Portland Water Bureau Micro Hydro Case Study David Peters, PE Bryan Robinson, PE May 2013
25

Portland Water Bureau Micro Hydro Case Study

Nov 20, 2021

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Portland Water Bureau Micro Hydro Case Study

Portland Water

Bureau

Micro Hydro

Case Study

David Peters, PE

Bryan Robinson, PE

May 2013

Page 2: Portland Water Bureau Micro Hydro Case Study

Outline

• Project Background

• Site Selection and Evaluation

• Design Process Requirements

• Installation

• Lessons Learned and future considerations

Page 3: Portland Water Bureau Micro Hydro Case Study

Portland Water Bureau System

• Bull Run Elevation at Headworks 750 feet

• Approximately 257 active pressure regulators throughout distribution network

Page 4: Portland Water Bureau Micro Hydro Case Study

• 1894 Installed (2) Pelton wheel turbines

PWB Turbine History

Page 5: Portland Water Bureau Micro Hydro Case Study

Portland Water Bureau –

Renewable Energy Projects

• Solar Generation – 267 kW Groundwater

– 12 kW Meter Shop

– 9.8 kW Groundwater chemical

– 7.92 kW Powell Butte (In Construction)

– 100 kW Interstate Shop (In Construction)

• Hydro – 35 MW Bull Run Hydro

– 170 kW Lucid

Page 6: Portland Water Bureau Micro Hydro Case Study

Pre Project Site Selection

• Power Available

• Existing Vault

• Power use at site

• Feasibility

• O&M/Safety

• Water Quality

• Capital Cost

• Environmental Impacts

• Social Impacts

• Revenue Generation

Page 7: Portland Water Bureau Micro Hydro Case Study

Vernon Site Characteristics

• 3 existing vaults

• Off street location

• 3-phase power available at the site

• High flow rate and head pressure

Page 8: Portland Water Bureau Micro Hydro Case Study

Vernon Site Characteristics

Vernon Flow vs. Head

4000.00

5000.00

6000.00

7000.00

8000.00

9000.00

10000.00

11000.00

12000.00

13000.00

14000.00

29-Sep-10 18-Nov-10 7-Jan-11 26-Feb-11 17-Apr-11 6-Jun-11 26-Jul-11 14-Sep-11 3-Nov-11

Date

Flo

w (

gp

m)

0.00

10.00

20.00

30.00

40.00

50.00

60.00

He

ad

Dif

fere

nc

e (

ft)

Total Flow

Head Diff (South)

Head Diff (East)

Page 9: Portland Water Bureau Micro Hydro Case Study

Step 1 – Obtain Permission

• Oregon Water Rights – 6 month wait

– Send letter to approximately 30 agencies inviting comments

– Public meeting at the site

• Apply for Conduit Exemption with Federal Energy Regulatory Committee – Wait

– And wait

– Proceed with design

Page 10: Portland Water Bureau Micro Hydro Case Study

Step 2 - Agreements

• Facility Study

• Power Purchase

• Infrastructure Connection

• Energy Trust

• American Recovery and Reinvestment Act (ARRA)

• Neighborhood Association

• State of Oregon - BETC

Page 11: Portland Water Bureau Micro Hydro Case Study

Step 3 – Design Requirements

• Replace 16” regulator with turbine in existing vault

• Restore 6” regulator in vault

• Maintain working clearances to meet electrical and safety codes

Page 12: Portland Water Bureau Micro Hydro Case Study

Step 3 - Design Requirements

• Safety Improvements

– Improved Access

– Lights in Vault

– Ventilation Fan

– Intruder Alarms

Page 13: Portland Water Bureau Micro Hydro Case Study

Step 3 - Turbine Selection

Page 14: Portland Water Bureau Micro Hydro Case Study

Step 4 – Pre-Construction

• Equipment Purchase Contract

• FERC final review and site evaluation with 3 month wait

• Utilize City Electrical Contract

• PWB M&C crews used for Installation

Page 15: Portland Water Bureau Micro Hydro Case Study

Step 5 - Construction

Page 16: Portland Water Bureau Micro Hydro Case Study

Final Mechanical Layout

Page 17: Portland Water Bureau Micro Hydro Case Study

Final Electrical

Page 18: Portland Water Bureau Micro Hydro Case Study

Hydro Performance

Vernon Micro Hydro

0

2,000

4,000

6,000

8,000

10,000

12,000

8/1/12 8/31/12 9/30/12 10/31/12 11/30/12 12/31/12 1/30/13 3/1/13 4/1/13

Da

ily

Av

era

ge

Flo

ws

(g

pm

)

0

10

20

30

40

50

60

70

Da

ily

Av

era

ge

He

ad

(ft

)

East Reg. Flow South Reg. Flow North Reg. Flow Head (ft)

Page 19: Portland Water Bureau Micro Hydro Case Study

Production Summary

Month

Avg Flow

(gpm)

Avg Head

Difference

(ft) Days

On peak

Energy

Generated

(kWh)

Off Peak

Energy

Generated

(kWh)

Total Power

Production

(kWh)

Sep-12 3739 39.43 30 5854 4867 10721

Oct-12 3775 44.01 31 7603 5379 12982

Nov-12 3715 43.20 30 7403 5001 12404

Dec-12 3683 43.06 31 7387 5432 12819

Jan-13 2419 50.25 31 4570 3548 8118

Feb-13 2300 52.0 28 3616 2370 5986

Mar-13 3500 39.5 31 6588 5068 11656

Apr-13 0 0.0 12000

May-13 0 0.0 12000

Jun-13 0 0.0 12000

Jul-13 0 0.0 12000

Aug-13 0 0.0 12000

Avg Annual Power Production 135000

* System came online September 8th

** Broken Solenoid system went down on January 20th

Actual Production

Page 20: Portland Water Bureau Micro Hydro Case Study

PWB Energy Use

• Production Range of Vernon Micro hydro

• Minimum 112,000 kWh 66 CO2 metric tons = 0.48% offset

• Maximum 213,000 kWh 125 CO2 metric tons= 0.91% offset

• Average US home 6 CO2 metric tons

Page 21: Portland Water Bureau Micro Hydro Case Study

Financial Incentives

• EnergyTrust of Oregon - $65,000

• Business Energy Tax Credit - $38,000

• American Recovery and Reinvestment Act of 2009 - $65,000

• Total Cost to PWB after incentives $375,000

Page 22: Portland Water Bureau Micro Hydro Case Study

Cost Summary

• Cost increase of approximately $120,000 due to no 3-phase power on site

Vernon Micro Hydro Cost

35%

17%

48%

PWB Internal

Utility Connection

Turbine and Electrical Eq.

Page 23: Portland Water Bureau Micro Hydro Case Study

Lessons Learned Future

Design Considerations

• Understand FERC process

• Utility infrastructure in place?

• Utility willingness to participate?

• Can energy be used on site?

• What is the constructability of the site?

Page 24: Portland Water Bureau Micro Hydro Case Study

Acknowledgements

• EnergyTrust of Oregon

• SOAR Technologies – Mike Maloney

• PWB – David Peters – Principal Design Engineer

– Vill Villanueva – Senior Engineer

– Frank Galida – Hydropower Manager

– Keith Walker – Program Manager

– Leigh Kojiro – Electrical Design Engineer

– Ryan Nelson – Structural Engineer

Page 25: Portland Water Bureau Micro Hydro Case Study

Questions