Poppy Photo Credit: Jeff Larson La Fonda Overcrossing Construction Construct New Bridge (6-8 Months) 1. Bridge Abutments on both sides of the bridge • Excavate footings, drill holes (piles) and fill with reinforcing steel and concrete Build abutment footing and walls with reinforcing steel and concrete • Backfill dirt around the sides and front of the abutment 2. Center Columns • Build footing with reinforcing steel and concrete • Build columns with reinforcing cage and concrete 3. Bridge Structure including Deck (including utilities) • Build temporary supports (falsework) including steel beams and timber posts* • Build deck bottom (soffit) and sides (exterior girder and interior stem walls) with reinforcing steel and concrete • Install utilities going through the bridge (water and gas) Build top deck using reinforcing steel and concrete Cure concrete for 10-28 days Remove temporary falsework including steel beams and timber posts* • Build sidewalks and railing; Install fencing and lighting Rebuild the approaches to the bridge and perform final cleanup work • Reconnect utilities – gas, water, electricity, phone, cable * This work requires full freeway closure in one direction. Photos (above and below) from Coleman Ave in San Jose Photos (above and below) from Hwy 1/17 Project
1

Poppy Photo Credit: Jeff Larson La Fonda Overcrossing ...

Jun 28, 2022

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Poppy Photo Credit: Jeff Larson La Fonda Overcrossing ...

Poppy Photo Credit: Jeff Larson

La Fonda Overcrossing Construction

Construct New Bridge (6-8 Months)

1. Bridge Abutments on both sides of the bridge •Excavatefootings,drillholes(piles)andfillwithreinforcingsteel and concrete • Buildabutmentfootingandwallswithreinforcingsteelandconcrete• Backfilldirtaroundthesidesandfrontoftheabutment

2. Center Columns • Buildfootingwithreinforcingsteelandconcrete• Buildcolumnswithreinforcingcageandconcrete

3. Bridge Structure including Deck (including utilities)• Buildtemporarysupports(falsework)includingsteelbeamsand timber posts*• Builddeckbottom(soffit)andsides(exteriorgirderandinterior stemwalls)withreinforcingsteelandconcrete• Installutilitiesgoingthroughthebridge(waterandgas)• Build top deck using reinforcing steel and concrete• Cure concrete for 10-28 days• Removetemporaryfalseworkincludingsteelbeamsandtimberposts*• Buildsidewalksandrailing;Installfencingandlighting• Rebuildtheapproachestothebridgeandperformfinalcleanupwork• Reconnectutilities–gas,water,electricity,phone,cable

* This work requires full freeway closure in one direction.

Photos(aboveandbelow)fromColemanAveinSanJosePhotos(aboveandbelow)fromHwy1/17Project