Top Banner
12 - Project Procurement Management Project Management Training Created by [email protected], June 2010
29

PMP Training - 12 project procurement management

Oct 30, 2014

Download

Business

ejlp12

 
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: PMP Training - 12 project procurement management

12 - Project Procurement Management

Project Management Training

Created by [email protected], June 2010

Page 2: PMP Training - 12 project procurement management

12. Project Procurement Management

Knowledge AreaProcess

Initiating Planning Executing Monitoring & Contol Closing

Procurement  

Plan Purchases - and Acquisitions

Plan Contracting

Request Seller -Responses

Select Sellers

Contract -Administration

Contract Closure

Enter phase/Start project

Exit phase/End project

InitiatingProcesses

ClosingProcesses

PlanningProcesses

ExecutingProcesses

Monitoring &Controlling Processes

Page 3: PMP Training - 12 project procurement management

Project Procurement Management

• The process necessary to process and acquire product or services, or result needed from outside the project team.

• Involve planning, acquiring the product or services from sources, choosing a source, administering the contract, and closing out the contract.

• Can be applied to internal work orders, formal agreements, and contracts between organization units within single entity.

Page 4: PMP Training - 12 project procurement management

Project Manager’s Role in Procurements

• PM must be involved in the creation of contracts• Key roles:

– Know the procurement process– Understand contract terms and conditions– Make sure the contract contains all project management requirements such as 

attendance at meeting, reports, actions and communications deemed necessary

– Identify risks and incorporate mitigation and allocation of risks into the contract– Help tailor the contract to the unique needs of the project– Align schedule of the contract and schedule of the project– Involved in contract negotiation– Make sure procurement process done smoothly– Work with contract manager to manage changes to the contract

PM must be assigned before contract signed!

Page 5: PMP Training - 12 project procurement management

12.1 Plan Procurements• The process of obtaining seller responses, selecting a seller, and awarding a 

contract.

Inputs

1. Scope baseline2. Requirement documentation3. Teaming agreements4. Risk register5. Risk-related contract 

decisions6. Activity resource requirements7. Project schedule8. Activity cost estimates9. Cost performance baseline10.Enterprise environmental 

factors11.Organizational process assets

Tools & Techniques

1. Make-or-buy analysis2. Expert judgment3. Contract types

Outputs

1. Procurement management plan

2. Procurement statement of work

3. Make-or-buy decisions4. Procurement 

documents5. Source selection criteria6. Change requests

Page 6: PMP Training - 12 project procurement management

Make-or-buy analysis

• Determine whether an organization should make or perform particular product or service by themselves or buy/acquire from others.

• Evaluate of the benefit and drawback• Often involves financial analysis

• Make or buy analysis focus on:– skills and resources– cost– time– How critical is it that we retain detailed control over a certain area?– proprietary information or trade secret

See decision analysis in “Project Risk Management”

Page 7: PMP Training - 12 project procurement management

Contract Types

• Fixed-price (FP) contracts– Fixed Price (FP), or Lump Sum, or Firm Fixed Price (FFP) – Fixed Price Incentive Fee (FPIF)– Fixed Price with Economic Price Adjustment (FP-EPA)– Purchase order : simplest type of fixed-price contract; unilateral (signed by one 

party)

• Cost-reimbursable (CR) contracts– Cost Plus Fixed Fee (CPFF) or Cost Plus Percentage of Cost (CPPC)– Cost Plus Incentive Fee (CPIF) : – Cost Plus Award Fee (CPAF)– Cost Contract (No fee/profit e.g. contract in nonprofit organization)

• Time and Material Contracts (T&M)Hybrid type of contractual arrangement that contain aspects of both cost-reimbursable and fixed-price contracts

Page 8: PMP Training - 12 project procurement management

Fixed-price (FP) contracts

• Used for acquiring goods or services with well defined specifications or requirements.

• Seller is most concerned with the SOW• Sometime the buyer forces seller to accept a high level risk• Seller would need huge amount of reserves• Seller can try to increase profit by cutting scope

• Examples:– FP: Contract = $1M– FPIF: Contract = $1M + for every month added $1000– FPAF: Contract = $1M + for every month added $1000 if performance exceed– FPEA: Contract = $1M + additional pricing based on Government Center Bank 

depreciation rate.– PO: $1K per 1 metric ton

Page 9: PMP Training - 12 project procurement management

Cost Reimbursable (CR) contracts

• Used when work is uncertain and, therefore, costs cannot be estimated accurately  enough

• Requires the seller to have an accounting system that can track costs • Buyer requires auditing seller’s invoice

• Example:– CPF/CPPC: Contract = cost + fee (10% of cost)– CPFF: Contract = cost + $1K– CPIF: cost + additional fee based on performance– CPAF: cost + additional fee bases on manager satisfaction (performance 

criteria)

Page 10: PMP Training - 12 project procurement management

Time & Material (T&M) contracts

• Used for service  efforts in  which the  level of effort cannot be defined at the time the contract  is awarded

• To make sure the costs do not become higher  than budgeted, the buyer may put a "Not to Exceed" and time limits clause in the contract.

• Often used for staff augmentation, acquisition of experts, outside support

• Example:– Contract = $1K per day plus expenses or material cost.– Contract = $1K per day plus material at $5 per linear meter of wood.

Page 11: PMP Training - 12 project procurement management

Contract Types vs. Risk

Fixed Price

FFP

FPIF

Time and Materials

Cost Reimbursable

CPIF

CPFF

CPF

CPPC

• Effect of contract type on buyer & seller risk

SELLER RISK

High

Low

BUYERRISK

Low

High

T&M can be a high risk for buyer if contract does not

include a “total not-to-exceed” (NTE)

Page 12: PMP Training - 12 project procurement management

Plan Procurement Output

• Procurement Management plan – Describe how procurement process will be managed– Guidance for any procurement process

• Procurement Statement of Work (SOW)– Develop from scope baseline– Include only the portion will be included within the contract– This can be revised/refined through the procurement process until signed

• Make-or-buy decisions– The conclusion reach regarding what product/service/result will be acquired 

from outside

Page 13: PMP Training - 12 project procurement management

Procurement Documents (output)

• May includes:– Information for Sellers– Contract statement of  work– Proposed terms & conditions of the contract– Non-disclosure agreement (NDA) -- to disclose some confidential information

• Procurement documents, examples:– Request for Information (RFI)– Invitation For Bid (IFB)– Request For Proposal (RFP)– Request For Quotation (RFQ)– Tender notice– Invitation for negotiation– Invitation for seller’s initial response

Procurement document

Contract Type

RFP CRIFB FPRFQ T&M

Page 14: PMP Training - 12 project procurement management

Procurement Document

• Letter of Intent (LOI)– It is not a contract, but a letter without legal binding, that says the buyer intends to hire 

seller.

• Privity of contract– A contractual relationship– Example:

You hired a contractor A, and the contractor hires another sub-contractor B to deliver part of your work. Even though B is performing your work, he/she is contractually not bound to you, because B contractually bound to “A” only. So you need to talk to A instead of B.

• Teaming Agreements (or a join venture)– Two sellers join force for one procurement

Page 15: PMP Training - 12 project procurement management

Noncompetitive Form of Procurement

• Form used when only one seller awarded without a competitive procurement.• Should keep follow rules of bidding process and laws• Saving time on procurement process

• Would be implemented in the following condition:– The project under schedule pressure– A seller has unique qualification– There is only one seller– A seller hold a patent– Other mechanism exist that seller’s prices are reasonable.

• Type of noncompetitive procurement– Single source: contract directly to preferred seller.– Sole source: there is one seller; might be a company owns a patent

Page 16: PMP Training - 12 project procurement management

Source selection criteria

• Some criteria for evaluating proposals and bids (due diligence):– Understanding of need– Technical Capability– Past performance of sellers (experience)– Project management approach– Financial stability & capacity– Intellectual & property rights– Overall or life cycle cost– Risk– Warranty– References

Page 17: PMP Training - 12 project procurement management

Important Terms

• Price, Profit (fee), Cost• Target price: used  to compare the end result of the project with what was 

expected (the target price).• Sharing  ratio: Incentives  take the form of a formula, usually expressed as a ratio, 

e.g. 90/10 (buyer/seller)• Ceiling price: This  is the highest price the buyer will pay.• Point of total assumption (PTA):  

– This only applies to fixed price incentive  fee contracts– Refers to the amount above which the seller bears all the loss of a cost overrun. – Seller usually monitor actual costs against PTA to make still having profit.– Formula: 

PTA =  ((Ceiling  price -  Target price)/Buyer's  share ratio) + Target cost 

Page 18: PMP Training - 12 project procurement management

Exercise: Contract Calculation

In this cost plus incentive  fee contract, the cost  is estimated  at $210,000 and the fee at $25,000. The project is over, and the buyer has agreed that the costs were, in fact, $200,000. Because  the seller's costs came in lower than  the estimated  costs, the seller shares  in the savings: 80 percent to the buyer and 20 percent to the seller. Calculate the final  fee and final  price.

Target cost

Target fee

Target price

Sharing Ratio

Actual cost

Final fee

Final price

210,000

25,000

235,000

80/20

200,000

210,000 – 200,000 = 10,00010,000 x 20% = 2,00025,000 (target fee) + 2,000 = 27,000200,000 + 27,000 = 227,000

Page 19: PMP Training - 12 project procurement management

12.2 Conduct Procurements• The process of obtaining seller responses, selecting a seller, and awarding a 

contract.

Inputs

1. Project management plan

2. Procurement documents

3. Source selection criteria4. Qualified seller list5. Seller proposals6. Project documents7. Make-or-buy decisions8. Teaming agreements9. Organizational process 

assets

Tools & Techniques

1. Bidder conferences2. Proposal evaluation 

techniques3. Independent estimates4. Expert judgment5. Advertising6. Internet search7. Procurement 

negotiations

Outputs

1. Selected sellers2. Procurement contract 

award3. Resource calendars4. Change requests5. Project management 

plan updates6. Project document 

updates

Page 20: PMP Training - 12 project procurement management

Proposal Evaluation (Tools & Techniques)

Proposal Evaluation or Bid or Price Quote One or a combination of following process used for selecting seller:

– Weighting systemEvaluate by weighting the source selection criteria

– Independent estimateEstimation created in-house or with outside assistance

– Screening systemEliminate sellers who do no meet minimum requirement

– Past performance history

Page 21: PMP Training - 12 project procurement management

Procurement Negotiations (Tools & Techniques)

• PM may be involved during negotiation to clarify requirement, protect relationship.

• Objective of negotiation:– Obtain fair and reasonable price– Develop good relationship with the seller

• Main  items to negotiate:– Scope– Schedule– Price & payment– Responsibilities– Authority– Applicable law– Technical & business management approaches– Contract financing

Page 22: PMP Training - 12 project procurement management

Contract Document

• Purpose of contract:– To define role and responsibilities– To make things legally binding– To mitigate or allocate risks.

• Contract has many names and types from simple to complex document– Agreement, subcontract, purchase order, memorandum of understanding (MOU)

• A legal contract  will need..– An offer – Acceptance– Consideration (Something of value, not necessary money)– Legal capacity (Separate legal parties, competent parties)– Legal purpose (We cannot have a contract for something illegal)

Page 23: PMP Training - 12 project procurement management

Contract Document

• Contract document usually includes:– Statement of work or deliverables– Schedule baseline– Performance reporting– Period of performance– Role & responsibilities– Seller’s place of performance– Pricing– Payment terms– Place of delivery– Inspection and acceptance criteria– Warranty

Page 24: PMP Training - 12 project procurement management

12.3 Administer Procurements• The process of managing procurement relationship, monitoring contract 

performance and making change and corrections as needed.

Inputs

1. Procurement documents

2. Project management Plan

3. Contract4. Performance reports5. Approved change 

request6. Work Performance 

Information

Tools & Techniques

1. Contract change control system

2. Procurement performance reviews

3. Inspections and audits4. Performance reporting5. Payment system6. Claims administration7. Records management 

system

Outputs

1. Procurement documentation

2. Organizational process assets updates

3. Change request4. Project Management 

Plan updates

Page 25: PMP Training - 12 project procurement management

Contract Administration

• Assuring the performance of both parties to the contract meets contractual requirement.

• Contract change controls system– A process for modifying a contract– Review the impacts– Contract administrator is the only one with authority to change the contract– There are potential conflict between project manager and contract administrator

Page 26: PMP Training - 12 project procurement management

12.4 Close Procurements• The process of completing each project procurement.

Inputs

1. Project Management Plan 

2. Procurement documentation

Tools & Techniques

1. Procurement audits2. Negotiated settlements3. Records management 

system

Outputs

1. Closed procurements2. Organizational process 

assets updates

Page 27: PMP Training - 12 project procurement management

Negotiated Settlements

In all procurement relationships the final equitable settlement of all outstanding issues , claims , and disputes by negotiations is a primary goal. 

Whenever settlement cannot be achieved by direct negotiation , some form of alternative dispute achieved by direct negotiation , some form of alternative dispute resolution (ADR) including mediation or arbitration may be explored . 

When all else fails , litigation in the courts is the least desirable option 

Page 28: PMP Training - 12 project procurement management

Terms from International Chamber of Commerce To make the same definition between seller and buyer used for export/import

• Group E Incoterms (departure)– EXW (Ex works)

• Group F Incoterms (main carriage unpaid)– FCA (Free carrier)– FAS (Free alongside ship)– FOB (Free on board)

• Group C Incoterms (main carriage paid)– CFR (Cost and freight)– CIF (Cost, insurance and freight)– CIP (Carriage and insurance paid to)

• Group D Incoterms (arrival)– DAF (Delivered at frontier)– DES (Delivered ex ship)– DEQ (Delivered ex quay)– DDU (Delivered duty unpaid)– DDP (Delivered duty paid)

INCOTERMS 2000