8/13/2019 PM Chapter 05 Project Integration Management
1/72
Project Management(Project Integration Management)
8/13/2019 PM Chapter 05 Project Integration Management
2/72
What is the main role of the project managerto
perform integration.
Project manager must coordinate all the groups
and activities. This is project integration
management.
Project manager must make sure that everyone
perform their role.
Project integration management covers the entire
project life cycle.
Includes the processes required to ensure that
the various elements of the project are properly
coordinated.
Project Integration Management
8/13/2019 PM Chapter 05 Project Integration Management
3/72
8/13/2019 PM Chapter 05 Project Integration Management
4/72
While the work of the project is being done:
The team membersrole is to concentrate on
completing the work packages
The project sponsorsrole is to protect the
project from changes and loss of resources
The Project managersrole is to put all the
pieces of the project together into one
cohesive whole that gets the project done
faster, cheaper and with fewer resources
while meeting project objectives.
Project Integration Management
8/13/2019 PM Chapter 05 Project Integration Management
5/72
8/13/2019 PM Chapter 05 Project Integration Management
6/72
The need for integration in project management becomesevident in situations where individual processes interact.
For example, a cost estimate needed for a contingencyplan involves integration of the planning processesdescribed in greater detail in the Project CostManagement processes, Project Time Managementprocesses, and Project Risk Management processes.When additional risks associated with various staffingalternatives are identified, then one or more of those
processes must be revisited.
The project deliverables also need to be integrated withongoing operations of either the performing organizationor the customers organization, or with the long-termstrategic planning that takes future problems andopportunities into consideration.
Project Integration Management
8/13/2019 PM Chapter 05 Project Integration Management
7/72
Most experienced project management practitioners knowthere is no single way to manage a project. They apply
project management knowledge, skills, and processes indifferent orders and degrees of rigor to achieve the desiredproject performance.
However, the perception that a particular process is notrequired does not mean that it should not be addressed.The project manager and project team must address everyprocess, and the level of implementation for each process
must be determined for each specific project.
Among the processes in the Project Management ProcessGroups, the links are often iterated. The Planning ProcessGroup provides the Executing Process Group with adocumented project management plan early in the projectand then facilitates updates to the project managementplan if changes occur as the project progresses.
Project Integration Management
8/13/2019 PM Chapter 05 Project Integration Management
8/72
Integration is primarily concerned with
effectively integrating the processes
among the Project Management ProcessGroups that are required to accomplish
project objectives within an organizations
defined procedures.
Project Integration Management
8/13/2019 PM Chapter 05 Project Integration Management
9/72
Develop
Project
Charter
Project Integration Management Processes
Initiating Planning Executing Monitoring and
Control
Closing
Develop
Project
Mgt. Plan
Direct and
Manage
Project Exec.
Monitor and
Control
Project Work
Develop
Preliminary
Project Plan
Integrated
Change
Control
Close
Project
8/13/2019 PM Chapter 05 Project Integration Management
10/72
Project Integration Management Processes
Develop Project Charter:developing the project charter that formally authorizes a project or project
phase.
Develop Preliminary Project Scope Statement:developing the preliminary project scope statement
that provides a high level scope narrative.
Develop Project Management Plan:documenting the actions necessary to define, prepare, integrate
and coordinate all subsidiary plans into a project management plan.
Direct and Manage Project Execution:executing the work defined in the project management plan toachieve the projects requirements defined in the project scope statement.
Monitor and Control Project Work:monitoring and controlling the process used to initiate, plan,
execute, and close a project to meet the performance objectives defined in the project management plan.
Integrated Change Control:reviewing all change requests, approving changes, and controlling
changes to the deliverables and organizational process assets.
Close Project: finalizing all activities across all of the Project Management Process Groups to formally
close the project or a project phase.
8/13/2019 PM Chapter 05 Project Integration Management
11/72
Project Integration Management
8/13/2019 PM Chapter 05 Project Integration Management
12/72
4.1. Develop Project Charter
Define business requirementswhat the project is to
achieve
High level feasibility justificationtechnical and
financial feasibility
Secure formal commitment
We must ensure that a well defined project charterexists.
Project charter is nota project management plan.
Issued by sponsornot the project manager.
Created in the initiating process groups.
Broad enough so it does not need to change as the
project changes.
Any change to the project charter should call into
question whether or not the project should continue.
8/13/2019 PM Chapter 05 Project Integration Management
13/72
4.1. Develop Project Charter
The project charter is the document that formally
authorizes a project.
The project charter provides the project manager with
the authority to apply organizational resources to
project activities.
A project manager is identified and assigned as early in
the project as is feasible.
The project manager should always be assigned prior
to the start of planning, and preferably while the project
charter is being developed.
It is such an important document that a project cannot
be started without one.
8/13/2019 PM Chapter 05 Project Integration Management
14/72
The Project Charter is the primary tool and output of Initiation. Itencapsulates the collective visions of the key stakeholders andpasses it to the project team to enable, and as a basis for projectplanning. The Charter also authorizesthe project.
Customer
Executives
KeyStakeholders
Project
Charter ProjectTeam
ProjectSponsor
ProjectManager
4.1. Develop Project Charter
8/13/2019 PM Chapter 05 Project Integration Management
15/72
4.1. Develop Project Charter
A project initiator or sponsor external to the project
organization, at a level that is appropriate to funding
the project, issues the project charter.
Projects are usually chartered and authorized external
to the project organization by an enterprise, a
government agency, a company, a program
organization, or a portfolio organization.
8/13/2019 PM Chapter 05 Project Integration Management
16/72
4.1. Develop Project Charter
Projects are chartered as a result of one or more of the following:
A market demand(e.g., a car company author izing a pro ject to
bu i ld more fuel-eff ic ient cars in respon se to gasol ine sho rtages)
A business need(e.g., a training company author izing a pro ject
to c reate a new course to increase its revenues)
A customer request(e.g., an electr ic ut i l i ty authorizing a projectto bu i ld a new subs tat ion to serve a new industr ia l park)
A technological advance(e.g., an electr on ics firm auth orizing a
new project to develop a faster, cheaper, and smaller laptop after
advances in com puter memory and electronics technolog y)
A legal requirement(e.g., a paint manufact urer autho rizing apro ject to establ ish gu idel ines for handl ing toxic m ater ials)
A social need(e.g., a nongo vernmental organizat ion in a
developing country autho r izing a project to provid e po table water
systems)
8/13/2019 PM Chapter 05 Project Integration Management
17/72
4.1. Develop Project Charter
These stimuli can also be called problems,
opportunities, or business requirements. The central
theme of all these stimuli is that management mustmake a decision about how to respond and what
projects to authorize and charter.
Project selection methods involve measuring value
or attractiveness to the project owner or sponsor and
may include other organizational decision criteria.
Project selection also applies to choosing alternative
ways of executing the project.
8/13/2019 PM Chapter 05 Project Integration Management
18/72
4.1. Develop Project Charter
Chartering a project links the project to the ongoing
work of the organization.
In some organizations, a project is not formally
chartered and initiated until completion of a needs
assessment, feasibility study, preliminary plan, or
some other equivalent form of analysis that was
separately initiated.
Developing the project charter is primarily concerned
with documenting the business needs, project
justification, current understanding of the customers
requirements, and the new product, service, or result
that is intended to satisfy those requirements.
8/13/2019 PM Chapter 05 Project Integration Management
19/72
8/13/2019 PM Chapter 05 Project Integration Management
20/72
The Project Charter summarizes all of the pre-project planning bythe stakeholders, management, and customers
Constraints
ProjectObjectives
IdentifiedRisks
ProjectFramework
BudgetJustification
Business Case
Assumptions
StakeholderRoles/Authority
Project
Charter
4.1. Develop Project Charter
8/13/2019 PM Chapter 05 Project Integration Management
21/72
4.1. Develop Project Charter
Skeletal Example
Project Title and Description (What is the project?)Project Manager Assigned and Authority Level (Who is g iven the
author i ty to lead the pro ject and can (s)he determine, manage, and
approv e changes to b udget, schedu le, staf f ing , etc.)
Business Need (Why is the project being d one?)
Project Justification (Business case on what financ ial or oth er
bas is can we just i fy doin g the project?)Resources Pre-assigned (How m any or what resources wi l l be prov ided?)
Stakeholders (Who wil l affect , or be affected by the p roject?)
Stakeholders Requirements as Known (Requ irements related to both
produ ct and project scope).
Product Description / Deliverables (What specif ic product del iverables
are wanted and w hat wil l be the end resu lt of the project?)
Constraints and Assumptions (A con straint is any l imi t ing factor
and assump t ion is something taken to be true, but which may not be true)
Project Sponsor Approval
8/13/2019 PM Chapter 05 Project Integration Management
22/72
4.1. Develop Project Charter
Benefits
Formally recognizes (authorizes) the existence of the project, orestablishes the project.
Gives the project manager authority to spend money and commit
corporate resources.
Provides the high-level requirements for the project.
Links the project to the on-going work of the organization.
8/13/2019 PM Chapter 05 Project Integration Management
23/72
4.1. Develop Project Charter
8/13/2019 PM Chapter 05 Project Integration Management
24/72
4.1. Develop Project Charter
Inputs
Contract (for external customers,when applicable)
Project Statement of Work (SOW)
Enterprise Environmental Factors
Organizational Process Assets
Tools and Techniques
Project Selection Methods
Project Management Methodology
Project Management Information SystemExpert Judgment
Output
Project Charter
8/13/2019 PM Chapter 05 Project Integration Management
25/72
4.1. Develop Project Charter
Project Statement of Work (SOW)
The SOW is a narrative description of products or
services to be supplied by the project.
For internal projects, the project initiator or sponsor
provides the SOW based on business needs, product, or
service requirements.
For external projects, the SOW can be received from the
customer as part of a bid document, for example, request
for proposal, request for information, request for bid, or
as part of a contract.
SOW includes business needs, product scopedescription, and strategic plan.
4 1 C
8/13/2019 PM Chapter 05 Project Integration Management
26/72
Organizational Environment Factors
Company culture and existing systems that the project will have todeal with or can make use of.
Organizational Process Assets
Existing processes, procedures and historical information.
4.1. Develop Project Charter
4 2 D l P li i P j t S St t t
8/13/2019 PM Chapter 05 Project Integration Management
27/72
4.2. Develop Preliminary Project Scope Statement
The attempt to determine the project scope
what must be done to accomplish the project.
It is developed based on the information fromthe sponsor.
Making sure that the project manager and
sponsor have a similar understanding about
project scope before planning begins.
Effort during the initiating process to obtain
all the information needed in order to plan the
project.
4 2 D l P li i P j t S St t t
8/13/2019 PM Chapter 05 Project Integration Management
28/72
4.2. Develop Preliminary Project Scope Statement
The project scope statement is the definition of the projectwhat needs to be
accomplished. The Develop Preliminary Project Scope Statement process
addresses and documents the characteristics and boundaries of the projectand its associated products and services, as well as the methods of acceptance
and scope control. A project scope statement includes:
Project and product objectives
Product or service requirements and characteristics
Product acceptance criteria
Project boundaries
Project requirements and deliverables
Project constraints
Project assumptions
Initial project organization Initial defined risks
Schedule milestones
Initial WBS
Order of magnitude cost estimate
Project configuration management requirements
Approval requirements
4 2 D l P li i P j t S St t t
8/13/2019 PM Chapter 05 Project Integration Management
29/72
4.2. Develop Preliminary Project Scope Statement
Sponsor /Customer
asks?
What do Iwant?
ProjectSOW
Company
cultureand
existingsystem
Processes,
Proceduresand
historicalinfo.
Project Manager
assists the sponsorwith the character if
necessary
Sponsor issues thecharter
Project Manager
Develops thepreliminary project
scope statement andthe project
management plan
ProjectManagement
plan is boughtinto, approved,
realistic andformal.
4 2 D l P li i P j t S St t t
8/13/2019 PM Chapter 05 Project Integration Management
30/72
4.2. Develop Preliminary Project Scope Statement
4 2 D l P li i P j t S St t t
8/13/2019 PM Chapter 05 Project Integration Management
31/72
Inputs
Project CharterProject Statement of Work (SOW)
Enterprise Environmental Factors
Organizational Process Assets
Tools and Techniques
Project Management Methodology
Project Management Information System
Expert Judgment
Output
Preliminary Project Scope Statement
4.2. Develop Preliminary Project Scope Statement
4 2 D l P li i P j t S St t t
8/13/2019 PM Chapter 05 Project Integration Management
32/72
4.2. Develop Preliminary Project Scope Statement
Project Management Methodology
How you will use project management on the project
What parts of the PMBOK guide you will use on your project
4 3 De elop Project Management Plan
8/13/2019 PM Chapter 05 Project Integration Management
33/72
4.3. Develop Project Management Plan
Provides definitive statement to project
approach - scop e, cos t, t ime, qu al i ty, human
resource, communicat ion, r iskand
procurement.
All projects must include project management
plan.
4 3 Develop Project Management Plan
8/13/2019 PM Chapter 05 Project Integration Management
34/72
4.3. Develop Project Management Plan
Multi-page document based on input from the
team and other stakeholders. It contains all themanagement plans and performance
measurement baselines
It is these baselines that will be used to
measure the progress and completion of the
project.
Once completed, the project management plan
is used as a day-to-day tool to help manage
the project.
Though it may evolve and change over the life
of the project, it is designed to be as complete
as possible when the project execution
process group begins.
4 3 Develop Project Management Plan
8/13/2019 PM Chapter 05 Project Integration Management
35/72
4.3. Develop Project Management Plan
The project management processes selected by the project management team
The level of implementation of each selected process
The descriptions of the tools and techniques to be used for accomplishing those
processes
How the selected processes will be used to manage the specific project, including
the dependencies and interactions among those processes, and the essential inputsand outputs
How work will be executed to accomplish the project objectives
How changes will be monitored and controlled
How configuration management will be performed
How integrity of the performance measurement baselines will be maintained and used
The need and techniques for communication among stakeholders
The selected project life cycle and, for multi-phase projects, the associated project
phases
Key management reviews for content, extent, and timing to facilitate addressing open
issues and pending decisions.
Includes
4 3 Develop Project Management Plan
8/13/2019 PM Chapter 05 Project Integration Management
36/72
4.3. Develop Project Management Plan
The project management plan can be either summary level or detailed, and
can be composed of one or more subsidiary plans and other components.
Each of the subsidiary plans and components is detailed to the extentrequired by the specific project.
These subsidiary plans include, but are not limited to:
Project scope management plan
Schedule management plan
Cost management plan
Quality management plan
Process improvement plan
Staffing management plan
Communication management plan
Risk management plan
Procurement management plan
4 3 Develop Project Management Plan
8/13/2019 PM Chapter 05 Project Integration Management
37/72
4.3. Develop Project Management Plan
4 3 Develop Project Management Plan
8/13/2019 PM Chapter 05 Project Integration Management
38/72
Inputs
Preliminary Project Scope StatementProject Management Processes
Enterprise Environmental Factors
Organizational Process Assets
Tools and Techniques
Project Management Methodology
Project Management Information System
Expert Judgment
Output
Project Management Plan
4.3. Develop Project Management Plan
4 3 Develop Project Management Plan
8/13/2019 PM Chapter 05 Project Integration Management
39/72
4.3. Develop Project Management Plan
Configuration Management System
With all the documents that are part of productmanagement plan and all the changes to them that
will occur throughout the life of project, it would be wise to
have a plan for making sure everyone knows what version
of the scope, schedule and other components of the project
management plan are the latest version
The configuration management system may include a
change control system and is part of the project
management information system. It is designed in the
planning process group and used in integrated change
control process.
4 3 Develop Project Management Plan
8/13/2019 PM Chapter 05 Project Integration Management
40/72
4.3. Develop Project Management Plan
Change Control System
A collection of formal, documented procedures, paperwork, tracking system and
approval levels for authorized changes. There can be change control system foreach knowledge area in the project management. These systems are described in
the management plan for each knowledge area and are implemented in integrated
change control as part of the overall effort to control change.
The collected change control system may include:
A change control plan included in the project management plan outlining howchanges will be managed.
Creation of a change control board to approval all changes
Change control procedure (how, who)
Performance statistics
Reports
Change forms
4 3 Develop Project Management Plan
8/13/2019 PM Chapter 05 Project Integration Management
41/72
4.3. Develop Project Management Plan
Work Authorization System
If you think of a large project with team members from various locations, you might think it wouldbe worth while to create a system for authorizing worknotifying team members or contractors
that they may begin work on a project work package. In many cases this system for authorizing
work is a companywide system used on all projects, not created just for the project.
Project Management Plan Approval
Since the project management plan is a formal document that will be used to manage theexecution of the project and includes items like completion dates, milestones and cost, etc.
it must receive formal approval by management, the sponsor, the project team and other
stakeholders. Formal approval means sign-off (signatures)
4 4 Direct and Manage Project Execution
8/13/2019 PM Chapter 05 Project Integration Management
42/72
4.4. Direct and Manage Project Execution
Facilitate the development of project deliverables
The Direct and Manage Project Execution
process requires the project manager and the
project team to perform multiple actions to
execute the project management plan toaccomplish the work defined in the project
scope statement.
4 4 Direct and Manage Project Execution
8/13/2019 PM Chapter 05 Project Integration Management
43/72
4.4. Direct and Manage Project Execution
Perform activities to accomplish project objectives
Expend effort and spend funds to accomplish the project objectives
Staff, train, and manage the project team members assigned to the projectObtain quotations, bids, offers, or proposals as appropriate
Select sellers by choosing from among potential sellers
Obtain, manage, and use resources including materials, tools, equipment,
and facilities
Implement the planned methods and standards
Create, control, verify, and validate project deliverablesManage risks and implement risk response activities
Manage sellers
Adapt approved changes into the projects scope, plans, and environment
Establish and manage project communication channels, both external and
internal to the project team
Collect project data and report cost, schedule, technical and quality progress,
and status information to facilitate forecasting
Collect and document lessons learned, and implement approved process
improvement activities.
4 4 Direct and Manage Project Execution
8/13/2019 PM Chapter 05 Project Integration Management
44/72
4.4. Direct and Manage Project Execution
4 4 Direct and Manage Project Execution
8/13/2019 PM Chapter 05 Project Integration Management
45/72
Inputs
Project Management PlanApproved Corrective Actions
Approved Preventive Actions
Approved Change Requests
Approved Defect Repairs
Validated Defect RepairsAdministrative Closure Process
Tools and Techniques
Project Management Methodology
Project Management Information System
4.4. Direct and Manage Project Execution
4 4 Direct and Manage Project Execution
8/13/2019 PM Chapter 05 Project Integration Management
46/72
Output
DeliverablesRequested Changes
Implemented Change Requests
Implemented Corrective Actions
Implemented Preventive Actions
Implemented Defect Repair
Work Performance Information
4.4. Direct and Manage Project Execution
8/13/2019 PM Chapter 05 Project Integration Management
47/72
4.5. Monitor and Control Project Work
8/13/2019 PM Chapter 05 Project Integration Management
48/72
4.5. Monitor and Control Project Work
Manage the project for time, cost, etc.
Communication is essential.
The Monitor and Control Project Work process is
performed to monitor project processes associated with
initiating, planning, executing, and closing.
Corrective or preventive actions are taken to control the
project performance. Monitoring is an aspect of projectmanagement performed throughout the project.
Monitoring includes collecting, measuring, and
disseminating performance information, and assessing
measurements and trends to effect process improvements.
Continuous monitoring gives the project managementteam insight into the health of the project, and identifies
any areas that can require special attention.
8/13/2019 PM Chapter 05 Project Integration Management
49/72
4.5. Monitor and Control Project Work
8/13/2019 PM Chapter 05 Project Integration Management
50/72
4.5. Monitor and Control Project Work
4.5. Monitor and Control Project Work
8/13/2019 PM Chapter 05 Project Integration Management
51/72
Inputs
Project Management PlanWork Performance Information
Rejected Change Requests
Tools and Techniques
Project Management MethodologyProject Management Information System
Expert Judgment
Earned Value Management
4.5. Monitor and Control Project Work
Output
Recommended Corrective Actions
Recommended Preventive Actions
Forecasts
Recommended Defect Repair
Requested Changes
8/13/2019 PM Chapter 05 Project Integration Management
52/72
4.5. Monitor and Control Project Work
8/13/2019 PM Chapter 05 Project Integration Management
53/72
Defects Repair Process
Defects found whilemeasuring during quality
management
Recommended defectrepair - change
requested as part of
monitor and control
project work processes
Integrated changecontrol process
approves or rejects
change.
Defect repaired andvalidated
j
4.6. Integrated Change Control
8/13/2019 PM Chapter 05 Project Integration Management
54/72
g g
It is a continuous process
Manage all project changes
Ensure all changes are fully integrated into the project.
Changes need to go through change control process, i.e., all changesneed to be documented and approved and the baseline updated.
The Integrated Change Control process is performed from project inception
through completion.
Change control is necessary because projects seldom run exactly according
to the project management plan. The project management plan, the project
scope statement, and other deliverables must be maintained by carefully
and continuously managing changes, either by rejecting changes or by
approving changes so those approved changes are incorporated into
a revised baseline.
4.6. Integrated Change Control
8/13/2019 PM Chapter 05 Project Integration Management
55/72
g g
This is where all the recommendations for changes, corrective actions,
preventive actions and defect repairs are evaluated across all theknowledge areas and either approved or rejected.
Changes to any part of the project management plan or the product
of the project are handled in the integrated change control process.
4.6. Integrated Change Control
8/13/2019 PM Chapter 05 Project Integration Management
56/72
g g
The Integrated Change Control process includes the following change
management activities in differing levels of detail, based upon the completion
of project execution:
Identifying that a change needs to occur or has occurred.
Influencing the factors that circumvent integrated change control so that
only approved changes are implemented.
Reviewing and approving requested changes.
Managing the approved changes when and as they occur, by regulating theflow of requested changes.
Maintaining the integrity of baselines by releasing only approved changes for
incorporation into project products or services, and maintaining their related
configuration and planning documentation.
Reviewing and approving all recommended corrective and preventive actions.
Controlling and updating the scope, cost, budget, schedule and qualityrequirements based upon approved changes, by coordinating changes across
the entire project. For example, a proposed schedule change will often affect
cost, risk, quality, and staffing.
Documenting the complete impact of requested changes.
Validating defect repair.
Controlling project quality to standards based on quality reports.
4.6. Integrated Change Control
8/13/2019 PM Chapter 05 Project Integration Management
57/72
g g
Dealing with how to make changes
Evaluate impact
Create options
Get internal buy-in
Get customer buy-in (if required)
4.6. Integrated Change Control
8/13/2019 PM Chapter 05 Project Integration Management
58/72
g g
Process of making changes
Prevent the root cause of change
Identify changes
Create a change request
Assess the change
Look at the impact of changePerform integrated change control
Look for options
Change is approved / rejected
Adjust the project management plan and base line
Notify stakeholders affected by the change
Manage the project to the new project management plan.
4.6. Integrated Change Control
8/13/2019 PM Chapter 05 Project Integration Management
59/72
4.6. Integrated Change Control
8/13/2019 PM Chapter 05 Project Integration Management
60/72
Inputs
Project Management PlanRequested Changes
Work Performance Information
Recommended Preventive Actions
Recommended Corrective Actions
Recommended Defect Repair
Deliverables
Tools and Techniques
Project Management Methodology
Project Management Information SystemExpert Judgment
4.6. Integrated Change Control
8/13/2019 PM Chapter 05 Project Integration Management
61/72
Output
Approved Change Requests
Rejected Change Requests
Project Management Plan (updates)
Project Scope Statement (updates)
Approved Corrective Actions
Approved Preventive ActionsApproved Defect Repair
Deliverables
4.6. Integrated Change Control
8/13/2019 PM Chapter 05 Project Integration Management
62/72
Corrective Action and Integrated Change Control Process
Measure
Is there variance?
Is corrective actionrequired?
yes
Look at alternative actionsto make recommendation on
what corrective action to take
yes
Submit to internal change control
to approve or reject change
Changes identified in
project execution
Change s identified
in project monitoring and
control
approved
Change the project
management plan
Manage the project to new
project management plan
Monitor and control theproject
Measure effectiveness
of previously implemented
corrective actions
Look for more alternatives
or accept the impact.
rejected
4.6. Integrated Change Control
8/13/2019 PM Chapter 05 Project Integration Management
63/72
Reviews change requests to determine if additional analysis iswarranted
Approves and rejects changes
May include: Project Manager
Customers and Stakeholders
Experts
Sponsor
Others
Change Control Board
4.7. Close Project
8/13/2019 PM Chapter 05 Project Integration Management
64/72
Many projects never gets properly closed.
The Close Project process involves performing the
project closure portion of the project management plan.
In multi-phase projects, the Close Project process
closes out the portion of the project scope and
associated activities applicable to a given phase.
This process includes finalizing all activities completed
across all Project Management Process Groups toformally close the project or a project phase, and
transfer the completed or cancelled project as
appropriate.
The Close Project process also establishes the
procedures to coordinate activities needed to verify anddocument the project deliverables, to coordinate and
interact to formalize acceptance of those deliverables
by the customer or sponsor, and to investigate and
document the reasons for actions taken if a project is
terminated before completion.
4.7. Close Project
8/13/2019 PM Chapter 05 Project Integration Management
65/72
Two procedures are developed to establish the interactions necessary to perform the
closure activities across the entire project or for a project phase:
Administrative Closure Procedure
Contract Closure Procedure
4.7. Close Project
8/13/2019 PM Chapter 05 Project Integration Management
66/72
Administrative closure procedure
This procedure details all the activities,
interactions, and related roles and responsibilities
of the project team members and other stakeholders
involved in executing the administrative closure
procedure for the project.
Performing the administrative closure process also
includes integrated activities needed to collect
project records, analyze project success or failure,
gather lessons learned, and archive project
information for future use by the organization.
4.7. Close Project
8/13/2019 PM Chapter 05 Project Integration Management
67/72
Contract closure procedure
Includes all activities and interactions needed to settle
and close any contract agreement established for the
project, as well as define those related activities
supporting the formal administrative closure of the
project.
This procedure involves both product verification (all work completedcorrectly and satisfactorily) and administrative closure (updating of contract
records to reflect final results and archiving that information for future use).
The contract terms and conditions can also prescribe specifications for
contract closure that must be part of this procedure.
Early termination of a contract is a special case of contract closure that
could involve, for example, the inability to deliver the product, a budget
overrun, or lack of required resources.
This procedure is an input to the Close Contract process.
4.7. Close Project
8/13/2019 PM Chapter 05 Project Integration Management
68/72
4.7. Close Project
8/13/2019 PM Chapter 05 Project Integration Management
69/72
Input
Project Management Plan
Contract Documentation
Enterprise Environmental Factors
Organizational Process Assets
Work Performance Information
Deliverables
Tools and Techniques
Project Management Methodology
Project Management Information System (PMIS)Expert Judgment
4.7. Close Project
8/13/2019 PM Chapter 05 Project Integration Management
70/72
Output
Administrative Closure Procedure
Contract Closure Procedure
Final Product, Service, or Result
Organizational Process Assets (updates)
8/13/2019 PM Chapter 05 Project Integration Management
71/72
Project Management Information System (PMIS)
8/13/2019 PM Chapter 05 Project Integration Management
72/72
Standardized set of automated tools available within the organization and
integrated into the system. The PMIS is used by the project management team to:
support generation of a project charter, facilitate feedback as the document is
refined, control changes to the project charter, and release the approval document.
support generation of a preliminary project scope statement, facilitate feedback as the
document is refined, control changes to the project scope statement and release the approved
document.
support generation of project management plan, facilitate feedback as the document is
developed, control changes to the project management plan, and release the approved
document.
aid in the execution of the activities planned in the project management plan.
to monitor and control the execution of activities that are planned and scheduled in the projectmanagement plan. It is also used to create new forecasts as needed.
to support for the implementing an Integrated Change Control process for the project, facilitate
feedback for the project and control changes across the project.
to perform both administrative and contract closure procedures across the project