be granted by the appropriate commission. Trading has been
defined under the new act as purchase of electricity for resale thereof and,
therefore, the bulk supply of the electricity becomes a licensed activity being
180
covered under trading. Transmission of electricity has also been recognised as
an independent activity to be carried on under a license from the appropriate
commission.
GRIDCO in addition to its transmission functions as a State transmission
Utility is also operating as SLDC (State Load Despatch Centre). Under the
Electricity Act, 2003, the SLDC shall be operated by a govt. company or
under any state act, as may be notified by the respective state government.
Provided that until a Government Company or any authority or corporation is
notified by the state government, GRIDCO being the State Transmission
Utility (STU), shall operate as SLDC.
In view of the aforesaid statutory requirement, it has become necessary to
take steps for separating the Trading Functions of the GRIDCO from the
Transmission and SLDC functions.
The matter is now under consideration and the following course of action is
being contemplated.
1. GRIDCO will continue to undertake bulk supply and trading functions
and will transfer the transmission functions together with the SLDC
and State Transmission Utility Functions to another new Company
(Transferee Company).
2. A public limited company under the companies act, 1956 as a wholly
owned undertaking of state government shall be incorporated for
vesting and transfer or transmission/ STU and SLDC undertaking of
GRIDCO along with its personnel.
3. There shall be a transfer of Transmission and SLDC functions of
GRIDCO for vesting with the newly incorporated company. The
181
transmission and SLDC undertakings shall comprise all properties,
rights, liabilities, etc., pertaining to Transmission/STU function and
SLDC functions along with personnel and the transfer shall be affected
through a Statutory Transfer Scheme to be notified by Govt. of Orissa
u/s 39 read with section 131 of the Electricity Act, 2003. The said
transfer Scheme shall be effective from 01.04.2004 so that the newly
OPGC 144.96 147.31 195.68 208.97 194.68 215.91 OHPC 114.26 122.06 99.93 100.19 65.92 92.69 GRIDCO -162.03 -177.45 -428.7 86.85 -4.91 112.44 TOTAL 97.18 91.92 -133.09 396.01 255.69 421.04 Though the above mentioned outcomes are some positive aspects of the reforms but all was not well in the years that followed and some of the negative outcomes are discussed in the following paragraph. The reforms were supposed to improve the power position in Orissa, but peak
shortages continue. The finances of the companies have worsened to some
extent, and the losses continue to mount (financial as well as technical).
GRIDCO failed to pay generators what it owes, citing failure of receiving
payments from the DISTCOs. Had they received their money, the generators
187
(OHPC and OPGC) have a book profit of Rs. 768 crores between April 1,
1996 and March 31, 2001 (OERC 2002).
The WB-SAR (Staff Appraisal Report) based report called for a number of
milestones, details on which can be found in Prayas (2001). Most of these
were based on structural changes, like setting up the distribution zones,
having OERC issue tariff orders, etc. However, some of these had negative
operational effects as well. The goal of 16% return for OHPC along with its
valuation hiked the costs to GRIDCO significantly, by hundreds of percent.
This is an indication that reforms process, as profitable companies come up
along the power sector (generation, transmission, and distribution), this will
raise the average cost of power compared to today’s loss-making utility.
One casualty of the reforms process was rural electrification. Private
companies were not interested in such loss-making operations. The
agricultural demand for power went down from a low 6% in 1992-93 to a
very low 3% in 1999-00 (Kanungo Committee 2001). But yet, the finances
didn’t improve. This highlights the importance of mechanisms to ensure
rural/underserved areas are catered to. Either specific targets must be set and
met, or an outside entity should be entrusted with such a role. Rural
cooperatives might be one solution for such consumers. The noted
environmentalist Ashok Khosla points out that if communities treat electricity
as a shared resource, they would manage it better, as they have done
historically for things like a shared water supply (personal communication).
What Went Wrong
The main problem with the operations of the sector was relating to cash flows.
OERC limited the increase in tariffs (citing that not all costs could just be
passed on to the consumers – e.g., for bad performance – unlike the pre-
reform days). This created losses for the DISTCOs, who also had deferred
188
payment agreements with GRIDCO. GRIDCO, owned by the Govt. of Orissa,
was caught between the increasingly expensive generators and non-paying
DISTCOs, who were unable to improve performance as expected. While the
exact numbers have varied over time, some details are as follows (Prayas
2001): GRIDCO was owed over 7.7 billion rupees by the 4 DISTCOs as of
March 31, 2000. Of this, CESCO (the central zone operated and majority-
owned by AES) owed Rs. 1.6 billion. But, GRIDCO owed OPGC, of which
AES owned 49%, some Rs. 1.8 billion. AES shut down a power plant for a
week in protest, and the crisis escalated with the Govt. threatening prison time
for its officers (under the Essential Services Act). The compromise solution
involved the government promising to pay its dues in 15 days.
After the reforms, GRIDCO’s and DISTCOs finances went down because of a
number of factors (Prayas 2001; OERC 2002):
• The bulk of the liabilities went to GRIDCO, Rs. 16 billion vs. 6 billion for
all the DISTCOMs.
• Assets of GRIDCO were revalued upwards, to help match the increase in
liabilities. This had operating implications, like the increase in depreciation
costs.
• OHPC’s tariffs were increased to meet the 16% returns. Overnight, the tariff
went from Rs. 0.1 to Rs 0.49/kWh in 1996. Even central station’s power was
expensive, and GRIDCO had to off take such power.
• There were unrealistic T&D losses estimated during the unbundling process.
This stresses the importance of accurate baseline information, and realistic
performance targets. The forecast for T&D reduction from 39.5% in 1996-97
to 22.7% 2000-01 wasn’t achieved. Even the initial assessment of 39.5% for
1996- 97 was grossly incorrect. A later audit showed this to be 49.4%.
• Tariff increases were lower than in the WB-SAR.
189
• There was no budgetary support via subsidies.
• The growth of load, especially profitable load, did not materialize. The WB-
SAR called for 7,009 million kWh for railways plus industrial high tension
(bulk) supply, while the actual sale in 2000-01 was 2,760 million kWh. This
affected not only the cross-subsidy potential, but the T&D losses as well.
• Poor collection rates from consumers. DISTCOs achieved only 75 and 76%
collection in 1999-2000 and 2000-01, respectively.
In addition to these issues, we find several other factors at play. Not enough
was invested in this sector towards the reforms. Less than half the money just
from World Bank was spent, making the total fraction utilized based on the
billion dollar estimate even lower (Kanungo Committee 2001). Critics will
point out that a significant fraction went to consultants, 306.422 crores (but
the bulk of this came from DFID funds, and none came from consumers).
There was also a cyclone that hit just after privatization, before proper
insurance was in place, causing not only a financial loss, but a major
operational challenge.
The AES episode created a lot of controversy, with their reporting
Government interference and lack of law and order, but the Kanungo
Committee Report (2001) counters a lot of difficulties were caused by AES
practices. They created a new management cadre, which caused a lot of
resentment within CESCO, the Central DISTCOs. In addition, they came in to
CESCO expecting to take up an additional 2% in OPGC, giving them 51%.
When that didn’t materialize, that triggered their desire to sell their state in
CESCO in 2001.
190
However, the biggest reasons for the poor performance appear to be the false
assumptions and expectations of the players, and the limited support provided
by the government, either for subsidies or to the companies who had liquidity
issues in addition to solvency issues. Money coming in from outside sources
was often diverted to state budget needs, and there remained significant
institutional lethargy and morass in the sector. The government failed to pay
its own dues for power, some Rs. 1.5 billion.
Some of the lessons from the Orissa experience, other than the obvious ones
include (IDFC 2000):
• Incomplete separation of transmission and distribution can cause problems.
• Regulators should give a clear picture of their tariff philosophy, rate base,
valuation methods, likely profile of prices and expected performance levels.
• There should be a structured, time-bound financial support mechanism, with
a fixed schedule for tapering off coupled with improvements in operating
parameters and collection.
• The single buyer model is necessarily not the best, and the Transco might be
better as just a wires company.
• Determining who gets priority claims over revenues is important. Do not
escrow the revenues from the distribution zones for meeting TRANSCO
needs, like was done in Orissa.
• Don’t tinker with valuations, especially just before privatization. This can
have a serious impact on tariffs, as Schedule VI of the Supply Act 1948 is
based on assets (and newer methods allow for 16% returns on equity).
191
Transfer of Assets
The restructuring was done in two steps through the instrumentality of
transfer scheme framed under the Orissa Electricity Reform Act, 1995. Under
the first transfer scheme (effective from April 1, 1996) the assets, liabilities,
proceedings and personnel of erstwhile OSEB were transferred to OHPC (for
hydel generation) and GRIDCO (Transmission & Distribution). The second
transfer scheme (effective from November, 1998) further transferred the
distribution related assets, liabilities, proceedings and personnel of GRIDCO
to four wholly owned companies of GRIDCO.
Table 20: Details of Revaluation
Details of Revaluation done in Transfer Scheme dated April 1, 1996
Rs. in Crores
Book Value of T&D Asset 1103.2 Interest and expense capitalised 97.5 Total 1201.0 Uplift in Value of Assets 1120.0 Total 2320.7 Depreciation 363.0 Net Fixed Assets of GRIDCO as on April 1, 1996
1957.7
Total Revaluation Uplift In Assets 1120.0 Further Adjustment 74.0 Total 1194.0 Adjustment Subsidy due to OSEB 301.2 Electricity charges receivable from Government
39.2
Reduction in O&M stock 50.6 Total (A) 391.0 Fresh Equity to State Govt. 253.0 Zero Coupon Bond to State Govt. 400.0 Bonds issued to Pension Fund 150.0 Total (B) 803.0 Total (A+B) 1194.0
192
RESTRUCTURING EXERCISE INVOLVED CERTAIN MEASURES,
WHICH CAST A HEAVY STRAIN ON THE FINANCES OF GRIDCO
Under the transfer Scheme of April’96, the state government took over the
Transmission and Distribution assets of OSEB (book value plus capitalized
expenses and interest at 1200 Cr.) and reinvested them in GRIDCO after
upvaluing by an additional Rs. 1194 cr. (additional 134%). Against this
upvalued amount of 1194 Cr, the state Govt. adjusted subsidies and electricity
charges payable to OSEB/GRIDCO totalling Rs.340 Cr. In addition GRIDCO
issued Rs. 253 Cr. Worth of shares and Rs. 400 Cr. Worth zero coupon bonds
to the state govt. This left GRIDCO with a serious cash shortage right from
day one and compelled it to default it to generating companies and other
suppliers. In addition Rs. 1146 Cr. of loan and liabilities were also assigned to
GRIDCO.
The upvaluation exercise was prompted by considerations including the need
to have a capital base capable of absorbing substantial debt funds needed for
the up gradation of the T&D system and the requirement of having a self
financing ratio of 20% and an adequate debt-equity ratio as per World Bank
conditions. It was also felt that the assets should be valued on the basis of
their business potential and replacement value, not their book value. The
revaluation exercise also enabled the cash strapped state govt. to “Adjust”
dues totalling Rs. 340 Cr. Payable to OSEB/GRIDCO against the
upvalued amount.
The impact of revaluation on the distribution companies has been lower than
that to GRIDCO as they were allocated only project specific liabilities
totalling Rs. 630 Cr. for all four distribution companies put together, while
GRIDCO retained in their books liabilities (including accumulated losses)
totalling about Rs. 1950 Cr. While the assets were upvalued, there was no
such upvaluation of the liabilities. Besides, as stated earlier, the distribution
193
companies were assigned only project related liabilities. The only component
of asset upvaluation which has a bearing on tariff depreciation, which stood at
Rs. 81.69 Cr. in FY96 on the eve of the upvaluation and was pegged at Rs.
128.02 Cr. for FY98 by OERC in their tariff order effective from April 1,
1997.
The difference of Rs. 46.33 Cr. (Rs. 128.02 Cr. – Rs. 81.69 Cr.) in the
depreciation (which also included depreciation of assets created during FY97)
formed only 3.2% of GRIDCO’s total revenue requirements of Rs. 1451 Cr.
allowed by OERC. Hence the impact of upvaluation on distribution tariff has
been estimated to be only about 2.5%. Further, it must be emphasized that it is
not the upvaluation exercise per-se that resulted in GRIDCO’s cash crunch;
the cause is rather the “adjustment” of the totality of its receivables from the
state government (about Rs. 340 Cr.) right from inception.
Note: Till FY-1995-96 the performance is of erstwhile OSEB and subsequent years of GRIDCO. FY 1996-97 to 1998-99 includes performance of Transmission and distribution business and FY 1999-00 onwards include only Transmission business after privatization of distribution business. The huge loss in 2002-03 is due the unprecedented hydrology failure and consequent additional burden towards purchase of high cost EREB thermal power.
Table 23: DETAILS OF LOANS Rs. In
lakhs As on 1.4.1996 1.4.1997 1.4.1998 1.4.1999 1.4.2000 1.4.2001 1.4.2002 1.4.2 Govt. Loans
Sub Total 27964 25566 36185 97654 94808 106879 180744 2295Total 122145 127488 146068 240252 255477 291736 354990 4207The Loan outstanding figure given above does not include the overdue interest. The IBRD loan has been considered as 70% loan and 30% grants from FY 2001-02 onwards.
196
Table 24: STATEMENT OF POWER PURCHASE, SALE, T& D LOSS BILLING COLLECTION ETC YEAR Energy
Table 25: Sources & Application of Funds Sources of Funds
Rupees in Million Equivalent US$ (Million)
Internal Resources 9,816 222 Grant ODA grant towards State govt. equity to GRIDCO
2,260 63
ODA grant transferred to GRIDCO as GoO grant
1,265 34
Loans World bank 14,419 350 State Government 960 26 ADB 2,025 57 Other Sources 10,605 246 Total of Loans 28,008 678 Grand Total 41,348 997
Application of Funds
Item Rupees (Million) US$ Million Capital investment 35,370 840 Interest during construction
2,060 49
Reform Expenses 2,754 74 Repair and maintenance expenditure from ODA grant
400 12
Increase in maintenance inventory
765 22
Total Investment 41,348 997 Source: World Bank Staff Appraisal Report
198
Table 26: EXPENDITURE INCURRED ON CONSULTANCY SERVICES
Sl. No.
Project Agency Amount In million PS
Rupees in Crore@ Rs. 65/PS
Funding Agency
A Pre-reform
Consultancy KPMG led consortium
41.000 GoO
1 Reform Credit Switz Fast Boston (CSFB)
16.194 105.261 DFID Grant
2 PMU Merz McLilan Seaboard International
7.605 49.433 DFID Grant
3 ISP Price Waterhouse Coopers
4.668 30.342 DFID Grant
4
RIAP Price Waterhouse Coopers
7.884 51.246 DFID Grant
5
Training Centre
Price Waterhouse Coopers
0.150 0.975 DFID Grant
6
BEINA Social Study
Price Waterhouse Coopers
0.018 0.117 DFID Grant
7 RIAP Extension
Price Waterhouse Coopers
0.600 3.900 DFID Grant
8 TRISP Package
Price Waterhouse Coopers
3.715 24.148 DFID Grant
B
TOTAL
40.834
265.421
DFID Grant
Total amount
spent on consultancy
306.421
199
Kanungo Committee’s Findings and Recommendations
Encouraged by the Government of India, assisted by the World Bank, and
supported with grants from the government of U.K. (DFID), Orissa took the
initiatives and became the first state to reform its electricity industry. The
Orissa Electricity Reforms Act, setting out the basic frame work of the
reform, enacted in 1995 came in to force from 1st. April 1996. The principal
objectives of the reforms had been discussed earlier but out of so many only
three (03) objectives were achieved namely:
(a) Restructuring of the Electricity Industry for rationalization of
generation, transmission, distribution and supply of electricity.
(b) To provide avenues for participation in the industry of private
entrepreneurs, attract private investment and reduce the need for
government funding of the electricity sector.
(c) To provide a transparent mechanism for development and regulation
of the industry, including tariff fixation and dispute settlement,
through an independent, statutory body; the Orissa Electricity
Regulatory Commission.
The other expectations were yet to be realised.
The OERC has done pioneering work in our country in the establishment of a
regulatory mechanism for the electricity industry. The reform Act, which has
given the commission a wide mandate, requires it to act effectively and
independently. The OERC’s working in the last few years, has not been free
from problems. To avoid these, the following recommendations have been
made.
200
1. To ensure that commission is fully functional at all times, the
government must appoint commissioners promptly. Action for filling
up vacancies should start early so that recommendations of the
selection committee are available to government at least two weeks
before the vacancy occurs. In the event an appointment or selection is
stayed by court, prompt action should be taken to have it vacated by
moving a higher court or a larger bench. Further nobody should be
considered for appointment unless there’s a clear possibility of his/her
serving for five years. To attract persons of ability, integrity, and
standing, wide publicity should be given while inviting nominations
for commissioners.
2. Budgetary allocation for the commission should be adequate.
Ordinarily, the government should not apply any budgetary cuts as
long as the amount proposed by the commission is within the limit of
license fees received. Accounting regulation for the commission should
be settled forthwith and budgeted outlays placed in a banking account
at the disposal of the commission for incurring expenditure in
accordance with the accounting regulation, without further reference to
the government.
3. The commission should institute regular systems of monitoring to
ensure that the prescribed standards of performance are actually
adhered to in the industry.
4. The government and the commission should have purposeful
interaction on a wide range of issues of monitoring, problem solving,
planning and development of the state’s power sector. For exchange of
information and discussion on administrative matters of mutual
interest, the government should interact with commission’s secretary.
There should also be system of meeting with the commissioners, at
201
least once a year, taken at an appropriately high level to discuss and
settle matters involving important issues of policy.
5. The reforms were conceptualized under the guidance of the World
Bank and the road map for implementation was set out in its SAR
(Staff Appraisal Report). The assumption in the SAR of growth in the
demand for power in the state was highly ambitious, in terms of totals
and compositions. The demand for industrial power (EHT Supply),
which subsidizes domestic demand (LT supply), was grossly under
realized while domestic and commercial demand with high losses grew
fast. T & D losses, which were excessively high and were targeted for
substantial reduction, could not be brought down. Billing and
collection efficiency under the privatized distribution companies were
(DISTCOs) far from improving, actually worsened and theft of
electricity continued unabated.
6. The reform scheme was further vitiated by sharp, upvaluation of assets
at the time of transfer to utilities. This led to a steep increase in the cost
of power. Unrealistic assumptions that GRIDCO would become profit-
earning from 1999/98 led to the abrupt withdrawal of subsidy by the
state government from 1996/97. There has been considerable increase
in the average tariff at a cumulative rate of 15.5% annually over the
last nine years without any perceptible improvement in customer
service. The cross subsidy has also been brought down, particularly in
the post reform period, thereby casting a heavier burden on domestic
consumers.
7. Unabated increase in tariffs without a perceptible increase in techno-
commercial losses or improvement in customer service has led to
growing public discontent against the reforms. This situation has
worsened because of spiralling increase in costs and deteriorating
202
health of the utilities. The DISTCOs & GRIDCO have been rendered
utterly unviable as a result of their inability to reduce T&D losses,
control rampant misuse, and theft of electricity and contain costs.
DISTCOs are unable to pay salaries to their employees without
defaulting on payment to GRIDCO towards the purchase of power.
GRIDCO also is unable to recover costs and is incurring heavy debts to
finance losses year after year. In this situation, the generating
companies are also facing inadequate cash realisation. The situation
has become so critical that the private sector partner in one of the
DISTCOs, AES, has abandoned the management of CESCO, which is
now being managed by a CEO appointed by regulatory authority. It is
recommended that the CEO of CESCO should be for full time.
8. The key to the revival of the sector lies in improving the efficiency and
bringing down the costs. By efficiency improvement not only can
customer services be geared up but T&D losses, currently at an
unacceptably high level, can also be brought down substantially. The
reform scheme sought to address the problem of T&D losses through
(a) capital investment to strengthen the T&D system so as to reduce
technical losses, and (b) privatisation of distribution to bring in better
management skills and practices for enforcement of accountability to
reduce commercial loss. Neither of these two has succeeded so far.
9. Large capital investments have been made but not a single project has
been completed despite considerable time overruns. The delays in most
cases for want of forest clearance, land availability or right of way.
Since none of the projects has been commissioned, no benefit has been
realized from the investments worth more than 6000 million rupees out
of funds borrowed from the World Bank carrying heavy debt-servicing
liabilities. Efforts need to be intensified to complete and commission
the ongoing works. No new work should be contracted until the
203
majority of the ongoing works is completed. With the commissioning
of these works, there should be a significant improvement in system
reliability and reduction of technical losses, which would benefit
impact on cost reduction.
10. As far as massive commercial losses are concerned, the results
achieved over the last five years are insignificant. The T&D losses,
which were 46.94% in the 1995/96 as shown by the audit, are now
46.63% as reported by the utilities themselves. The loss is more
staggering in the LT segment at 68%. The DISTCOs, in their
projections, have proposed very little reduction. The rate of loss
reduction that needs to be attempted and achieved in the next five years
must not be less than an average of five percent which, in our view, is
well within reach. Attainment of the goal would, however, call for
determined, comprehensive and relentless effort. The following are
some suggestion in this regard:
(A) A concerted drive to remove illegal connections (such as hooking)
and effective measures to convert them in to regular connections
followed up by systematic billing and collection of energy charges.
(B) Should the DISTCOs wish police force escort for carrying out
special drives to prevent unauthorized use of electricity, over and
above the comfort of the chief secretary’s circular to DMs and SPs
asking for prompt intervention in the event of violence by antisocial
elements, the government should make available to the companies
the requisite support on payment of costs.
(C) Hundred percent consumers metering within a year and immediate
metering at the low voltage terminals of the step-down transformers
should be provided so that supplies in to HT & LT systems can be
204
quantified for purpose of proper energy accounting, which is
practically missing.
11. A major cause of sharp increase in the cost of power was steep
upvaluation of assets at the time of transfer to GRIDCO. It called for
substantially higher provision for the depreciation as well as return on
capital. Neither these could be met because of short fall in revenue. In
these circumstances it would be worth while in keeping the revaluation
in abeyance till the system is brought to balance. In fact there’s a case
setting aside the revaluation of OHPC, which is expected to be
profitable in the years to come. In addition to this, state government
may agree to allow a moratorium on debt servicing to the state except
the amounts in respect of loans from the World Bank, which the state
government would need to pay to the centre. After applying these
correctives and also taking credit for T&D loss reduction at an average
rate of five percent per year, the revenue gap at the existing retail tariff
would show a decline but would still be substantial. The unavoidable
revenue gaps would need to be financed from the sources other than
debt. Since the state governments are themselves passing through
severe financial stress, it may not be realistic to ask them to make a
sacrifice over and above what has been suggested already.
12. An exercise has been carried out to estimate the annual shortfall on a
cash flow basis without tariff hike but assuming that collection
efficiency of the DISTCOs would progressively improve from the
present level of 76% to reach 95% by the year 2005/06 instead of
ending up with a collection efficiency of 84% proposed by them. With
a tariff hike of 18% in 2005, the entire cash deficit would disappear
and the year 2005/06 would witness both an operational profit as well
as marginal cash surplus. The sector as a whole would turn around in
2005/06. The consumers could be called upon to pay higher tariffs at
205
that stage because by then the utilities are expected to have shown
evidence of their concern for and efficiency in T & D loss reduction
and improvement of customer service; not otherwise.
13. To bring the reforms back on the rails, the World Bank and the DFID
who helped Orissa initially, and hopefully have retained their interest
in the reform, should come forward with a suitable package to fill the
revenue gap in the intervening years. Without this interim financing
(estimated at 32400 million rupees), there seems hardly any prospect of
the reform coming to fruition. The Government of India should not
only persuade them to do so but also extend a helping hand in sharing
the responsibility of interim financing of the revenue gap.
14. Once decision is taken on interim financing and its apportionment, the
DISTCOs and GRIDCO may be pinned down to specific performance
parameters by desegregating the proposed T&D loss reduction
DISTCO-wise.
15. In the prevailing run down state of GRIDCO and DISTCOs, no durable
rehabilitation is possible without interim financing of unavoidable
losses. However it needs to be emphasized that no amount of support
from outside would succeed unless the utilities conduct themselves
with greater sense of responsibility. Privatization was seen as a means
to improve the performance of DISTCOs. The private sector partners
need to bear in mind their crucial role, which cannot be performed
satisfactorily unless they face the task as a challenge and an
opportunity and take the industry forward in the true spirit of
partnership and for mutual benefit.
16. The private promoters of DISTCOs neither brought superior
management skills nor did they arrange financial support even by way
206
of working capital for companies, which were in dire need of capital,
working capital in particular. Instead of using the good offices of
BSES to secure working capital in terms of clause 8.1 of the
shareholders agreement for the three DISTCOs under their
management, the DISTCOs have persistently defaulted in payment to
GRIDCO towards purchase of power. The outstanding overdue of
GRIDCO as on 30 September 2001 against these three DISTCOs is
6807.2 million rupees including bonds issued by them in lieu of cash
payments. So far as the other distribution company CESCO is
concerned, the situation is worse. AES, the private partner, never
fulfilled its commitment to bring working capital. They were allowed
to pile up unpaid power purchase bills amounting to 4030 million
rupees by the time they walked away in August 2001. Now that the
AES have abandoned CESCO, GRIDCO seems to be left with hardly
any other option except exploring a legal remedy. As far as BSES-
managed DISTCOs are concerned, the attitude of deliberate default in
payment to GRIDCO must end. The BSES should make all efforts to
bring in working capital in terms of the shareholders agreement.
17. The system of escrow put in place to secure regular payments to
GRIDCO towards power purchase has not worked. With the package
of financial relief recommended by us along with enforcement of the
provisions of the shareholders agreement, the escrow mechanism
should be made to work and strictly enforced. (Escrow-In the event of
non-payment by the SEB, IPP shall have recourse to L/C and revenues
shall be accumulated in the escrow account. In case funds in escrow
account are insufficient, IPP may invoke State Govt. guarantee)
18. There is an urgent need to develop trust and goodwill between the
employees and the management. The vital role of the employees and
their associations in building up the industry needs to be taken more
207
seriously. While firm action against known miscreants is necessary to
enforce discipline and accountability this cannot be done without
skillful handling of situations and willingness to mitigate genuine
grievances. A specific matter in this connection relates to pensionary
benefits. Employees apparently have found that the pension scheme
preferred by them, and also adopted by the companies, has turned out
to be disadvantageous, particularly for those who came over from the
government in a higher age group. In a matter like this neither the
present employers nor the government should take any rigid stand. The
effort should be to find a solution, which may not even be difficult to
reach. Likewise, there is an apprehension the liabilities of
government/GRIDCO towards the Pension Trust may not have
assessed correctly. This is a matter of actuarial calculation, which may
affect the viability of the pension funds, so there should be no
reluctance to take a fresh look at the estimates.
19. Orissa is richly endowed with natural resources, and now has the
additional advantage of the surplus power. This combination needs to
be exploited to accelerate industrialization of the state through
vigorous marketing of power by offering more competitive rates. By
selling surplus power to industries, even at tariffs lower than prescribed
by the OERC, not only would the state benefit from industrialization,
but the DISTCOs themselves would also stand to gain as long as they
recovered costs at the margin. The tariffs fixed by the OERC should be
treated as the ceiling in each category, and utilities should have the
freedom to supply power at lower rates in exercise of their commercial
judgement.
20. With restructuring and privatization, there’s a much greater need now
for rigorous enforcement of safety norms in the electricity industry.
However, care needs to be taken to see that there’s no mindless
208
expansion of the Electrical Inspectorate. Services of chartered
engineers, under a strict system of empanelment and penalty in the
event of misconduct, may be utilised for the purpose of supplementing
human resources of a slim, well structured inspectorate.
21. The services of local consultants as well as highly rated consulting
firms of international repute were used extensively in the preparation
of blueprint of reform, and to assist the utilities in developing internal
systems of operation management, financial control, technical services,
contract management, project implementation, etc. The cost incurred
so far is a staggering 3060 million rupees. However, judging by the
fate of reforms and the state of the utilities it is clear that the utilities,
for whose benefit the consultants were engaged, did not assimilate
much of their advice. Instead of developing an inner strength with the
assistance of consultants, they tended to be excessively dependent on
them leading to a near-atrophy of organisational strength. We suggest
that this practice, which weakens organisation rather than
strengthening them and demotivates employees instead of improving
their skill and confidence, should end as soon as possible.
22. Close attention should be given to strengthening the managerial
competence of GRIDCO, which is not only financially sick but also
organisationally very weak. The following recommendations are made
in this connection.
• The senior management of GRIDCO should be selected on the
basis of merit and must be appointed for a fixed term of three to
five years.
• The SLDC (State Load Dispatch Centre) and its commercial
counterpart, the energy billing centre, should be provided with the
209
necessary staff whose skills should be substantially honed and
upgraded by regular training.
• GRIDCO’s PMU (Project Management Unit) should take over the
responsibility of all capital works irrespective of the source of
funding. It should also monitor capital works executed by the
distribution companies in addition to managing and monitoring.
23. The entire power sector needs top management of a high calibre just as
it requires an efficient work force motivated to further the interest of
the industry. The task before the management is daunting.
Appointments to the boards of directors of all the utilities need to be
reviewed to ensure that professionals including administrators with
competence, vision and commitment may enrich the utilities at the top.
The prevailing system of part time appointments to key positions in the
sector, including the chief executive officer of the OHPC should end.
The chief executive officers of the DISTCOs should be stationed at
their respective head quarters.
24. The committee did not get the evidence of any innovative practice
introduced in the management of the privatized DISTCOs. However, in
some of the DISTCO areas, an experiment is in progress to involve
village communities in streamlining power supply in rural areas. While
the results seem to be encouraging, the exercise currently being
conducted by consultants can succeed in the long run and over large
areas only if the programme is implemented by DISTCO official
themselves.
25. It is recognised that regulatory commission need to lay down norms for
tariff determination, which would enable the utilities to have a clear
idea of the range in which tariffs may move over a reasonable period.
A multi-year tariff regime is therefore, being advocated by experts.
210
The OERC has also laid down norms in certain areas though much
more needs to be done. But no purposeful result can be achieved in the
matter of multi-year tariffs unless there is a reasonable financial
balance. Serious efforts are required to provide financial balance to the
sector before multi-year tariffs can become a reality.
26. Another idea often advocated by experts is multi-buyer model of
power trading. Here again attainment of financial balance is an
essential pre-requisite to provide a basis for competition through
various models of multi-buyers system as distinct from the single-
buyer model adopted by Orissa as well as other states who have
embarked on reform. In the prevailing situation of near bankruptcy of
GRIDCO and disarray in the functioning of DISTCOs, the sector
should be spared any further trauma. Meanwhile, GRIDCO needs to
strengthen itself to develop ability and skill to handle the power trading
function which calls for, among other things, prompt exercise of
commercial judgement. Urgent attention should be paid to develop this
within the organisation. It would be of advantage to develop within
GRIDCO a well functioning trading unit which may eventually be
turned in to an independent trading organisation as a step towards
bringing in a competitive regime that would provide the consumer the
opportunity to choose the source of this power supply.
27. Rural electrification seems to have unintentionally become the worst
casualty of the reform process. With the restructuring of OSEB, and
privatization of DISTCOs, the rural electrification wing of OSEB was
disbanded and it was left to the DISTCOs to carry on with whatever
schemes were in the pipeline. Since the activity is commercially not
attractive, the DISTCOs cannot be expected to be very enthusiastic
about rural electrification. The interest of DISTCOs has further
slackened because even the modest rural electrification work done by
211
them has not been paid for in spite of the fact that an amount of Rs. 23
Crore of capital subsidy due was certified by OERC several months
ago. No fresh scheme of rural electrification seems to have been posed
for funding support of agencies like REC, nor any scheme drawn up
for the purpose. Another regrettable feature is the utter lack of concern
for productive use of electricity for rural development through
agriculture pumping. In terms of agricultural demand for power among
states, Orissa is practically at the bottom. What is worse is that
agricultural demand for power in the state has gone down from a
meagre 6% in 1992-93 to a dismal 3% in 1999-00, compared with
national average of 30%. No single department of the state government
is entrusted with the administrative responsibility to plan, promote and
monitor growth and press for rural electrification for development of
irrigation pumping which is vital rural development. Under a high
priority national plan, all villages are required to be electrified by
March 2007. For a state like Orissa, with a 40% of the population from
weaker sections of scheduled castes and scheduled tribes living in
remote areas, the leeway to be made is large. Kutir Jyoti program
needs to be pursued with vigour. It must however be ensured that the
benefits of subsidised electricity supply under this program flow to the
targeted beneficiaries the goal is unlikely to be reached unless
determined efforts are made and an effective machinery is put in place
for planning, execution and monitoring of rural electrification projects.
The vacuum caused by abolition of the rural electrification wing of the
OSEB needs to be filled up and an alternative system created. The
following recommendations are made in this connection:
a) A Rural Engineering Planning Organisation (REPO)
should be set up under the Government to provide
focus and direction to this vital programme, to prepare
212
specific schemes, pose them to funding agencies and
over-see utilization of the funds procured.
b) REPO should have under it four Rural Electrification
Planning Units (REPU), each corresponding to a
DISTCO with which it would need to work in close
coordination. These units would draw up, detailed
schemes of rural electrification.
c) Prioritisation of villages for electrification should be
done by REPUs in consultation with the collector of the
concerned district.
d) Execution of the works would be the responsibility of
the concerned DISTCOs.
e) REPUs would need to monitor the execution and report
completion of schemes and the expenditures incurred
thereon to the Collector of the district and the State
REPO.
f) On the basis of the Collectors’ certificates of
satisfactory completion, the state Government should
promptly settle subsidy payments admissible to
DISTCOs.
g) Government would need to provide DISTCOs with
capital subsidy; revenue requirements would, in normal
course, be considered by OERC as a part of tariff
exercise.
28. Our recommendation would help rehabilitate the utilities, bring
stability and promote growth of the power sector only if these are
implemented as a package and implementation is managed and
monitored closely. The reform adopted by Orissa may have been
flawed, but mid-course corrections could have been managed rather
than its success taken for granted. The committee’s recommendations
213
towards putting back the reform on rails would succeed only if the
need for reform management is recognised and a system is put in place
by the government for regular monitoring, co-ordination and mid-
course correction. It is interesting to know that of all the major
parameters of reform laid down in the SAR; one of the few that proved
realistic was tariff. Retail tariff has been fairly close to the SAR
assumption in the first two years and substantially higher since 1998-
99. Thus, consumers have not failed to provide support; they have
made ample sacrifice in search of better quality of service which has
eluded them so far.
29. Power sector would succeed if the utilities bring in efficiency, cut
costs, reduce losses and ensure greater consumer satisfaction. It would
also require strong enforcement to ensure that consumers of electricity
pay for its use. All sections of the society, particularly those, who are
in a position to influence public opinion, have the responsibility to
provide the requisite support. Revival of the power sector would
depend to a large extent on how fast a consensus is built in this vital
area.
30. The state’s power sector is now on the brink of the crisis. It is high
time all agencies namely, the state government, the central
government, the world bank and the DFID, got together and took a
holistic view on what can be done by each to rescue the reform. If the
electricity reform fails in Orissa, it would have its inevitable adverse
impact on reform all over the country. What have taken place in the
electricity industry of Orissa is only restructuring, privatization and
establishment of a Regulatory Mechanism. The real reform, which
brings in its wake benefits to consumers, strength to the industry and
growth for the economy has yet to come.
214
Turnaround of GRIDCO / OPTCL - A Case Study
All the major steps in the restructuring process have since been taken as
envisaged under the reform scheme:
• OSEB was restructured and corporatised in to Grid Corporation of
Orissa (GRIDCO) and Orissa Hydro Power Corporation (OHPC) in
April 1996.
• The Orissa Electricity Regulatory Commission (OERC) was
established in August 1996.
• Orissa Power Generation Corporation (OPGC) was privatized with
divestment of 49% stake and transfer of management control to a
private operator, AES in January 1999.
• Four distribution companies (DISTCOs), incorporated as wholly
owned subsidiaries of GRIDCO, were privatized with transfer of 51%
stake to private operators: three of these, namely, NESCO, WESCO
and SOUTHCO were acquired by BSES in April 1999 and the fourth,
viz. CESCO by AES in September 1999.
GRIDCO disinvested 51% of its equity holding to private investors with
strong financial standing & technical capabilities. 10% of the equity has been
reserved for the employees of GRIDCO- that would entitle them to direct
monetary and welfare benefits. GRIDCO retains 39% of the holdings in the
DISTCOs.
215
Transfer of Assets
The restructuring was done in two steps through the instrumentality of
transfer scheme framed under the Orissa Electricity Reform Act, 1995. Under
the first transfer scheme (effective from April 1, 1996) the assets, liabilities,
proceedings and personnel of erstwhile OSEB were transferred to OHPC (for
hydel generation) and GRIDCO (Transmission and Distribution). The second
transfer scheme (effective from November, 1998) further transferred the
distribution related assets, liabilities, proceedings and personnel of GRIDCO
to four wholly owned companies of GRIDCO.
RESTRUCTURING EXERCISE INVOLVED CERTAIN MEASURES,
WHICH CAST A HEAVY STRAIN ON THE FINANCES OF GRIDCO
Under the Transfer Scheme of April’96, the state government took over the
Transmission and Distribution assets of OSEB (book value plus capitalized
expenses and interest at 1200 Cr.) and reinvested them in GRIDCO after
upvaluing by an additional Rs. 1194 cr. (additional 134%). Against this
upvalued amount of 1194 Cr, the state Govt. adjusted subsidies and electricity
charges payable to OSEB/GRIDCO totalling Rs.340 Cr. In addition GRIDCO
issued Rs. 253 Cr. Worth of shares and Rs. 400 Cr. Worth zero-coupon bonds
to the state govt. This left GRIDCO with a serious cash shortage right from
day one and compelled it to default it to generating companies and other
suppliers. In addition Rs. 1146 Cr. of loan and liabilities were also assigned to
GRIDCO.
The upvaluation exercise was prompted by considerations including the need
to have a capital base capable of absorbing substantial debt funds needed for
the up gradation of the T&D system and the requirement of having a self
financing ratio of 20% and an adequate debt-equity ratio as per World Bank
conditions. It was also felt that the assets should be valued on the basis of
216
their business potential and replacement value, not their book value. The
revaluation exercise also enabled the cash strapped state govt. to “Adjust”
dues totalling Rs. 340 Cr. Payable to OSEB/GRIDCO against the
upvalued amount.
Table 27: Revaluation of Assets
Details of Revaluation done in Transfer Scheme dated April 1,
1996
Rs. in Crores
Book Value of T&D Asset 1103.2 Interest and expense capitalised 97.5 Total 1201.0Uplift in Value of Assets 1120.0Total 2320.7Depreciation 363.0Net Fixed Assets of GRIDCO as on April 1, 1996
1957.7
Total Revaluation Uplift In Assets 1120.0 Further Adjustment 74.0 Total 1194.0Adjustment Subsidy due to OSEB 301.2Electricity charges receivable from Government
39.2
Reduction in O&M stock 50.6Total (A) 391.0Fresh Equity to State Govt. 253.0Zero Coupon Bond to State Govt. 400.0Bonds issued to Pension Fund 150.0Total (B) 803.0Total (A+B) 1194.0 Source-Price Water House Coopers
217
The impact of revaluation on the distribution companies has been lower than
that to GRIDCO as they were allocated only project specific liabilities
totalling Rs. 630 Cr. for all four distribution companies put together, while
GRIDCO retained in their books liabilities (including accumulated losses)
totalling about Rs. 1950 Cr. While the assets were upvalued, there was no
such upvaluation of the liabilities. Besides, as stated earlier, the distribution
companies were assigned only project related liabilities. The only component
of asset upvaluation which has a bearing on tariff depreciation, which stood at
Rs. 81.69 Cr. in FY96 on the eve of the upvaluation and was pegged at Rs.
128.02 Cr. for FY98 by OERC in their tariff order effective from April 1,
1997.
The difference of Rs. 46.33 Cr. (Rs. 128.02 Cr. – Rs. 81.69 Cr.) in the
depreciation (which also included depreciation of assets created during FY97)
formed only 3.2% of GRIDCO’s total revenue requirements of Rs. 1451 Cr.
allowed by OERC. Hence the impact of upvaluation on distribution tariff has
been estimated to be only about 2.5%. Further, it must be emphasized that it is
not the upvaluation exercise per-se that resulted in GRIDCO’s cash crunch;
the cause is rather the “adjustment” of the totality of its receivables from the
state government (about Rs. 340 Cr.) right from inception.
Privatization of Distribution Functions:
In pursuant to the Orissa Electricity Reform (Transfer of Assets, liabilities,
proceedings & personnel of GRIDCO to distribution companies) Rules, 1998,
the government of Orissa transferred the distribution assets and properties
along with personnel of GRIDCO to 4 distribution companies namely
CESCO, NESCO, WESCO, and SOUTHCO continued to function as
affiliates of GRIDCO up to 31.03.1999 and thereafter functioned under the
distribution & retail supply license obtained from OERC.
218
Objectives of Privatization of Distribution Function:
A. Operational Improvements:
(i) Improve quality of service to consumers
(ii) Improve operational efficiencies & reduce losses.
B. Financial Benefits:
(iii) Attract private investment in to the distribution business
(iv) Reduce the need for government funding of the electricity
sector
(v) Contribute to increased economic growth in Orissa.
C. Employee Considerations:
(vi) Create opportunities for secure & increasingly rewarding
employment for the qualified personnel
(vii) Provide a stable environment for employees
D. Sale of all 4 Zones to promote competition
In keeping with the objectives of power sector reform and the commitments
given to the World Bank by the state government, the distribution function
was required to be privatized. After considerations of various options
available for privatization, the corporation decided to adopt the best mode of
Joint sector/ Joint venture route. The sequence agreed was that the four
distribution zones which were functioning under the corporation will be
converted in to four distribution companies as its wholly owned subsidiary.
In spite of these pragmatic reform programmes, GRIDCO’s financials
worsened in the year 2000 and debt level of the company rose to the all time
high. Then state government did intervene and constituted a high power
committee lead by Mr. Sobhan Kanungo (I.A.S), to examine the fault lines
and asked the committee to suggest the measures to put the GRIDCO back on
track. After adhering to committee norms, improvements in all sectors are
219
visible now with increase in earnings and total turn around, with the GRIDCO
posted a net profit in FY 2004-05. The highlights of the results as follows:
1. GRIDCO started trading of its surplus power with the utilities/SEBs
through the Power Trading Corporation of India Ltd. (PTC) by
entering into an Agreement signed on 03.07.2003. The trading was
started with effect from 05.07.2003 initially for an average of 100 MW
@ Rs.2.60/unit for the evening peak @ Rs.2.00/unit for the off-peak
(18 hours) a day. The average rate was Rs.2.15/ unit Further, GRIDCO
has also entered into an agreement with NTPC Vidyut Vyapar Nigam
Ltd. (NVVNL), a wholly owned subsidiary of NTPC on 24.09.2003 for
an average of 100 MW trading. Trading of power with NVVNL was
started with effect from 01.10.2003.
During November, 2004 the peak export is 557 MW, off-peak export is
427 MW and the average export is 460MW.
Peak Trading 550 MW Off peak Trading 430 MW Average Trading 460 MW
2. T & D losses, which were excessively high and were targeted for
substantial reduction, could be brought down gradually. Billing and
collection efficiency under the privatized distribution companies
(DISTCOs) started improving, theft cases of electricity started falling
and due to the introduction of one time settlement of theft and irregular
connection cases, many new customers were created over the years and
receivable collection started increasing.
Steps taken in this regard to reduce T&D losses are through (a) capital
investment to strengthen the T&D system so as to reduce technical
220
losses, and (b) privatisation of distribution to bring in better
management skills and practices for enforcement of accountability to
reduce commercial loss (D) Hundred percent consumers metering
within a year and immediate metering at the low voltage terminals of
the step-down transformers were provided so that supplies in to HT &
LT systems can be quantified for purpose of proper energy accounting.
Year
1999-2000
2000-01 2001-02 2002-03
2003-04 2004-05
% of T&D Loss
44.16% 43.75% 46.56% 42.98% 40.14% 38.93%
Collection as % of Billing
79.96% 81.41% 75.59% 81.70% 83.25% 88.68%
3. An exercise was carried out to estimate the annual shortfall on a cash
flow basis without tariff hike but assuming that collection efficiency of
the DISTCOs would progressively improve from the present level of
76%(2001-02) to reach 95% by the year 2005/06 instead of ending up
with a collection efficiency of 84% proposed by them. Already 2004-
05 witnessed a collection efficiency of 90%.
With a tariff hike of 18% in 2005, the entire cash deficit would
disappear and the year 2005/06 would witness both an operational
profit as well as marginal cash surplus. The sector as a whole would
turn around in 2005/06, which includes the distribution companies
also.
The consumers could be called upon to pay higher tariffs at that stage
because by then the utilities are expected to have shown evidence of
their concern for and efficiency in T & D loss reduction and
improvement of customer service; not otherwise.
221
4. To bring the reforms back on the rails, the World Bank and the DFID
who helped Orissa initially came forward with a suitable package to
fill the revenue gap in the intervening years. Without this interim
financing (estimated at 32400 million rupees), this gradual turnaround
in GRIDCO’s fiscals were unlikely and hardly there was any prospect
of the reform coming to fruition.
5. The system of escrow put in place to secure regular payments to
GRIDCO towards power purchase has not worked initially. With the
package of financial relief recommended along with enforcement of
the provisions of the shareholders agreement, the escrow mechanism
has started working and has been strictly enforced.
6. The services of local consultants as well as highly rated consulting
firms of international repute were used extensively in the preparation
of blueprint of reform, and to assist the utilities in developing internal
systems of operation management, financial control, technical services,
contract management, project implementation, etc. The cost incurred
so far is a staggering 3060 million rupees. Judging by the fate of
reforms and the state of the utilities it is clear that the utilities, for
whose benefit the consultants were engaged, did not assimilate much
of their advice or it did not reach to the bottom line managers. These
services of the consultants, which weakened the organisation rather
strengthening them, were stopped and government appointed efficient
bureaucrat in-charge of GRIDCO, which made turnaround a reality and
it has been decided to keep the tenure of CMD, GRIDCO fixed for 03
years, prior to which they should not be disturbed on normal course.
Chief executive officers of the DISTCOs are now stationed at their
respective head quarters.
222
7. To ensure that commission (OERC) is fully functional at all times, the
government started appointing commissioners promptly because
OERC has done pioneering work in our country in the establishment of
a regulatory mechanism for the electricity industry. Commission
started instituting regular systems of monitoring to ensure that the
prescribed standards of performance are actually adhered to in the
industry.
8. The government and the commission started interacting on a wide
range of issues of monitoring, problem solving, planning and
development of the state’s power sector. For exchange of information
and discussion on administrative matters of mutual interest, the
government evolved a mechanism to interact with commission’s
secretary.
223
Comparison of Financial Performance – Orissa Vis-à-vis Andhra Pradesh Table 28: Financial Result Analysis of Andhra Pradesh
Particulars
2003 – 04
2004 - 05
1. Total Income
2468.37
2416.40
2. Total Expenditure
2481.77
2422.47
3. Profit / (Loss) before Tax
13.40
6.07
4. Provision for Income Tax
----------
0.45
5. Profit / (Loss) after Tax
(13.40)
(6.52)
6. Net prior period credits / (Charges)
19.38
9.13
7. SURPLUS / (DEFICIT)
5.98
2.61
• % increase in Profit : 129.01% • % increase in Income : 2.15% • % increase in Revenue : 5.84% • % increase in Sales : 11.98% • % reduction in Distribution Loss : 1.21% • % reduction in distribution Transformer Failure: 0.82%
224
Table 29: Financial Result Analysis of Orissa
Particulars
2002 – 03
2003 - 04
1. Total Income
1686.33
2809.74
2. Total Expenditure
1865.43
1921.62
3. Profit / (Loss) before Tax
(179.70)
888.12
4. Provision for Income Tax
------------------
------------------
5. Profit / (Loss) after Taxation, contingency & Resv.
(59.80)
41.11
• % increase in Profit : 231.18% • % increase in Income : 66.61% • % increase in Sales : 31.11% • % reduction in Distribution Loss : 3.24% • % reduction in distribution Transformer Failure: 1.17%
225
SOCIO ECONOMIC IMPACT ASSESSMENT OF POWER SECTOR
REFORMS: A MICRO LEVEL ANALYSIS
V.1 Introduction
5.1 Aggregative analysis as presented in the previous chapters gives a
macro perspective of the different aspects of power sector reform in Orissa
and its impact. However, the analysis of aggregated data may not serve to
bring out the subtle nuances of reform and its impact at the user level, the
spatial variations and ground-level perceptions. Accordingly, the present
chapter proposes to develop a general micro level perspective about the effect
of reform on different user categories on the basis of various impact
parameters. The data collected from the users is both factual and perception-
based.
5.2 These disaggregated data are collected from different sources and from
different districts of the state of Orissa. The sources are:
a) households,
b) commercial and small industrial establishments,
c) principal informants including key power sector
functionaries, high-level officials of the Government of
Orissa and user group representatives and
d) the Focus Group Discussions (FGDs) in the selected sites.
The instruments1 of data collection consist of a structured questionnaire for
households, FGD dairies, an open ended checklist for commercial and small
industrial users, a list of issues in connection with the power sector for being
discussed with the principal informants and also informal discussions. After
pilot testing of the instruments and rigorous training of the investigators for
administering them, the actual field investigation was conducted over a period
of 4-5 weeks in the months of November – December in 2003. The senior
226
members of the study team conducted some of the FGDs and principal
informant interviews themselves in two installments.
V.2 Micro Level Data Sources: Sampling Framework
5.3 The study on Socio-economic Impact of Power Sector Reform was
conducted in eight selected districts of Orissa, with 2 districts sampled from
each of the 4 geographical zones (North, South, East and West) of the State.
Figure-5.1 gives the design of the sampling frame. A total of 2112
households from 32 selected villages (falling in 16 sample blocks) and 8
selected urban centres were surveyed to elicit users’ perceptions on different
aspects of power sector reform.
227
Nandapur (LE)Bajapur (HE)
Chhutaraipur (LE)Nairi (HE)
Bhubaneshwar (Town / City)
Sanagarh (LE)Gopalpur (HE)
Patanda (LE)Kishor Prasad (HE)
Nayagarh (Town / City)
Mahul Chappal (LE)P Pathhar (HE)
Balaranga (LE)Bargoan (HE)
Sambalpur (Town / City) Sambalpur
Salgadia (LE)Santuri (HE)
Lunahandi (LE)Kundanali (HE)
Angul (Town / City)
Rajpur (LE)Padmanavapur (HE)
Lunghuri (LE)Damodarpur (HE)
Berhampur (Town / City)
Badagatiguda (LE)Chatikana (HE)
Dangasorda (LE)Chandrapure (HE)
Rayagada (Town / City)
Somapur (LE)Baligan (HE)
Malitira (LE)Purusandha (HE)
Bhadark (Town / City)
Machhala (LE)Deogaon (HE)
Khandara (LE)Lalahari Basti (HE)
Keonjhar (Town / City)
Note : LD = Less Developed Block & LE = Less Electrified Village : HD = Highly Developed Block & HE = Highly Electrified Village
Design of the Sampling Frame for Collection of Primary Data
O R I S S A S T A T E
Bhubaneshwar
Keonjhar
Bhadark
Rayagada
Berhampur
Angul
Gania
Bamra
Nayagarh (LD)
Nayagarh
East
ern
Zone
Wes
tern
Zon
e
(HD)
(HD)
(HD)
(LD)
(LD)
(HD)
Digapahandi
Sout
hern
Zon
e
(LD)
(LD)
Bissam Cuttack
(LD)
(HD)
(LD)
(HD)
Khurda (HD)
Ganjam (HD)
AthamallickAngul (LD)
Banarpal
Sambalpur (HD) Maneshwar
Khurda
Chilika
Ranapur
Nor
ther
n Zo
ne
Ghasipura
Joda
Ganjam
Keonjhar (LD)
Rayagada (LD)
Bhadark (HD)
Chandrapur
(HD)
(LD)
Chandabali
Banta
(HD)
(LD)
228
V.3 Analysis of Household Data
5.4 This section analyzes the information gathered from responding
households* using electricity on different aspects of power sector reform that
are closely linked to the stated objectives of:
increasing access to electricity,
improving the quality of power supply,
enhancing billing and collection efficiency in the distribution of
power, and
generating a system for better supplier-consumer interface that
includes quality customer care.
We have discussed the household level data in respect of all the
indicators for the pre reform and reform periods and for rural/urban areas. The
study conducted by Xavier Institute of management (1996) is supposed to be
used as the benchmark (baseline) in order to have a comparative perspective
of pre and post reform periods. But for all the indicators used in the present
study, we are not able to use Xavier institute’s study due to the following
reasons: (i) the sample size for the domestic consumers of the Xavier study
was 288 while in the present study it is 2112; (ii) the analysis of rural and
urban area separately as well as by social groups was not made in respect of
all the indicators in the Xavier study. Therefore, wherever possible, we have
used the Xavier’s study as benchmark, otherwise, we have used CMDR’s
field survey data for the pre reform period.
Profile of Sample Households
5.5 Of the 2112 sample households, rural households constitute 52 %
(1107) and the rest are situated in urban areas. A little more than half (52 %)
of the total sample households belong to the socially less privileged categories
(Scheduled Castes, Scheduled Tribes, Other Backward Castes), hereinafter to
be referred to as the ‘Less privileged class’. While more than 70 % of the
* On an average, the extent of non-response on different aspects ranges between 2 and 20 % of the total sample size.
229
rural households belong to less privileged castes, about 67 % of the urban
households belong to the privileged category. The sex ratio (number of
females per 1000 males) in rural areas is 826 while the same is 859 in urban
areas. The sex ratio among upper caste is in favour of females in both rural
and urban areas. Expectedly, the urban literacy rate comes out much higher
than the rural literacy rate, particularly for education at the secondary level
and beyond2. Thus, while for the rural sample the literacy rate at secondary
level and beyond is estimated to be about 47% of the total number of persons
in the sample, the same is close to 60% for all persons in the urban sample.
Across the different caste groups it is found that the less privileged categories
are always behind the privileged category as one move towards higher and
higher levels of education. Irrespective of the social category, female literacy
rate at all levels of education is always behind the corresponding male literacy
rate.
Access to Electricity
5.6 “Kutir Jyoti” Scheme: The government of Orissa has a special scheme
named ‘Kutir Jyoti’ that is intended to improve the access to and use of
electricity among the rural SC, ST and OBC households living below poverty
line (BPL). The survey data relating to the sample households shows a
significant number of forward caste households (about 14%) coming under
this scheme (Chart-5.1). This gives an impression that, like any other scheme
for the rural poor, the benefits of this scheme are also enjoyed by the
privileged category. About 29 % SC and 39 % ST households are covered
under ‘Kutir Jyoti’ scheme. The relatively low targeting of the scheme among
the sample households may also be due to the high illiteracy rate of the SC
and ST population and their ignorance of the schemes meant for their welfare.
2 The focus on secondary level of education and beyond it is based on the assumption that awareness about power sector reform is likely to be more crystallized at this level.
230
Chart 5.1: Composition of Kutir Jyoti Households
SC29%
ST38%
OBC19%
Forward Caste14%
5.7 Access to Electricity by Sample Households: From Table-5.1 it is
found that 85 % of the total sample households got their connection before the
reform in the power sector. There is no difference between the average
connected load of the households between pre reform and reform period. The
average distance from the nearest electric pole to domestic connection was 20
meters (distance) in the pre reform period while the same comes out as 28
meters during the reform period. The amount spent in getting connection is
found to be nearly double in the reform period than that during pre reform
period. As per the rules, the domestic consumers are expected to get
connection within 30 days of their application. During the pre reform period
(XIMB,1996) only 29 % of the total domestic consumers got connection
within 30 days while during the reform period (CMDR study) it is reported
that the average number of days to get connection is 21 days which seems to
be an achievement of the reform process.
231
Table 5.1: Indicators of Access to Electricity by Sample Households
Information on
Pre-reform period
Reform period
Percentage of sample households that received connection 85.0 15.0
Connected Load (in kwh) 1.4 1.4 Distance from the pole (in meters) 19.9 27.6 Amount spent in connection (in Rs) 854.7 1521.9 Time taken for getting connection in days (CMDR study) - 21
XAVIER study: % of HH got connection in <30 days 29 -
Metering of Electricity Use
5.8 Metered Connections: The reform aims at achieving 100 percent
metering of the use of electricity. In the sample taken up for study, about 17
% of rural households and 2 % of urban households revealed that they did not
have meters in the pre reform period (Table 5.2). During the reform period
about 10 percent of the households did not have meters (CMDR study, 2003)
while 19 percent households did not have meters during the pre reform period
(Xavier study, 1996). On the whole, the reform objective of 100% meter
connections to the households is yet to be achieved.
5.9 Functioning of meters: About 25 % meters were not in working
condition in the pre reform period, while the same declines to 3 % for the
reform period (Table 5.2). It thus seems that significant achievement in
respect of repairing and replacing the non-working meters has been
observed. This possibly reflects a greater emphasis of the DISCOMs not only
installation of meters but making them effectively functional.
232
5.10 Frequency of Meter Reading: The irregularity in meter reading has
declined from 26 % (Xavier study) in the pre reform period to about 8 %
(CMDR study) in the reform period. There is a significant improvement in
the frequency of meter reading (every 2 months) in rural areas during the
reform period (as reported by 74% of sample households in reform period
compared to 48 % in the pre reform period). Similarly, for the urban areas the
monthly reading of meter is reported to be more frequent during the reform
period by 66% of urban households, compared to 44 % in the pre reform
period (Table 5.2).
5.11 Complaints about Meters: More than 80 % of the rural households and
more than 90 % in urban areas did not lodge any complaint in case of non
working of the meters in the pre reform period. In comparison, during the
reform period this increased to 98 % and 96 %, respectively, of households in
rural and urban areas. It is significant to note that the proportion of
households going for lodging any complaint in case of defective meters
declined sharply (from 18 percent to 2 percent) during the reform period,
particularly in rural areas (Table 5.2). It is possible that there is less cause
for complaint as far as the working of meters is concerned in the reform
period and this is definitely an indicator of improving system efficiency in
energy accounting by the DISCOMs. There is an alternative viewpoint on
this aspect of metering and it is based on the widely reported dissatisfaction
about the customer care services of the DISCOMs. Thus, if the public
perception is that complaints lodged by them are less likely to receive
timely and satisfactory attention, there would be a clear disinclination to
access the existing grievance redressal system. However, the latter
viewpoint seems unlikely considering that the next two indicators relating to
customer care (for meter related problems) give a positive impression of
the reform impact.
233
5.12 Time taken for Repairing of Meters: As per the norm, in case of non-
working of meters, the concerned DISTCOM is required to attend to it within a
maximum period of 22 days from the day of complaint lodged by the consumer
household. For the sample households it is found that the number of days taken in
correcting/repairing the meter has been reduced on an average from 29 days in the
pre reform period to 17 days in the reform period in rural areas while the
corresponding decline in urban areas has been from 25 to 15 days. It seems that
reform has been successful in this respect, irrespective of whether the consumer
is from rural or urban area (Table 5.2). This again is an indicator of greater
responsiveness of the DISCOMs in attending to consumer complaints as far as
the grievance relates to the functioning of meters. 5.13 Payment for Repairing
the Meters: As per rules, if the officially supplied meter goes out of order due
to some inherent defect, it will be replaced/repaired without any charge from
the consumers. But if the consumer damages the same, a penalty has to be paid
by the consumer. It is observed that in the pre reform period the payment
made by the consumers, on an average, towards repairing/replacing the meter
was higher when compared to the amount of payment made during reform
period (Table 5.2). This is possibly an indirect corroboration of the idea that
perhaps during the pre reform period more meters were damaged by the
households (either by tampering or any other way) for which they had to pay
very high price towards repairing/replacing the meters. During the reform
period the payment made by the households has significantly reduced. It is
likely that the vigilance system instituted by the DISCOMs in the reform period has
been largely effective in reducing the incidence of tampering/damage of the meters
by domestic consumers in both rural and urban areas.
234
Table 5.2: Metering of Households in Rural and Urban areas
Figures in % of Responding Households
Rural Urban Total Indicators related to metering Pre-Reform Reform Pre-Reform Reform Pre-Reform Reform
1. Meter Connection CMDR Study (2003) Metered 83 84.2 97.6 97.9 Un metered 17 15.8 2.4 2.1 9.5 Total 100 100 100 100 Xavier Study (un metered households - 1996) NA 19 2. Working of Meters CMDR Study Working 87.2 95.3 96.1 97.7 Not Working 12.8 4.7 3.9 2.3 3.2 Total 100 100 100 100 Xavier Study (meters not working) NA NA 25 3. Frequency in Meter Reading CMDR Study (2003) Irregular 18.6 13.5 6.6 4.5 7.7 Monthly 30.3 9.5 44.3 66.2 Every 2 months 47.9 74.3 48.9 29.3 More than 2 months 3.2 2.7 0.2 - Total 100 100 100 100 Xavier Study (Irregular Meter Reading)- 1996 NA NA 26 4. Complaint lodged by consumers in case of meter not working CMDR Study (2003) Lodged 17.7 2.4 5.1 4.3 Not lodged 82.3 97.6 94.9 95.6 Total 100 100 100 100 Xavier Study (1996) Not available 5. Time taken for repairing the meter (in days) 29 17 25 15 6. Payment made by the consumers to repair the meter (in Rs.) 63.77 9.15 85.68 18.64
235
Uses of Electricity
5.14 Type of Use: The domestic consumers use electricity largely for the
purposes of lighting, cooking, washing, entertainment, refrigeration,
education, health and hygiene, etc. For the sample households it is observed
that during the reform period there has been a definite shift in the pattern of
use of electricity in case of both rural and urban area consumer households.
While the traditional use of electrical appliances for lighting and cooking
purposes appears to have declined (possibly due to greater economy of use
and better availability of alternative sources of energy, such as LPG), there is
relatively greater reporting of the application of electricity for non-
conventional purposes like domestic chores, education, entertainment,
health and hygiene among both rural and urban area consumers, and
more so in the case of the latter (Table5.3).
Table 5.3: Uses of Electricity by Households in Rural and Urban Areas Figures in % of total sample householdsRural Urban
Type of Use Pre Reform
Period Reform Period
Pre Reform Period
Reform Period
Lighting 39.97 32.54 28.99 17.36 Cooking 13.09 6.1 10.88 5.76 Washing Cloth 0.46 0.56 3.37 6.76 Entertainment 16.32 20.04 16.67 15.61 *Other domestic chores 28.35 35.21 30.8 39.34 **Any other use 1.81 5.55 9.29 15.17 Total 100 100 100 100 * Electrical Appliances, e.g: Grinder, Iron, Fan, Refrigerator etc. **Education, Health & Hygiene, Income Generating activities
5.15 Economy in Use: It is assumed that reform would induce economy in
the use of electricity through the rationalization of electricity tariffs. From the
field survey data it is found that more than 90 % (not shown in the table) of
the sample households (rural and urban) have reported practicing economy in
the use of electricity at their home in both pre reform and reform periods. It is
found that the women members of the household are in general more
conscious about the economy in use of electricity. Compared to about 60 %
236
women in the rural areas and 70 % women in the urban areas that are found in
the pre reform period to be more conscious about economy measures in the
use of electricity, these percentages has increased significantly in the reform
period as more than 70 % women in rural and 80 - 90 % women in urban
areas are found to be practicing economy measures (Table 5.4). This
gender aspect about the consumers’ response to the power sector reform
needs to be noted as this brings out the crucial role that women can play in
matters of socio economic importance to the family and the economy as a
whole.
Table 5.4: Economy in use of electricity by members of the household Figures in % of total sample households
Rural Urban
Members of the Household
Pre Reform Period Reform Period
Pre Reform Period Reform Period
Women 62.72 70.55 73.31 89.78 Men 27.65 22.78 20.75 7.3 Old People 1.75 1.67 1.82 0.73 Children 3.61 0.56 1.09 0.73 Every one 4.27 4.44 3.03 1.46 Total 100 100 100 100
5.16 Reasons for economy in use: The information gathered from the
households reveals that when asked to prioritize the reasons for practicing
economy measures in the use of electricity, 70 to more than 80 % of the
sample households give minimization of the electricity bill as the most
important factor. This evidence of a price impact is in accordance with the
expectation from reform. Energy saving gets the second priority among the
reasons stated by the households (Table 5.5). Chart 5.2 and 5.3 provide a
clearer picture of the reasons for the economy in use of electricity.
237
Table 5.5: Reasons for Economy in Use by Households in reform period and
Figures in % of responding households
Reasons Rural Urban To minimize the bill 76.7 86.9 Installation of china meters 1.7 0.7 Energy saving 21.7 12.4
Reasons for Economy in use of Electricity Chart 5.2 Chart 5.2 A
Rural
77
2
22
To minimize the bill Installation of China metersEnergy saving
Urban
87
1 12
To minimize the bill Installation of China meters Energy saving
238
Electricity Tariff
5.17 Change in Cost/Tariff of Electricity: The overwhelming majority of
household consumers in rural as well as urban areas perceives that price of
power has increased in the reform period. This is to be expected considering
the frequent hikes in tariff carried out in the reform period. What is
interesting, however, is that about 11 % rural and 4 % urban households
perceive a decrease in the price of power in the reform period (Table-5.6). It
is likely that these households are referring to the real price of electricity,
which after adjusting for the inflation rate during the period, is likely to
have come out as lower for the reform period in the perceptions of some
of the consumers. This is a possibility that also came out strongly in some of
the discussions with key informants from different user groups as well as
from the OERC functionaries.
Table 5.6: Perceived changes in electricity tariff in reform period
Perceived Change in Electricity Tariff Rural Urban
Increased 88.5 95.9
Decreased 11.5 4.1
Total 100.0 100.0
Figures in % of responding households
5.18 Collusion: An attempt has been made on the basis of the reported
information to relate the extent of use of electricity by a household
with the amount of payment for the same. It is assumed that the
number of power points in the households is a more accurate indicator
of actual/potential consumption of electricity than the units billed,
since there is a chance that tampering of meters by the consuming
household contaminates the latter figure. The expectation is that
239
households with 15 ampere points would be at the high end of
domestic users and accordingly would be paying on an average higher
electricity charges. It is rather interesting to notice that the rural
households using 15 ampere points reported on an average lesser
amounts of electricity charges than the households using 5 ampere
points (not shown in Table). While it is possible that the high end
users in the rural domestic segment are more economical in their
actual use of electricity, nevertheless the possibility of collusion,
either in meter reading or in billing, cannot be entirely ruled out.
Box-5.1 gives the case of one of the sample villages where such
collusive activity still exists despite reform.
Billing/Payment for the use of electricity
5.19 Frequency of Billing: Though there has been significant improvement
in the billing procedure in the reform period, still 2 to 5 % of the rural sample
households reported about no billing (Table-5.7). There is a significant shift
in the billing system from bi-monthly in the pre reform period to monthly in
the reform period in urban areas. The billing system in rural areas has largely
remained bi monthly in both pre reform and reform periods, but more so in
the latter period.
Box 5.1: Collusion: Who will stop? In one of the sample villages it was found during the household survey that the
meters of most of the houses are stopped for 3/4th of the month and it is operated only towards that part of the month when the meter reader is expected to visit. On
enquiry it was found that the lineman of the erstwhile OSEB used to help the villagers to do the tampering by taking some monetary or non-monetary benefits
(example: free rental house for the line man in exchange for providing free electricity to the owner). Over time, most of the households have learnt to do the
tampering by themselves. The meter reader takes down the deflated reading as the correct reading and the households clear the grossly underestimated dues in time.
240
Table 5.7: Billing frequency as reported by the households Figures in % of responding households
Rural Urban Total
Billing Frequency Pre-reform (Xavier Study)
Reform (CMDR Study)
Pre-reform (Xavier Study)
Reform (CMDR Study)
Pre-reform (Xavier Study)
Reform (CMDR Study)
No Billing 2.86 5.1 Nil 2.3 1.4 1.3 Monthly 16.4 14.1 26.4 68.5 21.5 43.4 Bimonthly 40.0 72.4 46.6 24.1 43.4 45.1 More than Bimonthly 40.7 8.4 27.0 5.1 33.7 10.2 Total 100.0 100 100.0 100 100.0 100.0
5.20 Regularity in Billing: One of the basic objectives of reform is to reduce
the irregularity in the billing. There is a significant achievement of the reform
process in this respect as the irregularity has declined from 50 per cent in the
pre reform period to 11 per cent during the reform period (Table 5.8). Across
rural and urban areas it was found that the irregularity in billing had declined
significantly in urban areas while it remained more or less constant in rural
areas over the years.
Table 5.8: Irregularity in Billing (% of households)
Research Studies Region Pre-reform Reform Rural 18.2 17.0 Urban 21.3 9.7 CMDR Study
(2003) Total - 11.2
Xavier Study (1996) Total 50.3
241
5.21 Billing efficiency and consumer perceptions: In order to determine
the efficiency in the reform period billing system, the perceptions of the
people on 5 indicators were collected: correctness in billing, clarity in
billing, ease of payment, timely complaint redressal and satisfactory
solution of the complaint. Table-5.9 gives the extent of incidence of the
perceptions among the households according to 3 possibilities: ‘improved’,
‘deteriorated’ and ‘no change’. The perceptions of people are found to be the
most favourable regarding the payment procedure of the bill. Nearly 74 %
rural and 88 % urban households feel that there has been greater ease of
payment in the reform period. Correctness and clarity in billing comes next
in the ranking and get equal rank in both rural and urban areas, with the
backing of a little more than half of the sample households in both areas.
However, almost 2/3rd (72 %) of the sample households in rural areas
reported that they do not get satisfactory solution to their complaints. In
comparison, about 44 percent of the urban households reported their
satisfaction from the solution to their complaint. It is worth noting that only a
small minority (about 12%) of urban consumers feel that there has been
deterioration with regards to getting a satisfactory solution to their billing
complaints. What comes out as certain is that customer care and grievance
redressal by the DISCOMs in case of complaints related to billing are
perceived to be the least satisfactory by the majority of households in rural
areas. This may be contrasted with the earlier discussion of people’s largely
favourable perceptions about the DISCOMs’ handling of metering-related
complaints. It appears that the reform period system for customer care and
grievance redressal is yet to be developed properly for the different areas of
interface between the consumers and suppliers, particularly in the rural
areas.
242
Table 5.9: Billing efficiency in rural and urban areas
Figures in % of responding householdsIndicators of billing efficiency
5.22 Non-payment of bills and disconnection of electricity: Under the new
system it is expected that if there were no payment of the bills, the electricity
connection would be withdrawn. From the field survey it is found that there is
not much difference between rural and urban areas in respect of disconnection
of power due to non-payment of bills. About 9 % of the rural households and
7 % of the households in urban areas reported that their connection was
withdrawn due to non-payment of bills. It seems that the households have
become conscious about the payment of bills in the reform period.
Problems in the Supply of Power
5.23 Power supply and consumers’ perceptions: The problems related
to power supply may be classified as technical and non-technical. The
technical problems are mainly power failures, voltage fluctuation, scheduled
and unscheduled power cuts. The non-technical problems are mainly related
to metering, billing, theft of power, etc. A comparative assessment of rural
and urban consumers’ perceptions indicates that the overall situation of
power supply in urban areas is better than in rural areas during the
243
reform period. More than 80 % to about 90 % of the urban households feel
favorably about the power supply scenario in the reform period, while a
similar sentiment finds expression from 55 % to slightly more than 60 % of
the rural consumers (Table 5.10).
Table 5.10: Consumer perceptions on power supply in the reform period Figures in % of responding households
Rural Urban Problems of power supply I D NC I D NC
Power Failure 59 17 24 82 8 10 Voltage Fluctuation 55 11 34 83 7 11 Un-notified Power cut 61 14 25 90 4 6 Frequent power cut 56 17 27 88 5 7 I=Improved, D=deteriorated, NC= No change
5.23 Power Failure: Power failure is different from power cut. Power
failure occurs due to the problems that are beyond the control of the
supply authorities, e.g. natural calamities (cyclone, flood etc.), over
loading from excess consumption of electricity, theft of electricity, etc.
During the reform period, as judged from the sample households
reporting its incidence, power failure of greater hourly duration
appears to have declined in both rural and urban areas (Table-5.11).
This improvement is more marked in case of the urban areas sampled.
Significantly, about 45% of the urban consumers say that they do not
suffer from power failure at all as against 5% in the pre-reform period
(Xavier Study). Only 13 % consumers in rural areas do not suffer from
power failure during reform period while the same was zero percent
(Xavier Study) during pre-reform period. Though the power supply
situation has improved during the reform period to a great extent,
the incidence of improvement is found to be higher in urban areas
than in the rural areas.
244
Table 5.11: Duration of Power Failure in pre-reform and reform periods (Figures in % of sample households reporting for different durations of power failure)
Rural Urban Duration of power
failure Pre Reform Period
Reform period
Pre Reform Period Reform period
CMDR Study, 2003 < 1 hour 18.3 30.4 36.1 35.5 1 - 3 hours 35.4 26.5 32.5 10.5 > 3 hours 46.3 30.5 16.2 9.2 No Power Failure - 12.6 - 44.8 Xavier Study, 1996 No Power Failure 0 5
5.25 Power theft, breakdown of transformers, etc: The major contributing
factors for power failure, as gathered from the consumers themselves, are
frequent theft of power, overloading and poor maintenance of transformers,
falling of trees, etc in rural areas and over loading, theft in urban areas,
besides frequent natural calamities common to the state. Despite the serious
steps taken by the DISCOMs to control the misuse (theft) of power, still
the practice appears to continue on a significant scale in both rural and
urban areas of the State (Box 5.2). The field survey conducted by CMDR
generated a lot of anecdotal evidence about incidents relating to theft of
conductors, the practice of hooking and breakdown of distribution
transformers during both the pre-reform and reform periods. By and large, the
respondents were of the opinion that there has been a significant decline in the
number of incidents involving theft/misuse of power. This general perception
gathered from the field survey matches with the trends observed in the data
obtained from secondary sources. Table-5.11a presents the data relating to the
number of hooking cases detected, length of conductor stolen, number of
transformers burnt, etc. as provided by the DISCOMs to the OERC.
245
5.26 Power cut: Power cut is made deliberately by the authorities when
there is a shortage of supplies or need for repair and maintenance of
transformers, etc. As perceived by the sample households, there appears to
have occurred a marked decline in the duration of power cuts during
summer as well as rest of the year in the reform period for both rural
Performance Indicators 2000-01 2001-02 2002-03 2003-04Number of transformers burnt 6341 6741 4936 4501Cost involved (Rs. Crores) 17.85 18.95 13.96 4.75Length of conductor stolen (Km) 1659.29 1760.26 968.05 423.61Cost involved (Rs. Crores) 4.071 4.351 1.406 0.563Number of hooks detected 83484 68192 309324 126383Number of hooks repeated out of hooks detected 0 0 21701 156Number of connections regularised 29345 75097 109479 54090Number of disconnections made 77277 86572 216860 406702
Table-5.11a: Performance of DISTCOMs in checking theft/misuse of power in Orissa during the reform period
Source: OERC's Review of Performance of DISTCOMs based on data submitted by the companies to the Commission
Box 5.2: THEFT OF POWER IN THE CAPITAL!
About 40-50 unauthorized temporarily constructed houses in the premises of an apex institution in the capital city of Orissa are found to have taken electrical connection through ‘hooking’ from the main lines of electricity provided to the staff quarters. Since the last 10 to 15 years, these households have been using power not only for lighting purposes but also for TV, cooking heaters, electrical grinders and other appliances, etc. Some of them have temporary shops in which they use electricity. The authorities of the Institution have attempted several times to disconnect the illegal connections of the employees but failed. Whenever the authority has taken any initiative towards disconnection, these people have resorted to threatening the authority and other bullying tactic. Consequently, the practice of theft continues and its effect is felt by the consumers residing in the staff quarters who suffer from poor quality of power supply due to over loading. The financial burden of the institution also increases. There is a main meter for the institution for the payment of electricity cost and the illegal users are using the electricity (free of cost) at the cost of the institution.
The theft of power is still continuing almost everywhere which has been stated
by various key informants i.e. Sarapanch (Nayagarh), Sarapanch (Khurda), Councillor (Bhadrak Municipality), Field Officer (Gramyabank, Khurda), Executive officer(Keonjhar,NESCO), Advocate (Bar Association,Nayagarh), OIC Town Police
246
and urban areas. This has been a significant achievement of reform and is
commonly acknowledged. For the reform period, the most common duration
of power cut during summer as well as rest of the year is 1 to 3 hours daily in
rural areas and less than 1 hour in urban areas (Table-5.12).
Table 5.12: Duration of power cut during pre reform and reform periods (Figures in % of sample households reporting for different durations of power cut)
5.30 Difficulties caused on account of Voltage Problem: Comparatively a
greater proportion (51.4%) of urban consumers than those in rural
areas (37.1%) reported the absence of any type of voltage-related
difficulties in the reform period (Table 5.15). While looking at the
various types of difficulties reported by the consumers on account of
voltage fluctuation, the pattern comes out to be similar in both rural
and urban areas, with the majority complaint being linked to low
voltage in the evening time. The damage to electrical appliances due to
high voltage problem declined significantly from 23 percent in the pre-
reform period to 6 percent during the reform period both in rural and
urban areas. This of course is a healthy sign of the reform process.
Table 5.15: Difficulties reported due to voltage problem in the reform period Figures in % of responding households
Type of difficulty reported by the household Rural Urban Total CMDR Study (2003) Tube lights not working in the evening 42.2 32.0 33.2 Electrical appliances not working at night 11.9 9.1 10.9 Damage to electrical appliances 6.9 5.2 5.9 Accidents caused by high voltage 1.9 2.3 2.1 No problem 37.1 51.4 47.9 Total 100 100 100 Xavier Study (1996) Damage caused to electrical appliances NA NA 22.9
5.31 Management of voltage problem: It seems that the non-use of
electrical equipment in times of voltage fluctuation is the most
common strategy among the rural and urban consumers. However,
during the reform period the use of stabilizer has been reduced to a
large extent and the proportion of consumers not using any type of
protective measure has increased, particularly in rural areas. This gives
a clear impression that there has occurred significant
improvement in the voltage profile during the reform period
(Table 5.16).
249
Table 5.16: Protective measures by households in case of voltage problem Figures in % of responding households
Rural Urban Total
Items Pre
Reform Period
Reform Period
Pre Reform Period
Reform Period
Pre Reform Period (Xavier Study)
Reform Period
(CMDR Study)
Use of Stabilizer 42.2 12.9 27.6 18.6 24 16.0 Use of Capacitor 1.4 1.3 1.6 2.9 NA 1.9 Use of alternative sources of energy 3.4 5.5 6.0 2.4 1 4.3 Non-use of equipment 48.2 48.2 46.6 55.4 19 51.1 No protective measure 4.8 32.0 18.1 20.6 56 26.7 Total 100.0 100.0 100.0 100.0 100.0 100.0
5.32 Electrical accidents: Information about electrical accidents during the
reform period is obtained from the OERC, which has been continuously
monitoring the performance of DISCOMs. Table-5.16a gives the data about
electrical accidents, both fatal and non-fatal, throughout the state. It is a
matter of concern that there is a significantly higher incidence of fatal
electrical accidents to humans in 2003-04 as compared to the previous year.
ALL ORISSATable-5.16a: Incidence of Electrical Accidents in Orissa during 2002-03 & 2003-04
Source: OERC, Bhubaneswar
Electrical accidents
Fatal
Non-Fatal
CESCO NESCO SOUTHCO WESCO
250
V.4 Socio economic Impact of Power Sector Reform: Impact on
Education
Direct impacts
5.33 Study hour duration: The supply of electricity nowadays affects to a
great extent the education of children. If the supply of electricity is interrupted
frequently, particularly during the study hours of children (early morning and
evening) and during examination days, it tends to have a significantly adverse
impact on the education of children. This may be considered as a direct
impact of power sector reform on education. So far as the effect of power
supply on the duration of children’s study hours is concerned, the
majority perception points to an improvement in the current situation
over the pre reform period situation. The perceived improvement
appears to be quite independent of the social status of the sample
households and is relatively more widespread in urban areas than in
rural areas. Table 5.17 provides this information. At the same time, it needs
to be kept in mind that a significant proportion (25 to 36 %) of households
feels that there is still no perceptible change in the situation relating to the
quality of power supply during study hours as compared to the earlier pre
reform years.
5.34 Access to information and e-education: The supply of power to an
area brings with it the potential to increase consumers’ access to e-education
and e-information. This helps in particular the children to increase their
educational standard to great extent. The overwhelming majority of rural
households sampled perceive no change in the situation relating to access
to computer and Internet in the reform period (Table-5.17). On the other
hand, a significant % of urban households, particularly from the
privileged category, do feel that there has been improved access to e-
education in the reform period.
251
Indirect Impacts
5.35 Educational performance of children: In a general way, the standard
of educational performance of children is likely to be closely linked with the
duration of study hour. If the study hour is affected on account of poor power
supply, the performance level is likely to deteriorate. The power sector reform
in this case affects education indirectly. A majority of sample households
(over 60 % in rural areas and about 50 % in urban areas) failed to
perceive any type of impact on the educational performance of their
children resulting from the changed power supply situation in the reform
period. However, the urban bias of the reform impact appears again in
the form of a relatively greater percentage of urban households opining
that compared to the pre-reform period the reform-period educational
performance of children has improved.
5.36 Attendance of evening classes (Girl/female children): Generally
students attend the evening classes (either tutorial or coaching, dance, music,
etc) because the regular schooling hours is during the daytime. In a situation
of regular and frequent interruptions in power supply during evening hours,
parents would naturally hesitate to send their children to such classes. It is
found that irrespective of the social category, majority of the parents in
urban areas (more than 50% to 76 %) do perceive the current situation
conducive for allowing their daughters to attend evening classes. This
feeling is found to be much less spread in rural areas. Also a significant
proportion of less privileged caste households particularly in rural areas does
not feel any change in the attendance of evening classes by girl children
during the reform process. However, it should be kept in mind that there
might be limited opportunities for children in rural Orissa to avail themselves
of facilities offered by evening classes.
252
Table-5.17: Consumer perceptions about reform’s impact on education of children
Figures in % of responding households Rural Urban
Privileged Less Privileged Privileged Less PrivilegedImpact Indicators
I D NC I D NC I D NC I D NC Duration of Study Hours (early morning & evening hours)
47 18 36 47 17 36 58 13 28 58 17 25
Access to information and e-education (TV, Computer & Internet)
10 0 90 4 0 96 45 5 50 32 8 60
Educational performance of children
28 9 63 26 14 60 37 13 49 35 15 50
Conduciveness of situation for girls to attend evening classes
35 16 49 26 23 52 76 1 23 51 3 46
Note: (i) I = Improved; D = Deteriorated; NC = No Change (ii) Figures may not add up horizontally to 100 for different social categories because of rounding up V.5 Socio Economic Impact of Power Sector Reform: Impact on
Health
Direct impact
5.37 Diagnostic tests: Electricity has a crucial role to play in the
provisioning of health care services. The machines/equipment used for
different types of diagnostic tests and operations depend largely on
continuous and uninterrupted power supply, which is a basic objective of
power sector reform. More than 50 % households in rural and more than
80 % in urban areas are reported to have perceived that there is an
improvement in the situation relating to the timely conduct of diagnostic
tests of different types in the reform period (Table 5.18).
5.38 Health care of children and sick: Not only different diagnostic tests
but the health care of children and sick persons in the households are also
253
affected by the quality of power supply. (For instance, the sick persons, old
persons and persons with hypertension etc require continuous fans and AC
during summer, which require un-interrupted power supply.) It is found that
about 50 to 57 % of households in the total sample perceive that there has
been improvement in the health care status in households due to
improvement in power supply in the reform period. At the same time,
more than 40 % of the households do not feel any change in the situation.
Across social categories, it is observed that a relatively larger percentage of
privileged group households give a favorable opinion about the impact of
reform.
Indirect Impact
5.39 Health status of women: Women in general, and working women and
rural women in particular, get very little time to take care of their own health.
The use of electrical appliances in domestic chores is expected to reduce
drudgery and improve the health status of women along with the overall
quality of life enjoyed by them. Since the use of such appliances is linked to
the quality of power supply, the issue of the impact of reform in the power
sector again becomes relevant. Barring the urban households belonging to the
privileged category, the majority perception in all other categories is that there
has been no change in the health status of female members in the household
during the reform period. Nevertheless, it is encouraging to note that close
to one-third of sample households cutting across social categories as well
as the rural-urban division provides the perception that points to a likely
positive impact of reform on health status of women.
254
Table-5.18: Consumer perceptions about reform’s impact on health services and health care in households (Figures in % of responding households)
Rural Urban
Privileged Less Privileged Privileged Less PrivilegedImpact Indicators
Note: (i) I = Improved; D = Deteriorated; NC = No Change
V.6 Socio Economic Impact of Power Sector Reform: Impact on
Women
Direct impact
5.40 Time saved from domestic work: About 45 % (less privileged) to 50 %
(privileged) of the households in rural and 52 % (less privileged) to 63 %
(privileged) households in urban areas are reported to have perceived that
their time used for domestic work has reduced during the reform period as
compared to the pre reform period (Table 5.19). It appears that the reduced
drudgery of work burden for women in the reform period has a larger
incidence among urban households and those belonging to the privileged
social category.
5.41 Leisure time: About 55 to 67 % households in rural and 66 to 69 %
households in urban areas have reported that their leisure time has increased
during the reform period as compared to 10 years back. The availability of
leisure time appears to be more among women belonging to the
privileged category households in urban areas than that in rural areas
and women in less privileged households.
255
Indirect impact
5.42 Productive utilization of extra time: It is observed that 90 % to 93 %
of rural households and 66 % to 73 % urban households are not able to
productively utilize the extra time gained on account of reduced work
burden on the domestic front. It is possible that there may be a dearth
of opportunities for women to use their time gained for productive
activities, particularly in the rural areas (Table 5.19).
Table-5.19: Consumer perceptions about reform’s impact on women (Figures in % of responding households)
Rural Urban
Privileged Less Privileged Privileged Less PrivilegedImpact Indicators
I D NC I D N
C I D NC I D NC
Time spent for domestic work 20 50 30 24 45 31 16 63 21 18 52 30
Leisure time 57 12 31 55 13 32 69 15 16 66 16 18 Time used for skill building 9 1 90 6 1 93 32 2 66 26 1 73
Time used for income generation 11 1 88 10 1 89 16 4 80 15 4 81
Safety and security of women 20 17 63 18 23 59 32 33 35 35 28 37
Note: (i) I = Improved; D = Deteriorated; NC = No Change (ii) Figures may not add up horizontally to 100 for different social categories because of rounding up
5.43 Safety and Security: More than 50 % (59 to 63 %) of households in
rural areas and 35-40 % households in urban areas reported that there is no
change in so far as the security of women is concerned during reform period.
In fact, among the urban households sampled, the opinion about insecurity of
women is almost equally divided as to whether there has been improvement,
deterioration or no change in the situation in the reform period.
256
V.7 Impact of power sector reform on livelihood
5.44 Employment: Improved power supply in the reform period is
supposed to generate rural employment in the cottage, tiny and small-scale
industries, such as flour mills, rice mills, textile units, appliqué and other craft
centres, tailoring units, etc that are located in villages and their vicinity. In
both rural and urban areas, households belonging to the privileged category
generate a majority (> 50 %) opinion that there has been increased
employment of male workers in the cottage and small-scale industry sector
during the reform period (Table-5.20). The same opinion comes from the
perceptions of a significant percentage of the sample households belonging to
the less privileged category in both rural and urban areas.
Table 5.20: Employment in cottage, tiny and small scale industries Less Privileged Privileged
V.8. Impact of Power Sector Reform on Consumption Pattern of the
households
5.45 In view of the hike in tariff, it is expected that there may be a change in
the consumption pattern of the household and due to this change, there is
possibility of foregoing some of the family expenditures The majority of the
perceptions in respect of this aspect indicates that there is an increase in the
household spending on consumption but no expenditure is postponed due to
the hiked rate of tariff of electricity (Table 5.21). This provides a clear idea
257
that in view of the improved power supply the consumers are willing to pay
for electricity uses without distorting their consumption pattern.
V.9 Impact of Power Sector Reform on Agriculture
5.46 Agricultural productivity: The majority of rural households surveyed
(nearly 85 %) perceived no change in the productivity of agriculture during
the reform period as compared to its pre reform position. Considering the very
low consumption of electricity in agriculture in Orissa, it is almost a foregone
conclusion that there is very limited scope for power sector reform to make its
impact significantly felt on the productivity level.
5.47 Cold storage facility: Has the better power supply scenario in the
reform period induced addition to cold storage facility for agricultural
produce? The rural households surveyed almost near unanimous in their
opinion that there has been no change in the availability of cold storage
facility in the reform period. However, a small minority of 17 % of the
privileged urban households felt that there has been a reform-period
improvement in the storage situation in urban areas.
258
Summary statement of the perceptions of HHs on impact indicators
5.48 The perception of households (HHs) on impact indicators discussed above are summarized in Table 5.21in amore descriptive way. Table 5.21 Summary statement of the perceptions of HHs on impact indicators
Majority Perception Rural Urban
Impact Indicators Privileged Category
Less Privileged Category
Privileged Category
Less Privileged Category
Impact on Education Power Supply during Study Hours I I I I Access to Information and E-education NC NC I NC Average Per Performance Level of Children NC NC I I Attendance of evening classes by girls NC NC I I Impact on Health Timely Conduct of Diagnostic Tests I I I I Health care of sick and children I I I I Health status of Women I NC I I Impact on Women Time saving by women from Domestic work I I I I Leisure time available to women I I I I Skill-building and income generating activities NC NC NC NC Safety and Security of women NC NC NC NC Impact on Consumption Pattern Family Consumption expenditure I I I I Foregone or postponement of familyexpenditure NC NC NC NC Impact on agriculture Impact on productivity of agriculture NC NC - - Impact on storage NC NC - - Impact on Employment Employment in cottage, tiny and small scale industries Male Employment I NC I I Female Employment NC NC I NC Total NC NC I NC Impact on Income Generation Participation of family members in incomegenerating activities Male Employment I I NC I Female Employment I I I I I = Improved, NC = No Change, D=Deteriorated
259
V.10 Consumers’ Willingness to Pay at a Hiked Rate
5.49 Willingness to Pay: The present tariff rate seems to put financial
burden on the consumers to such an extent that about 73 % rural and 51 %
urban households of the total sample are not willing to pay any extra rate for
electricity over and above the present tariff. However, it is interesting to note
that with a rise in the level of education consumer’s willingness to pay
increases. It seems higher level of education and urbanization enhance the
willingness of the consumers to pay more towards electricity charges if they
are assured of better and regular supply of electricity. This can be seen from
Table 5.22.
Table 5.22: Consumer’s Willingness to Pay for Electricity at a Hiked Rate of Tariff by Levels of Education
% of Households revealing willingness to payLevels of Education Nothing 5 % more 10 % more
5.52 Impact of reform on productivity/efficiency/profitability: So far as the
impact of reform on the productivity, efficiency and profitability of the
commercial and industrial consumers is concerned, most of the sample units
reported that the promised benefit of power sector reform relating to adequate
supply of quality power is yet to reach them in a significant way. They
complain that power problems like irregularity in power supply and poor
quality of voltage still exist and continue to affect adversely the functioning of
the units. The problem is particularly severe during summer time. District
wise, the units located in the northern region (Keonjhar and Bhadrak) come
out as the worst sufferers of continuing power sector problems. At the same
time, however, there appears to be a growing realization among the sampled
units that the situation may be turning for the better.
It is significant and a cause for concern that in contrast to the generally
favourable perception of household consumers regarding the reform-
period power supply situation and also in contradiction with the
improved power supply scenario brought out by macro performance
262
indicators, there is a general feeling of discontent among the commercial
and industrial category of users about the adequate availability of quality
power, particularly among units located in the relatively backward
districts of the State.
5.53 Alternative sources of power and associated cost: Table-5.24
presents the other-than-electricity sources of power used by different
categories (connected load wise) of commercial and industrial units and the
average cost per month associated with such use. In the case of diesel
generators, larger units are seen to have a relatively lesser need to use them as
compared to the units with small loads, since the average hours of use of such
generators per month decline as one moves from units with small loads to the
more power-intensive units. This appears to be a case of the regressive
impact of power sector reform on commercial and industrial users. The
average monthly cost on this source of power is higher for larger units, but
one cannot rule out the possibility that when estimated relative to their
respective turnovers, the financial burden on the smaller units would be
disproportionately higher. Taking all units using diesel generators together,
the average monthly cost comes to Rs.5614, which is a significant amount.
For units using gas as the alternative power source, the average monthly cost
is considerably lower (Rs.745).
263
Table 5.24 a: Alternative Sources of Power / Stand by Facilities and the associated cost for commercial and industrial users of different capacity size (KW terms)
Capacity wise User Category Type of Alternatives
<=1 KW >1 KW TO <=5 KW
>5 KW TO <=10 KW
Above 10 KW Total
No.of Units 7 9 7 17 40 Avg Cost (Rs. Per month) 3078 2650 8597 6789 5614
Diesel Generator
Avg Hrs per Month 61 55 31 39 45 No.of Units 28 18 3 0 49 Avg Cost (Rs. Per month) 369 1290 733 0 745 Gas
Avg Hrs per Month 38.2 41.7 72.7 0 42.3 No.of Units 0 0 0 2 2 Avg Cost (Rs. Per month) 0 0 0 335 335 Solar
Avg Hrs per Month 0 0 0 7.5 7.5 No.of Units 25 14 3 2 44 Avg Cost (Rs. Per month) 757 2005 1133 500 1141 Others
Avg Hrs per Month 40.0 46.3 8.7 7.0 37.1 No.of Units 100 59 28 34 222 Avg Cost (Rs. Per month) 867 1773 5060 5421 2268 Total
Avg Hrs per Month 42.2 45.6 37.8 31.2 40.9 5.54 Customer care and grievance redressal: With the exception of the
units coming under CESCO, the majority of the consumer units served by the
other 3 DISCOMs complain of poor customer care and un-satisfactory
solution to grievances. Again, the units coming under NESCO turn out to be
the worst sufferers. Most of the complaints of the industrial units relate to the
improper functioning of meters and the incorrect reading of meters.
264
CONCLUSION
SUMMARY
In the first two chapters of my thesis, I have discussed the theoretical
framework of reforms and its necessity for timely adoption. The main aim of
this thesis is to bring out an ideal framework for all those state utilities
aspiring to unbundle their vertically integrated utility. The earlier Electricity
Act. 1909 failed to deliver the results in terms of their financial viability.
Power sector investment has always been dependent on budgetary support and
external borrowings. Electricity Act. 2003 was enacted with a view to de-
regularizing the vertically integrated utilities, opening the field of generation
and distribution to private players and introduction of power trading system.
To achieve a robust GDP growth of 8 per cent per annum, the growth rate of
power sector is prescribed to grow over 10 per cent per annum. Initiatives
were taken in the chief minister’s conference on Common Minimum National
Action Plan for Power (CMNPP) convened by Prime Minister in 1996 which
ushered in the comprehensive reforms program for power sector including
reforms in distribution sector. The results were visible in the Ninth Plan (1997
– 02) with an addition of 19,015 MW from the preceding plan period. The
reform policy also allowed private sector to set up companies with 100%
foreign participation and with a maximum 4:1 debt equity ratio. The return on
foreign equity was protected in foreign currency and a number of tax
concessions were extended to woo the investors.
I have analyzed the growth of power sector in detail. The way the power
sector has performed in the past several years across several plan periods has
been supplemented with necessary tables and graphs. In spite of many
rewarding initiatives the participation from the private players has been
considerably low as compared to public sector participation. One of the
reasons may be attributed to the lack of comprehensive fuel supply agreement
265
(FSA). The IPPs insist that the penalty for supply interruptions should cover
the loss of revenue (Fixed cost component of tariff) attributable to the default
in fuel supply. Penalty could be on the basis of the additional cost incurred in
procuring fuel from alternate sources but railways contend that it should be on
the value of the fuel not on supplied.
In the subsequent chapter, I have discussed the success of global players in
power sector reforms which includes nations falling in European Union, USA
and Latin American countries and few other successful reform programs
which acted as the precursor to India’s reforms initiatives. During my course
of research the California power crisis happened and I’ve discussed it at
length. In India, Orissa became the pioneer state to adopt the reform program
way back in 1996 which had set a mile stone in the field of power generation
and distribution. Other states like Andhra Pradesh and Delhi soon started the
calibrated reforms initiatives after examining the fault line in the Orissa
model of power sector reforms. During my analysis I found to conclude that
the reform processes which were extremely successful abroad is not viable
because of several underlying reasons like: High AT&C losses, concentric
area development, ability to pay, willingness to pay and above all the
excessive political interference from the successive state governments. Power
has always been subsidised by several state governments but government fails
to make the payment to the state run SEBs.
Chapter IV deals with the enactment of a new Electricity Act. 2003 and
implementation of Montek Singh Ahluwalia Report recommended the ways
and means for one time settlement of outstanding dues of SEBs to CPSUs.
The World Bank’s model on structural reforms in power sector has been
discussed in detail. It is the prerogative of the different state governments to
adopt the most suitable one as per their viability and need. This chapter also
traces the changes in the legal provisions governing electricity power tariffs
and discusses the processes and methodologies adopted over time for tariff
setting till the formulation under Section 178 of the Electricity Act, 2003,
266
which may be called the Central Electricity Regulatory Commission (Terms
and Conditions of Tariff) Regulations, 2004. A broad comparison has been
made over the existing tariff structure vis-a-vis availability based tariff
(ABT). An in-depth analysis has been made to find out the mechanism of
calculation of cross-subsidy put forth by different agencies working in this
area. The financial crisis besetting the Indian power sector has always been an
issue of great concern for the planners and experts but evolving an audit i.e.
Energy audit mechanism was never introduced to the system because it may
lead to some path breaking findings such as excessive estimation of T&D
losses, High Transmission (11KV & above) losses, unwillingness of utilities
for effective metering, indication of significant commercial losses in HT
level, etc.
Chapter V deals with the appraisal of Orissa’s reforms experience and its
failure to become a financially profitable organization as against predicted by
consultants who drew up this pragmatic reform model against a staggering
Rs.306.422 crores as consultancy fees from Britain's Department for
International Development (DFID). Consultants includes KPMG – Pre-reform
Consultancy, Credit Suisse First Boston – privatization consultancy, Merz
McLellan & Seaboard International – Project management consultancy, Price
Waterhouse Coopers – other consultancy, has raised many unanswered
questions on the efficacy and practicability of their consultancy. A detailed
study has been made after examining its fault lines, and suggestions have
been placed to improve its performance. During the course of my research,
GRIDCO witnessed its turnaround in the A.Y 2003 – 04 and predictions are
strong that complete turnaround after writing off previous losses will be
possible in the year 2008 – 09. A complete case study has been prepared in
this regard and it has received appreciation from several quarters after its
publication in the Journal of Power Professionals “HORIZON”, Oct – Dec,
2005 Vol. 7 No.1. An attempt has been made to compare the financial
performance of Orissa with Andhra Pradesh, though AP started its reforms
267
process much later than the state of Orissa. Orissa has become a model state
among its counterparts as far as power sector reform is concerned and its
successful turnaround under Mr. Suresh Chandra Mahapatra, IAS the then
CMD of GRIDCO has again reaffirmed the faith in a person with dedication
towards duty and transparent functioning.
In the concluding chapter “Socio economic impact assessment of power
sector reforms – An impact analysis” an attempt has been made to develop a
general micro level perspective about the effect of reform on different user
categories on the basis of various impact parameters. The data collected from
the users is both factual and perception-based. The instrument of data
collection consists of a structured questionnaire for households, Focus Group
Discussion dairies, an open ended checklist for commercial and small
industrial users, a list of issues in connection with the power sector for being
discussed with the principal informants and also informal discussions. The
study on Socio economic Impact of Power Sector Reform was conducted in
eight selected districts of Orissa, with 2 districts sampled from each of the 4
geographical zones (North, South, East and West) of the State. The summary
of findings has been quite convincing which leaves scope for further study.
One cannot generalize from this specific focused research. There are only
tentative formulations and proposals for further investigation. These areas of
potential research have been illustrated after careful consideration.
In the course of my research there have been many changes in the regulatory
aspect and it has been done with a singular objective of facilitating the
reforms process. I’ve a strong belief that with the growth of power, India will
become resurgent India and the coming decade will be the decade for growth
of “Power” in India.
268
FINDINGS
1. The central government started spending more money on power in
comparison to previous years and a substantial hike in central outlay in
ninth plan can be seen.
2. Actual capacity addition fell seriously short of target in both Eighth
and Ninth Plan.
3. Private sector participation in capacity addition was worse among these
three. In eighth plan actual capacity addition almost 50% of the target
set but in ninth plan it was even less than 30% of the target set.
4. Capacity addition of hydro power in state sector was steadily
increasing and phenomenal rise can be observed in ninth plan.
5. Actual capacity addition fell seriously short of target both in Eighth
and Ninth Plan periods.
6. Establishment of Central Electricity Regulatory Commission (CERC)
and the State Electricity Regulatory Commission (SERC) in each state
in time bound manner.
7. Rationalization of retail tariff, under which no sector shall pay less
than 50 per cent of the average cost of supply and tariffs for agriculture
should not be less than fifty paise per unit and should be increased to
50 per cent of the average cost in not more than three years.
8. Finalization of National Energy Policy.
9. Gradual private participation in distribution has already taken place,
initially in one or two viable geographical areas were covered both
urban and rural areas and extends to other parts of state gradually.
10. Restructuring & corporatisation of SEBs and make them function on
commercial basis.
11. Improvement in plant load factor (PLF).
12. Compulsory metering of all sub-stations and all major feeders, all new
connections and all connections including agricultural connections has
metered by the year 2002 as per the proposal.
13. Compulsory energy audit for all consumers.
269
14. Evolvement of a national policy on hydro power development
15. Encouragement for co-generation and captive generation.
The above findings were possible because of the success of international
experience in distribution reforms, namely UK, USA, and Latin American
countries like Chile, Argentina, Peru, Columbia, EU Nations and Australia.
Their reform programs were based on country’s governmental structure,
demographics, socio-economic and political environments and resource
availability. But it was amply clear those countries undertaken restructuring
the electric utilities was for:
• Improving the efficiency,
• Reducing tariff
• To provide better quality of service to consumers, through
competition and consumers would gain from efficiency gains in
generation, transmission and distribution.
Restructuring also led to the removal of certain problems like load shedding,
blackouts, and high degree of T&D losses, which includes theft of energy, etc.
Basing on these experiences and taking world bank model for structural
reforms on power sector India appears to be relying on the single buyer model
for now (making the role of TRANSCO special – monopoly seller to
DISTCOs, and monopsony buyer from the GENCOs). While there is
recognition of the pros and cons of a single-buyer model, the government
hopes this is a transitional solution, leading to open access to the wires
(Deepak Parekh Expert Committee on State Specific Reforms 2002). Instead
of the transmission companies, privatizing the handful of DISCOMs per state
appears to be the thrust of the government as of now. The states kicked off
their reform process notably among them were Andhra Pradesh, Delhi &
Orissa.
270
In Andhra Pradesh the unbundling of the sector was primarily aimed to
increase operational efficiencies and to allow these entities to function
independently and put them in decision taking mode. More than 90% of the
employees were allotted to the company of their choice. The new power
generation projects would be mainly developed by the Independent Power
Producers (IPPs) selected through International Competitive Bidding (ICB)
and joint venture companies of APGENCO with private parties, other states
or central undertakings. The achievements of Andhra Pradesh reforms
because of the fact that Andhra Pradesh has taken up full-fledged energy
auditing of 114 towns and the T&D loss levels in these towns have been
brought down to less than 10 per cent. CRISIL Rated Andhra Pradesh as
the Best Utility in Implementing Reform program in a calibrated way.
In Delhi the main metric for choosing companies was not based on valuation,
but on performance improvement goals. The DISTCOs annual revenue
requirements are calculated based on their expenditure, performance (targets),
and return on equity (16%). The process of choosing the companies were
• Valuation of assets
• Mitigating uncertainty
• Criteria for selection of successful investor
• Incentives for achieving higher efficiency gains
• Baseline data
• Treatment of receivables
It is clear from Delhi privatization process that there was a better recognition
of the need for government support during the transition period in the Delhi
privatization which was totally absent in Orissa reforms.
Encouraged by the Government of India, assisted by the World Bank, and
supported with grants from the Government of U.K (DFID), Orissa took the
initiatives and earned the reputation of being the first state to reform its
271
electricity industry. Though the purpose of the reform was pious but because
of the under mentioned reasons, it failed to make any impact operationally
and financially as well, namely
• Incomplete separation of transmission and distribution caused
problems.
• Regulators should have given a clear picture of their tariff philosophy,
rate base, valuation methods, likely profile of prices and expected
performance levels.
• There should have been a structured, time-bound financial support
mechanism, with a fixed schedule for tapering off coupled with
improvements in operating parameters and collection.
• The single buyer model is necessarily not the best, and the Transco
might be better as just a wires company.
• Determining who gets priority claims over revenues is important. Do
not escrow the revenues from the distribution zones for meeting
TRANSCO needs, like was done in Orissa.
• Tinkering with the valuations, especially just before privatization has
caused heavy damage. This can have a serious impact on tariffs, as
Schedule VI of the Supply Act 1948 is based on assets (and newer
methods allow for 16% returns on equity).
However, the main reason for the poor performance appear to be the false
assumptions and expectations of the players, and the limited support provided
by the government, either for subsidies or to the companies who had liquidity
272
issues in addition to solvency issues. After examining the fault lines carefully
few steps were taken to improve the financials of new utility. It includes:-
• GRIDCO started trading of its surplus power with the utilities/SEBs
through the Power Trading Corporation of India Ltd. (PTC) by
entering into an Agreement signed on 03.07.2003.
• Billing and collection efficiency under the privatized distribution
companies (DISCOMs) started improving.
• To bring the reforms back on the rails, the World Bank and the DFID
who helped Orissa initially came forward with a suitable package to fill
the revenue gap in the intervening years.
• These services of the consultants, which weakened the organisation
rather strengthening them, were stopped and government appointed
efficient, dynamic bureaucrat in-charge of GRIDCO / OPTCL, which
made turnaround a reality & it has been decided to keep the tenure of
CMD fixed for 03 years.
• To ensure that commission (OERC) is fully functional at all times, the
government started appointing commissioners promptly because
OERC has done pioneering work in our country in the establishment of
a regulatory mechanism for the electricity industry.
• The government and the commission started interacting on a wide
range of issues of monitoring, problem solving, planning and
development of the state’s power sector.
273
SUMMARY OF THE MAIN FINDINGS OF SOCIO ECONOMIC
IMPACT ASSESSMENT OF POWER SECTOR REFORMS
1. Use of electricity: During the reform period there appears to
have occurred a significant change in the pattern of use of electricity
since, compared to the pre-reform period, more households particularly
in the urban areas report its application in non-conventional uses like
domestic chores other than cooking, education, health and hygiene,
entertainment, etc in addition to the extensive use of modern electrical
appliances. More than 80 % of the households have reported about the
economy in the use of electricity at their homes and more than 70 %
women in the rural and 80 –90 % women in urban areas are found to
be practicing economy measures in the use of electricity. It is possible
that on account of the economy in use, the average monthly
expenditure on electricity by households in both rural and urban areas
is less in reform period than in pre reform period despite the fact that
there has been a significant rise in electricity tariff in the reform period.
2. Access and metering: The inclusion of forward caste
consumers among the sample households in the ‘Kutir Jyoti’ scheme
points to relatively poor targeting. Though the objective of 100 %
metering of user households is yet to be achieved in rural areas, there is
significant achievement in repairing and replacing of non-working
meters in the rural areas in the reform period. Evidence of improved
system efficiency in the reform period is contained in the less time
taken for households to get connections, significant decline in the
irregularity in meter reading, less time taken for repairing of meters
and the reduced incidence of tampering/damage of meters. The finding
that there is a sharp increase in the proportion of households’ not
lodging metering-related complaints during the reform period,
particularly in rural areas, is more likely explained in terms of
274
improved system efficiency in energy accounting by the DISCOMs at
the domestic users end.
3. Billing efficiency: Irregularity in billing has been eliminated
significantly; still it needs to be brought down to a tolerable level,
particularly in the rural areas. There is an overall increase in billing
efficiency, specifically in terms of more correct billing, better clarity in
billing and greater ease in payment procedure during the reform period
as compared to the pre-reform period. However, in terms of customer
care, the system set up by the DISCOMs is yet to provide satisfaction to
the majority of consumers in the rural areas. The overall improvement in
the efficiency in billing system seems to be relatively more pronounced
in urban areas than in rural areas.
4. Supply of power: According to the information gathered
from consumers, the overall power supply situation in urban areas
appears to have improved significantly during the reform period. The
rural consumers suffer from longer duration (more than 3 hours) of
power failure on an average while urban consumers suffer from power
failure for less than one hour. There is a marked decline in the
frequency of power cuts during summer as well as the rest of the year
during the reform period. The most common duration of power cut
during summer is 1 to 3 hours daily while it is less than 1 hour duration
during rest of the year in both rural and urban areas in the reform period.
Despite the various steps undertaken in the reform period to control the
misuse (theft) of power, still the practice appears to continue quite
extensively in both rural and urban areas, possibly in collusion with the
field functionaries of the DISCOMs.
275
5. Voltage quality: Slightly more than half (50.41%) of the
households in rural areas while more than 2/3 rd (72.74%) households in
urban areas have reported that they get adequate power supply with
normal voltage. In rural areas about 36 % of the households have
reported that they suffer from very low voltage. The damage to electrical
appliances and accidents due to voltage problem seems to be negligible
in both rural and urban areas, which of course seems to be a healthy sign
of the reform process. During the reform period the use of stabilizers has
been reduced to a large extent and the proportion of consumers not using
any protective measure for voltage problem has increased which gives a
clear impression that there has been a lot of improvement in the quality
of voltage during the reform period.
6. Impact on education: It appears that on account of the
improvement in power supply the duration of the study hours has
increased in both rural and urban areas, but in a more pronounced
manner in the latter areas. There is significant improvement in the
access to computer and internet in the urban areas in the reform period.
No perceptible change is observed in the educational performance of
children in rural and urban households. Due to less frequent power cuts
in the evenings there seems to be greater confidence among the urban
parents, irrespective of their social status, to allow their daughters to
attend evening classes.
7. Impact on health: More than 50 % rural more than 80 % urban
households reported that there is an improvement in the timely conduct
of diagnostic tests of different types in the reform period. Largely it is
found that the privileged urban area households are in a relatively
favourable position to avail of the benefits of improved health care
services due to better quality power supply in the reform period. There
appears to be a significantly perceptible positive impact of reform on the
276
health care of the sick, old persons and children in the sample
households. A significant proportion of households perceived that the
health status of women has improved in the reform period on account of
reduced drudgery.
8. Impact on women: The women members of urban households
are found to save more time than their rural counterparts by the greater
use of electrical appliances in domestic chores. By and large, the leisure
time gained by the women members of rural and urban households has
not been productively utilized possibly due to the lack of opportunities
for women. About one-third of urban households and a quarter of
households in rural areas have reported that the insecurity of women has
increased during the reform period.
9. Impact on agriculture, employment and consumption
pattern: There is no perceptible impact of power sector reform either
directly on agricultural productivity or indirectly in terms of the
provisioning of storage services for agricultural produce, as reported by
the overwhelming majority of rural households. In both rural and urban
areas, households belonging to the privileged category generate a
majority (> 50 %) opinion that there has been increased employment of
male workers in the cottage and small-scale industry sector during the
reform period. Majority of the households expressed that their
consumption expenditure is not distorted due to increased cost of
electricity.
10. Awareness about reform: About 76 % of the rural consumers
and 95 % of the urban consumers are aware of the reform measures.
Regarding the sources of information about the reform it is found that
largely news papers (as stated by 56 % consumers) in urban area and
radio (as mentioned by 46 % consumers) in rural areas have played
important role in creating awareness about reform measures among the
consumers.
277
11. Willingness to pay: The present tariff rate seems to put
financial burden on the consumers to such an extent that about 73 % in
rural and 51 % in urban area consumers are not willing to pay any extra
rate for electricity over and above the present tariff. However, it would
be interesting to note that higher level of education and urbanization
enhance the willingness of the consumers to pay more towards electricity
charges if they are assured of better and regular supply of electricity.
SUGGESTIONS
1. The poor performance of the existing power generation facility is to be
dealt, hence forthwith. The national average has almost reached 75% plant
load factor (PLF). Gradually it should be increased to 85% PLF and
continuous benchmarking should be done in this regard and this type of
exercise needs to be continued.
2. There are a large number of states where a considerable amount of work
needs to be done to set up rural electricity infrastructure and government
intervention in a big way might be necessary.
3. Orissa was the first state which started the exercises of reforming its power
sector in early nineties. It is therefore very essential to draw upon the
experiences of this initiative.
4. Distribution is the cutting edge of the power industry and it needs to be set
right. Unless the electricity market allows itself to be put under competitive
pressure, performance improvement to the desired level might be difficult to
achieve.
278
5. To meet the resource requirements of expansion, we have to devise the
policies and programmes and revive this sector in a manner that it attracts
investments and also generate surplus to fund growth.
6. The political willingness is required from the government to further its
development. The political bosses must desist themselves from announcing
populist policies relating to power. Any subsidy or free power extended to
any sections of population will have severe pressure on the ailing state
finances and ultimately the growth will be hindered. There is a need for
continued political support for reforms.
7. The private power producers must be encouraged to operate in their area of
preference. The option of producing power from Atomic energy must be
pursued with great vigor.
279
SCOPE FOR FURTHER RESEARCH
1. Single Buyer vs. Multi Buyer Model in Distribution
The state owned Single Buyer is often reluctant to take unpopular action
against delinquent distributor, who either overdraws power or most
importantly does not honour the payment schedule for the power purchased
by it. It affects the commercial viability of the transmission and distribution
company, which may not pay enough attention to disconnect power supply of
the defaulting consumers across the board vitiating the very purpose for
encouraging competition and privatization. The single buyer model retains the
role of the government in the power sector instead of distancing it. So the
research on Multi Buyer Model would be an ideal one at this juncture.
2. Scope of Foreign Direct Investment in Power Sector
There has been an insignificant inflow of FDI in power sector. The time when
power sector growth was required, then corresponding liberalized policies
were announced, yet the response is not so encouraging. The different areas
where it has failed to attract the FDI must be analyzed and a comprehensive
roadmap needs to be prepared to woo the investors. So a comprehensive
research needs to be carried out to suggest the ways and means to encourage
the participation of private players in the power sector by the way of FDI.
280
THE SCHEDULE ENACTMENTS
(See sub-Section (3) of Section 185)
1. The Orissa Electricity Reform Act, 1995 (Orissa Act no. 2 of 1996)
2. The Haryana Electricity Reform Act, 1997 (Haryana Act no. 10 of 1998)
3. The Andhra Pradesh Electricity Reform Act, 1998 (Andhra Pradesh
Act no. 30 of 1998)
4. The Uttar Pradesh Electricity Reform Act, 1999 (Uttar Pradesh Act no. 24 of 1999)