Page 1
POWER ENGINEERING CONSULTING JSC 2
HSX: TV2
UPDATE REPORT June 4, 2021
TV2 - BUY
Stock information
(03/06/2021)
Stock exchange HOSE
Market price (VND) 50.800
Average volume (10
days)
117.980
Capitalization (VND
billion)
1.830
Common share (million) 36
Target price 77.700
Upside +53,0%
Equity Research
Mr. Trinh Van Ha
[email protected]
+84-2838200796 ext 643
VCBS’s Report
www.vcbs.com.vn/vn/Services/AnalysisResearch
VCBS Bloomberg Page: <VCBS><go>
Research Department Page | 0
TV2 – WIND POWER SUPPORT GROWTH, O&M MAKE
A BREAKTHROUGH
RECOMMENDATION
Our expectations for the long-term growth of all three spearheads: Consulting, Construction
and Investment. In addition, operations management is a new field with great potential .
We recommend BUY for TV2 with a target price in 2021-2022 of VND 77,700/share,
offering an upside of 53.0% compared to the closing price on June 3nd, 2021. Based on
the significantly growth of O&M services along with the good performance of invested
projects and consulting, electricity construction and installation are still stable in the short
term and have many long-term potential contracts.
FORECAST
VCBS forecasts that TV2’s net revenue in 2021 will reach VND3,790 billion (+13.2% yoy,
2.9% higher than 2021’s plan) and NPAT is estimated to reach VND301 billion (+15% yoy,
11.5% higher than 2021’s plan), equivalent to 2021F EPS of VND8,355/share and a forward
PE of 6.0.
PROSPECTIVE
(1) O&M is a new segment with nearly 5% revenue but bring significantly profit (~20%) due
to high GPM.
(2) Wind EPC help TV2 to offset high base of Solar PV EPC last year beside long term growth
of Thermal power (coal – fired and LNG)
(3) Profitable investing in power generation projects due to take advantage of planning, pre –
FS, FS contract and other electricity consultant projects.
(4) Although low contributed in revenue, Consulting still be a majority segment to support
other segments.
Major financial factors 2019 2020 2021F 2022F
Revenue (VND billion) 3,322 3,346 3,790 4,084
+/- yoy (%) 80.5% 0.7% 13.2% 7.8%
NPAT (VND billion) 255 262 301 375
+/- yoy (%) 3% 15% 25%
Total Equity (VND billion) 931 1,167 1,453 1,810
D/A (%) 14% 14% 11% 11%
GMP (%) 9.6% 12.8% 12.7% 13.1%
ROE (%) 31% 25% 23% 23%
Dividend/Share holder equity 83% 50% 35% 40%
EPS (VND) 10,626 7,280 8,355 10,421
P/E 8 7 6.01 4.82
BVPS (VND) 38,781 32,411 40,348 50,248
P/B 2.5 1.9 1.24 1.00
Page 2
Research department - VCBS Page | 1
TV2 – UPDATE REPORT
PERFORMANCE
2020’s performance
Revenue increased 0.7% yoy with VND 3,346 billion, contributed by completing of Vinh Tan 4 expand
thermal power and 2 another Solar PV (Gio Thanh 1, 2).
GPM rose to 12.8% compared to 9.6% in 2019 due to Solar module decreased 20% - 30% in 2020.
Gross profit reached VND 428 billion (+33% yoy)
Revenue increased significantly in 2019 and 2020 compare to 2017 and 2018 contributed by EPC
contract of solar power in short time (only 3 – 6 months) and uncomplicated. That’s the reason why
GPM decreased considerably (from nearly 20% to 10% – 13% only).
In 2020, warranty expense double to VND 89 billion due to complete 3 projects above. In 2019,
Warranty time expired without failure, a VND 58,6 billion of warranty expense reversed.
2020 recorded TV2’s NPAT increase to VND 262 billion (+3% yoy).
Source: TV2, VCBS
1Q2021 1Q2021’s Revenue dropped sharply, reaching VND 346 billion (-45.9% yoy) because the major pending
projects were almost accounted for in Q4.2020 and the same period handed over the extended Vinh Tan
4 thermal power plant project in the same period. .
GPM increased sharply from 8% in the same period to 15% in 1Q2021, mainly due to the accounting of
the first items of Tan Thuan wind power with higher profit margin and the O&M segment having good
NPAT. As a result, Gross profit reached VND 52 billion (+2% yoy).
However, selling expenses in the same period incurred a reversal of the warranty provision for Vinh Tan
4 thermal power plant when the warranty period expired. Administration expense also increased strongly
to 24 billion dong (+24%).
Therefore, NPAT in Q1.2021 was only 28.5 billion dong (-48% yoy).
214 225 255 262 28.5
22%20%
10%
13%
15%
0%
5%
10%
15%
20%
25%
0
500
1,000
1,500
2,000
2,500
3,000
3,500
4,000
2017 2018 2019 2020 Q1.2021
Business performance
Total Revenue Gross profits Profit after Tax Gross Profit margin
VND Bil
Page 3
Research department - VCBS Page | 2
TV2 – UPDATE REPORT
Source: TV2, VCBS
FINANCIAL POSITION
TV2 is a state-owned company with 51% shares owned by EVN, so it is always prudent in financial.
With the starting point as a consulting, surveying, planning and designing company for electrical
network, labor is the most using and the major asset. Fixed assets do not account for much in the asset
structure. The high amount of money accumulated in the past makes the company had a strong financial
statement. At the end of Q1.2021, cash/cash equivalents accounted for 32% of total assets (VND999
billion). This will help TV2 able to invest in power projects with good efficiency in the future.
Safe financial leverage with D/A lower than 5%.
Account receivables increased sharply at the end of 2020 to VND 1,570 billion, mainly because at the
end of 2020, TV2 completed 02 Gio Thanh 1 and 2 solar power projects and some rooftop projects but
have not yet collected them all. On the other hand, prepayment for subcontractors and suppliers for Tan
Thuan Wind Power project and other projects. At the end of Q1.2021, receivables related to Gio Thanh
1 and 2 projects were fully collected and some other receivables were also recovered.
Receivables/prepayments at the end of Q1.2021 were only VND1,213 billion, down 23% compared to
the end of 2020.
COMPANY’S PROSPECTS
Operation and management
sevice have huge potiental
with high profit margin.
TV2 officially inaugurated the remote Power Plant Operation Management center (POMC), take the
first step in the field of power plant operation and management. O&M services will help investors
minimize operations and focus on developing other projects. The management team will control the
640
346
55 29
8%
15%
0%
5%
10%
15%
20%
0
100
200
300
400
500
600
700
Q1/2020 Q1.2021
1Q2021 performance
Total Revenue Profit after Tax Gross Profit margin
0.0%
1.0%
2.0%
3.0%
4.0%
5.0%
2017 2018 2019 2020 Q1.2021
D/A
Source: TV2, VCBS
Page 4
Research department - VCBS Page | 3
TV2 – UPDATE REPORT
power plant 24/24 to maximize the power generation and can calculate in advance the possible problems,
the parts to be replaced through the management system. POMC will reduce human and material
resources for each plant to reduce operating costs and increase power generation efficiency for investors.
The main cost of this activity segment is the cost of labor and operating assets, so the
As out expect, TV2 charge 5% - 7% of Power generation revenue for O&M service with Solar power
plants (without replacement cost), 30% - 35% lower than average cost (7% - 10% of revenue).
Solar projects TV2 managing now:
Source: TV2, VCBS
By the end of 2019, the company had operated nearly 500 MWp of total solar power capacity. And by
the end of 2020, the capacity of cultural management has tripled to 1,500 MWp of solar power capacity.
Simultaneously signed 75MW of Tan Thuan wind power capacity; management and operation of coal
and coal ash system of Duyen Hai 2 Thermal Power Plant. These two projects are expected to operate
from the end of 2021.
O&M revenue in 2020 is expect to reach VND 170 - 180 billion (only account for 5% 2021 revenue).
In opposite side, NPAT projected to VND 45 – 50 billion (15% NPAT in 2021).
We expect this segment to grow strongly in the coming years as TV2's reputation in the industry is
increasingly enhanced and can sign new contracts, especially a lot of wind power projects that come
into operation in 2021 and 2022.
Wind EPC contract offset
high base of Solar EPC
contract last year
It is expected that in 2021, only about 3GW - 4GW of wind power capacity can be put into operation to
have the FIT price of up to 8.5 cents/kWh for onshore wind power and 9.35 cents/kWh for offshore one.
There are still more than 10 GW that have been included in the revised PDP 7 but not being operational
this year. In addition, according to the draft PDP 8, wind power capacity in 2045 will reach 60 GW,
accounting for 20% of the total power capacity. The draft extension of the FIT price for wind power
after 2021 is still attractive, creating motivation for investors to continue investing in the wind power
sector, especially nearshore wind power projects.
In terms of total power capacity, according to the draft PDP 8, the total capacity will grow at more than
5.7% in the period from 2020 to 2045 with the largest growth coming from renewable energy such as
wind power, solar power and both Gas-fired thermal power (an indispensable source of electricity to
Singed in 2019 Signed 2020 MW
Page 5
Research department - VCBS Page | 4
TV2 – UPDATE REPORT
In addition, coal and LNG
thermal power projects are
also in the process of
completing the initial stages
to go into construction
stabilize the power grid). TV2 is a reputable contractor, can now be the general contractor for most types
of power sources as above. Accordingly, there are huge of contract waiting for TV2.
Currently, TV2 is implementing EPC general contractor for Tan Thuan wind power with a total capacity
of up to 75 MW, total investment capital of about 2,950 billion VND - nearshore wind power project in
Ca Mau. Currently, the progress has reached 100% of the stage 1 concrete foundation (25 MW) and
100% of phase 2 piles (50 MW), about 50% of the concrete foundation for phase 2 and the remaining
foundations are being constructed in parallel. Early in June 2021, TV2 successfully installed the second
turbine. This is expected to be put into operation on time before November 1, 2021.
With its experience in the Tan Thuan wind power project along with the large position of a surveying,
consulting and designing company for power projects, TV2 is a great candidate that can compete directly
with other constructer. We expect that this year and next year TV2 will sign another contract for wind
power when FIT are extended.
In the long term, Vietnam focus on developing energy sources especially renewable energy (Solar PV
+ Wind power accounts for more than 40% of capacity in 2045) with the disadvantage of unstable,
depend on wind or sun, it is necessary to have backup sources can be immediately mobilized whenever
sun or wind stop. Other sources include coal-fired power, gas-fired power. Coal-fired power plants
polluted environment and lack of domestic coal supply, will not be developed much. Gas-fired thermal
power also limits the domestic gas supply due to the decrease of gas reserves. Only LNG gas thermal
power that can be imported from abroad will be the main stable source. Thus, in the long term, LNG gas
thermal power and a number of coal-fired power projects are still essential to have a stable and safe
power generation structure. TV2 will take advantage to get more contract.
Major power projects are under construction and have construction plans:
Projects Source Capacity
(MW)
Operation
year
Ialy expan Hydro power 2x180 2023
Hoa Binh expand Hydro power 2x240 2023
Quang Trach 1 Coal – fired 2x600 2023
O Mon IV Gas - fired 1050 2023
Dung Quat I Coal – fired 750 2023
Dung Quat III Coal – fired 750 2024
O Mon III Gas - fired 1050 2025
0
50,000
100,000
150,000
200,000
250,000
300,000
2020 2025 2030 2035 2040 2045
Energy capacity base on resource 2020 - 2045
(base scenario)
Coal-fired Gas - fired Hydro power Wind Solar Other Import
MW
Page 6
Research department - VCBS Page | 5
TV2 – UPDATE REPORT
Tri An expand Hydro power 200 2025
Quang Trach II Coal – fired 2x600 2025
Nhon Trach 3&4
Gas – fired
(LNG) 2x750 2023 – 2025
LNG Long Sơn
Gas – fired
(LNG) 3.600 2025 – 2026
Source: EVN, VCBS
TV2 is currently carrying out procedures to invest in Long Son LNG thermal power plant with other
partners and may have a component contract to construct this project. This project has a total capacity
of up to 3,600 MW and is in the process of completing investment procedures.
On the other hand, BOT Quang Tri I coal – fire thermal power which TV2 is one of main EPC contractor
have been pending because the BOT law has expired on December 31, 2020, but the investor (EGATi)
has not yet established a BOT company in Vietnam, so it cannot start construction in 2021. ..
In 2020, the FIT price for Solar PV has expired and face a significantly growth of Solar PV with nearly
18,000 MWp, accounting for nearly 25% of total power capacity. However, it wouldn’t extend, so in
2021 there is no contract for Solar PV. Meanwhile, in the same period, the company recorded nearly
VND 2,300 billion in revenue from Solar PV only within Q3 and Q4.2020. Thus, the possibility of
revenue growth this year faces a lot of pressure.
Consultin, surveying and
design is the traditional
segment and the backbone
of the whole system and
brings stable revenue.
TV2 is one of the most famous names in consulting, grid planning, surveying and designing power
project. Projects from the parent company (EVN with 51% stake) will be given priority over other units.
Survey activities, pre-feasibility and feasibility reports, dam safety assessment, environmental impact,
etc. will still bring stable revenue to TV2.
By being exposed to projects at the first stage, TV2 can access high potential project for investment.
Therefore, the importance of consulting, surveying and designing fields is very significant, creating an
abundant source of work/projects for other fields such as EPC general contractor, project investment.
Project completed in 2020: Thermal power plant: Dung Quat I, III, Son My 3.1 thermal power plant,
Pre-FS Long Son LNG thermal power plant 1, Long An thermal power plant I – II, Vung Ang 3 thermal
power plant, bidding documents for thermal power plant Nhon Trach 3 – 4. Currently implementing FS
for Long An Thermal Power Plant I – II. Executing PMC of Song Hau 2 thermal power project; Establish
FS of hydropower plants such as: Tri An Extension, Thac Mo Extension, Da Nhim Extension, Dak Mi
2, Bao Lam, Thac Ba 2 and 500 kV transmission lines.
Revenue reach VND 100 – 150 billion/year with high GPM up to 20%.
Investment in power
projects will be the main
driving force for the
company to increase its
scale.
This is one of the three spearheads the company is aiming for in the near future. With the advantages
from the above-mentioned consulting, surveying and designing fields, TV2 can easily access high-
efficiency projects for investment. From this investment, TV2 also has a large source of work for the
construction segment, and O&M also.
Page 7
Research department - VCBS Page | 6
TV2 – UPDATE REPORT
Projects in timeline:
Projects Ownership Total investment
(VND bil)
Operation
year
Vinh Tan electricity center
Solar PV 100% 106.3 2019
Son My 3.1 Solar PV 25% 87.4 2019
Tan Thuan Wind power 25% 91.55 20211
Thac Ba hydro power expand 45% 5.4 20232
Biomass Hau Giang 25% N/a 2023
Gas – fired (LND) Long Son N/a N/a n/a
Source: TV2, VCBS
02 Solar PV project operated in 2019 with high efficiency of 9.35 cent/kWh within 20 years:
The Vinh Tan Power Center Solar PV, 100% owned by TV2 100% with a capacity of 6.2 MWp, is
considered quite successful with an estimated IRR of about 18% - 20%. Although the business results
are still low (EAT in 2020 is -1.33 billion VND, but because TV2 implements fast depreciation in 5 -
5.5 years compared to the project life of 20 years. Annual cash flow account for 18-21 billion dong,
expected to pay back without discount within 5.5 years. In 2020, although Binh Thuan is the place where
many projects are deflated, this project is almost not deflated due to its efficient operation.
Son My 3.1 Solar PV (25% stake of TV2). Annual revenue reach nearly 180 billion VND, equivalent
to 85 - 90 million kWh/year. 2020 is the first year this project pays dividends to TV2 with the amount
of VND 4.37 billion. This project is expected to bring a steady increase in income in the future while
reducing debt and financial expense. According to TV2, this project has 02 connecting lines to national
grid, so it is not affected by the overload. According to enterprises, the IRR of this project is over 20%.
About Tan Thuan wind power. According to our calculations, IRR can reach over 18% due to very
good selling price, up to 9.35 cents/kWh – applicable for offshore wind power projects. However, this
is only a nearshore project, so the installation cost will be much lower than offshore projects. According
to our calculation installation cost is equal to onshore wind power projects. The only difficulty of the
project is the water level and waves during construction. However, about simpler construction methods
such as: Pressing concrete piles then fill the foundation by concrete, without having to level or dig the
foundation like onshore wind power. The transportation is also simpler, it is not necessary to make the
access road to the wind tower, only need to put the material on the barge, pull it to the construction site,
install it, and do not have to dismantle the crane when moving to another wind power pylon.
We estimate that the capacity factor is up to more than 40%, bringing in annual revenue of about VND
500 - 550 billion/year and cash flow of more than VND 400 billion/year when the whole project comes
into operation. TV2 currently owns 25% of this project.
This project is expected to be profitable right after it is put into operation due to its good price and
location with a steady wind with an average speed of up to 7 m/s – 8 m/s.
The remaining projects are in the early stages, so they will not contribute revenue in the next 2 years.
1 Plan 2 Plan
Page 8
Research department - VCBS Page | 7
TV2 – UPDATE REPORT
All projects invested are accounted by using the cost method, so profits will only be generated when
the joint venture/associate pays dividends, so the profits in the early stages of these projects will not
reflect reflect the true value of those investments.
EVN divest plan will help
TV2’s operation without
limited
According to sharing from enterprises and EVN, TV2 has proposed to reduce EVN's ownership from
51% to about 30%. It is expected that this will be included in the divestment plan for the period 2021 -
2025 so that TV2 can operate better, avoid barriers to bidding law and be more proactive in business. If
the divestment plan is successful, TV2 will have more autonomy in business matters, while still
benefiting from projects inside and outside EVN to ensure continuous work and create new
breakthroughs in the future. However, in our opinion, the divestment plan will take a long time, going
through many complicated processes, so in the short term it is not a catalist to help TV2 increase its
price.
VALUATION
We chose the method of some of the parts (SOTP) to valuate each segment of TV2 because of its different properties. O&M services
and consulting - survey - design - construction general contractor segment use P/E method, power source development investment
segment uses discounted cash flow (DCF) method.
O&M service Assumptions:
- O&M service revenue without replacement cost is about 7 USD/kW/year or 3.7% - 4.0% of power
generation revenue for solar pv.
- O&M service revenue for wind power reach nearl 11 USD/kW/year or 3.5% – 4.0% of power
generation revenue.
- O&M service revenue for Duyen Hai 2 thermal power account to VND 20 billion/year.
- After 2021, when more than 3 GW – 5GW of wind power is put into operation, TV2 can sign more
O&M contracts for wind power plants.
We estimate O&M service revenue reach VND 185,8 billion in 2021 and NPAT of VND 47.5 billion.
EPS achieve VND 1,320.
The service will bring steady growth in revenue with high efficiency depending on how to operate to
maximize the generating capacity. In addition, in our opinion, the revenue and profit of this segment in
the coming years will grow by about 20% - 30%/year. Therefore, we choose a P/E of about 10x for this
segment (PEG is only 0.3 – 0.5).
As a result, fair value for O&M service as below:
Fair value/share = 10 x 1,320 = VND 13,200 per share.
Consulting, surveying,
construction + mechanics
We use the P/E comparison method to evaluate the consulting, surveying, design and EPC general
contractors due to the volatility of the project progress and high dependence on the back log and new
sign contract value.
Page 9
Research department - VCBS Page | 8
TV2 – UPDATE REPORT
TV2’s contracts in 2021:
Project Categories Contract Value
(estimate)
Chinh Thang Wind power Substation + Grid line EPC 400
Tan Thuan Wind power Whole project EPC 2,000
Duyen Hai 2 thermal power Grid line PMC 400
Van Phong 1 thermal power
500 kV Distribution
floor EPC 320
Kien Binh - Phu Quoc 500 kV grid line EPC 200
Total 3,820
These contracts have been partially accounted in 2020 according to schedule.
Given the short/long term outlook for wind power and thermal power projects, we assume 5%/year
growth in new contract value in consulting, surveying, design, construction and engineering for the next
5 years, equivalent to the CAGR of the total power capacity according to the draft PDP 8.
Ongoing projects above will almost be put into operation in 2021.
We forecast that revenue from surveying, design, construction and engineering in 2021 will reach VND
3,581 billion, NPAT reach VND 217 billion, equivalent to EPS of VND 6,029/share.
Source: TV2, VCBS
We use a P/E of about 7.7x for construction, engineering and consulting, which is equivalent to Power
Construction Joint Stock Company 1 (HSX: PC1) with almost similar activities as calculated. calculated
in PC1's report and give a specific valuation for this segment of TV2's activities as follows:
Fair value = P/E x EPS 2021
= 7.7 x 6,029 = 46,427 VND/share.
Capital expenditure: We use
DCF to valuate projected
TV2 invested.
1. Vinh Tan power center solar PV
TV2 own 100% this project, total capacity of 6,2 MWp, using 100% equity. Annual average output of
10 – 10,5 million kWh, with stable revenue of VND 21 – 22 billion/year. Deprecitaion period of 5 years
base on 20 year of whole life. As the result, profit will be low in firs 5 years.
Our assumptions:
- Useful life of 20 years.
0.0%
5.0%
10.0%
15.0%
20.0%
2,800
3,000
3,200
3,400
3,600
2019 2020 2021F
EPC, consultion performance
Revenue Backlog GPM
Page 10
Research department - VCBS Page | 9
TV2 – UPDATE REPORT
- Annual degradation: 0,5%.
- Annual O&M expense: 10 USD/kW or 6,3% of revenue.
- Income tax: 0% in first 4 year, 5% in next 9 year, then 10% in 13rd year and then 20%.
- WACC = Re = 12,7% by not using debt.
Valuation in detail:
Unit: VND bil FY 2021E FY 2022E FY 2023E FY 2024E FY 2025E
Revenue 22.73 22.61 22.50 22.39 22.28
EBIT 1.93 1.81 1.70 1.59 1.48
+ Depreciation 19.36 19.36 19.36 19.36 19.36
- Working capital - - - - -
- CAPEX - - - - -
- Tax - - - 0.08 0.07
FCFF 21.29 21.18 21.06 20.87 20.76
NPV FCFF 19.64 17.33 15.30 13.45 11.87
NPV of FCFF after
2025
66.93
Sum of NPV of FCFF 144.52
Adjustment -
Equity value 144.52
2. Son My 3.1 Solar PV
The project owned by TV2 with 25% capital, EPC contractor and O&M, operated in 2019 and started
to pay dividends from 2020.
Our assumptions:
- Useful life of 20 years.
- Annual escalation in 2021 and 2022 is 3%
- Annual degradation: 0.5%/year
- O&M expense: 10 USD/kW/year or 6.2% of revenue .
- Tax: Tax free in first 4 years 5% in next 9 year, then 10% in 13rd year and then 20%.
- Financial leverage: 70% debt, 30% equity. Interest rate of 8,5%, Rd = 12,7%.
- WACC = 9,8%
Our valuation in detail:
Unit: VND bil FY 2021E FY 2022E FY 2023E FY 2024E FY 2025E
Revenue 183.00 183.00 188.66 187.72 186.78
EBIT 94.80 94.80 100.46 99.52 98.58
+ Depreciation 76.60 76.60 76.60 76.60 76.60
- Working capital - - - - -
- CAPEX - - - - -
Page 11
Research department - VCBS Page | 10
TV2 – UPDATE REPORT
- Tax - - - 2.486 2.665
FCFF 171.40 171.40 177.06 173.64 172.52
NPV FCFF 160.94 146.63 138.00 121.52 110.14
NPV of FCFF after 2025 759.57
Sum of NPV of FCFF 1436.80
Adjustment (745.73)
Equity value 691.07
TV2 ownership 25%
Value for TV2 172.77
3. Tan Thuan Wind power.
TV2 own 25% of this project.
Our assumption:
- Useful life of 20 years.
- Financial structure (D/A): 70/30. Loan period: 15 years, interest rate of 8.5%/year.
- Re = 12,7%, WACC recalculate each year base on financial structure.
- Selling price 9.35 cent/kWh
- Capacity factor of >40%, annual average output of 260 million kWh.
- Average wind speed: 7 – 8 m/s.
- O&M expense: 35 USD/kW, or 11% of revenue.
Valuation in detail:
Unit: VND bil FY
2021E
FY
2022E
FY
2023E FY 2024E
FY
2025E
FY
2021E
Revenue 79 552 551 550 550 549
EBIT 44 344 342 342 341 341
+ Depreciation 25 148 148 148 148 148
- Working
capital - - - - - -
- CAPEX (1,967) (441) - - - -
- Tax - - - - 10 11
FCFF (1,898) 50 490 489 489 488
NPV FCFF (489)
NPV of FCFF after 2025 1,821
Sum of NPV of FCFF 1,332
Adjustment -
Equity value 1,332
Ownership 25%
Value for TV2 333
Page 12
Research department - VCBS Page | 11
TV2 – UPDATE REPORT
Sum of valuation:
Project
Value (VND
billion)
Value per share
(VND)
Vinh Tan PC Solar PV 145 4,013
Son My 3.1 Solar PV 173 4,797
Tan Thuan Wind power 333 9,249
Total 650 18,059
In addition, TV2 also invests in projects such as: Owning 45% of Thac Ba hydropower plant expansion
(capacity of 18.9 MW) and 25% of biomass power (20 MW) in Hau Giang. These 2 projects are expected
to ground breaking this year and are expected to operate in 2023. However, these projects are in legal
procedures completing stage, so we have not included these projects in their valuation.
Sum of valuation Segments Valuation
method
Value
(VND bil)
Value/share
(VND)
EPC,
Mechanism,
Consulting
P/E
1.672
46,427
Capital
expenditure FCFF
650
18,059
O&M service P/E
476
13,212
Total 2.798
77.697
Upside 53,0%
We recommend BUY for TV2 with a target price in 2021-2022 of VND 77,700/share, offering an upside
of 53.0% compared to the closing price on June 3nd, 2021.
INVESTMENT RISKS
(1) Bad weather will slow down the project progress. In 2021, the project that contributes the most
revenue is the Tan Thuan wind power in nearshore area in Ca Mau. This area will enter the
monsoon season from October every year onwards. Strong winds will make the sea surface very
rough, making it impossible for continuous construction. If the project is behind schedule up to
this point, there is impossible of COD in time, reducing the project's efficiency. Thus, both
construction revenue and profit shared from this project will not meet our plan and our estimate.
(2) Steel prices have increased sharply in recent times, affecting the GPM of construction
companies. However, whenever signing the contract, TV2 has signed with the supplier as well.
EPC general contractor activities also often re-sign prices with subcontractors, so they are not
affected much.
Page 13
Research department - VCBS Page | 12
TV2 – UPDATE REPORT
Unit: VND billion
BALANCE SHEET 2021F 2022F 2023F 2024F 2025F
INCOME
STATEMENT 2021F 2022F 2023F 2024F 2025
Cash and equivalents 784 844 1236 1758 2215
Revenue 3,790 4,084 3,887 4,095 4,302
Short term
investments 509 509 509 509 509
COGS (3,310) (3,550) (3,368) (3,546) (3,725)
Account receivable 1350 1119 1065 1010 1061 Gross profit 480 534 519 549 577
Inventories 311 392 373 393 413 Sale expense (38) (41) (39) (41) (43)
Other Current Assets 38 41 39 41 43 Administration expense (145) (154) (145) (152) (159)
Current asset 2992 2905 3222 3710 4241 EBIT 297 339 335 356 375
Fixed asset 423 423 425 426 428 Financial income 82 133 150 181 214
Long term investment 202 202 202 202 202 Financial expense (4) (4) (4) (4) (4)
Other non-current
asset 4 4 4 4 4
Other income 0 0 0 0 0
Non-Current Asset 630 629 631 632 634 Investment income 0 0 0 0 0
TOTAL ASSET 3622 3534 3853 4343 4875 EBT 375 468 481 533 585
Tax (74) (93) (95) (106) (116)
Account payable 907 973 923 971 1020 NPAT 301 375 386 428 469
Short term debt 0 0 0 0 0 Minorities interest 0 0 0 0 0
Other shorterm
liabilities 822 293 275 289 303
NPATMI 301 375 386 428 469
Short term liabilities 1764 1320 1272 1356 1443
EPS 8,355 10,421 10,717 11,871 13,025
Long term debt 404 404 404 404 404
Other long term liabilities
0 0 0 0 0
CASH FLOW
STATEMENT 2020F 2021F 2022F 2023F 2024F
Long term liabilities 404 404 404 404 404 CFO 368 16 332 437 345
LIABILITIES 2169 1724 1676 1760 1847 CFI 169 44 60 85 113
Common share and
other funds 360 360 360 360 360
CFF (55) 0 0 0 0
Retain earning 648 948 1257 1599 1974
Net cash flow 482 60 392 522 458
Treasury stock 5 5 5 5 5
Beginning Cash
Balance: 302 784 844 1236 1758
Other equity 440 496 554 618 689
Ending Cash Balance: 784 844 1236 1758 2215
EQUITY 1453 1810 2176 2583 3028
Minorities interest 0 0 0 0 0 ROE 23% 23% 19% 18% 17%
TOTAL
LIABILITIES AND
EQUITY
2169 1724 1676 1760 1847
ROA 9% 10% 10% 10% 10%
Source: VCBS
APPENDIX
Page 14
Research department - VCBS Page | 13
TV2 – UPDATE REPORT
DISCLAIMER
This report is designed to provide updated information on the fixed-income, including bonds, interest rates, some other related. The VCBS analysts
exert their best efforts to obtain the most accurate and timely information available from various sources, including information pertaining to market
prices, yields and rates. All information stated in the report has been collected and assessed as carefully as possible.
It must be stressed that all opinions, judgments, estimations and projections in this report represent independent views of the analyst at the date of
publication. Therefore, this report should be best considered a reference and indicative only. It is not an offer or advice to buy or sell or any actions
related to any assets. VCBS and/or Departments of VCBS as well as any affiliate of VCBS or affiliate that VCBS belongs to or is related to
(thereafter, VCBS), provide no warranty or undertaking of any kind in respect to the information and materials found on, or linked to the repor t and
no obligation to update the information after the report was released. VCBS does not bear any responsibility for the accuracy of the material posted
or the information contained therein, or for any consequences arising from its use, and does not invite or accept reliance being placed on any
materials or information so provided.
This report may not be copied, reproduced, published or redistributed for any purpose without the written permission of an authorized representative
of VCBS. Please cite sources when quoting. Copyright 2012 Vietcombank Securities Company.
CONTACT INFORMATION
Any further information, please contact as below:
Tran Minh Hoang Ly Hoang Anh Thi Trinh Van Ha
Head of research
[email protected]
Deputy head of research
[email protected]
Equity research
[email protected]
VIETCOMBANK SECURITIES CORPORATION
http://www.vcbs.com.vn
Headquarters Hanoi 12rd & 17th Floor, Vietcombank Building, No. 198 Tran Quang Khai, Hoan Kiem District, Hanoi,
Tel: (84-24) -393675- Ext: 18/19/20
Ho Chi Minh branch 1st & 7th Floor, Green Star Building, No. 70 Pham Ngoc Thach, Ward 6, District 3, City. Ho Chi Minh
Tel: (84-28)-3820799 - Ext: 104/106
Da Nang branch 12th floor, 135 Nguyen Van Linh, Vinh Trung Ward, Thanh Khe District, Da Nang
Tel: (84-236) -33888991 - Ext: 12/13
Can Tho Branch 1st floor, Vietcombank Can Tho Building, 7 Hoa Binh, Ninh Kieu District, Can Tho
Tel: (84-710) -3750888
Phu My Hung Transaction Office Lawrence Sting Building, No. 801 Nguyen Luong Bang, Phu My Hung Urban Area, District 7, City. Ho Chi Minh
Tel: (84-28)-54136573
Giang Vo Transaction Office 1st floor, C4 Giang Vo Building, Giang Vo Ward, Ba Dinh District, Hanoi.
Tel: (+84-24) 3726 5551
An Giang Representative Office 6th floor, Nguyen Hue Building, 9/9 Tran Hung Dao, My Xuyen Ward, Long Xuyen, An Giang
Tel: (84-76) -3949841
Representative Office of Dong Nai F240-F241 Vo Thi Sau Street, Quarter 7, Thong Nhat Ward, City. Bien Hoa, Dong Nai
Tel: (84-61)-3918812
Representative office of Vung Tau Ground floor, 27 Le Loi Street, City. Vung Tau, Ba Ria - Vung Tau
Tel: (84-64)-3513974/75/76/77/78
Hai Phong Representative Office 2nd floor, 11 Hoang Dieu Street, Minh Khai Ward, Hong Bang District, Hai Phong
Tel: (+84-31) 382 1630
DISCLAIMER